MEETING: REGULAR MEETING OF THE PUBLIC WORKS &
HIGHWAYS COMMITTEE
DATE & TIME: Wednesday, June 3, 2026 at 5:30 PM
LOCATION: Germantown Village Hall Board Room
N112 W17001 Mequon Road
Any member of the body and/or citizen may attend the meeting virtually through the WebEx platform, Meeting #: 2555 672 0428 Password:
ZNmFyjsD343 which can be accessed by phone at 408-418-9388 or by logging on
at: https://villageofgermantown.my.webex.com/villageofgermantown.my/j.php?MTID=mc28ed9f85300bb8f63267a15d2f40b55
Citizens not wishing to attend the meeting personally or virtually may submit any public comments by sending an email
to comments@germantownwi.gov by 4 p.m. on the day of the meeting so that it can be provided to the members of the body for their
consideration. Previously recorded Village Board Meeting Videos can be viewed at
https://www.youtube.com/channel/UCOYp0EgELzTCa9X_iCohyhQ.
AGENDA
I. CALL TO ORDER: This meeting has been given public notice in accordance with
Section 19.83 and 19.84, Wis. Stats, in such form that will apprise the general public
and news media of subject matter that is intended for consideration and action.
II. ROLL CALL:
III. MEETING MINUTES:
A. May 13, 2026 (ACTION)
IV. PUBLIC COMMENT: Please be advised per State Statute Section 19.84(2),
information will be received from the public. It is the policy of this municipality that
there be a four-minute time period, per person, with time extensions per the Chief
Presiding Officer’s discretion; be further advised that there may be limited discussion
on the information received, however, NO ACTION will be taken under public
comments. Comments that may be injurious to village personnel or other individuals
will not be allowed.
V. UNFINISHED BUSINESS:
A. April Storm Update (DISCUSSION)
VI. NEW BUSINESS:
A. Dombrock Relocation Order/Appraisal Rebuttal. (ACTION)
B. Award of a contract to Fahrner Asphalt Sealers for the 2026 Road Program not
to exceed the budgeted amount of $250,000.00. (ACTION)
C. Award of contract to Payne & Dolan for the Division Road Phase 1
improvements in a total amount, including a 10% contingency, not to exceed
$2,341,449.10. (ACTION)
D. Professional services agreement with RA Smith for Division Road Phase 1
inspection in an amount, including 10% contingency, not to exceed
$184,800.00. (ACTION)
VII. DIRECTOR'S REPORT:
A. June Director's Report
Page 1 of 31
PUBLIC WORKS & HIGHWAYS COMMITTEE AGENDA
June 3, 2026
Page 2
VIII. NEXT MEETING DATE:
IX. ANNOUNCEMENTS:
X. ADJOURNMENT:
UPON REASONABLE NOTICE, efforts will be made to accommodate the needs of disabled individuals through
appropriate aids and services. For additional information or to request this service, please contact the Village
Clerk at (262)250-4745 at least 2 days prior to the meeting.
Notice is hereby given that a possible quorum of other boards, committees, and/or commissions may attend this
meeting to gather information about an item over which they have decision-making responsibility. This may
constitute a meeting of these bodies per State ex rel. Badke v Greendale Village Board, even though these
bodies will not take formal action at this meeting.
Page 2 of 31
AMENDED REGULAR MEETING OF THE PUBLIC
WORKS & HIGHWAYS COMMITTEE
Wednesday, May 13,2026 5:30 PM
Germantown Vi!lage Hall Board Room
N112 W17001 Mequon Road
MEETING:
DATE AND TIME:
LOCATION:
Chairperson Trustee Terri Kaminski called the Public Works and Highways Committee
meeting to order at 5:30PM.
Present: Trustee Terri Kaminski, Trustee Robert Warren, Trustee Jan Miller, Trustee
Jim Stout
Also Present: DPW Director Tim Zimmerman, Water Superintendent Paul Haugen,
Village Engineer Kevin Driscoll, Deputy Clerk Maddy Laufenberg
III. MEETING MINUTES:
A. April 1,2026 (ACTION)
Motion: Approve as presented
Motioned By: Robert Warren
Seconded By: Jan Miller
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
Melanie Smythe (N140W17938 Cedar Ln) spoke regarding presentation procedures
and yard waste permits.
UNFINISHED BUSINESS:
NEW BUSINESS:
Consideration of Well 7 liner installation and contract extension #1 with CTW in
the amount of $'136,555.00. (ACTION)
v.
