Packet
Village of Oregon · Dane County · meeting of Sep 22, 2026 · Agenda packets
Open the original document More from Village of Oregon
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
h
101 Alpine Parkway Oregon, WI 53575 | Phone: (608) 835-3118 | Fax: (608) 835-6503
www.oregonwi.gov | Find us on Facebook!
PUBLIC NOTICE
Pursuant to Wis. Stat. § 19.84, notice is hereby given to the public by the Chairperson of the Public
Works & Utilities Committee, that the following meeting will be held:
Meeting: Public Works & Utilities Committee Location: Village Hall
Date: Tuesday, September 22, 2026 101 Alpine Parkway
Time: 5:00 PM Oregon, WI 53575
f
Note: Any person who has a qualifying disability as defined by the Americans with Disabilities Act that requires the
meeting or materials at the meeting to be in an accessible location or format must contact the Village Clerk at (608) 835-
3118, 101 Alpine Parkway, Oregon, Wisconsin, at least twenty-four (24) hours prior to the commencement of the meeting
so that any necessary arrangements can be made to accommodate each request.
Notice is hereby given that a majority of the Village Board of the Village of Oregon is expected to be present at this meeting
to gather information about subjects over which they have decision-making responsibility. This constitutes a meeting of
the Village Board of the Village of Oregon pursuant to State ex rel. Badke v. Greendale Village Board, 173 Wis. 2d 553, 494
N.W. 2d 408 (1993) and must be noticed as such although the Village Board will not take any formal action at this meeting.
Page 1 of 1
AGENDA
1) Call to Order.
2) Roll Call.
3) Approval of August 25, 2026 meeting minutes if correct, and correction of mistakes, if any (staff
recommendation: motion to approve as presented).
4) Public Appearances, Comments, and Communications (items are for discussion and / or possible
action).
a) Public Comment. This part of the agenda allows members of the public to provide information to
the Public Safety Committee, including items both on and off the agenda. Under the Open Meetings
Law, this agenda item allows the Board to receive information, and to ask questions of a presenter
to facilitate a better understanding of the information. Board members may discuss procedural
matters relating to the information, such as whether the information should be directed to staff,
referred to a committee, or placed on a future Board agenda. However, Board members may not
expand their discussion beyond such procedural matters. Fifteen (15) minutes will be provided for
this item with a three (3) minute maximum per speaker; otherwise, the agenda will proceed as
posted. (This note may or may not be read at meetings.)
5) Reports from Village Staff
a) Status of Public Works Projects.
6) Business (items are for discussion and / or possible action).
a) Review request from Ruekert & Mielke, Inc. for amendment to Task Order No. 2023-03
(East Lincoln Street Reconstruction Project Engineering Services)(staff recommendation:
motion to recommend to the Village Board approval as presented).
b) Discussion of proposed logo art to be added to the South Standpipe and Lincoln Road
Tower above-ground water storage facilities with the 2027 recoating project.
Page 2 of 2
7) Future Agenda Items.
8) Adjournment.
Members: Tim Higgins (Chairperson), Tom Kirchdoerfer, and Paige Knipfer.
h
101 Alpine Parkway Oregon, WI 53575 | Phone: (608) 835-3118 | Fax: (608) 835-6503
www.oregonwi.gov | Find us on Facebook!
PUBLIC NOTICE
Pursuant to Wis. Stat. § 19.84, notice is hereby given to the public by the Chairperson of the Public
Works & Utilities Committee, that the following meeting will be held:
Meeting: Public Works & Utilities Committee Location: Village Hall
Date: Tuesday, September 22, 2026 101 Alpine Parkway
Time: 5:00 PM Oregon, WI 53575
f
Note: Any person who has a qualifying disability as defined by the Americans with Disabilities Act that requires the
meeting or materials at the meeting to be in an accessible location or format must contact the Village Clerk at (608) 835-
3118, 101 Alpine Parkway, Oregon, Wisconsin, at least twenty-four (24) hours prior to the commencement of the meeting
so that any necessary arrangements can be made to accommodate each request.
Notice is hereby given that a majority of the Village Board of the Village of Oregon is expected to be present at this meeting
to gather information about subjects over which they have decision-making responsibility. This constitutes a meeting of
the Village Board of the Village of Oregon pursuant to State ex rel. Badke v. Greendale Village Board, 173 Wis. 2d 553, 494
N.W. 2d 408 (1993) and must be noticed as such although the Village Board will not take any formal action at this meeting.
Page 1 of 1
AGENDA
1) Call to Order.
2) Roll Call.
3) Approval of August 25, 2026 meeting minutes if correct, and correction of mistakes, if any (staff
recommendation: motion to approve as presented).
4) Public Appearances, Comments, and Communications (items are for discussion and / or possible
action).
a) Public Comment. This part of the agenda allows members of the public to provide information to
the Public Safety Committee, including items both on and off the agenda. Under the Open Meetings
Law, this agenda item allows the Board to receive information, and to ask questions of a presenter
to facilitate a better understanding of the information. Board members may discuss procedural
matters relating to the information, such as whether the information should be directed to staff,
referred to a committee, or placed on a future Board agenda. However, Board members may not
expand their discussion beyond such procedural matters. Fifteen (15) minutes will be provided for
this item with a three (3) minute maximum per speaker; otherwise, the agenda will proceed as
posted. (This note may or may not be read at meetings.)
5) Reports from Village Staff
a) Status of Public Works Projects.
6) Business (items are for discussion and / or possible action).
a) Review request from Ruekert & Mielke, Inc. for amendment to Task Order No. 2023-03
(East Lincoln Street Reconstruction Project Engineering Services)(staff recommendation:
motion to recommend to the Village Board approval as presented).
b) Discussion of proposed logo art to be added to the South Standpipe and Lincoln Road
Tower above-ground water storage facilities with the 2027 recoating project.
