1
THE VILLAGE OF GAYS MILLS
Minutes of the regular meeting of the Village Board of Gays Mills held Monday, October 5, 2020,
which began at 6:00 p.m. in the Community Commerce Community Room.
Village President Harry Heisz called the meeting to order at 6:00 p.m. Roll call was taken with the
following present: Harry Heisz, Larry McCarn, Kevin Murray, Seamus Murray, Kim Pettit and Lee
Ruegg (by phone). Aaron Fortney was absent.
The board received verification that the agenda was posted in accordance with the open meeting law.
Under citizens and delegations Charley Preusser stated his concern regarding masks not being worn
by everyone present.
Swimming Pool Manager Kayla Fortney was present to report that pool income was not as much as
previous years due to no summer school programs participating because of COVID-19. Made a
recommendation to do more outreach to other areas regarding the pool season in 2021.
Under the Public Works report Jim Chellevold informed the board that he will be testing out the new
street sweeper with cleaning up leaves and if it works well will place an ad in the newspaper for
residents to rake leaves to curb. Public works plans on marking locations for new grills to be
installed and public spaces are being cleaned. Camping in Robb Park will continue until water
needs to be shut off. Participated in a public hearing regarding the wastewater treatment plant
permit renewal and variance. New sewer testing equipment has been purchased. Heisz informed the
board that Soldiers Grove has decided not to participate in a joint wastewater treatment plant.
Chellevold recommended the board begin looking for an engineering firm to start working with.
There was nothing new to report on the sewer facility plan.
Kitchen Co-Manager Jill Riggs was present and reported that setup and inspections have been
scheduled with three new kitchen clients. Some website work has been completed but there is still
more to be done. Still planning on reviewing kitchen fees and rewriting the facility use agreement.
Questioned John Lenz’s participation in kitchen co-management duties.
Kevin Murray reported for the Tree Advisory Board and asked if the public works crew was able to
complete the felling of trees that need to come down in order to fulfill the grant requirements.
It was discussed and agreed that public works would complete with a rented lift. It was asked if the
public works could commit to future tree projects such as pruning and tree removal. Director of
Public Works Jim Chellevold stated that the public works crew would help if able but unable to
commit to specific projects or timetable. It was asked for the Village to start a new checking
2
account to specifically keep track of urban forestry donations and log sales. Asked if income from
the log sales this year could be used as matching funds for the 2021 grant. Village Clerk Dawn
McCann explained that all urban forestry activity has been entered under specific urban forestry
budget lines for income and expenses. A detailed report can be printed out for each year. The
board verbally stated that the current accounting system being used is acceptable and urban forestry
log sale funds could be used as a match in the urban forestry grants.
McCarn made a motion to approve the board meeting minutes of September 1, 2020. Seconded by
K. Murray. Motion carried.
McCarn made a motion to approve payment of the bills as listed in the monthly expense report.
Seconded by K. Murray. Motion carried.
Members of the ARC agreed to schedule a meeting to review restrictions and covenants of North
Mills and First Addition to North Mills which are to expire in February of 2021.
Lee Ruegg joined meeting at 6:38 p.m.
Demolition bids for 207 School Street were received of the former Mushroom Farm:
Smithstonian Materials $386,750
LLK Excavating $210,000
G.T. Nelson, LLC $137,500
Showen Excavating $233,360
Guy Nelson was present to discuss details with the board and after much discussion the agreed goal
is to have the building down weather permitting by the end of the year. Other work such as concrete
removal, dirt work and seeding may need to be finished in the spring. Ruegg made a motion to
approve low bid from G.T. Nelson, LLC in the amount of $137,500. Seconded by McCarn. Motion
carried.
Jim Chellevold, DPW, updated the board that the TIF Trail project is going well and that a light pole
will need to be moved. Heisz asked why the edge of the pavement was cut so far along the highway
near the Community Commerce Center - curb and gutter will be installed.
No bids were received for the Old Mill Museum roof demolition project. The board discussed
rewriting the bid to include the replacement of the roof. Kevin Murray agreed to re-write specs.
The village office received a request to rent the upstairs office at 212 Main Street. After discussion
McCarn made a motion to set a rate for the larger upstairs office at $225 per month plus $225
deposit. Seconded by K. Murray. Motion carried.
3
Ruegg made a motion to approve the renewal of the Quartz employee health insurance policy with
an increase of $377.08 per month (+7.87%) effective on 12/1/2020. Seconded by K. Murray.
Motion carried.
K. Murray made a motion to approve Resolution 2020-10 adopting the refinancing of the Sewer
Loan with Royal Bank of $825,484.27 at a rate of 1.95%. Seconded by McCarn. Motion carried.
McCarn made a motion to approve operators licenses for John LaLande, Lyrica Marks and Michelle
Ford. Seconded by S. Murray. Motion carried.
Draft 2021 budgets were provided to the board: General of $746,824; Water of $115,950; and
Sewer of $165,000. The budget will be reviewed at the November meeting.
Under correspondences a letter was received from Kati Heisz concerning a snow pile near her house
last winter and is requesting the snow pile to be placed somewhere else this winter. An
informational article from The Municipality was provided Putting the “Responsible” Back into Low
Bidders.
The next regular board meeting has been scheduled for Monday, November 2, 2020 at 6:00 p.m.
At 7:08 p.m. Ruegg made a motion to convene into closed session pursuant to Wisconsin State
Statutes for the purpose of 19.85(1)(c) employee evaluations. Seconded by K. Murray. Motion
carried.
At 7:38 p.m. Ruegg made a motion to reconvene into open session. Seconded by Pettit. Motion
carried.
K. Murray made a motion to approve a 2020 swimming pool bonus of $.50 for each hour of work to
employees that finished the season in good standing and to provide the manager a bonus that
matches the top bonus of the swimming pool employees. Seconded by Ruegg. Motion carried.
Ruegg made a motion for the 2021 general employees to continue with bonuses in lieu of wage
increases. Seconded by McCarn. Motion carried.
Ruegg made a motion to adjourn the meeting at 7:40 p.m. Seconded by K. Murray. Motion carried.
Respectfully Submitted
Dawn R. McCann, Village Clerk
APPROVED 11-02-2020