Building Construction Oversight Committee — Agenda Packet
Village of Germantown · Washington County · Building Construction Oversight Committee · meeting of Jun 11, 2026 · Agenda packets
Open the original document More from Village of Germantown
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
MEETING: REGULAR MEETING OF THE BUILDING
CONSTRUCTION OVERSIGHT COMMITTEE
DATE & TIME: Thursday, June 11, 2026 at 5:45 PM
LOCATION: Germantown Village Hall Board Room
N112 W17001 Mequon Road
Any member of the body and/or citizen may attend the meeting virtually through the WebEx platform, Meeting #: 2551 513 3009 Password:
tvMpQE8JH38 which can be accessed by phone at 408-418-9388 or by clicking the link below:
https://villageofgermantown.my.webex.com/villageofgermantown.my/j.php?MTID=m1e5740d04b273adc00cd972977e2c00a
NOTICE: Citizens not wishing to attend the meeting personally or virtually may submit any public comments by sending an email
to comments@germantownwi.gov by 4 p.m. on the day of the meeting so that it can be provided to the members of the body for their
consideration.
Previously recorded meeting videos can be viewed at https://www.youtube.com/channel/UCOYp0EgELzTCa9X_iCohyhQ
AGENDA
I. CALL TO ORDER: This meeting has been given public notice in accordance with
Section 19.83 and 19.84, Wis. Stats, in such form that will apprise the general public
and news media of subject matter that is intended for consideration and action.
II. ROLL CALL:
III. CITIZEN INPUT: (Please be advised per 19.84(2) that information and comment will
be received from the public. It is the policy of this municipality that public input be
limited to a four (4) minute period per person with a time extension granted at the
discretion of the Chairperson. Be advised that there may be limited discussion of the
information received but no action will be taken under public comments.) Comments
that may be injurious to village personnel or other individuals will not be allowed.
IV. MEETING MINUTES:
A. March 23, 2023, Meeting Minutes (ACTION)
V. NEW BUSINESS:
A. Owners Representation services related to the Police Department building
project (ACTION)
B. Construction Manager at Risk services related to the Police Facility project
(DISCUSSION / ACTION)
C. Committee's Process and Procedures for Exercising its Powers and Duties with
Respect to Police and Fire Department Construction Projects. (ACTION)
VI. ADJOURNMENT:
UPON REASONABLE NOTICE, efforts will be made to accommodate the needs of disabled individuals through
appropriate aids and services. For Additional information or to request this service please contact the Village
Clerk at (262)250-4740 at least 2 days prior to the meeting.
Notice is hereby given that a possible quorum of other boards, committees, and/or commissions may attend this
meeting to gather information about an item over which they have decision-making responsibility. This may
constitute a meeting of these bodies per State ex rel. Badke v Greendale Village Board, even though these
bodies will not take formal action at this meeting.
Page 1 of 169
BUILDING CONSTRUCTION OVERSIGHT COMMITTEE MEETING MINUTES
March 23rd, 2023
Village Hall Board Room
CALL: Trustee Baum called the meeting to order at 5:30pm.
ROLL CALL: In attendance were Chairman Baum, Trustee Neureuther, Member Nilles and Public Works Director
Ratayczak.
APPROVAL OF MINUTES: MOTION Neureuther/Nilles approval of the Minutes from January 24th, 2023.
Motion Unanimous.
NEW BUSINESS
A: Review new Salt Storage Building located at New DPW Campus
Director Ratayczak distributed building plans and discussed options. Committee Members would like to see colored
wall samples; to match DPW building color scheme.
MOTION Nilles/Neureuther to recommend approving the building as designed. Motion Unanimous.
B: Review new Fueling Station located at New DPW Campus
Director Ratayczak distributed building plans and discussed options. Committee Members would like to see a
sample of colors for canopy; to match DPW building color scheme.
MOTION Neureuther/Nilles to recommend approving the building as designed. Motion Unanimous.
C: Review new Residential Yard Waste Facility Building located at New DPW Campus
Director Ratayczak distributed building plans and discussed options. Committee Members would like to see colored
wall samples; to match DPW building color scheme.
MOTION Nilles/Neureuther to recommend approving the building as designed. Motion Unanimous.
ADJOURNMENT: Chairman Baum adjourned the meeting at 5:45pm.
Page 2 of 169
BUSINESS OF THE BUILDING CONSTRUCTION OVERSIGHT COMMITTEE
MEETING DATE: June 11, 2026
PLACEMENT: Action Item
ITEM TITLE: Owners Representation services related to the Police Department
building project (ACTION)
SUBMITTED BY: Patrick Merten, Police Chief
SUMMARY EXPLANATION:
ATTACHMENT:
1. M-C Group Summary Recommendation
2. MC Group Proposal
3. MC Group Fees_revised
STAFF RECOMMENDATION:
ACTION BY COMMITTEE:
Page 3 of 169
BUSINESS OF BUILDING CONSTRUCTION OVERSIGHT COMMITTEE
GERMANTOWN, WI
MEETING DATE: June 11, 2026
AGENDA ITEM: Action
ITEM TITLE: Contract for Owners Representation for New Police Department
SUBMITTED BY: Chief Patrick Merten
SUMMARY EXPLANATION:
The Village has already initiated the selection of an Architectural/Engineering (A/E) team and
intends to utilize a Construction Manager at Risk (CMAR) project delivery method. The Owner’s
Representative (OR) will serve as the Village’s primary advocate, ensuring the project remains
on schedule, within budget, and aligned with the operational, security, and functional
requirements of a modern law enforcement facility. While the final project cost has not yet been
determined, preliminary estimates place the total project cost at approximately $34.5 million.
The Police Department Working Group issued a Request for Proposals (RFP) to three Owner’s
Representative firms and received proposals from all three: M -C Group, Luther Group, and
Cadence Consulting. The Working Group reviewed and evaluated each proposal using the
following criteria:
• Experience with Public Safety / Police Facilities (20 points)
• Qualifications of Personnel (30 points)
• Approach to CMAR Budget and Schedule Oversight (20 points)
• Proposed Fee Structure (10 points)
• References from Similar Wisconsin Municipalities (10 points)
• Interview (10 points)
The Police Department Working Group conducted interviews with two of the three firms.
Cadence Consulting was unable to participate in the scheduled interview process and therefore
did not receive interview points. The firms interviewed were M -C Group and Luther Group.
Following the interviews and final evaluation process, the firms received the following overall
scores on a 100-point scale:
• M-C Group – 83 out of 100
• Luther Group – 49 out of 100
Based on the results of the proposal review, interviews, references, and overall evaluation
process, the Working Group determined that M -C Group is the most qualified firm to serve as
the Village’s Owner’s Representative for the new police facility project. M -C Group
demonstrated extensive experience with public facility projects, a strong understanding of
CMAR project delivery, and a proven ability to provide effective project oversight. In addition, M -
C Group has established professional relationships with numerous qualified A/E and CMAR
firms throughout the region and is well-positioned to collaborate with FGM Architects and the
selected CMAR team throughout the design and construction process.
Therefore, the Police Department Working Group recommends that the Village Board authorize
staff to enter into an agreement with M-C Group to provide Owner’s Representative services for
the new police facility project.
Thank you for your consideration of this request.
Page 4 of 169
ATTACHMENT: ORDINANCE___ RESOLUTION_____ OTHER__X__
RECOMMENDATION:
A positive recommendation for M-C Group to provide Owner’s Representative services for the
new Police Facility project and further recommends forwarding this recommendation to the
Village Board for final consideration and approval.
Page 5 of 169
May 22, 2026
New Police Department Facility
Page 6 of 169
Dear Chief Merten,
Congratulations on receiving community support to plan and implement a much-needed new Police Department in
the Village of Germantown. The new state-of-the-art facility will serve the community for current and future
generations to come.
MC Group LLC will be honored to play a role in assisting you, your staff and the Village’s' leaders in the planning,
design and implementation of this important and exciting project. We will act as an extension of your staff
protecting your interests as though they were ours in all aspects of the project. We feel that we have developed a
customized fit of owner representative services that do not overlap efforts and responsibilities of other project
stakeholders, including the design team and construction manager at risk.
The services and the resulting added value that they create are depicted and outlined in this proposal. If you have
any questions about any component of our proposal, please contact me; I will enthusiastically address any inquiries
you may have. After digesting the contents of our proposal, we hope that you will agree that MC Group LLC is the
perfect partner for this important project. Some of our key differentiators include:
The Most Experience: MC Group's experience is unmatched. We have been providing focused Owner's Rep
services since 1998, serving many notable institutional, educational, corporate and healthcare clients in
Southeast Wisconsin. The majority of our work is through repeat clients; testimony to the value that we bring.
A Recognized Entity: We are the longest standing Owner’s Representative firm serving Southeast Wisconsin
guiding Owners through complex projects to successful conclusions. Having a wide net of respected resources
brings more exposure and interest to your project; this translates to high value outcomes.
Customized Work Plan: No cookie cutter services proposal from us. We carefully craft the levels of services to the
specific needs of the project. We focus on the specific needs and avoid duplicative services provided by other
project stakeholders. By focusing our efforts where we drive value we can provide efficient involvement which
allows our reduced fee proposal.
We Are Facilitators: We believe in Win-Win relationships. We are avid facilitators working in an open, transparent
and respectful environment. By listening, reacting and monitoring the needs and inquiries of other project
stakeholders including the designers and constructors, we keep information flowing. Answers are the grease that
keeps the gears turning. Architects and construction managers respect us for the collaborative environment
that we foster.
We Are Highly Interested: We're really excited about the opportunity to serve on this project. I’ve called the
Germantown area home for the past 36 years, having sent my kids through the Germantown school district,
having coached Germantown Rec youth football and basketball and enjoying all that Germantown offers. (Our
current favorite is the Relish). We love projects that bring valuable services to the local community, especially
the community that we live in.
Thank you for the opportunity to present our firm, our values, our people and our proposed work plan for your
important project. We believe that we've hit the mark, but if not, please let us know. We are highly interested in
serving you in the manner that you envision and are amenable to feedback.
We look forward to next steps!
Ric Miller
Founding Partner - MC Group LLC
Village of Germantown
N122W17177 Fond du Lac Avenue
Germantown, WI 53022
Attn: Chief Patrick Merten, Police Chief, Germantown Police
Page 7 of 169
SECTION 1 | Firm Information & 1
Independence
SECTION 2 | Project Team 3
SECTION 3 | Experience 7
SECTION 4 | Project Approach 19
SECTION 5 | Compensation 29
SECTION 6 | Insurance 31
WHY MC GROUP? 33
TABLE OF CONTENTS
Page 8 of 169
SECTION 1
Firm Information
& Independence
“Thanks for the ongoing relationship which is anchored by
the very successful project to expand our corporate
headquarters... Our senior administration appreciates that
all of the project success parameters that we established
from the onset of the project have been met or exceeded.
Through this and subsequent projects, our real estate
management team benefits from the expertise your group
provides. We plan to continue leaning on MC Services as
our company grows and our facilities needs expand.”
Randy Stark | Director of Internal Services
West Bend Mutual Insurance
1
Page 9 of 169
ABOUT MC GROUP
Commitment to Diversity, Equity,
Accessibility and Inclusion
MC Group, LLC was originally formed as Ric Miller Construction
Consulting, LLC (RMCC) in January 1998 as a Wisconsin limited
liability company with the vision of providing Owners technical
support and expertise in planning and implementing their facilities
projects. In 2019, RMCC evolved into MC Group allowing for
increased capacity and capabilities to better serve our clients. We
now have a highly experienced and accomplished staff of
professionals providing Owner’s Representative services on
challenging and rewarding projects in many markets.
MC Group has managed over $4 billion worth of projects
constructed in the past 25+ years by applying a proven approach
that focuses on planning, communicating, motivating, and leading.
We have had the great privilege to serve many notable clients
within Southeastern Wisconsin and beyond.
To learn more about our firm, our people, and the clients that we
have had the privilege to serve, we encourage you to visit our
website at MCGroup-gbs.com
MC Group has extensive experience supporting our Client’s
diversity, equity, accessibility and inclusion commitments and is
comfortable collaborating with and supporting experienced
diversity consultants to open doors of opportunity. MC Group
understands the value and vision that diversity brings to our
communities and projects, and are committed to creating
opportunities for both individuals and businesses. Through careful
pre-planning and aggressive engagement, we have been able to
support some of our Clients, such as Froedtert Health, to exceed
their diversity goals by 10%, both in business participation and in
“hard hats” providing labor on projects.
Additionally, MC Group obtained its own certification as a woman-
owned business in 2024. Ric Miller, original sole proprietor, has
embraced the growth and development that Jackie Clarke and
Angela Brzowski have brought to the partnership, and the ability to
serve our Clients most collaboratively. Similarly, MC Group wants to
provide others their chance and encourage their growth in our
Wisconsin communities.
SECTION 1: Firm Information & Independence
2
Page 10 of 169
SECTION 1: Firm Information & Independence
3
Capacity
On an annual basis, we are positioned to provide more than $2 million in services to our customers. MC Group’s
capacity to serve has incrementally grown over the past five years and is projected to continue that same trajectory
of growth in the coming five years. With the Project Team and Approach as outlined in this Proposal, MC Group is well-
positioned with capacity to support the Village of Germantown in this exciting project and in future project needs.
In addition, prior to submitting on this RFP, we examined our workload and capacity as it specifically correlates to your
project scope and schedule. The team proposed has the capacity to fully address this project and act in the Village’s
best interests as an Owner’s Representative. Further, the team presented will be dedicated to this project for its
duration.
MC Group LLC is an independent Owner’s Services
Consulting firm with no financial or corporate affiliation with
FGM Architects or any other related firms.
We value our independence and see it as an asset to the
Village of Germantown to have our representation with your
growing team of outside experts. Our value comes from
helping our clients successfully achieve their project goals,
while objectively assessing all situations and providing sound
guidance and support.
Firm Independence
Page 11 of 169
SECTION 2
Project Team
“Job well done! Once again, the MC Group has been our
valued partner in facilitating a successful project conclusion.
You can be assured that you’ve played an instrumental role
in the exciting exponential growth that Froedtert Health has
experienced over the past 20 years. We look forward to
working with you and your staff for the next 20 years as we
continue on our journey to bring the most advanced health
care environments to our community and beyond.”
John A. Balzer, MSEM | VP, Facility Planning & Development
(Retired)
Froedtert Health
3
Page 12 of 169
RIC MILLER
Principal-in-Charge
MAURA RIORDAN
Senior Project Manager
CHIEF PATRICK MERTEN
Police Chief, Village of Germantown
CONSTRUCTION MANAGER
PROJECT TEAM
MC Group has a staff of experienced professionals that are ready to serve you. We propose to provide the services
relative to your Public Safety Building project with the following team members. This team bring to the Village of
Germantown over 50 years of project development experience (design through construction) experience that
complements Village’s Police Department team. Ric & Maura are currently wrapping up the very successful new Public
Safety Building project in Port Washington and are anxious to leverage their lessons learned on your project.
RIC MILLER, Founding Partner
As our Founding Partner will serve as the Principal-in-Charge. He will support the team with his extensive project
experience and bring his industry relationships to the table to benefit the project.
MAURA RIORDAN, Team Lead and Senior Project Manager
As Project Team lead and Project Manager, Maura will be your consistent point of contact throughout the project, from
Day One to move-in. She will assure clear communication is maintained with all project stakeholders and will hold all
parties accountable for their roles and responsibilities.
SECTION 2: Project Team
RIC MILLER MAURA RIORDAN
Overall Team Leadership and Accountability Management Project Meetings and Coordination
Client Relationship Contract Negotiations and Modifications
Executive Team Engagement Milestone and Phasing Schedule Development and
Management
Total Project Budget Development Design Meetings and Coordination
Monthly Financial Report Review & Meetings (1x/month) Estimate Reviews
Project Team Development and Governance Support Specialty Vendor Coordination and Management
Pay Application Review
Change Management and Cost Issue Reviews
Project Progress Reporting
Conduct Project Closeout
MC GROUP RESOURCE ROLES & RESPONSIBILITIES
4
Page 13 of 169
RIC
MILLER
PROFILE
Sense of accomplishment is at the root of Ric’s
passion for the construction industry. Ric finds it
very motivating and truly inspiring to experience
the progress on a jobsite week by week and
month by month overseeing and observing
what a diverse group of people have
accomplished. Starting with a University of
Wisconsin Construction Administration degree,
Ric personally brings almost 40 years of
experience in the construction industry to the
table with a valuable mix of 17 years serving the
constructor’s role as CMGC with the balance of
the years serving as Owner’s Representative
leading the project team on the journey to
success.
A lesson that Ric has learned along the journey
in life is that there are certain things that we all
covet, but which we can’t begin to receive until
we first give them away to others. Respect is
one of those things and is a cornerstone of Ric’s
interactions with all people
EDUCATION & EXPERIENCE
BS Construction Administration University of
Wisconsin-Madison
44 years in the Construction industry
PRINCIPAL-IN-CHARGE
SELECTED PROJECT EXPERIENCE
Historic Haymarket Milwaukee Future Museum Project
Milwaukee, WI | $240M
COLLABORATIVE TEAM | MULTIPLE FUNDING SOURCES | MULTIPLE BUILDING/PHASES |
TAX EXEMPT | COMMUNITY ENGAGEMENT | CITY OF MILWAUKEE | DEMOLITION/ABATEMENT
School District of Menomonee Falls - 2016 Referendum Work
Menomonee Falls, WI | $37M
COLLABORATIVE TEAM | MULTIPLE FUNDING SOURCES | MULTIPLE BUILDING/PHASES |
TAX EXEMPT | COMMUNITY ENGAGEMENT | OCCUPIED CAMPUS
Milwaukee Regional Medical Center - Thermal Energy Plant & Distribution System
Milwaukee, WI | $246M
COLLABORATIVE TEAM | MULTIPLE FUNDING SOURCES | MULTIPLE BUILDING/PHASES |
TAX EXEMPT | CITY OF MILWAUKEE | OCCUPIED CAMPUS | DEMOLITION/ABATEMENT
Froedtert Health - Parking Area 6
Milwaukee, WI | $80M
COLLABORATIVE TEAM | MULTIPLE BUILDING/PHASES | TAX EXEMPT | COMMUNITY ENGAGEMENT |
CITY OF MILWAUKEE | OCCUPIED CAMPUS
Cedar Community – The Lofts at Cedar Lake
West Bend, WI | $35M
COLLABORATIVE TEAM | MULTIPLE BUILDING/PHASES | TAX EXEMPT | COMMUNITY ENGAGEMENT |
LOCAL PROJECT | OCCUPIED CAMPUS | PROPERTY DEVELOPMENT
West Bend Badger Middle School
West Bend, WI | $27M
COLLABORATIVE TEAM | MULTIPLE FUNDING SOURCES | MULTIPLE BUILDING/PHASES | TAX EXEMPT |
COMMUNITY ENGAGEMENT | OCCUPIED CAMPUS
CAMPUS West Bend Silverbrook Intermediate School
West Bend, WI | $28M
COLLABORATIVE TEAM | MULTIPLE FUNDING SOURCES | MULTIPLE BUILDING/PHASES |
TAX EXEMPT | COMMUNITY ENGAGEMENT | OCCUPIED CAMPUS
MRMC West Campus Development Project Phase 1
Milwaukee, WI | $54M
COLLABORATIVE TEAM | TAX EXEMPT | COMMUNITY ENGAGEMENT | CITY OF MILWAUKEE |
OCCUPIED CAMPUS
Port Washington Public Safety Building
Port Washington, WI | $35M
COLLABORATIVE TEAM | TAX EXEMPT | COMMUNITY ENGAGEMENT | MULTIPLE DEPARTMENTS |
HIGH PROFILE/PUBLIC PROJECT | PUBLIC PROJECT COMMUNICATIONS
E-One, Inc. Plant 4 Expansion
Ocala, FL | $23.5M
COLLABORATIVE TEAM | PUBLIC SAFETY INDUSTRY | MULTIPLE BUILDING/PHASES |
DEMOLITION/ABATEMENT | COMMUNITY ENGAGEMENT | ACCELRATED SCHEDULE| OCCUPIED
CAMPUS
SECTION 2: Project Team
5
Spartan Emergency Response. Manufacturing Plant Expansion
Brandon, SD | $20M
COLLABORATIVE TEAM | PUBLIC SAFETY INDUSTRY | MULTIPLE BUILDING/PHASES |
DEMOLITION/ABATEMENT | COMMUNITY ENGAGEMENT | ACCELRATED SCHEDULE| OCCUPIED
CAMPUS
Page 14 of 169
MAURA
RIORDAN
PROFILE
Maura brings to MC Group over 20 years of
construction experience managing a wide
variety of projects. From highly complex
healthcare projects here in Wisconsin, to
large-scale tenant buildouts in Chicago, to
managing the design and construction of
projects across the country, Maura has
developed excellent communication skills and
a strong work ethic. She instills a collaborative
team approach in each project to ensure the
client’s needs are met, risks are identified and
mitigated, and the project is completed on
time, on budget and with the highest standard
of quality.
EDUCATION & EXPERIENCE
BS Architecture
University of Illinois, Urbana-Champaign
25 years in Construction Industry
COMMUNITY/INDUSTRY TRAINING
LEED AP
OSHA 30-Hour
Wauwatosa School District Task Force 2075
PROJECT MANAGER
SELECTED PROJECT EXPERIENCE
Historic Haymarket Milwaukee Future Museum Project
Milwaukee, WI | $240M
COLLABORATIVE TEAM | MULTIPLE FUNDING SOURCES | MULTIPLE BUILDING/PHASES
TAX EXEMPT | COMMUNITY ENGAGEMENT | CITY OF MILWAUKEE | DEMOLITION/ABATEMENT
Froedtert Health - Inpatient Support Renovations
Menomonee Falls, WI | $9.4M
COLLABORATIVE TEAM | MULTIPLE BUILDING/PHASES | TAX EXEMPT | CITY OF MILWAUKEE |
OCCUPIED CAMPUS | DEMOLITION/ABATEMENT
Froedtert Health - Sargeant Health Ambulatory Surgery Center
Milwaukee, WI | $7M
COLLABORATIVE TEAM | MULTIPLE FUNDING SOURCES | MULTIPLE BUILDING/PHASES | TAX EXEMPT |
CITY OF MILWAUKEE | OCCUPIED CAMPUS | DEMOLITION/ABATEMENT
Oconomowoc Memorial Hospital - Patient Tower
Oconomowoc, WI | $70M
COLLABORATIVE TEAM | MULTIPLE BUILDING/PHASES | TAX EXEMPT | OCCUPIED CAMPUS |
DEMOLITION/ABATEMENT
Oconomowoc Memorial Hospital - Emergency Department and Sitework
Oconomowoc, WI | $3M
COLLABORATIVE TEAM | MULTIPLE BUILDING/PHASES | TAX EXEMPT | OCCUPIED CAMPUS |
DEMOLITION/ABATEMENT
Oconomowoc Memorial Hospital - Surgery Family Lounge
Oconomowoc, WI | $800K
COLLABORATIVE TEAM | MULTIPLE BUILDING/PHASES | TAX EXEMPT | OCCUPIED CAMPUS |
DEMOLITION/ABATEMENT
Waukesha Memorial Hospital - Mukwonago: Emergency Department & Patient Tower
Mukwonago, WI | $100M
COLLABORATIVE TEAM | MULTIPLE BUILDING/PHASES | TAX EXEMPT | OCCUPIED CAMPUS |
DEMOLITION/ABATEMENT
Truman State University - Campus Planning and Renovations
Kirksville, MO | Varies
MULTIPLE FUNDING SOURCES | MULTIPLE BUILDING/PHASES | TAX EXEMPT | COMMUNITY
ENGAGEMENT | OCCUPIED CAMPUS | DEMOLITION/ABATEMENT
Children’s Wisconsin - Pediatric ICU Expansion Project
Milwaukee, WI | $26M
COLLABORATIVE TEAM | MULTIPLE BUILDING/PHASES | TAX EXEMPT | CITY OF MILWAUKEE |
OCCUPIED CAMPUS
SECTION 2: Project Team
6
Froedtert Health - Parking Area 6
Milwaukee, WI | $80M
COLLABORATIVE TEAM | MULTIPLE BUILDING/PHASES | TAX EXEMPT | COMMUNITY ENGAGEMENT |
CITY OF MILWAUKEE | OCCUPIED CAMPUS
Port Washington Public Safety Building
Port Washington, WI | $35M
COLLABORATIVE TEAM | TAX EXEMPT | COMMUNITY ENGAGEMENT | MULTIPLE DEPARTMENTS |
HIGH PROFILE/PUBLIC PROJECT | PUBLIC PROJECT COMMUNICATIONS
Page 15 of 169
SECTION 3
Experience
“[We] extend our sincere appreciation for the leadership
and guidance that you [Ric Miller] and the MC Group have
provided in managing our complex campus Thermal Power
Plant Project. Your organization and ongoing management
of the many aspects of the project allowed our
administration and board comfort and confidence over the
entire 5-year journey. Your meticulous management and
monthly reporting of the detailed project financial status
allowed MRMC Thermal and the campus members to invest
project savings into plant reliability and efficiency-added
features as the project proceeded, giving us far more in the
end than we originally planned. Thanks for guiding us down
that successful path.”