Page 2 of 2
7) Future Agenda Items.
8) Adjournment.
Members: Tim Higgins (Chairperson), Tom Kirchdoerfer, and Paige Knipfer.
h
101 Alpine Parkway Oregon, WI 53575 | Phone: (608) 835-3118 | Fax: (608) 835-6503
www.oregonwi.gov | Find us on Facebook!
PUBLIC NOTICE
Pursuant to Wis. Stat. § 19.84, notice is hereby given to the public by theChairperson of the Public
Works & Utilities Committee, that the following meeting will be held:
Meeting: Public Works & Utilities Committee Location: Village Hall
Date: Tuesday, August 25, 2026 101 Alpine Parkway
Time: 5:00 PM Oregon, WI 53575
f
Note: Any person who has a qualifying disability as defined by the Americans with Disabilities Act that requires the
meeting or materials at the meeting to be in an accessible location or format must contact the Village Clerk at (608) 835-
3118, 101 Alpine Parkway, Oregon, Wisconsin, at least twenty-four (24) hours prior to the commencement of the meeting
so that any necessary arrangements can be made to accommodate each request.
Notice is hereby given that a majority of the Village Board of the Village of Oregon is expected to be present atthis meeting
to gather information about subjects over which they have decision-making responsibility. This constitutes a meeting of
the Village Board of the Village of Oregon pursuant to State ex rel. Badke v. Greendale Village Board, 173 Wis. 2d 553, 494
N.W. 2d 408(1993) and must be noticed as such although the Village Board will not take any formal action at this meeting.
To be Approved 09-22-2026 Page 1 of 4
MEETING MINUTES
1) Call to Order.
Public Works Chair Tim Higgins called the Public Works & Utilities Committee Meeting to order
at 5:00 p.m. on Tuesday, August 28, 2026.
2) Roll Call.
Present: Tim Higgins, and Tom Kirchdoerfer.
Absent: Paige Knipfer.
Also Present: Public Works Director Lauren Striegl, Civil Engineer Rich Koceja, and Deputy
Clerk Peggy Haag.
3) Approval of the July 28, 2026, meeting minutes if correct, and correction of mistakes, if any (staff
recommendation: motion to approve as presented).
Kirchdoerfer moved, seconded by Higgins, to approve July 28, 2026, meeting minutes.
Motion carried 2-0.
4) Public Appearances, Comments, and Communications (items are for discussion and / or possible
action).
a) Public Comment. This part of the agenda allows members of the public to provide information to
the Public Safety Committee, including items both on and off the agenda. Under the Open Meetings
Law, this agenda item allows the Board to receive information, and to ask questi ons of a presenter
to facilitate a better understanding of the information. Board members may discuss procedural
matters relating to the information, such as whether the information should be directed to staff,
referred to a committee, or placed on a futur e Board agenda. However, Board members may not
expand their discussion beyond such procedural matters. Fifteen (15) minutes will be provided for
3
To be Approved 09-22-2026 Page 2 of 4
this item with a three (3) minute maximum per speaker; otherwise, the agenda will proceed as
posted. (This note may or may not be read at meetings.)
There was no discussion.
5) Reports from Village Staff
a) Status of Public Works Projects.
Director Striegl reviewed the memorandum dated August 25, 2026, included in the meeting
packet, regarding the current status of Public Works projects.
The Alpine Street project is progressing, with asphalt scheduled for September 4. Staff
continues to coordinate with the School District to maintain bus access through the area
while school is in session. The intersection will operate as a four -way stop an d remain
closed to regular traffic. Staff will assist with traffic control during the first week.
Once the asphalt is completed and the signal equipment is installed, the intersection will
operate as a flashing -red four-way stop. The City of Madison will program the signals,
which is expected to take approximately two to three weeks. Signal poles are a nticipated
to be installed next week. The signal cabinets are still awaiting delivery and will require a
three-day waiting period before installation.
Regular traffic will continue to be discouraged from using the area. Staff will post an update
on Facebook, and the Police Department has been notified of the traffic restrictions.
The Lincoln Street project is not as far along as Alpine Street but is a larger project. Staff
continues to coordinate with the School District regarding bus and parent access. Oak
Street will need to remain open and passable as an alternative route. Cross ing guard
locations may be adjusted early in the school year. Staff will also explore opening the
Soden Street intersection earlier than currently anticipated.
The School District is working on a pedestrian detour, and staff will continue to coordinate
with the District regarding traffic and pedestrian access during construction.
6) Business (items are for discussion and / or possible action).
a) Review and consider approval of the 2027 – 2036 Capital Improvement Plans for Public
Works, Sewer Utility and Water Utility (staff recommendation: motion to recommend to
the Village Board approval as presented).
Staff presented the proposed 2027–2036 Capital Improvement Plans (CIPs) for Public
Works, Sewer Utility, and Water Utility. The Committee reviewed the proposed projects
and discussed the following items.
Netherwood Road drainage: The Committee discussed previous flooding concerns
involving the Alpine Dairy Land property northwest of Cusick Street and
Netherwood Road. Staff explained that the “Lerner Lateral” and “Cusick Parkway
SW Improvements” projects were included in the 2026–2035 CIP to address flooding
experienced in 2018. Options included improving drainage through Lerner Park or
installing an underground system; however, due to extensive wetlands and
discussions with DNR, the projects as proposed were unlikely to receive approval.
Staff has therefore proposed removing the projects from the CIP. The area remains
vulnerable to flooding during wet years and heavy rain events. The Committee also
To be Approved 09-22-2026 Page 3 of 4
discussed the possibility of a detention pond or other stormwater infrastructure if the
property were acquired or annexed.
