AGENDA
JOINT REVIEW BOARD
CITY OF PLYMOUTH
TAX INCREMENTAL DISTRICT NO. 11
July 9, 2026 at 5:00 PM
The meeting will be held at the Plymouth City Hall, located at 128 Smith St. Room 210
1. Call to order.
2. Roll call.
3. Appointments (as needed):
a. Public member.
b. Chairperson.
4. Review responsibilities of the Joint Review Board.
5. Review and discuss draft Project Plan.
6. Set next meeting date to consider approval of the TID.
7. Adjourn.
July 9, 2026
PROJECT PLAN
City of Plymouth,
Wisconsin
Tax Incremental District No. 11
Prepared by:
Ehlers
N19W24400 Riverwood Drive,
Suite 100
Waukesha, WI 53188
BUILDING COMMUNITIES. IT’S WHAT WE DO.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 2
KEY DATES
Organizational Joint Review Board Meeting:
Scheduled for July 9, 2026
Public Hearing Held:
Scheduled for
July 9, 2026
Action by Plan Commission:
Scheduled for
July 9, 2026
Action by Common Council:
Scheduled for
July 28, 2026
Action by the Joint Review Board:
Scheduled for TBD
TABLE OF CONTENTS
Executive Summary
................................
................................
................................
................................
.....
3
Preliminary Map of Proposed District Boundary
................................
................................
............
6
Map Showing Existing Uses and Conditions
................................
................................
....................
9
Preliminary Parcel List and Analysis
................................
................................
................................
....
11
Equalized Value Test
................................
................................
................................
................................
.
12
Statement Listing the Kind, Number and Location of All Proposed Public Works or
Improvements Within the District
................................
................................
................................
.......
13
Map Showing Proposed Improvements and Uses
................................
................................
.......
20
Detailed List of Estimated Project Costs
................................
................................
.........................
24
Economic Feasibility Study, Description of the Methods of Financing Estimated
Project Costs and the Time When Related Costs or Monetary Obligations are to be
Incurred
................................
................................
................................
................................
..........................
25
Annexed Property
................................
................................
................................
................................
.....
30
Estimate of Property to Be Devoted to Retail Business
................................
...........................
30
Proposed Changes of Zoning Ordinances, Master Plan, Map, Building Codes and City
Ordinances
................................
................................
................................
................................
....................
30
Statement of the Proposed Method for the Relocation of any Persons to be Displaced
................................
................................
................................
................................
................................
............
31
How Creation of the Tax Incremental District Promotes the Orderly Development of
the City
................................
................................
................................
................................
............................
31
List of Estimated Non
-
Project Costs
................................
................................
................................
.
32
Legal Opinion Advising Whether the Plan is Complete and Complies with Wis. Stat. §
66.1105(4)(f)
................................
................................
................................
................................
.................
33
Calculation of the Share of Projected Tax Increments Estimated to be Paid by the
Owners of Property in the Overlying Taxing Jurisdictions
................................
......................
35
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 3
SECTION 1:
Executive Summary
DESCRIPTION OF DISTRICT
Tax Incremental District (“TID”) No. 11 (“District”) is a proposed Industrial
District comprising approximately
190
acres located
in the general area of
County Road PP and State Highway 57.
The District will be created to pay the
costs of
facilitating the public infrastructure upgrades (
“Project”) to
facilitate
an expansion of Sartori Cheese
(“Developer”).
AUTHORITY
The City is creating the District under the provisions of Wis. Stat. § 66.1105.
ESTIMATED TOTAL PROJECT COST EXPENDITURES
The City anticipates making total expenditures of approximately $
2,081,481
(“Project Costs”) to undertake the projects listed in this Project Plan (“Plan”).
Project Costs include an estimated
$561,481 in long
-
term principal and interest
payments, $775,00 in capital project costs, $490,000 to repay advances from
other funds and $255,00 in ongoing planning and administrative costs.
INCREMENTAL VALUATION
The City
projects that new land and improvements value of approximately
$
4,700,000
will result from the Project. Creation of this additional value will be
made possible by the Project Costs made within the District. A table detailing
assumptions as to the development timing and associated values is included in
the Economic Feasibility St
udy located within this Plan.
EXPECTED TERMINATION OF DISTRICT
Based on the Economic Feasibility Study located within Section 9 of this Plan,
the City anticipates that the District will generate sufficient tax increment to
pay all Project Costs within
20
of its allowable 20 years.
SUMMARY OF FINDINGS
As required by Wis. Stat. § 66.1105, and as documented in this Plan and the
exhibits contained and referenced herein, the following findings are made:
1.
That “but for” the creation of this District, the development projected to
occur as detailed in this Plan: 1) would not occur; or 2) would not occur in
the manner, at the values, or within the timeframe desired by the City. In
reaching this determination,
the City has considered:
The substantial investment needed to provide the public infrastructure
necessary to allow for development within the District. Absent the use of tax
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 4
incremental financing, the City is unable to fully fund this program of
infrastructure improvements.
2.