Mark Geronime, PE | Vice President of Operations
Milwaukee Regional Medical Center Thermal Services, Inc
7
Page 16 of 169
MC GROUP’S PROVEN RECORD OF SUCCESS
and deep excavations adjacent densely populated and
busy campuses, just feet away from the busiest Emergency
Department in Milwaukee County. Our unique experiences
also range to oversight of sensitive archaeological
excavations of pauper graves, with careful removal of
human remains through collaboration with UW Milwaukee
archaeologists.
While these unique experiences may not directly apply to
the Village of Germantown’s New Police Department
building project, it demonstrates our capabilities to develop
unique and collaborative solutions.
Services for clients and projects routinely include tracking
progress, schedule, budget, costs, cost forecasting,
diversity and inclusion engagement, as well as helping to
guide major decisions and navigate project changes.
SECTION 3: Experience
At MC Group, we have found that a collaborative project
team has improved outcomes and increased project
delivery speed, while promoting cost efficiency and
reducing overall risk to both the Owner and the project. An
outcome of completing decades of successful and
collaborative projects, MC Group has developed strong,
professional relationships with most qualified AE and CMAR
firms in the regional market, and look forward to continuing
this tradition working with FGM Architects and the selected
CM team members.
Utilizing the collaborative team approach that MC Group
outlines in this proposal, the Village of Germantown can take
advantage of a huge range of project experience. Ric, and
Maura have extensive project experience with highly
complex and technical campus and building construction,
including hospitals, schools, corporations, and industrial
facilities. Project examples include multi-story vertical high-
rise expansions above high acuity inpatient units
for extremely vulnerable transplant patients, and demolition
OWNER’S REPRESENTATION EXPERTISE AND EXPERIENCE
8
Page 17 of 169
CITY OF PORT WASHINGTON
PUBLIC SAFETY BUILDING
Originally established with a $35 million total project budget, the Port
Washington Public Safety Building project was successfully value-
engineered to approximately $32 million through a disciplined and
highly collaborative preconstruction process led by MC Group as the
Owner’s Representative.
The new Public Safety Building will consolidate police, fire, and civic
functions into a unified shared campus while modernizing and
expanding the City’s existing public safety infrastructure.
The police component of the facility includes secure police
administration space, a virtual indoor training range, secure evidence
storage, a squad garage with integrated sallyport operations, and
dedicated emergency operations space designed to support critical
incident management and continuity of operations. The fire
department portion includes fire administration, a six-bay apparatus
area, and full-time living quarters designed to support 24/7 operations.
Shared spaces between the police and fire functions include a public
lobby, large training and courtroom space, and a shared fitness room
intended to support both operational readiness and staff wellness.
As Owner’s Representative, MC Group has led overall project
coordination and management efforts including schedule oversight,
budget management, design-phase coordination, value engineering,
procurement support, stakeholder engagement, construction
administration, and ongoing communication between the City,
consultants, contractors, and user groups. MC Group continues to
guide the project through active construction with occupancy
anticipated in Summer 2026.
• Preconstruction Services/Oversight
• Bidding/GMP/Total Project Budget
Development
• Construction Administration/Oversight
• Project Financial Management
• Project Management of Owner's FFE
INDUSTRY
Public Safety
YEAR
2026
FINANCIAL
$35M Overall – trending to $32M
ARCHITECT
Bray Architects
CONSTRUCTION
C.D. Smith Construction
Collaborative Team
Approach Tax-Exempt Occupied Campus High-Profile / Public
Project
Public Project
Communications
Community
Engagement Municipal Project Public Safety Project
PROJECT ELEMENTS
SERVICES
SECTION 3: Experience
9
Page 18 of 169
WISCONSIN MUSEUM OF NATURE &
CULTURE
FUTURE MUSEUM
Located on 2.4-acres in the Haymarket neighborhood, adjacent
the city’s Deer District, the Future Museum will be the largest
cultural project in Wisconsin’s history. Following abatement and
demolition of several existing buildings, an approx. 200,000 SF,
five-story building will house an open atrium gathering space, four
floors of exhibits, two gardens (one rooftop) and a butterfly
vivarium. A parking structure and offset collections storage are
also planned.
MC Group is helping to guide the Museum through each
milestones necessary to secure funding through multiple sources,
including State, County and private funding. The funding process
also includes pursuit of other public funding sources such as
brownfield funding and New Market Tax Credit allocations.
SERVICES
• Preconstruction Services/Oversight
• Bidding/GMP/Total Project Budget Mgmt
• Project Scope Validation
• Construction Administration/Oversight
• Project Financial Management
• Project Management of Owner’s FFE
• Project Close-out/Oversight
INDUSTRY
Cultural, Educational
YEAR
2022-Ongoing
FINANCIAL
$240M Overall
ARCHITECT
Kahler Slater/Ennead
CONSTRUCTION
Mortenson
Collaborative Team
Approach Tax-Exempt Multiple
Building/Phases Demolition/Abatement
Multiple Funding
Sources City of Milwaukee Community
Engagement
High Profile/ Public
Project
PROJECT ELEMENTS
SECTION 3: Experience
10
Page 19 of 169
MILWAUKEE REGIONAL MEDICAL CENTER
REDEVELOPMENT PHASES 1 THRU 3
The Milwaukee Regional Medical Center (MRMC) project encompasses a series of
projects, the majority of which are west of 92nd St, north of Wisconsin Avenue,
east of 141 and south of Watertown Plank road, consisting of approximately 80
acres. The current projects consist of mass grading across the 80 acres with
relocation of removed materials on site, roadway design, installation of
underground infrastructure and construction of 0.35 miles of 95th Street, 0.26 miles
of Doyne Extension, 0.12 miles reconstruction of 92nd Street, the driveway
relocation of Kathy's House, surface parking lot construction and retention pond
expansion. The project budget is approximately $54M and the Owner's
Representative project duration is 30 months.
The role of MC Group on this project is to serve as MRMC's principal point of
contact and liaison between the Engineer, CM and MRMC's Consultants
throughout the project. MC Group monitors and ensures quality, timely and cost-
sensitive design and construction while maintaining professional relationships with
all parties. MC Group is also responsible for monitoring, reporting and identifying
discrepancies in the budget or schedule and provide early warning of problems
that may affect either, as well as reviewing Applications for Payment, invoices
and Change Orders, making recommendations to MRMC.
INDUSTRY
Community, Medical
YEAR
2022-Ongoing
FINANCIAL
$100M Overall
ENGINEER
Graef
CONSTRUCTION
Walbec
Collaborative Team
Approach Tax-Exempt Occupied Campus Demolition/Abatement
Multiple Project Phases City of Milwaukee Community
Engagement
Environmentally
Contaminated Properties
PROJECT ELEMENTS
SERVICES
• Team Selection
• Preconstruction Services/Oversight
• Bidding/GMP/Total Project Budget
Development
• Construction Administration/Oversight
• Project Financial Management
• Project Management of Owner's FFE
SECTION 3: Experience
11
Page 20 of 169
Collaborative Team
Approach Tax-Exempt Occupied Campus Multiple Project Phases
Multiple Funding
Sources
Community
Engagement Utilities Multiple Municipalities
MILWAUKEE REGIONAL MEDICAL CENTER
THERMAL ENERGY PLANT & DISTRIBUTION SYSTEMS
In 2014 the members of MRMC formed MRMC-Thermal with the intent to
purchase, expand, upgrade, and operate the centralized plant. On
4/21/2016 MRMC Thermal closed on the property and proceeded with the
major upgrades and expansion projects with the goal of increasing
reliability, redundancy, and increased efficiency.
The high-risk nature of the business plan, and no ability to fund budget
overages, prompted MRMC to engage Ric Miller's support. Ric was able
to work with Bob Mlynarek to guide the project budget back into
alignment. Throughout the course of the project, with detail monitoring
and forecasting, the project was able to use significant budget savings to
re-invest those dollars into additional system improvements.
The overall budget supported three projects including a temporary boiler
plan, and conversion of the main plan from coal to natural gas while
adding n+ 1 redundancy. The third project focused on distributing chilled
water and steam to multiple landowners and tenants throughout the
MRMC Campus. The 36" and 48" pipelines crossed Watertown Plank Road,
a major thoroughfare providing access to US Hwy 41. From there, the
pipelines had to be distributed throughout the campus to multiple end
users, running parallel and crossing multiple campus roadways. Ric
coordinated and communicated with the project's CMGC and MRMC
Campus' Mark Geronime daily to ensure the project phasing, utility
coordination, and pedestrian and vehicle traffic management prevented
any impacts to the busiest campus in the Milwaukee regional area.
• Team Selection
• Preconstruction Services/Oversight
• Bidding/GMP/Total Project Budget
Development
• Construction Administration/Oversight
• Project Financial Management
• Project Management of Owner's FFE
• Project Closeout Oversight
• Oversight of CMGC Contracting
INDUSTRY
Community, Medical
YEAR
2018
FINANCIAL
$246M
ENGINEER
Burns & McDonnell Engineering
Company, Inc.
CONSTRUCTION
Boldt
PROJECT ELEMENTS
SERVICES
SECTION 3: Experience
12
Page 21 of 169
WEST BEND SCHOOL DISTRICT
2012 Referendum Projects: Silverbrook Middle School Addition
and Green Tree Elementary School Renovations
The 2012-approved $22.8M referendum encompassed a
180,000 SF new addition to the Silverbrook Middle School
providing the students a new food servery and cafeteria, and
a new gym and classrooms. Renovations were performed at
Green Tree Elementary. The work was necessary to support the
District’s realignment strategy based on changing student
enrollment.
Point of interest: the hallways included decorative patterns
that replicated streams and brooks in celebration of the name
of the school and indigenous surroundings.
• Team Selection
• Preconstruction Services/Oversight
• Bidding/GMP/Total Project Budget
Development
• Construction Administration/Oversight
• Project Financial Management
• Project Management of Owner's FFE
INDUSTRY
Community, Education
YEAR
2015
FINANCIAL
$22.8M Overall
ARCHITECT
Eppstein Uhen Architects
CONSTRUCTION
VJS Construction Services
Collaborative Team
Approach Tax-Exempt Occupied Campus Multiple Project Phases
Demolition/Abatement Community
Engagement Municipal Project Public Project
Communications
PROJECT ELEMENTS
SERVICES
SECTION 3: Experience
13
Page 22 of 169
WEST BEND SCHOOL DISTRICT
2009 Referendum Project: Badger Middle School
The 2009-approved $27.4M referendum encompassed much-
needed improvements at Badger Middle School including
partial demolition of the outdated facility which was beyond
its useful-life. A 125,000 SF building addition included new
modern classrooms, and renovations to existing spaces
provided new safe and secure building entries. MC Group
represented the District from referendum approval through
occupancy.
Point of interest: Some historic architectural elements were
salvaged from the original 1925 West Bend high school and
incorporated into this new construction as a means of
preserving the original community historical importance.
• Team Selection
• Preconstruction Services/Oversight
• Bidding/GMP/Total Project Budget
Development
• Construction Administration/Oversight
• Project Financial Management
• Project Management of Owner's FFE
INDUSTRY
Community, Education
YEAR
2009
FINANCIAL
$27.4M Overall
ARCHITECT
Zimmerman Architectural Studios
CONSTRUCTION
VJS Construction Services
Collaborative Team
Approach Tax-Exempt Occupied Campus Multiple Project Phases
Demolition/Abatement Community
Engagement Municipal Project Public Project
Communications
PROJECT ELEMENTS
SERVICES
SECTION 3: Experience
14
Page 23 of 169
MENOMONEE FALLS SCHOOL DISTRICT
DISTRICT WIDE EXPANSION/IMPROVEMENTS
The scope of this project included extensive capital
improvements and upgrades throughout multiple facilities
including the Valley View Elementary School, Shady Lane
Elementary School, North Middle School, and Menomonee
Falls High School. The referendum included a plethora of
capital improvements, facilities upgrades, the mass demolition
of an outdated facility, 128 individual projects at 5 different
locations within the district. Individual cost tracking and
management were developed for each group of projects
under the overall referendum.
• Team Selection
• Preconstruction Services/Oversight
• Bidding/GMP/Total Project Budget
Development
• Construction Administration/Oversight
• Project Financial Management
• Project Management of Owner's FFE
INDUSTRY
Community, Education
YEAR
2018
FINANCIAL
$37.2M Overall
ARCHITECT
Eppstein Uhen Architects
CONSTRUCTION
VJS Construction Services
Collaborative Team
Approach Tax-Exempt Occupied Campus Multiple Project Phases
Multiple Funding
Sources
Community
Engagement Municipal Project Demolition/Abatement
PROJECT ELEMENTS
SERVICES
SECTION 3: Experience
15
Page 24 of 169
SECTION 3: Experience
16
ADDITIONAL PROJECT EXPERIENCE
In addition to the highlighted representative projects on the previous pages, below are additional project examples completed
by MC Group team members that further demonstrate our expertise and experience related to the Village of Germantown
Police Department project.
FROEDTERT HEALTH
SOUTHEAST CAMPUS: CANCER CENTER, CFAC & PARKING
$0.5 billion development of the southeast corner of their campus, including the state-of-the-art
cancer care center and 12-story Center for Advanced Care (CFAC), constructed to house medical
services to support efficient care coordination for specialized medical services including cardiac,
transplant, surgical and interventional care.
COLLABORATIVE TEAM | LOCAL PROJECT | TAX EXEMPT | URBAN SITE | DEI MONITORING
DEMOLITION/ABATEMENT | HIGH PROFILE/PUBLIC PROJECT | COMMUNITY ENGAGEMENT
SUSTAINABLE BUILDING SYSTEMS | NEW SITE DEVELOPMENT
CEDAR COMMUNITY
THE LOFTS AT CEDAR LAKE
$35 million development of the Lofts at Cedar Lake within the Cedar Community senior living campus on
the shores Big Cedar Lake in West Bend WI. Construction progressed through phases to minimized
disruptions and to allow a phased lease/occupancy program all while working on an active campus and
within the 24/7 occupied main facility.
COLLABORATIVE TEAM | LOCAL PROJECT | PROPERTY DEVELOPMENT| TAX-EXEMPT |
MULTIPLE FUNDING SOURCES | OCCUPIED CAMPUS | COMMUNITY ENGAGEMENT
CHILDREN’S WISCONSIN
MILWAUKEE CAMPUS IMPROVEMENT: SURGERY, CRAIG YABUKI TOWER, CENTRAL GENERATOR & SKYWALK BUILDINGS
$385 million redevelopment of the Milwaukee Children’s campus, including the 155,000 sf state-of-the-art
Emergency Department, the 6-story, 237,000 sf Craig Yabuki Tower which houses ambulatory clinical
services, and an 83,000 SF complete renovation-in-place of the existing surgical platform.
COLLABORATIVE TEAM | LOCAL PROJECT | TAX EXEMPT | URBAN SITE | DEI MONITORING
DEMOLITION/ABATEMENT | HIGH PROFILE/PUBLIC PROJECT | COMMUNITY ENGAGEMENT
SUSTAINABLE BUILDING SYSTEMS | NEW SITE DEVELOPMENT
WEST BEND MUTUAL INSURANCE
NEW CORPORATE HEADQUARTERS & UPDATES
$73 million development, this 210,000-square-foot corporate headquarters expansion included open
office areas, private offices, conference and meeting rooms. The project also included a kitchen and
serving area, a fitness center as well as extensive remodeling of their existing facility including doubling the
size of their existing data center.
COLLABORATIVE TEAM | LOCAL PROJECT | DEMOLITION/ABATEMENT | COMMUNITY ENGAGEMENT
SUSTAINABLE BUILDING SYSTEMS | OCCUPIED CAMPUS
E-ONE, INC.
PLANT 4 MANUFACTURING EXPANSION
$23.5 million expansion of their manufacturing plant that manufactures fire apparatus and emergency
vehicles. This 4-phase project adds over 75,000 sf to their current operations in order to meet the growing
industry demands by increasing production by 35%. Project is in construction and scheduled to complete
by first quarter of 2027.
COLLABORATIVE TEAM | PUBLIC SAFETY INDUSTRY | DEMOLITION/ABATEMENT | COMMUNITY ENGAGEMENT
ACCELERATED SCHEDULE | OCCUPIED CAMPUS
Page 25 of 169
SECTION 3: Experience
17
ADDITIONAL PROJECT EXPERIENCE
In addition to the highlighted representative projects on the previous pages, below are additional project examples completed
by MC Group team members that further demonstrate our expertise and experience related to the Village of Germantown
Police Department project.
WISCONSIN ENERGY INSTITUTE
Wisconsin Energy Institute is a new 107,000 SF research and education facility located in the heart of
the science and technology campus at UW-Madison. The building, opened in 2012, is LEED Gold
Certified and uses 52% less than energy code minimum, while supporting essential research that is
focusing on moving the world toward clean energy systems and solutions.
COLLABORATIVE TEAM APPROACH | STATE OF WI FUNDING AND PAY REQUESTS | TAX-EXEMPT | DEI MONITORING NEW
SITE DEVELOPMENT/ENTITLEMENTS | COMMUNITY ENGAGEMENT•URBAN SITE | LOCAL PROJECT | HIGH PROFILE/PUBLIC
PROJECT
CITY OF FITCHBURG LIBRARY
The City of Fitchburg developed the new two-story, 36,000 SF building to house their 60,000 item
collection and serve their growing community well into the future. The LEED Gold certified building
was funded by both public funding and through a Capital Campaign lead by the Friends of
Fitchburg Library.
COLLABORATIVE TEAM APPROACH | TAX-EXEMPT | NEW SITE DEVELOPMENT/ENTITLEMENTS
COMMUNITY ENGAGEMENT | HIGH PROFILE/PUBLIC PROJECT
MADISON CENTRAL LIBRARY
The Madison Public Library is a 120,000 SF redevelopment of the existing 45-year-old building in the
heart of downtown. The new building, opening in 2013, was completely transformed, stripping down
to the structure and adding a vertical expansion to provide a user-centric environment that also
serves as a community destination and enhances Madison’s cultural offerings.
COLLABORATIVE TEAM APPROACH | TAX-EXEMPT|COMMUNITY ENGAGEMENT | URBAN SITE | HIGH
PROFILE/PUBLIC PROJECT
UNITED COMMUNITY CENTER
NEW CONSTRUCTION FOR EARLY LEARNING ACADEMY
$12.1 million, new 3-story, 34,300 SF, Early Learning Academy serving infants to 3K. The building consists of
(17) classrooms, multi-purpose room, indoor and outdoor playground areas, and kitchen. Included the
razing of (7) houses and a daycare building, phase II environmental study, asbestos abatement, utility
disconnects and relocates, and soil testing for the new Early Learning Academy building.
COLLABORATIVE TEAM | CITY OF MILWAUKEE | PROPERTY DEVELOPMENT| TAX-EXEMPT |
MULTIPLE FUNDING SOURCES | OCCUPIED CAMPUS | COMMUNITY ENGAGEMENT
SPARTAN EMERGENCY REPONSE
MANUFACTURING PLANT EXPANSION
A $20 million expansion of their manufacturing plant that manufactures fire apparatus and emergency
vehicles. This multi-phase project adds nearly 56,000 sf to their current operations in order to meet the
growing industry demands by increasing production by 40%. The Project is in construction and scheduled
to complete in less than a year.
COLLABORATIVE TEAM | PUBLIC SAFETY INDUSTRY | DEMOLITION/ABATEMENT | COMMUNITY ENGAGEMENT
ACCELERATED SCHEDULE | OCCUPIED CAMPUS
Page 26 of 169
SECTION 3: Experience
18
MC GROUP REFERENCE
Page 27 of 169
SECTION 4
Project Approach
“Ric and his team brought overarching leadership
and expertise in managing the entire process from
initial planning and smart budget planning through
design, construction and occupancy. They brought a
calm, calculated and steady hand to the
complexities of our facilities initiatives.”
Sue Smith | President, Nativity Jesuit Academy
19
Page 28 of 169
Drawing from MC Group’s experience
supporting complex public safety
projects, including the Port Washington
Public Safety Building that combines
both police and fire department
operations within a single facility, we
understand the operational and
security challenges associated with
modern law enforcement and
emergency services facilities. We
recognize the importance of balancing
operational requirements, security
considerations, constructability, budget
constraints, and long-term functionality
throughout the planning and
construction process.
MC Group will function as an extension
to the Department’s staff and to the
Village’s leaders while always acting in
the best interest of the Owner without
conflicting interests. We will bring our
extensive experience, knowledge,
processes and tools to guide the Project
Team to successful outcomes by all
measures.
PROJECT UNDERSTANDING
MC Group understands the Village of Germantown is undertaking the development of a new Police Department
facility at N122W17177 Fond du Lac Avenue in Germantown, Wisconsin, on the site of the former Department of
Public Works (DPW) facility. The project also includes utility infrastructure sanitary sewer and water main
extensions that will be overseen by the Village Engineer.
The Village’s goal is to deliver a modern, purpose-built public safety facility that supports current operational
needs while accommodating future growth, evolving service demands, and modern law enforcement best
practices. The facility is anticipated to include specialized public safety components such as a live-fire indoor
training range, secure evidence storage, sallyport operations, emergency operations space, and integrated
security and technology systems requiring careful coordination throughout design and construction.
The Village has selected the Architectural/Engineering (A/E) team and is in the process of selecting the
Construction Manager at Risk (CMAR). MC Group will complete the team roster as Owner’s Representative to serve
as the Village’s advocate by providing project leadership, coordination, budget oversight, schedule management,
and strategic guidance necessary to support successful project delivery below the Village’s established $35 million
Total Project Budget.
SECTION 4: Project Approach
20
Page 29 of 169
SECTION 4: Project Approach
21
PHASE 1: DESIGN & PRE-CONSTRUCTION PHASE 2: BIDDING & PROCUREMENT
• Engagement and execution of due diligence to
support the project development
• Review and alignment of AE and CM contracts
• Planning & Schedule development
• Budget development, validation & designing to
target budget
• Aligned Project governance and decision-making
• Design deliverables review with users
• Cost estimating and project options review
• Equipment layout and procurement plan
• Disruption avoidance and site utilization planning
• Permitting and AHJ approvals
• Deliver complete and transparent bids that inform the
final GMP
• GMP establishment and contracts
PHASE 3: CONSTRUCTION PHASE PHASE 4: OCCUPANCY & CLOSE-OUT
• Budget and schedule management
• Pay application review and approvals
• Change management with Owner team
• On-site status review and observations
• Owner systems coordination
• Activation planning and support
• Occupancy permitting and approvals
• Activation and move execution
• Customer training and commissioning
• Project closeout documentation and warranties
• Project costs and contract close-out
We have organized out approach and services by each phase of your project as was organized in your RFP and
offer our estimate on duration of each phase along with the key outcomes by phase. While the Pre-Design phase
only represents 25% of the overall project duration, you will see how critical the outcomes of this phase are to the
successful delivery and activation of your project. We are anxious to join forces with your team to integrate our
plans and execute to achieve the Village of Germantown for the future.
