Committee of The Whole Meeting — Agenda Packet
St. Croix County · St. Croix County · Committee of The Whole · meeting of Jul 9, 2026 · Agenda packets
Open the original document More from St. Croix County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Committee of The Whole Agenda
July 9, 2026 8:00 AM
St. Croix County Government Center - Room 1400
Government Center - 1101 Carmichael Road, Hudson, Wisconsin
Call to Order
Roll Call
Approval of Minutes
1. Minutes of Previous Meeting — May 5, 2026
Public Comment
Business
1. Debt Funding and Timing of Major Projects - Big Picture Introduction
2. Presentation of the Jail Expansion Project
3. Presentation of the Emergency Communications Infrastructure Project
4. Consideration of 2027-2031 Capital Projects
5. Consideration of Debt Funding and Timing for Major Projects
Request for Future Agenda Items
Announcements
Date of Next Meeting
1. Date of Next Meeting - October 8, 2026
Adjournment
Reasonable efforts will be made to provide special accommodations for access to public meetings. To request a special
accommodation, please contact the County Clerk’s Office at (715) 386-4600 at least two business days prior to the time of the
meeting. For more information on St. Croix County's public meetings visit: sccwi.gov/meetings
Page 1 of 88
Committee of The Whole Minutes
May 5, 2026 5:15 PM
St. Croix County Government Center - Room 1400
Government Center - 1101 Carmichael Road, Hudson, Wisconsin
Call to Order
The meeting was called to order at 5:35 p.m.
Roll Call
PRESENT: Jared Bell, Dani Erickson, Mitch Ruedebusch (remote), Kerry Reis, Diana Delaney, Denise Shirley-Carter,
Bob Feidler, Wayne Roen, Scott Counter, Daniel Hansen, Danielle McIntosh, Greg Tellijohn, Mark
Carlson, Mike Barcalow, Bob Swanepoel, Jerry VanSomeren, John Betchkal
ABSENT: Dan Fosterling
Approval of Minutes
1. Minutes of Previous Meeting - October 9, 2025
Minutes were accepted as presented.
Public Comment
None.
Business
1. Presentation - Budget Overview
County Administrator Ken Witt provided an overview of the 2027 budget development process. He explained that the
purpose of the meeting was to establish budget priorities for 2027. Administrator Witt reviewed the projected revenues
available to support County operations and discussed the various revenue sources. He also outlined expenditure
obligations and cost drivers that impact available revenues, providing context for budget planning and priority-setting
for the upcoming fiscal year.
2. Department Annual Reports
All department heads presented their annual reports, highlighting accomplishments, activities, and financial
performance from budget year 2025. Department heads also reviewed any proposed requests, initiatives, or funding
considerations for inclusion in the 2027 budget.
3. Consideration of 2027 Budget Priorities
The County Board participated in a budget prioritization exercise to identify and rank funding priorities for 2027. The
results of the exercise will assist the County Administrator in developing budget recommendations and establishing
budget priorities.
Request for Future Agenda Items
None.
Announcements
Page 2 of 88
None.
Date of Next Meeting
1. Date of Next Meeting - To be determined (July CIP)
Adjournment
Meeting adjourned at 8:37 p.m.
Page 3 of 88
St. Croix County Sheriff’s Office
Jail Master Plan
Page 4 of 88
Jail History
• Current jail opened in 1993 with overall capacity of 131 inmates
• Huber addition in 2003 added an additional 44 beds
• 9-bed special housing unit added in 2020
• Total inmate capacity allowed by DOC is 185
• Department of Corrections guidance indicates functional capacity at 80%
of available beds to account for proper housing and separation of inmates
• Functional capacity is 148 inmates
2
Page 5 of 88
Existing Jail
3
Page 6 of 88
Jail Expansion Concept
4
Pod and SHU -
105
Huber/ Minimum Security - 72
Special Housing - 24
Receiving Center - 28
New Pod -
96
Page 7 of 88
Inmate Daily Population
5
• 2018 Average Daily Population - 119, Min 103, Max 140
• 2019 Average Daily Population - 123, Min 84, Max 153
• 2020 Average Daily Population - 79
• 2021 Average Daily Population - 84
• 2022 Average Daily Population - 98, Min 62, Max 128
• 2023 Average Daily Population - 109, Min 89, Max 135
• 2024 Average Daily Population - 114, Min 95, Max 140
• 2025 Average Daily Population - 116, Min 96, Max 139
AVERAGE DAILY
POPULATION
PEEK POPULATION
Page 8 of 88
Inmate analysis – projected daily populations
• Peaking is the highest number of
inmates housed in the jail on any given
day
• Peaking is generally 20%higher than
average daily population
• By 2030, projections regularly estimate
inmate population peaking above 150
• Once daily populations are regularly over
148, the Sheriff will need to transfer
inmates to other jails
• At the current going rate of $60/day, for
every 10 inmates housed out of County,
it will cost an estimated $18,000 per
month for room and board
• Additional costs for transport, logistics
and other inmate services such as
medical care
6
PEEK POPULATION
AVERAGE DAILY
POPULATION
Page 9 of 88
Inmate analysis – Length of stay
• 76% of inmates stay less than 4
days
• In 2025, the jail averaged 7.04
bookings per day
• Department of Corrections
suggest 10% of total jail capacity
consist of receiving/booking cells
• St. Croix County jail currently has
3 receiving cells
• 2024 Jail study recommended
adding 20-22 additional receiving
cells
7
Page 10 of 88
