MINUTES
Plan & Review Commission Public Hearing
Wednesday, May 6, 2026 at 6:00 PM
NOTICE WAS GIVEN that the Town of Spider Lake Plan & Review Commission would
hold a Public Hearing on Wednesday, May 6, 2026 at 6:00 P.M. at the Town Hall,
10896W Town Hall Rd, Hayward Wisconsin, to consider the following:
Conditional Use Permit - Land owner: Nathan & Julie Gassman. Located in part of the
NE¼ of the NE¼, Sec 29, T42N, R7W, PRT NENE Lot 2 CSM 29/240 #7444, Legacy ID:
028742291107. Site address: 11495W Clear Lake Rd, 5.00 Acres, Zoned A-1 Agriculture
One. Purpose of request is to build a year-round dwelling on the property.
The Hearing was Called to Order by P&RC Vice Chair Johnson at 6:00 pm.
1. Present were Vice Chair Quentin Johnson and Commissioners Capes, Becker,
Tumbleson, Alternate Commissioner Victoria Ross and Zoning Administrator
Mike Gardner. Johnson confirmed a quorum was present and that Notices were
posted in compliance with Open Meetings Law (in Sawyer County Record
editions of April 22
nd and 29th, and on the Town website).
2. Motion to approve the Agenda was made by Don Becker, seconded by Bob
Capes. All in favor; motion carried.
3. Vice Chair Johnson informed the public of the hearing procedures before the
Hearing commenced.
Gassman CUP Application Hearing: The applicants, Nathan & Julie Gassman, attended
via Zoom and provided a statement describing the proposed project: a year-round
dwelling cabin. The septic system was previously installed. Nine letters were sent to
adjacent property owners; 3 were returned without objection and zero with objections.
There was no testimony offered by the public. The Commissioners asked questions for
understanding, and the hearing concluded at 6:10 pm.
Respectfully submitted,
Bob Capes
Plan & Review Commissioner
May 6, 2026
MEETING MINUTES
Town of Spider Lake
Plan and Review Commission Meeting
May 6, 2026
1. Vice Chair Johnson called the meeting to order at 6:00 pm, immediately
following the Gassman CUP Public Hearing. Present were Johnson and
Commissioners Capes, Becker, Tumbleson, Alternate Commissioner Victoria
Ross and Zoning Administrator Mike Gardner. Johnson confirmed a quorum
was present.
2. Motion to approve the Agenda made by Don Becker, seconded by Bob Capes.
All in favor; motion carried.
3. Pledge of Allegiance
4. Motion to approve the Minutes of the April 1, 2026 Public Hearing made by
Quentin Johnson, seconded by Don Becker. All in favor; motion carried.
5. Gassman CUP - Discussion and Recommendation: The owner’s intended use
(year-round dwelling) satisfies the conditional use requirement per Part I, Section
15.4 B) 1) of Land Use Ordinance 17-88. Possible Conditions were discussed
and are attached to these Minutes. Motion to recommend approval of the
Gassman CUP 26-02 with proposed conditions to the Town Board made by
Quentin Johnson, seconded by Don Becker. All in favor; motion carried.
6. Zoning Administrator’s Report: ZA Gardner reported follow-up conversations and
prospective owner inquiries, with six permit applications for review.
a. Permit Applications:
i. LUP 26-09 – Gassman – New Dwelling: Permit application for
single family dwelling on A-1 zoned parcel. CUP applied for and will
be reviewed by the Board on May 13, 2026. As all Ordinance
requirements are met, Motion to approve LUP 26-09 contingent
on Town Board approval of the CUP made by Victoria Ross
seconded by Don Becker. All in favor; motion carried.
ii. LUP 26-10 – Scrivner - New Dwelling on vacant parcel. As all
Ordinance requirements are met, Motion to approve LUP 26-10
made by Don Becker, seconded by Jeff Tumbleson. All in favor;
motion carried.
iii. LUP 26-11 – Vesel – New Dwelling on vacant parcel. As all
Ordinance requirements are met, Motion to approve LUP 26-11
made by Quentin Johnson, seconded by Don Becker. All in
favor; motion carried.