DESIGN & PRE-
CONSTRUCTION
7 months
CONSTRUCTION PHASE
14 months
OCCUPANCY &
CLOSE-OUT
3 months
BIDDING &
PROCUREMENT
2 months
Our Project Approach, how we intend to work with your team, and outlined services is
comprehensive to the services outlined and requested in your RFP.
PROJECT PHASING & KEY OUTCOMES
PROJECT APPROACH
Our approach is focused on efficiency, cost-effectiveness, and
collaboration with your team and all project stakeholders,
ensuring a streamlined process and successful project delivery.
Based on our extensive experience from preconstruction to
construction management and project oversight, we have
developed a scope of services tailored specifically to meet the
needs of your projects while avoiding duplication of efforts with
the Architect and CMAR. Our goal is to work seamlessly with the
Village of Germantown’s project team, leveraging our expertise
to add value and support the successful completion of the
project.
Page 30 of 169
SECTION 4: Project Approach
PHASE 1: DESIGN & PRE-CONSTRUCTION PHASE
1 Conduct “Kick-Off” Meeting
Meet with Village representatives, A/E team, CMAR, and key stakeholders to confirm project goals, operational
priorities, communication protocols, reporting expectations, decision-making processes, and project success criteria.
Establish meeting cadence, information flow, and project coordination procedures.
2 Review Existing Project Information & Due Diligence
Review available project documentation, studies, planning materials, contracts, and due diligence efforts to
understand project status, accomplishments, risks, and immediate action items. Evaluate needs related to surveys,
geotechnical work, utilities, environmental matters, permitting, and validation of specialized public safety design
requirements including the live-fire range, IT/security systems, and specialized HVAC systems.
Determine what imminent planning resources may be necessary to engage to further advance the due diligence
and planning phases of the project.
3 Review Architect / Engineer Agreement
Review the A/E agreement and provide recommendations regarding scope alignment, deliverables, responsibilities,
project controls, and potential clarifications or amendments supporting the Village’s interests.
4 Review CMAR Agreement
Review the CMAR agreement and provide observations and recommendations regarding contract terms, risk
allocation, project controls, procurement requirements, GMP development, and overall contractual alignment with
project goals.
5 Support Land Acquisition & Entitlement Activities
Because the Fond du Lac Avenue site is already owned by the Village and zoned Institutional, MC Group will assist the
Village with remaining site due diligence, permitting, utility extensions, and closing-related activities as necessary to
support timely project advancement.
6 Develop Master Project Schedule
Develop and maintain an integrated Master Project Schedule encompassing planning, design, permitting,
procurement, construction, commissioning, and occupancy milestones. Monitor schedule risks, long-lead
procurement items, phasing requirements, and critical path activities supporting the targeted 2028 occupancy.
7 Develop & Maintain the Total Project Budget
Establish and maintain a comprehensive Total Project Budget and project cost tracking system inclusive of
construction costs, owner-direct costs, soft costs, contingencies, escalation, and forecasted exposures. Total Project
Budget includes Construction Costs, Design and Management Fees, Soft Costs, Owner's Equipment, Appliances,
Furniture and Furnishings, IT/Phone Systems, Audio Visual Systems, Security Systems, Signage & Graphics and other
Owner procured items necessary to deliver a completed project.
8 Establish Project Meetings & Reporting Structure
Establish regular coordination meetings, agendas, action item tracking, reporting responsibilities, and project controls
necessary to monitor progress, drive accountability, and support timely decision-making.
22
Page 31 of 169
SECTION 4: Project Approach
PHASE 1: DESIGN & PRE-CONSTRUCTION PHASE (continued)
9 Manage Design Phase Planning & Coordination
Coordinate progression through schematic design, design development, and construction document phases by
establishing design schedules, milestones, deliverables, and decision points aligned with project goals, budget, and
schedule.
10 Review Design Progress & Cost Estimating
Coordinate and audit CMAR cost estimates at established design milestones to ensure the project is consistently
"designed to budget” rather than "priced to completed design". Review estimates, identify cost drivers, evaluate
value management opportunities, and protect operational requirements.
11 Manage Approvals & Permitting Strategy
Coordinate with the project team to develop and maintain a comprehensive approvals, permitting, and regulatory
compliance schedule supporting uninterrupted project progression.
12 Establish Design Milestones & Deliverables
Facilitate planning and design meetings, establish milestone deliverables, and monitor completion of project
objectives within the approved overall schedule.
13 Evaluate Energy & Operational Efficiency Opportunities
Review Focus on Energy opportunities, sustainability measures, value engineering concepts, operational efficiencies,
and lifecycle considerations supporting long-term facility performance.
14 Develop Owner-Direct Cost Estimates
Coordinate development of cost estimates for owner-direct project categories including IT, security, AV, FF&E,
kitchen equipment, specialty systems, and other non-construction costs for inclusion in total project budget reporting.
15 Maintain Project Cost Tracking & Reporting
Maintain MC Group’s Total Project Cost Status Report (TPCSR) and related cost logs to provide current,
comprehensive, and audit-ready financial tracking throughout the project.
23
MANAGING PROJECT TIME
▪ Establish key project milestones and keep in clear
focus with entire Project Team
▪ Assure Project Team commitments through
collaborative planning and understanding of
each stakeholders needs to succeed
▪ Assess time and schedule impacts with all project
changes
▪ 6-week look ahead schedules essential to day-to-
day planning
▪ Regular schedule updates throughout project
Page 32 of 169
SECTION 4: Project Approach
PHASE 2: BIDDING & PROCUREMENT PHASE
16 Review Procurement & Bid Strategy
Review CMAR subcontractor procurement strategy, trade package structure, invited bidder lists, bid coverage, and
budget allocations by trade division. Support compliance with municipal procurement requirements, Wisconsin
statutes, and Village priorities related to local or M/WBE participation if applicable.
Align the current overall budget values by bid division so that each bid division has an established budget that is
consistent with the scope included within each bid division solicitation.
17 Monitor Trade Bidding Process
Monitor subcontractor bidding activities to promote competitive pricing, adequate bid participation, fair
procurement practices, and alignment between bid results and project budget objectives.
18 Support Bid Documentation & Selection Process
Assist in documenting bid results, post-bid scope reviews, recommendation summaries, budget variances, and
contractor selection activities for trade packages and procurement decisions.
19 Support GMP Development & Review
Assist in development and review of the Guaranteed Maximum Price including schedule of values, bid tabulations,
allowances, contingencies, general conditions, exclusions, qualifications, contract documents, and schedule
assumptions. The GMP Amendment and associated exhibits are critical to enforcement of the CMAR's obligations
and compliance to the many business terms.
20 Monitor Schedule, Phasing & Constructability
Review schedule sequencing, construction phasing, logistics, and constructability considerations to maintain
alignment with project goals, operational requirements, and late 2028 occupancy target.
21 Review Safety, Site Logistics & Disruption Avoidance Plans
Review CMAR safety plans, site utilization plans, logistics strategies, and disruption mitigation procedures to confirm
adequate planning for project execution.
24
MANAGING PROJECT COSTS
Financial management is essential in the success of any project. MC Group has been a leader in
developing simple yet proven proprietary financial systems and processes.
We work closely with the Project Team – especially your Construction Manager – to proactively
understand costs, mitigate risks, and forecast the overall budget effectively to support the Village
of Germantown.
Contingency Waterfall
Key elements of our approach include the following:
• Real-time cost tracking and forecasting in the
TPCSR
• Regular Change Management meetings with the
CM and Owner to review potential risks and
resolve cost impacts fair and reasonably
• Cost Event Log updated regularly to include
approved and anticipated cost issues
• Rigorous Pay Application review to assure all costs
are in accordance with contract terms
• Contingency Waterfall to understand the overall
financial Project Health
Page 33 of 169
SECTION 4: Project Approach
PHASE 3: CONSTRUCTION PHASE
22 Manage Project Communications
Facilitate project communications and information management among the Village, A/E team, CMAR, vendors, and
stakeholders to support efficient coordination and issue resolution.
23 Construction Observation & Progress Monitoring
Attend progress meetings and conduct regular site visits to monitor schedule performance, construction progress,
quality of workmanship, and compliance with approved plans, specifications, and high-security operational
requirements.
24 Facilitate Issue & Dispute Resolution
Assist the project team in proactively identifying, managing, and resolving project issues, conflicts, and disputes
before they negatively impact budget, schedule, or project relationships.
25 Maintain Construction Cost Controls
Continue maintaining project cost reports, forecasts, commitments, and financial summaries. Review and
recommend action on pay applications, budget transfers, contingencies, and other project financial matters.
Review, log and document all cost commitments and invoices in an accurate, comprehensive and
contemporaneous manner allowing for real time reporting and accurate cost projections.
26 Review Change Orders & Claims
Review, evaluate, negotiate, and recommend disposition of change orders and budget transfers, claims, and
related financial adjustments in coordination with Village representatives.
27 Provide Weekly Project Reporting
Provide concise weekly project updates summarizing completed activities, upcoming milestones, schedule status,
budget considerations, and emerging issues.
28 Provide Executive Reporting
Provide monthly executive reporting to Village leadership and governing bodies summarizing schedule, budget,
procurement status, project progress, open issues, and photographic documentation as appropriate. Present in-
person at Village Public Meetings.
29 Review Contractor Pay Applications
Review contractor pay applications and supporting documentation to verify compliance with contract
requirements, project progress, approved changes, and applicable billing procedures. Record findings on the
monthly generated Pay Application Review Forms. Track open observations until mutually resolved.
30 Coordinate Owner-Direct Procurement Activities
Assist the Village in planning, procurement coordination, scheduling, and integration of owner-direct systems,
equipment, furnishings, technology, and specialty operational items. It is critical to begin planning these various
systems early in the design phase so that architecturally significant elements are properly accommodated, and
systems installation is ready and progresses sequentially and on time during construction.
25
Page 34 of 169
SECTION 4: Project Approach
PHASE 4: OCCUPANCY & CLOSE-OUT PHASE
31 Provide Occupancy / Activation Guidance
Provide general advisory support regarding occupancy, activation, and move planning coordination. Assist Owner's
designated representatives in their planning and implementation of the related activities. Implementation of the pre-
move and move services are assumed to be by Department internally designated individuals. MC Group can take
on select tasks as specifically requested as an additional service if directed.
32 Manage Project Close-Out & Commissioning Support
Coordinate project close-out activities performed by designated and responsible parties including punch lists,
commissioning, training, final documentation, warranty turnover, financial close-out, and testing of critical systems
including security systems, evidence storage controls, range ventilation, and other specialized operational
components.
33 Post-Occupancy Support
Remain available to assist the Village in addressing issues arising during transition, occupancy, warranty, and early
operational periods.
26
Page 35 of 169
SECTION 4: Project Approach
PROJECT TOOLS
The following are samples of project tools that MC Group uses to track, measure, manage and achieve success.
These tools drive timely decision making, ensure budget accountability, and make sure there are no surprises.
Communication to internal and external stakeholders is also key to successful outcomes. These tools use
collaborative processes to draw out critical data and present it in a clear, concise and logical manner that produces
confidence in the process and its outcomes.
Choosing by Advantage (CBA)
Decision Matrix
CBA Weighting
Data Driven Selections
Project Schedule Management
Pull Planning
Schedule Mapping
Total Project Cost Summary
Report/Cost Management
Monthly/Weekly Reports
Contingency Waterfall
Financial Risk Management
Pay Application and
Invoice Reviews
A3 One-Page Analyses
Weighing Options vs. Priorities
27
Page 36 of 169
ADDED VALUE
MC Group has many examples of how we bring added value to our Owner’s every day as part of our services, and
they are supported by the key things we bring as a steward of your project. At the heart of our ability to drive value
into all of our projects includes the following attributes.
SECTION 4: Project Approach
We provide Owner’s Representation
Services, and that’s all that we do. We
aren’t real estate developers that
provide Owner’s Representation
Services on the side as fill in work. We
aren’t a construction firm that dabbles
in Owner’s Representation Services. We
only provide Owner’s Representation
Services and we do it very well.
MC Group has been serving some of
the most notable clients in Southeast
Wisconsin for the past 25 years. No
other firm has been providing
Owner’s Representation Services in
this region as long as we have.
MC Group has extensive experience
in public institutional projects. We
know how to manage and how to
communicate to all stakeholders and
interested parties in a professional
manner that always represents you,
our client.
Expert Owner’s
Representation Services
Proven Track Record in
Southeastern Wisconsin
Extensive Market Experience
and Expertise
MC Group is the Owner’s
Representative Services leader in this
market. We’ve developed specific
management systems and tools that
guide the project team through the
project journey to success. The MC
Group systems and tools have been
developed, honed, time-tested and
proven to be highly effective.
MC Group has a team of executive-
level resources that have worked in this
industry and market for a collective of
100+ years. This depth of experience
provides our clients with advice and
guidance that has proven results in
achieving client goals.
MC Group is highly interested in
joining your team for this challenging
and important project. We’re ready
to go, our project approach is ready
to execute immediately.
Effective Leader
in Projects
Unparalleled Executive
Experience
Ready to Jumpstart
Your Project
28
Page 37 of 169
SECTION 5
Compensation
“I want to express a thank you to you and the MC Group in
helping us plan and implement our new Distribution Center
facility in Germantown. Throughout the entire project there
was a high degree of security knowing that the MC Group
was protecting our business in all dealings with the general
contractor and architect. I look forward to working with you
again.”
Jeff Stawicki | Senior Director, Distribution Operations &
Logistics
Airgas
29
Page 38 of 169
OWNER REPRESENTATION SERVICES COMPENSATION
SECTION 5: Compensation
We propose the following 2026 hourly rates which are inclusive of all costs except expenses as noted below which will be invoiced
in addition to the fees. We are offering a 5% discount to our standard rates for a preferred client discount. The rates are subject to
a 3.0% increase on the first of each year starting in 2027.
Proposed Hourly Rates
In accordance with the RFP we offer the following proposed lump sum fees organized by project phase. We have estimated the
likely durations based on information provided in the RFP. Fee amount will be subject to adjustments, credits or adds based on the
actual schedule that is developed by the Project Team and accepted by Owner.
Project Phases & Fee Estimate
Standard reimbursable expenses which include mileage at the IRS rate and parking costs will be invoiced in addition to the hourly rate at cost
times a multiplier of 1.0. Items such as phone/IT costs, office supplies, etc. are included within the hourly fee and therefore are not considered
reimbursable expenses. Extraordinary expenses, such as overnight travel, outsourced document reproduction costs, etc. are notincluded and
if pre-approved and incurred will be cause for adjustment of the above estimated fee amount.
Phase 2: Bidding & Procurement Phase
Duration: 2 months Assumed Time Period: 1/1/2027 through 3/1/2027
Lump Sum Fee for this phase: 2 months x $5,925/hour = $11,850
Ric Miller,
Principal-in-Charge Rate
Maura Riordan,
Sr. Project Manager Rate
Christina Markham,
Project Coordinator Rate
Standard Rate $244.43/hour $128.34/hour $97.86/hour
Proposed Rate $232.21/hour $216.92/hour $92.97/hour
Phase 4: Occupancy & Close-Out Phase
Duration: 3 months Assumed Time Period: 4/1/2028 through 7/1/2028
Lump Sum Fee for this phase: 3 months x $8,000/month= $24,000
Total Proposed Fees: $236,540
(For reference – the proposed fee is 0.67% of the $35M Project Budget)
Estimated Expenses: $7,500
Phase 1: Design & Pre-Construction Phase
Duration: 7 months Assumed Time Period: 6/1/2026 through 1/1/2027
Lump Sum Fee for this phase: 7 months x $8,970/month= $62,790
30
Phase 3: Construction Phase
Duration: 14 months Assumed Time Period: 3/1/2027 through 4/1/2028
Lump Sum Fee for this phase: 14 months x $9,850/month= $137,900
Hourly Rates
Page 39 of 169
SECTION 6
Insurance
“Because of MC Group’s involvement in the project, and
the amount of work, follow up and coordination they
provided, more time than I can estimate was saved for City
Police and Fire command personnel to work on other
department business or to really research key aspects of
construction and wants. They truly took much of the
workload off of city staff, and made the whole experience
less stressful, and more efficient than, in my opinion, it would
have otherwise been. I am happy to say that they were
integral to the project completing on time and under
budget.
Based on our experience, I would strongly recommend MC
Group for similar public safety and municipal facility
projects.”
Craig Czarnecki| Captain of Police
Port Washington Police Department
31
Page 40 of 169
MC GROUP INSURANCES
SECTION 6: Insurance
32
Page 41 of 169
Personal Message from Ric Miller | MC Group
We are honored to be considered for this critical
project, one that will be a major addition to this
local community. With our decades of historical
experience, stakeholder relationship building
skills, and knowledge of the current project and
schedule implications, we truly feel that our
team is the most qualified and best choice for
Betty Brinn Children’s Museum. Our team looks
forward to the next step in the process and the
opportunity to develop a trusted partnership.
Over $4 billion
in successful projects
Strong Commitment to
Community Service
Local, present and
experienced in
Wisconsin regional market
Extensive experience
with local AE and CM firms
Competitive fee
with minimal expenses
A State of Wisconsin
Women-Owned Business
(WBE)
25+ Years specializing in
Owner’s Representative services
Experienced senior &
executive level team,
ready and available to start
Well-established reputation
for building consensus
amongst stakeholders and
fostering effective decision-making
Proven success in delivering
high-quality projects within
established budgets
Action-focused approach
that drives projects to on time
successful completionWHY MC GROUP?
Page 42 of 169
Page 43 of 169
OWNER REPRESENTATION SERVICES COMPENSATION
SECTION 5: Compensation
We propose the following 2026 hourly rates which are inclusive of all costs except expenses as noted below which will be invoiced
in addition to the fees. We are offering a 5% discount to our standard rates for a preferred client discount. The rates are subject to
a 3.0% increase on the first of each year starting in 2027.
Proposed Hourly Rates
In accordance with the RFP we offer the following proposed lump sum fees organized by project phase. We have estimated the
likely durations based on information provided in the RFP. Fee amount will be subject to adjustments, credits or adds based on the
actual schedule that is developed by the Project Team and accepted by Owner.
Project Phases & Fee Estimate (revised 5/27/2026)
Standard reimbursable expenses which include mileage at the IRS rate and parking costs will be invoiced in addition to the hourly rate at cost
times a multiplier of 1.0. Items such as phone/IT costs, office supplies, etc. are included within the hourly fee and therefore are not considered
reimbursable expenses. Extraordinary expenses, such as overnight travel, outsourced document reproduction costs, etc. are notincluded and
if pre-approved and incurred will be cause for adjustment of the above estimated fee amount.
Phase 2: Bidding & Procurement Phase
Duration: 2 months Assumed Time Period: 1/1/2027 through 2/28/2027
Lump Sum Fee for this phase: 2 months x $5,925/hour = $11,850
Ric Miller,
Principal-in-Charge Rate
Maura Riordan,
Sr. Project Manager Rate
Christina Markham,
Project Coordinator Rate
Standard Rate $244.43/hour $128.34/hour $97.86/hour
Proposed Rate $232.21/hour $216.92/hour $92.97/hour
Phase 4: Occupancy & Close -Out Phase
Duration: 3 months Assumed Time Period: 7/1/2028 through 9/30/2028
Lump Sum Fee for this phase: 3 months x $8,000/month= $24,000
Total Proposed Fees: $236,540
(For reference – the proposed fee is 0.67% of the $35M Project Budget)
Estimated Expenses: (mileage at IRS rate): $2,500
Phase 1: Design & Pre -Construction Phase
Duration: 7 months Assumed Time Period: 6/1/2026 through 12/31/2026
Lump Sum Fee for this phase: 7 months x $8,970/month= $62,790
30
Phase 3: Construction Phase
Duration: 16 months Assumed Time Period: 3/1/2027 through 6/30/2028
Lump Sum Fee for this phase: 14 - 16 months x $9,850/month, capped at = $137,900
Hourly Rates
Page 44 of 169
BUSINESS OF THE BUILDING CONSTRUCTION OVERSIGHT COMMITTEE
MEETING DATE: June 11, 2026
PLACEMENT: Action Item
ITEM TITLE: Construction Manager at Risk services related to the Police Facility
project (DISCUSSION / ACTION)
SUBMITTED BY: Patrick Merten, Police Chief
SUMMARY EXPLANATION:
ATTACHMENT:
1. CMAR Summary Proposal
2. CG Schmidt
3. Kraus-Anderson
4. Moore Construction
STAFF RECOMMENDATION:
ACTION BY COMMITTEE:
Page 45 of 169
BUSINESS OF BUILDING CONSTRUCTION OVERSIGHT COMMITTEE
GERMANTOWN, WI
MEETING DATE: June 11, 2026
AGENDA ITEM: Action
ITEM TITLE: Construction Manager at Risk for New Police Department
SUBMITTED BY: Chief Patrick Merten
SUMMARY EXPLANATION:
The Village has concurrently retained FGM Architects as the Architectural/Engineering (A/E)
team to lead the design of the new Police Department facility. The selected Construction
Manager at Risk (CMAR) will be integrated into the project team at the 30% Design Milestone to
provide pre-construction services, cost estimating, scheduling assistance, and construction
phase management.
The Village is also in the process of onboarding an Owner’s Representative (OR) who will serve
as the Village’s primary advocate throughout the project. The OR will help ensure the project
remains on schedule, within the approved budget, and meets the operational, security, and
functional requirements of a modern law enforcement facility. Current preliminary cost estimates
place the project at approximately $34.5 million.
The Police Department Working Group issued a Request for Proposal (RFP) for CMAR services
to six qualified firms. The Village received proposals from the following three firms:
• CG Schmidt
• Kraus-Anderson
• Moore Construction
The working group is currently reviewing and evaluating each proposal based on the following
criteria:
• Relevant Experience – 5 points
• Project Team – 30 points
• Pre-Construction Approach – 20 points
• Schedule and Logistics – 15 points
• Fee Proposal – 10 points
• Safety and Quality Management – 10 points
• Interview – 10 points
The PD Working Group and Owner’s Representative will conduct interviews with all three firms
on June 17, 2026. Following the interviews, each firm will be scored and ranked on a 100 -point
scale. The committee will then provide a recommendation for CMAR selection to the Village
Board for consideration and approval.
Thank you for your consideration of this request.
ATTACHMENT: ORDINANCE___ RESOLUTION_____ OTHER__X__
RECOMMENDATION:
Recommendation for the PD Working Group to proceed with interviews on June 17, 2026, and,
following completion of the evaluation process, to return to the Village Board with a
recommendation for the selection of a Construction Manager at Risk (CMAR) for the Police
Department facility project.
Page 46 of 169
GERMANTOWN POLICE DEPARTMENT
FACILITY CONSTRUCTION
PROPOSAL FOR CONSTRUCTION MANAGER AT RISK (CMAR)
May 29, 2026
Page 47 of 169
May 29, 2026
Chief Patrick Merten
Police Chief
Germantown Police Department
Village of Germantown
N112 W16877 Mequon Road
Germantown, WI 53022
Dear Chief Merten and Ms. Barth,
Thank you for the opportunity to submit CG Schmidt’s qualifications to serve as Construction Manager at Risk for the new
Germantown Police Department facility. We are honored that the Village recently selected CG Schmidt as CMAR for the
Fire Station renovation project. As we begin working with Village leadership and staff on that important public safety
investment, we appreciate the opportunity to continue building upon those relationships through this project.