Inmate analysis – Special watch status
Special watch –
66% males, 33% females
Through end of May 2026:
9-bed Special Housing Unit was filled
at 87.38% of capacity
2024 Jail study and architect
recommendation of 24 additional
Special Housing cells
8
Page 11 of 88
Jail analysis – Classification/separation
• The Department of Corrections
identifies 16 different inmate
classifications that require separate
housing per sex
• 32 possible separation scenarios
• Large housing units at the pod (24,
24, 20, 16, 8, 4) and Huber areas
(8, 8, 8, 12, 18, 26) limit separation
ability
• 2024 Jail study recommended a
minimum of 20 separate housing
units consisting of 2-16 beds each
9
Page 12 of 88
2023 Department of Corrections Jail Inspection
10
Date of inspection: 7/11/2023
Inmate Population: 107
Additional 2 on EHM
Page 13 of 88
2024 Department of Corrections Jail Inspection
11
Date of inspection: 8/8/24
Inmate Population: 134
Additional 7 on EHM
Page 14 of 88
2025 Department of Corrections Jail Inspection
12
Date of inspection: 8/5/25
Inmate Population: 125
Additional 7 on EHM
Page 15 of 88
St. Croix 800 MHz
Page 16 of 88
The Why
• In the next five years there will need to be an investment of $6
million dollars for routine maintenance with no improvements to
system
• Requests from public safety leaders for expanded capabilities:
• More channels to communicate
• Clearer radio communication and coverage
• Network Security
• Interoperability
• Growing needs of county:
• First responders using network: 495 in 2017 and 621 in 2025
• An 800 MHz system would meet the needs of first responders
Page 17 of 88
A More Robust Network
• Going from five radio frequencies to countless talkpaths
• Expanded ability to communicate during incidences occurring at same
time, allowing for agencies to have their own talkpaths
• Clearer signal/better building penetration
• Like going from analog television to digital television
• Recording and private frequencies
• An 800 MHz system will allow for all communications to be recorded
• Local first responders have their own private frequencies not tied into
countywide communication system
Page 18 of 88
Security
• Ability to make network secure
• Documented cases of intrusion on current system
• Managed access to radio network
Page 19 of 88
Interoperability
• WISCOM 800 ( state interoperability system)- 800 MHz
• ARMER (MN radio network)- 800 MHz
• Dunn County- 800 MHz
• Pierce and Polk Counties- VHF
• 83% of St. Croix County public safety leaders polled believe
interoperability is an important feature
• An 800 MHz system allows for seamless communication with
mutual aid agencies and would put interoperability in the hands
of first responders rather than relying on dispatch to create
communication patches
Page 20 of 88
From Public Safety
• Many of our newer and larger buildings have penetration issues on the talk-around
channels. We have found some better coverage with a truck mounted repeater, but still
not great… We are also very supportive of having several incident channels available to
use as the main fire channel gets crowded when more than 2 or 3 incidents are
happening at the same time.
-Chief Drew Spielman, Hudson FD
• When our ambulances and supervisors are responding to any major incidents in St. Croix
County, we rarely have the opportunity to communicate with St. Croix County
Communications Center due to the overcrowding on the fire channel with multiple units
trying to all communicate on the same channel. This has been an issue for many years
now and it is only getting worse because the call volumes have increased, there is more
auto aid happening, and more radios on the system now than ever before.
-EMS Director Jon Muller, Lakeview
Hospital
Page 21 of 88
Hammond Tower
• Current tower lease expires January of 2030
• Must start replacement process early 2027 so there is not a gap in
service
• County decided to not renew lease at former highway shop
location
• Land has been located to construct a new tower in Hammond
• Ideal location to serve the public safety needs of St. Croix County
Page 22 of 88
Towers
Current Tower
Proposed
Tower
Page 23 of 88
Enhancements
• Construction of at least two communication towers and shelters
• 12 Dispatch consoles for primary and back-up locations
• Over 400 mobile and portable radios
• New 800 MHz radio base stations and repurposing current base
stations when possible
• Refresh of antennas and peripheral parts of radio network
Page 24 of 88
CIP Plan 2027-2031
Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget
Fund Cost Ctr Project FY27 FY28 FY29 FY30 FY31 Project Title Category Class Description
Facilities
405 7140 10001 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 Building Remodeling/Furniture/Plumbing Capital Improvements Recurring This is for any small remodeling projects being done or furniture replacement at any of St
Croix Facilities.
405 7320 10004 $ 265,000 $ 285,000 $ 330,000 $ 355,000 $ 290,000 Fleet vehicle replacement. Vehicles Recurring 5-year rotating plan to replace shared fleet vehicles. Increase in 2029 for HCC bus that is 20
years old and 16 passenger van 7 years old. 2030 increase for parks dump truck that will be
10 years old
405 7140 10005 $ 65,000 $ 65,000 $ 65,000 $ 65,000 $ 65,000 Equipment/Electrical Equipment Equipment Recurring This project continuously replaces Furniture/Equipment/Appliances for the public areas and
other areas in case of failure as needed.
