AGENDA
Fredonia Government Center Commission Meeting
Thursday, May 28th, 2026 at 2:00PM
Fredonia Government Center - Board Room
242 Fredonia Avenue, Fredonia, Wisconsin
THE FOLLOWING BUSINESS WILL BE BEFORE THE FREDONIA GOVERNMENT
CENTER COMMISSION
FOR INITIATION, DISCUSSION, CONSIDERATION, DELIBERATION
AND POSSIBLE FORMAL ACTION
1. Call to Order
2. Pledge of Allegiance
3. Public Comments:
Please note public comments are limited to five minutes per person
4. Items for Discussion and/or Action:
a) Appointment of FGCC Chair
b) Review of Intermunicipal Agreement for the Management of Fredonia
Government Center
c) Update on Facility Condition by Village of Fredonia DPW Director Paulus
d) Discussion and Possible Action on Keyless Door Access System
e) Discussion and Possible Action on Shared Maintenance Projects
f) Discussion and Possible Action on Shared Services
5. Correspondence
6. Items for Future Consideration.
7. Adjournment
UPON REASONABLE NOTICE, efforts will be made to accommodate the needs of disabled
individuals through appropriate aids and services. For additional information or to request this
service, contact the Village Clerk at (262) 692-9125.
NOTICE IS HEREBY GIVEN that a majority of the Fredonia Village or Town Board may attend
this meeting in order to gather information about a subject over which they have decision-
making responsibility.
Estimate #1503: – Village of Fredonia Door Access
Central Office Systems October 13, 2025
W223N777 Saratoga Drive
Waukesha, WI 53186
Phone: 262-228-9966
Client Name: Village of Fredonia
Site Location: 242 Fredonia Ave
Fredonia WI, 53021
Estimate #1503: – Village of Fredonia Door Access
Hi Chris,
Thank you for giving us the opportunity to bid on this project for your location. We propose to furnish and install
the below equipment.
Village Hall Door Access - $10,883.00
➢ Provide and Install (2) cut-in strike locks (Internal Office Doors)
➢ Provide and install (3) surface mount strike locks (External doors)
➢ Provide and Install (1) Enterprise Access Door hub for network door control
➢ Provide and Install (5) Access card readers
➢ ***Assumes client IT responsible for open POE+ network ports at location***
➢ Includes Cat 6 network cable, all lines tested / certified
➢ Includes programming & training
➢ Includes 10 keycards and 10 keyfobs
Park Restrooms - $2,750.00
➢ Reinstall existing door handles, remove power from keypads
➢ Provide and install (2) cut-in strike locks
➢ Provide and Install (2) network door controllers
➢ Provide and install (1) 60W POE+ switch for power (to be installed at point of Fire Dept network
hookup)
➢ Run network line from Fire Department, to crawlspace above bathrooms, down to doors
➢ Test / certify lines
➢ Includes programming & training
Total Estimate (without sales tax): $13,633.00
Estimate #1503: – Village of Fredonia Door Access
Notes:
➢ If an IDF Installation is required due to network length / camera location a change order will be provided (not
expected)
➢ Any additions (Materials / Network Equipment Needed) outside of this estimate will be added via change
order.
➢ 50% down payment required to start the project. The remainder of the estimate, plus any
change orders, are due upon completion.
➢ Sales Tax not Included.
QUALIFICATIONS:
➢ Prices based on the above counts only & guaranteed for 15 days from date.
➢ Delays caused by situations beyond our control will result in renegotiation of the work schedule/pricing.
➢ Figures based on all areas being available and clear to install during the installation.
➢ All work is to be completed in a professional manner, according to the EIA/TIA standard practices.
➢ All work takes place during regular business hours. Any overtime hours not listed will have to be billed as
a separate ticket for hours worked.
➢ All telephone system hardware is provided and installed by others.
➢ Any Demarc extensions would be additional.
➢ All agreements contingent upon strikes, accidents, or delays beyond our control.
➢ COSC will warranty the installation for one full year, from the date of completion. Parts will be covered
under manufacture warranty. Labor will be billed T&M unless others caused damage. Service work
required because of damage to the installation will be charged on a T&M basis.
Submitted by: Accepted by:
Thomas Rosecky 10/13/2025
Central Office Systems Authorized Signature Date Client Authorized Signature Date
Print Name Title
Print Name Title