PUBLIC WORKS COMMITTEE MEETING MINUTES
Tuesday, September 2nd, 2025 at 5:30 p.m.
Allouez Village Hall, 1900 Libal Street
CALL TO ORDER/ ROLL CALL
Chairperson Leiterman called the meeting to order at 5:32 p.m.
Present: Collison, Genrich, Lefebvre, Leiterman
Excused: Beyler
Also present: Sean Gehin, Jim March
MODIFY/ADOPT AGENDA
Genrich/Collison moved to adopt the agenda as presented. Motion carried.
APPROVAL OF AUGUST 5TH, 2025 MINUTES
Lefebvre/Leiterman moved to approve the August 5, 2025 minutes. Motion carried.
ANNOUNCEMENTS
- None
PUBLIC APPEARANCES
- None
AMENDMENT TO BULK AND BRUSH COLLECTION SCHEDULE
S. Gehin:
- An alternate to the previously presented bulk and brush collection schedule was prepared
by staff addressing citizen’s concerns received at the August 19, 2025, Village Board
Meeting. The alternate schedule includes an added brush collection during the month of
August.
- Two schedule options were present to the Public Works Committee for review and
consideration:
o Proceed with the originally presented schedule or
o Proceed with the alternate schedule adding an additional brush collection in the
month of August for the week of the 17th
- Alternate collection schedule includes:
o Collection of brush for one week in the month of January, April, June, August, and
October.
o Bulk to be collected for one week in the months of May, August, September , and
December .
- The extra week added in the month of August will prevent street repairs from being made
during that time.
- A special collection of brush will be completed if warranted by severe weather .
Lefebvre/Genrich moved to suspend the rules. Motion carried.
Joan Brusky, 2568 S Webster Avenue
- Spoke at the August 19th meeting in regard to the amended brush/bulk collection schedule.
- Owns a large property made up of two parcels that contain a lot of brush items.
- Does not own a truck to transport the brush to the Allouez yard waste site.
- Had requested that another week be added to the brush schedule during the summer
months.
Lefebvre/Genrich moved to return to regular business. Motion carried.
- This is a two-year pilot program that will be monitored and reviewed beginning after the
first six months.
- If the program would not be a success, the Village could return to the current schedule.
Genrich/Collison moved to approve the alternate bulk and brush collection schedule
including the addition of the week in August to be recommended to the Village Board. Motion
carried 3-1. (Lefebvre voted nay).
LIBAL STREET ENGINEERING SERVICES – LEBRUN STREET to HOFFMAN ROAD (CTH XX)
S. Gehin
- The Village of Allouez has received a Surface Transportation Block Grant (STGB) for the
resurfacing of Libal Street from LeBrun Street to Hoffman Road. The estimated construction
cost is $1,424,100 with federal funding of $1,139,280 (80%) and local share of $284,820.
- The program funding does not cover design, r/w acquisition and public utility
improvements (sanitary sewer and watermain).
- In July a request for Proposal (RFP) was sent to a handful of civil engineering consultants to
provide design for the federally funded street improvement project. Those firms included
Ayres, JT Engineering, Graef, Mead and Hunt, and raSmith.
- A selection committee reviewed and ranked proposals in order of preference based on
qualification criteria, not by price.
- RaSmith received the highest score.
- Public Works Committee made a recommendation to the Village Board to proceed with
RaSmith for the scoping and negotiating of an engineering service agreement.
- Once drafted, the engineering agreement will be brought back to the Public Works
Committee and the Village Board for review and approval.
- The street project is to be bid and constructed in 2028.
Collison/Lefebvre moved to recommend the selection of raSmith for the Libal Street
Engineering Services – LeBrun Street to Hoffman Road (CTH XX). Motion carried.
RECYCLING INTERGOVERNMENTAL COOPERATIVE AGREEMENT
S. Gehin
- The Village applies for a DNR recycling grant on an annual basis. In 2025 the Village
received approximately $98,500 from the program.
- To be eligible for the grant a resolution from the Board is required supporting a collective
effort with our neighboring communities to educate residents about the importance of
recycling and their responsibility to do so.
- The grant application is due October 1st.
Leiterman/Collison moved to recommend approval of the Resolution 2025-16, Recycling
Intergovernmental Cooperative Agreement. Motion carried.
2025 LEAK DETECTION SURVEY
a. Water Usage Update
S. Gehin
- From July 21st through August 6th Waterwise Utility Solutions completed a leak detection
survey of the Village’s water distribution system.
- In total there were eleven leaks pinpointed of which one was discovered at a watermain
valve, two hydrants and eight involved water services. The estimated gallon per minute loss
associated with the leaks is 54 GPM. The estimated daily and annual loss of water is roughly
78,000 and 28,000,000 gallons respectively.
- The estimated minimum yearly financial loss if undetected and unfixed is approximately
$125,000.
- The cost to the Village to perform the leak detection survey was approximately $23,425.70.
- The Village Water Utility is currently addressing and repairing the leaks.
- Monthly water loss from the Village’s water distribution system remains above normal
levels. Recently discovered leaks and an unusual number of watermain breaks this summer
have contributed to the higher-than-normal levels of water loss.
- The impact of the recent and planned repairs to leaks and to watermain breaks will take
time to determine. That coupled with the water loss associated with replacement of old
watermain under this year’s Street Reconstruction Project will hamper our ability to
determine now if recent efforts have corrected water loss problem. The Water Department
staff is hoping to know more by November billing.