The economic benefits of the District, as measured by increased
employment, business and personal income, and property value, are
sufficient to compensate for the cost of the improvements. In making this
determination, the City has considered the following
information:
The expectation that the Project
add an additi
onal
27
jobs to
the area and
that
the Developer is likely to purchase goods and services from local
suppliers in construction of the Project, and induced effects of employee
households spending locally for goods and services from retailers,
restaurants and service companies.
3.
The benefits of the proposal outweigh the anticipated tax increments to be
paid by the owners of property in the overlying taxing jurisdictions. As
required by Wis. Stat. § 66.1105(4)(i)4., a calculation of the share of
projected tax increments estimated t
o be paid by the owners of property in
the overlying taxing jurisdictions has been prepared and can be found in this
Plan. However, because the Project would not occur without the use of tax
incremental financing, these tax increments would not be paid but
for
creation of the District. Accordingly, the City finds that the benefits
expected to be realized as set forth in this Plan outweigh the value of the
tax increments to be invested in the Project.
4.
Not less than 50% by area of the real
property within the District is suitable
for industrial sites as defined by Wis. Stat. § 66.1101, and has been zoned for
industrial use. Any real property within the District that is found suitable for
industrial sites and is zoned for industrial use at t
he time of creation of the
District will remain zoned for industrial use for the life of the District.
5.
Based on the foregoing finding, the District is designated as an industrial
district.
6.
The Project Costs relate directly to promoting industrial development in the
District, consistent with the purpose for which the District is created.
7.
Improvements to be made in the District are likely to significantly enhance
the value of substantially all of the other real property in the District.
8.
The equalized value of taxable property in the District, plus the incremental
value of all existing tax incremental districts within the City does not exceed
12% of the total equalized value of taxable property within the City.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 5
9.
The City estimates tha
t less than 35%
of the territory within the District will
be devoted to retail business at the end of the District’s maximum
expenditure period, pursuant to Wis. Stat. § 66.1105(5)(b).
10.
That there are no parcels to be included within the District that were
annexed by the City within the preceding three
-
year period.
11.
The Plan for the District is feasible and is in conformity with the Master Plan
of the City.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 6
SECTION 2:
Preliminary Map of Proposed District Boundary
Map
s
Found on Following Page.
To the extent District boundaries include wetlands identified on a map
prepared under Wis. Stat. § 23.32, the wetlands are excluded from the District.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 7
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 8
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 9
SECTION 3:
Map Showing Existing Uses and Conditions
Map Found on Following Page.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 10
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 11
SECTION 4:
Preliminary Parcel List and Analysis
ROW Areas
0.00
59271822647
WILLOW ROAD
CITY OF PLYMOUTH
24.03
24.03
59271820935
WILLOW ROAD
CITY OF PLYMOUTH
11.73
11.73
59271820938
N5490 WILLOW RD
PLYMOUTH INDUSTRIAL DEVELOPMENT CORPORATION
11.77
11.77
59271820941
N/A
PLYMOUTH INDUSTRIAL DEVELOPMENT CORPORATION
11.13
11.13
59271820942
N/A
PLYMOUTH INDUSTRIAL DEVELOPMENT CORPORATION
12.68
12.68
59271820957
N/A
PLYMOUTH INDUSTRIAL DEVELOPMENT CORPORATION
1.63
1.63
59271820946
N/A
PLYMOUTH INDUSTRIAL DEVELOPMENT CORPORATION
0.30
0.30
59271820960
N/A
STATE OF WI DEPT OF TRANSPORTATION
9.39
0.00
59271820953
SARTORI WHEY
CITY OF PLYMOUTH
1.99
0.00
59271820890
N/A
LAWN BOY INC
23.39
23.39
59271820910
STATE HIGHWAY 57
LAWN BOY INC
24.14
24.14
59271820955
4200 CTH PP
SFC-PLMOUTH LLC
22.31
22.31
59271820940
N/A
LAWN BOY INC
5.52
5.52
59271820931
1001 SARTORI WHEY
SARTORI REAL ESTATE LLC
2.00
2.00
59271821081
N/A
CITY OF PLYMOUTH
4.60
4.60
59271821067
COUNTY ROAD PP
CITY OF PLYMOUTH
0.40
0.40
59271821066
N/A
CITY OF PLYMOUTH
1.14
1.14
59271821073
N/A
CITY OF PLYMOUTH
3.36
3.36
59271822687
N/A
CITY OF PLYMOUTH
2.67
0.00
59271820952
WILLOW ROAD
SHEBOYGAN COUNTY
0.84
0.00
59271822693
N/A
SHEBOYGAN COUNTY
0.89
0.89
59271820950
WILLOW RD & COUNTY RD
CITY OF PLYMOUTH
12.75
59271820943
COUNTY ROAD PP
CITY OF PLYMOUTH
1.09
TOTALS
189.75
161.02
Percentage of TID Area Suitable for Mixed Use Development (at least 50%)
85%
Percentage of TID Area Not Suitable for Development
15%
Wetland Acreage Removed from District Boundaries
30.23
Owner
Acres
Industrial
Suitable
Acres
Parcel Number
Address
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 12
SECTION 5:
Equalized Value Test
The following calculations demonstrate that the City expects to be in
compliance with Wis. Stat. § 66.1105(4)(gm)4.c., which requires that the
equalized value of the taxable property in the proposed District, plus the value
increment of all existing tax in
cremental districts, does not exceed 12% of the
total equalized value of taxable property within the City
.