iv. LUP 26-12 – Matson – Accessory Structure (Carport) and
walkway: Owner’s proposal to construct open-sided carport and
connecting walkways meets the Ordinance requirements. Motion
made to approve LUP 26-12 made by Don Becker, seconded by
Victoria Ross. All in favor; motion carried.
v. LUP 26-07rev – Hallquist – New Dwelling on a non-conforming
parcel. Original site plan was not approved at the April 1, 2026
P&RC meeting. The dwelling footprint was reduced by adding a
second story and meets the required height regulations and side
setbacks of 30 feet. As the revised site plan meets Ordinance
requirements, Motion to approve LUP 26-07rev was made by
Quentin Johnson and seconded by Don Becker. All in favor;
motion carried.
vi. LUP 26-13 – Larson – Dwelling addition; conversion of a seasonal
porch to permanent and small footprint addition. As the proposed
change meets the Ordinance requirements, Motion to approve
LUP 26-13 was made by Don Becker and seconded by Bob
Capes. All in favor; motion carried.
b. Notices and anticipated activity
i. Second Corrective Action Notices have been sent to Kroll and Frick
for removal of trailers by June 2nd; the trailers are currently in
violation of the Ordinance. The Town is set up to issue and process
citations when required.
7. Land Use Ordinance 17-88 update: Zoom call with von Briesen & Roper (vB&R)
principals is set for April 20, 2026. Activity plan for the month involves continued
review and recommendations for Use Table and Supplemental Use Regulations,
Lot Standards and Short Term Rental Standards. Thor Jeppsen, vB&R Project
Manager, will participate in the June 3 P&RC Meeting.
8. As there was no other business coming before the Commission, Motion to
adjourn was made by Victoria Ross, seconded by Don Becker. All in favor;
motion carried.
Respectfully submitted,
Bob Capes
Plan & Review Commissioner
May 10, 2026
Town of Spider Lake
Conditional Use Permit
Approval Conditions
(DRAFT for Board Consideration)
Owner: Permit N
umber: CUP 26-02
NATHAN & JULIE GASSMAN Hearing Date: May 6, 2026
609 Ronell St
St Peter, MN 55082
Property Address: 11495W Clear Lake Rd, Hayward, WI 54843
PRT NENE Lot 2, CSM 29/240 #7444
The Conditional Use Permit described above has been recommended for approval
subject to the following conditions:
1. The CUP is issued only to facilitate the building of a single family year-round
principal structure used as a dwelling. (Per Ordinance 17-88, Part I Section
15.4 B) 1)).
2. As the parcel is less than ten acres, Livestock is not permitted except for
poultry which may be allowed by separately obtained Conditional Use permit
(Per Ordinance 17-88, art I Section 15.4 A) 1) a).
3. The landowner consents to periodic inspections by the Town of Spider Lake’s
Zoning Administrator (ZA) or the ZA’s designee.
6. The conditions of this CUP are binding upon any heirs, successors or
assignees. In the event of the sale or transfer of the property, the land owner
or successors will disclose the existence of the CUP to any prospective buyers.
Town of Spider Lake
Zoning Report
May 2026
Date Permit# Name Address Descrip1on Construc1on
Cost
Total
Sq Ft
Fee
5/4 Larson LUP inquiry
5/7 Vessel,
Gassman
LUP follow ups, Larson LUP review
5/7 Schroeder LUP inquiry
5/13 Wheel Inn Ordinance violaEon, RV Parked follow up
5/13 Lilyblad Landscaping contractor inquiry
5/13 Damaske Realtor, Accessory Structure inquiry
5/19 Barnes Accessory Structure inquiry
5/19 Grayjek Setback inquiry
5/19 Keller Setback inquiry
5/19 LUP 26-
04
Velasquez Provided complete permit documents
5/19 Bender Hill ConstrucEon Scrivner applicaEon
5/21 Boss Contacted Boss InspecEons regarding Frick
permit / violaEon
5/23 Melick LUP inquiry
5/25, 27 Kryer Returned inquiry message
5/26 Promersberger LUP inquiry
5/26,27 Dums Inquiry and follow up site visit
5/28 LongEne LUP applicaEon follow up, informaEon
request
5/28 Bender LUP follow up, informaEon request
5/28 Clark & Clark Zoom meeEng to discuss violaEon / citaEon
process. Kroll and Frick
LUP 26-14
$200.00
LUP 26-14
Sisters of Charity of the Blessed Virgin Mary
Foundation Replacement
June 3, 2026
Application for Land Use/Building Permit Town of Spider Lake
Sawyer County, Wisconsin
CONSTRUCTION MAY NOT BEGIN UNTIL THE PERMIT IS ISSUED AND A PERMIT CARD POSTED AT THE PROPERTY
ENTRANCE.