405 7140 10006 $ 125,000 $ 125,000 $ 125,000 $ 125,000 $ 125,000 HVAC Replacement Equipment Recurring As the buildings HVAC systems are aging, this allocation allows proper upkeep and
repair/replacement.
405 7140 10007 $ 45,000 $ 45,000 $ 45,000 $ 45,000 $ 45,000 Safety and Security Equipment Recurring These funds will allow us to continue to provide additional security equipment throughout
the County buildings, cameras, card swipes, electronic locks & strikes. Front door metal
detector and scanner. Building security measures.
405 7140 10051 $ 50,000 $ - $ - $ 50,000 $ - Parking Lot patch and seal Capital Improvements Recurring
2020
Parking lot patch 2027 will include the GC South Addition Lots and Drives. These projects
would reset to start again in 2030 beginning with the GC.
405 7140 10079 $ 5,000 $ - $ - $ - $ - New Folder/Inserter Machine Equipment Recurring
2019
Average lifespan of this asset is approximately 5 years. This is an integral piece of equipment
that is used constantly and serves many purposes for Clerk of Courts including mass mailings
of documents such as default judgments letters, jury questionnaires, jury summons, and
notices of hearing.
405 7140 10095 $ 220,000 $ - $ - $ - $ - New parking lot for DD building Capital Improvements Recurring
2021
DD building parking lot replacement in New Richmond
405 7140 10108 $ 130,000 $ - $ - $ - $ - Replace GC West Driveway Capital Improvements Recurring
2022
Replace West Driveway and western portion of lower parking lot.
405 7140 10137 $ 1,600,000 $ - $ - $ - $ - GC/Jail New Roof on 1993 Roof Capital Improvements Necessity
2023
The current roof is from 1993, in 2023 facilities has had to patch 3 holes in the roof. The
roofs rubber membrane is starting to get brittle crack.
405 7140 10111 $ 140,000 $ - $ - $ - $ - Huber Carpet Removal and Floor Polising Capital Improvements Enhancement 2025 Remove carpet and polish floors, carpet is 33 years old and polishing keeps it better
sanitized. If jail project is approved this would be reassessed and possibly removed.
405 7140 10151 $ - $ - $ - $ - $ 1,500,000 Court Room Remodel for 5th Judge Capital Improvements Enhancement 2025 Remodel courtroom 6 and add secure hallway for safe inmate transfer. Updating to match
courtrooms 1-4 for potential 5th judge and future needs.
Facilities Totals $ 2,845,000 $ 720,000 $ 765,000 $ 840,000 $ 2,225,000
Information Technology
405 7150 10002 $ 150,000 $ 150,000 $ 150,000 $ 150,000 $ 150,000 IT Recurring Projects Equipment Recurring This ongoing CIP request provides funding for IT projects and equipment replacement that
are not part of the operating budget; Added Jail camera storage 2023.
405 7150 10064 $ - $ - $ 500,000 $ - $ -
Courts AV Upgrades Equipment Enhancement 2025
Replace aging AV equipment in courtrooms 5-7 equipment will be unsupported by 2030.
Moved up one year.
405 7150 10140 $ - $ 200,000 $ - $ - $ - County Data Storage Replacement Equipment Recurring
2023
The data storage system is an integral part of the IT infrastructure. This is where we store
and safeguard all of the data that our employee's generate. The systems typically have a life
expectancy of 7 years. The current systems will be 8 years old and will require replacement
in 2028.
405 7150 10141 $ - $ 250,000 $ 250,000 $ - $ - Replace aging Jail and Health Center security cameras. Equipment Enhancement 2023 The Jail and Health Center security cameras were installed in 2016 as part of the Jail remodel
and Health Center build. Most of these cameras are end of life and no longer supported by
the vendor and, as such, are no longer able to be repaired. We replace a number of these
cameras annually due to failure and there is currently no budgeted line item for
replacement.
405 7150 10070 $ 15,000 $ - $ - $ - $ 15,000 Copy Machines for Clerk of Courts and District
Attorney's Office
Equipment Recurring 5 Year replacement schedule alternating between Clerk of Courts and District Attorney's
Office.
405 7150 10071 $ - $ - $ 75,000 $ - Cellular Signal Repeaters for SC Equipment Enhancement 2025 Install a small cell repeater system at the service center as cell service is not adeauate for
coducting business
Information Technology Total $ 165,000 $ 600,000 $ 900,000 $ 225,000 $ 165,000
County Clerk
405 7120 10155 $ - $ - $ 40,000 $ - $ - Election Software and Server Updgrade Software Recurring
2024
Every 5-7 years the election software and servers need to be replaced, this was last done in
fall of 2023. This provides election support to all municipalities in the county.
