Town Board Meeting April 18, 2025
The Town Board of the Town of Cooperstown, Manitowoc County, Wisconsin, convened
in open session on April 18, 2025, at 2:00 p.m., at the Town Hall for the purpose of a
Road Review and Town Board Meeting to follow. Town Chairman called the meeting to
order at 4:03 p.m.
Pledge of Allegiance.
Roll Call: Chairman Joe Havlovitz, Supervisor Anthony Shibler, and Supervisor Nick
Propson. No others were present.
The agenda has been publicly noticed at the one posting site and on the Town website.
Road Review: The Board, along with Dan Kasten, traveled the roads in Cooperstown
from 2:00 p.m. until 3:52 p.m., making observations of current conditions of roads,
bridges and culverts, with prior established 2025 road plans in mind. No action was taken
while on the road review.
As previously stated, the Town Board meeting then began at 4:03 p.m., to discuss the
road observations and identify potential next steps. Observations:
• Rosecrans from Fisherville to Marshek in the next several years will need some
random spot wedging.
• Rameker Road is currently having various potholes filled by our crew and does
show some slight early "alligator" cracking, which should be minor for the next
few years.
• Kocian Road is in need of major repair. The Board will move ahead with updated
quotes for future discussion of a plan of action.
• Frelich road is in overall good condition with some small pot patching by our
crew this year.
• Zander Road from the curve to the next curve, by Kane's property, is showing
alligator cracking and several newly erupted potholes. This will be considered for
repair in the future plan.
• Devil's River Drive is in need of a culvert replacement and leveling close to the
intersection of Zander. The Board will pursue quotes and investigate any
additional funds available (ARPA, etc.)
• Cedar Creek Drive has several potholes to be filled by our crew.
• Cooperstown Road west of Cedar Creek has some areas in need of leveling by the
bridge. The Board will investigate if the Town of New Denmark is able to add
several feet of repair on to their next road repair plan with our town adding that
extra cost for the repair.
• Kvitek Road 2025 road repair project was questioned as to reducing the scope or
postponing if possible due to the overall fair shape of the road sections listed/bid.
If flexible, freed up funds ($79K), could be redirected to Natchwey Road and
parts of Hidden Valley Road, between Pleasant Road and R. This may not be
possible in 2025 if the previous road repair bids have already been signed off with
Scott Construction. Town Chairman will verify status with the Town Clerk.
• Gretz Drive gravel road condition and culvert condition were reviewed. Potholes
have been filled and leveled by the Town crew with fair current condition. Culvert
is still functional and will be evaluated again next year.
• Fairhills Road will need some future edging with some potholes filled by the town
crew this year.
• Pleasant Road from Fisherville to Hidden Valley has some pothole damage with a
significant area near Fisherville to be filled by our crew. We will monitor the
long-term stability of this section to determine the next steps over the next few
years.
• Additional road details are listed in the updated Road Plan below:
2025 and Future Four Year Road Plan Tentative Updates 2025-2029
2025
Cooperstown Road Rosecrans Road to CTH T - chip seal
Zander Road CTH T to Pleasant Road - chip seal
Luebke Road Chip seal
Parizek Road Chip seal
Pautz Road Wedge
Kvitek Road Wedge (flexibility within contract and/or move to 2026?)
Hidden Valley Road Pleasant Road to R (resources available for some work in 2025?)
Devil's River Road Culvert and leveling by Zander Road - bids/option for 2025?
2026
Kvitek Road Possible move from 2025
Hidden Valley Road Pleasant road to R - remaining repairs needed not done in 2025
Hidden Valley Road Rosecrans to Chavla Road - wedge (LRIP grant expires 6/30/2029)
Pleasant Road Schley to washout area north - wedge
Kocian Road Estimated 1-1/2 miles of significant work - refresh bids for options
Hickory Grove Road Keehan to Kvitek Road - wedge
2027
Pleasant Road Devil's River Bridge to Schley Road - chip seal
Hickory Grove Road Herold Road to CTH NN - wedge
Fairhills Road & Ct Various wedging
Hickory Heights Cul de sac chip seal
Lakeview Drive Cul de sac chip seal
Zander Road CTH NN to Herold Road - wedge
Pautz Road Chip seal
2028
Hickory Grove Road CTH NN to Keehan Road - chip seal
Fairhills Road & Ct Chip seal
Zander Road CTH NN to Herold Road - chip seal
Schley Road CTH R to Pleasant - wedge
Rameker Road Marshek Road to curve
2029 Long Term
Pantzlaff Road TBD
Marshek Road Hidden Valley to Greenstreet - wedge
Fisherville Road Rosecrans Road to Kvitek Road
Herold Road Zander Road to Hickory Grove Road
Hickory Grove Road Rosecrans to Kvitek
The Board wrapped up the meeting with additional discussion to pursue investigating
ongoing additional funding opportunities such through LRIP and others. This is an
ongoing discussion point at the regular Town meetings as well.
On a motion by Supervisor Propson and seconded by Supervisor Shibler, moved to
adjourn. Motion passed at 4:52 p.m.
Minutes approved May 13, 2025 Respectfully submitted,
Joe Havlovitz, Chairman