Be sure to complete all steps in this application.
Click Skip or Continue to save your input.
To exit the application at any point, close the app or browser after saving.
Is agent/builder same as owner? Yes No
First name
Joseph
Last name
Karlgaard
Property Owner Daytime Phone #
6507045736
Property Owner Mailing Address
153 Maple Hill Road, Hopkins, MN 55343
First name
Hill
Last name
Construction LLC
Agent/Builder Daytime Phone #
7156380849
Agent/Builder Mailing Address
15988 US Hwy 63, Hayward, WI 54843
Govʼt Lot 1/4 1/4
Sec.
34
Twn.
42N
R______W
07
Alternate/Legacy ID
028742345206
LUP 26-15
LND 58
Description
Prt Govt Lot 2, Lot 1, CSM 38/41 #8670
Site Address
12459N Town Hall Rd, Hayward, WI 54843
Acreage
1.07
Deed
Document #
443973
Sanitary Permit #
24313
Sanitary Permit Date
10/9/2024
Sanitary Permit Issued By
Sawyer County
Year Installed
2024
Owner When Installed
Joseph Karlgaard
Attach Copy Of Approved Sawyer County Sanitary Permit
Visit heygov.co/townofspiderlake.com/fr_01krnyv1vgdb8d3455kcwyrtnj to view or download full files.
Zone District R1 RR1 RR2 A1 C1 I1 F1
Wetland/Shoreland Yes No
Shoreland: The area of frontage on navigable waters measured from the normal high-water elevation within one thousand 1,000
feet from lakes, ponds and flowages; and three hundred 300 feet from rivers and streams.
To Download the Power of Attorney Form open this link here.
Please upload filled in and notarized Power of Attorney
power-of-attorney-1778854656506.pdf
Visit heygov.co/townofspiderlake.com/fr_01krnyv1vgdb8d3455kcwyrtnj to view or download full files.
Throughout the process the inputed information is automatically saved as a
Draft document and you can always revisit it to continue where you left off.
Permit
Requested
For
New Dwelling Addition To Dwelling Accessory Structure
Addition To Accessory Structure Other/Misc Use of Land
Home Occupation/ Professional Office Alternative or Renewable Energy Systems
Communication Systems Other New Building/Structure (e.g., Commercial, Industrial, Agricultural)
Other New Addition To Building/Structure (e.g., Commercial, Industrial, Agricultural)
Other/ Misc info
Other
/ Misc
type
Foundation Replacement
Roof Structure Replacement
Other
Stairs/Walkways Within 75ʼ Of OHWM
Area Involved (length X width = total SQFT
4 x 54 = 216
Height of Structure Grade to Peak
4
Construction Cost
$20000
Submit Completed Application And Fee To:
Clerk, Town of Spider Lake
Attn: Sarah Delaney
Chair PRC
10896 Town Hall Rd.
Hayward, WI 548543
Skip if project is not Shoreland/Wetland
To take a look at any Additional Information, the Worksheet & the Example Plot
Plan open this link here.
To Download the Shoreland Preservation Agreement open this link here.
Total land area within 300ʼ of the water body:
46609 sf
Please Upload the SHORELAND PRESERVATION A GREEMENT
shoreland-preservation-
1778855393634.pdf
Visit heygov.co/townofspiderlake.com/fr_01krnyv1vgdb8d3455kcwyrtnj to view or download full files.
