Packet
Village of Oregon · Dane County · meeting of Sep 30, 2026 · Agenda packets
Open the original document More from Village of Oregon
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Page 1 of 1
Pursuant to Wis. Stats. § 19.84, notice is hereby given to the public by the Chairperson of the Oregon
Area Fire-EMS District Commission, the Town Chairpersons of the Town of Dunn, Town of Oregon,
and Town of Rutland, and the Village President of Oregon that the following meeting will be held:
Meeting: Joint Meeting of the Oregon Area Fire-EMS District Commission, the Town Boards of
Dunn, Oregon, and Rutland and the Village Board of Oregon
Date: Wednesday, September 30, 2026
Location: Oregon Village Hall – Community Room, 101 Alpine Parkway, Oregon, WI 53575
Time: 6:30 PM
Note: Any person who has a qualifying disability as defined by the Americans with Disabilities Act that requires
the meeting or materials at the meeting to be in an accessible location or format must contact the Village Clerk
at (608) 835 -3118, 101 Alpine Parkway , Oregon, Wisconsin, at least twenty -four (24) hours prior to the
commencement of the meeting so that any necessary arrangements can be made to accommodate each
request.
AGENDA
1) Call to Order and Roll Call – Oregon Area Fire-EMS District Commission, Town Board of Dunn,
Town Board of Oregon, Town Board of Rutland, and Village Board of Oregon.
2) Business (items are for discussion and / or possible action).
a) Review and approval of Oregon Area Fire - EMS District 2027 Budget
i. Review of the Approved 10 Year Capital Improvement Plan.
b) Updates on future fire station building project.
i. Presentation from Tim Higgins.
ii. Presentation by Wendel/Five Bugles Design
iii. Option discussion for next steps moving forward.
3) Public Comment.
4) Announcements.
a) 2028 Budget Joint Meetings planned for Wednesday, July 28, 202 7, and Wednesday,
September 29, 2027, at 6:30 pm in the Oregon Village Hall Community Room.
4) Adjournment of all Boards.
Page 1 of 1
Pursuant to Wis. Stats. § 19.84, notice is hereby given to the public by the Chairperson of the Oregon
Area Fire-EMS District Commission, the Town Chairpersons of the Town of Dunn, Town of Oregon,
and Town of Rutland, and the Village President of Oregon that the following meeting will be held:
Meeting: Joint Meeting of the Oregon Area Fire-EMS District Commission, the Town Boards of
Dunn, Oregon, and Rutland and the Village Board of Oregon
Date: Wednesday, September 30, 2026
Location: Oregon Village Hall – Community Room, 101 Alpine Parkway, Oregon, WI 53575
Time: 6:30 PM
Note: Any person who has a qualifying disability as defined by the Americans with Disabilities Act that requires
the meeting or materials at the meeting to be in an accessible location or format must contact the Village Clerk
at (608) 835 -3118, 101 Alpine Parkway , Oregon, Wisconsin, at least twenty -four (24) hours prior to the
commencement of the meeting so that any necessary arrangements can be made to accommodate each
request.
AGENDA
1) Call to Order and Roll Call – Oregon Area Fire-EMS District Commission, Town Board of Dunn,
Town Board of Oregon, Town Board of Rutland, and Village Board of Oregon.
2) Business (items are for discussion and / or possible action).
a) Review and approval of Oregon Area Fire - EMS District 2027 Budget
i. Review of the Approved 10 Year Capital Improvement Plan.
b) Updates on future fire station building project.
i. Presentation from Tim Higgins.
ii. Presentation by Wendel/Five Bugles Design
iii. Option discussion for next steps moving forward.
3) Public Comment.
4) Announcements.
a) 2028 Budget Joint Meetings planned for Wednesday, July 28, 202 7, and Wednesday,
September 29, 2027, at 6:30 pm in the Oregon Village Hall Community Room.
4) Adjournment of all Boards.
Oregon Fire & EMS District Budget Worksheet - Fire District Page: 1
Period: 11/26 Sep 25, 2026 09:52AM
Report Criteria:
Accounts to include: With balances or activity
Budget note year end periods: Future year
Print FUND Titles
Page and Total by FUND
Print SOURCE Titles
Total by SOURCE
Print COST CATEGORY Titles
Total by COST CATEGORY
All Segments Tested for Total Breaks
2025-25 2026 2026 2027 2027 Pct
Prior year Current year Current year Dept Head FY Adopted Change
Account Number Account Title Actual Budget Actual Budget Budget
GENERAL FUND
INTERGOVERNMENTAL AID
100-43250 FEMA GRANT 59,912.00 .00 .00 59,912.00 .00 .00
100-43251 WI CERTIFIED EXPENDITURE PRGRM .00 35,000.00 .00 18,000.00 .00 48.57-
100-43425 FIRE INS DUES VILLAGE OF OREGO 80,217.15 60,500.00 60,893.48 85,000.00 .00 40.50
100-43426 FIRE INS DUES TOWN OF OREGON 24,272.97 17,600.00 24,976.28 24,000.00 .00 36.36