Netherwood Road improvements: The CIP includes $130,000 for engineering
related to Netherwood Road. The Committee discussed resurfacing the southern half
of Featherwood Drive and potential improvements to the north side. Concerns were
raised about changing the character of the area from its existing rural nature. The
Committee also discussed coordinating the timing of improvements at Netherwood
Road and County CC.
Bergamont traffic circles: The traffic circles have been in the CIP for
approximately three years and are approximately 25 years old. Staff noted that the
circles are showing their age and that some residents have expressed concerns about
their appearance. A traffic engineer may recommend replacing the circles with a
four-way stop; however, the estimated cost would be similar. Higgins expressed a
preference for retaining the traffic circles.
Leaf vacuum truck: The CIP includes funding for an additional leaf vacuum truck
which staff anticipates will be needed by 2030.
Neighborhood street and utility improvements: The Committee discussed the
significant infrastructure needs in older areas of the Village. Many of the street
projects are being driven by the need to replace aging water and sewer infrastructure,
including older clay tile sewer.
Wolfe Street/County Highway CC: The Committee discussed the proposed projects
and Dane County participation. Dane County’s contribution is expected to be
minimal because no utilities are involved, leaving the Village responsible for most
project costs, including approximately 50% of the municipal portion of local
stormwater improvements. The Village may also be responsible for stormwater
infrastructure and culvert costs associated with Highway MM. Higgins expressed
concern about the Wolfe Street/Highway CC and Netherwood projects occurring at
the same time.
Sidewalk costs: The Committee discussed the Village's current sidewalk cost-
sharing policy and whether a greater portion of sidewalk costs should be assessed to
adjacent property owners. Staff noted that the Village's current policy is relatively
generous compared with other communities. The issue may return to the Committee
for further consideration given current financial pressures.
Village Hall solar project: The Committee discussed the potential installation of
solar panels at Village Hall. The discussion included the age and remaining life of the
roof, estimated at approximately 10–15 years, as well as the potential cost of
reinforcing the roof structure, future utility rate increases, and the building's energy
usage. Staff noted that there are currently several unknowns regarding the structural
requirements and project costs.
Higgins recommended removing the solar project from the 2027 CIP and moving it to
2030. He noted that the current payback period is too long and that there are no grants
currently available. The Committee generally agreed that the project should be delayed
and revisited if grant funding becomes available or when the roof requires replacement.
Staff recommended maintaining $30,000–$50,000 in the CIP for potential skylight
improvements. Staff will also consult with the Village's sustainability efforts regarding
the solar project.
The Committee discussed the proposed CIPs and recommended moving the Village Hall
solar project from 2027 to 2030.
Kirchdoerfer moved, seconded by Higgins, to recommend to the Village Board
approval of the 2027 –2036 Capital Improvement Plans for Public Works, Sewer
Utility, and Water Utility ; however, reduce the 2027 rooftop solar allocation for
To be Approved 09-22-2026 Page 4 of 4
skylight repairs and structural evaluation and move the projected rooftop solar
project to 2029. Motion carried 2-0.
7) Future Agenda Items.
The next Public Works & Utilities Committee meeting is scheduled for Tuesday, September 22,
2026, at 5:00 p.m.
Director Striegl met with Strand & Associates regarding the water tower project. If the
Committee would like to recommend a different art design, the September 22 meeting may be the
best opportunity to do so. The art design could also be included as an alternate bid.
8) Adjournment.
The Public Works & Utilities Committee meeting was adjourned at 6:03 p.m. on Tuesday,
August 25, 2026 without objection.
Submitted by,
Peggy Haag
Deputy Clerk
Village Hall 101 Alpine Parkway Oregon, Wisconsin 53575-3812
Telephone: (608) 835-6285 Fax: (608) 835-6503
lstriegl@oregonwi.gov
MEMO
TO: Public Works & Utilities Committee
FROM: Lauren Striegl, Director of Public Works
DATE: September 22, 2026
RE: Status of Public Works Projects (September 2026)
This memorandum includes information on the status of ongoing and planned (2026) Village Public
Works & Utilities projects.
Staff would like to make the Committee aware of a recent update to construction site access plans. At the
start of the 2026 – 2027 academic year, Village staff from the Police and Public Works Departments had
coordinated with the construction teams for both major ongoing 2026 Oregon street projects to open the
Alpine Pkwy / CTH CC intersection to school bus traffic, and the East Lincoln St / North Oak St
intersection to all traffic. This was done to mitigate disruption to school buses, and to facilitate access to
Oregon School District schools while construction was ongoing.
Unfortunately, over the first two weeks of the school year, Oregon Police Department (OPD) observed a
marked rise in unsafe driving behavior at both sites, including private vehicles ignoring posted
construction and traffic control signage (primarily stop signs). Public Works staff also received
complaints about unsafe driving from East Lincoln St residents. This behavior put construction crews,
residents, and passengers and drivers at serious risk of injury. As such, on Friday, September 11, OPD
and Public Works agreed that closure of all active construction sites in Oregon to non-emergency vehicles
was the best approach going forward, and notified the construction teams and Oregon School District
(OSD) staff of the change immediately.
While the closures are inconvenient and frustrating, Village staff across departments agree that resident
and contractor safety are the top priority in this situation. OPD and Public Works staff appreciate OSD’s
patience and partnership on this issue. Public Works will continue to work with the construction teams to
ensure that these major projects are completed to the Village’s high standards and as quickly as possible.
Ongoing (2025) Construction Projects
Well 6 is online. Concluding sitework (driveway, apron, restoration) is underway, to be
completed after the completion of Highlands of Netherwood Ph 4B.
Richards Road lift station – construction is ongoing. Traffic detour will be kept in place for a
significant portion of the project. Target substantial completion date is October 2026.