Total impervious surface area (including this project)
2161
Please Upload the the worksheet in the Additional Information Worksheet document
B/A x 100 = % Used
4.6 %
Attach the Site Plan
site-sketch-1778856922922.pdf
Visit heygov.co/townofspiderlake.com/fr_01krnyv1vgdb8d3455kcwyrtnj to view or download full files.
In the event this application is approved by the Zoning Office, I agree:
That no work shall commence until I have received the issued Land Use Permit, and the Permit Card is posted
That all work shall be done in accordance with the requirements of the Town of Spider Lake Land Use Permit, the Town of
Spider Lake Land Use Ordinance, all other applicable County Ordinances and the laws and regulations of the State of
Wisconsin,
That the signing of this application grants permission to allow free and unlimited access to the property for onsite inspections
between the hours of 800 AM 600 PM Mon – Fri to the Zoning Administrator(s) and/or Plan & Review Commissioners.
I (we) declare that this application (including any accompanying information) has been examined be me (us) and to the best of my
(our) knowledge and belief it is true, correct and complete. I (we) acknowledge that I (we) am (are) responsible for the detail and
accuracy of all information I (we) am (are) providing and that it will be relied upon by the Town of Spider Lake in determining
whether to issue a permit. I (we) further accept liability which may result of the Town of Spider Lake relying on this information I
(we) am (are) providing in or with this application.
Signature of Owner or Agent with Power of Attorney)
Signed electronically on 5/15/26, 1006 AM
To Review the Fee Schedule for the Land Use Application open this link here.
Enter amount of calculated fees
200
Thank you for calculating your payment fees. The Zoning Administrator will review the calculations and will send you a request for
payment.
SUBMITED ON 5/15/26
For Zoning & Building Department use only
Does the Plan & Review Commission recommend approval from the Town Board? Yes No
Reason for recommendation
DN
UP
UP
20'20'
5'
5'
10'-0" X 4'-0"
4'-5" X 4'-5"
5'-0" X 5'-0"
DECK
DECK
DECK
Cross Section 1
P-1
REVISION TABLE
NUMBER DATE REVISED BY DESCRIPTION
SHEET:
SCALE:
DRAWINGS PROVIDED BY:
DATE:
5/14/2026
Karlgaard
Application for Land Use/Building Permit
Town of Spider Lake
Sawyer County, Wisconsin
Application No .. _________ _
CONSTRUCTION MAY NOT BEGIN UNTIL THE PERMIT IS ISSUED AND A PERMIT CARD POSTED AT THE PROPERTY ENTRANCE.
This is a Three (3) page document. Be sure to complete all pages
Print Or Type - Use Black Ink
Site Information (From Real Estate Property Tax Bill)
Gov'tlot ____ 1/4_1/4, Sec. __ Twn. __ N R_W Alternate/LegacylD: Q.)J..-t,.!J.J,.·J.'·~./-..fJ::J
Description: __ {2-'ll---.T--/V...-.....,~.;..."'...,..s~E---------------------
SiteAddress: 7 617 ~) Sfw,~ f-k.,,1 77 Acreage). ()5 Deed Document# 'i06oC3
~:=~z;z;;.::~~f.:.f4t>~r,-:.,By :~r:.1/tJ=~P«mLQ
Zone District: 0 R-1 0 RR-1 0 RR-2 0 A-1 0 C-1 0 1-1 0 F-1
Wetland/Shoreland: D Yes p( No (Shoreland: The area of frontage on navigable waters measured from the normal high-water elevation within one
thousand (1,000) feet from lakes, ponds and flowages; and three hundred (300) feet from rivers and streams.)