Risk Management for a Highly Specialized Public Safety Facility
This facility is far more than a standard municipal building. Secure circulation, detention functions, evidence handling,
tactical training, emergency operations, public access, and indoor live-fire training all must operate together within one
highly coordinated environment. Successfully delivering a facility of this complexity requires disciplined planning, strong
communication, and proactive coordination from the earliest stages of design.
Early Infrastructure & Site Risk Reduction
The project also presents significant infrastructure and site coordination challenges, including utility extensions,
stormwater management, and subsurface conditions. CG Schmidt brings relevant experience managing complex site and
infrastructure work throughout Southeastern Wisconsin, including projects involving challenging bedrock conditions and
municipal utility coordination. That experience helps reduce uncertainty early and supports more reliable budgeting and
scheduling throughout the project.
Transparent Municipal Partnership
Equally important, we understand the responsibility of guiding a transparent municipal process. As a CMaR with no self-
perform work, CG Schmidt approaches this role entirely from the owner’s perspective. Our responsibility is to provide
open-book cost transparency, objective recommendations, competitive procurement, and clear communication throughout
design and construction.
We also believe there is meaningful value in extending the Village’s partnership with CG Schmidt across both public safety
projects. The Village has already invested time establishing communication processes, project expectations, and working
relationships with our team. Continuing that partnership creates efficiencies in coordination, decision-making, and project
management while reducing the learning curve associated with complex municipal projects.
Thank you again for your consideration. We would be honored to continue partnering with the Village of Germantown on
this important facility.
Sincerely,
Joe Hoffmeier
Principal
(414) 828-8162
joeh@cgschmidt.com
11777 West Lake Park Drive
Milwaukee, WI 53224
Julie Barth
Administrative Assistant
Germantown Police Department
Village of Germantown
N112 W16877 Mequon Road
Germantown, WI 53022
Page 48 of 169
TABLE OF CONTENTS
01 // Technical Proposal
Firm Profile
Relevant Project Experience
Proposed Site-Specific Staffing Plan
Proposed Project Team and Resumes
02 // Project Approach
03 // Cost Proposal
04 // Proof of Insurance & Bond Ability
05 // Draft Contract: AIA A133-2019
Page 49 of 169
YOUR PROJECT
Understanding Crucial Project Elements
Deliver a Modern,
Future-Ready Facility
Maintain Budget Discipline
Amid Recent Cost Challenges
Ensure Confidence and
Clarity in Decision-Making
Execute a Technically Complex
Project without Disruption
YOUR PARTNER
We Know Complex
Municipal Facilities
CG Schmidt is a trusted construction management partner with
deep experience delivering complex municipal and secure facilities
through a collaborative CMAR approach. Our strength lies in proactive
preconstruction, disciplined cost control, and the ability to guide
public clients through technically demanding projects with clarity and
confidence.
We understand that this project comes at a time of evolving leadership
for the Village. Our role is to provide stability, transparency, and
experienced guidance—ensuring the Police Chief and stakeholders
have the information and support needed to make confident decisions
throughout the process.
YOUR TEAM
Safe. Experienced. Proactive.
Joe Hoffmeier
Principal
Ethan Sippel
Senior Project Manager
John Kaltenburg
Project Executive
Angela Resnick
Senior Estimator
The Difference
RISK MANAGEMENT FOR A
HIGHLY SPECIALIZED PUBLIC
SAFETY FACILITY
EARLY INFRASTRUCTURE
& SITE RISK REDUCTION
TRANSPARENT MUNICIPAL
PARTNERSHIP
We really enjoy working with CG Schmidt. They act as an
extension of our business, and they understand what we need.
Hiring CG Schmidt is like pushing the ‘easy button’. They are
committed to our goals, and they know how to get stuff done!
— Isaac Larson
Executive Director of Facilities
Froedtert ThedaCare
Josh Schmitz
Safety Director
Ben Prindiville
Quality Manager
Tom Caluette
Fire Range Resource
Max McCollow
Project Engineer
KNOWLEDGE.
COMMUNICATION.
REPUTATION.PROVEN 70%
CONSTRUCTION
WORK COMPLETED IN
OCCUPIED SPACE 15
PERSON IN-HOUSE
PRECONSTRUCTION
TEAM 0.99
2025 OSHA
INCIDENT
RATING
CREATING EXCEPTIONAL
FACILITIES THAT IMPROVE
THE LIVES OF OTHERS.
Core Team
Support Team
We bring experience in secure, operationally sensitive environments where
safety, sequencing, and performance are critical, including:
» Justice and detention facilities
» Secure municipal infrastructure projects
» Police-related or controlled-access environments
Our experience positions us to successfully deliver:
» Secure circulation and controlled access environments
» Evidence storage and operational spaces
» Mission-critical building systems
» Specialized environments requiring strict performance standards
Kris Brakken
Superintendent
Page 50 of 169
Technical
Proposal
01
Page 51 of 169
6
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
SECTION 01
FIRM PROFILE
OUR MISSION
To create exceptional facilities that improve
the lives of others.
VALUE PROPOSITION
Delivering an exceptional client experience,
founded on trust, quality construction and
dedication to strengthening communities.
DATE FIRST ORGANIZED
Founded in 1920
TYPE OF FIRM
Privately Owned
RECENT RECOGNITIONS
Top Workplaces (2010-2025)
Milwaukee Journal Sentinel
Best Places to Work (15x winner)
Milwaukee Business Journal
Best Places to Work (5x winner)
Wisconsin State Journal
Best Places to Work (2x winner)
Madison Magazine
Top 100 Construction Managers in the
Country
Engineering News Record
2x WI Family Business of the Year
Skills / Integrity / Responsibility Award
Distinguished Performer in DEI
Deloitte 75
LOCATIONS
Milwaukee (HQ & Project Managing Office)
11777 West Lake Park Dr. | Milwaukee, WI 53224
Madison
433 West Washington Ave. | Madison, WI 53703
Arizona
999 E Playa Del Norte Dr. #110 | Tempe, AZ 85288
Schmidt: A family name. A 106-year promise.
Founded in 1920 by Dutch immigrant Charles Schmidt, CG Schmidt was built
on a simple yet powerful idea: a name is only as strong as the reputation
behind it. He believed that every project was a reflection of character, and
that belief still guides us today.
Now in our fifth generation of family leadership, CG Schmidt has grown into
one of Wisconsin’s leading commercial builders. We’ve stayed true to the
core values passed down over the past 106 years—integrity, caring, and a
passion for excellence.
We are proud to be the trusted partner on many of the state’s most
respected organizations in communities across the state and nation, and
look forward to the opportunity to serve The Village of Germantown and
Germantown Police Department.
Pictured above clockwise from lower right: President & CEO, Eric Schmidt; Chairman,
Rick Schmidt; Managing Director, Ryan Schmidt; Senior Project Manager, Brad Schmidt.
106
YEARS
EXPERIENCE
5
GENERATIONS
STRONG
373
OFFICE & FIELD
PROFESSIONALS
3
OFFICE
LOCATIONS
0
LAWSUITS
WITH ANY
CLIENTS
OR ARCHITECTS
Page 52 of 169
7
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
RELEVANT PROJECT EXPERIENCE
DOC Juvenile Detention Center -
Southeast Regional Care Center for
Youth
MILWAUKEE, WI | $53M
“A secure, controlled, high-performance public
safety facility requiring specialized systems
coordination and operational planning.”
This project involved the ground-up construction of a Type 1 secure
juvenile detention facility designed for durability and controlled
operations. Masonry construction, a precast roof system, and a steel
penthouse created a robust and secure structure. The facility includes
32 detention rooms, program and administrative spaces, and a
gymnasium, all organized to support safe circulation and supervision.
A secure outdoor recreation area with basketball court and perimeter
fencing reinforces controlled access and occupant safety.
Aurora Health Center
Psychiatric Hospital - Dewey Center
WAUWATOSA, WI | $18.3M
“A secure, operationally complex facility
requiring controlled environments, durable
systems, and coordinated user functions.”
CG Schmidt completed this ground-up behavioral health facility
designed to support both inpatient and outpatient care in a secure,
patient-focused environment. The two-story, 75,000-square-foot
building features precast and steel construction and includes
treatment spaces, patient rooms, and support areas organized
for safety, privacy, and operational efficiency. Program elements
include therapy spaces, administrative offices, a gym/fitness area,
and communal amenities such as lounges, cafeteria, and chapel.
Exterior and site features, including a roof deck and lower-level
parking, support patient well-being and staff functionality within a
controlled healthcare setting.
PROJECT HIGHLIGHTS:
Secure Facility Planning
Controlled Circulation
Specialized System Coordination
Material Durability & Lifecycle
Safety & Risk Mitigation
Highly Sensitive Environment
PROJECT HIGHLIGHTS:
Secure, Controlled Environment
Complex Program
Lifecycle Alignment
Patient Safety
Site & Operational Support
Page 53 of 169
8
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
Mendota Mental Health Institute -
Boiler Replacement
MADISON, WI | $4.6M
“A critical infrastructure upgrade focused on
enhancing utility reliability and supporting
continuous operations within an active
healthcare campus.”
This project included replacement and upgrade of aging boiler
systems within the central heating plant serving a state-operated
psychiatric facility. Work involved installation of new high-capacity
steam boilers, removal of existing units, and modifications
to heating and chiller plant equipment to support electrical,
steam, condensate, and fuel systems. Additional scope included
decommissioning a coal-fired boiler, installing a new gas/oil-
fired boiler with economizer, and upgrading controls and building
management systems. These improvements were part of a broader
campus initiative to modernize utility infrastructure and enhance
reliability for ongoing healthcare operations.
Advocate Aurora Health -
Mental Health Emergency Center
MILWAUKEE, WI | $8.7M
“A high-performance, emergency response
facility requiring efficient intake, controlled
circulation, and secure, high-sensitivity
environments.”
Developed in partnership with Milwaukee County and leading
healthcare systems, this facility was created to address the
region’s mental health crisis through a centralized, patient-focused
model of care. The 12,000-square-foot center provides 24/7 crisis
assessment, stabilization, treatment, and transitional care for
both adults and children. The program includes six inpatient beds
and is organized to support efficient intake, evaluation, and care
delivery. Designed as a recovery-oriented and culturally informed
environment, the center serves as a national model for emergency
mental health response.
PROJECT HIGHLIGHTS:
Active Psychiatric Hospital
Utility Reliability & Redundancy
Mechanical & Infrastructure
Coordination
Critical Systems Replacement
Occupied Facility
PROJECT HIGHLIGHTS:
Crisis Response Flow
Emergency Operations
High Sensitivity Environment
Site Security
Complex Stakeholder
Coordination
Compact Footprint
National Model
Page 54 of 169
9
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
Gibralter School District
FISH CREEK, WI | $31.4M
“A complex, phased infrastructure
project involving subsurface
challenges, utility coordination, and
active-site logistics management.”
This multi-phase renovation and addition project
transforms existing elementary and high school
facilities to support modern, flexible learning
environments. The work includes new classrooms,
gymnasium and athletic spaces, along with renovations
to building systems, restrooms, and circulation
areas to improve functionality and student flow.
Strategic demolition and reconstruction address aging
infrastructure while enhancing safety and security
across the campus. Site and operational improvements,
including updated drop-off areas and expanded
multipurpose spaces, support evolving educational
needs and community use.
PROJECT HIGHLIGHTS:
Bedrock & Subsurface Risk
Management
Complex Utility Coordination
Infrastructure Upgrades
Phased Construction
Occupied Environment
Logistics & Site Circulation
Improvement
Adaptive Planning & Field
Coordination
BEDROCK CONSIDERATIONS
During construction, the project team encountered site conditions where underlying bedrock
influenced both utility infrastructure and excavation activities. With much of the site underlain
by shallow bedrock, traditional subsurface installations required careful coordination and
adaptation, particularly in relation to existing and new gas systems. The team worked closely
with the owner and trade partners to evaluate subsurface conditions, adjust system layouts,
and manage risk associated with limited excavation depths and unknown existing conditions.
This included coordinating the replacement of multiple propane systems and ensuring all
work was executed safely and in compliance with excavation protocols. Through proactive
investigation, strategic planning, and continuous field coordination, the team successfully
navigated the challenges associated with bedrock conditions while maintaining project
schedule and minimizing disruption to ongoing school operations.
Page 55 of 169
10
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
PROPOSED SITE-SPECIFIC
STAFFING PLAN
This project requires a hands-on, experienced team with both municipal and
specialized facility knowledge.
Our staffing approach focuses on:
» Senior-level leadership continuity to support Village decision-making
» Dedicated preconstruction resources for cost, schedule, and risk
management
» Field leadership experienced in complex site and building systems
» Access to specialized partners for the live-fire range
We will maintain a consistent team from preconstruction through
completion—ensuring continuity, accountability, and clear communication
throughout the project lifecycle.
Page 56 of 169
11
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
PROPOSED PROJECT
TEAM AND RESUMES
PRECONSTRUCTION CONSTRUCTION MANAGEMENT
Project Lead
Joe Hoffmeier
Principal
Ethan Sippel
Senior Project Manager
Josh Schmitz
Safety Director
John Kaltenberg III, P.E.
Project Executive
Ben Prindiville
Quality Manager
Angela Resnick
Senior Estimator
Tom Caluette
Fire Range Resource
Max McCollow
Project Engineer
The proposed CG Schmidt team was
chosen for their technical expertise and
experience alignment with the project’s
key challenges.
Joe Hoffmeier and John Kaltenberg
will oversee all phases of the project as
your designated points of contacts.
SAFETY & QUALITY
Kris Brakken
Superintendent
Page 57 of 169
12
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
JOE HOFFMEIER
Principal
Joe Hoffmeier brings extensive experience leading projects within occupied facilities and
active campus environments, where maintaining safety, accessibility, and uninterrupted
operations is critical. He excels at managing complex logistics, coordinating phased
work, and mitigating disruptions in high-traffic, high-sensitivity settings. Joe’s proactive
approach ensures that project teams remain aligned with operational needs while
advancing construction efficiently. His ability to navigate these challenges makes him
a valuable leader for projects requiring careful planning, stakeholder coordination, and
seamless integration into ongoing operations.
RELEVANT PROJECT EXPERIENCE
DOC Juvenile Detention Center - Southeast Regional Care Center for Youth
Milwaukee, WI | $53M
This project involved the construction of a secure correctional facility designed to
support controlled operations and occupant safety. The building incorporates secure
entries, controlled circulation, and durable systems appropriate for high-sensitivity
environments. Careful coordination of program spaces supports supervision, security,
and operational efficiency, delivering to complex public safety–oriented environments.
Master Lock Security Improvements
Milwaukee, WI | $2.7M
Fast-tracked security upgrades across occupied parking areas to enhance
controlled access and site safety. Work included perimeter fencing, access
control systems, gate operations, lighting, and integrated cameras. Construction
was phased to maintain continuous operations and access.
Racine Readiness Storage Building
Racine, WI | $850K
Construction of a prefabricated dry storage facility within an active readiness
campus. The project included site excavation, utility extensions, footings and
foundations, concrete flatwork, and installation of a pre-engineered metal
building system. Interior build-out included secured storage areas with fencing
and minor electrical systems. Work required coordination to integrate new
infrastructure with existing campus operations.
BMO Harris - Bluemound Road Branch Renovation
Milwaukee, WI | $900K
Renovation of an active retail banking branch to update customer-facing and
operational spaces, including coordination of secure access elements. Work was
phased to maintain daily operations and controlled access throughout.
West Allis West Milwaukee School District Rec Center Addition & Renovation
West Allis, WI | $10M
The West Allis-West Milwaukee Rec Center project included demolition of outdated
facilities, remodel of the 2005 building, and site prep for future additions. Completed
in summer 2020, the upgraded center features a gym, walking track, fitness and dance
studios, preschool, multipurpose rooms, and modern offices. Reclaimed brick was
used to build a retaining wall honoring the original FDR-era Works Project.
Education &
Training
BS, Construction
Management
UW - Stout
AAS, Architectural Drafting/
Construction Technology
Waukesha County Technical
College
Healthcare Construction
Certificate (HCC)
Wisconsin Healthcare
Engineering
CPR, AED and First Aid
Certification
Medic First Aid
30-Hour Construction Safety
Course
OSHA
SafeStart® Training
CG Schmidt
PROJECT ALIGNMENT:
Municipal & Public Works, Secure
Facilities & Entrances, Site Utilities,
Bedrock
Page 58 of 169
13
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
JOHN KALTENBERG III, P.E.
Project Executive
John provides strategic leadership and executive oversight, guiding project teams to ensure
successful delivery from preconstruction through closeout. He focuses on strengthening
client relationships, aligning team performance, and supporting key decision-making to
maintain momentum and project clarity. With a strong emphasis on budget management
and overall project outcomes, John ensures that work is delivered on time, within budget,
and to the highest quality standards. His leadership fosters accountability, collaboration,
and consistent performance across all phases of the project.
RELEVANT PROJECT EXPERIENCE
Aurora Psychiatric Hospital - Inpatient Renovations
Wauwatosa, WI | $6.7M
Renovations within an active behavioral health facility focused on enhancing
patient care environments and operational efficiency. The work required careful
coordination in an occupied setting, emphasizing safety, controlled access, and
uninterrupted operations. Improvements supported functional upgrades to
treatment and patient care spaces within a secure healthcare environment.
Aurora Health Center Psychiatric Hospital - Dewey Center
Wauwatosa, WI | $18.3M
Ground-up construction of a 75,000-square-foot behavioral health facility utilizing
precast and steel systems. The two-story building includes inpatient and outpatient
treatment spaces, patient rooms, and support areas organized for safety and
efficiency. Program elements include therapy spaces, offices, a fitness area, and
communal amenities. Site features include a roof deck and lower-level parking
within a controlled healthcare environment.
*Milwaukee County Sheriff’s Office and Patrol Bureau
Milwaukee, WI
This public safety facility includes secure entries with bullet-resistant glazing and
integrated security technology. The project incorporates detention cells, debriefing and
training spaces, and equipment and vehicle storage areas. It was designed to support
secure operations, staff safety, and functional efficiency, demonstrating experience with
law enforcement environments.
*ProHealth Care – Waukesha Memorial Hospital Behavioral Health
Waukesha, W
This behavioral health project includes secure entry points, a centralized nurse station,
and patient spaces designed for safety and supervision. The work required coordination
of specialized systems to support controlled environments and patient needs.
Improvements enhance safety, durability, and operational performance.
*BMO Tower
Milwaukee, WI
Located in downtown Milwaukee, this project required extensive coordination within a
dense urban environment, including management of existing and abandoned utilities and
new connections. Careful planning addressed site constraints and maintained schedule.
This project reflects experience navigating complex infrastructure & conditions.
Education &
Training
Master of Business
Administration (MBA)
Marquette University
BS, Civil and Environmental
Engineering
University of Wisconsin
Association of General
Contractors Project
Management
Wisconsin Health Care
Engineering Association
Member
Wisconsin Health Care
Construction Certificate
OSHA
Licensed Professional
Engineer
State of Wisconsin
SafeStart® Training
CG Schmidt
PROJECT ALIGNMENT:
Municipal & Public Works, Secure
Facilities, Underground Parking,
Site Utilities
*Completed through previous employer
Page 59 of 169
14
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
ANGELA RESNICK
Senior Estimator
Angela brings a disciplined, client-focused approach to cost management, aligning project
budgets with design intent from the earliest stages of preconstruction. She combines
real-time estimating with transparent communication to support informed decision-making
and maintain strong budget accountability. Known for her subject matter expertise and
proactive mindset, Angela helps teams navigate cost considerations while identifying
outcome-oriented solutions. Her ability to integrate cost, scope, and design ensures
alignment throughout the project lifecycle and supports successful project delivery.
RELEVANT PROJECT EXPERIENCE
Northwestern Mutual - North Office Building
Milwaukee, WI | $500M
This corporate office project required significant coordination of site utilities, including
relocation of existing infrastructure associated with the nearby Cass Street corridor.
The work involved integrating new utility systems while maintaining project schedule
and minimizing disruptions. The project reflects experience managing complex site
and infrastructure challenges in a dense urban setting.
Milwaukee Recreation Community Center
Milwaukee, WI | $53.4M
Ground-up renovation and expansion transforming the former Browning School
site into a 100,000+ SF community recreation center. The project includes
gymnasium, indoor pool, multi-purpose spaces, and site redevelopment across
a 7.5-acre campus. Work integrates new construction with existing structures
within a complex brownfield site.
911 Call Center
Preconstruction services for a municipal emergency response facility, including
development of conceptual budgets and early cost planning. Efforts focused on
aligning project scope with funding parameters prior to project start. The work reflects
experience supporting public safety projects from initial planning stages.
Advocate Aurora Healthcare - Mental Health Emergency Center
Milwaukee, WI | 8.8M
This behavioral health facility supports 24/7 crisis assessment, stabilization, and
treatment in a controlled environment. The project required coordination of program
elements to support efficient intake, evaluation, and care delivery. Spaces are
organized to prioritize safety, supervision, and operational flow in a high-sensitivity
setting.
Northwestern Mutual - Jackson St. Parking Structure
Milwaukee, WI | $140K
This structured parking facility supports high-density urban use, requiring
coordination of circulation, access, and integration with surrounding infrastructure.
The project involved careful planning to support efficient vehicle flow and structural
performance. Coordination of site and building systems was critical to successful
delivery within an urban environment.
Education &
Training
BS, Construction
Management
MSOE
LEED Green Association
U.S. Green Building Council
30-Hour Construction Safety
Certification
OSHA
SafeStart® Training
CG Schmidt
PROJECT ALIGNMENT:
Accurate Cost Estimating, Site
Utilities, Secure Entrances
Page 60 of 169
15
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
ETHAN SIPPEL
Senior Project Manager
Ethan provides leadership oversight to project teams, guiding both project managers and
superintendents to ensure coordinated, efficient execution from preconstruction through
closeout. He is highly engaged in core project controls, managing RFIs, subcontractor
coordination, schedules, and change order negotiations while maintaining clear and
consistent documentation throughout the project lifecycle. Known for his organized
approach and attention to detail, Ethan keeps teams aligned and responsive to evolving
project needs. His ability to manage complex processes while driving accountability
contributes to streamlined delivery and successful project outcomes.
RELEVANT PROJECT EXPERIENCE
Medical College of Wisconsin - Professional Office Building (HUB)
Wauwatosa, WI | $90M
This healthcare facility supports complex clinical and administrative functions
within an active medical campus environment. The project required coordination of
specialized building systems and careful planning to maintain ongoing operations.
Program spaces are organized to support efficiency, safety, and user needs in a high-
sensitivity setting. The facility reflects a disciplined approach to integrating technical
requirements with functional design.
AO Smith - Corporate Technology Center
Milwaukee, WI
This corporate technology center supports advanced research, development, and
office functions within a high-performance environment. The project required
careful coordination of building systems and program elements to meet technical
performance requirements. Spaces are organized to support efficiency, collaboration,
and operational flexibility. The facility demonstrates a coordinated approach to
delivering technically demanding environments.
Greendale School District 2019-2020 Referedum
Greendale, WI | $33.8M
This multi-phase improvement project includes additions, renovations, and
infrastructure upgrades across an active school campus. The work required strategic
phasing, stakeholder coordination, and detailed planning to maintain ongoing
operations during construction. Improvements enhance building functionality, safety,
and circulation throughout the campus. The project reflects experience delivering
complex public-sector work in occupied environments.
Horlick Lofts - The William Apartments Historic Renovation
Racine, WI | $15.9M
This adaptive reuse project transformed a historic structure into a modern, functional
space while preserving key architectural elements. The work required coordination
within an existing building and responsiveness to field conditions encountered
during construction. Careful planning and trade coordination supported successful
integration of new systems into the historic framework. The project demonstrates a
flexible and detail-oriented approach to complex renovation work.