WWTP – on schedule. Clarifier and UV structure construction is completed (some equipment still
to be installed). Building 15 (new preliminary treatment building) and sitework construction is
progressing. Staff expects that the next project change order will be presented to the Village
Board in October 2026. No major surprises so far, and change orders remain well within
contingency.
5(a)
Page | 2
2026 Construction Projects
Alpine Pkwy / CTH CC – project is nearing completion, with all paving completed and pole and
signal infrastructure erection in progress. Remaining work includes striping, signal programming,
and final restoration. Staff are working with the contractor (Rock Road) and engineer (KL) to
coordinate the re-opening of the intersection as soon as is safe.
East Lincoln St – underground utility, road grading, and most concrete work has been completed
between North Main St and North Oak St. Underground utility installation (sanitary sewer and
water main) between North Oak St and North Perry Pkwy is in progress.
Senior Center – construction is ongoing.
Gary Disch Park – grading, utility, irrigation system, play structure installation, and concrete
work is substantially complete, with restoration to follow in the next several weeks. The play
structure will remain closed to public use until the site is stabilized and safe for public access.
2026 Design Projects
CTH MM / Wolfe St Ph 1 – on schedule for bidding in Nov-Dec 2026 for construction in 2027.
Transportation Project Plat (TPP) has been approved by the Plan Commission and will be
presented to the Village Board on September 21 for approval. Real estate acquisition process
(roundabout land, some small acquisitions to accommodate sidewalk and clean up ROW
boundary) has begun with preliminary data gathering, but official work will follow approval of
the TPP.
Bethel Greenacre Park Improvements – Master Plan was approved by the Village Board on 8/17.
Design is ongoing. Bidding is scheduled for January 2027.
Water tower painting/rehabs – design and bid package preparation are ongoing.
New water tower and interzonal booster station planning – Town & Country presented siting
options to the Village Board in July 2026. The Village Board directed staff and Town & Country
to proceed with the North Standpipe site for the new water tower, and with improvements to the
pump stations at Wells No. 4 and 5 for interzonal boosting capacity. A final siting study and
water system master plan update will be presented to the Village Board for approval in Fall 2026.
Public Works Garage space needs analysis – ongoing.
2026 Private Development Projects
Greenview Preserve (Veridian) Ph 4 – utilities have been completed, road construction is
ongoing.
Highlands of Netherwood (FDG) Ph 4 – utilities have been completed, paving is scheduled for
September 21.
Highlands of Netherwood (FDG) Ph 5 – some discussion has occurred, but unlikely that any
construction will occur in 2026.
Village Hall 101 Alpine Parkway Oregon, Wisconsin 53575-3812
Telephone: (608) 835-6285 Fax: (608) 835-6503
lstriegl@oregonwi.gov
MEMO
TO: Public Works & Utilities Committee
FROM: Lauren Striegl, Director of Public Works
DATE: September 22, 2026
RE: Contract Amendment to Task Order No. 2023-03 with Ruekert & Mielke, Inc. for
Engineering Services for the East Lincoln Street Reconstruction Project
The Village of Oregon Public Works Department is presenting a request from Ruekert & Mielke, Inc.
(RM) for a contract amendment to Task Order No. 2023-03 with the Village. TO No. 2023-03 includes
engineering services associated with the Village’s ongoing East Lincoln Street Reconstruction Project,
which is funded in part by the Wisconsin Department of Transportation’s Surface Transportation Program
(STP) – Urban program. The services originally scoped in TO No. 2023-03 included:
Survey and basemap creation
Temporary Limited Easement (TLE) creation (where required)
Public outreach
Utility outreach
Environmental screening
Preliminary and final design, including plans, specifications, and construction cost estimates
Permitting
Coordination with the Wisconsin DOT, including the development of reports and other materials
required for road construction projects using State and Federal monies
Other tasks as outlined in TO No. 2023-03 (attached for review)
TO No. 2023-03 was originally approved on May 8, 2023. The scope outlined in TO No. 2023-03 was
structured to support a WisDOT-required final plans, specifications and estimate (PS&E) date of
November 1, 2025, and a WisDOT-led bid date in February 2026. The project schedule remained
generally unchanged from start to end.
Throughout the project planning and design effort, the scope of the overall project expanded in a number
of key areas. The attached memorandums from RM Project Manager Cory Horton, PE to the Public
Works & Utilities Committee and Director of Public Works Lauren Striegl, as well as the proposed
contract amendment, outline in detail the overage categories and associated amounts.
The most significant changes were direct requests from WisDOT communicated once design was
underway, including the following items:
1) Significant expansion in sidewalk replacement for compliance with ADA standards for new
sidewalk throughout the project area,
2) Pedestrian accommodations and detour infrastructure in excess of that typically installed for
similar projects,
3) Expanded documentation and notification for a found contaminated area near (but outside) the
project limits, and
4) Significantly expanded coordination, revision work and communication.
6(a)
Page | 2
The Village also requested some additional work from RM as a result of WisDOT requirements,
including the following:
1) Coordination with standalone East Lincoln Street curb stop replacement project (completed in
Summer 2025),
2) Additional TLE documentation, and
3) Additional analysis and documentation for funding review.
The final major component of the proposed amendment includes re-work required due to misalignment
between the planned East Lincoln Street improvements and the (at the time) in-progress North Oak Street
improvements. This issue was identified during the construction of North Oak Street and at the 90% point
in the East Lincoln Street design process, which required some re-design and, more significantly,
updating of various documents required by WisDOT ahead of the PS&E date. Both RM and Public
Works staff acknowledge that this issue should have been caught earlier in the design process, and that its
timely identification could have mitigated these costs. As such, RM and Public Works staff propose that
costs associated with this item be shared equally between the Village and RM.