VI
MINUTES
I. CALL TO ORDER:
II. ROLL CALL:
IV. PUBLIC COMMENT:
Page 3 of 31
Page 2
B
Water Superintendent Haugen provided information on this item.
Motion: Approve as presented
Motioned By: Robert Warren
Seconded By: Jan Miller
Yes: Terri Kaminski, Robert Warren, Jan Miller. Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
Award of professional services agreement to Foth in the amount of $34,000.00
for Well 7 liner installation and pump replacement professional services.
(ACTTON)
Water Superintendent Haugen and a representative from Foth provided information on
this item.
Motion: Approve as presented
Motioned By: Jan Miller
Seconded By: Robert Warren
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
C. April Storm Update (DISCUSSION)
DPW Director Zimmerman and Village Engineer Driscoll gave an update on the April
storm.
Public comments were made by the following individuals:
. Steven Mohar (N 1 06W17050 Juniper Dr) spoke regarding drainage easements
. Amy Willard (N106W17355 Wildflower Ln) spoke regarding flooding on
Wildflower Lane.
r B. N. Ranganathan (N'106W17159 Juniper Dr) spoke regarding flooding on
Juniper Drive.
. Tom Willard (N 1 06W17355 Wildflower Ln) spoke regarding flooding on
Wildflower Lane.
. Paul Spitz (N106W17085 Juniper Drive) spoke regarding sewer backups.
. Randy Ryskoski (N106W171'13 Juniper Dr) spoke regarding sewer backups.
. Jeff Perschke (W173N10727 Willow Wood Dr) spoke regarding the Old Farm
Rd pump station.
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Page 4 of 31
Page 3
. Melanie Smythe (N140W17938 Cedar Ln) spoke regarding a hydraulic/storm
study and communications.
Motion: Examine Cedar Hills and Willow Wood subdivision drainage ditches and
determine which ones are private and public
Motioned By: Terri Kaminski
Seconded By: Jan Miller
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
D. Acceptance of Well #7 Rehab (ACTION)
Motion: Combine ltems D-J for consideration as presented
Motioned By: Robert Warren
Seconded By: Terri Kaminski
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
Motion: Approve ltems D-J as presented
Motioned By: Robert Warren
Seconded By: Jan Miller
Yes: Terri Kaminski. Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
E. Acceptance of Well 7 Generator Replacement (ACTION)
Acceptance of Well #12 (ACTION)
Acceptance of Goldendale Booster Station (ACTION)
Acceptance of Tower #3 Painting and Rehab (ACTION)
F.
G.
H.
l. Acceptance of Tower #1 Emergency Replacement of Water Fill Pipe (ACTION)
Page 5 of 31
Page 4
J. Acceptance of Tower #4 (ACTION)
K. Consideration of a credit policy for utility billing. (ACTION)
Water Superintendent Haugen provided information on this item
Motion: Approve as presented
Motioned By: Robert Warren
Seconded By: Teni Kaminski
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
Appraisal Payments for Division Road Phase I Road Reconstruction Project
(ACTTON)
Village Engineer Driscoll provided information on this item.
Motion: Approve as presented
Motioned By: Robert Warren
Seconded By: Jan Miller
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
Dtvision Road Relocation Order Resolution (ACTION) (Amended to include
Exhibit C. Resolution)
Village Engineer Driscoll provided information on this item.
Motion: Approve as presented
Motioned By: Robert Warren
Seconded By: Jan Miller
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
M
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
L.
Page 6 of 31
Page 5
N. Pleasant View Drive Relocation Order Resolution (ACTION)
Village Engineer Driscoll provided information on this item
Motion: Approve as presented
Motioned By: Jan Miller
Seconded By: Jim Stout
Yes: Terri Kaminski. Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
O. Award Contract for Road Program - Heritage Hills Reconstruction (ACTION)
Motion: Recommend approval of the contract to Stark Pavement Corp. as presented
Motioned By: Jan Miller
Seconded By: Jim Stout
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
P. Award Road Program Contract - Esquire Estates Reconstruction (ACTION)
Village Engineer Driscoll provided information on this item.
Motion: Recommend approval of the contract to Payne & Dolan with a 10%
contingency as presented
Motioned By: Robert Warren
Seconded By: Jan Miller
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motaon Garried by Voice Vote (Yes 4, No 0, Abstained 0)
O. Award Conract for Engineering Services - Site Plan Reviews (ACTION)
Village Engineer Driscoll provided information on this item.
