2026-10-14 Water Works and Lighting Commission Packet
City of Wisconsin Rapids · Wood County · meeting of Oct 14, 2026 · Agenda packets
Open the original document More from City of Wisconsin Rapids
This document is no longer listed on City of Wisconsin Rapids's website. We kept the copy we read.
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
If given 72 hours’ notice, efforts will be made by the General Manager’s office to accommodate the needs
of disabled individuals through sign language interpreters and other auxiliary aids.
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399, Wisconsin Rapids, WI 54495-0399 (715) 423-6300
AGENDA
There will be a regular meeting of the Water Works and Lighting Commission in the
conference room on Wednesday, October 14, at 2:00 PM.
Listed below is the agenda for this meeting.
1. Call to order
2. Approval, additions, or corrections to the minutes of the following meetings
2.1. Regular Commission Meeting held September 9, 2026
2.2. Special Commission Meeting held September 25, 2026
3. Action Items
3.1 Amend the utility’s current parallel generation tariffs and authorize Great Lakes
Utilities to submit an omnibus filing to the Public Service Commission of
Wisconsin on the utility’s behalf
3.2 Consider a donation to Team Rapids
4. Department updates
4.1. Safety Coordinator
4.2. Line Superintendent
4.3. Electrical Engineer
4.4. Water Department Operations
4.5. Information Systems Administrator
4.6. Key Accounts Manager
4.7. Customer Support Supervisor
4.8. Director of Engineering and Metering
4.9. Chief Financial Officer
4.10. General Manager
5. Review of accounts payable
6. Adjourn
2.1
Regular Meeting of the Water Works and Lighting Commission
Wednesday, September 9, 2026
In Attendance:
Commissioner John Bergin
Commissioner Rick Merdan
Commissioner John Harper
Commissioner Kevin Fangman
Absent: Commissioner Jeff Penzkover was excused.
Also in attendance: Todd Weiler, Jeff Kuhn, Owen Yenter, Lynn Schroer, Shawn Reimer, Matt Stormoen,
Adam Breunig, Tyler Sneen, Sean Wall, and Heidi Schroeder.
Absent: Josh Elliott was excused.
1. Call to Order
Chairperson John Bergin called the meeting to order at 1:00 PM.
2. Approval, additions, or corrections to minutes of the following meeting
2.1 Regular Commission Meeting held
There was a motion made by John Harper, seconded by Kevin Fangman and carried to approve the
minutes of Regular Commission Meeting held on last meeting August 12, 2026, and to place them on
file. No nay votes were recorded.
3. Presentation from Ehlers Investment
There was a presentation by Tami Olszewski from Ehlers Investment Partners on the utility’s
investments. This presentation was informative only and no action was taken.
4. Department Updates
4.1 Safety Coordinator’s Report
This report was reviewed and discussed. Sean Wall answered questions regarding safety incidents.
4.2 Line Superintendent’s Report
This report was reviewed and discussed. In Josh Elliott’s absence, Todd Weiler answered questions
regarding failed transformers.
4.3 Electrical Engineer’s Report
This report was reviewed and discussed. In Tyler Sneen answered questions regarding recloser
troubleshooting and RTAC programming.
2.1
4.4 Water Department Operation’s Report
This report was reviewed and discussed. Adam Breunig answered questions regarding water volume
usage, bulk water fill station, and lead replacement status.
4.5 Information Systems Administration’s Report
This report was reviewed and discussed. Matt Stormoen answered questions regarding Virtual
Environment Migration and cell phone provider changes.
4.6 Conservation Manager’s Report
This report was reviewed and discussed. Shawn Reimer answered questions regarding solar array site
progress and rate change letters sent to commercial customers.
4.7 Customer Support Supervisor’s Report
This report was reviewed and discussed. Lynn Schroer answered questions regarding payments and
collections.
4.8 Director of Engineering and Metering
This report was reviewed and discussed. Owen Yenter answered questions regarding summer help,
usage and information to be displayed in new lobby, High School Substation Upgrade, and RP3
Applications.
4.9 Chief Financial Officer
This report was reviewed and discussed. Jeff Kuhn answered questions regarding water volume usage
and income, upcoming budget meeting, lead services customer contact, and the Ehlers presentation.
4.10 General Manager’s Report
This report was reviewed and discussed. Todd Weiler answered questions regarding GLU Marshfield
Energy Center.
5. Review of Accounts Payable
A listing of invoices and checks covering August was provided to the commission for review and all
questions answered truck 89 issues, tree trimming charges, bulk water fill station, projected health care
increase, lobby budget, parking lot completion, and Strand engineering charges.
6. Adjourn
There was a motion made by Rick Merdan, seconded by Kevin Fangman and carried to adjourn at 1:53
PM. No nay votes were recorded.
Respectfully submitted,
Rick Merdan, Secretary
2.2
Special Meeting of the Water Works and Lighting Commission
Friday, September 25, 2026
In Attendance:
Commissioner John Bergin
Commissioner Kevin Fangman
Commissioner John Harper
Commissioner Jeff Penzkover
Also in attendance: Todd Weiler, Jeff Kuhn, Owen Yenter, Shawn Reimer, Matt Stormoen, Adam Breunig, and
Matt Zacher.
Commission Rick Merdan was excused from this meeting.
1. Call to Order
Chairperson John Bergin called the meeting to order at 9:30 AM.
2. Consider donation to Team Rapids
The Commission discussed a donation to Team Rapids. Additional information was requested and will be
reconsidered at the next Commission meeting.
3. 2027 budget discussion and approval
There was substantial discussion on the 2027 capital and operation budget. Adjustments were made
to the capital budget. In the water capital budget, the line for replacing hydrants was increased to
$70,000. In the IT capital budget, a budget line for audio and video equipment for the conference
room was removed.
There was a motion made by Jeff Penzkover, seconded by Kevin Fangman and carried to approve the
2027 capital budget as amended. No nay votes were recorded.
There was a motion by Kevin Fangman, seconded by Jeff Penzkover and carried to approve the 2027
operation budget as presented. No nay votes were recorded.
4. Adjourn
There was a motion made by Kevin Fangman, seconded by Jeff Penzkover and carried to
adjourn at 12:01 PM. No nay votes were recorded.