County Clerk Totals $ - $ - $ 40,000 $ - $ -
HWY
HWY Totals $ - $ - $ - $ - $ -
HHS
405 7160 10003 $ 55,000 $ 145,000 $ 55,000 $ 145,000 $ 55,000 Replacement of Vehicles for ADRC Vehicles Recurring Replace vehicles every 5 Years. Updated 2027 CIP from 145K to 55K to replace van instead
of bus
HHS Totals $ 55,000 $ 145,000 $ 55,000 $ 145,000 $ 55,000
Law Enforcement
405 7210 10000 $ 650,000 $ 750,000 $ 750,000 $ 750,000 $ 750,000 Sheriff Squad Cars Vehicles Recurring Annual purchase of vehicles to rotate fleet every 3 years increases include addition of 9 new
deputies.
405 7210 10167 $ 250,000 $ 250,000 $ 300,000 $ 300,000 $ 300,000 Sheriff Investigator and Command Vehicles Vehicles Recurring Changing from leases to purchases 21 vehicles, 4 year rotation
Page 25 of 88
405 7210 10156 $ - $ 147,000 $ - $ - $ - Sheriff Night Vision Equipment Enhancement
2024
For 14 sets of night vision for primary responders for use in critical incidents and tactical
approaches. Moved up one year.
405 7210 10157 $ - $ 40,000 $ - $ - $ - Sheriff Forensic Servers replacement Equipment Recurring
2024
Replace computer forensic storage servers wich are coming to end of life in 2026.
405 7210 10127 $ 422,562 $ - $ - $ - $ - Sheriff Patrol Boat Replacement Equipment Recurring 2025 Purchase a 25ft patrol boat and trailer to replace current primary river boat, new boat would
have similar design and include FLIR camera system. Federal Port Security grant will cover
75% of boat if fulfilled by August 2028. Asking to move from 2030 CIP to 2027 CIP to meet
the grant closing date. Increased amount from $240K to $422K.
405 7210 10128 $ - $ - $ - $ 400,000 $ - Dash and body camera replacement Equipment Recurring 2025 Replace 86 body cameras, 41 dash cameras to improve video quiality, storage capacity,
reliability, and officer safety. The change will help the DA office as SCC will then be using
same Getac cameras. Current dash cam warrenty ends in 2028, body cameras due in 2030
405 7210 10131 $ - $ - $ - $ 60,000 $ - Squad Radar Units Replacement Equipment Recurring 2025 Replace radar units with new, current are 10-13 years old and beyond recommended service
life resulting in high repair costs. Will add a few a year to phase and reduce CIP
405 7210 10132 $ - $ - $ - $ 392,670 $ - Taser replacement Equipment Recurring 2025 Tasers need to be replaced as the X26P ends it's service life. Either a one time CIP or spread
out over 5 years at $88,194 per year
405 7210 10133 $ - $ - $ - $ 40,000 $ - Trimble Forensic Scanner Equipment Recurring 2025 Replace current scanner that was purchased in 2018, newer technology provides fast,
accurate, and objective representation of a crime scene in criminal investigations
405 7210 10134 $ - $ - $ - $ 21,375 $ - Cradlepoints Squad car replacements Equipment Recurring 2025 Replace current 4G routers with 5G routers as technology has changed, increased speeds
and less connectivity issues
405 7210 10164 $ - $ - $ - $ - $ 50,000 Emergency Response Unit Armor Equipment Recurring 2026 Need to replace body armor for 12 deputies on the ERU, these are due for replacement
every 5 years. Previously was able to be absorbed in operating budget but converting to
capital budget for sustainable funding solution
405 7210 10165 $ - $ - $ - $ - $ 29,250 Handgun mounted optics Equipment Recurring 2026 Optics for 65 handguns to increase accuracy, target acquisition, and effectiveness. Follows
handgun replacement of every 5 years
405 7210 10166 $ - $ - $ - $ - $ 44,500 Drone (sUAS) Fleet Replacement Equipment Enhancement 2026 Replace aging small unmanned aircraft sytstems fleet. Includes $25K DJI M300 large
airframe with thermal, $13K DJI M30T mid size airframe with thermal, and $6,500 tether for
sustained drone operations
Law Enforcement Totals $ 1,322,562 $ 1,187,000 $ 1,050,000 $ 1,964,045 $ 1,173,750
Corrections
405 7270 10124 $ 46,000,000 $ - $ - $ - $ - Jail Expansion and renovation Capital Improvements Enhancement
2022
Jail expansion including special needs cells, excluding new pod.
405 7270 10159 $ 55,000 $ - $ - $ - $ - Jail Dishwasher replacement Equipment Recurring
2024
Replace jail dishwasher in kitchen. Increased from $13K to $55K
405 7270 10112 $ - $ - $ - $ - $ 160,000 Jail Body Scanner Replacement Equipment Enhancement 2026 Replace aging body scanner with Tek-84 in the jail receiving. Assists in detecting inmates for
contraband to protect both inmates and staff.
Corrections Totals $ 46,055,000 $ - $ - $ - $ 160,000
Emergency Comm
405 7260 10025 $ - $ 100,000 $ - $ - $ - Audio Log - Audio Recorder System Equipment Recurring
2019
Replace audio recorder system that records 911 phone calls, non-emergency phone lines
and radio communications of the Communication Centers radio network. This also will
record metadata that is received for phone calls and radio channels. Cost increased from
$90K to $100K from 2026 CIP
405 7260 10103 $ - $ - $ - $ 100,000 $ - Portable Radio Cache Update Equipment Recurring
2025
Recurring every 5 year for replacement to keep up with technology
405 7260 10142 $ 70,000 $ 70,000 $ 70,000 $ 70,000 $ 70,000 DC Power Battery Replacement Communication
Tower Sites
Recurring
2023
Replacement of DC Power Batteries at the 14 tower sites. These are batteries providing
backup power 48 volts to the equipment for Emergency Communications infrastructure.