Village Engineer Driscoll provided information on this item.
Page 7 of 31
Page 6
Motion: Award contract to Haruood Engineering Consultants, not to exceed $15,000
as presented
Motioned By: Jan Miller
Seconded By: Terri Kaminski
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
R. Maple Road Bridge Repair (ACTION)
Village Engineer Driscoll provided information on this item.
Motion: Approve Option A as presented
Motaoned By: Jan Miller
Seconded By: Terri Kaminski
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Acceptance of lmprovements - Water Main Extension for Green Bay Packaging
at Holy Hill Road (ACTION)
Village Engineer Driscoll provided information on this item
Motion: Approve as presented
Motioned By: Robert Warren
Seconded By: Jim Stout
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
T. Award Contract for Pioneer Road Survey (ACTION)
Village Engineer Driscoll passed around an updated contract for review
Motion: Approve updated contract in the amount of $677.50 as presented
Motioned By: Jan Miller
Seconded By: Robert Warren
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
S.
Page 8 of 31
Page 7
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
U. Agreement with WisDOT for STH '145 lmprovements (ACTION)
Village Engineer Driscoll provided information on this item.
Motion: Enter into an agreement with WisDOT for STH 145 improvements as
presented
Motioned By: Robert Warren
Seconded By: Jan Miller
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
Discussion on Main Street and Old Farm Lift Station Facilities Plan
Amendment. (DISCUSSION)
W. Autorization to Purchase - Emergency Bypass Pump (ACTION)
DPW Director Zimmerman provided information on this item.
Motion: Approve purchase of an emergency bypass pump from Thompson {ump, not
to exceed $58,300 as presented
Motioned By: Jan Miller
Seconded By: Robert Warren
Yes: Terri Kaminski, Robert Warren, Jan Miller, Jim Stout
No: None
Abstain: None
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
X. Consideration of Cost Recovery - Yard Waste Permit (ACTION)
DPW Director Zimmerman provided information on this item.
Motion: Limit the number of permits issued to two per household as presented
Motion Carried by Voice Vote (Yes 4, No 0, Abstained 0)
DPW Director Zimmerman led discussion on this item.
Page 9 of 31
Page I
Motioned By: Robert Warren
Seconded By: Terri Kaminski
Yes: Terri Kaminski, Robert Warren, Jim Stout
No: Jan Miller
Abstain: None
Motion Carried by Voice Vote (Yes 3, No '1, Abstained 0)
VII. DIRECTOR'SREPORT:
A. May Directors Report
DPW Director Zimmerman spoke regarding Village Engineer Driscoll's last day and
upcoming culvert replacements.
VIII. NEXT MEETING DATE:
The next Public Works and Highways Committee Meeting will be held on June 3.2026
at 5:30PM.
IX. ANNOUNCEMENTS:
Trustee Miller announced the upcoming Maifest event on May 1 5th - 17th.
X. ADJOURNMENT:
Chairperson Trustee Kaminski adjourned the Public Works & Highways Committee
meeting at 8:36 PM.
Page 10 of 31
BUSINESS OF THE PUBLIC WORKS & HIGHWAYS COMMITTEE
MEETING DATE: June 3, 2026
PLACEMENT: Presentation
ITEM TITLE: April Storm Update (DISCUSSION)
SUBMITTED BY: Timothy Zimmerman, Public Works Director
SUMMARY EXPLANATION:
ATTACHMENT:
STAFF RECOMMENDATION:
ACTION BY COMMITTEE:
Page 11 of 31
BUSINESS OF THE PUBLIC WORKS & HIGHWAYS COMMITTEE
MEETING DATE: June 3, 2026
PLACEMENT: Action Item
ITEM TITLE: Dombrock Relocation Order/Appraisal Rebuttal
SUBMITTED BY: Tim Zimmerman – Director of Public Works
SUMMARY EXPLANATION:
The Division Road Phase 1 project required relocation orders and appraisals on four
properties to accommodate an extension of sidewalk which also required some
additional pipe work. Staff met with concerned residents Mary Dombrock and Tom
Truse who both expressed an unwillingness to execute the relocation orders and
appraisals unless the Village would absolve them of any maintenance responsibility of
the new sidewalk. Per the updated sidewalk ordinance, they would become responsible
for the winter maintenance of the sidewalk.