Education &
Training
BS, Architectural
Engineering
MSOE
BS, Construction
Management
MSOE
10-Hour Quality Control
Certification
OSHA
SafeStart® Training
CG Schmidt
PROJECT ALIGNMENT:
Municipal & Public Works, Secure
Entrances, Complex Systems,
Multi-Phase Work in Active
Environments
Page 61 of 169
16
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
KRIS BRAKKEN
Superintendent
Kris brings more than 24 years of construction experience, beginning his career as a
foreman and advancing through field leadership roles. His hands-on background provides
a strong foundation in field coordination, safety, and trade management, allowing him
to effectively lead day-to-day construction operations. Kris is known for maintaining
organized, efficient jobsites, proactively resolving field challenges, and ensuring work is
completed in alignment with project goals. His practical approach and steady leadership
contribute to consistent quality, schedule adherence, and successful project delivery.
RELEVANT PROJECT EXPERIENCE
Northwestern Mutual - North Office Building
Milwaukee, WI | $500M
This corporate office project required significant coordination of site utilities, including
relocation of existing infrastructure associated with the nearby Cass Street corridor.
The work involved integrating new utility systems while maintaining project schedule
and minimizing disruptions. The project reflects experience managing complex site
and infrastructure challenges in a dense urban setting.
St. Francis School District - Additions & Remodel
St. Franics, WI | $25.9M
Following successful referendum approval, led phased additions and renovations
across occupied K-12 facilities, including Willow Glen Primary and Deer Creek
Intermediate. Work included coordination of demolition, structural modifications, and
MEP system integration to support districtwide improvements focused on safety,
security, accessibility, and STEM learning environments, as well as upgrades to
recreation, theater, and athletic facilities. Maintained strict sequencing and site control
to support ongoing school operations throughout construction.
Muskego Norway School District 2022 Referendum
Muskego, WI | $42.4M
Provided master planning and pre-referendum support resulting in successful voter
approval of a $44.6M, two-question facilities program. The referendum included
additions for technical education and STEM programming, as well as specialized
spaces for health sciences and an indoor practice facility at Muskego High School.
The program required careful planning, stakeholder coordination, and clear
communication to align community priorities with complex, long-term facility needs—
reflecting the collaborative approach necessary for municipal and public safety
projects.
Old National Bank
Milwaukee, WI | $4.5M
Fit-out of 2,000 SF of retail banking and 28,000 SF of office space within the Huron
Building. The project team navigated material procurement delays and complex
logistics, including the absence of a freight elevator to serve the 8th-floor space in a
busy downtown location. Work occurred within an occupied building under strict noise
constraints. Solutions included enhanced material management, 360-degree weekly
documentation, air quality controls, and automated cleaning processes to maintain a
safe, controlled environment.
Education &
Training
BS, Civil Engineering
Michigan Technology
University
30-Hour Construction Safety
Certification
OSHA
10-Hour Construction Safety
Certification
OSHA
LEED AP 2.2
U.S. Green Building Council
SafeStart® Training
CG Schmidt
PROJECT ALIGNMENT:
Municipal & Public Works, Secure
Facilities with Complex MEP
Infrastructure, Early Phase Risk
Identification, Existing Conditions
Management, Jobsite Control
Page 62 of 169
17
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
MAX McCOLLOW
Project Engineer
Max supports project teams through a proactive, detail-oriented approach, focusing on
coordination, documentation, and day-to-day execution. He brings a steady presence
to the team, working through challenges with practical problem-solving and clear
communication. Max collaborates closely with project managers, field teams, and trade
partners to maintain alignment and keep work progressing efficiently. His ability to stay
organized, anticipate needs, and support team coordination contributes to consistent
project performance.
RELEVANT PROJECT EXPERIENCE
DOC Juvenile Detention Center - Southeast Regional Care Center for Youth
Milwaukee, WI | $53M
This project involved the construction of a secure correctional facility designed to
support controlled operations and occupant safety. The building incorporates secure
entries, controlled circulation, and durable systems appropriate for high-sensitivity
environments. Careful coordination of program spaces supports supervision, security,
and operational efficiency. The facility reflects experience delivering complex public
safety–oriented environments.
Froedtert PA4 & PS6
Wauwatosa, WI | $70M
This project includes the construction of structured parking facilities integrated within
an active healthcare campus. The work required coordination of underground and
interior parking systems while maintaining access, safety, and circulation for ongoing
operations. Phasing and logistics planning were key to minimizing disruption in a
high-traffic environment. The project reflects experience delivering complex parking
and site infrastructure solutions.
*Germantown Gateway Corporate Park
Germantown, WI
This corporate development required careful coordination of site and infrastructure
elements within challenging subsurface conditions. The project team navigated
bedrock-related constraints, adapting excavation and foundation approaches to
maintain schedule and cost control. Site planning and utility coordination supported
long-term functionality and flexibility for tenants. The project demonstrates experience
managing site complexities and subsurface risk.
*UW-Milwaukee Chemistry Building
Milwaukee, WI
This academic facility required coordination of specialized building systems
and complex utility infrastructure to support laboratory and research functions.
The project involved detailed planning of site utilities and building systems to
accommodate performance requirements and long-term flexibility. Integration of
mechanical, electrical, and plumbing systems supported efficient operation within a
highly technical environment. The project demonstrates strong experience managing
system complexity and utility coordination.
*Completed through previous employer
Education &
Training
BS, Environmental Science &
Land-Use Planning
UW-Oshkosh
Board Member
ACI - Wisconsin Chapter
WRMCA Technical
Committee
AGGTEC Level I - Soil/
Aggregate
ACI Grade I - Field Concrete
Testing
PTI Level I & II - Unbonded
First Aid, CPR & AED
Certification
NSC
10-Hour Safety Certificate
OSHA
SafeStart® Training
CG Schmidt
PROJECT ALIGNMENT:
Secure Facilities & Entrances,
Bedrock, Site Utilities,
Underground/Interior Parking
Page 63 of 169
Project
Approach
02
Page 64 of 169
19
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
Deliver a modern,
future-ready facility
Maintain budget
discipline amid
recent cost
challenges
Ensure confidence
and clarity in
decision-making
Execute a
technically complex
project without
disruption
PROJECT UNDERSTANDING
SECTION 02
PROJECT APPROACH
We understand the Village’s priorities:
Transparent, Data-Driven Preconstruction
We provide clear, milestone-based estimating at 30%, 60%, 90%,
and 100% design to ensure continuous alignment with budget.
Germantown Benefit: Village confidence in decision-making +
early course correction in response to market conditions
Strong Schedule Control Through Early Planning
We prioritize early identification and procurement of long-lead
systems—including security, technology, and critical utilities—to
minimize exposure to delays.
Germantown Benefit: Protection of critical milestones +
maintained overall project certainty
Continuous Constructability & Value Optimization
Our team performs ongoing design and constructability reviews to
align building systems with budget, performance, and long-term
operational needs.
Germantown Benefit: Informed decision-making + maximized
functionality without compromising cost discipline
Clear Communication & Stakeholder Alignment
We establish a direct and consistent communication structure
with Village leadership, the Police Chief, and project stakeholders
to ensure timely decisions and shared understanding.
Germantown Benefit: Village confidence in decision-making +
early course correction in response to market conditions
CG SCHMIDT’S APPROACH
Our approach is grounded in:
Page 65 of 169
20
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
5 STEPS TO DELIVER A SAFE, SECURE, AND PREDICTABLE
PROJECT FOR CONTINUOUS POLICE OPERATIONS
CG Schmidt’s approach is rooted in early, collaborative involvement to support informed decision-making, minimize
disruption to police operations, and proactively manage cost and schedule risk. For the Germantown Police Department,
our process is focused on maintaining continuous operations, addressing security requirements, and identifying risks
early to support a predictable and efficient project delivery.
STEP 5: EXECUTE
Finalize GMP,
procure qualified
trade partners, and
execute a controlled
construction plan
that prioritizes
safety, security, and
timely delivery of
critical materials and
systems.
OUR 5-STEP PRECONSTRUCTION PROCESS WITH THE GERMANTOWN POLICE DEPARTMENT FACILITY
STEP 1: LISTEN
Align with Village
leadership and police
staff to understand
operational needs,
security requirements,
phasing constraints,
and budget. Begin
continuous estimating
and identify key cost
drivers.
STEP 2: INFORM
Evaluate design options
with constructability and
operational continuity
in mind. Initiate
procurement strategy
with early identification
of long lead systems
(security/technology,
HVAC, electrical) and
validate pricing and
availability with trade
partners.
STEP 3: ADVISE
Refine scope and
systems to maximize
value while
maintaining budget.
Incorporate real-time
market feedback,
develop alternates,
and implement
strategies to mitigate
escalation and
supply chain risks.
STEP 4: ALIGN
Advance phasing,
logistics, and site
security plans to
support continuous
operations. Release
early bid packages
for critical path
and long lead
components to
protect schedule.
Benefit: Our process emphasizes early cost alignment and transparent communication at each milestone.
Page 66 of 169
21
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
UTILITY EXTENSION STRATEGY
The 2,500-foot sanitary sewer and water main extension is a critical early driver
of both schedule and cost. The project team will deliver a disciplined, security-
focused approach to the utility extension and live-fire range integration, prioritizing
operational readiness, safety, and reliability throughout construction. Utility
extensions will be strategically planned and phased to support uninterrupted
service to mission-critical systems, with early coordination to ensure secure
routing and long-term performance.
Our strategy includes:
» Early Coordination & Permitting
» Engage utility providers and authorities immediately to confirm requirements and
timelines
» Phased/Early Bid Packaging
» Advance utility work early to maintain schedule momentum
» Bedrock & Subsurface Risk Mitigation
» Align excavation strategies with geotechnical data
» Plan for potential bedrock impacts to minimize cost and schedule disruption
» Integrated Site Logistics
» Sequence utilities with stormwater, access, and foundation work
LIVE-FIRE RANGE INTEGRATION STRATEGY
The live-fire range will be integrated with specialized attention to ballistic
protection, advanced ventilation systems, acoustic control, and life safety
infrastructure to meet stringent law enforcement training standards. Our
team will emphasize controlled access, clear separation of public and secure
zones, and detailed sequencing to maintain safe operations in an active public
safety environment. Through proactive preconstruction planning, stakeholder
collaboration, and rigorous quality control, we will deliver a facility that supports
effective training, enhances officer safety, and meets the operational needs of the
department.
Our approach focuses on integration, expertise, and risk mitigation:
» Early Engagement of Specialized Partners
» Collaborate with qualified range experts during preconstruction
» Full Building Systems Integration
» Coordinate HVAC, filtration, acoustics, and ballistic systems
» Performance & Lifecycle Focus
» Evaluate durability, maintenance, and long-term operational costs
» Preconstruction Risk Reduction
» Identify long-lead equipment and system constraints early
This ensures safe & reliable range performance from day one.
Reducing
Risk.
Protecting
Schedule.
Ensuring
Seamless
Integration.
Page 67 of 169
22
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
Safety is a top priority, and we are committed to maintaining a safe and healthy environment for all workers on our projects.
In 2025, our team worked an impressive 778,074 hours, with 19 OSHA recordable incidents and only 2 recordable injuries or
illnesses resulting in days away from work. Additionally, our lost time accidents for the year totaled 2, showcasing our
proactive approach to minimizing workplace injuries.
CG Schmidt has no lawsuits or liens.
YEAR OSHA Incident
Rate DART Rate
2025 0.99 0.00
2024 4.62 3.34
2023 3.22 2.58
2022 3.02 2.64
SAFETY IS OUR
#1 PRIORITY
ON THE JOBSITE
SAFETY METRICS
CG Schmidt’s Safety Manual is always available
and up-to-date on our website. View it here.
SAFETY FIRST
Click to View
INTERNAL SAFETY MANUAL
ZERO LAWSUITS
WITH CLIENTS IN
106 YEARS
SAFETY MANAGEMENT PROGRAM
A CG Schmidt Safety Stand-down meeting is
held before the day’s work begins.
Page 68 of 169
23
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
SYSTEMS TO ENSURE QUALITY
The Germantown Police Station will benefit from:
» PRE-INSTALLATION MEETINGS // Prior to the implementation of any large work packages being put in place, our
team holds pre-installation meetings to review shop drawings and identify potentially problematic construction
details or schedule, weather or material concerns that could impact the quality of the work. This often involves
creating mock-ups for key items to verify the quality of the work and the material. By identifying these items before
the work is installed, we offer clarity and address potential issues before they become costly field conditions or
punch-list or warranty items.
» BENCHMARKING // The first step of every key installation is inspection to confirm it meets the requirements of
the documents and the expectations of stakeholders before it is replicated throughout the space.
» FIELD ENGINEERING AND TESTING PROGRAM // We work with the project team to develop a comprehensive
field engineering and testing program, making recommendations for appropriate levels of independent inspection
for systems and materials.
» QC CHECKLISTS AND AUDITS // Problem-free installation is greatly achieved by pre-planning installation and
reviewing requirements for correct installation with field teams who perform the work. However, we still utilize
quality control checklists and audits to confirm that installations are, in fact, properly completed before the work is
covered by the next sequential installation.
Instead of relying on post-installation inspections to find and fix quality
issues that add cost and waste time, CG Schmidt’s Quality Management
Program finds problems before they occur. Our Quality Management
Program increases value and cost accuracy while mandating overall
project quality by:
» Building quality directly into the plans and specifications by
collaborating with architects as they complete their drawings and
addressing difficult or unclear construction details before they
become part of the final construction documents.
» Highlighting work scope and building systems which may require
mitigation to avoid warranty call-backs and repairs.
ENSURING
PROACTIVE
QUALITY
ASSURANCE
& QUALITY
CONTROL
QUALITY MANAGEMENT
PROGRAM
Page 69 of 169
24
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
PROJECT
MILESTONE
SCHEDULE
DRAFT
ID ID Task Name Duration Early Start Early Finish
0 0 CG Schmidt Project Schedule 571 days Mon 5/4/26 Mon 7/10/28
1 1 Design 141 days Mon 5/4/26 Mon 11/16/26
2 2 Schematic Design 46 days Mon 5/4/26 Mon 7/6/26
3 3 Design Development 40 days Tue 7/28/26 Mon 9/21/26
4 4 Construction Documents 25 days Tue 10/13/26 Mon 11/16/26
5 5 Budgeting 70 days Tue 7/7/26 Mon 10/12/26
6 6 SD Budget 15 days Tue 7/7/26 Mon 7/27/26
7 7 DD 60% Budget 15 days Tue 8/25/26 Mon 9/14/26
8 8 DD 90% Budget 15 days Tue 9/22/26 Mon 10/12/26
9 9 Bidding 40 days Tue 12/1/26 Mon 1/25/27
10 10 BP #1 15 days Tue 12/1/26 Mon 12/21/26
11 11 Final GMP 15 days Tue 12/22/26 Mon 1/11/27
12 12 GMP Approval 10 days Tue 1/12/27 Mon 1/25/27
13 13 Permitting 65 days Tue 11/17/26 Mon 2/15/27
14 14 State Regulatory Review 45 days Tue 11/17/26 Mon 1/18/27
15 15 Local Regulatory Review 15 days Tue 1/19/27 Mon 2/8/27
16 16 Building Permit 5 days Tue 2/9/27 Mon 2/15/27
17 17 Construction 320 days Mon 3/29/27 Mon 6/19/28
18 18 Mobilization 0 days Mon 3/29/27 Mon 3/29/27
19 19 Sitework 40 days Tue 3/30/27 Mon 5/24/27
20 20 Building Construction 255 days Tue 5/25/27 Mon 5/15/28
21 21 Building Commissioning 20 days Tue 5/16/28 Mon 6/12/28
22 22 Final Inspections 5 days Tue 6/13/28 Mon 6/19/28
23 23 Final Inspections Complete 0 days Mon 6/19/28 Mon 6/19/28
24 24 Move-In / Owner Occupancy 15 days Tue 6/20/28 Mon 7/10/28
25 25 Furniture & Equipment 15 days Tue 6/20/28 Mon 7/10/28
26 26 Owner Training 5 days Tue 6/20/28 Mon 6/26/28
27 27 Occupancy 0 days Tue 6/20/28 Tue 6/20/28
Schematic Design Schematic Design
Design DevelopmentDesign Development
Construction DocumentsConstruction Documents
SD Budget
DD 60% Budget
DD 90% Budget
BP #1
Final GMP
GMP Approval
State Regulatory Review
Local Regulatory Review
Building Permit
Mobilization
Building Construction
Building Commissioning
Final Inspections
Final Inspections Complete
Furniture & EquipmentFurniture & Equipment
Owner Training
Occupancy
A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029
New Police Department Facility
Village of Germantown
5/29/2026
DRAFT
Page 70 of 169
Cost
Proposal
03
Page 71 of 169
26
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
SECTION 03
COST PROPOSAL
GENERAL CONDITIONS
(Assumes 14 Month Construction Duration)
ITEM QUANTITY UNIT UNIT COST TOTAL COST
MANAGEMENT & SUPERVISION - 2027 RATES
Sr. PM - Project Executive 275 HR $178.00 $48,950
Sr. Project Manager (Full-Time On-Site) 2,595 HR $160.00 $415,200
Project Engineer 1,453 HR $110.00 $159,830
General Superintendent 56 HR $177.00 $9,912
Superintendent (Full-Time On-Site) 2,422 HR $153.00 $370,566
Project Coordinator / Risk Management 350 HR $85.00 29,750
Project Accountant 121 HR $85.00 10,285
Safety Manager 128 HR $153.00 $19,584
TOTAL $1,064,077
FEES
ITEM QUANTITY
Preconstruction Services (Lump Sum) $20,000.00
CM Contingency as a Percentage of the Cost of Work 2.00%
CM Fee as a Percentage of the Cost of Work 1.95%
Benefit: Our fee structure reflects
a highly engaged preconstruction
effort designed to reduce risk,
avoid costly changes, and deliver
overall best value.
Page 72 of 169
27
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
GMP DEVELOPMENT APPROACH
The sample project dashboard monitors the progression of the total project budget throughout the entirety of the project.
$7.0M
$6.5M
$6M
$5.5M
$5M
$4.5M
7/10/2024 7/29/2024 10/15/2024 12/8/2024 6/22/2025 8/13/2025 9/7/2025 9/17/2025
Budget:
$5.0M
$6.55M
$5.14M $5.03M
$4.77M
$4.96M $4.96M
$5.08M
$4.92M
CONFIDENTIAL RENOVATION: OWNER’S BUDGET $5.0M
Continuous estimating keeps CG Schmidt ahead of every cost
driver to deliver accurate, data-driven budgets.
Our GMP strategy is built on confidence and
accuracy, not assumptions:
» Continuous cost validation throughout
design
» Early trade partner involvement
» Real-time market pricing feedback
» Alignment with Owner expectations at each
milestone
We deliver a GMP that is:
» Dependable
» Transparent
» Aligned with current market conditions
Our Guaranteed Maximum Price (GMP) proposal reflects a
comprehensive and well-defined understanding of the project
scope, developed through detailed preconstruction planning and
real-time market input. We have structured the GMP to provide
cost certainty while maintaining transparency and flexibility,
incorporating clearly defined assumptions, allowances, and
contingencies to manage risk effectively.
Our approach emphasizes early trade partner engagement,
open-book communication, and continuous cost validation to
ensure alignment with the project’s budget and goals. This
disciplined process allows us to proactively identify cost-saving
opportunities, mitigate potential impacts, and deliver a reliable,
well-supported GMP that positions the project for successful
execution.
RIGHT ON TARGET:
ANGELA’S ESTIMATING PERFORMANCE
Angela brings a disciplined, data-driven
approach to estimating, ensuring budgets
remain aligned with project goals throughout
design and preconstruction. Her track record
of delivering GMPs at or below target budgets
reflects strong cost control and proactive
market coordination.
Page 73 of 169
Proof of Insurance
and Bond Ability
04
Page 74 of 169
29
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
CG Schmidt is able to provide 100% Performance and Payment Bonds for a cost of .75% for a $35M total project cost.
Please see the following pages for our proof of insurance and bond ability.
SECTION 04
PROOF OF INSURANCE
AND BOND ABILITY
Insurance & Bond Ability
Page 75 of 169
30
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
INSURER(S) AFFORDING COVERAGE
INSURER F :
INSURER E :
INSURER D :
INSURER C :
INSURER B :
INSURER A :
NAIC #
NAME:
CONTACT
(A/C, No):
FAX
E-MAIL
ADDRESS:
PRODUCER
(A/C, No, Ext):
PHONE
INSURED
REVISION NUMBER:CERTIFICATE NUMBER:COVERAGES
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed.
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on
this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
OTHER:
(Per accident)
(Ea accident)
$
$
N / A
SUBR
WVD
ADDL
INSD
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
$
$
$
$PROPERTY DAMAGE
BODILY INJURY (Per accident)
BODILY INJURY (Per person)
COMBINED SINGLE LIMIT
AUTOS ONLY
AUTOSAUTOS ONLY
NON-OWNED
SCHEDULEDOWNED
ANY AUTO
AUTOMOBILE LIABILITY
Y / N
WORKERS COMPENSATION
AND EMPLOYERS' LIABILITY
OFFICER/MEMBER EXCLUDED?
(Mandatory in NH)
DESCRIPTION OF OPERATIONS below
If yes, describe under
ANY PROPRIETOR/PARTNER/EXECUTIVE
$
$
$
E.L. DISEASE - POLICY LIMIT
E.L. DISEASE - EA EMPLOYEE
E.L. EACH ACCIDENT
ER
OTH-
STATUTE
PER
LIMITS(MM/DD/YYYY)
POLICY EXP
(MM/DD/YYYY)
POLICY EFF
POLICY NUMBERTYPE OF INSURANCELTR
INSR
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)
EXCESS LIAB
UMBRELLA LIAB $EACH OCCURRENCE
$AGGREGATE
$
OCCUR
CLAIMS-MADE
DED RETENTION $
$PRODUCTS - COMP/OP AGG
$GENERAL AGGREGATE
$PERSONAL & ADV INJURY
$MED EXP (Any one person)
$EACH OCCURRENCE
DAMAGE TO RENTED
$PREMISES (Ea occurrence)
COMMERCIAL GENERAL LIABILITY
CLAIMS-MADE OCCUR
GEN'L AGGREGATE LIMIT APPLIES PER:
POLICY PRO-
JECT LOC
CERTIFICATE OF LIABILITY INSURANCE
DATE (MM/DD/YYYY)
CANCELLATION
AUTHORIZED REPRESENTATIVE
ACORD 25 (2016/03)
© 1988-2015 ACORD CORPORATION. All rights reserved.
CERTIFICATE HOLDER
The ACORD name and logo are registered marks of ACORD
HIRED
AUTOS ONLY
1/13/2026
M3 Insurance Solutions, Inc.
828 John Nolen Drive
Madison WI 53713
Trisha Stark
608-288-2805
trisha.stark@m3ins.com
Zurich American Insurance Comp 16535
SCHMC-2 Canopius US Insurance, Inc. 12961
C. G. Schmidt, Inc.
11777 West Lake Park Drive
Milwaukee WI 53224-3047
SiriusPoint Specialty Insuranc 16820
Vantage Risk Specialty Insuran 16275
1316989658
A X 2,000,000
X 100,000
10,000
2,000,000
4,000,000
X X
GLO2925094-05 1/1/2026 1/1/2027
4,000,000
A 2,000,000
X
X
BAP2925095-05 1/1/2026 1/1/2027
C
B
X 5,000,000
X
IPS-EX-00000137
CUSXU23000079-01
1/1/2026
1/1/2026
1/1/2027
1/1/2027
5,000,000
X 10,000 Excess Each/Aggregate 5,000,000
A X
N
WC2925093-05 1/1/2026 1/1/2027
1,000,000
1,000,000
1,000,000
D
D
Professional Liability/
Pollution Liability
P0C3P0000097330
P0C3P0000097330
1/1/2026
1/1/2026
1/1/2027
1/1/2027
Professional Liab
Pollution Liability
10,000,000
10,000,000
**Informational Only**
Page 76 of 169
31
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
Member of Liberty Mutual Group
Liberty Mutual Su r et y
January 16, 2026
Contractor: C.G. Schmidt, Inc.