100-43427 FIRE INS DUES TOWN OF DUNN 12,551.14 8,800.00 13,669.64 13,000.00 .00 47.73
100-43428 FIRE INS DUES TOWN OF RUTLAND 5,316.68 4,400.00 5,585.68 5,000.00 .00 13.64
100-43522 EMS FUNDING ASSISTANCE PROGRA 62,669.26 10,000.00 .00 55,000.00 .00 450.00
100-43528 STATE AID EMERGENCY GOVERMEN .00 1,000.00 .00 1,000.00 .00 .00
Total INTERGOVERNMENTAL AID: 244,939.20 137,300.00 105,125.08 260,912.00 .00 90.03
FINES AND FORFEITURES
100-45110 INSPECTION FEES .00 5,000.00 250.00 5,000.00 .00 .00
Total FINES AND FORFEITURES: .00 5,000.00 250.00 5,000.00 .00 .00
PUBLIC CHARGES FOR SERVICES
100-46100 OTHER PUBLIC CHARGES 5.00 .00 10.00 .00 .00 .00
100-46230 EMS REVENUE 1,818,592.15 1,505,640.00 1,317,278.02 1,650,000.00 .00 9.59
100-46231 BAD DEBT EXPENSES 680,196.31- 1,000,000.00- 944,705.48- 950,000.00- .00 5.00-
100-46235 CPR CLASS REVENUE 1,880.00 2,000.00 720.00 2,000.00 .00 .00
100-46245 RACETRACK REVENUE 20,410.00 22,000.00 8,360.00 23,000.00 .00 4.55
100-46250 EMS SERVICES 4,745.00 14,000.00 760.00 10,000.00 .00 28.57-
Total PUBLIC CHARGES FOR SERVICES: 1,165,435.84 543,640.00 382,422.54 735,000.00 .00 35.20
CHARGES FOR INTERGOVERNMENTAL
100-47200 HIGHWAY RESPONSES 15,491.70 20,000.00 12,389.00 20,000.00 .00 .00
100-47325 VILLAGE OF OREGON 935,011.00 936,350.00 936,350.00 954,267.00 .00 1.91
100-47326 TOWN OF OREGON 252,862.00 253,519.00 253,519.00 250,043.00 .00 1.37-
100-47327 TOWN OF DUNN 137,640.00 149,367.00 149,367.00 151,392.00 .00 1.36
100-47328 TOWN OF RUTLAND 65,108.00 64,016.00 64,016.00 64,808.00 .00 1.24
100-47331 VILLAGE OF OREGON - CAPITAL 113,462.00 155,941.00 155,941.00 203,683.00 .00 30.62
100-47332 TOWN OF OREGON - CAPITAL 30,685.00 42,222.00 42,222.00 53,370.00 .00 26.40
100-47333 TOWN OF DUNN - CAPITAL 16,702.00 24,876.00 16,702.00 32,314.00 .00 29.90
100-47334 TOWN OF RUTLAND - CAPITAL 7,901.00 10,661.00 10,661.00 13,833.00 .00 29.75
Total CHARGES FOR INTERGOVERNMENTAL: 1,574,862.70 1,656,952.00 1,641,167.00 1,743,710.00 .00 5.24
MISCELLANEOUS INCOME
100-48100 INTEREST INCOME 75,238.69 25,000.00 36,119.17 40,000.00 .00 60.00
100-48300 SALE OF PROPERTY 2,335.50 .00 900.00 1,000.00 .00 .00
Oregon Fire & EMS District Budget Worksheet - Fire District Page: 2
Period: 11/26 Sep 25, 2026 09:52AM
2025-25 2026 2026 2027 2027 Pct
Prior year Current year Current year Dept Head FY Adopted Change
Account Number Account Title Actual Budget Actual Budget Budget
100-48400 INSURANCE REFUND .00 .00 49,795.46 .00 .00 .00
100-48500 DONATION 100.00 .00 .00 500.00 .00 .00
100-48505 FIRE STATION DONATION 4,060.00 .00 .00 .00 .00 .00
100-48520 GENERAL DONATIONS 12,520.00 .00 5,750.00 3,000.00 .00 .00
100-48610 MISCELLANEOUS 312.00 .00 2,041.46 2,000.00 .00 .00
Total MISCELLANEOUS INCOME: 94,566.19 25,000.00 94,606.09 46,500.00 .00 86.00
OTHER FINANCING SOURCES
100-49300 UNAPPROPRIATED FB APPLIED .00 216,300.00 .00 .00 .00 100.00-
Total OTHER FINANCING SOURCES: .00 216,300.00 .00 .00 .00 100.00-
PUBLIC SAFETY
100-52200-110 FIRE CHIEF SALARY 114,190.79 117,106.00 79,763.24 119,448.00 .00 2.00
100-52200-111 FIRE OPERATION SALARIES 536,995.83 587,059.00 402,016.60 690,486.00 .00 17.62
100-52200-113 FIRE STRAIGHT TIME 7,444.61 5,000.00 3,671.69 5,000.00 .00 .00
100-52200-114 FIRE OVERTIME 20,840.30 25,000.00 21,896.49 25,000.00 .00 .00
100-52200-131 FIRE FICA 81,314.36 79,975.00 59,177.71 91,335.00 .00 14.20
100-52200-132 FIRE MEDICARE 19,017.31 18,704.00 13,840.00 21,361.00 .00 14.21
100-52200-133 FIRE RETIREMENT 160,077.87 131,526.00 115,188.61 167,916.00 .00 27.67
100-52200-134 FIRE HEALTH INSURANCE 143,503.92 179,577.00 92,612.52 191,754.00 .00 6.78
100-52200-143 FIRE LIFE INS/INC CONTINUATION 1,551.89 1,450.00 975.83 1,922.00 .00 32.55
100-52200-150 EMS MEDICAL DIRECTOR 17,000.04 16,500.00 11,569.70 17,000.00 .00 3.03
100-52200-152 FIRE VOLUNTEER INTERN 7,975.00 20,000.00 6,450.00 20,000.00 .00 .00
100-52200-153 FIRE VOLUNTEER REIMBURSEMENT 576,517.42 500,000.00 442,139.98 500,000.00 .00 .00
100-52200-155 FIRE VOLUNTEER TRAINING REIMB 24,738.98 12,000.00 28,055.51 16,000.00 .00 33.33
100-52200-190 FIRE UNEMPLOYMENT .00 .00 184.11- .00 .00 .00
100-52200-193 FIRE WORKERS COMPENSATION 27,465.75 35,000.00 21,048.05 34,000.00 .00 2.86-
100-52200-210 FIRE CONTRACTED SERVICES 101,346.03 85,000.00 93,146.64 100,000.00 .00 17.65
100-52200-215 FIRE LEGAL 1,662.00 10,000.00 10,576.60 10,000.00 .00 .00
100-52200-216 FIRE AUDIT 10,800.00 8,500.00 10,800.00 11,000.00 .00 29.41
100-52200-227 FIRE CONTINGENCY .00 5,000.00 .00 .00 .00 100.00-
100-52200-310 FIRE OFFICE SUPPLIES 5,582.02 4,500.00 4,564.77 5,500.00 .00 22.22
100-52200-312 FIRE COMPUTERS 8,175.99 4,600.00 .00 5,000.00 .00 8.70