ATTACHMENT: ORDINANCE RESOLUTION OTHER___X____
RECOMMENDATION:
Staff recommends stopping the sidewalk at Ava Circle and install a crosswalk at that
location to direct pedestrian traffic back to the east side of Division Road. The crosswalk
was originally proposed at Lilac Ln. The redirection eliminates the concerns of the
Dombrock’s and the Truse’s and will only require a quantity reduction in the bid tab
which will reflect a savings for the overall project in the amount of approximately
$75,120.00. It would further eliminate the need for TLE’s on both properties and also
negate the Dombrock tree compensation.
COMMITTEE ACTION:
Proper parliamentary procedure to deny a request is to have a motion made in the
affirmative and by voting NAY would deny the request if a majority vote.
Page 12 of 31
Page 13 of 31
Village of Germantown GIS
Division Rd Alternate Sidewalk Crossing Options
Village Of Germantown
N112 W17001 Mequon Road
Germantown, WI 53022
262-250-4700
724.96
DISCLAIMER:
This map is not a survey of the actual boundary of any property this map
depicts.
The Village of Germantown Does not guarantee the accuracy of the material contained
here in and is not responsible for any misuse or misrepresentation of this information
or its derivatives. Print Date: 5/29/2026
SCALE: 1 = 60'
Page 14 of 31
BUSINESS OF THE PUBLIC WORKS & HIGHWAYS COMMITTEE
MEETING DATE: June 3, 2026
PLACEMENT: Action Item
ITEM TITLE: Award of Contract – Seal Coat Program
SUBMITTED BY: Tim Zimmerman – Director of Public Works
SUMMARY EXPLANATION:
The 2026 Road Program includes money for the seal coat program. The program will be
administered by the Engineering Dept. on various roads throughout the Village.
Program includes multiple types of coatings depending on road type and age of
pavement. Fahrer Asphalt Sealers were our only bidder at $223,469.50
ATTACHMENT: ORDINANCE RESOLUTION OTHER___X____
RECOMMENDATION:
Staff requests the PWHC recommend to the Village Board approval of a contract with
Fahrner Asphalt Sealers For the amount not to exceed the budgeted amount of
$250,000.00. The bid came in under the engineer’s estimate of $249,975.00. Additional
roads will be added at the bid unit price up to an additional $26,530.50. Funded in 40-
561000-5316400.
COMMITTEE ACTION:
Proper parliamentary procedure to deny a request is to have a motion made in the
affirmative and by voting NAY would deny the request if a majority vote.
Page 15 of 31
2026 Sealcoating Project (#10195391)
Owner: Germantown, Village of
Solicitor: Germantown, Village of
05/28/2026 10:00 AM CDT
Engineer Estimate Fahrner Asphalt Sealers, LLC
Section Tit Line Item Item Code Item Descr UofM Quantity Unit Price Extension Unit Price Extension
GSB-88 $24,030.00 $22,107.60
1 1 CONCORD SY 11030 $1.50 $16,545.00 $1.38 $15,221.40
2 1 EDGEWOO SY 4990 $1.50 $7,485.00 $1.38 $6,886.20
FLEX PATCHING $57,275.00 $47,400.00
3 2 MAPLE RO LF 1430 $7.25 $10,367.50 $6.00 $8,580.00
4 2 HIGHLAND LF 170 $7.25 $1,232.50 $6.00 $1,020.00
5 2 PRESERV LF 1100 $7.25 $7,975.00 $6.00 $6,600.00
6 2 HILLTOP RLF 1200 $7.25 $8,700.00 $6.00 $7,200.00
7 2 FREISTAD LF 4000 $7.25 $29,000.00 $6.00 $24,000.00
MICRO SURFACING $25,480.00 $32,250.40
8 3 PRESERV SY 7280 $3.50 $25,480.00 $4.43 $32,250.40
CHIP SEALING $143,190.00 $121,711.50
9 4 MAPLE RO SY 25870 $3.00 $77,610.00 $2.55 $65,968.50
10 4 HIGHLAND SY 5960 $3.00 $17,880.00 $2.55 $15,198.00
11 4 OAKWOOD SY 2200 $3.00 $6,600.00 $2.55 $5,610.00
12 4 HILLTOP RSY 13700 $3.00 $41,100.00 $2.55 $34,935.00
Base Bid Total: $249,975.00 $223,469.50
Page 16 of 31
BUSINESS OF THE PUBLIC WORKS & HIGHWAYS COMMITTEE
MEETING DATE: June 3, 2026
PLACEMENT: Action Item
ITEM TITLE: Award of Contract – Division Road Phase 1
SUBMITTED BY: Tim Zimmerman – Director of Public Works
SUMMARY EXPLANATION:
The 2026 Road Program includes money for the Phase 1 reconstruction of Division Rd.
the bid are summarized below:
Stark Pavement Corp. $2,402,772.10
Musson Bros., Inc $2,397,799.60
Payne and Dolan $2,128,590.12
This project includes full pavement removal, drainage improvements, and pedestrian
movement improvements. Engineer’s estimate: $2,468,385.00.