The equalized value of the increment of existing tax incremental districts within
the City, plus the base value of the proposed District, totals
$
46,955,100.
This
value is less than the maximum of $
151,383,516
in equalized value that is
permitted for the City
.
Calculation of City Equalized Value Limit
City TID IN Equalized Value (Jan. 1, 2025)
1,261,529,300
$
TID Valuation Limit @ 12% of Above Value
151,383,516
$
Calculation of Value Subject to Limit
Estimated Base Value of Territory to be Included in District
10,707,000
$
Incremental Value of Existing Districts (Jan. 1, 2025)
36,248,100
$
Total Value Subject to 12% Valuation Limit
46,955,100
$
Total Percentage of TID IN Equalized Value
3.72%
Residual Value Capacity of TID IN Equalized Value
104,428,416
$
Valuation Test Compliance Calculation
City of Plymouth, Wisconsin
Tax Increment District No. 11
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 13
SECTION 6:
Statement Listing the Kind, Number and Location of All
Proposed Public Works or Improvements Within the
District
Project Costs are any expenditure made, estimated to be made, or monetary
obligations incurred or estimated to be incurred as outlined in this Plan. Project
Costs will be diminished by any income, special assessments or other revenues,
including user fees
or charges, other than tax increments, received or
reasonably expected to be received in connection with the implementation of
the Plan. If Project Costs incurred benefit territory outside the District, a
proportionate share of the cost is not a Project Co
st. Costs identified in this
Plan are preliminary estimates made prior to design considerations and are
subject to change after planning, design and construction is completed.
With all Project Costs, the costs of engineering, design, survey, inspection,
materials, construction, restoring property to its original condition, apparatus
necessary for public works, legal and other consultant fees, testing,
environmental studies, perm
its, updating City ordinances and plans, judgments
or claims for damages and other expenses are included as Project Costs.
The following is a list of public works and other tax incremental financing
eligible Project Costs that the City expects to make, or may need to make, in
conjunction with the implementation of the District’s Plan. The map found in
Section 7 of this Plan al
ong with the Detailed List of Project Costs found in
Section 8 provide additional information as to the kind, number and location of
potential Project Costs.
Property, Right
-
of
-
Way and Easement Acquisition
Property Acquisition for Development
To promote and facilitate development the City may acquire property within
the District. The cost of property acquired, and any costs associated with the
transaction, are eligible Project Costs. Following acquisition, other Project
Costs within the categor
ies detailed in this Section may be incurred to make
the property suitable for development. Any revenue received by the City from
the sale of property acquired pursuant to the execution of this Plan will be used
to reduce the total project costs of the Dis
trict. If total Project Costs incurred
by the City to acquire property and make it suitable for development exceed
the revenues or other consideration received from the sale or lease of that
property, the net amount shall be considered “real property assem
bly costs” as
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 14
defined in Wis. Stat. § 66.1105(2)(f)1.c., and subject to recovery as an eligible
Project Cost.
Property Acquisition for Conservancy
To promote the objectives of this Plan, the City may acquire property within
the District that it will designate for conservancy. These conservancy objectives
include: preserving historic resources or sensitive natural features; protection
of scenic and hi
storic views; maintaining habitat for wildlife; maintaining
adequate open space; reduction of erosion and sedimentation by preserving
existing vegetation; and providing adequate areas for management of
stormwater. The cost of property acquired for conserva
ncy, and any costs
associated with the transaction, are eligible Project Costs.
Acquisition of Rights
-
of
-
Way
The City may need to acquire property to allow for installation of streets,
driveways, sidewalks, utilities, stormwater management practices and other
public infrastructure. Costs incurred by the City to identify, negotiate and
acquire rights
-
of
-
way are el
igible Project Costs.
Acquisition of Easements
The City
may need to acquire temporary or permanent easements to allow for
installation and maintenance of streets, driveways, sidewalks, utilities,
stormwater management practices and other public infrastructure. Costs
incurred by the City to identify, negotiate
and acquire easement rights are
eligible Project Costs.
Relocation Costs
If relocation expenses are incurred in conjunction with the acquisition of
property, those expenses are eligible Project Costs. These costs may include,
but are not limited to: preparation of a relocation plan; allocations of staff time;
legal fees; public
ation of notices; obtaining appraisals; and payment of
relocation benefits as required by
Wis. Stat. Chapter 32 and Wis. Admin. Code
ADM 92.
Site Preparation Activities
Environmental Audits and Remediation
If it becomes necessary to evaluate any land or improvement within the District,
any cost incurred by the City related to environmental audits, testing, and
remediation are eligible Project Costs .