100-52200-322 FIRE BOOKS .00 3,000.00 .00 1,000.00 .00 66.67-
100-52200-325 FIRE DUES 956.04 1,500.00 746.00 1,200.00 .00 20.00-
100-52200-330 FIRE TRAINING 10,427.52 20,000.00 6,562.78 15,000.00 .00 25.00-
100-52200-331 FIRE INTERN ED REIMB. 2,956.84 8,000.00 3,196.03 10,000.00 .00 25.00
100-52200-332 INTERN TRAINING 4,761.24 8,000.00 3,900.71 5,000.00 .00 37.50-
100-52200-335 FIRE PUBLIC EDUCATION 2,282.17 1,500.00 899.94 5,000.00 .00 233.33
100-52200-340 FIRE OPERATING SUPPLIES 90,795.45 50,000.00 61,967.89 95,000.00 .00 90.00
100-52200-341 FIRE UNIFORMS 6,004.84 6,000.00 2,640.02 6,500.00 .00 8.33
100-52200-342 EMS OXYGEN 3,766.85 2,000.00 3,461.22 3,500.00 .00 75.00
100-52200-343 FIRE COMMUNICATION REPAIRS 353.00 4,000.00 .00 2,500.00 .00 37.50-
100-52200-344 EMS CPR SUPPLIES 761.13 .00 468.65 1,000.00 .00 .00
100-52200-350 FIRE REPAIRS & MAINTENANCE 34,553.75 20,000.00 3,028.64 25,000.00 .00 25.00
100-52200-360 FIRE VEHICLE REPAIR SUPPLIES 6,471.83 15,000.00 14,106.37 15,000.00 .00 .00
100-52200-362 FIRE GAS & OIL 24,262.91 18,000.00 21,567.68 25,000.00 .00 38.89
100-52200-363 FEMA GRANT EXPENSE 21,202.78 .00 .00 .00 .00 .00
100-52200-522 FIRE TRUCK INSURANCE 23,899.00 20,000.00 12,816.61 25,000.00 .00 25.00
100-52200-790 EMS FUNDING ASSIST PROGRAM-FA 2,049.02 10,000.00 .00 5,000.00 .00 50.00-
100-52200-793 2% DUES 98,760.65 77,245.00 2,960.45 98,000.00 .00 26.87
100-52200-794 ANNUAL PHYSICALS 6,515.54 8,000.00 6,907.51 8,000.00 .00 .00
100-52200-830 FIRE EQUIPMENT .00 280,000.00 206,241.99 .00 .00 100.00-
100-52200-840 FIRE VEHICLES PURCHASE 340,316.08 80,000.00 843,638.92 283,200.00 .00 254.00
Oregon Fire & EMS District Budget Worksheet - Fire District Page: 3
Period: 11/26 Sep 25, 2026 09:52AM
2025-25 2026 2026 2027 2027 Pct
Prior year Current year Current year Dept Head FY Adopted Change
Account Number Account Title Actual Budget Actual Budget Budget
100-52250-210 BUILDING CONTRACTED SERVICES .00 .00 286.00 .00 .00 .00
100-52250-221 BUILDING GAS & ELECTRIC 29,604.94 32,000.00 24,393.26 32,000.00 .00 .00
100-52250-222 BUILDING TELEPHONE 6,564.90 8,000.00 4,573.17 8,000.00 .00 .00
100-52250-223 BUILDING WATER & SEWER 5,722.65 4,100.00 5,330.80 7,000.00 .00 70.73
100-52250-224 BUILDING MONITORING SYSTEM 430.60 .00 735.75 500.00 .00 .00
100-52250-230 BUILDING MAINTENANCE CONTRACT 6,528.80 8,000.00 6,045.33 8,000.00 .00 .00
100-52250-340 BUILDING OPERATING SUPPLIES 14,888.77 9,000.00 12,211.80 18,000.00 .00 100.00
100-52250-350 BUILDING REPAIRS & MAINTENANCE 40,620.69 15,000.00 55,538.34 25,000.00 .00 66.67
100-52250-524 BUILDING INSURANCE 9,385.00 9,350.00 3,401.20 10,000.00 .00 6.95
100-52250-820 FIRE/EMS BUILDING 17,834.00 20,000.00 12,250.00 20,000.00 .00 .00
Total PUBLIC SAFETY: 2,678,877.10 2,584,192.00 2,737,186.89 2,791,122.00 .00 8.01
GENERAL FUND Revenue Total: 3,079,803.93 2,584,192.00 2,223,570.71 2,791,122.00 .00 8.01
GENERAL FUND Expenditure Total: 2,678,877.10 2,584,192.00 2,737,186.89 2,791,122.00 .00 8.01
Net Total GENERAL FUND: 400,926.83 .00 513,616.18- .00 .00 .00
Net Grand Totals: 400,926.83 .00 513,616.18- .00 .00 .00
Report Criteria:
Accounts to include: With balances or activity
Budget note year end periods: Future year
Print FUND Titles
Page and Total by FUND
Print SOURCE Titles
Total by SOURCE
Print COST CATEGORY Titles
Total by COST CATEGORY
All Segments Tested for Total Breaks
2027 OAFED Proposed Budget Municipal Contributions
(Estimate as of 9/25/2026; need final Department of Revenue CPI-U factor to finalize)
2026 BUDGET 2027 BUDGET
(EST.) DIFFERENCE
Village of Oregon
Operating Contribution 936,350.00 954,267.00 17,917.00
Capital Contribution 155,941.00 203,683.00 47,742.00
Total Village of Oregon Assessed Charges 1,092,291.00 1,157,950.00 65,659.00
Town of Oregon
Operating Contribution 253,519.00 250,043.00 (3,476.00)
Capital Contribution 42,222.00 53,370.00 11,148.00
Total Town of Oregon Assessed Charges 295,741.00 303,413.00 7,672.00
Town of Dunn
Operating Contribution 149,367.00 151,392.00 2,025.00
Capital Contribution 24,876.00 32,314.00 7,438.00
Total Town of Dunn Assessed Charges 174,243.00 183,706.00 9,463.00
Town of Rutland
Operating Contribution 64,016.00 64,808.00 792.00
Capital Contribution 10,661.00 13,833.00 3,172.00
Total Town of Rutland Assessed Charges 74,677.00 78,641.00 3,964.00
TOTAL ASSESSED CHARGES 1,636,952.00 1,723,710.00
$ DiƯerence 86,758.00
% DiƯerence 5.30%
CPI-U + 2% (ESTIMATE) 5.30%
*Percent is based on an estimated CPI-U of 3.3%. Actual value is published at the end of September by State of
Wisconsin. Amounts will be recalculated based on final value to maximize levy limit exception.