Respectfully submitted,
John Harper, Acting Secretary
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399 Wisconsin Rapids, WI 54495-0399 (715) 423-6300
3.1
Amend the Utility’s current parallel generation tariffs and
authorize Great Lakes Utilities to submit an omnibus filing to the
Public Service Commission of Wisconsin on the utility’s behalf
Almost ten years ago, the utility changed its parallel generation tariff (buyback rate) from retail
rate to a cost that coincided with the true purchased power cost to the utility. At the time, the
utility decided to use the average cost of power from the previous year to pay solar customers
for excess generation, with some adjustments. This rate is updated annually. The 2026 rate is
7.28 cents per kWh.
The Public Service Commission did not provide any guidance on what utilities should pay
customers for excess generation. Some utilities continue to pay retail rates to incentivize
residential solar installation. Sturgeon Bay Utilities worked for several years to change their
buyback rate to reflect the historical cost of energy at the local MISO pricing node. This request
was approved earlier this year. Sturgeon Bay’s current rates change based on season and time
of day and range between 2.49 cents and 8.76 cents per kWh.
Great Lakes Utilities will be filing and omnibus request to the PSC for interested members to
update their buyback rate calculation. While the calculation will be a little more complex to
explain to customers, this filing will make our rate consistent with other GLU members and be
an accepted methodology from the PSC.
We request you authorize Great Lakes Utilities to submit the filing to amend Wisconsin Rapids
WWLC’s parallel generation tariffs on the utility’s behalf.
Jeff Kuhn
Jeff Kuhn
Chief Financial Officer
4.1
Wisconsin Rapids Water Works & Lighting Commission
September 2026
Prepared By: Sean T. Wall, MEUW Regional Safety Manager
SAFETY REPORT
ACCOMPLISHMENTS
1. Training
a. Fall Protection safety training and equipment inspections (Water and Electric) 9/9
b. Confined Space Entry hands on training (Water) 9/15
2. Audits / Inspections
a. No inspections in September
3. Compliance/Risk Management
a. Attended Commission meeting
4. Safety incident(s) / updates
a. 3 incidents reported in September, 9 incidents total in 2026
i. Property Damage report for door damage while transporting with the forklift
ii. Vehicle Damage report for Excavator thumb malfunction
iii. Property Damage report for hot water heater wired incorrectly
b. All incidents above were properly reported and addressed. Good to have on file.
c. Conducted meeting to further discuss previous month incident with Electric employee to get more
details and discuss reporting
GOALS AND OBJECTIVES
1. Training
a. Emergency Action Plan & Fire Extinguisher hands on safety training 10/14
2. Audits/Inspections
a. Field inspections to still take place as time / weather allows.\
b. Facility inspection to take place in Q4 (Nov / Dec)
3. Compliance/Risk Management
a. Attend Commission meeting
b. Follow up on all incidents
c. Take Utility group picture 10/2 in front of new building remodel
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399, Wisconsin Rapids, WI 54495-0399 (715) 423-6300
Line Superintendent’s Report
September 2026
Work Performed
During September the Electric Department processed work orders, electric service
orders, and 93 trouble slips.
Other Projects
• Continued tree trimming
• Continued pole replacements
• Continued 2026 URD conversion
• Continued Jackson St project
After Hours Calls
In September there were 8 after-hour call-ins.
The call for “other” was for a Charter line down.
Respectfully submitted,
Josh Elliott
Electric Line Superintendent
0
1
2
3
4
ANIMAL
RELATED
CUSTOMER
PROBLEM
OTHER TREE RELATED UNKNOWN
September 2026 call-ins
Total
4.3
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399, Wisconsin Rapids, WI 54495-0399 (715) 423-6300
PROJECT ELECTRICAL ENGINEER’S REPORT
September 2026
RTAC Programming
I have been steadily working on our RTAC HMI screens for the pas t month. This has
included the following:
- Completing the connection between the RTAC and every PLC
- Translating the digital tags from each PLC so that the RTAC can understand them
- Creating aliases for every tag in the RTAC so that they can be easily understood
without needing a key
- Lobby water and electric screens are working but will stop working in the lobby
whenever I make changes to the RTAC. I am currently trying to find a way to
mitigate this.
- I am 90% done with the water overview SCADA screen. All digital and analog
values display correctly. I am still working on getting flow animations to display the
way I want them to.
My next step after completing the water overview page is to start working on backwash,
reclaim, and filter controls. This will require more tag setup and will be tricky since I have
been doing all of this without the use of the main SCADA PLC where most of this
automation programming currently takes place.
Distribution Transformer Deliveries Update
We have now received 80 of 92 transformers for 2026.
Yet To Receive:
• 1 @ 10KVA 120/240 POLE
• 1 @ 50KVA 240/480 POLE
• 3 @ 75KVA 120/240 POLE
• 3 @ 100KVA 120/240 POLE
• 3 @ 100KVA 277/480 POLE
• 1 @ 100KVA 120/240 PAD
Tyler Sneen
Project Electrical Engineer
4.4
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399, Wisconsin Rapids, WI 54495-0399 (715) 423-6300
WATER DEPARTMENT OPERATIONS REPORT
September 2026
WATER PROJECTS
During September, the water department worked on the following projects.
• The water department began the 2nd St N reconstruction project located between
Spring St and Pleasant View Dr.
• The water department assisted the Wastewater Department with replacing a sanitary
lateral located at 271 19th Ave S.
• A water break occurred at 473 Sparks Ave. This 6” CI (Cast Iron) water main was
repaired and placed back into service.
• The water department worked alongside Williams Plumbing on replacing lead water
services at 301 13th St S and 920 9th St S.
TROUBLE CALLS
The water meter crew responded to 34 trouble calls/service material inspections and 7
residential cross connection inspections.
WATER DEPTHS AT WELLHEAD MONITORING SITES FOR THE LAST 5 YEARS
The readings given below were taken during the last week of September of the year.
26.75
34.95
16.55
15.70 15.70 13.83 15.10 15.10
20.60
0
5
10
15
20
25
30
35
40
2022 2023 2024 2025 2026
Municipal Well Water Depth (ft) Below Grade
Collector 1 Collector 2 Collector 3 Collector 4 Well 5
4.4
PUMPING TOTALS AT EACH MUNICIPAL WELL FOR THE LAST 3 YEARS
PUMPING TOTALS FOR ENTIRE WATER SYSTEM FOR THE LAST 3 YEARS
Sincerely,
Adam Breunig
Water Superintendent
0
5
10
15
20
25
30
35
2024 2025 2026
Million of Gallons Pumped Per Wellhead
Collector 1 Collector 2 Collector 3 Collector 4 Well 5
65
66
66
67
67
68
68
69
69
70
70
71
2024 2025 2026
Million of Gallons Pumped This Month
4.5
Water Works and Lighting Commission
221 16th St. So. P.O. Box 399 Wisconsin Rapids, WI 54495-0399 715/423-6300
INFORMATION SYSTEMS ADMINISTRATOR’S REPORT
September 2026
APPA CAP Program
We participated in the APPA’s first ever Cybersecurity Accelerator Program (CAP)
assessment this year. I am happy to say that we have achieved the second highest
designation, which is Platinum-Medium in our first assessment. We will use this
assessment as a guide to make changes for the better in our cybersecurity program. This
being the first year for this program, they do not have a plaque or certificate like they do
for their RP3 program.