Permit Requested For
Type of Dwelling #of Walk Out Attached Garage Footprint of Proposed Hght of Structure
0 Frame built on site Bedrooms □ Yes □ Yes □ No Structure Grade to Peak
0 Modular/manufactured □ □ No __ X __ = __ SF
□ New 0 Other
__ X __ = __ SF
Dwelling Loft #of □ Yes Deck □ Yes □ No Total Habitable Sq. Ft. Construction Cost
Type of Construction Stories
D Frame D Log D Pole/Metal □
□ No __ X __ = __ SF $
D Block D Other
Use of Addition Bedrooms #of Stories Size of Proposed Structure Hght of Structure
Existing □ □ Grade to Peak
Addition 0 Living room 0 Kitchen O Bathroom __ x __ = __ SF
□ To Additional D 0 Bedroom D Garage □ Deck Loft Total Habitable Sq. Ft. Construction Cost Dwelling 0 Storage Building D Screened Porch Total □ □Yes $
D Other □ No
#of Type of Accessory Structure Size of Proposed Structure Hghtof Construction Cost
□
Accessory Stories D Garage D Storage Building D Gazebo Structure
Structure □ 0 Screen house D Greenhouse __ X __ = __ SF Grade to Peak $
D Other
Addition To Size of Existing Accessory Structure Size of Proposed Addition Hght of Structure Construction Cost
□ Accessory Grade to Peak $ Structure __ X __ = __ SF __ X __ = __ SF
~
,Foundation Replacement Area Involved Hght of Structure Construction Cost
r)Q Other/ Misc • Roof Structure Replacement Grade to Peak
$ }!/_. IJ Ob.,. Other
~X~=./.12AI/ ~J' 0 Stairs/Walkways Within 75' Of OHWM -y
D UseofLand D Filing D Dredging 0 Grading O > 10,000 S.F. Grading 0 Other
Type of Business Total Area of Existing Building SF
Home Occupation/ D Located in Existing Dwelling
Area Being Used for Business
□ Professional Office D Located in Existing Accessory Structure
(Not more than 1 nonresident person may be employed on the premises}
D Alternative or Renewable Energy Systems I B ~~~:. □ Wind
□ Communication
Systems
TOWN OF SPIDER LAKE
ZON!NGADM 5.25.16
0 Cell Tower Height of Tower:
D Other
(May not exceed 25% of the tol.al floor area of the d-1/ing 750 sq. ft. in an
accessory building)
X = SF
Construction Cost
$
Construction Cost
$
Page 1 ofJ
LUP 26-16
Plan and Review Commission Meeting
Town of Spider Lake
Land Use Ordinance Update
Project Team: von Briesen & Roper, s.c. and the Town of Spider Lake Plan and Review
Commission
Date: June 3, 2026
WHAT IS ZONING
Balancing public health, safety, and
community welfare with established
property rights.
Police power delegated to municipalities by the State
Regulates:
Presumption of property rights
Regulations must have rational nexus to legitimate
government interests – health, safety, and public welfare
Land uses - what a property can be used for
Building Form - how structures on that property look
RECENT LEGAL CONTEXT
TAKEAWAY: Set objective standards for residential
development, less leeway to add site-specific
conditions
Limits standing to challenge denial, but courts
may order residential approval directly
2017 WI Act 67
TAKEAWAY: Greatly reduce subjective approval
processes - objective zoning standards are easiest to
defend
2023 WI Act 16
All special zoning approvals are considered
conditional uses
All conditional use decisions must be based on
substantive evidence (opinion, hearsay, etc.,
are not reasons to deny)
Municipalities must grant applications for
residential housing development if the permit
is complete when submitted and meets all
existing requirements at the time the
application is filed
PROJECT GOALS
Fix typos and inconsistencies
Improve clarity and organization
Align standards with State Law
Align with Comprehensive Plan and current
development patterns
Modernize the Land Use Table
Reduce use of conditional uses and implement
objective performance standards
Streamline administration
Improve long-term usability
Preserve rural residential Northwoods character,
natural resources, and recreation
Add missing modern use categories, remove
outdated or unnecessary categories
PROJECT TIMELINE
Phase 1: Land Uses & Lot and Dimensional Standards (March-July 2026)
Establish zoning districts
Land Use Table and supplemental use regulations/performance standards
Lot Standards
Site Design regulations (lighting, landscaping, etc.)