Demolition
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 15
To make sites suitable for development, the City may incur costs related to
demolition and removal of structures or other land improvements, to include
abandonment of wells or other existing utility services.
Site Grading
Land within the District may require grading to make it suitable for
development, to provide access, and to control stormwater runoff. The City
may need to remove and dispose of excess material, or bring in fill material to
provide for proper site elevatio
ns. Expenses incurred by the City for site
grading are eligible Project Costs.
Utilities
Sanitary Sewer System Improvements
To allow development to occur, the City may need to construct, alter, rebuild
or expand sanitary sewer infrastructure within the District. Eligible Project
Costs include, but are not limited to, construction, alteration, rebuilding or
expansion of: collect
ion mains; manholes and cleanouts; service laterals; force
mains; interceptor sewers; pumping stations; lift stations; wastewater treatment
facilities; and all related appurtenances. To the extent sanitary sewer projects
undertaken within the District prov
ide direct benefit to land outside of the
District, the City will make an allocation of costs based on such benefit. Those
costs corresponding to the benefit allocated to land within the District, and
necessitated by the implementation of the Project Plan,
are eligible Project
Costs. Implementation of the Project Plan may also require that the City
construct, alter, rebuild or expand sanitary sewer infrastructure located outside
of the District. That portion of the costs of sanitary sewer system projects
un
dertaken outside the District which are necessitated by the implementation
of the Project Plan are eligible Project Costs.
Water System Improvements
To allow development to occur, the City may need to construct, alter, rebuild
or expand water system infrastructure within the District. Eligible Project Costs
include, but are not limited to, construction, alteration, rebuilding or expansion
of: distribut
ion mains; manholes and valves; hydrants; service laterals; pumping
stations; wells; water treatment facilities; storage tanks and reservoirs; and all
related appurtenances. To the extent water system projects undertaken within
the District provide direct
benefit to land outside of the District, the City will
make an allocation of costs based on such benefit. Those costs corresponding
to the benefit allocated to land within the District, and necessitated by the
implementation of the Project Plan, are eligib
le Project Costs. Implementation
of the Project Plan may also require that the City construct, alter, rebuild or
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 16
expand water system infrastructure located outside of the District. That portion
of the costs of water system projects undertaken outside the District which are
necessitated by the implementation of the Project Plan are eligible Project
Costs.
Stormwater Management System Improvements
Development within the District will cause stormwater runoff. To manage this
stormwater runoff, the City may need to construct, alter, rebuild or expand
stormwater management infrastructure within the District. Eligible Project
Costs include, but are not l
imited to, construction, alteration, rebuilding or
expansion of: stormwater collection mains; inlets, manholes and valves; service
laterals; ditches; culvert pipes; box culverts; bridges; stabilization of stream and
river banks; and infiltration, filtratio
n and detention Best Management Practices
(BMP’s). To the extent stormwater management system projects undertaken
within the District provide direct benefit to land outside of the District, the City
will make an allocation of costs based on such benefit. T
hose costs
corresponding to the benefit allocated to land within the District, and
necessitated by the implementation of the Project Plan, are eligible Project
Costs. Implementation of the Project Plan may also require that the City
construct, alter, rebui
ld or expand stormwater management infrastructure
located outside of the District. That portion of the costs of stormwater
management system projects undertaken outside the District which are
necessitated by the implementation of the Project Plan are eligi
ble Project
Costs.
Electric Service
To create sites suitable for development, the City may incur costs to provide,
relocate or upgrade electric services. Relocation may require abandonment and
removal of existing poles or towers, installation of new poles or towers, or
burying of overhead el
ectric lines. Costs incurred by the City to undertake this
work are eligible Project Costs.
Gas Service
To create sites suitable for development, the City may incur costs to provide,
relocate or upgrade gas mains and services. Costs incurred by the City to
undertake this work are eligible Project Costs.
Communications Infrastructure
To create sites suitable for development, the City may incur costs to provide,
relocate or upgrade infrastructure required for voice and data communications,
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 17
including, but not limited to: telephone lines, cable lines and fiber optic cable.
Costs incurred by the City to undertake this work are eligible Project Costs.
Streets and Streetscape
Street Improvements
To allow development to occur, the City
may need to construct or reconstruct
streets, highways, alleys, access drives and parking areas. Eligible Project Costs
include, but are not limited to: excavation; removal or placement of fill;
construction of road base; asphalt or concrete paving or rep
aving; installation
of curb and gutter; installation of sidewalks and bicycle lanes; installation of
culverts, box culverts and bridges; rail crossings and signals; utility relocation,
to include burying overhead utility lines; street lighting; installatio
n of traffic
control signage and traffic signals; pavement marking; right
-
of
-
way restoration;
installation of retaining walls; and installation of fences, berms, and landscaping.