Levy Limit Exception Calculation (based on proposed 2027 Budget)
(Estimate as of 9/25/2026; need final Department of Revenue CPI-U factor to finalize)
TOTAL ASSESSED
CHARGES 2026 BUDGET 2027 BUDGET LEVY EXCEPTIONS FOR
WORKSHEET (EST)
Village of Oregon 1,092,291.00 1,157,950.00 65,659.00
Town of Oregon 295,741.00 303,413.00 7,672.00
Town of Dunn 174,243.00 183,706.00 9,463.00
Town of Rutland 74,677.00 78,641.00 3,964.00
Total 1,636,952.00 1,723,710.00 86,758.00
*Municipalities must pass levy exception resolution.
OAFED Budget Calculation Formula
The Oregon Area Fire-EMS District provides fire protection and emergency medical services to the Village of
Oregon and portions of the Towns of Oregon, Dunn, and Rutland. The District’s annual costs are divided
among the municipalities using a formula established in the intergovernmental agreement.
After accounting for other available revenues, the remaining amount of the District budget is allocated
among the municipalities based on two factors:
- 50% is allocated according to equalized property value. Equalized value is a state -calculated
measure of the relative size of each municipality’s property tax base. This portion generally
recognizes the property protected by the District.
- 50% is allocated according to population. This portion generally recognizes the number of residents
receiving emergency medical services.
Each municipality’s percentage of the District budget is therefore the average of its share of the District’s
equalized value and its share of the District’s population.
The formula is as follows:
(PEV / DEV) × (DB / 2) + (PP / DP) × (DB / 2) = Party’sShare of District’s Budget
Here is a breakdown of what each abbreviation in the formula stands for:
- PEV (Party's Equalized Value): This is the equalized value of all property within a specific
municipality's territory that receives fire protection services.
- DEV (District's Equalized Value): This represents the total equalized value of all property within
the entire Fire-EMS District that is furnished with fire protection.
- PP (Party's Population): This is the total population in a specific municipality's territory that
receives emergency medical services.
- DP (District's Population): This is the total population in the entire Fire -EMS District that is
furnished with emergency medical services.
- DB (District's Budget): This is the net annual budget of the District that is assessed to the
municipalities.
The agreement specifies where the data for these calculations must come from:
Equalized Values: The calculation uses the most recently available equalized values from the Wisconsin
Department of Revenue. Only property within the municipality’s territory receiving District fire protection is
included.
Population Values:
The population component is calculated somewhat diƯerently for the Village and the towns:
- For the Village, the agreement uses the most recent Department of Administration population
estimate for the entire Village.
- For the Towns of Oregon, Dunn, and Rutland, the agreement estimates the population within the
EMS service area by multiplying the number of households in that service area by the town’s average
persons per household.
- A town’s average persons per household is calculated by dividing its total DOA population estimate
by the total number of households throughout the town.
(Town Population / TotalTown Households) × Households in Service District = Population Value
This is necessary because only portions of a town may be within the District’s service territory, while
the entire Village is served.
Party Population Worksheet (for Towns)
Towns DOA Population Total
Households
Avg
Persons/HH
EMS-Area
Households
Party
Population (PP)
Town of Oregon 3,123 1,088 2.87 958 2,748
Town of Dunn 4,825 2,162 2.23 696 1,552
Town of Rutland 1,984 769 2.58 282 728
--
Budget Calculation
District Budget (DB) 1,723,710
Party PEV PP Total Party Share Percent
Village of Oregon 2,129,359,300 12,441 1,157,950 67.18%
Town of Oregon 656,770,600 2,748 303,413 17.60%
Town of Dunn 419,238,213 1,552 183,706 10.66%
Town of Rutland 167,184,275 728 78,641 4.56%
Totals 3,372,552,388 17,469 1,723,710 100.00%
Example Calculation (Village of Oregon)
(2,129,359,399 / 3,372,552,388) × (1,723,710 / 2) + (12,441 / 17,469) × (1,723,710 / 2) = 1,157,950
(PEV / DEV) × (DB / 2) + (PP / DP) × (DB / 2) = Party’s Share of District’s Budget
Operating Contribution 2026 Budget 2027 Budget DiƯerence
Village of Oregon 936,350 954,267 17,917
Town of Oregon 253,519 250,043 (3,476)
Town of Dunn 149,367 151,392 2,025
Town of Rutland 64,016 64,808 792
Total 1,403,252 1,420,510 17,258
Capital Contribution 2026 Budget 2027 Budget DiƯerence
Village of Oregon 155,941 203,683 47,742
Town of Oregon 42,222 53,370 11,148
Town of Dunn 24,876 32,314 7,438
Town of Rutland 10,661 13,833 3,172
Total 233,700 303,200 69,500
Total 2027 Operating Contribution 1,420,510
Total 2027 Capital Contribution 303,200
Total 2027 Contribution Required 1,723,710
Municipality Operating Capital Total %
Village of Oregon 954,267 203,683 1,157,950 67.18%
Town of Oregon 250,043 53,370 303,414 17.60%
Town of Dunn 151,392 32,314 183,706 10.66%
Town of Rutland 64,808 13,833 78,641 4.56%