Phase 2: Shoreland-Wetland Zoning
July-September 2026
Phase 3: Subdivision Control
August-October 2026
Phase 4: Administrative Procedures
October-December 2026
Phase 5: Final Review, Testing, and Adoption
December 2026-March 2027
EXISTING ZONING DISTRICTS
Unmapped R-1 and I-1 districts
Overlapping district intents and
characteristics
Inconsistent permitted uses
Overuse of conditional uses
Zoning District District Characteristics
Residential R-1 Single- and Two-Family year-round residential homes;
Multifamily and institutional uses allowed conditionally
Rural Residential RR-1 Low-density residential
Residential-Recreational
RR-2 Residential, recreation-oriented service uses, and hospitality
Agricultural A-1 Agriculture and recreation, limited residential and institutional
Industrial I-1 Manufacturing, warehousing, and industrial operations
Commercial C-1 Retail, professional services, institutional, and entertainment
Forestry F-1 Forestry, recreation, and limited residential
Wetland/Shoreland W-1 Wetland preservation
Shoreland Protection
Overlay SP Shoreland preservation
NEW ZONING DISTRICTS
Zoning District District Purpose District Uses
Rural Residential RR-1 Provide low-density residential development that preserves the Town’s
rural character and protects natural resources Low-density residential
Residential-
Recreational RR-2
Accommodate residential development in recreational areas, allowing a
mix of dwellings with limited lodging and service establishments
Residential, hospitality, and recreational
services, with limited institutional uses
Agricultural A-1
Preserve agricultural and open space uses that maintain rural character,
support land stewardship and recreation, and limit fragmented
development
Agriculture and recreation
Commercial C-1
Concentrate commercial, professional, institutional, and limited light
industrial uses in designated areas that serve community and visitor
needs while remaining compatible with surrounding land uses and
orderly development patterns
Retail, professional services, institutional, and
light-industrial
Forestry F-1
Protect forested lands by allowing forestry, passive recreation, and very
low-intensity development consistent with long-term conservation of
rural landscape and ecological values
Forestry, recreation, and limited residential
Wetland Overlay W-1
Protect wetlands by limiting development and requiring that land use
activities avoid, minimize, or mitigate impacts to wetland resources and
their ecological functions
Base district with wetland preservation
standards
Shoreland Protection
Overlay SP
Preserve the environmental quality, water resources, and rural character
of shoreland areas by regulating development intensity and land
disturbance adjacent to navigable waters
Base district with shoreland preservation
standards
Remove Residential (R-1) and Industrial (I-1) districts
Make Wetland/Shoreland District an overlay to strengthen resource protection and allow greater flexibility
USE TABLE OVERVIEW
Update list of permitted uses to a simplified and modernized Use Table
Supplement with additional regulations and performance standards for
conditional uses
Reduce ambiguity and improve readability
USE / ACTIVITY R RR C AG F NOTES / CONDITIONS
Residential
Residential-
Recreational
Commercial
Agricultural
Forestry
Single-Family Dwelling P P P¹ P¹ 1 - when accessory to an agricultural or forestry use
Two-Family Dwelling (Duplex) P P P¹ P¹ 1 - when accessory to an agricultural or forestry use
Multifamily Dwelling (3+ units) P Subject to design standards
Boarding or Rooming House P P
Accessory Dwelling Unit (ADU) C C Max. 1 ADU per parcel; must remain subordinate to primary dwelling
Caretaker / Employee Residence P Must be accessory to primary permitted use on parcel
Mobile Home Park C Subject to Wis. Stat. 66 standards and design standards
Short-Term Rentals C Standards to be drafted at a future time
Bed and Breakfast (B&B) C C
Lodging (Resorts, Hotels, Motels) C P
Accessory Structure P P P P P