Increased costs starting in 2027 due to rising costs the county has seen
405 7260 10145 $ - $ 120,000 $ - $ - $ - Radio Console Upgrade Hardware Equipment Recurring
2023
Replace/update computer system hardware that controls the Emergency Communications
radio network. This would replace computers and peripheral hardware at the workstations
in the primary and backup Communication Centers that operate 24 hours a day.
405 7260 10160 $ - $ - $ - $ 180,000 $ - 911 System replacement hardware Equipment Recurring
2025
Replacement of 911 system hardware at both Primary-Hudson and backup-Baldwin centers.
Replacement strongly recommended every 5 years.
405 7260 10162 $ - $ - $ 85,000 $ - $ - UPS replacement for Hudson and Baldwin 911 Centers Equipment Recurring
2024
Replacement of UPS - Uninterruptable Power Supplies - for Hudson 911 and Baldwin 911
Centers. Increased cost from $70,000 to $85,000 from 2026 CIP
405 7260 10062 $ 19,347,000 $ - $ - $ - $ - Emergency Communicaitons Infrastructure Upgrade Capital Improvements Enhancement 2025 Hammond tower and radios including portable and mobile. This request expands current
radio infrastructure and allows inter-agency communication on 800 MHZ frequency along
with VHF band. Total project cost increased from $13,885,050 to $19,347,000.
405 7260 10063 $ - $ - $ - $ 100,000 $ - Mobile Command Vehicle Refresh Vehicles Recurring 2025 Current electronics are 10 years old and need updating since are a part of the networking of
the vehicle in order to maintain reliability when responding to critical situations
Emergency Comm Totals $ 19,417,000 $ 290,000 $ 155,000 $ 450,000 $ 70,000
Medical Examiner
405 7120 10081 $ 5,000 $ - $ - $ - $ - XL Electric Body & Casket Lift Equipment Enhancement 2026 Lift to help load and unload decedents when back in office, with increased size of decedents
this will improve safety as typically one employee is performing the task.
405 7120 10082 $ 17,000 $ - $ - $ - $ - Stryker Power-Load cot fastner system Equipment Enhancement 2026 Need upgrade to new transport van in order for stryker cot purchased in 2025 will work with
new height of vehicle. Will help load and unload safely
Medical Examiner Totals $ 22,000 $ - $ - $ - $ -
Parks
CIP Plan 2027-2031
Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget
Fund Cost Ctr Project FY27 FY28 FY29 FY30 FY31 Project Title Category Class Description
Page 26 of 88
405 7620 10035 $ 35,000 $ 35,000 $ 35,000 $ 35,000 $ 35,000 Parks Equipment Equipment Recurring Replace Utility Terrain Vehicles (UTV), zero-turn and front mount mowers, car-hauler
trailers, skid-steer, tractor, side-mount ditch mower, etc. Attachments may be needed or
replaced also.
405 7620 10036 $ 50,000 $ - $ - $ - $ - Ongoing maintenance of County Park driveways,
parking lots
Capital Improvements Recurring Ongoing maintenance of park driveways and parking lots. Moved up from 2028 to 2027 for
Glen Hills pavement to co-incide with paving of RR3 by Highway
405 7620 10075 $ - $ - $ 2,200,000 $ 1,650,388 $ - Bike Ped Plan SCRC Loop Trail to Willow River State
Park Connection
Capital Improvements Enhancement
2017
Construction of a 3.4-mile Off-Road Bike Trail from North Hudson to Eckert Blufflands to
Willow River State Park to St. Croix River Crossing Loop Trail in 3 Phases. Phase 3 scheduled
for 2029, phase 4 for 2030. Offset by 80% cost match but design is not included in the
match.
405 7620 10125 $ 600,000 $ 500,000 $ 500,000 $ - Eckert Blufflands Park Development Capital Improvements Enhancement
2022
Eckert Bluffands Park is a 170-acre County property occupying 2,800 feet of shoreline along
the Scenic St. Croix Riverway in the Towns of Hudson and St. Joseph. In 2022, the County
Board approved the Eckert Blufflands Park Master Plan. The Master Plan identifies
improvements and park amenities. The Master Planning process included 18-months of
public input including meetings with the general public, adjacent landowners and impacted
towns, public open houses, on-line public engagement, and continued dialogue with the WI
Department of Natural Resources and WI Department of Transportation. Master Plan
implementation cost estimates and phasing of development were created for park
development. The cost estimate above has been adjusted for inflation. Link below to Master
Plan which includes cost estimates (using 2020 dollars):
https://www.sccwi.gov/DocumentCenter/View/7192/Eckert-Blufflands-Master-Plan Please
see attached map and photos.