Fill Station
We have received the camera and require a special SD card for recording video locally.
Due to chip shortages the SD cards required for these cameras are not available. The SD
cards are currently 6 months out for delivery. We are working with the vendor to find
another solution.
Cellular Issues
We have migrated all AMI meter collectors to our AT&T FirstNet account. We are currently
testing one of the field tablets to make sure everything works as it should on the FirstNet
network.
4.5
Projects
1. SCADA Network Updates
2. Outage Management
3. Cloud Migration
4. SCADA Switch Upgrades
5. Cybersecurity
Sincerely,
Matt Stormoen
Information Systems Administrator
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399 Wisconsin Rapids, WI 54495-0399 (715) 423-6300
4.6
Key Accounts Manager/Energy Efficiency Specialist Report
September 2026
High School Substation
Owen and I met with the Wisconsin Rapids Public Schools (WRPS)
Superintendent to discuss the possibility of acquiring approximately .25 acres of
property for our new substation building. The preliminary footprint drafted by
Forester Engineering was smaller than the final detailed diagram. The WRPS
Superintendent was optimistic that the WRPS board members would allow
WW&LC to attain more property to continue with the High School Substation
project. Owen is waiting for approval from the Public Service Commission and
the exact sizing of the switchgear to determine the final dimensions of the
building footprint. When this process is complete, we will present the information
to the WRPS Superintendent for school board approval of the property
acquisition.
Marianin Cold Storage
All load profile information was monitored and reviewed to make sure the
operation cooled down their storage buildings properly prior to the cranberry
season. I reached out to the facility Manager to discuss the time periods and
freezing times to assure them that the freezing process was performed during
off-peak hours to eliminate large demand charges. Further discussions are
pending on a return call back from the Facility Manager.
WW&LC Bookmark Contest
This year we decided to bring back our annual Bookmark Contest. The contest
was sent to private and public-school educators to disperse to 6th and 7th
graders. Students put their artistic abilities in a creative design to represent
conserving energy or water representing its importance to save energy or water.
Four bookmark designs were selected and displayed in our new lobby area over
the week of Public Power Week and grand opening of our new lobby.
Bookmarks will be printed for giveaways, and the winners will be highlighted in
our next WW&LC newsletter and on our social media platforms.
Rate Increase/Decrease Letter
This past month, three commercial customers have been sent a rate change
letter. The organizations were contacted due to a change in their electric usage
and offer them the opportunity to discuss how this may affect their monthly
invoices moving forward. This also allows them, in some instances, to discuss the
option of a regular fixed, or time-of-day rate offering the most monthly electric
cost savings. All load analysis has been performed to discuss the best rate when
they call.
Respectfully,
Shawn Reimer
Key Accounts Manager
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399 Wisconsin Rapids, WI 54495-0399 (715) 423-6300
CUSTOMER SUPPORT SUPERVISOR’S REPORT
SEPTEMBER 2026
COLLECTIONS
September marked the final full month of electric disconnections before the Public Service Commission (PSC)
moratorium begins on October 15. We sent 1,240 phone calls and 429 follow-up text messages to notify
customers of an upcoming disconnection. This was followed by 201 disconnections and 204 reconnections.
Our past due percentages have consistently improved since May, however past due percentages do include
budget customers in good standing, pending energy assistant payments, existing properties that are currently
disconnected, and customers with payment arrangements.
We will continue electric disconnections through October 15th when the PSC Reconnection Program begins.
All customers who have been disconnected for non-payment will be notified to verify vacancy and possible
reconnection. At the end of September, 23 locations remained disconnected for non-payment.
ALL PROVIDERS – Active Accounts
May, 2026 June, 2026 July, 2026 August, 2026 September, 2026
30 day 216,615 7.69% 149,636 4.95% 236,369 7.02% 234,781 6.40% 225,381 6.53%
60 day 44,085 1.57% 41,297 1.37% 25,152 0.75% 24,425 0.67% 23,402 0.68%
90 day 44,020 1.56% 30,945 1.02% 23,954 0.71% 18,587 0.51% 16,349 0.47%
Current 2,510,486 89.18% 2,799,992 92.66% 3,082,740 91.52% 3,388,165 92.42% 3,187,941 92.32%
Active 2,815,206 3,021,870 3,368,215 3,665,958 3,453,073
Inactive 48,144 54,934 51,641 50,976 48,728
Total AR 2,863,350 3,076,804 3,419,856 3,716,934 3,501,801
Payment Arrangements
Forty-seven payment arrangements were made in September this year, compared to just 19 in September 2025.
To enter a payment arrangement, a customer is required to pay 50% of their past due balance.
Commercial Accounts
In September, 33 commercial properties were notified of disconnection. One account remains disconnected to
date.
Tax Refund Interception Program (TRIP) and State Debt Collection (SDC)
We received $3,126 through SDC in September for a 2025 total of $73,677.
OFFICE INFORMATION
Office staff processed one new electric service and three new water services in September. In addition,
235 electric and 136 water move orders were processed. Forty-seven of these orders were received
electronically.
1,175 payments were processed in the lobby.
70 welcome letters were sent to new customers in September.
Office staff answered 1,426 phone calls in September.
4.7
OFFICE INFORMATION CONT
Jeff Kuhn, Holly Tucker and I attended the MEUW Accounting and Customer Service Seminar on
September 23rd.
With the construction complete, office staff transitioned back to the utility.
The upcoming Fall/Winter Currents and Waves Newsletter is attached.
OFFICE PAYMENTS
We received 15,811 payments in September with 72 percent received via one of our electronic payment options.
SOCIAL MEDIA / WEBSITE
Four messages were posted on social media in September.
Our website generated over 7,000 page views.
Respectfully submitted,
Lynn Schroer
Customer Support Supervisor
Fall/Winter 2026
Currents &
Waves
Funding Available for Private Lead Service Replacement
Wisconsin Rapids Water Works and Lighting Commission (WWLC) is pleased to announce a
generous grant donation from the Legacy Foundation to help eligible homeowners replace private-
side lead service lines (LSLs).