RE: Surety Bonding Reference
To Whom It May Concern:
C.G. Schmidt, Inc. has been a highly regarded and valued client of Liberty Mutual Insurance
Company since 1990. During that time we have witnessed their continued success and steady
growth due to sound management and skillful execution of numerous projects. We maintain a
high degree of confidence in their reputation, financial strength and management expertise. It is
my pleasure to recommend this fine contractor to anyone, as they are surely one of the premiere
contractors in the Midwest.
We have approved bonds for single projects exceeding $600,000,000 and aggregate cost to
complete backlogs of $1,200,000,000. Our agreement to provide work programs and execute bid
and/or final bonds is subject to mutually acceptable final contract terms, conditions, financing
and underwriting conditions to both C.G. Schmidt, Inc. and Liberty Mutual Insurance Company.
Any arrangements for a bond, or bonds, is a matter between C.G. Schmidt, Inc. and Liberty
Mutual Insurance Company, and we assume no liability to third parties.
Should you require additional information about our surety bond relationship with C.G. Schmidt,
Inc. please feel free to contact me at 763-202-2507.
Sincerely,
Chase Stoneback,
Attorney-in-Fact for Liberty Mutual Insurance Company
Page 77 of 169
Draft
Contract
05
Page 78 of 169
33
GERMANTOWN POLICE DEPARTMENT FACILITY CONSTRUCTION PROPOSAL
AIA - A133 & AIA - A201
Please see separate attachment in email for
CG Schmidt’s full AIA A133 & A201 Template.
SECTION 05
DRAFT CONTRACT
Page 79 of 169
cgschmidt.com
11777 West Lake Park Drive.
Milwaukee, WI 53224
Page 80 of 169
Germantown
Police
Department
Facility
Village of
Germantown, WI
Proposal for Construction
Manager at Risk Services
May 29, 2026
Page 81 of 169
May 29, 2026
PATRICK MERTEN
Police Chief
JULIE BARTH
Administrative Assistant
Village of Germantown
N112W1687 Mequon Road
Germantown, WI 53022
Kraus-Anderson ®
Construction Company
151 East Wilson Street, Suite 100,
Madison, WI 53703
Office: 608-838-5444
Fax: 608-838-5445
www.krausanderson.com
Dear Chief Merten, Ms. Barth, and Selection Committee,
Your vision for a modern, resilient public safety facility is more than
a construction project—it is a commitment to the safety, well-being,
and future of the Village of Germantown. The stakes are high, and the
expectations are clear: your new police station must not only serve as a
secure, efficient hub for law enforcement, but also stand as a symbol of
trust and service for every resident.
This project demands a partner who understands the unique
operational, logistical, and technical challenges of public safety
construction. The experience Kraus-Anderson (KA) has gained from
delivering complex police stations and public safety facilities—including
those listed in our project experience—translates directly to your goals.
These projects required seamless phasing, uninterrupted operations,
and close coordination with multiple user groups, all while maintaining
strict budget and schedule discipline.
Key project considerations, including bedrock excavation, stormwater
management, extensive utility extensions, and the specialized
requirements of a live-fire range with its unique ballistics and ventilation
systems, necessitate a CMaR with a deep understanding of complex
municipal and law enforcement facility construction. The focus remains
on delivering a facility that not only meets the immediate needs but also
aligns with the Village’s 30-year operational life cycle objectives through
careful cost management, schedule adherence, and rigorous quality and
safety protocols.
The Village's new police department project deserves a team that brings
proven solutions, not just promises. The lessons learned from managing
active municipal campuses, integrating advanced security and evidence
handling, and delivering sustainable, future-ready facilities will be
leveraged to anticipate challenges and drive results. The focus remains
on your priorities: operational continuity, stakeholder engagement, and
a facility that supports your officers and staff for decades to come.
This is your moment to set a new standard for public safety in the
Village. Let’s build a facility that not only meets today’s needs but
also inspires confidence and pride for generations. The opportunity to
partner with you on this transformative project is both an honor and
a responsibility—one that will be met with unwavering commitment,
expertise, and purpose.
For questions or additional information, please contact:
KRAUS-ANDERSON ® CONSTRUCTION COMPANY
Michael J. Timmers, Director of Operations-Milwaukee
C: 414-216-7246 | mike.timmers@krausanderson.com
Page 82 of 169
Contents
TECHNICAL PROPOSAL . . . . . . . . . . . . . . . . . . . 1
PROJECT APPROACH . . . . . . . . . . . . . . . . . . . 15
COST PROPOSAL . . . . . . . . . . . . . . . . . . . . . 21
PROOF OF INSURANCE AND BOND ABILITY . . . . . . . 22
DRAFT CONTRACT . . . . . . . . . . . . . . . . . . . . 23
Page 83 of 169
New Village of Germantown Police Department Facility | KA Proposal | 1
TECHNICAL PROPOSAL
Firm Profile
Kraus-Anderson Construction Company is a family-owned, privately held
corporation established in 1897 and headquartered at 525 South Eighth Street,
Minneapolis, MN 55404. Kraus-Anderson consistently ranks among the top-tier
construction management firms in the United States by Engineering News-
Record, with operations spanning Minnesota, North Dakota, Wisconsin, Iowa,
and Arizona and a network of more than 675 skilled personnel.
Kraus-Anderson's financial strength is underscored by a bonding capacity
of $1.2 billion, confirming the firm's stability and commitment to enduring
client relationships. Over the past five years, Kraus-Anderson has delivered
more than 1,300 projects totaling over $3.17 billion under the Construction
Manager at Risk (CMaR) method, with a portfolio spanning municipal,
education, healthcare, aviation, and commercial sectors.
Our Milwaukee office positions Kraus-Anderson to serve the Village of
Germantown with locally embedded resources, regional subcontractor
relationships, and direct familiarity with Wisconsin municipal bidding
requirements. Kraus-Anderson's preconstruction and construction teams
are integrated from project inception through closeout, a model purpose-
built for CMaR delivery on complex public facilities such as the proposed new
Germantown Police Department.
Core Values
Integrity
Commitment
Valuing People
Teamwork
Page 84 of 169
New Village of Germantown Police Department Facility | KA Proposal | 2
TECHNICAL PROPOSAL
11. PUBLIC SAFETY | ADDITION + RENOVATION
CITY OF WHITE BEAR LAKE
White Bear Lake, MN
The City of White Bear Lake Public Safety Addition and
Renovation project involved a 42,000 SF expansion and
modernization of the city’s fire and police stations to
enhance emergency response and community service.
Key features include a 250 MPH tornado safe room,
modern apparatus bays, training spaces, gear wash and
turnout rooms, updated living quarters, squad garage,
offices, bunk rooms, fire day room, dining room, fire
pole, and tool room. The project was executed adjacent
to an active city hall, neighborhood, and business park,
with a detailed phasing plan developed to maintain
uninterrupted city operations. Upgrades encompassed
new mechanical, electrical, and life safety systems,
as well as improved site access and parking.
Kraus-Anderson served as construction manager and
project manager, delivering a resilient, efficient public
safety facility that prioritizes operational continuity,
firefighter wellness, and community safety for the City of
White Bear Lake.
Page 85 of 169
New Village of Germantown Police Department Facility | KA Proposal | 3
TECHNICAL PROPOSAL
11. POLICE DEPARTMENT RENOVATION
CITY OF EDEN PRAIRIE
Eden Prairie, MN
The City of Eden Prairie Police Department Renovation
involved a partial demolition and rebuild of the police
and fire administration areas, as well as the below-grade
parking garage. Portions of the remaining station were
remodeled and received miscellaneous updates to
enhance functionality and support the evolving needs of
the department. This project was delivered for the City
of Eden Prairie, reflecting a commitment to modernizing
public safety infrastructure and providing improved
facilities for both staff and the community.
Page 86 of 169
New Village of Germantown Police Department Facility | KA Proposal | 4
TECHNICAL PROPOSAL
11. POLICE + PUBLIC WORKS BUILDING
CITY OF ROSEMOUNT
Rosemount, MN
PHOTOS COURTESY OF THE CITY OF ROSEMOUNT
The City of Rosemount Police and Public Works building
is a modern, multipurpose municipal facility designed
to enhance public safety and operational efficiency
for the community. The 160,000 SF complex includes
a 48,000 SF police department with a squad garage,
administrative offices, a storm shelter, holding rooms,
and a six-lane gun range, alongside a 112,000 SF public
works area with garages for plow trucks and vehicles,
offices, shops, maintenance areas, and a wash bay.
Additional structures include cold and salt storage
buildings, all situated on a 20-acre site. Delivered using
a Construction Manager at Risk (CMaR) approach, the
project was completed ahead of schedule and under
budget, supporting the City of Rosemount’s mission to
provide safe, efficient, and sustainable services while
accommodating future growth.
Page 87 of 169
New Village of Germantown Police Department Facility | KA Proposal | 5
TECHNICAL PROPOSAL
11. CITY HALL AND POLICE DEPARTMENT EXPANSION
CITY OF BURNSVILLE
Burnsville, MN
The City of Burnsville City Hall and Police Department
Expansion project features a 212,000 SF, two-story
addition and comprehensive interior renovation to
modernize and expand municipal services. The scope
includes a new police station and a dedicated squad
car garage, enhancing operational efficiency and public
safety. Delivered through a construction management
approach, the project addresses construction budgets,
detailed estimates, schedules, and timelines to meet
the City’s evolving needs. This expansion was designed
to provide state-of-the-art facilities for both city
administration and law enforcement, supporting the
community’s growth and service expectations. The
project is currently under construction and is scheduled
for completion in March 2028.
Page 88 of 169
New Village of Germantown Police Department Facility | KA Proposal | 6
TECHNICAL PROPOSAL
11. POLICE STATION RENOVATION AND FIRE STATION ADDITION
CITY OF MINNETONKA
Minnetonka, MN
The City of Minnetonka Police Station Renovation and Fire
Station Addition project modernized the municipal campus
with a comprehensive 97,000 SF transformation, including
a 43,000 SF police station remodel, a 15,800 SF police
garage addition, and a 37,000 SF fire station addition.
The project delivered essential garage and storage space
for emergency vehicles and equipment, a dedicated
decontamination area, and extensive site improvements
such as new electric service, generator, retaining walls,
underground storm vault, and well water line. Sustainable
features included a white roof for cooling efficiency, reused
wood from on-site century-old oak trees, ultra-low-flow
plumbing fixtures, smart control and LED lighting, and
enhanced landscaping. Delivered using the Construction
Manager at Risk (CMaR) method, the project maintained
continuous City Hall and water supply operations,
resulting in a state-of-the-art public safety campus that
advances the City of Minnetonka’s commitment to safety,
sustainability, and community service.
Page 89 of 169
New Village of Germantown Police Department Facility | KA Proposal | 7
TECHNICAL PROPOSAL
11. FBI MILWAUKEE FIELD OFFICE - OFFICE CAMPUS RENOVATION
FEDERAL BUREAU OF INVESTIGATION
Milwaukee, WI
The FBI Milwaukee project is a Level IV, built-to-suit
project leased to the government for 20 years. The
building’s occupancy is Class A office space for a
federal law enforcement tenant. The office building,
annex, parking structure, visitor screening facility,
and secondary security entrance were designed and
constructed to meet exact specifications and a Program
of Requirements similar to those required by the FBI.
This four-story, Class A LEED Gold federal office campus
serves as the Milwaukee Division’s headquarters. The
project includes renovation of 65,000 RSF of existing
space and the addition of 17,546 RSF. The office building
is designed for high efficiency and functionality, featuring
Level IV security, a progressive collapse structural
system, blast force protection, and a highly secured
perimeter and setback.
Page 90 of 169
New Village of Germantown Police Department Facility | KA Proposal | 8
TECHNICAL PROPOSAL
JON PORTER
Director of Building Science
KYLE GOW
MEP Group Manager
ANDREA BLAIR
BIM/VDC Group Manager
DAN ANSELMENT
Public Safety Consultant
JAY VANDER LEEST
Director of Safety
TECHNICAL RESOURCES TEAM
JOE KOLAVO
Preconstruction Services
Manager/Estimator
MARK BREIDEL
Project Manager
TOMMY
CUMMINGS
Construction
Superintendent
PRECONSTRUCTION + CONSTRUCTION TEAM
PROJECT LEADERSHIP
MIKE TIMMERS
Project Director
MARK KOTTEN
National Director of Government Sector
Page 91 of 169
New Village of Germantown Police Department Facility | KA Proposal | 9
TECHNICAL PROPOSAL
PROPOSED
PROJECT TEAM
Kraus-Anderson proposes a dedicated, site-specific team with direct municipal and public safety facility experience.
Each team member will commit the availability necessary to deliver preconstruction and construction services from
the 30% design milestone through project closeout.
PROJECT LEADERSHIP
MIKE TIMMERS
Project Director/Director of Operations-Milwaukee
Mike, as your single point of contact, is responsible for corporate oversight of all
preconstruction and construction services. He will direct Kraus-Anderson resources to
establish and achieve the Village of Germantown goals and expectations. Mike’s knowledge
and insight, along with his superior organizational skills, gained from managing, directing,
and overseeing construction projects of all types and sizes, are key elements in the
successful management planning that goes into all of KA’s construction projects.
MARK KOTTEN
National Director of Government Sector
As the National Director of Government Sector at Kraus-Anderson, Mark is instrumental
in leveraging our expertise for projects like the Village of Germantown Police Department
project. Mark will advocate for the City's vision, making sure every aspect aligns with
expectations. With a focus on project team coordination and relationship-building, Mark
confirms KA’s commitment to delivering excellence within established goals at every stage.
Page 92 of 169
New Village of Germantown Police Department Facility | KA Proposal | 10
TECHNICAL PROPOSAL
PRECONSTRUCTION + CONSTRUCTION TEAM
JOE KOLAVO
Preconstruction Services Manager/Estimator
Joe will be responsible for developing the project cost
estimate from schematic documentation to the final
cost estimate. He will lead the budgeting/estimating
activities during preconstruction. He will also be
responsible for assisting in constructability reviews
and value management with the project team. Joe will
work to confirm that the most current subcontractor
pricing trends are reflected in our estimates and that
the upcoming bid period of the project is effectively
communicated to the subcontractor market.
EDUCATION
Architectural Engineering
Milwaukee School of Engineering
Milwaukee, WI
INDUSTRY EXPERIENCE
Since 2012
RELEVANT PROJECTS
» City of Eau Claire -
- Training facility preconstruction services
» City of Cedarburg
- Police & Fire department concept estimating
» Southern Ozaukee Fire Department
- Headquarters concept estimating
» Breck Athletic Facility
- Conceptual estimating for a 190,000 SF indoor
athletic training facility, soccer fields, baseball fields,
banquet hall and retail corridor with hotel on a
150-acre development with a plan for phased
construction over 5 years
» Southridge
- Mixed-Use Multifamily development, providing
enclosed parking, retail core and shell space, and
240 units of apartment building with amenity spaces,
as well as site development for future phases
» Steris Labs
- Renovation of an existing space for a new Steris
Laboratory location, including office support space,
media prep, cleanroom laboratory and sampling
space, and their bio-burden handling facility.
Page 93 of 169
New Village of Germantown Police Department Facility | KA Proposal | 11
TECHNICAL PROPOSAL
PRECONSTRUCTION + CONSTRUCTION TEAM
MARK BREIDEL
Project Manager
Mark will serve as the project manager from
preconstruction through construction completion.
He will provide management oversight of all project
elements including budget and schedule control and
overall project communication.
In addition to comprehensive preconstruction phase cost
estimating, value engineering, and project scheduling,
Mark will develop a cash flow disbursement schedule for
use by the Village of Germantown. He will also provide
the front-end bidding documents and generate bidder
interest in the project. His responsibilities will include
subcontractor performance review, subcontractor
negotiation and award, monitoring and updating
progress schedules, and administration of job site staff.
EDUCATION
B.S., Architecture
University of Minnesota-Twin Cities,
Minneapolis, MN
INDUSTRY EXPERIENCE
Since 2004
RELEVANT PROJECTS
» Ellsworth High School
- 15,000 SF fitness center, greenhouse, and CTE
classroom additions and renovations to existing
2-story high school
» West Salem High School
- 40,000 SF CTE addition with a fitness center,
greenhouse replacement, and renovations at the
high school
» Village of Lake Delton
- 10,094 SF interior renovation of existing
Delton Kay C. Mackesey - administration building
» Verizon Wireless
- 18,500 SF expansion to existing Master Switch Center
including demo of existing
Page 94 of 169
New Village of Germantown Police Department Facility | KA Proposal | 12
TECHNICAL PROPOSAL
TOMMY CUMMINGS
Construction Superintendent
Tommy is responsible for the day-to-day supervision and
management of all construction activities associated
with the Village of Germantown Public Safety Training
Facility project. He is directly responsible for scheduling,
coordination, quality control, and confirming the safety
of all on-site personnel, as well as overseeing general
procedures. Tommy will hold weekly meetings with trade
contractors to review the progress of the work.
He is also the direct point of contact for users regarding
logistics and coordination of ongoing operations. During
the construction phase, he will work closely with project
manager Mark Breidel to lead, manage, and direct all
field activities.
Tommy’s responsibilities will involve preparing detailed
construction schedules, conducting daily safety huddles
and weekly trade foreperson meetings, monitoring the
safety program, administering construction support
activities, confirming construction compliance, resolving
field installation details/issues, and developing a
punch list.
EDUCATION
Normandale Community College
Bloomington, MN
INDUSTRY EXPERIENCE
Since 1993
RELEVANT PROJECTS
» Village of Summit
- 20,000 SF of new public works buildings, including a
15,000 SF police and city hall building, and a 5,000 SF
timber-framed salt storage building
» City of Oconomowoc
- A 20,000 SF new public works facility that houses
offices, and equipment
» U.S. Department of Veterans Affairs
- 8,781 SF new VA Olympia Fields outpatient clinic
» Enerpac
- 47,734 SF corporate HQ office build-out
» Menasha Corporation
- 89,000 SF addition to a manufacturing facility,
including interior remodel of the mezzanine, restroom,
breakroom, stair tower and 9,274 SF new office space;
and site work consisting of a new 100-stall parking lot
and fire lane
PRECONSTRUCTION + CONSTRUCTION TEAM
Page 95 of 169
New Village of Germantown Police Department Facility | KA Proposal | 13
TECHNICAL PROPOSAL
Our technical experts are available to offer support across various areas, including market trends, cost estimating,
value management, Building Information Modeling (BIM), constructability, quality management, and safety. Their
invaluable contributions are immediately apparent during the preconstruction phase, where they efficiently identify
and resolve conflicts and challenges long before they can manifest in the field, potentially causing cost overruns and
delays. With a proven track record of successfully planning and executing numerous construction projects similar to
yours, our technical experts have become an indispensable asset to our clients.
KYLE GOW, PE (MN)
MEP Group Manager
Kyle specializes in long-term growth strategies, mechanical system design, and MEP
coordination. Known for his cost estimating and preconstruction expertise, he provides
options analysis, constructability review, and project scheduling, while overseeing
installation, commissioning, and occupancy planning.
JON PORTER, PE (MN), ASSOCIATE AIA
Director of Building Science
Jon’s 30 years of commercial building expertise bring invaluable building science
knowledge to Kraus-Anderson. He advises on constructability, materials, workflow,
installation techniques, and testing protocols. Jon also oversees Kraus-Anderson’s
quality control and assurance programs.
ANDREA BLAIR
BIM/VDC Group Manager
Andrea plays a key role on the team by leveraging Building Information Modeling and
Virtual Design and Construction (BIM/VDC) technologies to improve project efficiency and
coordination. She applies Lean principles to proactively identify system conflicts before
construction, streamline clash detection, and minimize costly rework. Andrea also utilizes
a range of in-house reality capture tools, including drone operations and laser scanning
technologies, to capture precise existing conditions that support design validation, quality
control, and progress documentation. Her expertise helps drive better project outcomes
while reducing both time and resource expenditures.
JAY VANDER LEEST
Director of Safety
Jay’s responsibilities include corporate construction safety management, federal, state,
and local regulations, investigations, evaluations, and analyses of job site issues, training
and employee development, inspections, policy development and implementation,
Workers’ Compensation and claims management, record-keeping, strategic planning,
Safety Department leadership, and further development of a safety culture through KA
and our contracting partners.
TECHNICAL RESOURCES TEAM
Page 96 of 169
New Village of Germantown Police Department Facility | KA Proposal | 14
TECHNICAL PROPOSAL
DAN ANSELMENT
Public Safety Consultant
Dan is a public safety professional with 20 years of experience as a practitioner and
subject matter expert in various areas within law enforcement, forensics, and public safety
training, most recently regarding public safety training centers. He brings with him a
unique skillset through his work, getting a $30M public safety training center construction
project completed and the facility staffed and operational. This state-of-the-art training
center now supports over 55 federal, state, county, and local city public safety agencies in
the east metro area of the Twin Cities. This facility has become a gold standard for other
agencies nationwide, and Dan frequently consults with other agencies from around the
U.S. who are looking to design and build their own training facility.
His knowledge regarding public safety training, operating, and maintaining a firearms
range, managing a laboratory and various training environments, and working as a project
manager to develop a 2-acre outdoor training location for human remains makes Dan a
valuable resource and allows him to give a much-needed perspective when designing
a facility. He is a strong asset to any team regarding the design and use of these facility
spaces. He has identified vulnerabilities and design changes needed that will better allow
organizations to remain in compliance with OSHA regulations regarding hazardous lead
waste, lead mitigation strategies, and other facility-related designs to assist with the overall
operations, which have been valuable to architects and construction companies.
Dan holds a B.S. degree from Metropolitan State University and an M.A. degree in
Organization Leadership through Concordia University. He is a licensed police officer and
teaches at two large universities. Dan has been awarded a Life-Saving Award and several
Distinguished Service Awards as a police officer.
TECHNICAL RESOURCES TEAM
Page 97 of 169
New Village of Germantown Police Department Facility | KA Proposal | 15
Bedrock Risk
Range Complexity
Utility Logistics
Long-Lead Equipment
Budget Discipline
Life Cycle Focus
The Village of Germantown is undertaking one of its most significant public
safety investments in recent history — the complete replacement of its existing
police department facility with a new, approximately 64,500 to 66,500 SF
headquarters designed to serve the community for decades to come. Sited at
the former Department of Public Works building at N122 W17177 Fond du Lac
Avenue, the project involves complex site conditions, a substantial 2,500-foot
sanitary sewer and water main extension, and technically demanding program
elements — including a live-fire range, secure indoor sallyport, evidence
storage, and modern police administration and investigation spaces.
Kraus-Anderson understands that the Village's primary concerns center on five
interrelated challenges: unpredictable bedrock conditions that could introduce
cost and schedule risk; the complexity and safety requirements of the live-fire
range systems; the logistics of a 2,500-foot utility corridor along a live public
roadway; long lead times for specialized range HVAC and electrical switchgear;
and maintaining rigorous budget discipline within a $35 million construction
budget while protecting a 30-year operational life cycle for the facility.
Kraus-Anderson will join the project team at the 30% design milestone,
working in close collaboration with FGM Architects to deliver preconstruction
and construction phase services under a Guaranteed Maximum Price (GMP)
contract framework. The team's approach is grounded in the principle that the
most successful construction projects start with collaborative planning and
communication well before breaking ground, allowing every decision to be made
with accurate cost and schedule data in hand.