Streetscaping and Landscaping
To attract development consistent with the objectives of this Plan, the City may
install amenities to enhance development sites, rights
-
of
-
way and other public
spaces. These amenities include, but are not limited to: landscaping; lighting of
streets, sidew
alks, parking areas and public areas; installation of planters,
benches, clocks, tree rings, trash receptacles and similar items; and installation
of brick or other decorative walks, terraces and street crossings. These and any
other similar amenities inst
alled by the City are eligible Project Costs.
Community Development
Cash Grants (Development Incentives)
The City may enter into agreements with property owners, lessees, or
developers of land located within the District for sharing costs to encourage
the desired kind of improvements and assure tax base is generated sufficient
to recover Project Costs. No cas
h grants will be provided until the City executes
a developer agreement with the recipient of the cash grant. Any payments of
cash grants made by the City are eligible Project Costs.
Cont
ribution to Community Development Authority (CDA)
As provided for in Wis. Stat. § 66.1105(2)(f)1.h and Wis. Stat. § 66.1333(13), the
City may provide funds to its
CDA
to be used for administration, planning
operations, and capital costs, including but not limited to real property
acquisition, related to the purposes for which it was established in furtherance
of any redevelopment or urban renewal project. Funds provided
to the
CDA
for
this purpose are eligible Project Costs.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 18
Revolving Loan/Grant Program
(Development Incentives)
To encourage private development consistent with the objectives of this Plan,
the City, through its
CDA
,
may provide loans or grants to eligible property
owners in the District. Eligible improvements will be those that are likely to
improve the value of the property, enhance the visual appearance of the
property and surrounding area, correct safety deficienci
es, or as otherwise
specified by the
CDA
in the program manual. Any funds returned to the
CDA
from the repayment of loans made are not considered reven
ues to the District,
and will not be used to offset District Project Costs. Instead, these funds may
be placed into a revolving fund and will continue to be used for the program
purposes stated above. Any funds provided to the
CDA
for purposes of
implementing this program are considered eligible Project Costs.
Miscellaneous
Rail Spur
To allow for development, the City may incur costs for installation of a rail spur
or other railway improvements to serve development sites located within the
District.
Projects Outside the Tax Increment District
Pursuant to Wis. Stat. § 66.1105(2)(f)1.n, the City may undertake projects within
territory located within one
-
half mile of the boundary of the District provided
that: 1) the project area is located within the City’s corporate boundaries; and
2) the projec
ts are approved by the Joint Review Board. The cost of projects
completed outside the District pursuant to this section are eligible project
costs, and may include any project cost that would otherwise be eligible if
undertaken within the District. The Cit
y intends to make the following project
cost expenditures outside the District:
-
New Drinking Well
-
$250,000
-
Sanitary Force Main
-
$150,000
-
WWTP Facilities Plan
-
$50,000
-
WWTP Upgrades
-
$100,000
-
Terciary Effluent Filtration
-
$500,000
Professional Service and Organizational Costs
The costs of professional services rendered, and other costs incurred, in relation
to the creation, administration and termination of the District, and the
undertaking of the projects contained within this Plan, are eligible Project Costs.
Professional ser
vices include but are not limited to: architectural;
environmental; planning; engineering; legal; audit; financial; and the costs of
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 19
informing the public with respect to the creation of the District and the
implementation of the Plan.
Administrative Costs
The City may charge to the District as eligible Project Costs reasonable
allocations of administrative costs, including, but not limited to, employee
salaries. Costs allocated will bear a direct connection to the time spent by City
employees relating to th
e implementation of the Plan.
Financing Costs
Interest expense, debt issuance expenses, redemption premiums, and any other
fees and costs incurred in conjunction with obtaining financing for projects
undertaken under this Plan are eligible Project Costs.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 20
SECTION 7:
Map Showing Proposed Improvements and Uses
Map
s
Found on Following Page.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 21
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 22
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 23
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 24
SECTION 8:
Detailed List of Estimated Project Costs
The following list identifies the Project Costs that the City currently expects to incur in implementing the
District’s Plan. All projects identified and related costs reflect the best estimates available as of the date of
preparation of this Plan. All cos
ts are preliminary estimates and may increase or decrease. Certain Project
Costs listed may become unnecessary, and other Project Costs not currently identified may need to be made.
(Section 6 details the general categories of eligible Project Costs). Chan
ges in Project Cost totals or the types
of Project Costs to be incurred will not require that this Plan be amended. T
his Plan is not meant to be a budget
nor an appropriation of funds for specific Project Costs, but a framework within which to manage Project
Costs.