Total 2027 Contribution 1,420,510 303,200 1,723,710 100.00%
Recent Historical Proportionate Share of Costs
Using 2015 as the baseline, the proportionate shares have changed as follows:
Municipality 2015 Share 2026 Share 2027 Share Change, 2015–2027
Village of Oregon 62.15% 66.73% 67.18% +5.03%
Town of Oregon 20.71% 18.07% 17.60% −3.11%
Town of Dunn 11.71% 10.64% 10.66% −1.05%
Town of Rutland 5.43% 4.56% 4.56% −0.87%
OREGON AREA FIRE & EMS
DISTRICT:
STUDY UPDATE
September 30, 2026
TEAM INTRODUCTION:
LAURA EYSNOGLE, RA, CID
Wendel / Five Bugles Design
Architect
• Goals
• Project-to-Date
• Recap:
• Existing Conditions Assessment
• Space Needs Analysis
• Station Location Analysis
• Conceptual Design
PRESENTATION
OUTLINE
GOALS
1. Public safety
• Safe, training, inclusive
2. Protection for our first responders and their families
• Cancer prevention, cardiac risk reduction, suicide reduction
3. Longevity
• Think to now and the future
• Determine if 1 or 2 stations are needed
4. Fiscally responsible
• Is it a need or a want
• Are we doing right by the taxpayer
5. UNITE
• Be a community
• Be part of the community
6. Station should be in concert with Villages’ long-term plan
PROJECT-TO-DATE
WINTER
2025
SPRING
2025
SUMMER
2025
FALL
2025
WINTER
2026
SPRING
2026
SUMMER
2026
FALL
2026
FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
Project Kick-off
Establish goals
GIS Kick-off
Programming
Initial GIS Maps
Initial Concepts
Existing Conditions
Joint Commission Presentation
Re-Group
Additional Concepts
Draft Report Complete
Additional Concepts & GIS Mapping
Additional Concepts & GIS Mapping
Additional
Concept
Joint
Commission
Presentation
We are here:
EXISTING CONDITIONS
• Walk though of existing facilities
• Review floor plans
• Interviews with staff
• Consider:
• IBC (International Building Code)
• IEBC (International Existing Building Code)
Structural Requirements
• ADA (Americans With Disabilities Act)
• NFPA Standards (National Fire Protection
Association)
• Needs of contemporary and future fire
departments
• Could it be renovated?
• Phasing of construction:
o Minimize the impacts and costs of renovations.
o Can it be occupied while under construction?
o Phasing the limits of demolition
o Phasing to maintain existing services and
keeping the bay accessible
o Maintain egress during construction
Existing Conditions Assessment
• Common Fire Deficiencies:
o Overall, undersized:
o Office, storage, dorms, apparatus, etc.
o No clearances around apparatus
o Apparatus doors physically too small
o No personal decontamination areas
o No proper gear / PPE storage
o Not designed for multiple genders
o Dorms
o No dorms
o Spaces converted to dorms – do not meet code
o Lack of visual and audible privacy:
o Office, dorms, toilet/shower rooms
o No Exercise Rooms
o Does not meet ADA compliance
Existing
Conditions
Assessment
BUILDING INFORMATION
• Built in 1966
• Partial demolition and major
building addition in 2002
• Landlocked on a city block
• 19,100 s.f.
• Single-story original building
• Three-story addition
ASSESSMENT
SUMMARY
• Does not meet current IBC
• Does not meet current ADA
• Does not meet current NFPA health
& safety recommendations for
contemporary fire stations
• Does not meet current NFPA turnout
time recommendations
• Some interior & exterior finishes past
useful life; need repair and/or
replacement
• Under-sized for current needs
• Exterior
• Poor site drainage on south side
• Inadequate gutters above apparatus bay
doors
• Damaged stucco
• Water infiltration at stair tower
• Aging overhead doors with limited visibility
• Interior
• Apparatus bay trip hazards
• Numerous ADA and IBC non-compliance
• Entry / exit thresholds
• Door push/pull clearances
• Toilet rooms
• Stair guardrails, handrails, cane
detection deficiencies / non-
compliance
• Dorm walls
CONDITION
SUMMARY
o Training room undersized
o Apparatus bays undersized:
o No clearances around apparatus
o Back-in vs drive-thru safety
o Apron too short
o Ineffective personal decontamination (decon)
areas
o No separate gear / PPE storage
o Responders re-enter app bay after gear laundry
o Inefficient admin layout
FIRE DEPARTMENT - OPERATIONS
o Living spaces distance from PPE causes
increased turnout time
o Dorms
o Do not meet code
o Lack of security
o Overall station / building
o Training room
o Lack of station alerting
o No mental health or quiet spaces
Key Challenges:
SPACE NEEDS ANALYSIS
• Operational
Programming
• Understand HOW you
work
• Confirm space Needs
Analysis
• Wants and Needs
• Planning for the
Future
• 50-Year Building
SPACE NEEDS ANALYSIS
SPACE PROGRAMMED
APPARATUS BAYS 13,230 SF
APPARATUS SUPPORT 4,240 SF
TRAINING 3,046 SF
ADMINISTRATION 4,508 SF
LIVING QUARTERS 7,273 SF
MECHANICAL, ELECTRICAL, SUPPORT 4,844 SF
TOTAL NEW CONSTRUCTION 37,140 SF
SPACE NEEDS ANALYSIS
SPACE PROGRAMMED EXISTING FACILITY
APPARATUS BAYS 13,230 SF 6,132
APPARATUS SUPPORT 4,240 SF 1,204
TRAINING 3,046 SF 593
ADMINISTRATION 4,508 SF 4,985
LIVING QUARTERS 7,273 SF 4,460
MECHANICAL, ELECTRICAL, SUPPORT 4,844 SF 882
TOTAL NEW CONSTRUCTION 37,140 SF 20,644
SPACE NEEDS ANALYSIS
STATION LOCATION
ANALYSIS
WHAT IS RESPONSE TIME?
RESPONSE TIME = TURNOUT TIME + TRAVEL TO INCIDENT
WHY DOES RESPONSE TIME
MATTER?