PROJECT APPROACH
Project Understanding
Page 98 of 169
New Village of Germantown Police Department Facility | KA Proposal | 16
PROJECT APPROACH
Pre-Construction Services
Kraus-Anderson's preconstruction process is a cornerstone of its project delivery
approach, emphasizing collaboration, transparency, and strategic planning. At its
core, the team considers that the greatest ability to influence cost, schedule, quality,
and constructability occurs well before construction starts — making early integration
at the 30% design milestone a critical advantage for the Village.
Cost Estimating and Estimate Reconciliation
Kraus-Anderson will provide detailed milestone estimates at the 30%, 60%, 90%,
and 100% design phases, reconciling each estimate with FGM Architects to
confirm alignment between design intent and budget reality. Leveraging the team's
proprietary Modelogix platform and historical project cost database, estimates will
be structured to reflect the actual level of design detail at each milestone — from
conceptual system-level modeling through trade-specific line items as the documents
mature. All estimates will be presented as living documents, updated transparently
throughout the design phase to reflect market conditions, design evolution, and any
scope adjustments — eliminating financial surprises for the Village.
Value Management
Value management at Kraus-Anderson is a collaborative team endeavor involving not just the project manager and
estimator, but also the project superintendent, in-house MEP specialists, and building science managers — all
working together to identify alternatives that protect design intent while aligning scope with the Village's $35 million
budget and the facility's 30-year operational life cycle requirements. Alternatives will be tracked within the estimate
body as voluntary alternates, allowing the full cost impact to be seen in real time as options are accepted or rejected
by the Village and FGM Architects.
Constructability Reviews
Kraus-Anderson will conduct rigorous constructability reviews at each design
milestone, with particular focus on the two highest-risk technical elements: bedrock
excavation and live-fire range systems. These reviews identify and resolve conflicts
within the documents, detect and eliminate future change orders and requests for
information, minimize project delays, and enhance overall project scheduling. BIM
and VDC tools will be employed to detect system conflicts — particularly between
mechanical ductwork, ballistic wall assemblies, and structural elements — before
construction begins, preventing costly field rework.
Baseline Schedule Development
Kraus-Anderson will develop a comprehensive baseline construction schedule at the outset of the preconstruction
phase that encompasses all critical milestones — from design completion through construction and closeout. The
schedule will specifically account for long-lead equipment procurement, with early identification of specialized
range HVAC systems and electrical switchgear that carry extended manufacturing lead times. The schedule will also
address sequencing for the utility extension corridor, earthwork and bedrock mitigation, and the phased construction
approach required on the Fond du Lac Avenue site.
Page 99 of 169
Proposal Name | KA Proposal | 17
PROJECT APPROACH
TRUCKING/HAULING/PRIMARY DELIVERY ENTRANCE
OFFICE TRAILER
CONSTRUCTION PARKING
MATERIAL LAYDOWN/STAGING AREA
FOND DU LAC AVE
DIVISION ROAD
GATE
1
2
2
3 4
5
4
1
5
2
3
4
Page 100 of 169
New Village of Germantown Police Department Facility | KA Proposal | 18
PROJECT APPROACH
Utility Extension Strategy
The 2,500-foot sanitary sewer and water main extension represents one of the most logistically demanding elements
of this project, requiring careful coordination along Fond du Lac Avenue to manage traffic, maintain public access,
and control costs within the overall $35 million construction budget.
During preconstruction, Kraus-Anderson will work with FGM Architects and the Village's civil engineer to conduct
a detailed constructability review of the utility corridor, identifying trench depth requirements, potential bedrock
interference along the route, and any conflicts with existing underground utilities. Bedrock conditions identified
along the Fond du Lac Avenue alignment will be modeled early to avoid unforeseen excavation costs and to give the
Village a realistic contingency framework before the GMP is established.
Our team will develop a phased utility installation sequence that coordinates closely with the building construction
timeline. The utility extension will be advanced as an early work package — activated ahead of the main building
footprint work — so that site service connections are ready and available when the facility structure reaches critical
milestones. This sequencing strategy directly supports schedule compression and eliminates the risk of the building
being ready while utility connections remain incomplete.
A detailed traffic control and disruption avoidance plan will be prepared for work along Fond du Lac Avenue,
addressing site entrance and exit points, designated delivery and staging zones, signage and wayfinding, and
coordination protocols with the Village and adjacent property owners. Stormwater management controls will be
established and maintained in compliance with Best Management Practice (BMP) requirements throughout the
duration of the utility excavation work.
Page 101 of 169
New Village of Germantown Police Department Facility | KA Proposal | 19
PROJECT APPROACH
Live-Fire Range Integration
The indoor live-fire range is one of the single most technically complex element of the new Germantown Police
Department facility, requiring specialized expertise in ballistic containment systems, acoustic isolation, and
dedicated range ventilation. Kraus-Anderson treats this scope as a distinct work package within the broader project,
applying focused constructability review, early procurement, and heightened quality inspection protocols to this
element from the start of preconstruction.
During the design phase, Kraus-Anderson's in-house MEP specialists will engage directly with FGM Architects and
the range systems designer to review ventilation design documents for accuracy, thoroughness, code compliance,
and value management opportunities. BIM coordination will be used to confirm that the range exhaust and supply
systems, ballistic wall assemblies, and structural elements are fully coordinated, with all system conflicts resolved in
the virtual environment before construction activities commence.
The specialized range HVAC system will be identified as a long-lead item at the outset of preconstruction, with early
manufacturer engagement initiated to confirm lead times, lock in equipment specifications in coordination with the
design team, and sequence procurement to avoid any impact on the construction schedule. During construction,
preinstallation meetings will be held with the range systems installer before any ballistic or ventilation components
are placed, confirming that trade sequencing, fit, and performance standards are understood and agreed upon by all
parties. Inspection checkpoints specific to ballistic panel installation, trap and bullet containment, and ventilation
system performance will be built into the project's quality control plan.
Page 102 of 169
New Village of Germantown Police Department Facility | KA Proposal | 20
PROJECT APPROACH
Safety and Quality Management
Job site safety is Kraus-Anderson's top priority. Our team strives for zero lost time on every project through a
proactive, prevention-first approach to safety management. For the Germantown Police Department project, a
site-specific safety plan will be developed that includes an emergency management plan developed jointly with
the Village, safety program reviews for each subcontractor, a comprehensive job site safety orientation, daily
safety huddles, weekly toolbox meetings led by the superintendent, and weekly OAC progress meetings to keep all
stakeholders aware of ongoing and upcoming construction activities.
Special safety protocols will govern work within and adjacent to the live-fire range construction zone. Given the
specialized nature of ballistic wall system installation and range ventilation equipment, Kraus-Anderson will implement
mandatory preinstallation meetings for these scopes, with all trade personnel briefed on the specific handling,
sequencing, and installation requirements before work commences. Inspection checkpoints will be established at critical
installation stages to confirm compliance with design specifications and all applicable safety standards.
Kraus-Anderson's quality assurance and quality control program spans all project phases, from preconstruction
through closeout, with an emphasis on prevention over correction. During construction, quality control will be
maintained through full-time on-site supervision and preinstallation meetings for all critical work scopes, with daily
job site walks conducted to confirm the quality of work as it progresses. The closeout phase will include system
testing and commissioning, walk-throughs with Village facility personnel, and comprehensive as-built documentation
to support the long-term 30-year operational life cycle of the new facility.
Throughout all phases, Kraus-Anderson will leverage Forma Build (Formerly known as Autodesk Build) for real-time
communication, document control, and project reporting, making sure the Village, FGM Architects, and all project
stakeholders have access to current schedules, submittals, and project status information at all times. Monthly
progress reports, ongoing budget tracking, and schedule updates will be delivered to the Village throughout the
construction phase, providing full transparency and supporting prompt, informed decision-making at every stage of
the project.
Page 103 of 169
New Village of Germantown Police Department Facility | KA Proposal | 21
COST PROPOSAL
1. Estimated Construction Cost
2.
Total
Assumes 14 month Construction
Phase duration
Monthly
Notes
1.75% 1.75% CM Fee
1.00% 1.00% Umbrella Liability Insurance
0.00% 0.00% By Owner, KA can provide quote if applicable
0.0545% 0.0545% Performance & Payment bond
2.80% 2.80%
Notes
$ - $ - No cost with Award
$0.00 $0.00
Notes
$ 363,720 $ 25,980.00
$ 363,720 $ 25,980.00
$ 19,600 $ 1,400.00
$ 747,040 $ 53,360.00
Notes
$ - $ - Included in Fee
$ 17,360 $ 1,240
$ 16,240 $ 1,160
Project Coordinator $ 67,894 $ 4,850
$ 7,840 $ 560
$ 109,334 $ 7,810
Notes
Telecommunications Allocation $ 25,500 $ 1,821
Copy/Postage/Supplies - Allocation $ 24,000 $ 1,714
$ 44,304 $ 3,165
$ 30,310 $ 2,165
$ 124,114 $ 8,865
Total
Assumes 14 month Construction
Phase duration
Monthly Notes
2.80% 2.80%
$ - $ -
$ 747,040 $ 53,360
$ 109,334 $ 7,810
$ 124,114 $ 8,865
see below see below Cost of Work
$ 980,488 $ 70,035
Notes
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ - Cost of work
$ - $ -
PRECONSTRUCTION PHASE
CONSTRUCTION MANAGEMENT SERVICES PROPOSAL
Request For Proposal (RFP) response prepared for the
Village Germantown, WI - Police Dept Facility
CONSTRUCTION MANAGER NAME: Kraus-Anderson Construction
$28,000,000.00
April 2027 -June 2028
CONSTRUCTION MANAGEMENT FEES AND INSURANCES
Construction Management Fee
Umbrella Liability Insurance
Builder's Risk Insurance
Performance and Payment Bond
Construction Management Fee and Insurance %:
General Superintendent
Pre-Construction Phase Services Fixed Fee
Pre-Construction Sub-Total:
CONSTRUCTION PHASE - PROJECT PERSONNEL
Field Superintendent
Public Safety Consultant
Project Director and National Market Sector Leader
On-Site Personnel Sub-Total:
CONSTRUCTION PHASE - ADDITIONAL ADMINISTRATION
Project Manager
GENERAL REQUIREMENTS - ASSUMED COST OF WORK
SUMMARY
Superintendent Vehicle
Reimbursable Sub-Total:
Safety Personnel
Project Accountant
Construction Manager Expenses Sub-Total:
REIMBURSABLE EXPENSES
Project Collaboration - IT Allocation
CONSTRUCTION MANAGEMENT FEES AND INSURANCES
PRECONSTRUCTION PHASE
CONSTRUCTION PHASE - PROJECT PERSONNEL
CONSTRUCTION PHASE - ADDITIONAL ADMINISTRATION
REIMBURSABLE EXPENSES
Totals:
Dumpsters / Hauling / Tipping Fees
Tools / Equipment
GENERAL REQUIREMENTS - ASSUMED COST OF WORK
Temporary Toilets
General Requirements Total
Delivery / Yard Expenses
Safety Supplies and/or Equipment
Project Signage
Temporary Heat and Conditioning (equipment and fuel)
Job Trailer (setup, removal, utility hookups & operating costs)
Copy, Postage, Office Supplies
Temporary Utilities
Travel Expenses (Subsistence) / Mileage
Page 104 of 169
New Village of Germantown Police Department Facility | KA Proposal | 22
Kraus-Anderson Construction Company utilizes Kraus-Anderson Insurance
Agency for standard insurance coverage, including general liability, builder's
risk, and all other requirements applicable to a project of this scale. A Certificate
of Liability Insurance confirming current coverage levels is available and will be
included as an appendix to this submission.
Subcontractor Default Insurance
To provide an additional layer of financial protection, Kraus-Anderson uses
Subcontractor Default Insurance (SDI) alongside traditional bonding wherever
possible. SDI offers broader and more flexible coverage than conventional
subcontractor bonding, and grants Kraus-Anderson greater control over claims
resolution in the event of a default — supporting timely project delivery and
protecting the Village from non-payment exposure at the second-tier level.
Additionally, Kraus-Anderson maintains a lien waiver policy to confirm that all
subcontractors are paying their sub-subcontractors and suppliers, providing
the Village with protection against non-payment concerns throughout the
construction phase of the New Police Department Facility.
Bonding Capacity
Kraus-Anderson confirms the ability to furnish 100% Performance and Payment
Bonds for the Village of Germantown's New Police Department Facility at the
required $30 million total project cost threshold.
Kraus-Anderson's bonding company is Travelers Casualty and Surety Company
of America. Travelers Casualty and Surety Company of America has bonded
Kraus-Anderson for over 60 years and stands as a leader in the surety industry
for over a century. Kraus-Anderson remains financially strong with a bond
program of $500 million per contract, with an overall capacity of $1.2 billion
— well in excess of the $35 million bond requirement established by this RFP.
In the past, Travelers has supported and bonded Kraus-Anderson projects up
to $500,000,000, demonstrating the depth of the surety relationship and the
financial standing of Kraus-Anderson relative to the demands of this engagement.
Insurance Questions
For questions regarding
insurance capabilities or
capacities, please contact:
Clay Shelton, CPCU, Senior
Director of Risk Management
952-707-8211
clay.shelton@krausanderson.com
PROOF OF INSURANCE
AND BOND ABILITY
Insurance Coverage
Bonding Questions
For questions regarding
bonding capabilities,
please contact:
Mary Jo Dingwall,
Director of Surety —
Kraus-Anderson Insurance
952-426-6281
mdingwall@kainsurance.com
Page 105 of 169
New Village of Germantown Police Department Facility | KA Proposal | 23
PROOF OF INSURANCE AND BOND ABILITY
Page 106 of 169
New Village of Germantown Police Department Facility | KA Proposal | 24
PROOF OF INSURANCE AND BOND ABILITY
Page 107 of 169
New Village of Germantown Police Department Facility | KA Proposal | 25
DRAFT CONTRACT
Please see separately attached draft contract for your review.
Page 108 of 169
Positively Impacting Lives
VILLAGE OF GERMANTOWN
POLICE DEPARTMENT
Proposal for:
CONSTRUCTION
MANAGEMENT SERVICES
FACILITY
Page 109 of 169
2.
FIRM PROFILE:
LEGAL NAME:
Moore Construction Services, LLC
ADDRESS:
W146 N5650 Enterprise Ave,
Menomonee Falls, WI 53051
TYPE OF ORGANIZATION:
Established Limited Liability Company
STAFF SIZE:
30
YEAR ESTABLISHED:
2007
SERVICES:
Pre-Construction
Construction Management
CONSULTANTS:
Siteguard Safety
Services
AWARDS:
Daily Reporter
Top Projects
Milwaukee Business Journal
Real Estate Awards
Best Places to Work
Largest Milwaukee-Area Construction Firms
Positively Impacting Lives
At Moore Construction Services we are driven
by our mission of Positively Impacting Lives.
Our partnership approach and how we engage
with our customers, designers, subcontractors
and employees is reflective of this mission,
guiding every interaction and decision we make.
It’s what we strive for each and every day as we
work to deliver meaningful, reliable outcomes
for our clients and the communities we serve.
Page 110 of 169
3.
VILLAGE OF GERMANTOWN DPW
GERMANTOWN, WI
The new Germantown Department of Public Works spans 141,000 sq. ft. across three
buildings on a 37-acre site, consolidating the Village's operations under one roof and
modernizing spaces for equipment, vehicles and staff. The site includes dedicated
workshops for each division, drive-through truck wash bays, a state-of-the-art vehicle
maintenance shop, dedicated fueling station, a yard waste collection and composing
facility, and advanced brine making capabilities.
262-345-1280 • marketing@moore-cs.com • moore-cs.com
Page 111 of 169
4.
262-345-1280 • marketing@moore-cs.com • moore-cs.com
HARTFORD CITY HALL
HARTFORD, WI
This project consisted of a 52,000 sq. ft. remodel of the existing city offices to create new
spaces for City Hall & the Police Department, including a new 2,500 sq. ft. Sally Port
addition. This project was completed in 3 phases to allow the city offices to remain open
during construction.
Page 112 of 169
5.
JACKSON COMMUNITY CENTER
JACKSON, WI
A 9,840 sq. ft. addition and full renovation transformed the Jackson Community
Center while keeping the facility open throughout construction. The project
enhances a wide range of community offerings — including senior meals,
business meetings, fitness classes, pickleball leagues, early education programs,
youth services, and church gatherings.
262-345-1280 • moore-cs.com
Page 113 of 169
6.
NEW BERLIN ACTIVITY AND
RECREATION CENTER PHASE II
NEW BERLIN, WI
The second phase of the ARC is a 57,000 sq. ft addition includes an indoor
gymnasium, sport courts, meeting spaces, concession area, elevated track &
exercise space.
262-345-1280 • moore-cs.com
Page 114 of 169
7.
NEW BERLIN DPW
NEW BERLIN, WI
Our team is partnering with Perspective Design and The City of New Berlin to add two
23,000 sq. ft. cold storage buildings to the 10 acre site for the city's new Department of
Public Works.
262-345-1280 • moore -cs.com
Page 115 of 169
8.
262-345-1280 • marketing@moore-cs.com • moore-cs.com
NEW BERLIN UTILITIES
NEW BERLIN, WI
The City of New Berlin remodeled 8,700 sq. ft. of their existing building and
constructed a 25,000 sq. ft. addition. This addition included combining the offices,
vehicle storage, and a workshop, in addition to centralizing the Water Utility
Department to better serve its customers.
Page 116 of 169
9.
NOTABLE P ROJECTS
COMMERC IAL PROJECTS
Ally’s Bistro & Ally's Powerhouse
Alto-Shaam
Amazon DML6
Beyond Vision
Burghardt Sporting Goods
Chenequa Country club
Entrust Manufacturing
Five Star Manufacturing
Glenroy, Inc.
Moore Corporate Office
Server Products, Inc.
Standard Electric Supply
Village of Germantown DPW
Westmoor Country Club
Yerkes Observatory
INSTIT UTIONAL PROJECTS
Carroll University
Catholic Memorial High School
Crossroads Community Church
Fox Point Lutheran Church
Germantown DPW
Hartford City Hall & Police Station
Holy Apostles Adoration Chapel
Menomonee Falls School District
New Berlin Utilities
New Berlin Historical Museum
New Berlin DPW
New Berlin Activity and Recreation Center
Rogers Behavioral Health
St. Dominic Church and Gym
Waukesha School District
Wauwatosa Ave. United Church
M
ULTI - FAMI LY PR OJ EC T S
Arrabelle Apartments
Drexel Ridge Apartments Phase II
Orchard Hills
SoNa Lofts
Tennessen Flats & Fussville Market
The Westerly Senior Living
MICHAEL J. MOORE
PRESIDENT
EXPERIENCE
After a successful career in construction that spanned over three decades, Mike
founded Moore Construction Services in 2007. His business acumen and commitment
to exceptional project delivery has helped fuel the company’s growth since its
inception, earning multiple designations as one of the fastest growing companies in the
region. Clients credit Mike’s strong project management skills and abilities, his no
nonsense approach to customer service, and his ability to assemble and organize highly
efficient teams, as his primary keys to success. Most importantly, he commits to a true
partnership approach on each and every project which supports the company's mission
to positively impact lives. This commitment has earned him a strong reputation
in the industry for achieving high quality results.
Mike’s role as President of Moore Construction Services is to manage and mentor all
team members while ensuring the client’s goals are kept top of mind and achieved.
With more than $1 billion worth of commercial projects under his belt and experience
in building a strong and successful business operation, Mike is a leader who achieves
project success.
EDUCA TION & AW ARDS
University of Wisconsin-Stout, 1984
Bachelor of Science, Industrial Technolog
y, Concentration in Building Construction
President Award, 2015 The Chamber, Inc - Greater Menomonee Falls & Sussex Captain
of Industry, 2017, The Chamber, Inc - Greater Menomonee Falls & Sussex Future 50
Award 2017, 2018, 2019, 2021, 2022, 2023, 2024 MMAC
Fastest Growing Firm, 2018, 2019, 2020 Milwaukee Business Journal
Emerging Business of the Year, 2019, The Daily Reporter
Business Owner of the Year, 2019, The Daily Reporter
Humanitarian of the Year, 2021,
The Chamber, Inc - Greater Menomonee Falls & Sussex
Best Places to Work, 2023, 2024, Milwaukee Business Journal
PROFESSIONAL A FFILIA TIONS
University of Wisconsin - Stout
Industry Advisory - STEM College/Construction Program 2018-19 Committee Chair
Menomonee Falls Chamber of Commerce, 2013 President
Metropolitan Milwaukee Assoc. of Commerce, CEO Roundtable Facilitator
Catholic Memorial High School, Building Committee Chair
Menomonee Falls Chamber of Commerce, CEO Roundtable Facilitator
Froedtert Menomonee Falls Hospital, Foundation Board Member
UW Stout and The Chamber, Guest Speaker, Servant Leadership
Beyond Vision, Board Member
Acacia, Roundtable Facilitator
office: 262-345-1280 • email: mike.moore@moore-cs.com • moore-cs.com
Page 117 of 169
10.
NOTABLE P ROJECTS
COMMERC IAL PROJECTS
Alto-Shaam
Amazon DML6
Beyond Vision
Burghardt Sporting Goods
Copart, Inc.
Five Star Fabrication
Lynch Truck Center
M
etal Era
Orthopaedic Associates of Wisconsin
Tesla, Inc.
Westmoor Country Club
INSTITUT IONAL PROJECTS
City of New Berlin
Fox Point Lutheran Church
Germantown DPW
Jackson Community Center
Innovation Station
Mequon-Thiensville Community Promenade
Primose School of Brookfield
Rogers Behavioral Health
Victory Christian Academy
Wauwatosa School District
Yerkes Observatory
MULT I - FAMI LY PROJECTS
Arrabelle Apartments
Drexel Ridge Apartments Phase II
Cedar Community
Norden Range Apartments
Orchard Hills Apartments
SoNa Lofts
The Emree
The Granary
The Margeurite Apartments
The Westerly
Tennessen Flats & Fussville Market
office: 262-345-1280 • email: tom@moore-cs.com • moore-cs.com
TOM SMITH , LEED AP
EXECUTIVE VICE P RESIDENT
EXPERIENCE
Tom is a highly-respected construction industry executive with 40+ years of
project management experience in a variety of building types of all sizes and
complexities. His forte is the ability to engage early on a project so he can
establish a strong foundation by accurately estimating, budgeting and scheduling
the project in real time. Once these preconstruction activities are complete and
the goals for the project are established, Tom oversees the project managers
and other team members to ensure they carry out all construction activities in
a first-class manner . His guidance, knowledge and support enhance the entire
building process and give owners the assurance that a successful outcome will
be achieved.
Tom’s core areas of expertise include commercial office, industrial, healthcare,
multi-family housing, senior living and hospitality/retail. In these areas, he
managed over $1 billion worth of construction on hundreds of projects.
EDUCA TION & TRAINING
University of Wisconsin - Madison 1983
Bachelor of Science, Construction Management
Icon of the Industry, 2020, The Daily Reporter
PROFESSIONAL AFFILIA TIONS
American Institute of Constructors
City of Waukesha, Member of the Board of Appeals
NAIOP - Wisconsin
Project Management Institute
Wisconsin Green Building Alliance
WasteCap Wisconsin
Page 118 of 169
11.
NOTABLE PROJECTS
COMMERCIAL PR OJECTS
Aurora Clinic Rehabilitation Wing
Aurora Clinic First Floor
Beyond Vision- VisABILITY Center
Mica Tool
National Business Furniture
Siebert Lutheran Foundation Office
TCI
INSTI TUTIONAL
Germantown DPW
Hope Church
Lynch, Waterford
Marian Milwaukee
MIAD 4th Floor
MSOE STEM Center
MSOE Baseball Fields
Rogers Behavioral Health
Ridge Community Church, Greenfield
Ridge Community Church, Oak Creek
Southbrook Church
Salem Lutheran Church
MULTI-FAMI LY
Point Place
Mammoth Springs
Menomonee Falls Mixed-Use
St. Mary of the Hill
KATHRYN SULLIVAN
ESTIMATOR / PROJECT MANAGER
EXPERIENCE
Working in the industry for a decade, she has experience managing a
variety of complex projects in commercial, industrial, educational, and
religious industries.
