CITY OF MINERAL POINT 137 HIGH STREET, SUITE 1
MINERAL POINT, WI 53565
608-987-2361
OFFICE OF THE CITY CLERK-TREASURER
Mayor – Danny Clark
City Administrator | Troy Maggied | administrator@cityofmineralpointwi.gov
City Clerk-Treasurer | Christy Skelding | cityclerk@cityofmineralpointwi.gov
AGENDA
CITY OF MINERAL POINT
STREETS AND WATER & SEWER JOINT COMMITTEE MEETING
Wednesday, August 12, 2026, 5:30 PM
City Hall Community Room
1. Call to Order, Roll Call, and Confirmation of Compliance with the Open Meetings Law
2. Approval of July 29, 2026, Minutes
3. Discussion and possible action on Maiden St. repairs.
4. Adjourn.
Agenda Posted and Distributed: Friday, August 7, 2026.
Reasonable accommodations for participation in this meeting by persons with disabilities, as defined by the
Americans with Disabilities Act, will be made upon request and if feasible. Please contact the City Clerk’s office
(608-987-2361) at least 24 hours prior to the scheduled meeting so that necessary accommodations can be
provided.
CITY OF MINERAL POINT 137 HIGH STREET, SUITE 1
MINERAL POINT, WI 53565
608-987-2361
OFFICE OF THE CITY CLERK-TREASURER
Mayor – Danny Clark
City Administrator | Matthew Honer | administrator@cityofmineralpointwi.gov
City Clerk-Treasurer | Christy Skelding | cityclerk@cityofmineralpointwi.gov
MINUTES
CITY OF MINERAL POINT JOINT MEETING
STREETS COMMITTEE AND WATER & SEWER COMMITTEE
Wednesday, July 29, 2026, 5:15 PM
Community Room, City of Mineral Point City Hall
CALL TO ORDER/ROLL CALL
Chair Christensen called the meeting to order at 5:15 pm.
Mike Christensen (chair) Present (left at 6:20 p.m.)
Brian Graber Present (Water and Sewer Alternate)
Steph McKeon Present (5:22 p.m.)
Jared Weier Present
Others Present: City Administrator Troy Maggied, Administrative Advisor Matthew Honer, City Clerk
Christy Skelding, Water/Sewer Superintendent Nate Fosbinder, Evan Chambers, Andy Jacque, Abby Lee
APPROVAL OF JULY 14, 2026 MINUTES
Motion (Graber/Christensen) to approve the minutes. Motion carried, all voting aye (3-0).
DISCUSSION AND POSSIBLE ACTION ON FOUNTAIN STREET LIFT STATION GENERATOR.
Water and Sewer Superintendent Nate Fosbinder reported that, following the committee's request at
the previous meeting, he obtained more comparable quotes for the Fountain Street Lift Station
generator project. The committee had requested quotes that included labor, materials, and installation
for an "apples-to-apples" comparison.
Fosbinder explained that A.B. Electric declined to provide a quote utilizing a used generator. Their
proposal, which included a new generator, totaled just over $76,000 and included a standard two-year
warranty. He noted that A.B. Electric's labor costs were lower than the competing quote.
Wisconsin Electric provided a proposal utilizing a used generator. Although its labor costs were slightly
higher, the total project cost was approximately $65,000 to $66,000, which aligns closely with the
$65,000 that was budgeted and borrowed for the project. Fosbinder stated that the project was
originally planned around the purchase of a used generator and did not believe the additional $10,000
cost for a new unit was justified solely for a two-year warranty. Based on the maintenance history of the
used unit, he expressed confidence in its reliability.
Fosbinder also noted that purchasing a new generator directly from the manufacturer would be less
expensive; however, the estimated lead time is approximately 22 weeks. That option would also include
a two-year warranty through the Wisconsin Electric distributor.
CITY OF MINERAL POINT 137 HIGH STREET, SUITE 1
MINERAL POINT, WI 53565
608-987-2361
OFFICE OF THE CITY CLERK-TREASURER
Mayor – Danny Clark
City Administrator | Matthew Honer | administrator@cityofmineralpointwi.gov
City Clerk-Treasurer | Christy Skelding | cityclerk@cityofmineralpointwi.gov
Based on the available options, Fosbinder recommended proceeding with the used generator and
contracting with Wisconsin Electric for installation. He explained that freight to deliver the generator to
the job site would cost approximately $2,550. As an alternative, the City could arrange for employees to
transport the generator, although the City does not own a suitable trailer. While employees or
coworkers may have access to trailers, Fosbinder suggested the committee recommend a total project
cost not to exceed the quoted amount.