• NFPA 1710 Standard:
• Sets standard for response times
• Standard for the Organization and Deployment of Fire
Suppression Operations, Emergency Medical
Operations, and Special Operations to the Public by
Career Fire Departments
• FIRE:
• Four personnel arrive within 4-minutes, 90% of the time
• EMS:
• First basic life support (BLS) should arrive within 4-
minutes, 90% of the time
• Typical Considerations:
• Response times
• Property ownership
• Contours
• Railroads
• Streams / rivers
• Federal Wetlands
• FEMA
• Adjacent properties
• Your Unique Considerations:
• Three Towns
• One Village
• Fast population growth
• Automatic Aid with surrounding departments
LOCATION STUDY:
OVERVIEW
LOCATION STUDY:
OVERVIEW
• Considered 13 different properties
• Existing (baseline)
• Four (4) given by the department
• Eight (8) GIS Generated
• Considered hypotheticals for Village growth
• Addresses Removed from Southeast
• Addresses Added to west/northwest
• Ran different scenarios:
• One-station
• Two-station
• Compared coverage to:
• District boundaries as a whole
• Incident locations (2023-2025)
LOCATION STUDY:
OVERVIEW
INCIDENT LOCATIONS: INCIDENT HEAT MAP:
LOCATION STUDY:
BASELINE
BASELINE (CURRENT LOCATION):
Positives:
• Department-Owned
• Excellent Response Times
• Not in floodplain or Wetlands
• In downtown (good community
connection)
Negatives:
• Landlocked
• Very small site (0.3 acres)
RESPONSE TIMES:
BASELINE
EXISTING STATION
0-2 Min. 2-4 Min. 0-4 Min.
Total
Total District
Boundary 1.6% 6.5% 8.1%
Total
Incident
Calls
21.1% 42.4% 63.5%
BEST SINGLE-STATION SCENARIO
FOR INCIDENT LOCATIONS.
RESPONSE TIMES:
BEST TWO-STATION SCENARIO
0-2 Min. 2-4 Min. 0-4 Min.
Total
Total District
Boundary 4.3% 12.9% 17.2%
Total
Incident
Calls
31% 41% 72%
RESPONSE TIMES:
ONE VS. TWO STATIONS
0-2 Min. 2-4 Min. 0-4 Min.
Total
Total District
Boundary 4.3% 12.9% 17.2%
Total
Incident
Calls
31% 41% 72%
0-2 Min. 2-4 Min. 0-4 Min.
Total
Total District
Boundary 1.6% 6.5% 8.1%
Total
Incident
Calls
21.1% 42.4% 63.5%
ONE-STATION: TWO-STATION:
Increase coverage of:
• 9.1% Total district boundary
• 8.5% Total incident calls
RESPONSE TIMES:
HYPOTHETICAL CLOSURES –
ADDRESSES REMOVED FROM
SENIOR LIVING CENTER
0-2 Min. 2-4 Min. 0-4 Min.
Total
Existing
Station,
Removal of
Sr. Living
Center
17% 37.9% 54.9%
Figure 13A,
GIS Site 7:
Total
Incident
Calls
16.7% 45.5% 62.2%
FIGURE 13A, GIS SITE 7: BMO Harris Bank Location
RESPONSE TIMES:
HYPOTHETICAL GROWTH –
ADDRESSES ADDED TO WEST
SIDE OF VILLAGE
0-2 Min. 2-4 Min. 0-4 Min.
Total
Total
Incident
Calls
19.5% 46.1% 65.6%
FIGURE 14A, GIS SITE 8:
LOCATION REMAINS WITHIN 1-
BLOCK OF EXISTING STATION
SITE ANALYSIS
STUDY
CONCLUSION:
July 2025:
• No conclusions have been made at
this time.
• Need to determine:
• Location for:
• Response times
• Large enough for needs
• Quantity of stations
UPDATE SEPTEMBER 2026:
• Quantity of stations: 1
• Location: At or within two blocks of
existing station
CONCEPTUAL DESIGN
• Show relationships between
spaces / departments
• Represent approximate sizes
• Colors represent each
department
• Full-size concept plans are in
appendix of report
CONCEPTUAL DESIGN
TOP 3 HEALTH & SAFETY CONCERNS
ADDRESSED IN NEW FACILITIES:
STATION & DEPARTMENT
CONSIDERATIONS:
CONCEPTUAL DESIGN:
RESPONDER SAFETY
Large fitness rooms,
fitness programs.
Dividing the Station
with Hot and Cold
Zones
• Hot / Cold Zones
• Properly pressurizing mechanical
systems.
• Proper gear storage
• Shower within the Hour
• Large fitness room
• Station alerting mechanisms
• Response lighting controls
• Creating comfortable home-like spaces
• Decompression areas
• Fitness room
1. Cardiac Arrest
2. Cancer
3. Mental Health
CONCEPTS
CONSIDERED
9 CONCEPTS IN 8 SCENARIOS:
• New Construction
• Renovation/Additions
• Existing Station with Annex Bays
• Two-Station Scenario
Concepts Considered
• Concept 1:
• NC, Existing location & Village Hall site
• Concept 2:
• NC, Existing location & parking to north
• Concept 3:
• NC, New site
• Concept 4:
• 2-Stations, Both new sites
• Concept 5:
• Full Renovation, new bays, 3rd floor over
bays
• Concept 6:
• Detached bays on adjacent property
• Concept 7:
• 1st floor bare-bones renovation
• Concept 8:
• Renovation of floors 1 & 2, Detached
bays on adjacent property.
• Concept 9:
• NC, Existing location & Village Hall site
Goal
Yes, Partially, No
1 2 3 4 5 6 7 8 9
Change in Response Times *
Public Safety
Safe, training, Inclusive
Protection for first responders
Cancer prevention, cardiac risk reduction, mental health
Longevity
Now & Future
Fiscally Responsible
Need vs want
Doing right by taxpayer?
UNITE
Be a community, part of the community
In concert with Villages long-term plan?