TDS FIBER NETWORK PROJECT
S. Gehin
- The Village was notified by TDS that work to complete the fiber network in Allouez will
resume this fall and will continue through the end of next year. The TDS fiber project that
started in 2022 was postponed at the end of 2023. At that time, TDS had placed fiber
throughout the south half of Allouez and north of Hwy 172 west of Libal Street to
approximately Allouez Avenue. Roughly 40 miles of fiber has been placed to date.
- TDS estimates another 40 miles of fiber to be placed.
- A meeting was held with TDS on August 21st and the following were discussed:
o Escrow Account Balance – for payment of project expenses
o Overall Project Schedule
o Project Contacts
o Property Owner Notification Expectations
o Avoidance of Public Utilities and precautionary measures
o Locating services (storm laterals)
o Inspection
o Landscape Restoration
- The installation of fiber will begin as soon as the middle of September. TDS will be notifying
impacted residents ahead of construction.
2025 CONSTRUCTION PROJECT UPDATE
S. Gehin
- The following streets will be completed this year:
o Park Drive – St. Francis Drive to Arrowhead Drive
o St. Francis Drive – Langlade Road to S. Webster Avenue
o Crescent Drive – St. Francis Drive to Arrowhead Drive
o Greene Avenue – Libal Street to East River Drive
o Regina Street – Simonet Street to Green Avenue
Project Update:
Park Dr. – St. Francis Dr. to Arrowhead Dr.
Weather permitting the anticipated project schedule is as follows:
Work to Begin – Week of June 2nd
Substantial Completion Date – Mid October
Project Status: Private Side Sanitary Sewer Lateral work to begin early September with concrete
work (curb and driveway aprons) to follow. Project is on schedule.
St. Francis Dr. – Langlade Rd. to S. Webster Ave.
Weather permitting the anticipated project schedule is as follows:
Work to Begin – Week of May 26th
Substantial Completion Date – Mid October
Project Status: Storm sewer main and lateral installation between Crescent Dr and Webster Ave
to begin this week. Private Side Laterals scheduled for early Sept. Project is on schedule.
Crescent Dr. – St. Francis Dr. to Arrowhead Dr.
Weather permitting the anticipated project schedule is as follows:
Work to Begin – Week of May 26th
Substantial Completion Date – Mid October
Project Status: Private Side Sanitary Sewer Lateral work to begin early September with concrete
work (curb and driveway aprons) to follow. Project is on schedule.
Greene Ave. – Libal St. to East River Dr.
Weather permitting the anticipated project schedule is as follows:
Work to Begin – Week of June 9th
Substantial Completion Date – Mid October
Project Status: Contractor to begin road excavation at the East River Drive Intersection. Work
between Greenwald and Libal to restart after utility work on Regina is completed. Project is
slightly behind schedule due to extra work added.
Regina St. – Simonet St. to Greene Ave.
Weather permitting the anticipated project schedule is as follows:
Work to Begin – End of July
Substantial Completion Date – Mid October
Project Status: Sanitary sewer lateral and water service installations to continue with storm
sewer main to follow. Project is slightly behind schedule due to extra work added.
*Webster Avenue Crossing – Webster Ave at Greene Ave
Weather permitting the anticipated project schedule is as follows:
Work completed – Wednesday August 20th
Project Status: Work completed. Turf restoration to be monitored.
Sanitary Sewer Lining Project:
The sanitary sewer lining projects have been completed.
East River Dr. Watermain Relay:
Replacement of the East River Dr. watermain from Riviera Rue to Broadview Dr.
East River Dr. – Riviera Rue to Broadview Dr.
Weather permitting the anticipated project schedule is as follows:
Work completed – July 14th
Project Status: Work completed. Road restoration to be completed under separate contract.
Street Resurfacing Project:
Weather permitting the anticipated project schedule is as follows:
E. Ledgeview St. – S. Webster Ave. to S. Clay St.
Weather permitting the anticipated project schedule is as follows:
Project Anticipated to Begin – 7/14/25
Substantial Completion Date – Early October
Project Status: Lower layer of pavement has been placed surface layer and landscaping to follow.
Gwynn St. – S. Clay St. to Libal St.
Weather permitting the anticipated project schedule is as follows:
Project Anticipated to Begin – 7/14/25
Substantial Completion Date – Early October
Project Status: Paving scheduled for the week of August 25th and landscaping to follow.
Normandy Ln. – Hoffman Rd. to the Cul-De-Sac
Weather permitting the anticipated project schedule is as follows:
Project Anticipated to Begin – 7/14/25
Substantial Completion Date – Early October
Project Status: Minor utility work and concrete work to be completed this week grading, paving and
landscaping to follow.
East River Dr. – Hoffman Rd to Broadview Dr.
Weather permitting the anticipated project schedule is as follows:
Project Anticipated to Begin – 7/14/25
Substantial Completion Date – Early October
Project Status: Minor utility work to be completed this week grading, paving and landscaping to
follow.
Braebourne Ct. – Du Charme Ln. to the Cul-De-Sac
Weather permitting the anticipated project schedule is as follows:
Project Anticipated to Begin – 7/14/25
Substantial Completion Date – Early October
Project Status: Paving scheduled for the week of August 25th and landscaping to follow.
W. Mission St. – West of Du Charme Ln. (200 feet)
Weather permitting the anticipated project schedule is as follows:
Project Anticipated to Begin – 7/14/25
Substantial Completion Date – Early October
Project Status: Paving scheduled for the week of August 25th and landscaping to follow.
FUTURE AGENDA ITEMS
- None
ADJOURNMENT
Collison/Lefebvre moved to adjourn at 6:30 p.m. Motion carried.
Minutes submitted by Kim Siudzinski, Deputy Clerk.