Marinas and Moorings Committee Meeting Agenda
Wednesday, October 7, 2026 – 8:00 AM
Village Hall – 9996 Water Street
NOTE: THIS MEETING WILL BE SIMULTANEOUSLY HELD VIA TELECONFERENCING. STAFF,
COMMITTEE MEMBERS AND THE PUBLIC ARE WELCOME TO PARTICIPATE IN THIS MANNER.
TELECONFERENCING WILL BE AVAILABLE BY COMPUTER, PHONE, TABLET, OR DIAL-IN.
CONNECTION INFORMATION BELOW:
1. Call to order
2. Changes in agenda
3. Visitors’ comments
4. Previous Minutes
5. Discussion and consideration regarding the 2027 Budget
6. Next Meeting Date
7. Adjournment
Please join my meeting from your computer, tablet, or smartphone.
https://meet.goto.com/524334237
You can also dial in using your phone.
Access Code: 524-334-237
United States: +1 (408) 650-3123
***Deviation from the listed order may occur***
There may be a quorum of the Village Board or another Village Committee present; no action will be taken by any committee other
than the one listed on the agenda. Please note that upon reasonable notice, efforts will be made to accommodate the needs of
disabled individuals through appropriate aids and services. For additional information, please contact Andrea Collak, Clerk, Village
of Ephraim, PO Box 138, Ephraim, WI 54211
Date: 10/2/2026
Andrea Collak, Clerk X Village Administrative Office
X Visitors’ Center
X Post Office
Kim Roberts, Deputy Clerk X Website: ephraim.wi.gov
X Emailed to WDOR Radio/Peninsula Pulse
1
VILLAGE OF EPHRAIM
MARINAS AND MOORINGS MINUTES
WEDNESDAY, SEPTEMBER 2, 2026 – 8:00 AM
9996 Water Street - Ephraim Village Hall
Action Items:
B. Nelson moved, Thorp seconded to approve the minutes of August 5, 2026, as presented, all ayes.
Motion carried.
The consensus of the Marinas and Moorings Committee members present regarding parcels 121240033B and
121240031C was to consider expanding state highway parking along the parcels as a priority to the greatest
extent possible, to extend the existing walking path that originates from the North, and the method of how to
extend the walking path is to be determined and may need preliminary engineering to answer pending questions
about grade and curb separation, and a path spur from the parking spaces to the marina building is not
recommended.
B. Nelson moved, Thorp seconded to adjourn at 9:45 AM, all ayes. Motion carried.
Present: John Held, Bruce Nelson, Bob Plansky, BD Thorp, Tim Nelson-Chair.
Absent: None.
Guests: None.
Staff: Brent Bristol - Village Administrator/Harbormaster, Justin MacDonald – Fire Chief/Maintenance
Manager, and Kim Roberts – Deputy Clerk.
1. Call to Order: The meeting was called to order by T. Nelson at 8:01 AM.
2. Changes to the agenda: There were no changes.
3. Visitors’ Comments: There were no comments.
4. Approval of the previous minutes:
B. Nelson moved, Thorp seconded to approve the minutes of August 5, 2026, as presented, all ayes.
Motion carried.
5. Discussion regarding future use of newly acquired property north of Firehouse Dock:
The Committee engaged in substantial discussion regarding the future development of the newly acquired
property north of the Firehouse Dock. Held and B. Nelson collaborated and presented two (2) conceptual
proposals to the Committee to consider and review visually during the meeting.
Site Overview
The site was described as bounded to the north by the existing walkway, with a limited asphalt shoulder
along the road serving as a step-out area for parked vehicles. The site also contains some underbrush, a
potentially salvageable tree, a manhole cover near the marina office, and utility boxes. An existing cement
sidewalk originates from near the launch ramp and connects the area to the crosswalk leading to the
Firehouse Museum.
Parking Expansion
Both proposals incorporated the addition of parking spaces along the road, extending southward from the
current last designated parking spot. Preliminary measurements suggested a possibly exaggerated maximum
of seven (7) additional spaces, though it was acknowledged that large vehicles with trailers could
effectively reduce the usable number and create sightline concerns for drivers exiting the marina. The
Committee broadly agreed that expanding parking to the extent legally and practically feasible was a high
priority.