Public Works staff has reviewed the contents of this contract amendment request in detail, both
independently and with RM. Staff agrees with RM that the costs included in the amendment reflect items
not in the original design project scope, and that the majority of the expenses are ones that could not have
been reasonably predicted by either party at the time that TO No. 2023-03 was presented to the Village
Board.
Public Works staff was made aware of this potential amendment request in late February 2026. At the
time, RM provided an approximate dollar amount associated with the amendment, which staff included in
the total required borrowing amounts for the East Lincoln Street Reconstruction Project as shown in the
2026 Debt Plan. As the final requested amendment amount is below the initial estimate, sufficient money
is available in the project budget to fund it without impacting construction funding or contingency.
Based on the above considerations, Public Works staff recommends that the Committee recommend this
contract amendment request to the Village Board for approval.
Recommended Motion: Motion to recommend to the Village Board approval of an amendment to
Task Order No. 2023-03 with Ruekert & Mielke, Inc. for engineering services for the East Lincoln
Street Reconstruction Project.
9/17/26 Ruekert & Mielke, Inc. East Lincoln Street- Task Order No. 2023-03 Amendment
4630 South Biltmore Lane, Madison WI 53718
This is ATTACHMENT A, made part of Task Order No.
2023-03 between Client and Consultant for Professional
Services dated April 25, 2023.
This document modifies Task Order No. 2023-03 between Ruekert & Mielke, Inc. (R/M) and the Village of
Oregon (Village) as described below:
Amendment to Task Order No. 2023-03
1) BACKGROUND DATA:
Effective Date of Task Order: April 25, 2023
Client: Village of Oregon
Consultant: Ruekert & Mielke, Inc.
Specific Project: East Lincoln Street Reconstruction- WisDOT Project ID 5627-00-01/71/72
DESCRIPTION OF MODIFICATIONS:
Additional Services
The following services are added to the Task Order. These services were required as the project developed and were beyond the
assumptions and level of effort included in the original scope.
Additional Meetings and Project Coordination- $3,636
Provide recurring project check-ins with Village staff and WisDOT and additional coordination regarding real estate impacts,
environmental findings, pedestrian accommodations, ADA compliance, and Oak Street utility revisions beyond the meetings
identified in the original scope.
Hazardous Materials Findings and Coordination- $5,574
Provide additional coordination, documentation, agency interaction, and project management required to address contaminated-
material findings identified during project development and maintain project progression.
Additional Temporary Limited Easements and Property Acquisition Support- $2,095
Prepare expanded temporary limited easement exhibits, provide survey and right-of-way documentation support, and coordinate
additional property impacts identified as ADA, grading, and sidewalk requirements were refined beyond the four TLE exhibits
assumed in the original scope.
Expanded Traffic and Pedestrian Control Design- $4,982
Develop and revise traffic control and pedestrian accommodation requirements resulting from WisDOT review, including detour
planning, temporary audible messaging devices, and updates to the Wisconsin Transportation Management Plan, cost estimate,
special provisions, and plans.
Curb Stop and Water Service Lateral Revisions- $3,187.50
Evaluate existing curb stop replacement needs and revise the plans to distinguish curb stops replaced before the roadway
project from those included in the WisDOT letting after work beyond the right-of-way was restricted.
Grant Funding Revision Request- $552.50
Assist the Village with documenting project costs that may qualify for additional grant funding.
Additional Curb Ramps and Sidewalk Replacement for ADA Compliance- $12,500.75
Evaluate additional ADA deficiencies identified after completion of the original survey and design expanded curb ramp and
sidewalk replacement improvements, including cross-slope evaluation and additional ADA compliance review.
Expanded Storm, Sanitary Sewer, and Water Main Design / Oak Street Redesign- $12,968.25
Incorporate late-received Oak Street design information by redesigning storm and sanitary facilities, reevaluating water main
conflicts and separations, and updating plans, quantities, permit documents, and bidding documents.
9/17/26 Ruekert & Mielke, Inc. East Lincoln Street- Task Order No. 2023-03 Amendment
4630 South Biltmore Lane, Madison WI 53718
Additional WisDOT Coordination and PS&E Revisions- $35,992.00
Provide additional coordination and design support associated with the expanded scope, extended schedule, and multiple
WisDOT review cycles, including comment resolution and repeated updates and resubmittals of plans, specifications, estimates,
special provisions, quantities, utility status reports, funding documentation, and PS&E packages.
Rate Adjustment Credit– ($1,467.50)
Upon review of the contract, the billing followed the master services agreement pricing. The task order included language to
hold the rates from 2023-2024. The entire project was reconciled to correct for this and a credit of $1,467.50 will be provided.
COMPENSATION
For the Additional Services described above, Client shall pay Consultant on a time-and-expense basis in accordance with the Task
Order and applicable rate schedules, up to the revised not-to-exceed amount shown below.
Original Task Order $143,310
Additional Services $80,020.50
Total Revised Task Order $223,330.50
Client and Consultant agree to modify the above -referenced Task Order as set forth in this Amendment. All provisions of the
Agreement and Task Order not modified by this or previous amendments remain in effect. The Effective Date of this Amendment
is September 9, 2026.
CLIENT: CONSULTANT:
Village of Oregon Ruekert & Mielke, Inc.
Signature: __________________________ Signature: __________________________
Title: ______________________________ Jason P. Lietha, P.E.
Chief Operating Officer
Date: ______________________________ Date: August 20, 2026
September 17, 2026
Village of Oregon Public Works Committee
117 Spring Street
Oregon, Wisconsin 53575
Re: East Lincoln Street Reconstruction Project
Task Order No. 2023-03 Contract Amendment Request
Ruekert & Mielke, Inc. (R/M)respectfully submits the enclosed contract amendment and
supporting documentation for additional professional services associated with the East
Lincoln Street Reconstruction Project.