405 7620 10100 $ - $ - $ 250,000 $ - $ - 15-Site RV Campground for larger RV with
infrastructure
Capital Improvements Enhancement
2022
New 15 site RV camp site to accommodate RV's over 35 feet with supporting infrastructure
in new area of Glen Hills Park.
405 7620 10097 $ - $ - $ 50,000 $ - $ - County Dam Maintenance Capital Improvements Recurring
2024
Maintain and replace county dams to prevent failure.
405 7620 10077 $ - $ - $ - $ 150,000 $ - Parks Playground Upgrade Capital Improvements Enhancement 2025 Upgrade to over 20 year old playgrounds at Peninsula Campground, Whispering Oaks
campground, and Homestead park.
Parks Totals $ 685,000 $ 535,000 $ 3,035,000 $ 1,835,388 $ 35,000
CIP TOTALS $ 70,566,562 $ 3,477,000 $ 6,000,000 $ 5,459,433 $ 3,883,750
Funding Sources
CIP Fund Balance Applied $ 3,066,562 $ 3,160,079 $ 4,240,000 $ 4,331,579 $ 3,883,750
Bond Issue $67,500,000 Bond Issues for Large Capital Project
10075 $1,760,000 $1,127,854 TAP grant for HWY 35 off road trail - 80%. 2030 is slightly less as it does not cover design costs of $225K
10127 $316,922 Received federal port security grant that pays 75% of purchase price upon delivery to be completed by August 2028
CIP TOTALS $ 70,566,562 $ 3,477,000 $ 6,000,000 $ 5,459,433 $ 3,883,750
CIP Fund Balances Projected
Beginning of Year $ 5,381,022 $ 3,964,460 $ 2,454,382 $ (135,619) $ (2,817,198)
Use $ (3,066,562) $ (3,160,079) $ (4,240,000) $ (4,331,579) $ (3,883,750)
Property Sales $ 150,000 $ 150,000 $ 150,000 $ 150,000 $ 150,000
Transfer from GF $ 1,500,000 $ 1,500,000 $ 1,500,000 $ 1,500,000 $ 1,500,000 Projected (Needs County Board Authorization)
End of Year Balance $ 3,964,460 $ 2,454,382 $ (135,619) $ (2,817,198) $ (5,050,948)
CIP Plan 2027-2031
Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget Capital Budget
Fund Cost Ctr Project FY27 FY28 FY29 FY30 FY31 Project Title Category Class Description
Page 27 of 88
Capital Improvement Request – Capital Expenditures, Equipment,
Renovations, Miscellaneous
Purpose
To request any new resources that cost in excess of $5,000.00.
NOTE: New projects should be planned 5 years out.
Instructions
• Estimated Cost - approximate cost of equipment, service, or renovation. The Requesting
Department will provide estimates for those items needed. Facilities will assist departments in
estimating the costs associated with facility modifications.
• Brief Summary of Request - short description of resources being requested. Below are some
examples:
o Ultra-low Temperature Freezer for Laboratory,
o Major building maintenance projects,
o Requests for equipment in excess of $5000.
• Discussion of Need, etc. - describe in detail the need and justification of the requested items with
cost information described as accurately as possible. Please make sure to address how this
request supports the County’s Strategic Plan if applicable. Attach any backup material that you
think may be helpful in evaluating the cost/benefit value of the new item. If any annual costs will
result from the requested item (e.g., staff to operate it, insurance, repair costs, etc.), provide an
estimate of this cost.
• On Going Increase in Revenues/Expenses or Cost Savings if Approved - provide estimate of
changes to revenues or expenses that will become part of the operating budget if this capital project is
approved. For example, additional staffing, additional heating/cooling costs or reduction of expenses
if approved.
Page 28 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 29 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 30 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 31 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 32 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 33 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 34 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 35 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 36 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 37 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 38 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 39 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 40 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 41 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 42 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 43 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 44 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 45 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 46 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 47 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 48 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 49 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 50 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Sheriff's Office
Squad and equipment replacement
New
2030
The Sheriff's Office maintains a fleet of patrol vehicles that are critical to public safety and daily operations. Due to the
high mileage and demanding use of these vehicles, we follow a 5-year rotation schedule to ensure each squad remains
within warranty and avoids significant repair costs. This cycle has been effective in maintaining vehicle reliability and
minimizing downtime.
Since 2020, the cost of purchasing a new squad car has increased by approximately 30%. The estimated 2025 cost per
vehicle is $46,000, with an additional $16,000 required to outfit each vehicle with emergency lighting and basic
equipment. This cost can vary depending on design changes from Ford, which may make older equipment incompatible
with newer models.
These figures do not include the cost of technology and equipment such as tablets, Cradlepoints, mobile radios, radars,
AEDs, stop sticks, dash cameras, or other misc gear.
Our agency currently replaces 7 to 10 squads per year. Maintaining this replacement allows us to avoid major mechanical
failures, officer safety, and a steady budget cycle.
Replacement of 7 to 10 squads and equipment on a recurring basis with a 5% increase per year.
$750,000 with 5% increase per year
Page 51 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 52 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 53 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 54 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 55 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New 10128
Brief Title of Request Dash and Body camera replacement
Estimated Cost Department Priority(year) 2030
Capital Improvement Plan Form For Years 2026-2030__
St. Croix County Sheriff's Office
400,000
Brief Summary of Request
To upgrade our body camera and squad dash cameras to improve video quality, storage capacity, and system
reliability, and officer safety.