Committee members discussed the delivery options. Administrator Maggied expressed concern about
asking employees to transport the generator using personal vehicles and trailers, stating that the City
would remain responsible for any issues that may arise. Alder Christensen agreed, indicating that he
preferred paying the $2,550 delivery charge to avoid potential liability and to prevent City employees
from being away from their regular duties for an entire day.
Motion (Christensen/Weier) to recommend Council approval of Wisconsin Electric’s proposal with a
used generator, including delivery, and installation done by Wisconsin Electric. Motion carried, all
voting aye (4-0).
DISCUSSION AND SUGGESTIONS FROM WATER QUALITY INVESTIGATIONS REGARDING OUR
CORROSION CONTROL TREATMENT STUDY.
Andy Jacque reviewed the Corrosion Control Treatment Study completed by Water Quality
Investigations (WQI), which was issued in March. The study evaluated the underlying causes of lead
corrosion within the City's water system.
Jacque explained that the study identified three primary factors contributing to corrosion. First, overall
water usage has declined significantly over the past 30 years, resulting in longer periods of water
stagnation within household plumbing, which increases the potential for corrosion. Second, the
condition of the City's wells has contributed to water quality concerns. He noted that Well No. 4 had
experienced a loss of capacity but has since been successfully chemically rehabilitated. Prior to the
rehabilitation, each time the well was placed into service it contributed water quality issues to the
distribution system. Third, naturally occurring chlorides in Well No. 3 make the water slightly more
corrosive.
The study concluded that replacing lead service lines is the most effective long-term solution for
reducing lead exposure. Jacque emphasized that public education will also play an important role by
informing residents of steps they can take to maintain their plumbing systems and reduce the potential
for corrosion. He noted that federal regulations govern water quality within the public water system, but
water quality at the tap cannot be regulated.
Jacque also explained that updates to the state plumbing code will require newly constructed homes to
utilize smaller plumbing systems, which should help reduce water stagnation. He stated that this code
change should be included as part of the City's public education efforts.
The Wisconsin DNR is expected to complete its review of the study within approximately 180 days and
will determine whether additional corrosion control treatment, such as the addition of a chemical
additive, will be required. Regardless of the DNR's determination, the City remains obligated under
federal and state requirements to continue replacing lead service lines.
CITY OF MINERAL POINT 137 HIGH STREET, SUITE 1
MINERAL POINT, WI 53565
608-987-2361
OFFICE OF THE CITY CLERK-TREASURER
Mayor – Danny Clark
City Administrator | Matthew Honer | administrator@cityofmineralpointwi.gov
City Clerk-Treasurer | Christy Skelding | cityclerk@cityofmineralpointwi.gov
Committee members discussed whether the City should begin implementing a public education
campaign before receiving the DNR's determination or wait until additional direction is provided. Alder
Christensen recommended developing a public education plan now so the City is prepared regardless of
the DNR's decision. Jacque noted that WQI has remaining funds available under its existing contract and
could assist with developing educational materials and messaging. He stated that WQI could provide the
technical information and suggested language, while the City could format the materials for public
distribution.
The committee also discussed adding a standing agenda item to future meetings to provide regular
updates on corrosion control efforts and the DNR review process. In addition, members discussed
amending the City's Water Use Ordinance to reference the current state plumbing code.
No action taken.
FACILITY PLAN UPDATE FROM TOWN AND COUNTRY ENGINEERING.
Evan Chambers of Town & Country Engineering provided an update on the City's wastewater treatment
facility planning process. He explained that the project has reached approximately 33% completion and
is being completed in three phases. The first phase focused on reviewing existing system data,
evaluating current conditions, and projecting future growth.
Chambers reviewed preliminary flow and nutrient data, noting that the wastewater treatment plant's
primary exceedances are hydraulically driven. Based on historical operating data, both the average daily
flow and peak hourly flow currently exceed the facility's original design capacity.