It was noted that any parking added should be formally documented, as those spaces could be credited
toward future marina expansion requirements. Bristol noted that marina expansion is subject to parking
ratios, and that documenting a net gain in parking spaces now could protect the Committee's options down
the road, even if expansion is not an immediate goal. A prior informal understanding with the DOT that
2
would have allowed a simple extended shoulder to serve as a walking path was noted to no longer be viable
given changes in DOT personnel and policy.
Walkway Extension
The second major element discussed was extending the pedestrian walkway through the property to connect
the existing northern path to the marina area and ultimately to the crosswalk toward the Firehouse Museum.
Two (2) conceptual alignments were presented: One routing the path closer to the highway, and one routing
it along the shoreline side of the property.
The highway-adjacent alignment would likely require a barrier curb between the parking stalls and the
walkway per DOT standards, and would preserve the bulk of the interior green space. The shoreline-
adjacent alignment would follow the water's edge, potentially requiring some fill, and would necessitate
coordination with the existing beach and natural shoreline features. Both alignments were noted to have
similar walkway widths and comparable impact on overall green space.
It was agreed that both options remained viable and would benefit from preliminary engineering review to
answer questions about curb requirements before a final recommendation is made.
Spur Walkway
A proposed spur walkway running between the marina building and the dinghy storage area was discussed
as an element of one of the concepts. After debate, the Committee reached consensus that no spur walkway
should be included in either option. Members expressed concern about increasing foot traffic near the
dinghy storage area and the launch ramp. It was noted that no well-worn path currently exists in that
corridor, indicating that a formal walkway is not needed.
Shoreline and Green Space
The Committee expressed a strong preference for preserving the natural character of the existing shoreline.
The small sandy beach area was described as one of the last natural shoreline segments in the Village, and it
was agreed that it should not be formally developed or restricted. Members noted the beach has been used
informally for kayak launches, dog walking, and occasional sunbathing, and that enforcement of any use
restrictions would be impractical. The area was also identified as a potential future access point for dredging
operations on the north side of the main pier.
Concerns were raised about invasive phragmites growth along the rocky shoreline to the north. It was
suggested that the Village explore eradication efforts, referencing a prior community permit with the DNR
for phragmites removal. Bristol indicated they would contact the relevant county invasive species
coordinator to determine the current process.
Existing Maple Tree and Concrete
The Committee noted that any grading or fill work in the area should be carefully managed to avoid
harming the existing maple tree near the dinghy storage area. A preference was stated for routing any
walkway toward the road rather than around the tree. Additionally, it was recommended that any upcoming
concrete work on the property be coordinated with known deferred repairs to the existing sidewalk system
near the marina building, including sections that have been cracked by heavy equipment. Reinforcing the
concrete and installing a protective trench for the shallow waterline beneath the courtyard was also raised as
a concurrent improvement to consider.
Marina Expansion
B. Nelson raised the question of whether the Committee intended to make any recommendation regarding
marina slip expansion in connection with this property. After discussion, the Committee affirmed it is not
recommending marina expansion at this time, citing the significant cost involved — estimated at $500,000
to $1,000,000 depending on scope — and the lack of a practical path forward in the near term. However, it
was emphasized that the Committee is not recommending against future expansion, and that documenting
current slip counts and any parking gains is important to preserve that option for future Committees.
3
Next Steps
The Committee agreed to prepare refined versions of the two walkway concepts, parking, removal of the
spur element, and to present them to the Physical Facilities Committee for their input with the following
consensus from the Marinas and Moorings Committee: The consensus of the Marinas and Moorings
Committee members present regarding parcels 121240033B and 121240031C was to consider expanding
state highway parking along the parcels as a priority to the greatest extent possible, to extend the existing
walking path that originates from the North, and the method of how to extend the walking path is to be
determined and may need preliminary engineering to answer pending questions about grade and curb
separation, and a path spur from the parking spaces to the marina building is not recommended.