WWLC has partnered with Van Rite Plumbing to complete the lead service line replacements, with
work scheduled to begin in 2027.
Who May Qualify?
Grant eligibility and funding levels will be based on household size and total household income. This
funding will help eligible homeowners reduce the cost of replacing lead service lines on their property.
Over the past several years, WWLC has been working to identify and document the material of every
private water service in the city. Approximately 300 private services remain unidentified and may
contain lead.
If you received a letter or phone call from WWLC asking you to verify your water service and have not
yet responded, please contact WWLC at 715-422-9045 to schedule an appointment. Verification is a
quick, five-minute process, and completing it is essential in determining eligibility for available grant
funding.
What Happens Next?
This winter, WWLC will contact homeowners whose private water service is known to contain lead
and will:
• Verify the homeowner’s potential funding level
• Explain the replacement process
• Answer all questions
• Schedule appointments when applicable
WWLC’s goal is to replace all private side lead service lines in the city before the 2037 deadline.
Questions or need to verify your service?
Contact Wisconsin Rapids Water Works and Lighting Commission at 715-422-9045.
With the upcoming Holiday Season
approaching, we would like to wish our
customers a happy celebration. If you
are looking for a last-minute holiday gift
idea, consider a gift certificate from
Water Works and Lighting Commission.
We can mail your certificate to our
customer indicating the monetary
amount of your gift. Call or stop in our
office for details.
Water Works &
Lighting Commission
221 16th St. S., P.O. Box 399
Wisconsin Rapids, WI 54495-0399
Office - 715.423.6300
Service Department - 715-423-6310
wrwwlc.com
The Wisconsin Section of the American Water
Works Association recently held its 40th Annual Drinking
Water Taste Test competition in Madison, in conjunction
with their annual conference.
Water Works and Lighting Commission competed
against groundwater and surface water public utilities
and took 1st Place for the Best-Tasting Tap Water in
Wisconsin.
The utility will now submit a sample at the Annual
AWWA conference in San Diego on June 13-16, 2027, to
represent Wisconsin.
We are very proud of the effort our Water
Department puts forth, starting with our Filter Plant
Operators and finishing with our Distribution Operators
who make sure the water reaches the customer.
The utility strives every day to make sure the City
of Wisconsin Rapids receives the best water quality
possible.
OUR EASIEST PAYMENT OPTION
Automatic Bill Payment
Have you ever forgotten to pay your bill by the due date? Sign up for
our easy and safe automatic bill payment option and you will never
have to worry about remembering a due date again! By setting up
recurring payment from your checking or savings account, you can be
certain your bill is always paid on time. Sign up online at
https://www.wrwwlc.com/form/ach.php, stop in or office, or just call
us at 715-423-6300 and we will mail you a form.
If you have a hydrant near your property, consider
adopting it for the winter and clear the snow
around it. Heavy snow makes finding and
accessing a fire hydrant very difficult for firefighters.
When there is an emergency, every second counts!
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399 Wisconsin Rapids, WI 54495-0399 (715) 423-6300
4.8
Director of Engineering and Metering’s Report
September 2026
Good News and Gratitude
Job well done to all involved in making the Lobby Remodel project come to life. Great teamwork all
around from the electric work being performed in house by the Electric Metering department, lobby
display screens built by Tyler and the IT department, retaining walls and streetlights being installed
jointly by the Electric and Water crews.
Noteworthy Outages
One momentary outages analyzed in September.
1. West Rural Mid-Line Recloser 106S momentary at 09:41:26 on 09/20/2026
a. Overcurrent and interrupting devices operated as intended
b. No direct cause identified
West Wisconsin Rapids Wholesale Power Meter Upgrade
Issued prints for construction for the upgrade of the two Wholesale Power Meters at West Wisconsin
Rapids Substation. In addition to Great Lakes Utilities (GLU) reading these new meters for Wholesale
Power, Alliant Energy (Alliant) and Wisconsin Public Service (WPS) will also read these meters as a
Local Balancing Authority (LBA) tie. The Electric Metering department is doing the construction for this
project in house. A joint checkout of the new meters is scheduled with Alliant/GLU/WPS for Tuesday,
October 13th.
High School Substation Upgrade
Continued working with Forester Engineering on site layout and physical design package for the
switchgear. Forester Engineering to continue working on bid documents to have switchgear pack age
ready to send out for bids in mid October with bids due back on December 1st. The Certificate of
Authority for this project is scheduled to be deliberated during the Thursday, October 8th Public Service
Commission’s 10:30 AM meeting.
RP3 Application
Final submittal for RP3 application completed on September 17 th. American Public Power Association
will review applications during the month of October. Follow-up questions for clarifications will be sent
out after review in November with final reviews completed and scores awarded before the end of the
year in December.
Owen Yenter, P.E.
Director of Engineering and Metering
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399 Wisconsin Rapids, WI 54495-0399 (715) 423-6300
4.9
Chief Financial Officer Report
September 2026
Financial Reports
Included in your packet are August’s interim financial statements. Both utilities reported strong
results for the month. The electric utility increased operating income by $398,268 in the current
month, bringing 2026 operating income to $1,436,770. The water utility recorded August net
income of $312,816, bringing its year-to-date operating income to $466,653.
Purchased power costs remain higher than in previous years. Our power supply costs include
energy, demand, power cost adjustment (PCA), and transmission charges. As shown below, the
wholesale purchased power cost per kWh has increased over the past five years.
Water utility sales are up 3.5%, with increases across all customer classes except industrial sales,
which are 4% lower. The increase in rent from water property relates to leases with cellular
providers on the water towers. Before last year, rent payments were received consistently, but one
company has experienced recurring payment issues. Beginning in late 2025, we started issuing
invoices and accruing the related revenue rather than recognizing revenue when the payment was
received.
September generated positive cash flow of $410,327 for the month, bringing year-to-date cash flow
to a positive $344,657. This result is comparable to the positive year-to-date cash flow of $348,525
reported for the same period in 2025.
7.3
7.81 7.81
8.09
8.7
6.5
7
7.5
8
8.5
9
2022 2023 2024 2025 2026 (through
Aug)
Purchased Power Costs in Cents per kWh
WPUI Programming
On September 22, WPUI presented the online program “Grid Under Pressure: Deep Dive –
Affordability, Nuclear and Environmental Nexus.” Speakers discussed steps utilities are taking to
protect customers from cost increases associated with rapid demand growth from data centers, as
well as the potential for growth in nuclear generation. The nuclear speakers noted that when a data
center project is paired with a proposed nuclear power plant, the data center has become the more
contentious part of the plan.