Body Camera replacement is 86 cameras (including the corrections deputies)
Dash Camera replacement is 41
Cloud storage for all body and dash cameras.
Discussion of Need
Technology will continue to change, and our current dash cameras will become outdated. They are electronic
equipment exposed to harsh conditions. The recommended replacement of dash cameras is 7-10 years, leading to
reduced video clarity and reliability issues. Our current dash cameras are under a 5 year warranty and it ends
5/1/2028, which is the end of our contract. For years 2028 and 2029, we will have to cover cloud service and we
will be out of warranty.
Body Cameras should be replaced every 3 to 5 years, depending on when the batteries start to lose their ability to
hold a charge. We have one free refresh on our current body cameras, which will be done in 2026-2027.
Most agencies on our county are using Getac dash and body cameras, which makes it easier for our District
Attorney's office.
The cost does include install of new cameras in alls squads.
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Page 56 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department St. Croix County Sheriff's Office Project # or New 10131
Brief Title of Request Squad Radar Replacement
Estimated Cost Department Priority(year) 2030
Capital Improvement Plan Form For Years 2026-2030__
$60,000
Brief Summary of Request
We need to begin replacing aging speed radar units in squads due to their age and rising maintenance costs. Most of
our current units are 10–13 years old and beyond their recommended manufacture service life.
Discussion of Need
urrently, 30 of our 38 patrol squads are equipped with radar units that are between 10 and 13 years old. In recent
years, new radar units have only been purchased for newly added patrol positions, meaning the majority of our
equipment is well beyond its typical service life.
As these radar units continue to age, the cost of repairs is steadily increasing. Our most recent repair resulted in a
recommendation to replace the units due to age.
With the addition of new patrol positions, we have already integrated a limited number of new radar units into the
fleet. To fully update the remaining squads, 30 new radar units are needed at an estimated cost of $3,000 per unit.
Radar units generally have a recommended replacement cycle of 7 to 10 years. To avoid a large, one-time
replacement cost in 2030, we plan to purchase a few radar units each year as part of a phased upgrade.
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Page 57 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New 10132
Brief Title of Request Taser replacment Sheriff's Office
Estimated Cost $392,670 for 75 Tasers or $88,194per year for 15 Department Priority(year) 2030-2035
Brief Summary of Request Taser Replacement– Transition from X26P to Taser 10
The X26P has been a reliable Conducted Electrical Weapon (CEW), but with advancing technology and the X26P nearing its end of service life within
the next three years, it is time to plan for replacement.
We propose beginning a phased replacement with the Taser 10 by purchasing 15 units per year, starting prior to 2030, at an annual cost of $88,194,
with a 5% annual price increase. This would establish a recurring expense and maintain a 5-year replacement cycle.
Cost Breakdown & Life Cycle:
• X26P (with warranty): $1,857.76/unit | 5-year service life (current Taser)
• Taser 10 (with warranty): $5,379/unit | 5-year service life
o One-time training/equipment cost: $10,200 (unless all 75 units are purchased at once there will be a $7,500 discount is available.)
Annual Replacement Cost (Q4 2025 estimates, 13 units):
• X26P: $24,150 (current tasers)
• Taser 10: $77,434 (if we upgraded in 2025 with mandatory VR equipment for training)
Discussion of Need
The X26P is coming to the end of its life, and Taser will transition with the replacement Taser 10, which has a
significant increase per unit. A Taser is a critical tool for law enforcement, providing a less-lethal option to control
resistant or violent individuals while reducing the risk of injury to officers and suspects. It allows for effective de-
escalation in dangerous situations, minimizing the need for physical force or lethal alternatives. Tasers improve
officer safety, enhance public protection, and align with modern policing strategies focused on reducing harm. There
are no competitors in this field for an alternative. With this package, it will also include Tasers, Virtual Reality
training, which we cannot op-out of.
We currently have the following estimated replacement schedule of tasers:
2026- 16 X26 Tasers ($29,724)
2027- 18 X26 Tasers ($33,439)
2028 - 0 Replacements
2029- 25 X26 Tasers ($46,444)
Axon offers a few incentives-discounts based on quantity, time of year. The prices are estimates until a final quote.
On Going Increase in Revenues/Expenses or Cost Savings if Approved
None at this time.
Capital Improvement Plan Form For Years 2026-2030__
Sheriff's Office
Page 58 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 59 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 60 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 61 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 62 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or NewNew
Brief Title of Request Drone (sUAS) fleet replacement
Estimated Cost $44,500 Department Priority(year) 2031
Brief Summary of Request
This request seeks funding for the phased replacement of the Sheriff''s Office aging Small
Unmanned Aircraft Systems (sUAS) fleet.
Discussion of Need
The current inventory of eight airframes will be pushed to their operational limits, resulting in degraded battery
performance, software obsolescence, and increased maintenance downtime.
The Sheriff's Office drone program has evolved to a critical daily resource. Our current fleet will pushed to meet the
rigorous demands of modern law enforcement operations.