Held and B. Nelson indicated they would attend that meeting to provide context and answer questions.
Bristol suggested that preliminary engineering — at roughly a 30-percent design level — may be
appropriate to address grade, drainage, and DOT compliance questions before a final recommendation is
brought to the Village Board.
6. Discussion regarding Pier and Waterfront projects:
Bristol reported that Pier and Waterfront had been consulted regarding installation of the two new finger
piers. The contractor expressed a preference for a fall rough installation during the scheduled haul-out,
which would allow the Committee to evaluate placement, spacing, and structural connections before the
spring season. Bristol suggested that rub rail repairs would be addressed as part of that installation. No
redecking was contemplated at this time.
The Committee discussed the need to extend the main pier by two feet (2’) in relation to installation of the
new finger piers in order to be parallel with the main pier. Bristol and T. Nelson were authorized by the
Committee to work directly with the contractor to determine the preferred configuration and associated cost,
given the time-sensitive nature of a fall installation.
Bristol noted that proposals for shoreline repair work, including sheet pile analysis discussed in prior
meetings, had been set aside during the busy season and would be pursued again in the fall and winter to
have options ready for a future decision.
7. Update regarding off-season work list and current projects/operations:
Bristol noted that the off-season work list, included in the previous meeting minutes, would be maintained
as a standing agenda item going forward, with amendments added as work is completed. Maintenance Staff
did not have an opportunity to debrief prior to this meeting, but Bristol acknowledged that additional items
had been completed since the last meeting.
Regarding mooring buoy inventory, Bristol indicated that a mid-season inventory discrepancy — where the
mooring area was short on buoys — had been miscommunicated. An updated inventory list had since been
received, and orders for replacement and additional buoys would be placed promptly for readiness ahead of
the next season.
8. Discussion regarding 2027 budget:
Bristol advised that the full budget reconciliation is conducted at the end of September each year to ensure
year-to-date numbers are current and consistent. Detailed budget figures would be distributed to the
Committee in advance of the October meeting, which would serve as the primary budget discussion session.
On the topic of fee increases, Bristol noted that the Board's direction from the prior year was to consider
inflation-based annual adjustments to the fee schedule. He acknowledged there is an administrative burden
to annual changes and suggested a possible approach of tracking annual inflation figures and applying
adjustments periodically rather than every year. It was also noted that launch fees may be subject to
additional DNR approval requirements once they exceed ten dollars, and that staff would clarify the current
process if an increase is being considered.
The Committee discussed whether current fee levels remain competitive with comparable facilities in Door
County. Members expressed support for keeping fees at or near the regional market rate — particularly for
the launch ramp — noting that being the lowest-priced launch in the area generates excess demand that
4
strains parking and staffing. Research into current regional rates was suggested as a precursor to any fee
recommendation. The possibility of implementing digital or QR-code-based payment options at the launch
ramp was briefly revisited, with Bristol noting the key challenge remains ensuring real-time payment
verification for staff in the field. Further research was required.
The Committee acknowledged several anticipated near-term capital expenditures, including the two new
finger piers, a share of the utility trench work associated with the Anderson Dock reconstruction (estimated
at approximately $15,000 for the marina's portion), and potential dredging. It was noted that the current
reserve fund balance is estimated at approximately $340,000. B. Nelson cautioned that while the reserve
appears healthy, a meaningful portion is already earmarked for known projects, and the Committee should
be thoughtful before directing any of it toward Village-wide expenditures such as the recently acquired
property.
Held complimented Assistant Harbormaster Reynolds's strong performance throughout the season.
Bristol noted that staffing challenges with a third seasonal employee resulted in fewer hours worked than
planned — meaning salary expenditures are likely to come in below budget. Bristol indicated that off-
season conversations would address staffing expectations for the coming year.
9. New business for the next meeting:
The next meeting of the Marinas and Moorings Committee will take place on Wednesday, October 7, 2026,
at 8:00 AM.
10. Adjournment:
B. Nelson moved, Thorp seconded to adjourn at 9:45 AM, all ayes. Motion carried.
Recorded by Kim Roberts – Deputy Clerk
Activity
Description Code Description
Item.