Project ID Project Name/Type Phase I Ongoing Non-Project Costs Totals 1/2 Mile Est. Timing
1 New Drinking Well 250,000 1,550,000 250,000 250,000 2027
5 Water Main Reroute 325,000 325,000 2028
6 Sanitary Force Main 150,000 1,350,000 150,000 150,000 2027
11 WWTP Facility Plan 50,000 100,000 50,000 50,000 2026
9 New Road Construction 150,000 150,000 2028
11 WWTP Upgrades 100,000 34,900,000 100,000 100,000 2030
8 Terciary Effluent Filtration 500,000 4,500,000 500,000 500,000 2027
12 WPS Gas Main 400,000 400,000 2027
Interest on Long Term Debt 176,481 0
Financing Costs 57,850 0
Ongoing Planning & Administrative Costs 255,000 255,000
Total Projects 1,925,000 489,331 42,400,000 2,180,000 1,050,000
City of Plymouth, Wisconsin
Tax Increment District No. 11
Detailed List of Estimated Project Costs
Est. Cost
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 25
SECTION 9:
Economic Feasibility Study, Description of the Methods
of Financing Estimated Project Costs and the Time When
Related Costs or Monetary Obligations are to be Incurred
This Section includes a forecast of the valuation increases expected within the
District, the associated tax increment collections, a summary of how Project
Costs would be financed, and a projected cash flow demonstrating that the
District is economically
feasible.
Key Assumptions
The Project Costs the City plans to make are expected to create $
4,700,000
million in incremental value by
2027,
Estimated valuations and timing for
construction of the Project are included in
Table 1.
Assuming the City’s current
equalized TID Interim tax rate of
$13.80
per thousand of equalized value, and
no economic appreciation or depreciation, the Project would generate
$1,264,530
in incremental tax revenue over the 20
-
year term of the District as
shown in
Table 2
.
Tab
le 1
–
Development Assumptions
Annual Total
1 2026 2,350,000 2,350,000 2026 1
2 2027 2,350,000 2,350,000 2027 2
3 2028 0 2028 3
Totals 4,700,000 4,700,000
Construction
Year
Construction
Year
City of Plymouth, Wisconsin
Tax Increment District No. 11
Development Assumptions
Sartori Phase
1
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 26
Table 2
–
Tax Increment Projection Worksheet
Type of District Base Value 10,707,000
District Creation Date Economic Change Factor 0.00%
Valuation Date Jan 1, 2026 Apply to Base Value
Max Life (Years) Base Tax Rate 13.80$
End of Expenditure Period 15 7/28/2041 Rate Adjustment Factor 0.00%
Revenue Periods/Final Year 20 2047
Extension Eligibility/Years Yes 3
Eligible Recipient District
Construction
Year Value Added
Valuation
Year
Economic
Change
Total
Increment
Revenue
Year Tax Rate1 Tax Increment
1 2026 2,350,000 2027 0 2,350,000 2028 $13.80 32,424
2 2027 2,350,000 2028 0 4,700,000 2029 $13.80 64,848
3 2028 0 2029 0 4,700,000 2030 $13.80 64,848
4 2029 0 2030 0 4,700,000 2031 $13.80 64,848
5 2030 0 2031 0 4,700,000 2032 $13.80 64,848
6 2031 0 2032 0 4,700,000 2033 $13.80 64,848
7 2032 0 2033 0 4,700,000 2034 $13.80 64,848
8 2033 0 2034 0 4,700,000 2035 $13.80 64,848
9 2034 0 2035 0 4,700,000 2036 $13.80 64,848
10 2035 0 2036 0 4,700,000 2037 $13.80 64,848
11 2036 0 2037 0 4,700,000 2038 $13.80 64,848
12 2037 0 2038 0 4,700,000 2039 $13.80 64,848
13 2038 0 2039 0 4,700,000 2040 $13.80 64,848
14 2039 0 2040 0 4,700,000 2041 $13.80 64,848
15 2040 0 2041 0 4,700,000 2042 $13.80 64,848
16 2041 0 2042 0 4,700,000 2043 $13.80 64,848
17 2042 0 2043 0 4,700,000 2044 $13.80 64,848
18 2043 0 2044 0 4,700,000 2045 $13.80 64,848
19 2044 0 2045 0 4,700,000 2046 $13.80 64,848
20 2045 0 2046 0 4,700,000 2047 $13.80 64,848
Totals 4,700,000 0 Future Value of Increment 1,264,530
Notes:
1) Tax rate shown is actual 2025/2026 rate per DOR Form PC-202 (Tax Increment Collection Worksheet).
No
City of Plymouth, Wisconsin
Tax Increment District No. 11
Tax Increment Projection Worksheet
Mixed Use
July 28, 2026
20
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 27
Financing and Implementation
The projects funded through this project plan will be financed both with long
-
term General Obligation Debt and advances from other funds.
Table
3.
provides
a summary of the District’s financing plan.
Table 3
–
Financing Plan
G.O.
Promissory
Note
2030
Projects
Phase I 325,000
Total Project Funds 325,000
Estimated Finance Related Expenses 57,850
Total Financing Required 382,850
Estimated Interest 3.00% (2,438)
Assumed spend down (months) 3
Rounding 4,588
Net Issue Size 385,000
City of Plymouth, Wisconsin
Tax Increment District No. 11
Estimated Financing Plan
DEBT ISSUES
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 28
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 29
Based on the Project Cost expenditures as included within the cash flow exhibit
(Table 4)
, the District is projected to accumulate sufficient funds by the year
2045
to
pay off all
Project cost liabilities and obligations. The projected closure is based on the various assumptions noted in this Plan and wi
ll vary dependent on actual Project Costs incurred and the
actual amount of tax increments collected.