2027 Budget
The approved budget was sent to the City on September 28, ahead of the October 1 ordinance
deadline. We have not yet heard back on a date to present to the Council, but will be ready to
discuss the budget when a date is set.
Respectively submitted,
Jeff Kuhn
Jeff Kuhn
Chief Financial Officer
Cash Receipts:
Utility Receipts, Net of Returns 4,603,461$ 36,468,287$ 34,780,908$
Interest and Dividends 168$ 3,186$ 2,971$
Transfer from Investments 4,276,553$ 2,385,157$
ATC Dividend Payment 590,476$ 562,341$
Total Cash Receipts 4,603,629$ 41,338,502$ 37,731,377$
Disbursements
AP Payments (1,191,981)$ (15,655,329)$ (13,990,102)$
GLU Power Bill (2,464,135)$ (17,473,262)$ (16,309,327)$
Transfer to Investments (250,000)$ (2,890,000)$ (2,204,963)$
ATC - Voluntary Capital Call (1,085,899)$ (894,097)$
Sales Tax Payment (47,409)$ (392,064)$ (550,626)$
Payroll (234,110)$ (3,453,704)$ (3,389,319)$
Service Fees (5,667)$ (43,587)$ (44,419)$
Total Disbursements (4,193,303)$ (40,993,846)$ (37,382,851)$
Net Cash Flow 410,327$ 344,657$ 348,525$
Prior Year to Date
Wisconsin Rapids Water Works and Lighting Commission
Cash Flow Summary
for Month Ending September 30, 2026
Current Month Year to Date
Electric Water Total Electric Water Total Electric Water Total
Charges for Services 22,296,716$ 3,026,805$ 25,323,522$ 21,186,036$ 2,925,304$ 24,111,341$ 5.2% 3.5% 5.0%
Other Operating Revenues 382,540 1,322,132 1,704,672 382,695 1,335,350 1,718,044 (0.0%) (1.0%) (0.8%)
Total Operating Revenues 22,679,256$ 4,348,937$ 27,028,193$ 21,568,731$ 4,260,654$ 25,829,385$ 5.1% 2.1% 4.6%
Purchased Power 15,642,883$ -$ 15,642,883$ 14,517,115$ -$ 14,517,115$ 7.8% 7.8%
Other Operating Expenses 2,912,176 2,480,606 5,392,781 2,875,365 2,351,436 5,226,801 1.3% 5.5% 3.2%
Depreciation Expense 1,702,428 699,679 2,402,107 1,650,219 680,114 2,330,333 3.2% 2.9% 3.1%
Taxes Expense 986,000 702,000 1,688,000 952,000 640,000 1,592,000 3.6% 9.7% 6.0%
Total Operating Expenses 21,243,487$ 3,882,284$ 25,125,771$ 19,994,699$ 3,671,551$ 23,666,250$ 6.2% 5.7% 6.2%
Operating Income (Loss) 1,435,769$ 466,653$ 1,902,422$ 1,574,032$ 589,104$ 2,163,135$ (8.8%) (20.8%) (12.1%)
Non-Operating Income 1,069,586 442,167 1,511,752 890,441 304,850 1,195,292 20.1% 45.0% 26.5%
Interest Charges 230,863 - 230,863 103,893 - 103,893 122.2% 122.2%
Other Non-operating Exp 247,799 75,052 322,851 233,822 71,201 305,023 6.0% 5.4% 5.8%
Net Income (Loss) 2,026,692$ 833,767$ 2,860,460$ 2,126,759$ 822,752$ 2,949,511$ (4.7%) 1.3% (3.0%)
Wisconsin Rapids Water Works and Lighting Commission
Combined Utility Income Statement
Year to date through August 2026
Current Year to Date Prior Year to Date % Increase (Decrease)
Current Budget
Year To Date
Balance
Prior Year to
Date Balance
2 Years ago
Year to Date
Balance
Current Year
Remaining
Budget
Sales of Electricity
Residential $12,414,300 $8,703,082 $8,581,017 $8,160,617 $3,711,218
General Service 4,852,400 3,181,315 3,269,942 3,128,080 1,671,085
Small Power- (demand up to 400 kW) 5,372,200 3,628,791 3,594,239 3,476,116 1,743,409
Large Power/Industrial - (demand over 400 kW) 6,382,200 4,031,008 4,116,812 4,067,772 2,351,192
Lighting 681,000 448,204 451,325 461,809 232,796
PCAC 2,039,700 2,304,316 1,172,701 673,453 (264,616)
Total Sales of Electricity $31,741,800 $22,296,716 $21,186,036 $19,967,847 $9,445,084
Other Operating Revenues
Reconnect Fees $29,000 $22,600 $19,655 $21,135 $6,400
Rent from Electric Property 306,500 299,834 300,225 291,689 6,666
Late Fees 98,000 57,502 59,600 55,296 40,498
Other Electric Revenues 1,500 2,604 3,214 3,069 (1,104)
Total Other Operating Revenues $435,000 $382,540 $382,695 $371,189 $52,460
Total Operating Revenues $32,176,800 $22,679,256 $21,568,731 $20,339,036 $9,497,544
Operating Expenses
Purchased Power Expense $22,028,847 $15,642,883 $14,517,115 $13,545,631 $6,385,964
Maintenance & Distribution Expense 1,934,000 1,487,245 1,391,039 1,168,683 446,755
Customer Accounts Expense 848,900 594,813 596,650 555,977 254,087
Advertising Expense 16,500 - 8,964 3,255 16,500
Administrative And General Expense 1,420,200 830,118 878,711 796,090 590,082
Depreciation Expense 2,531,100 1,702,428 1,650,219 1,572,791 828,672
Taxes Expense 1,442,100 986,000 952,000 1,088,000 456,100
Total Operating Expenses $30,221,647 $21,243,487 $19,994,699 $18,730,426 $8,978,160
Operating Income $1,955,153 $1,435,769 $1,574,032 $1,608,610 $519,384
Non-Operating Income and Expenses
Merchandise and Jobbing $50,000 $11,163 $23,130 $64,322 $38,837
Interest and Dividend Income 1,456,200 871,132 761,981 700,918 585,068
Miscellaneous Non-Operating Income 145,000 187,290 105,331 106,872 (42,290)
Total Non-Operating Income $1,651,200 $1,069,586 $890,441 $872,112 $581,614
Interest Charges $143,300 $230,863 $103,893 $110,388 ($87,563)
Other Income Deductions $390,000 $247,799 $233,822 $306,545 $142,201
Net Income (Loss) $3,073,053 $2,026,692 $2,126,759 $2,063,789 $1,046,361