Kathryn is responsible for managing the planning, schedule preparation,
resource allocation, bid tracking and forecasting on her projects. Her
supportive and friendly demeanor, as well as passion for the industry,
helps ensure project success.
EDUCAT ION & TRAINING
Milwaukee School of Engineering
Bachelor of Science in Construction Management
Project Manager of the Year, 2025, Daily Reporter
office: 262-922-1609 • email: kathryn@moore-cs.com • moore-cs.com
Page 119 of 169
12.
NOTABLE PROJECTS
COM MER C I AL PROJECTS
Amazon DML6
Chicago Tube & Iron
Copart, Inc.
Create-A-Pack
Entrust
Five Star Fabricating
Gray & Associates Law Offices
Harken
Ingeteam
Kapco
Lake Geneva Yacht Club
Landmark Credit Union
Metal Era
River Glen
Rogers Behavioral Health
Rosendale Biodigester (BD2)
Sendik’s Grocery Stores
Standard Electric Supply
Tesla, Inc.
INSTITUTIONAL PROJECTS
St. Anthony on the Lake
Trek
University of Wisconsin Oshkosh
Catholic Memorial High School -
Sullivan Campus
JASON BIVER
SENIOR PROJECT SUPERINTENDENT
EXPERIENCE
Jason's expertise in construction and facilities management encompasses
more th
an thirty years of supervising building projects of all sizes and types
throughout Southeastern Wisconsin. Currently, Jason’s focus is on
commercial and industrial projects that are complex and have many
stakeholders.
On the jobsite, Jason is successful at problem solving and running an
efficient program to achieve client objectives. He manages daily on-site
operations and oversees subcontractor work, monitoring all construction-
related tasks so they are accomplished safely, within the approved
schedule and in a high-quality manner that is representative of Moore
Construction Services. Jason is an aggressive project advocate, a self-
starting leader with high standards and has the expertise needed to turn
challenges in to positive results.
EDUCAT ION & TRAINING
OSHA 10 Hour
Certification, 2009
Uniform Dwelling Code Training, 2006
Managing Exterior Moisture Course, 2005
Rough Terrain Telescopic (Fork Lift) Certification (OSHA 1926.602), 2000 &
2011
Basic Supervision Course, 1999
Completed Course of Facilities Management, 1998
Completed C.P .O Course, Cert.#85-54750, 1996
office: 262-345-1280 • email: jason@moore-cs.com • moore-cs.com
Page 120 of 169
13.
NOTABLE PROJECTS
COMMERCIAL PROJECTS
Amazon
Tesla, Inc.
Five Star Fabricating
Germantown DPW
Glenroy
Burgardt Sporting Goods
New Berlin ARC
MUL T I -FAMIL Y / S ENI OR LI V ING
Orchard Hills
White Oaks
The Granary
Arrabelle
SoNa Lofts
I N S T I T U T I O N A L
Catholic Memorial High School
Fox Point Lutheran Church
Holy Apostles
St. Joan Antida
St. Mary of the Hill
LEE DUHS
ASSISTANT PROJECT SUPERINTENDENT
EXPERIENCE
As an Assistant Project Engineer, Lee supports our project
superintendents by managing trade coordination, overseeing
punch lists, and maintaining the electronic documentation
required for each project.
His experience in the industry has given him the tools to succeed on the
jobsite as a passionate team player with a proactive approach.
EDUCAT ION & TRAINING
University of Wisconsin Parkside
Bachelor of Science, Sports Management
OSHA 10 Hour Certification
office: 262-345-1280 • email: lee@moore-cs.com • moore-cs.com
Page 121 of 169
14.
PROJECT APPROACH
UTILITY EXTENSION:
Our approach to utility extensions focuses
on early identification, coordination,
and seamless integration with existing
infrastructure.
Collaborate with the civil engineer, utility providers, and design
team early in the design phase to confirm routing, capacity, and
connection requirements
Identify potential conflicts or constraints and develop solutions
proactively to avoid delays during construction
Incorporate utility work into the overall project schedule and
phasing plan to maintain continuity of service where required
Create a separate bid package for utility work to support clear
scope definition and coordination with trade partners
Coordinate closely with subcontractors and local authorities
to ensure compliance with all permitting and inspection
requirements
Monitor installation activities in the field to confirm alignment
with design intent and regulatory standards
Coordinate daily with subcontractors through on-site supervision
to align field activities with project goals
Moore Construction Services was part of a team, along with Graef and PRA, to assess the Village’s Public
Safety Building options. As part of this effort, we toured the existing facilities, interviewed key staff
members, and developed design concepts and budgets for both co-site and separate site locations,
ultimately producing a final report that was presented to the Village Board.
This experience has provided Moore Construction Services with in-depth knowledge of the project
approach. In addition, we recognize that this project involves specialized components—such as utility
extensions and a live-fire training range—that require thoughtful integration with the overall facility,
site, and operations. Our team approaches these elements with an emphasis on early coordination, safety,
regulatory compliance, and long-term functionality. We work closely with the Village, design team, and
stakeholders to ensure all systems are aligned, constructible, and executed with minimal disruption.
Page 122 of 169
15.
PROJECT APPROACH
LIVE-FIRE RANGE
INTEGRATION:
Our approach to the live-fire range
integration focuses on early coordination,
clear delineation of responsibilities, and
ensuring all specialized systems are fully
aligned with building infrastructure. Given
the complexity of range systems and the
likelihood of multiple contractors, we
prioritize proactive collaboration and
dedicated oversight to support proper
installation, performance, and final
commissioning.
A key part of the live-fire range integration is coordinating
with the building’s HVAC systems. Because this project will go
through a public bidding process, there’s a good chance the
range contractor and HVAC contractor will be different teams.
T o ensure both systems tie together properly, we would
recommend a budget line item for a third-party specialist to
assist with overseeing the installation and providing the final
commissioning of the systems
Partner with the design team and specialty consultants
to fully understand performance, safety, and acoustic
requirements
Coordinate structural, mechanical, and ventilation systems to
support proper operation and safety standards
Ensure all materials, assemblies, and systems meet applicable
codes, certifications, and operational requirements
Integrate range construction into the overall sequencing and
phasing plan to maintain safety and quality control
Maintain strict adherence to safety protocols during
construction, recognizing the specialized nature of this
environment
Page 123 of 169
16.
COST PROPOSAL:
General Conditions
Phase Codes Superintendent #1 Superintendent 2 Laborer Superintendent 3
14 MONTHS 8 MONTHS 8 MONTHS 0 MONTHS
60.76 WEEKS 34.72 WEEKS 34.72 WEEKS 0 WEEKS
303.8 WORKING DAYS 173.6 WORKING DAYS 173.6 WORKING DAYS 0 WORKING DAYS
COST LABOR LABOR MATERIAL MATERIAL
CODE DESCRIPTION HR/DY HR/WK QTY UNIT UNIT PRICE TOTAL UNIT PRICE TOTAL TOTAL
01040 Superintendent #1 8 2430.40 HR $125.00 $303,800 $0.00 $0 $303,800
01040 Superintendent #2 8 1388.80 HR $125.00 $173,600 $0.00 $0 $173,600
01042 Safety Inspections 0 24.00 ALLOW $0.00 $0 $250.00 $6,000 $6,000
01046 Project Manager 4 1215.20 HR $130.00 $157,976 $0.00 $0 $157,976
01047 Assistant Project Manager 0.5 152.00 HR $55.00 $8,360 $0.00 $0 $8,360
01048 General Laborer 8 1388.80 HR $55.00 $76,384 $0.00 $0 $76,384
01050 Professional Surveying 1.00 ALLOW $0.00 $0 $35,000.00 $35,000 $35,000
01410 Testing Services 1.00 ALLOW $0.00 $0 $0.00 $0 By Owner
01511 Temp. Electricity 12.00 Months $0.00 $0 $2,500.00 $30,000 $30,000
01513 Temp. Heating 5.00 Units $0.00 $0 $2,000.00 $10,000 $10,000
Temp Heat Equip 5.00 EA $2,000.00 $10,000 $10,000
Temp Dehumid Eq 0.00 EA $500.00 $0 NA
01515 Temp. Water 12.00 WE $0.00 $0 $100.00 $1,200 $1,200
01516 Temp. Toilets 56.00 EA $0.00 $0 $110.00 $6,160 $6,160
01528 Temp Roads By Earthwork 0.00 LS $0.00 $0 $0.00 $0 By Trade Pkg
01535 Construction Fencing 0.00 LF $0.00 $0 $8.00 $0 By Trade Pkg
01560 Dumpsters 28.00 EA $0.00 $0 $550.00 $15,400 $15,400
01565 Snow Removal 1.00 ALLOW $0.00 $0 $10,000.00 $10,000 $10,000
01580 Project Signs 0.00 ALLOW $0 $0.00 $0 By Owner
01590 Field Office 14.00 MO $0.00 $0 $1,100.00 $15,400 $15,400
01600 Small Tools/Office Supplies 14.00 ALLOW $0.00 $0 $2,000.00 $28,000 $28,000
Temp Enclosures 1.00 LS $0.00 $0 By Trades
Technology 14.00 mnths $3,500.00 $49,000 $49,000
01602 Equipment Rental Lift & Connex 14.00 Mnth $0.00 $0 $3,500.00 $49,000 $49,000
01710 Final Cleaning 0 SF $0.00 $0 $0.65 $0 By Trade Pkg
Floor Protection 0 SF $0.20 $0 By Trade Pkg
TOTAL : $720,120 $265,160 $985,280
Pre-Construction Services Lump Sum Fee: $7,500
Construction Management Fee: 2.25%
Page 124 of 169
17.
COST MANAGEMENT
BIDDING AND
PROCUREMENT
METHODOLOGY:
Moore Construction Services utilizes
a structured, transparent bidding and
procurement process that emphasizes early
trade partner engagement, competitive
pricing, and alignment with project goals
ensuring we meet Wisconsin state statutes
for public bidding.
GMP DEVELOPMENT
APPROACH:
Our Guaranteed Maximum Price (GMP)
development process is collaborative,
transparent, and rooted in real-time cost
awareness. We work closely with the Village
and design team to develop a GMP at 60%
to 90% CDs that reflects a complete, well-
understood scope aligned with project
objectives.
Develop comprehensive bid packages that clearly define
scope, expectations, and project requirements
Prequalify subcontractors to ensure experienced, capable
trade partners aligned with project needs
Solicit competitive bids across all trades to achieve best value
while maintaining quality standards
Conduct thorough bid leveling and scope comparisons to
ensure consistency and completeness
Facilitate bid review meetings with the project team to
evaluate pricing, scope coverage, and qualifications
Identify opportunities for scope refinement or value
optimization prior to award
Coordinate subcontractor onboarding, including contract
execution, schedule alignment, and safety requirements
Maintain clear and consistent communication with all bidders
throughout the procurement process to ensure transparency
and accountability
Provide ongoing cost input throughout design to track budget
alignment as decisions are made
Develop detailed estimates at key design milestones,
incorporating subcontractor and supplier input for accuracy
Reconcile estimates with the design team to ensure
alignment between scope, budget, and project expectations
Clearly identify allowances, contingencies, and potential cost
risks within the GMP
Communicate the cost impacts of design changes in real
time and recommend alternatives when appropriate
Engage trade partners early to validate pricing, identify
efficiencies, and confirm constructability
Present a fully detailed GMP that is transparent,
comprehensive, and supported by market-based pricing
Continue to actively manage costs throughout construction
to maintain alignment with the GMP
Our approach to cost management and procurement emphasizes transparency, early collaboration, and disciplined planning. We
work closely with the Village, design team, and trade partners to ensure pricing aligns with project goals and supports informed
decision-making throughout the process.
Page 125 of 169
ID Task
Mode
Task Name Duration Start Finish
1 CMAR Selection 1 day Mon 7/6/26 Mon 7/6/26
2 Preconstruction Services 180 days Tue 7/7/26 Mon 3/15/27
3 Utility Extension Design 40 days Tue 1/19/27 Mon 3/15/27
4 Utilitiy Extension Bidding & Construction 120 days Tue 3/16/27 Mon 8/30/27
5 Mobilize & Erosion Control 5 days Tue 3/16/27 Mon 3/22/27
6 Site Cut & Fills 5 days Tue 3/23/27 Mon 3/29/27
7 Pond Construction 10 days Tue 3/30/27 Mon 4/12/27
8 Storm Drainage 10 days Fri 4/9/27 Thu 4/22/27
9 Excavate Building Lower Level 6 days Tue 3/30/27 Tue 4/6/27
10 Lower Level Foundations 20 days Tue 4/6/27 Mon 5/3/27
11 Stair & Elevator Masonry Shafts 15 days Thu 4/29/27 Wed 5/19/27
12 Parking Level Precast 12 days Thu 5/20/27 Fri 6/4/27
13 Waterproofing Lower Half 5 days Tue 5/4/27 Mon 5/10/27
14 Partial Backfill 2 days Mon 5/10/27 Tue 5/11/27
15 Balance Waterproofing 5 days Tue 5/11/27 Mon 5/17/27
16 Balance Backfill 3 days Mon 5/17/27 Wed 5/19/27
17 Precast Waterproofing 5 days Mon 6/7/27 Fri 6/11/27
18 Precast Topping 6 days Mon 6/14/27 Mon 6/21/27
19 First Floor Steel Framing 25 days Tue 6/22/27 Mon 7/26/27
20 Lower Level Underfloor MEP 7 days Mon 6/7/27 Tue 6/15/27
21 Lower Level Masonry Partitions 20 days Wed 6/16/27 Tue 7/13/27
22 Lower Level SOG 10 days Wed 7/14/27 Tue 7/27/27
23 Level One Exterior Wall Framing 25 days Tue 7/27/27 Mon 8/30/27
24 Soffit Framing 15 days Tue 8/31/27 Mon 9/20/27
25 Roof Blocking & Window Blocking 15 days Tue 8/24/27 Mon 9/13/27
26 Roof Tops Curbs 5 days Fri 9/3/27 Thu 9/9/27
27 Roofing 12 days Tue 9/14/27 Wed 9/29/27
28 Metal Pan Stairs 15 days Wed 7/28/27 Tue 8/17/27
29 Air Barrier 10 days Tue 9/7/27 Mon 9/20/27
30 Brick Veneer 25 days Thu 9/16/27 Wed 10/20/27
31 Metal Composite Siding 20 days Mon 10/18/27 Fri 11/12/27
32 Windows and Storefronts 20 days Thu 10/21/27 Wed 11/17/27
33 Overhead Doors 10 days Thu 10/21/27 Wed 11/3/27
CMAR Selection
Preconstruction Services
Utility Extension Design
Utilitiy Extension Bidding & Construction
Mobilize & Erosion Control
Site Cut & Fills
Pond Construction
Storm Drainage
Excavate Building Lower Level
Lower Level Foundations
Stair & Elevator Masonry Shafts
Parking Level Precast
Waterproofing Lower Half
Partial Backfill
Balance Waterproofing
Balance Backfill
Precast Waterproofing
Precast Topping
First Floor Steel Framing
Lower Level Underfloor MEP
Lower Level Masonry Partitions
Lower Level SOG
Level One Exterior Wall Framing
Soffit Framing
Roof Blocking & Window Blocking
Roof Tops Curbs
Roofing
Metal Pan Stairs
Air Barrier
Brick Veneer
Metal Composite Siding
Windows and Storefronts
Overhead Doors
25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 4 9 14 19 24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 4 9 14 19 24 29 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13
May June July August September October November December January February March April May June July August September October November December January February March April May June
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Village of Germantown
Police Department
Tue 5/19/26 Moore Construction Services
Project: GermantownPD.mpp
Date: Tue 5/19/26
Page 126 of 169
ID Task
Mode
Task Name Duration Start Finish
34 Lower Level Overhead MEP 15 days Thu 9/30/27 Wed 10/20/27
35 First Floor Overhead MEP 25 days Wed 10/13/27 Tue 11/16/27
36 Lower Level Partitions 15 days Thu 10/21/27 Wed 11/10/27
37 First Floor Partitions Framing 20 days Wed 11/17/27 Tue 12/14/27
38 In-Wall MEP Rough-in First Floor 20 days Wed 12/1/27 Tue 12/28/27
39 Drywall 25 days Wed 12/22/27 Tue 1/25/28
40 Elevator 10 days Wed 1/26/28 Tue 2/8/28
41 First Coat Paint Lower Level 5 days Thu 11/11/27 Wed 11/17/27
42 First Coat Paint First Floor 8 days Wed 1/26/28 Fri 2/4/28
43 Ceiling Grid 12 days Mon 2/7/28 Tue 2/22/28
44 Hard Tile floors 12 days Wed 2/23/28 Thu 3/9/28
45 Epoxy Floors 10 days Wed 2/23/28 Tue 3/7/28
46 Millwork First Floor 15 days Wed 2/23/28 Tue 3/14/28
47 First Floor Flooring 15 days Wed 3/15/28 Tue 4/4/28
48 Doors & Hardware 15 days Wed 3/15/28 Tue 4/4/28
49 Overhead MEP finishes 15 days Wed 2/23/28 Tue 3/14/28
50 Ceiling Tile 12 days Wed 3/15/28 Thu 3/30/28
51 MEP Finishes 12 days Mon 2/7/28 Tue 2/22/28
52 Misc Accessories 10 days Wed 2/23/28 Tue 3/7/28
53 Final Coat Paint Lower Level 7 days Wed 3/15/28 Thu 3/23/28
54 Final Coat Paint First Floor 8 days Wed 4/5/28 Fri 4/14/28
55 Prepunch 12 days Mon 4/17/28 Tue 5/2/28
56 Punchlist 12 days Wed 5/3/28 Thu 5/18/28
57 Occupancy 7 days Fri 5/19/28 Mon 5/29/28
58 Site Improvements
59 Site Utilities 20 days Fri 4/23/27 Thu 5/20/27
60 Site Concrete 15 days Tue 10/19/27 Mon 11/8/27
61 Site Paving 5 days Tue 11/9/27 Mon 11/15/27
62 Landscaping 15 days Mon 5/1/28 Fri 5/19/28
Lower Level Overhead MEP
First Floor Overhead MEP
Lower Level Partitions
First Floor Partitions Framing
In-Wall MEP Rough-in First Floor
Drywall
Elevator
First Coat Paint Lower Level
First Coat Paint First Floor
Ceiling Grid
Hard Tile floors
Epoxy Floors
Millwork First Floor
First Floor Flooring
Doors & Hardware
Overhead MEP finishes
Ceiling Tile
MEP Finishes
Misc Accessories
Final Coat Paint Lower Level
Final Coat Paint First Floor
Prepunch
Punchlist
Occupancy
Site Utilities
Site Concrete
Site Paving
Landscaping
25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 4 9 14 19 24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 4 9 14 19 24 29 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13
May June July August September October November December January February March April May June July August September October November December January February March April May June
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Village of Germantown
Police Department
Tue 5/19/26 Moore Construction Services
Project: GermantownPD.mpp
Date: Tue 5/19/26
Page 127 of 169
20.
May 18 th, 2026
Phil Lazarski
Bond Manager
2100 Stewart Ave
Suite 235
Wausau, WI 54401
(715) 688-9888
Contractor: Moore Construction Services, LLC
Project: Village of Germantown Police Department Facility
N122W17177 Fond du Lac Avenue
Germantown, WI 53022
To Whom It May Concern:
Moore Construction Services, LLC is a highly valued customer of Liberty Mutual Insurance Company.
We consider Moore Construction Services, LLC to be a financially sound and well-managed company
Liberty Mutual Insurance Company is willing to extend surety credit to Moore Construction Services, LLC
in the amount of $75,000,000 for single projects with an aggregate bonding limit of $150,000,000.
Liberty Mutual Insurance Company reserves the right to perform normal underwriting at the time of any
request including, but not limited to, a review of contract documents and bond forms, confirmation of
project financing, and a review of any other pertinent underwriting documents.
This letter is not an assumption of liability nor is it a bond. Any arrangement for bonds is a matter
between Moore Construction Services, LLC and Liberty Mutual Insurance Company. We assume no
liability to you or to third parties if for any reason we do not supply said bond or bonds.
Liberty Mutual Insurance Company is listed on the U.S. Department of the Treasury’s Listing of
Approved Sureties (Department Circular 570). Liberty Mutual Insurance Company is licensed to transact
business in all states and many international jurisdictions and has a rating of “A” and a financial size
category of “XV” in the A.M. Best’s Insurance Guide.
Sincerely,
Phil Lazarski AFSB
Liberty Mutual Surety
PROOF OF INSURANCE AND BOND ABILITY
Page 128 of 169
Page 129 of 169
Page 130 of 169
Page 131 of 169
Page 132 of 169
Page 133 of 169
Page 134 of 169
Page 135 of 169
Page 136 of 169
Page 137 of 169
Page 138 of 169
Page 139 of 169
Page 140 of 169
Page 141 of 169
Page 142 of 169
Page 143 of 169
Page 144 of 169
Page 145 of 169
Page 146 of 169
Page 147 of 169
Page 148 of 169
Page 149 of 169
Page 150 of 169
Page 151 of 169
Page 152 of 169
Page 153 of 169
Page 154 of 169
Page 155 of 169
Page 156 of 169
Page 157 of 169
Page 158 of 169
Page 159 of 169
Page 160 of 169
Page 161 of 169
Page 162 of 169
Page 163 of 169
Page 164 of 169
Page 165 of 169
Page 166 of 169
Page 167 of 169
BUSINESS OF THE BUILDING CONSTRUCTION OVERSIGHT COMMITTEE
MEETING DATE: June 11, 2026
PLACEMENT: Action Item
ITEM TITLE: Committee's Process and Procedures for Exercising its Powers
and Duties with Respect to Police and Fire Department
Construction Projects. (ACTION)
SUBMITTED BY: Brian Sajdak, Attorney
SUMMARY EXPLANATION:
With two Village construction projects forthcoming for the Police and Fire Departments,
the Committee should establish its rules, procedures and processes for exercising its
powers and duties with respect to these projects.
Under the Municipal Code, the Committee has the following powers and duties:
1.37(3) POWERS AND DUTIES. The Committee shall play a consultative and
oversight role with respect to any project to build or expansively reconstruct or
remodel a Village building, and shall report directly to the Village Board. In such
capacity it shall:
(a) Consult with the Village and/or any village agency or department which may
have need of construction or remodeling of building facilities in order to assess
need, formulate preliminary project definition and parameters, coordinate
conceptualization of the project, and assist the Village, agency or department in
presenting an overview and making recommendations to the Village Board.
(b) Participate in the project development and planning, including interfacing with
staff and consultants and overseeing engineering, design, and creation of detailed
plans and specifications, and cost assessment and development of financing
options, in order to formulate detailed final recommendations to the Village Board.
(c) Utilize the assistance of Staff, such as the Finance Director, Planner, or Village
Attorney, as may be required.
Given the somewhat broad language used, the Committee should consider and
establish its process and procedures for exercising this authority. Such processes and
procedures may include:
• What matters and decisions on which the Committee believes it should be
considering and making recommendations/reports to the Board.
Page 168 of 169
• Does the Committee want to set a standing meeting interval, or simply be
available at the call of the Chair as matters necessitate. This might change
during the project. For example, at the outset, there may be a need for regular
meetings which eventually give way to meetings which are more space apart or
are not set in stone.
ATTACHMENT:
STAFF RECOMMENDATION:
ACTION BY COMMITTEE:
Page 169 of 169