The original task order was established in April 2023, with most preliminary and final design
work anticipated during 2023 and 2024. The project ultimately extended into 2026. What
began as a relatively straightforward street and utility reconstructionand roadway
resurfacing project became substantially more complex as design advanced and additional
environmental conditions, regulatory requirements, property impacts, utility conflicts,
accessibility deficiencies, and agency requirements became known.
Several significant changes were identified relatively early in the project. The hazardous-
materials investigation identified a contaminated site that required additional investigation,
coordination, documentation, agency interaction, and related work beyond the original
scope. The number of temporary limited easements also increased from the four
contemplated in the original scope to six, requiring additional survey, exhibit preparation,
property coordination, and right-of-way documentation.
Additionally, the sidewalk and most curb ramps within the project corridor were found not
to comply with applicable accessibility requirements. Rather than the limited sidewalk and
curb-ramp improvements originally anticipated, the project required substantially broader
replacement of the sidewalk system and additional curb ramps. WisDOT also required
significantly more detailed traƯic-control and pedestrian-accommodation measures than
anticipated, including expanded pedestrian routing, detour planning, temporary audible
messaging devices, and multiple revisions to the plans, specifications, cost estimates, and
Wisconsin Transportation Management Plan.
The project became more complex as design progressed. Late-received Oak Street design
information showed that existing storm and sanitary sewer infrastructure diƯered from the
information available during earlier design. This required substantial redesign of the storm
sewer and sanitary sewer systems, reevaluation of related water-main improvements and
utility conflicts, and corresponding revisions to plans, quantities, permit documents,
specifications, and bidding documents.
The majority of the contract overage occurred during Phase 4, the final design and PS&E
phase. During this phase, the project team was working under a firm schedule to complete
the plans, specifications, estimates, utility documentation, agency forms, andapprovals
necessary to maintain the planned PS&E submission, bidding, and construction schedule.
Maintaining that schedule was also necessary to protect the Village’s project grant funding.
At the same time, multiple WisDOT review cycles required repeated and interconnected
revisions to nearly every component of the project. These included updates to plans,
specifications, estimates, quantities, traƯic control, pedestrian accommodations, utility
status reports, environmental commitments, funding documents, AASHTOWare
information, and final PS&E packages. Because changes to one component frequently
aƯected several others, the cumulative eƯort substantially exceeded the standard WisDOT
Local Program review process anticipated in the original task order.
For additional context, the Village’s original construction budget was approximately
$1,484,830, while the final construction contract was approximately $2,717,944. The
original overall engineering budget, including the separately authorized hazardous-
materials work, was approximately $148,310, or approximately 10.0% of the original
construction budget. The current engineering eƯort is approximately $223,330.50, or
approximately 8.2% of the final construction contract. Although the total engineering cost
increased, the engineering eƯort remained generally proportional to the substantially
expanded construction scope and final construction cost.
Smaller change order discussions occurred as the project proceeded for thesidewalk
revisions and additional easements – although these were not formalized in a contract
amendment. R/M began discussing the need for a broader contract amendment with
Village staƯ in March 2026. We recognize, however, that the changing scope and
associated cost implications should have been more formally documented and brought
forward earlier. We takeresponsibility for that.
Our intent was to resolve each issue as it arose, maintain project momentum, protect the
Village’s grant funding, and avoid jeopardizing the PS&E, bidding, and construction
schedule. However, the volume and interconnected nature of the project changes, together
with continuing WisDOT comments and requested PS&E revisions, made it diƯicult to
determine the full extent of the additional eƯort while the work was actively progressing.
In hindsight, maintaining the project schedule and formally documenting the changing
scope and budget should have occurred in parallel. We regret that the formal amendment
did not keep pace with the work, and we apologize for placing the Village and Committee in
the position of considering these costs after much of the additional eƯort had already
occurred. We have since completed a detailed review of the original scope, project billing,
and supporting records to distinguish the additional services from the work included in the
original task order and to provide the Village with a transparent accounting of the requested
amendment.
The enclosed amendment specifically modifies Task Order No. 2023-03 from $143,310 to a
revised not-to-exceed amount of $223,330.50, representing $80,020.50 in additional
services. The broader engineering-cost figures referenced above include the separately
authorized hazardous-materials work and are provided to show the overall relationship
between engineering eƯort and the original and final construction costs.
We respectfully request the Committee’s consideration of the amendment based on the
documented work required to deliver a compliant, coordinated, and constructible project
while protecting the Village’s funding and overall project schedule.
We are committed to answering the Committee’s questions openly and to applying the
lessons from this project through earlier documentation of scope changes, more frequent
budget communication, and timelier amendment discussions on future work.
Respectfully submitted,
Ruekert & Mielke, Inc.
MEMO
To: Lauren Striegl
From: Cory Horton
Subject: Evaluation of Additional Services Relative to Task Order 2023-03
Lauren,
We evaluated the original scope included in Task Order 2023-03 against the additional
services that were required as the project advanced. The following summary is intended to
provide a clear and transparent explanation of where the actual level of eƯortexceeded the
assumptions in the original task order.We recognize that project needs can evolve over
time, and we appreciate the Village’s partnership throughout the process. We would be
happy to meet and discuss any of these items in more detail, answer questions, or review
the supporting information together if that would be helpful.
Additional Meetings and Project Coordination – $3,636
The original task order specifically identified and budgeted for the anticipated project
meetings, including the project kickoƯ meeting, railroad coordination meeting, public
involvement meeting (PIM), utility coordination meetings, and 30%, 60%, and 90% design
review meetings. The total budget allocated for meeting-related eƯort was $4,145.