YTD
Electric Income Statement
For Period Ending August 31, 2026
Current Budget
Year To Date
Balance
Prior Year to
Date Balance
2 Years ago
Year to Date
Balance
Current Year
Remaining
Budget
Metered Sales of Water
Residential Sales $2,087,400 $1,408,136 $1,388,060 $1,328,525 $679,264
Commercial Sales 800,200 549,831 540,639 496,255 250,369
Industrial Sales 684,200 439,082 458,795 431,993 245,118
Irrigation Sales 356,700 310,762 242,001 187,435 45,938
Multi-Family Residential Sales 237,000 164,942 156,616 153,105 72,058
Public Authority Sales 208,800 154,053 139,194 132,064 54,747
Total Sales of Water $4,374,300 $3,026,805 $2,925,304 $2,729,377 $1,347,495
Other Operating Revenues
Private Fire Protection
$57,300 $40,316 $38,064 $38,206 $16,984
Public Fire Protection 1,430,619 962,128 965,868 934,753 468,491
Forfeited Discounts 36,000 26,423 24,476 25,470 9,577
Miscellaneous Service Revenues 2,000 1,470 1,785 1,610 530
Rent From Water Property 89,000 68,754 50,980 63,055 20,246
Other Water Revenues 47,000 223,041 254,176 257,625 (176,041)
Total Other Operating Revenues $1,661,919 $1,322,132 $1,335,350 $1,320,719 $339,787
Total Operating Revenues $6,036,219 $4,348,937 $4,260,654 $4,050,096 $1,687,282
Operating Expenses
Source of Supply Expense
$376,000 $390,313 $143,505 $41,914 ($14,313)
Pumping Expense 305,200 249,217 215,710 208,847 55,983
Water Treatment Expense 756,800 501,142 535,980 503,001 255,658
Water Transmission/Distribution Expense 847,200 463,787 513,068 433,437 383,413
Customer Accounts Expense 196,800 227,795 233,703 212,485 (30,995)
Sales Expense 100 - 100 23 100
Administrative And General Expense 1,055,800 648,352 709,370 675,548 407,448
Depreciation Expense 945,600 699,679 680,114 649,106 245,921
Taxes Expense 828,100 702,000 640,000 680,000 126,100
Total Operating Expenses $5,311,600 $3,882,284 $3,671,551 $3,404,360 $1,429,316
Operating Income (Loss) $724,619 $466,653 $589,104 $645,736 $257,966
Merchandise and Jobbing $2,000 $23,864 ($20,748) ($1,029) ($21,864)
Interest and Dividend Income 350,800 291,722 230,158 206,751 59,078
Miscellaneous Non-operating Income 109,700 126,581 95,441 68,814 (16,881)
Total Non-Operating Income $462,500 $442,167 $304,850 $274,535 20,333
Other Income Deductions $108,000 $75,052 $71,201 $102,173 $32,948
Total Net Income $1,079,119 $833,767 $822,752 $818,098 $245,352
YTD
Water Income Statement
For Period Ending August 31, 2026
Period Ending August 31, 2026 Period Ending August 31, 2025
Electric Utility Water Utility
Combined
Utilities Electric Utility Water Utility
Combined
Utilities
ASSETS
Utility Plant
Utility Plant in Service $77,011,173 $52,530,932 $129,542,105 $74,765,921 $51,120,173 $125,886,094
Utility Plant in Service - Common 8,888,276 3,107,409 11,995,684 8,392,014 2,978,331 11,370,345
Property Held for Future Use 500 104,255 104,755 500 104,255 104,755
Construction Work in Progress 3,752,264 1,157,347 4,909,612 3,864,769 854,311 4,719,080
Total Utility Plant $89,652,213 $56,899,943 $146,552,156 $87,023,203 $55,057,070 $142,080,274
Less: Accumulated Depreciation
Accumulated Depreciation ($35,800,899) ($22,504,708) ($58,305,607) ($33,906,720) ($21,434,850) ($55,341,570)
Accumulated Depreciation - Common (7,205,662) (2,384,126) (9,589,788) (7,015,071) (2,223,456) (9,238,527)
Total Accumulated Depreciation ($43,006,561) ($24,888,834) ($67,895,395) ($40,921,791) ($23,658,306) ($64,580,097)
Net Utility Plant $46,645,653 $32,011,109 $78,656,761 $46,101,412 $31,398,765 $77,500,177
Current and Accrued Assets
Cash $1,294,834 $1,098,303 $2,393,138 $592,882 $1,145,812 $1,738,694
Working Funds 690 - 690 690 - 690
Rate Stabilization Deposit 264,987 - 264,987 781,742 - 781,742
Temporary Cash Investments 411,901 351,098 762,999 560,341 447,022 1,007,363
Customer Accounts Receivable 4,256,491 823,178 5,079,669 4,176,259 778,725 4,954,984
Other Accounts Receivable 177,373 465,327 642,700 197,578 414,687 612,266
Receivable From Municipality 42,069 53,051 95,121 23,470 38,745 62,215
Notes Receivable - - - 500,000 - 500,000
Sewer Fee For Collections - 324,781 324,781 - 340,330 340,330
Plant Materials & Supplies 2,391,814 658,838 3,050,653 2,112,727 611,803 2,724,530
Stores Expense 89,715 (115,534) (25,819) 7,397 (34,040) (26,643)
Prepayments 184,639 35,876 220,515 177,533 35,262 212,794
Interest Receivable - - - - - -
Total Current and Accrued Assets $9,114,514 $3,694,919 $12,809,433 $9,130,619 $3,778,345 $12,908,965
Other Investments
Depreciation Fund $5,353,027 $8,779,786 $14,132,813 $6,094,141 $7,848,212 $13,942,353
Other Investments 12,380,869 1,004,628 13,385,497 11,014,215 - 11,014,215
Other Special Funds 75 3,280 3,355 318,877 3,280 322,157
Total Other Investments $17,733,971 $9,787,695 $27,521,665 $17,427,233 $7,851,492 $25,278,724
Deferred outflows of Resources
Unamortized Debt Disc & Expense $0 $0 $0 $243,016 $0 $243,016