He explained that during dry weather there is little measurable infiltration into the collection system;
however, during wet weather events, significant infiltration and inflow (I&I) enter the system. As a
result, the City is treating large volumes of water that are not generated by customers, increasing the
hydraulic loading on the treatment plant.
Chambers discussed population projections used in the planning process. The Wisconsin DNR requires
the use of Wisconsin Department of Administration (DOA) population projections, which estimate
Mineral Point's population will be approximately 1,996 residents by 2050. He noted, however, that
these projections do not reflect the City's current growth efforts. The City's existing population is
approximately 2,599 residents, and a projected 69-lot residential buildout at an estimated 2.5 persons
per household would increase the design population to approximately 2,771 residents. Chambers stated
that even if the final design population is established closer to 2,600 residents, there are design
approaches available to accommodate future growth.
Based on the preliminary analysis, Town & Country anticipates the facility will need to be designed for
additional hydraulic capacity, as current flows already exceed the plant's original design and future
growth is expected. Chambers noted that the engineering team continues to evaluate peak flow events,
as those conditions drive the sizing of pumps and other critical treatment infrastructure.
Chambers explained that Phase 1 will document all existing conditions and compile the information
required for submission to the DNR. Phase 2 will identify deficiencies, recommend improvements, and
provide preliminary cost estimates. During Phase 3, the City will evaluate the available alternatives and
determine its preferred path forward. The Facility Plan is scheduled for completion by the end of April
CITY OF MINERAL POINT 137 HIGH STREET, SUITE 1
MINERAL POINT, WI 53565
608-987-2361
OFFICE OF THE CITY CLERK-TREASURER
Mayor – Danny Clark
City Administrator | Matthew Honer | administrator@cityofmineralpointwi.gov
City Clerk-Treasurer | Christy Skelding | cityclerk@cityofmineralpointwi.gov
2027.
Chambers indicated that the existing wastewater treatment plant site has limited available space,
making future expansion through additional treatment tanks potentially challenging. He also reminded
the committee that the City must have a wastewater disinfection system operational by 2031 to meet
regulatory requirements.
No action taken.
ADJOURN.
Motion (Graber/McKeon) to adjourn at 6:26 pm. Motion carried, all voting aye (3-0).
STAFF REPORT
8/3/2026
TOPIC: Maiden St. Mill and overlay
☒ New Business ☐ Unfinished Business ☐ Reports
☐ Closed Session ☐ Ordinance/Resolution
Meeting: Streets, Sidewalks, and Solid Waste
Committee
Department Reporting: Streets Submitted by: Chad Whitford
ISSUE:
Maiden St. Asphalt surface deterioration
BACKGROUND/ANALYSIS:
Maiden St. From South Chestnut going west approx. 450 feet is in desperate need of attention. The
past two spring and summers I have tried to patch it. It is beyond patch repair at this point. I am
afraid with this surface also being in front of a church it is going to cause issues with elderly people
trying to navigate it to attend services. This stretch is also on my plow route and is pretty hard on
the front blade, you may be able to hear it across town when I go through there. WISLR report on
this Street has it at HMA 1988, I am not sure if that is accurate or not. Moving forward I will keep all
WISLR data up to date to the best of my ability.
RECOMMENDATION: Mill and overlay 450 ft heading west from intersection with South Chestnut.
I have two bids, one from Iowa County Highway Department, and one from Iverson Construction. It is my
recommendation to not take the lower bid and to and to accept the bid from Iverson Construction. Iverson is
a company that does asphalt all day every day. Their products, hot mix and cold mix are superior to the
County. The County uses a more coarse aggregate in their hot mix and does not get as smooth of a finish
as Iverson. Iverson will haul the millings and I will keep them for good fill. The county will take the milling
and use them in recycle blacktop. Iverson will do all the work necessary to clean the street and prep it for
tack and asphalt. The county requests that the city clean the street after milling. I don’t think we should take
the responsibility of prepping the surface for hot mix. Neil and Dillon both met me there at different times
and looked at the job in person. Neil has stated a couple times he is a little concerned about it milling and
we could have added costs. Dillion did not share those same concerns, said they might just have to skim
coat then do a final lift. I do think there is work in the future that Iowa County can help us get done. We used
them last year for a storm water project, I don’t think they are the best choice for this one.
FISCAL IMPACT: CIP $30,329.14
ATTACHMENTS:
Mineral Point, Wisconsin