CONCEPTUAL
DESIGN:
1ST FLOOR RENOVATION
ONLY
Concept 7
• No changes to buildings
exterior
• Response remains on Spring
Street
CONCEPTUAL DESIGN
OVERALL
• Renovations to 1st floor & 2nd floor only
• No changes to 3rd floor or bays
CONCEPTUAL DESIGN
OVERALL
FIRST FLOOR:
• Administration
• Personal decon
• Apparatus
support
• Watch office
• Convert public toilets to gear lockers
• Renovate and expand personal-
decon
• Create toilet from bays
• Create larger watch/dispatch Room
CONCEPTUAL DESIGN
OVERALL
SECOND FLOOR:
• Administration
• Convert conference room
into two offices
CONCEPTUAL DESIGN
OVERALL
Goal
Yes,
Partially,
No
Change in Response Times Partially
Public Safety
Safe, training, Inclusive
Partially
Protection for first responders
Cancer prevention, cardiac risk reduction,
suicide reduction
Partially
Longevity
Now & Future
No
Fiscally Responsible
Need vs want
Doing right by taxpayer?
UNITE
Be a community, part of the community
In concert with Villages long-term plan?
PROS:
• Gear off bay floors
• Improved personal decon
• Larger watch office
• Stays within the current
footprint
CONS:
• Dorms:
• Remain non-code compliant
• Remain furthest point of travel for
response
• Bays:
• Full
• Undersized for contemporary apparatus
• Remain as back-ins
• Safety:
• Numerous trip hazards
• No training
• Does not increase size of:
• Fitness
• Training room
• Loss of public toilet rooms
• Operational efficiency is decreased
OPINION OF PROBABLE
COSTS
CONCEPT –
BARE-BONES
RENOVATION
Site Acquisition $0
Building Construction Costs $784,455
Furniture, Fixtures, & Equipment (FFE) $37,456
Communication & Technology $15,000
Professional & Legal Fees $132,668
TOTAL $969,579
Opinion of Probable Costs
Ask of the Joint Commission:
How are we moving forward?
• Bare-bones/Band-Aid approach?
• Expand outside of current footprint?
• Village Hall?
• New construction, or renovation & addition
• Relocate?
• Potential consolidation?
QUESTIONS?
Thank you.
CONCEPTUAL
DESIGN:
DOWNTOWN SITE
PARKING
RESPONSE
MAIN ENTRY
• New Construction
• Demo’s:
• Existing fire station
• Former Village Hall
• Two-story
CONCEPTUAL DESIGN
OVERALL
FIRST FLOOR:
• Training
• Administration
• Personal decon
• Apparatus
support
• Watch office
• Apparatus bays
CONCEPTUAL DESIGN
OVERALL
FIRST FLOOR
COMMUNITY ZONE:
• Training room
• Voting
• Public Toilets
• Walk-in Med Check
• Safe-Haven Baby
Box
COMMUNITY
ZONE
CONCEPTUAL DESIGN
OVERALL
SECOND FLOOR:
• Living quarters:
• Dorms
• Toilet/showers
• Kitchen
• Living
• Day room
• Mezzanine
CONCEPTUAL DESIGN
OVERALL
Goal
Yes,
Partially,
No
Public Safety
Safe, training, Inclusive
Yes
Protection for first responders
Cancer prevention, cardiac risk reduction,
suicide reduction
Yes
Longevity
Now & Future
Yes
Fiscally Responsible
Need vs want
Doing right by taxpayer?
UNITE
Be a community, part of the community
In concert with Villages long-term plan?
PROS:
• Safety:
• Proper clearances around
apparatus
• Code compliant facility
• Complete decon
• Training:
• Increased training room
• Ability for interior & exterior
training props & tower
• Community:
• Community zone with
toilets, training room, and
med. check
• Long-term solution
CONS:
• Higher cost than minimal
renovation
• Would require Village Hall
property
• Most bays would remain
as back-in
• Will need to relocate
during construction
CONCEPTUAL
DESIGN:
RENOVATION &
DETACHED BAYS PARKING
RESPONSE
MAIN ENTRY
• Partial renovation of existing
multi-story portion of fire
station
• Demo of existing apparatus
bays
• New Construction of
apparatus bays
• Support bays across the
street
• Two-Buildings:
• Primary station: Three-
stores
• Support bays: Single-
story with small
equipment platform
CONCEPTUAL
DESIGN:
RENOVATION &
DETACHED BAYS PARKING
RESPONSE
MAIN ENTRY
ITEMS OF NOTE:
• Apparatus divided by street is:
• Unsafe for responders and
community.
• Inefficient for operations.
• 3rd Floor dorms will remain out of
code compliance.
• 3rd floor dorms remain a long
response time.
• Training room remains undersized
for department.
• Plan relies on purchase of
neighboring property.
• Costs to relocate any below grade
infrastructure is unknown.
CONCEPTUAL DESIGN
OVERALL
FIRST FLOOR:
• Administration
• Personal decon
• Apparatus
support
• Watch office
• Apparatus bays
CONCEPTUAL DESIGN
OVERALL
SECOND FLOOR:
• Administration
• Personal decon
• Mechanical
THIRD FLOOR:
• Existing to
remain. No work
to be completed
CONCEPTUAL DESIGN
OVERALL
Goal
Yes,
Partially,
No
Public Safety
Safe, training, Inclusive
Partially
Protection for first responders
Cancer prevention, cardiac risk reduction,
suicide reduction
Partially
Longevity
Now & Future
No
Fiscally Responsible
Need vs want
Doing right by taxpayer?
UNITE
Be a community, part of the community
In concert with Villages long-term plan?
PROS:
• Gear off bay floors
• Improved personal decon.
