John W. Neumeier
DIRECTOR OF PUBLIC WORKS / CITY ENGINEER
PROJECT 3-25
2025 ALLEY PAVING PROJECT
P u b l i c I n f o r m a t i o n M e e t i n g
June 9th, 2025
Ninth Street / Tenth Street Alley
- Between Crooks Avenue and Eden Avenue
PROJECT AREAS
C I T Y O F
K A U K A U N A
C I T Y O F
K A U K A U N A
PROJECT OVERVIEW
• Remove Existing Pavement and Base
• Relay section of storm sewer
• Remove Sub-Grade Material As-Needed
• Install and Grade Granular Base
• Install Asphalt Pavement
• Replace Concrete Apron/Walk Where Needed
• Add Gravel Shouldering
• Turf Restoration
• The Ninth/Tenth Street Alley was last
reconstructed in the early 1950’s
• There was a storm sewer installed
from Hendricks Avenue to 130 feet
east during the 1950’s alley
reconstruction, by the Bethany
Lutheran Church.
CONSTRUCTION – WHY IS IT NEEDED
C I T Y O F
K A U K A U N A
• The contractors tentative schedule has them
starting the storm sewer replacement, excavation
and stone placement on July 28th on the alley.
• They will first replace the section of storm sewer.
• The contractor will then excavate the alley.
Excavations are 1 foot beyond the proposed edge
of pavement and dug down 16 inched below the
proposed top of the alley.
• A geotextile fabric is laid at the bottom of the
excavation. Stone will be placed on top of the
fabric.
• The stone is graded and compacted.
• Shortly after the stone is graded and compacted,
the paving contractor will pave the alley with
asphalt. The alley will have two mats of asphalt –
a binder mat and a final mat.
CONSTRUCTION – EXCAVATION AND STONE PLACEMENT
C I T Y O F
K A U K A U N A
• RESIDENTIAL ASSESSMENTS
– 8.03(2) ASSESSMENTS
(h) The cost per foot for such assessments shall be
set based on current bid prices and include
reasonable engineering fees.
– Ordinance changing special assessment for alley
paving adopted in 2019. Ordinance now states
property owners are responsible for 2/3 of the project
costs and the City is responsible for 1/3.
6
ASSESSMENT RATES
C I T Y O F
K A U K A U N A
C I T Y O F
K A U K A U N A
ASSESSMENT RATES
Special Assessment Rates for Asphalt Alley Reconstruction
2025 Asphalt Alley Reconstruction
• Alley Between E. 9th Street and E. 10th Street – Crooks Avenue to Main Avenue
• Alley Between W. 9th Street and W. 10th Street - Main Avenue to Eden Avenue
$38.32/ Frontage Foot
(14 feet wide)
Comparison to 2023:
- 2023 Assessment Rate was $34.02 / Frontage Foot (12 feet wide)
- 2023 Average Assessment was $ 2,275.82
Proposed 2025 Average Assessment is $2,435.98
8.03(2) ASSESSMENTS
(i) All special assessments under this section
8.03(2) shall be paid over a period of 10 years or
less. ……. If the City borrowed the money for the
project, the interest rate shall be at the same
interest rate paid by the City plus 1%.
Estimated Interest Rate: 6.0% (5.0% +1%)
8
ASSESSMENT PAYMENTS
C I T Y O F
K A U K A U N A
C I T Y O F
K A U K A U N A
ASSESSMENT PAYMENTS
Special Assessment Timeline
October 2025 • Project is completed.
• Engineering Department measures “as-built” quantities.
November 2025 • Final Special Assessment totals forwarded to Finance Department.
• Special Assessment Invoices sent out to property owners.
• 30 days to pay in full to avoid finance charges.
December 2025 • Any unpaid special assessments appear on property tax bill.
• 1/10th of total assessment plus interest due.
Following Decembers • 1/10th of assessments plus interest due.
REPAIRS AND LIFE EXPECTANCY
The City estimates that hot mix asphalt alleys
should last 15 years. If any surface repairs are
necessary during the life expectancy the repairs
shall be made at the City’s general expense, and
not by special assessment against abutting
property owners.
10
ASSESSMENT POLICIES
C I T Y O F
K A U K A U N A
SPECIAL ASSESSMENT
PUBLIC HEARING
• QUESTIONS/COMMENTS FROM
ALDERPERSONS
• CHAIRPERSON OF BOPW TO OPEN PUBLIC
HEARING TO RECEIVE COMMENTS
• STAFF AVAILABLE AFTER THE BOPW
MEETING FOR INDIVIDUAL DISCUSSIONS
12
SPECIAL ASSESSMENT PUBLIC HEARING
C I T Y O F
K A U K A U N A
THANK YOU
Source: City of Kaukauna website. First collected Oct 15, 2026.