1 25 Concrete Street Paving Public Information Meeting
City of Kaukauna · Outagamie County · meeting of Apr 1, 2025 · Notices
Open the original document More from City of Kaukauna
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Jeff Bodoh
Project Engineer
City of Kaukauna
PROJECT 1-25
2025 CONCRETE STREET PAVING
P u b l i c I n f o r m a t i o n M e e t i n g
April 7, 2025
NEW CONCRETE STREETS
• White Birch Street (Sidewalk)
• Antelope Trail
• Bear Paw Trail
PROJECT AREAS – NEW CONSTRUCTION
C I T Y O F
K A U K A U N A
NEW CONCRETE STREETS
• South Weiler Road
• Campfire Court
• White Wolf Lane
• Snow Goose Way
• Beckett Lane
PROJECT AREAS – NEW CONSTRUCTION
C I T Y O F
K A U K A U N A
NEW CONCRETE STREETS
• Ash Grove Place
• State Street (sidewalk)
PROJECT AREAS – NEW CONSTRUCTION
C I T Y O F
K A U K A U N A
• The area of Antelope Trail, Bear
Paw Trail, Snow Goose Way,
Beckett Lane, White Wolf Lane,
Weiler Road, Campfire Court and
Ash Grove Place was developed
over the past several years. Most
of the lots in this area are built on.
The streets are in need of the
permanent road surface to be
installed, and the remaining
sidewalks need to be constructed.
CONSTRUCTION – WHY IS IT NEEDED
C I T Y O F
K A U K A U N A
The construction will be done in 2 phases. The contractor will complete Phase 1 before starting
Phase 2. This will allow for parking on the streets that are not being worked on and better
access for residents.
Phase 1 Streets: Ash Grove Place, Bear Paw Trail, Snow Goose Way, Beckett Lane, Campfire
Court, and White Wolf Lane
Parking for Phase 1: South Weiler Road, Antelope Trail, White Dove Lane, Haas Road and
White Birch Street
Phase 2 Streets: South Weiler Road, Antilope Trail and White Dove Lane
Parking for Phase 2: Ash Grove Place, Bear Paw Trail, Snow Goose Way, Beckett Lane,
Campfire Court, White Wolf Lane, Haas Road, and White Birch Street
CONSTRUCTION – PHASING
C I T Y O F
K A U K A U N A
• The contractor’s current schedule has them
starting the paving of the first lanes on April 29th
and go to May 7th. Paving of the second lanes is
scheduled to start on May 9th and go to May
16th. Paving the first lanes on Antelope Trail,
Weiler Road and White Dove Lane would start on
July 8th and go to July 15th. The second lanes
would start on July 16th and end on July 23rd.
• The contractor will send out notices at least 24
hours before prepare a street for paving. The
prep work includes setting string line and fine
grading.
• Paving is done one lane at time. The second
lane is not paved until the first lane has cured.
Curing takes about 7 days. Vehicles and
equipment must stay off the concrete while it is
curing.
CONSTRUCTION – CONCRETE STREET PAVING
C I T Y O F
K A U K A U N A
• Sidewalk and driveway apron new construction is
scheduled to start on May 20th for the first phase.
The sidewalk for Antelope, Weiler and White Dove will
start on July 30th. The contractor will excavate, set
forms and place stone for the sidewalk. Typically, a
day or two after placing the stone they will pour the
sidewalk.
• The driveway aprons usually are poured a day or two
after the sidewalk is poured. The contractor needs to
remove the sidewalk forms before they can form and
pour the driveway aprons.
• Vehicles and Large Equipment must stay off newly
poured concrete for 7 days while it cures and
strengthens.
• The 4-inch sidewalk will be installed with a slip form
paver, which is a small paving machine, instead of
forms. The contractor will use a string line like the
street paver to guide the slip form machine. The 6”
sidewalk and driveway aprons will be hand poured
using forms.
CONSTRUCTION – SIDEWALK & DRIVEWAY APRONS
C I T Y O F
K A U K A U N A
• RESIDENTIAL ASSESSMENTS
– 8.03(2) ASSESSMENTS
(h) The cost per foot for such
assessments shall be set based on
current bid prices and include
reasonable engineering fees.
– The cost of paving with asphalt or
concrete for a standard residential street
shall be divided as follows: Abutting
property owners will pay 2/3 of the cost
and the City 1/3.
9
ASSESSMENT RATES
C I T Y O F
K A U K A U N A
C I T Y O F
K A U K A U N A
ASSESSMENT RATES
11
ASSESSMENT RATE HISTORY
C I T Y O F
K A U K A U N A
• RESIDENTIAL ASSESSMENTS
– 8.03(1)(d) Sidewalks
(4) All properties, whether vacant or
improved, abutting streets that are
planned for new pavement or curb and
gutter or replacement of same shall
have sidewalk installed in conjunction
with the street improvement.
12
SIDEWALK ASSESSMENT RATES
C I T Y O F
K A U K A U N A
C I T Y O F
K A U K A U N A
SIDEWALK ASSESSMENT RATES
8.03(2) ASSESSMENTS
(i) All special assessments under this section
8.03(2) shall be paid over a period of 10 years
or less. ……. If the City borrowed the money for
the project, the interest rate shall be at the
same interest rate paid by the City plus 1%.
Estimated Interest Rate: 6.0% (5.0% +1%)
14
ASSESSMENT PAYMENTS
C I T Y O F
K A U K A U N A
C I T Y O F
K A U K A U N A
ASSESSMENT PAYMENTS
Special Assessment Timeline
Late August • Project is completed.
• Engineering Department measures “as-built” quantities.
October 2025 • Final Special Assessment totals forwarded to Finance Department.
• Special Assessment Invoices sent out to property owners.