Actual meeting and coordination eƯort totaled approximately $7,781, resulting in an
additional $3,636 of uncompensated eƯort.
The additional meeting eƯort was due to additional meetings that were not in the original
scope. These additional meetings included:
Recurring project check-in meetings with Village staƯ and WisDOT.
Meetings regarding temporary limited easements (TLEs), right-of-way impacts, and
property acquisition requirements.
Coordination meetings related to environmental and contamination findings.
Pedestrian accommodation and ADA compliance meetings required by WisDOT.
Oak Street utility redesign discussions and associated stakeholder coordination.
These meetings addressed issues that were not included in the original scope assumptions
and were necessary to successfully advance the project through design, agency review,
utility coordination, and final PS&E development.
Hazmat Findings and Coordination – $5,574
The original scope did not anticipate additional eƯort associated with contaminated
materials encountered during project development. Additional coordination,
documentation, agency interaction, and project management were required to address
environmental findings and maintain project progression. These services were performed
in response to conditions identified after the original task order was established.
Additional Temporary Limited Easements (TLEs) and Property Acquisition – $2,095
The original scope assumed a limited number of easements. As design advanced and ADA,
grading, and sidewalk requirements were refined, additional property impacts were
identified, resulting in expanded easement exhibits, coordination with property owners,
survey support, and right-of-way documentation beyond the original assumptions.
TraƯic /Pedestrian Control Complexity – $4,982 ($4,580.00 Design+ $402.00 CAD)
The original scope anticipated vehicular traƯic to be closed to local traƯic with minimal
pedestrian accommodation during construction. TraƯic control requirements expanded
significantly during project development due to WisDOT review comments, pedestrian
accommodation requirements, detour planning, temporary audible messaging devices,
and additional traƯic control documentation (WisTMP/Cost estimates/Special
provisions/Plans). The final traƯic control eƯort exceeded the level anticipated in the
original task order and required multiple revisions throughout final design.
Curb Stop and Lateral Revisions – $3,187.50 ($2,558.00 Design+ $629.50 CAD)
The original scope anticipated entire watermain replacement as well as service
replacement up to and including all curb stops. As a result of the real estate requirements
(not allowing temporary construction permits), the work was not allowed to disturb any
ground beyond the rights-of-way. As a result, the project needed to identify which existing
curb stops needed to be replaced before the road project, and the road plans needed to be
modified to document which curb stops would need to be replaced and which had already
been replaced prior to the WisDOT letting.
Grant Revision Request – $552.50
The Village was made aware of the potential for additional grant funding. R/M was asked to
assist with documenting project costs that could be eligible for additional funding. This
was not a part of the original scope.
Additional Curb Ramps and Full Sidewalk Replacement for ADA Compliance –
$12,500.75 ($6,964.50 Design+ $5,536.25 CAD)
The original scope assumed limited sidewalk replacement and ADA improvements. During
design development, additional ADA deficiencies were identified (after the survey had been
completed). This necessitated additional curb ramp replacement, evaluation of sidewalk
cross slopes, additional ADA compliance reviews, and ultimately the design of
substantially more sidewalk replacement and curb ramp improvements than originally
contemplated.
Expanded Storm, Water, and Sanitary Design / Oak Street Redesign– $25,936.50
($20,741.00 Design+ $5,195.50 CAD). We propose splitting this 50%-50%
The sump pump discharge system underwent multiple design revisions due to right-of-way
and easement constraints identified during project development. What was initially
envisioned as a more straightforward system ultimately evolved into two separate sump
pump discharge systems to collect and convey flows independently from each side of the
corridor. This required additional hydraulic evaluation, utility conflict analysis, plan
revisions, and coordination to accommodate existing underground infrastructure while
maintaining constructability and operational performance.
After the 30% and 60% designs of the East Lincoln project had been completed, as built
drawings became available for the Oak Street intersection. The East Lincoln Street sanitary
sewer and storm sewer systems were originally designed based onOak Street plan
information available early in the project. However, late in the design process, newly
obtained as-built information revealed that the existing storm and sanitary facilities
diƯered from the previously provided records with respect to configuration and depth. This
new information necessitated substantial redesign of both systems. The revised design
altered portions of the sewer alignment (and flow direction), allowed for the use of smaller
sanitary sewer pipe sizes resulting in construction cost savings, and created opportunities
to increase storm sewer capacity and improve overall system functionality.
Because the storm and sanitary sewer systems were redesigned, the proposed water main
improvements also had to be reevaluated to identify and resolve new utility conflicts,
maintain required separations, and ensure constructability. These interconnected utility
revisions required additional engineering analysis, design iterations, coordination among
disciplines, revision of plans and quantities, and updates to permit and bidding documents
beyond the level of eƯort contemplated in the original scope.
WisDOT Coordination Associated with Expanded Scope and Extended Timeframe –
$35,992.00 ($28,764.75 Design+ $7,227.25 CAD)
The original task order anticipated a standard WisDOT Local Program review process and a
typical progression through final design. However, as the project scope expanded and the
schedule extended, the level of agency coordination and design documentation eƯort
increased substantially beyond what was originally contemplated.
Throughout final design, multiple rounds of WisDOT review comments generated
significant downstream impacts across virtually every project component. Revisions
associated with traƯic control, right-of-way and property requirements, utility coordination,
environmental commitments, quantities, PS&E documentation, and special provisions
required repeated updates to plans, specifications, estimates, and supporting project
documents. These comments often resulted in interconnected revisions, where changes in
one discipline necessitated corresponding modifications throughout the project package.