- $25,000 DJI M300 with H30T thermal camera - Large airframe, search and rescue platform.
- $13,000 DJI M30T with thermal camera - Mid size airframe, search and resuce, special events, cell tower inspections.
- $6,500 Tether - Used for sustained drone operations during special events.
These will be requested for the 2032 CIP
- $32,000 ($8,000 each) DJI Matrice 4T - Small size airframe, search and resuce, four issued to patrol for immeditae critical
response.
- $4,200 ($2,100 each) DJI Avata2 - Mini drone size, two used for interior building search and clearanc for tactical
operations.
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Sheriff's Office
Page 63 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2025-2029__
Page 64 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 65 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 66 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 67 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 68 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 69 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 70 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 71 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 72 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 73 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 74 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 75 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 76 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 77 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 78 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 79 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 80 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 81 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2027-2031__
Page 82 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 83 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 84 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
Staff Review and Comment
Capital Improvement Plan Form For Years 2024-2028__
Page 85 of 88
CAPITAL IMPROVEMENT REQUEST
CAPITAL, EQUIPMENT, RENOVATION,
and MISCELLANEOUS
Department Project # or New
Brief Title of Request
Estimated Cost Department Priority(year)
Brief Summary of Request
Discussion of Need
On Going Increase in Revenues/Expenses or Cost Savings if Approved
Capital Improvement Plan Form For Years 2026-2030__
Page 86 of 88
Consideration of Debt Funding and Timing for Major Projects
Cover Memo
To: Committee of The Whole
From: Ken Witt, County Administrator
Dustin Hawkins, Finance Director
Date: July 9, 2026
Agenda Item: Consideration of Debt Funding and Timing for Major Projects
Background Information:
Current annual debt service payments are approximately $11 million. Issuing an additional $70 million in debt would
increase annual debt service to approximately $15 million. Based on the current County tax levy rate of $2.595 per
$1,000 of equalized value, and assuming no growth in the tax base, the County levy rate would increase to
approximately $2.87 to support the additional debt payments.
In practice, growth in the tax base would likely reduce the actual impact because the cost would be spread across
additional taxable property value. Under this baseline assumption, however, the increase from $2.595 to $2.87
represents an additional $0.275 per $1,000 of equalized value, or approximately $27.50 annually for every $100,000 of
property value. A home valued at $400,000 would therefore see an estimated annual County tax increase of
approximately $110.
If the project were delayed until 2030, annual debt service would peak at approximately $14.5 million due to the
scheduled retirement of existing debt. Under the same assumptions, the County levy rate would increase to
approximately $2.84, or $0.245 per $1,000 above the current rate. This equates to approximately $24.50 annually per
$100,000 of property value, or about $98 annually for a $400,000 home.
Delaying the project by three years would reduce the estimated tax impact by approximately 11%. However, that
savings should be weighed against anticipated construction cost inflation. If project costs increase by more than 11%
over the next three years, the financial benefit of delaying the project would largely be offset. This comparison provides
a useful benchmark when evaluating project timing.
For historical context, the County tax levy rate was $2.825 per $1,000 in 2024 and has declined over the past two years
to the current rate of $2.595. In addition, the County portion represents, on average, only about 20% of a property's
total tax bill.
Page 87 of 88
Options
Option A: Move Ahead as Planned
Complete both the jail expansion and emergency communications infrastructure as a single project, allowing the
earliest project completion while locking in construction costs sooner.
o December 2026 - Resolution Authoring up to $70 million in Debt
o January 2027 - Start Design of Jail Expansion and Emergency Communications Infrastructure
o Late 2027 Resolution Approving Sale of Bonds
o 2028-2029 Construction Phase
Option B: Approve Single Bond Plan with Phased Construction
Authorize the full borrowing amount initially but phase project design and construction to spread implementation over
a longer period while maintaining one debt authorization.
o December 2026 - Resolution Authorizing up to $70 million in Debt
o January 2027 - Start Design of Emergency Communications Infrastructure
o January 2028 - Start Design of Jail Expansion
o Mid to Late 2028 Resolution Approving Sale of Bonds
o 2028-2029 Construction of Emergency Communication Infrastructure
o 2029-2030 Construction of Jail Expansion
Option C: Approve Multiple Bonding Stages
Separate the projects into two debt authorizations and two bond issuances, providing greater flexibility while delaying
the jail project, but potentially increasing total project costs.
o December 2026 - Resolution Authorizing up to $20 million in Debt
o January 2027 - Start Design of Emergency Communications Infrastructure
o December 2027 - Resolution Authorizing up to $50 million in Debt
o January 2028 - Start Design of Jail Expansion
o Early 2028 Resolution Approving Sale of $20 million Bonds
o 2028-2029 Construction of Emergency Communication Infrastructure
o Early 2029 Resolution Approving Sale of $50 million Bonds
o 2029-2030 Construction of Jail Expansion
Decision Point: The Board should determine whether its priority is (A) completing both projects as quickly as practical,
(B) phasing construction while maintaining a single financing strategy, or (C) preserving future flexibility through
separate debt authorizations and bond issuances.
Page 88 of 88
Source: St. Croix County website. First collected Oct 9, 2026.