Breakdown######## 2024 2025 2026 2027 Budget
Increase
(Decrease)YTD 9/30/2026 2025 Actual 2024 Actual 2023 Actual
Row 202-40-INCOME
1 Docks Fund 46751 Moorings 10,000$ 10,000$ 8,000$ 8,000.00$ -$ 7,610$ 6,549$ 9,529$ 9,435$
2 Docks Fund 46752 Seasonal Slips 82,000$ 84,000$ 84,000$ 84,000.00$ -$ 79,427$ 79,745$ 84,407$ 84,822$
3 Docks Fund 46753 Launching Fees $10 10,000$ 10,000$ 10,000$ 10,000.00$ -$ 8,037$ 9,340$ 10,780$ 11,308$
4 Docks Fund 46754 Transient Fees 15,000$ 25,000$ 25,000$ 25,000.00$ -$ 31,696$ 30,910$ 23,904$ 18,670$
5 Docks Fund 46755 Seasonal Dinghy Fees 1,500$ 1,000$ 1,000$ 1,000.00$ -$ 794$ 659$ 943$ 1,240$
6 Docks Fund 46756 Seasonal Launch Fees 2,000$ 2,000$ 2,000$ 2,000.00$ -$ 2,005$ 2,515$ 1,575$ 2,250$
7 Docks Fund 46757 Docks - Late Fees -$ -$ -$ -$ -$
8 Docks Fund 48100 Interest Income 500$ 2,000$ 4,000$ 4,000.00$ -$ 4,085$ 6,869$ 6,630$ 838$
9 Docks Fund 48900 Misc Income -$ -$ -$ -$ -$
10 Docks Fund 49200 Transfers In - Other Funds - Docks -$ -$ -$ -$ -$
11 Total Revenue 121,000$ 134,000$ 134,000$ 134,000.00$ -$ 133,654$ 136,587$ 137,768$ 128,563$
202-40 EXPENSE
12Docks Admin 55430-100Salaries Assis Harbormaster 27,000 $ 27,000$ 24,000$ 24,000.00$ -$ 11,295$ 17,227$ 18,052$ 25,338$
13Docks Admin 55430-101SS/Med 900$ 1,500$ 1,500$ 1,500.00$ -$ 864$ 1,317$ 1,381$ 1,938$
14Docks Admin 55430-102Retirement -$ -$ - $ - $ -$ - $
15Docks Admin 55430-103Health Insurance -$ -$ - $ - $ -$ - $
16Docks Admin 55430-104Disability Insurance -$ -$ - $ - $ -$ - $
17Docks Admin 55430-105Workers Compensation 660$ 337$ 337$ 337.40$ -$ 296$ 348$ 317$ 601$
18Docks Admin 55430-110Personel Services $14,400 prior to BR Cleaning 19,900$ 19,900$ 19,900$ 19,900.00$ -$ 19,900$ 19,900$ 19,900$ 12,000$
19Docks Admin 55430-211Property Insurance 5,398$ 5,776$ 5,903$ 5,903.15$ -$ 5,875$ 5,747$ 5,300$ 4,950$
20Docks Admin 55430-303Electricity 1,800$ 1,800$ 1,800$ 1,800.00$ -$ 1,266$ 1,746$ 2,084$ 2,564$
21Docks Admin 55430-305Well Tests -$ 120$ 120$ 120.00$ -$ 240$ 180$ 210$
22Docks Admin 55430-306Phone -$ -$ - $ - $ -$ - $ 284 $
23Docks Admin 55430-307Water Treatment Herbicide 1,000$ 1,000$ 3,000$ 3,000.00$ -$ 1,474$ 1,466$
24Docks Admin 55430-308Sewer Fees 496$ 496$ 496$ 496.00$ -$ 300$ 544$ 496$ 464$
25Docks Admin 55430-309Internet 1,000$ 1,300$ 1,300$ 1,300.00$ -$ 1,266$ 1,517$ 1,330$ 1,187$
26Docks Admin 55430-312Cellphone 600$ 300$ 300$ 300.00$ -$ 193$ 257$ 271$
27Docks Admin 55430-331Postage 175$ 175$ 175$ 175.00$ -$ - $ 82 $ 164$
28Docks Admin 55430-333Office Supplies/Expeses 1,200$ 1,200$ 1,200$ 1,200.00$ -$ 1,104$ 659$ 514$ 1,208$
29Docks Admin 55430-334Computer Supplies/Expensesdockwa 2,000 $ 3,600$ 6,000$ 6,000.00$ -$ 5,847$ 5,847$ 3,588$ 3,588$