• 30 days to pay in full to avoid finance charges.
December 2025 • Any unpaid special assessments appear on property tax bill.
• 1/10th of total assessment plus interest due.
Following Decembers • 1/10th of assessments plus interest due.
Corner Lot Credit
• Credit is 30% of frontage on each side up to a
maximum of 50 feet on each side
• Funded by Vehicle Registration Fees
– Lowers Municipal Borrowing for Project
– $10 / year on vehicles registered in Kaukauna
– $145,000 generated in 2024
– 2023 Project Bid Amount =$3,647,601.88
– 2024 Project Bid Amount =$2,081,269.59
– 2025 Project Bid Amount = $2,799,836.49
Parity
• Cul-de-Sac, Bump Out and Eyebrow Lots. Lots on the
outside of curves where more than 75% of the frontage
is concave, the assessable frontage shall be 130% of
the platted frontage.
• If less than 75% of the frontage is concave, the entire
frontage shall be assessed.
16
ASSESSMENT POLICIES
C I T Y O F
K A U K A U N A
REPAIRS AND LIFE EXPECTANCY
The City estimates that hot mix asphalt streets
should last 15 years, and concrete streets
should last 30 years. If any surface repairs are
necessary during the life expectancy the repairs
shall be made at the City’s general expense, and
not by special assessment against abutting
property owners.
17
ASSESSMENT POLICIES
C I T Y O F
K A U K A U N A
C I T Y O F
K A U K A U N A
COMMUNICATION – WEEKLY UPDATES
• EMAIL YOUR CONTACT INFORMATION TO
JBODOH@KAUKAUNA.GOV TO BE PUT
ON THE WEEKLY UPDATE LIST
FREQUENTLY ASKED QUESTIONS
• Will Driveway Access Be Restricted?
– Due to necessary equipment operations, driveways and on-street parking may be limited or
restricted throughout the project. You will need to find alternative parking on side streets.
– Contractor is required to notify residents 24 hours in advance of any driveway obstruction or
street closures
– While construction happens on your street, the road will be closed to traffic. Try to plan
accordingly if you need to come and go during working hours.
– Driveways should be open on a nightly basis once construction has ended for that day, unless
your street, driveway apron or sidewalk across your driveway was recently been paved. Vehicles
and large equipment should stay off new concrete until it has cured and strengthened for 7
days
– If you need special accommodations for parking, please reach out as we may be able to
arrange different parking options. This includes anyone with disabilities, recent surgeries,
expecting mothers, and mothers with newborns that have appointments. Unfortunately, there
is no “one size fits all” for parking and property access. The fewer cars that the contractor has
to work around, the safer it is for everyone and the faster they can get the work done on your
block.
FREQUENTLY ASKED QUESTIONS
• Will My Lawn be Disturbed?
– The grass area between the Sidewalk and the Road (the Terrace) will be disturbed during
construction
– There may be a need for some restoration work on private property depending on sidewalk
construction. New Sidewalk that the grade or slope has changed, may require work on
private property. Usually no more then 3 feet behind the sidewalk.
– The terrace areas along all newly constructed streets will be regraded and restored with
fresh topsoil, grass seed, fertilizer, and erosion mat
– Watering of new grass seed will be the responsibility of the resident. An informational flyer
will be provided outlining best practices for establishing new grass
– Coordinate with the City and the Contractor regarding any decorations, landscaping, and
underground dog fences
– Terrace Restoration costs are included in the Street Assessment
FREQUENTLY ASKED QUESTIONS
• What will happen with Garbage & Recycling Collection?
– The schedule for Garbage and Recycling Collection will not change
– In order to ensure all bins are collected, the City and Contractor will provide extra help
to bring bins toward the garbage truck when not easily accessed
– Place bins in the same spot you normally would leave them
• What will happen with Mail Delivery?
– If you have curbside delivery of mail, please make arrangements with the Kaukauna
Post Office for service during construction. It is the homeowner’s responsibility to
remove and re-install their mailbox. All curbside mailboxes must be removed prior to
installation of the new pavement. If the homeowner does not remove the mailbox, the
contractor will remove it with their construction equipment and lay it on the front lawn.
The contractor will not be responsible for any damage. Please contact Kaukauna Post
Office for guidelines on the installation of mailboxes. Mailboxes can be reinstalled
after the landscape restoration is completed.
FREQUENTLY ASKED QUESTIONS
• Will this Project be Noisy?
– Yes. There will be times where the required construction may be very loud. Saws,
excavators, compacting machines and paving machines will be running frequently
throughout the life of the project
– The Project Requirements related to noise will be followed during construction:
• No construction related noise may be made before 7:00 am or after 6:00 pm, without prior
approval from the Engineer.
• There may be a few nights, after they pave concrete lanes, that the contractor would need to
saw the new concrete after 6:00PM. They should not go later then 10:00 PM.
• Will this Project be Messy?
– Yes. Street Construction is not easy. There will be dirt, mud, dust, equipment, and workers
everywhere. The Contractor will be asked to limit the extent of scattered supplies.
– The Contractor is required to monitor the amount of dust on the project and will be asked to use
means and methods to reduce that dust. The most common practice is the use of a water truck on
site during periods of limited rainfall.
PUBLIC INFORMATION
MEETING
• QUESTIONS/COMMENTS FROM THE PUBLIC
• STAFF AVAILABLE AFTER THE PUBLIC
INFORMATION MEETING FOR INDIVIDUAL
DISCUSSIONS
• YOU CAN CONTACT JEFF BODOH AT
(920) 766-6305 EXT 3 OR AT
JBODOH@KAUKAUNA.GOV WITH QUESTIONS
24
PUBLIC INFORMATION MEETING
C I T Y O F
K A U K A U N A
THANK YOU