Garage / Carport P P P P P
Boathouse New boathouses not permitted
Deck, Porch, or Patio P P P P P
Agricultural Building / Barn P P
Alternative and Renewable Energy Systems P P P P P Subject to standards
Home Occupation P P P P P Subject to standards
Place of Worship P P
School (K–12) P P
Daycare / Child Care Center C P P
Medical / Assisted Living Facility P
Municipal / Government Facility P P P P P
Cemetery P
Park / Open Space P P P P P
Trail (Non-Motorized) P P P P P
Outdoor Recreation Facility C C C C
Golf Course C
Marina C C P
Campground C C C
Recreation / Youth Camp C
Event Venue / Wedding Barn C C parking, noise, and hours-of-operation standards; max event size
Drive-In / Drive-Through Establishment C Site plan review required
Entertainment Facility and Amusement Parks P Subject to Noise, lighting, operational standards
Shooting Range (Outdoor) C C Minimum setback from property lines; noise standards; berm requirements
Retail Store C P
Professional / Personal Services C P
Restaurant / Tavern C P
Food Truck / Mobile Food Vendor C P Annual permit; designated location; sanitation standards
Auto Sales C
Auto Service / Repair P
Brewery, Winery, or Distillery C P C May include tasting room; allowed in AG as accessory to farm operation
Mini-Storage / Self-Storage P
Wholesale and Distribution C
Kennel (Small Domestic Animals) C C
Laundromat P
Funeral Home P
Nursery / Garden Center C P C
Farm Stand / Direct Market Sales P P Accessory to on-site agricultural use
Agricultural Activity / Farm Operation P
Gardening P P P P P When accessory to a primary use
Horses / Equestrian Use C C P
Forest Crops / Timber Management P P Subject to Wis. Managed Forest Law (MFL) where applicable
Harvesting of Wild Crops P P
Drainage P P
Soil & Water Conservation Program P P
Sod / Topsoil Removal for Resale C C
Essential Services (accessory to principal use) P P P P P
Electric / Telecom Distribution Lines C C C C C
High-voltage Transmission Lines C
Public Utility Facility C
Communication Tower / Antenna C C C Subject to FCC requirements and fall-zone setbacks
Commercial-Scale Solar / Wind Energy C
Dam C C DNR permit required under Wis. Stats. Ch. 31
Pipeline C C Subject to state and federal pipeline safety regulations
Sewage Treatment / Disposal Facility C Required to serve permitted uses; DNR approval required
Landfill / Solid Waste Disposal C County and DNR approval required; only in AG with CUP
Light Manufacturing C No outdoor storage; no noxious emissions; site plan review
Data Centers C Subject to size limitations
Contractor Yard / Storage Yard C C
Sawmill / Wood Processing C On-site processing of timber harvested from same parcel
Non-Metallic Mining / Extraction C Reclamation plan required per Wis. Stats. § 295
Concrete / Aggregate Processing C
Salvage / Junk Yard C
Hazardous Material Manufacturing
Transportation Terminal C
UTILITY & INFRASTRUCTURE USES
COMMERCIAL USES
INDUSTRIAL USES
RESIDENTIAL USES
ACCESSORY USES
TOWN OF SPIDER LAKE — ZONING CODE UPDATE
CIVIC / INSTITUTIONAL USES
AGRICULTURAL & CONSERVATION USES
RECREATION & TOURISM USES
DRAFT LAND USE TABLE | May 2026
POST-ADOPTION
Update internal application forms and procedures
Continue long-term update cadence
Maintain ordinance as a living Zoning document
Update with changes in State law, common variances, etc.
Q1 2026
Task Mar-26 Apr-26 May-26 Jun-26 Jul-26 Aug-26 Sep-26 Oct-26 Nov-26 Dec-26 Jan-27 Feb-27 Mar-27
Phase 1: Uses and Lot Standard
1a: Establish Zoning Districts
1b: Use Table
1c: Supplemental Use Regulations
incl. Short-Term Rentals
1d: Lot Dimensional Standards
1e: Site Design Regulations (e.g.
lighting, landscaping)
Phase 1 Testing and Refinement
Phase 2: Shoreland-Wetland
Zoning
Interim Update Info Session
Hold Info
Session
Phase 3: Subdivision Control
Phase 4: Administrative Procedures
Phase 5: Final Review and Testing
Present to PRC and Town Board
Town of Spider Lake Land Use Ordinance - Project Timeline
Last Updated: March 2026
Q2 2026 Q3 2026 Q4 2026 Q1 2027