Table 4
–
Cash Flow
Total
$385,000 Debt
Year Issue Total Service Year
2026 480,000 480,000 0 0 450,000 30,000 480,000 0 0 0 2026
2027 10,000 10,000 0 0 10,000 10,000 0 0 0 2027
2028 32,424 32,424 0 0 10,000 10,000 22,424 22,424 385,000 2028
2029 64,848 64,848 0 0 10,000 10,000 54,848 77,272 385,000 2029
2030 64,848 132,000 325,000 521,848 0 0 325,000 264,119 10,000 599,119 (77,271) 0 385,000 2030
2031 64,848 64,848 26,150 26,150 28,698 10,000 64,848 (0) 0 375,000 2031
2032 64,848 64,848 25,725 25,725 29,123 10,000 64,848 (0) (0) 365,000 2032
2033 64,848 64,848 25,300 25,300 29,547 10,000 64,847 1 0 355,000 2033
2034 64,848 64,848 24,875 24,875 29,973 10,000 64,848 (0) 0 345,000 2034
2035 64,848 64,848 24,450 24,450 30,398 10,000 64,848 (0) (0) 335,000 2035
2036 64,848 64,848 24,025 24,025 30,823 10,000 64,848 (0) (0) 325,000 2036
2037 64,848 64,848 33,388 33,388 21,460 10,000 64,848 0 (0) 305,000 2037
2038 64,848 64,848 32,538 32,538 22,310 10,000 64,848 0 0 285,000 2038
2039 64,848 64,848 31,688 31,688 3,549 10,000 45,237 19,611 19,611 265,000 2039
2040 64,848 64,848 40,625 40,625 10,000 50,625 14,223 33,834 235,000 2040
2041 64,848 64,848 39,350 39,350 15,000 54,350 10,498 44,332 205,000 2041
2042 64,848 64,848 38,075 38,075 10,000 48,075 16,773 61,104 175,000 2042
2043 64,848 64,848 36,800 36,800 10,000 46,800 18,048 79,152 145,000 2043
2044 64,848 64,848 35,525 35,525 10,000 45,525 19,323 98,475 115,000 2044
2045 64,848 64,848 34,250 34,250 10,000 44,250 20,598 119,073 85,000 2045
2046 64,848 64,848 42,763 42,763 10,000 52,763 12,085 131,158 45,000 2046
2047 64,848 64,848 45,956 45,956 20,000 65,956 (1,109) 130,049 0 2047
Totals 1,264,530 132,000 490,000 325,000 2,211,530 561,481 561,481 775,000 490,000 255,000 2,081,481 Totals
Notes:
City of Plymouth, Wisconsin
Tax Increment District No. 11
Cash Flow Projection
Advance
from Other
Funds
Property
Sales
Tax
Increments
Debt
Proceeds
Ongoing
Planning &
Administratio
Projected Expenditures
Liabilities
Outstanding
PROJECTED CLOSURE YEAR
Projected Revenues
Total
Revenues
Balances
Capital
Projects
Repayment
of Advances
2030 G.O.
Promissory Note
Total
Expenditures Annual Cumulative
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 30
SECTION 10:
Annexed Property
A tax incremental district cannot include annexed territory unless at least three
years have elapsed since the annexation, or certain other requirements are met.
None of the property within the proposed District boundary was
annexed
during the past three years.
SECTION 11:
Estimate of Property to Be Devoted to Retail Business
Pursuant to Wis. Stat. § 66.1105(5)(b), the City estimates
that less than 35%
of
the territory within the District will be devoted to retail business at the end of
the District’s maximum expenditure period.
SECTION 12:
Proposed Changes of Zoning Ordinances, Master Plan,
Map, Building Codes and City Ordinances
Zoning Ordinances
The proposed Plan is in general conformance with the City’s current zoning
ordinances. Individual properties may require rezoning at the time of
development. Land within the District zoned industrial at the time of District
creation will remain in a zoning
classification suitable for industrial sites for the
life of the District.
Master (Comprehensive) Plan and Map
The proposed Plan is in general conformance with the City’s Comprehensive
Plan identifying the area as appropriate for industrial development.
Building Codes and Ordinances
Development within the District will be required to conform to State Building
Codes and will be subject to the City's permitting and inspection procedures.
The proposed Plan conforms to all relevant State and local ordinances, plans,
and codes. No changes
to the existing regulations are proposed or needed.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 31
SECTION 13:
Statement of the Proposed Method for the Relocation of
any Persons to be Displaced
Should implementation of this Plan require relocation of individuals or business
operations,
relocations will be handled in compliance with Wis. Stat. Chapter
32 and Wis. Admin. Code ADM 92.