30Docks Admin 55431-210Other Contractual ServicesBathroom Cleaning Elim - $ -$ - $ - $ -$ - $ 4,186 $
31Docks Operations55431-240Buoys & Placement J.Long $5,200 7,500$ 10,000$ 10,000$ 10,000.00$ -$ 10,687$ 13,966$ 13,554$
32Docks Operations55431-360Dock Repair 8,000$ 8,000$ 8,000$ 8,000.00$ -$ - $ 1,014 $ 15,799$
33Docks Operations55431-361Dock Equipment 1,500$ 1,500$ 1,500$ 1,500.00$ -$ 232$
34Docks Operations55431-362Minor Projects P&W $6,000 10,000 $ 10,000$ 10,000$ 10,000.00$ -$ 1,229$ 1,746$ 14,657$ 16,491$
35Docks Operations55431-810Equipment Outlay 31,871$ 39,996$ 38,468$ 38,468.45$ -$ - $ 33,639 $
36Docks Operations55431-820Bldg Improvement Outlay -$ -$ - $ - $ -$ - $
37Docks Operations55431-830Other Improvement Outlay -$ -$ - $ - $ -$ 8,255$ 9,970$
38Docks Operations55431-840Project Outlay -$ -$ - $ - $ -$ - $
39Debt Service - Principal58100-600Principal -$ -$ -$ -$ -$ -$
40Debt Service - Interest58200-601Interest -$ -$ - $ - $ -$ - $
41 Total Expense 121,000$ 134,000$ 134,000$ 134,000.00$ -$ 70,323$ 82,437$ 116,389$ 90,762$
Launch Fees in Door County
Location Launch Fee Amount
Village of Sister Bay • Launch fee Daily – $10.00
• Seasonal Pass – $100.00
• Commercial Seasonal Pass – $300.00 (For any business
using the launch ramp)
City of Sturgeon Bay: Sawyer Park Boat
Launch – Intersection of Neenah & East Oak
Street
City of Sturgeon Bay: Sunset Park Launching
Ramp – 747 North 3rd Avenue
• The cost for a daily (one time only) pass is $8.00.
• If you are a city resident, the fee for a seasonal pass is
$50.00, and the fee for a non-resident launch pass is
$80.00.
County of Door Launches:
Chaudoir's Dock County Park
George K. Pinney County Park
Robert M. Carmody County Park
Forestville Dam County Park
Lily Bay County Park
Frank E. Murphy County Park
Sugar Creek County Park
• Daily Launch $8.00 /day
• Annual Permit (recreational) $60.00
• 2nd Launch Permit (recreational) $30.00 Replacement
Permit $25.00
• Annual Permit (commercial) $100.00
Town of Baileys Harbor • Daily Launch Pass $10.00
• Seasonal Launch Pass -Property Owner $60.00
• Seasonal Launch Pass - Non Baileys Harbor Property
Owner $80.00
• Commercial Seasonal Launch Pass* $250.00
Village of Egg Harbor • Daily Launch $12.00
• Seasonal Launch non-resident, non-seasonal slip holder
$140
• Seasonal Launch: Resident and seasonal slip holder:
$110
• Seasonal Commercial Launch & commercial permit:
$140/trailer.
Town of Liberty Grove • Daily Launch $10
• Annual launch (private) $75/watercraft
• Annual launch (commercial rental outfitters)
$100/watercraft
• Commercial service launch $50/trailer
Washington Island • Daily Launch $7.00
• Annual Launch $50
Town of Gibraltar • Daily Launch $10.00
• Seasonal Launch $60.00
• Commercial Launch $180