Preliminary Survey & Investigation Charges 2,808 - 2,808 2,808 - 2,808
Clearing Accounts 22,301 18,184 40,485 (8,810) (21,521) (30,331)
Deferred Outflows Related To Pension 1,240,347 734,897 1,975,244 1,706,978 1,060,210 2,767,188
Misc Deferred Debits 199,220 130,897 330,118 247,049 168,075 415,124
Total Deferred Outflows of Resources $1,464,676 $883,979 $2,348,654 $2,191,041 $1,206,764 $3,397,805
Total Assets and Deferred Outflows $74,958,813 $46,377,702 $121,336,515 $74,850,305 $44,235,366 $119,085,671
Wis Rapids WWLC Balance Sheet
For Period Ending August 31, 2026
Period Ending August 31, 2026 Period Ending August 31, 2025
Electric Utility Water Utility
Combined
Utilities Electric Utility Water Utility
Combined
Utilities
Wis Rapids WWLC Balance Sheet
For Period Ending August 31, 2026
LIABILITIES
Current and Accrued Liabilities
Accounts Payable $3,354,408 $0 $3,354,408 $3,264,346 $0 $3,264,346
Payables To Municipality - - - - - -
City Utilities Billed by Utility Payable to City - - - - (290) (290)
Customer Deposits 644,022 - 644,022 646,325 - 646,325
Taxes Accrued 551,571 711,642 1,263,213 545,650 648,050 1,193,700
Interest Accrued 68,823 - 68,823 60,129 - 60,129
Tax Collections Payable 99,376 - 99,376 255,756 - 255,756
Misc Current And Accrued Liabilities 1,908,603 914,158 2,822,760 1,802,578 883,298 2,685,876
Total Current and Accrued Liabilities $6,626,803 $1,625,799 $8,252,602 $6,574,783 $1,531,058 $8,105,841
Long Term Debt
Long Term Debt - Bonds $0 $0 $0 $2,360,000 $0 $2,360,000
PROPRIETARY CAPITAL
Capital Paid In By Municipality $1,030,967 $798,819 $1,829,787 $1,030,967 $798,819 $1,829,787
Retained Earnings 65,915,275 42,181,455 108,096,730 62,539,515 40,824,613 103,364,128
Total Proprietary Capital $66,946,243 $42,980,274 $109,926,516 $63,570,483 $41,623,432 $105,193,914
Deferred Inflows of Resources
Customer Advance For Construction $63,732 $0 $63,732 $29,350 $0 $29,350
Rate Stabilization & Public Benefits Liabilities 302,879 - 302,879 819,326 - 819,326
Unamortized Premium On Debt 0 - 0 23,140 - 23,140
Other Deferred Credits 1,019,157 1,771,628 2,790,785 1,473,224 1,080,876 2,554,100
Total Deferred Inflows of Resources $1,385,768 $1,771,628 $3,157,396 $2,345,040 $1,080,876 $3,425,916
Total Liabilities, Equity and Def Inflows $74,958,813 $46,377,702 $121,336,515 $74,850,305 $44,235,366 $119,085,671
Wisconsin Rapids Water Works and Lighting Commission
Monthly Electric Purchases
2023-2026
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Electric Purchases - Demand by Month (kW)
2023
2024
2025
2026
-
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
35,000,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Electric Purchases by Month (kWh)
2023
2024
2025
2026
INSTITUTION FACE VALUE
FACE VALUE
& ACCRUED
INT
RATE/
YIELD
MATURITY
DATE
DATE
ACQUIRED TYPE
Local Government Investment Pool (LGIP) 952,817.42 952,817.42 3.810%
Prevail Bank 5,125,816.18 5,125,816.18 4.000%
Ehlers Investments
FIRST FOUNDATION BANK IRVINE (CA) 150,000.00 151,484.59 4.250% 10/7/2026 6/26/2025 CD
FIRST CENTRAL CREDIT UNION WACO TEXAS 145,000.00 145,407.59 5.400% 10/13/2026 10/11/2023 CD
ALLIANT CREDIT UNION CHICAGO 245,000.00 245,375.89 5.600% 11/20/2026 11/20/2023 CD
FARMERS TR & SVNGS BANK (IA) 241,000.00 248,471.00 3.866% 11/24/2026 11/24/2025 CD
HUGHES FEDERAL CREDIT UNION 248,000.00 248,037.37 5.500% 11/30/2026 11/29/2023 CD
NOBLE FEDERAL CREDIT UNION 249,000.00 249,674.01 3.800% 12/4/2026 11/25/2025 CD
COVANTAGE CREDIT UNION 247,000.00 247,000.00 3.850% 12/30/2026 12/17/2025 CD
FULLERTON (CA) TAXABLE REFERENDUM BONDS 110,000.00 110,997.08 4.950% * 4/1/2027 2/1/2024 MUNI BOND
NEVADA HOUSING DIVISION REV BONDS 150,000.00 153,635.94 4.875% 4/1/2027 3/12/2024 MUNI BOND
LOS ANGELES (CA) SCHOOL DISTRICT GO BONDS 75,000.00 76,108.98 4.950% * 5/1/2027 2/26/2024 MUNI BOND
WEST VIRGINIA STATE HOUSING DEV BONDS 350,000.00 357,228.57 4.990% 5/1/2027 6/18/2024 MUNI BOND
LIGHTHOUSE FEDERAL CREDIT UNION 100,000.00 100,256.16 4.250% 6/30/2027 6/25/2026 CD
ROCKLAND FEDERAL CREDIT UNION 200,000.00 200,000.00 4.300% 6/30/2027 6/25/2026 CD
MASSACHUSETTS ST SPL OBLIG REV BONDS 145,000.00 146,111.67 4.322% * 7/15/2027 3/21/2025 MUNI BOND
FISHERS (IN) ECONOMIC DEV BONDS 175,000.00 176,382.40 4.820% 8/1/2027 3/27/2024 MUNI BOND
IOWA TAXABLE STATE REVOLVING GREEN BONDS 250,000.00 251,819.17 4.440% 8/1/2027 1/30/2025 MUNI BOND
TEXAS STATE TAXABLE GO REF BONDS 290,000.00 297,209.72 4.222% * 10/1/2027 12/12/2024 MUNI BOND
CLARK COUNTY (NV) TAXABLE GO BONDS 325,000.00 326,614.17 4.524% * 11/1/2027 12/27/2024 MUNI BOND
USF FEDERAL CREDIT UNION TAMPA 249,000.00 249,741.88 3.750% 11/3/2027 10/31/2025 CD
PITNEY BOWES BANK (UT) 150,000.00 152,027.88 3.550% 11/15/2027 12/1/2025 CD
FIRST BANK CHICAGO 151,000.00 152,906.32 3.600% 11/26/2027 12/1/2025 CD
MICHIGAN HOUSING AUTHORITY REV BONDS 105,000.00 106,335.58 3.848% * 12/1/2027 10/2/2025 MUNI BOND