SECTION 14:
How Creation of the Tax Incremental District Promotes
the Orderly Development of the City
Creation of the District and the implementation of the projects in its Plan will
promote the orderly development of the
City
by
creating new industrial sites
,
providing necessary public infrastructure improvements
,
providing appropriate
financial incentives for private development projects
. Through use of tax
increment financing, the
City
can attract new investment that results in
increased tax base. Development will occur in an orderly fashion in accordance
with approved plans so that the Projects will be
compatible with adjacent land
uses. Development of new uses in the District will add to the tax base and will
generate positive secondary impacts in the community such as increased
employment opportunities and
maintaining large industries in the City
.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 32
SECTION 15:
List of Estimated Non
-
Project Costs
Non
-
project costs are public works projects which only partly benefit the
District. Costs incurred that do not benefit the District may not be paid with tax
increments. Examples of non
-
project costs are:
•
A public improvement made within the District that also benefits
property outside the District. That portion of the total Project Costs
allocable to properties outside of the District would be a non
-
project
cost.
•
A public improvement made outside the District that only partially
benefits property within the District. That portion of the total Project
Costs allocable to properties outside of the District would be a non
-
project cost.
•
Projects undertaken within the District as part of the implementation of
this Project Plan, the costs of which are paid fully or in part by impact
fees, grants, special assessments, or revenues other than tax increments.
T
he Plan includes the following non
-
project costs:
Project ID Project Name/Type Non-Project Costs Est. Timing
1 New Drinking Well 1,550,000 2027
5 Water Main Reroute 2028
6 Sanitary Force Main 1,350,000 2027
11 WWTP Facility Plan 100,000 2026
9 New Road Construction 2028
11 WWTP Upgrades 34,900,000 2030
8 Terciary Effluent Filtration 4,500,000 2027
12 WPS Gas Main 2027
Interest on Long Term Debt
Financing Costs
Ongoing Planning & Administrative Costs
Total Projects 42,400,000
City of Plymouth, Wisconsin
Tax Increment District No. 11
Detailed List of Estimated Project Costs
Est. Cost
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 33
SECTION 16:
Legal Opinion Advising Whether the Plan is Complete
and Complies with Wis. Stat. § 66.1105(4)(f)
Legal Opinion Found on Following Page.
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 34
NEED WET SIGNATURE & DATED LEGAL OPINION ON ATTORNEY
LETTERHEAD
SAMPLE
Mayor
City of Plymouth
128 Smith St
Plymouth, Wisconsin 53073
RE:
Project Plan for Tax Incremental District No. 11
Dear Mayor:
Wisconsin Statute 66.1105(4)(f) requires that a project plan for a tax
incremental financing district include an opinion provided by the City Attorney
advising as to whether the plan is complete and complies with Wisconsin
Statute 66.1105.
As City Attorney for the City of Plymouth, I have been asked to review the
above
-
referenced project plan for compliance with the applicable statutory
requirements. Based upon my review, in my opinion, the Project Plan for the
City of Plymouth Tax Increment
al District No. 11
is complete and complies with
the provisions of Wisconsin Statute 66.1105.
Sincerely,
City Attorney
Tax Incremental District No. 11 Project Plan City of Plymouth
Prepared by Ehlers Page | 35
SECTION 17:
Calculation of the Share of Projected Tax Increments
Estimated to be Paid by the Owners of Property in the
Overlying Taxing Jurisdictions
The following projection is provided to meet the requirements of Wis. Stat. §
66.1105(4)(i)4.
Revenue
Year
Sheboygan
County
City of
Plymouth
School District
of Plymouth
Lakeshore
Technical
College Total
Revenue
Year
2028 7,149 11,448 12,672 1,155 32,424 2028
2029 14,297 22,897 25,343 2,311 64,848 2029
2030 14,297 22,897 25,343 2,311 64,848 2030
2031 14,297 22,897 25,343 2,311 64,848 2031
2032 14,297 22,897 25,343 2,311 64,848 2032
2033 14,297 22,897 25,343 2,311 64,848 2033
2034 14,297 22,897 25,343 2,311 64,848 2034
2035 14,297 22,897 25,343 2,311 64,848 2035
2036 14,297 22,897 25,343 2,311 64,848 2036
2037 14,297 22,897 25,343 2,311 64,848 2037
2038 14,297 22,897 25,343 2,311 64,848 2038
2039 14,297 22,897 25,343 2,311 64,848 2039
2040 14,297 22,897 25,343 2,311 64,848 2040
2041 14,297 22,897 25,343 2,311 64,848 2041
2042 14,297 22,897 25,343 2,311 64,848 2042
2043 14,297 22,897 25,343 2,311 64,848 2043
2044 14,297 22,897 25,343 2,311 64,848 2044
2045 14,297 22,897 25,343 2,311 64,848 2045
2046 14,297 22,897 25,343 2,311 64,848 2046
2047 14,297 22,897 25,343 2,311 64,848 2047
Totals 278,794 446,484 494,197 45,056 1,264,530
Estimated portion of taxes that owners of taxable property in each taxing
jurisdiction overlaying district would pay by jurisdiction.
City of Plymouth, Wisconsin
Tax Increment District No. 11
Source: City of Plymouth website. First collected Oct 14, 2026.