• Larger watch office,
located between bays
• Stays within the current
footprint
• New bays will provide
better clearances around,
and will accommodate
contemporary apparatus
• Removes trip-hazards in
existing bays
CONS:
• Dorms will remain non-
code compliant
• Dorms remain furthest
point of travel for
response
• Bays:
• Full
• Remain as back-ins
• Does not increase size of:
• Fitness
• Training room
• Additional Bays across
the street is a safety
concern
CONCEPTUAL
DESIGN:
RENOVATION & NEW BAYS
OVERVIEW:
• Demo of existing bays
• New construction of bays
• Full renovation of 1st and 2nd
floors
• Full renovation and extension
of 3rd floor
ITEMS OF NOTE:
• New bays will no house all
apparatus
• Would require additional
bays to south (village
hall property)
PARKING
MAIN
ENTRY
RENOVATE
NEW
CONSTRUCTION
FIRE STATION
PROPERTY LINE
VILLAGE HALL
PROPERTY LINE
PROPOSED
ADDITIONAL BAYS
NEW BAYS
RENOVATE THREE-
STORY STRUCTURE
CONCEPTUAL DESIGN
OVERALL
FIRST FLOOR:
• Administration
• Personal decon
• Apparatus
support
• Watch office
• Apparatus bays
PROGRAMMED SPACES THAT
DO NOT FIT:
CONCEPTUAL DESIGN
OVERALL
SECOND FLOOR:
• Living quarters:
• Dorms
• Toilet/showers
• Kitchen
• Living
• Day room
• Mezzanine
CONCEPTUAL DESIGN
OVERALL
THIRD FLOOR:
• Living quarters:
• Dorms
• Toilet/showers
• Kitchen
• Living
• Day room
• Training
• Administration
CONCEPTUAL DESIGN
OVERALL
Goal
Yes,
Partially,
No
Public Safety
Safe, training, Inclusive
Yes
Protection for first responders
Cancer prevention, cardiac risk reduction,
suicide reduction
Yes
Longevity
Now & Future
Partially
Fiscally Responsible
Need vs want
Doing right by taxpayer?
UNITE
Be a community, part of the community
In concert with Villages long-term plan?
PROS:
• Safety:
• Code compliant facility
• Complete decon
• Training:
• Increased training room
• Ability for interior & exterior
training props & tower
• Long-term solution
• Can remain on existing
property
CONS:
• Higher cost than minimal
renovation
• Bays would remain as
back-in
CONCEPTUAL DESIGN:
GENERIC SITE
PARKING
RETURN
APRON
RESPONSE
APRON
MAIN
ENTRY
WATER
RETENTION
FUTURE
TRAINING
CONCEPTUAL DESIGN
OVERALL
FIRST FLOOR:
• Training
• Administration
• Personal decon
• Apparatus
support
• Watch office
• Apparatus bays
CONCEPTUAL DESIGN
OVERALL
SECOND FLOOR:
• Living quarters:
• Dorms
• Toilet/showers
• Kitchen
• Living
• Day room
• Mezzanine
SPACE PROGRAMMED CONCEPT –
NEW
CONSTRUCTION
CONCEPT –
RENOVATION &
NEW BAYS
CONCEPT –
RENOVATION &
DETACHED BAYS
APPARATUS BAYS 13,230 SF 12,255 SF 7,405 SF* 10,110 SF
APPARATUS SUPPORT 4,240 SF 4.745 SF 3,235 SF 6,060 SF
TRAINING 3,046 SF 2.910 SF 2,510 SF 1,030 SF
ADMINISTRATION 4,508 SF 3,720 SF 4,120 SF 1,630 SF
LIVING QUARTERS 7,273 SF 6.235 SF 6,300 SF 4,205 SF
MECHANICAL, ELECTRICAL,
SUPPORT
4,844 SF 5,845 SF 6,390 SF 3,830 SF
TOTAL NEW CONSTRUCTION 37,140 SF 35,710 SF 29,960 SF* 26,865 SF
SPACE NEEDS ANALYSIS vs CONCEPT
* DOES NOT INCLUDE ADDITIONAL BAYS PROPOSED ON VILLAGE HALL SITE.
Concepts Considered
• Concept 1:
• NC, Existing location & Village Hall site
• Concept 2:
• NC, Existing location & parking to north
• Concept 3:
• NC, New site
• Concept 4:
• 2-Stations, Both new sites
• Concept 5:
• Full Renovation, new bays, 3rd floor over
bays
• Concept 6:
• Detached bays on adjacent property
• Concept 7:
• 1st floor bare-bones renovation
• Concept 8:
• Renovation of floors 1 & 2, Detached
bays on adjacent property
• Concept 9:
• NC, Existing location & Village Hall site
Goal
Yes, Partially, No
1 2 3 4 5 6 7 8 9
Change in Response Times:
No NO
YES -
LONGER-
RESPONSE
YES –
SHORTER
RESPONSE
WITH 2
STATIONS
NO
YES –
LONGER DUE TO
DISTANCE TO
APPARATUS
NO
YES –
LONGER DUE TO
DISTANCE TO
APPARATUS
NO
Public Safety
Safe, training, Inclusive
YES YES YES YES PARTIAL PARTIAL PARTIAL PARTIAL YES
Protection for first responders
Cancer prevention, cardiac risk reduction, suicide reduction
YES YES YES YES YES PARTIAL PARTIAL PARTIAL YES
Longevity
Now & Future
YES YES YES YES YES NO NO PARTIAL YES
Fiscally Responsible
Need vs want
Doing right by taxpayer?
UNITE
Be a community, part of the community
In concert with Villages long-term plan?
Opinion of Probable Costs $21.35M $18.53M $20.41M $25.19M $16.65M $1.85M $1M $6.08M
+
$2.90M
$21.52M
CONCEPT –
NEW
CONSTRUCTION
CONCEPT –
RENOVATION & NEW
BAYS
CONCEPT –
RENOVATION &
DETACHED BAYS
Site Acquisition $0 $0 $70,000
Building Construction Costs $18,220,679 $13,845,149 $7,031,194
Furniture, Fixtures, & Equipment (FFE) $712,724 $559,580 $274,607
Communication & Technology $195,000 $195,000 $215,000
Professional & Legal Fees $2,391,878 $2,049,445 $1,389,952
TOTAL $21,520,281 $16,649,174* $8,980,753
Opinion of Probable Costs
* DOES NOT INCLUDE ADDITIONAL BAYS PROPOSED ON VILLAGE HALL
SITE, OR DEMO OF VILLAGE HALL STRUCTURE
Concepts
(Estimate)
Schematic
Designs
(Estimate)
Construction
Documents
Bidding
Construction
Occupancy
We Are
Here:
WHAT’S NEXT?:
Design
Development
(Estimate)
Source: Village of Oregon website. First collected Oct 16, 2026.