Additional eƯort included preparation and resubmittal of PS&E packages, utility status
reports, funding and program coordination, comment resolution, quantity updates, special
provision revisions, traƯic control reviews, and extensive document management
associated with multiple submission cycles. The cumulative eƯect of the expanded scope,
prolonged project duration, and iterative agency review process resulted in a substantially
greater level of WisDOT coordination and design support than was includedin the original
budget and level of eƯort.
Rate Adjustment Credit – ($1,467.50)
Upon review of the contract, the billing followed the master services agreement pricing.
The task order included language to hold the rates from 2023-2024. The entire project was
reconciled to correct for this and a credit of $1,467.50 will be provided.
Village Hall 101 Alpine Parkway Oregon, Wisconsin 53575-3812
Telephone: (608) 835-6285 Fax: (608) 835-6503
lstriegl@oregonwi.gov
MEMO
TO: Public Works & Utilities Committee
FROM: Lauren Striegl, Director of Public Works
DATE: September 22, 2026
RE: Water Tower Logo – South Standpipe and Lincoln Road Towers (Follow-Up)
At the July 28, 2026 meeting of the Public Works & Utilities Committee, the Committee discussed the
inclusion of a text and/or graphic logo(s) with the upcoming (2027) Lincoln Road Water Tower and South
Standpipe re-coating project (see attached memorandum). Ultimately, the Committee voted to
recommend to the Village Board approval of the Lincoln Road Water Tower and South Standpipe Logo
featuring a graphic reproduction consisting of a black hand-heart graphic with orange “Oregon” lettering,
replicating the heart sculpture in Alpine Parkway Park contingent upon securing approval fromthe artist
Marilea Groves.
Following this meeting, Village Trustee and Committee member Tom Kirchdoerfer spoke with Ms.
Groves about the use of her art. Ms. Groves asked for an opportunity to consider the Committee’s request,
and to potentially develop and present an alternate proposal for use as a logo on either or both of the water
storage facilities included in the 2027 project.
Committee Chairperson Tim Higgins has requested that this item be placed on the September Committee
agenda for consideration and possible new recommendation to the Village Board. Staff are seeking
Committee direction on this item and, if appropriate, a recommendation to the Village Board.
6(b)
Village Hall 101 Alpine Parkway Oregon, Wisconsin 53575-3812
Telephone: (608) 835-6285 Fax: (608) 835-6503
lstriegl@oregonwi.gov
MEMO
TO: Public Works & Utilities Committee
FROM: Lauren Striegl, Director of Public Works
DATE: July 28, 2026
RE: Water Tower Logo Options – South Standpipe and Lincoln Road Towers
UPDATE July 28, 2026: At the June 23, 2026 meeting of the Public Works & Utilities Committee,
Public Works Department staff provided a memorandum regarding options for logo painting on the
Village’s South Standpipe and Lincoln Road Tower in association with the planned 2027 rehab projects
for both facilities. Thad Noel from Strand Associates provided a presentation on water tower logo
painting options. The text of the June 23 memorandum is included below for review, and Strand’s
presentation is attached to this memorandum.
At the June 23 meeting, the Committee declined to recommend any action on this item. Staff is seeking
any further feedback from the Committee.
Village Water Utility staff is seeking Public Works & Utilities Committee guidance on the selection of a
graphic logo (or logos) for painting on the exterior of the South Standpipe and Lincoln Road Water
Tower.
The approved 2026 – 2035 Capital Improvement Plan (CIP) includes funding in 2027 for the exterior
painting of the Village’s South Standpipe and Lincoln Road Water Tower. In preparation, the Village has
contracted with Strand Associates, Inc. (Strand) to provide design and bidding services for that project in
2026. Strand provided similar services for the 2024 North Standpipe Rehabilitation project.
Strand has now completed site investigations and coating testing, and has used the information collected
to begin preliminary design work. Strand and Village staff have discussed the aesthetics of both facilities,
and are proposing to match the color scheme used for the North Standpipe in 2024 (white with black
font).
One major outstanding design decision remaining is whether to include a graphic or “logo” on one or both
of the facilities to be painted. In 2024, given the hidden location of the North Standpipe and the
positioning of its ladder along its front face, the project team made the decision to not include any
graphics apart from the word “OREGON.” However, both the South Standpipe and the LincolnRoad
Tower are significantly more visible from within and around Oregon. Many communities in Wisconsin
and beyond have elected to personalize their water towers by using unique color schemes, adding logos or
standalone graphics, or even painting the entire facility to create a water tower-shaped art piece.
Personalization of water towers is a rare opportunity to turn public works infrastructure, which is so often
designed to be as invisible as possible, into a fun and exciting part of a community’s landscape.
Given the visibility of these structures and the novelty (for Oregon) of adding art to them, Village staff
are requesting Committee guidance on how to scope and select a graphic for each facility. Strand has
Page | 2
prepared a presentation with examples of recently-painted water tower graphics. These graphics vary in
size, complexity, color range, and cost.
While staff would appreciate any guidance offered by the Committee, the following questions are
particularly important to advancing the project.
1) What is the general cost range that the Committee would recommend targeting for each logo?
a. For reference, note that the current draft 2027 – 2036 CIP includes an estimated $25,000
for a logo or graphic on both the South Standpipe and the Lincoln Road Tower.
2) Does the Committee or its members have any general themes or images that it would like to see
used for this purpose?
3) Who would the Committee prefer to make the final logo selection? The project team, the
Committee (via recommendation to the Village Board), or the Village Board?
4) Should the Committee prefer that they or the Board make the final selection/s, what process
would they like to see followed? Would they prefer to provide suggestions, select from a curated
list developed by the project team, or some other option?
Based on Committee feedback, the project team will progress in parallel with project design and logo
selection. In order to keep the planned project schedule, the team will need a final logo / graphic selection
for each facility by the end of August 2026.
Source: Village of Oregon website. First collected Oct 16, 2026.