GULF SHORES (AL) GO TAXABLE BONDS 100,000.00 100,962.50 3.300% * 12/15/2027 3/28/2025 MUNI BOND
TEXAS STATE GO WATER ASSISTANCE BONDS 200,000.00 201,261.62 3.849% * 2/1/2028 10/10/2025 MUNI BOND
TOYOTA FINANCIAL SAVINGS BANK 245,000.00 249,644.93 4.000% 4/10/2028 4/10/2025 CD
FEDERAL HOME LOAN BANK 350,000.00 352,994.44 3.549% * 4/26/2028 11/28/2025 US GOVT
NEW YORK TAXABLE GO BONDS 260,000.00 263,222.92 3.750% * 6/1/2028 3/26/2025 MUNI BOND
FISHERS (IN) ECONOMIC DEV BONDS 185,000.00 186,464.43 4.830% 8/1/2028 3/27/2024 MUNI BOND
PENNSYLVANIA HOUSING AUTHORITY REV TAX BO 245,000.00 250,766.93 4.734% 10/1/2028 8/29/2024 MUNI BOND
SOUTH DAKOTA HOUSING AUTHORITY TAX BONDS 350,000.00 356,886.70 4.754% 11/1/2028 2/20/2025 MUNI BOND
LOUISIANA HOUSING AUTHORITY TAX BONDS 75,000.00 76,194.96 4.820% 12/1/2028 4/18/2024 MUNI BOND
MICHIGAN HOUSING AUTHORITY REV BONDS 300,000.00 254,113.76 4.978% 12/1/2028 3/27/2024 MUNI BOND
HENRY & WHITESIDE COUNTIES (IL) SCHOOL DIST 225,000.00 226,406.25 5.000% 2/1/2029 1/30/2025 MUNI BOND
CFG COMMUNITY BANK (MD) 249,000.00 249,440.01 4.300% 4/13/2029 4/15/2025 CD
US TREASURY 244,000.00 246,592.50 4.148% * 6/29/2029 6/3/2026 US GOVT
NORTH CAROLINA HOUSING AGENCY TAX BONDS 350,000.00 354,146.41 4.792% 7/1/2029 6/21/2024 MUNI BOND
SAN DIEGO SCHOOL DISTRICT GO TAX BONDS 100,000.00 100,980.24 3.965% 7/1/2029 9/19/2024 MUNI BOND
FEDERAL HOME LOAN BANK 270,000.00 271,678.95 4.214% * 11/27/2029 6/3/2026 US GOVT
US TREASURY 253,000.00 253,000.00 3.625% 4/30/2030 6/3/2026 US GOVT
US TREASURY 250,000.00 254,027.68 3.875% 4/30/2030 4/30/2025 US GOVT
FEDERAL HOME LOAN BANK 279,000.00 279,930.00 4.265% * 6/24/2030 6/3/2026 US GOVT
FEDERAL HOME LOAN BANK 281,000.00 281,216.37 4.300% * 9/9/2030 6/3/2026 US GOVT
GOLDMAN SACHS BANK 101,000.00 102,608.39 3.750% 10/28/2030 6/25/2026 CD
MORGAN STANLEY BANK 200,000.00 203,041.10 3.750% 11/5/2030 6/25/2026 CD
DREYFUS PREFERRED GOVT MM FUND 211,293.35 211,293.35 MM
DREYFUS PREFERRED TREASURY FUND 399,842.30 399,842.30 3.340% MM
10,119,542.71
TOTAL INVESTMENTS 16,151,769.25 16,198,176.31
ACCOUNT BALANCES POST-JOURNAL ENTRY
ELECTRIC BAL WATER BAL
DEPRECIATION FUND (x.1261) 5,444,083.63 8,866,028.32
LEAD SERVICE REPLACEMENT FUNDS (2.1262) 1,007,620.92
TAX ESCROW FUND (x.1361) 367,229.86 358,930.89
GENERAL FUND (x.1365) 116,002.80 38,279.89
UTILITY BALANCES BY DIVISION 5,927,316.29 10,270,860.02
TOTAL UTILITY INVESTMENTS 16,198,176.31
Wisconsin Rapids Water Works & Lighting Commission
9/30/2026
Investment Report
4.10
Water Works and Lighting Commission
221 16th Street S, P.O. Box 399, Wisconsin Rapids, WI 54495-0399 (715) 423-6300
GENERAL MANAGER’S REPORT
September, 2026
Lobby Reopening
The WW&LC Lobby reopened on September 28th. I would like to thank all of our
employees and contractors who helped make the project a success. A special thank
you goes out to our IT and Office Staff who provided a seamless transition while
handling all our customer service needs from a remote location.
GLU BTM Solar Project
The GLU BTM Solar Project Team continued to meet multiple times in September. One
Energy had their drone conduct a topography study on September 28th. This will be
used by their engineering department to complete the final layout design of the array.
Red Run has cleared and dragged the inner 30 acres of the site and will be planting the
winter wheat in the near future. Red Run will still have to chip and remove the brush
piles on the South and North ends of the project; they have until the end of the year to
complete this work. Marshfield continues to make progress on their 4 sites, as does
Clintonville. Shawano is looking into a different location since their original site is no
longer valid due to wetland issues and FFA approval.
GLU Marshfield Energy Center
Due to the rising costs of the turbine units, GLU is planning to scale down the size of the
project. By reducing the size of the project by half, GLU could still move forward with
this project and own about 50 MWs of capacity generation. This would allow GLU to
have a more diverse portfolio which will allow them to consider other projects or
purchase power agreements. Board approval for the project will need to take place
before the end of the year in order to keep the project on track for a 2030 startup.
.
GLU Annual Meeting
This is the last reminder of the Annual Joint GLU/UMMEG meeting which is scheduled
for October 20th at the Radison Hotel in La Crosse. Currently I have John Bergin, Rick
Merdan, and Jeff Penzkover scheduled to attend along with Owen, Jeff and me. The
agenda is as follows:
• 8am breakfast
• 9am Introduction
• 9:45am UMMEG and GLU Board Meetings
• 11am Strategic Planning Partnership Discussion
• Noon Lunch
• 1pm to 4pm Speakers
o NextEra – US Energy Market Outlook
o Nicolet National Bank – Banking Security
o LightShift Energy – Battery Storage
o MEUW – Election Race Overview
o Caterpillar
Todd Weiler, P.E.
General Manager