ATTACHMENT: ORDINANCE RESOLUTION OTHER___X____
RECOMMENDATION:
Staff requests the PWHC recommend to the Village Board approval of a contract with
Payne and Dolan for the Division Road Phase 1 improvements in the amount of
$2,128,590.12 and allow a 10% contingency $212,859.01 for the total amount of
$2,341,449.10. Funded in 40-561000-5316400.
COMMITTEE ACTION:
Proper parliamentary procedure to deny a request is to have a motion made in the
affirmative and by voting NAY would deny the request if a majority vote.
Page 17 of 31
Page 1 of 2
Division Road: From Mequon Road to Jefferson Creek (#10205153)
Owner: Village of Germantown
raSmith Project Number: 2264801
Bid Opening: 05/28/2026 11:00 AM CDT
Item No. Item Description UofM Quantity Unit Price E xtension Unit Price Exten sion Unit Price Extension
Base Bid
1 Traffic Control LS 1 $50,513.68 $50,513. 68 $7,650.00 $7,650.00 $45,000.00 $45,000.00
2 Portable Changeable Message Signs DAY S 30 $136.86 $4,105.80 $35.00 $1,050.00 $50.00 $1,500.00
3 Clearing And Grubbing STA 5 $1,144.00 $5,720.00 $1,100.00 $5,500.00 $1,100.00 $5,500.00
4 Tree Removals IN-DIA 100 $70.20 $7,020.00 $80.00 $8,000.00 $80.00 $8,000.00
5 Remove Small Pipe Culverts EA 6 $312.00 $1,872.00 $283.00 $1,698.00 $600.00 $3,600.00
6 Sawcut Pavement LF 500 $2.34 $1, 170.00 $7.00 $3,500.00 $2.25 $1,125.00
7 Pulverize Pavement SY 16000 $3.42 $54,720.00 $8.50 $136,000.00 $5.50 $88,000.00
8 Remove Asphalt Pavement, Driveways S Y 400 $25.61 $10,244.00 $8.40 $3,360.00 $16.50 $6,600.00
9 Remove Asphalt Pavement, Sidewalks S Y 2450 $4.16 $10,192.00 $5.90 $14,455.00 $11.00 $26,950.00
10 Remove Curb and Gutter LF 750 $4. 16 $3,120.00 $8.40 $6,300.00 $10.00 $7,500.00
11 Remove Concrete Curb Ramps SF 640 $0.47 $300.80 $4.60 $2,944.00 $6.50 $4,160.00
12 Common Excavation (+/- 3,600 CY) LS 1 $117, 312.00 $117,312.00 $478,000.00 $478, 000.00 $230,000.00 $230,000.00
13 Excavation Below Subgrade (EBS) C Y 3300 $12.48 $41,184.00 $30.00 $99,000.00 $30.00 $99,000.00
14 Unsuitable Soil Removal CY 150 $20.80 $3,120.00 $31.50 $4,725.00 $45.00 $6,750.00
15 Geogrid Type SR SY 3000 $5.20 $15,600.00 $2.50 $7,500.00 $4.00 $12,000.00
16 Base Aggregate 3" Dense TON 6500 $25.84 $167,960.00 $23.50 $152,750.00 $22.00 $143,000.00
17 Base Aggregate 1" Clear Ston e TON 20 $32.34 $646.80 $22.00 $440.00 $102.00 $2,040.00
18 Base Aggregate 1-1/4" Dense TON 5650 $25.12 $141,928.00 $24.50 $138,425.00 $25.00 $141,250.00
19 Hot Mix Asphalt Pavement 3" Binder Course - 3 LT 58-28S, 19 MM TON 3150 $76.00 $239, 400.00 $75.00 $236,250.00 $79.00 $248,850.00
20 Hot Mix Asphalt Pavement 2" Surface Course - 4 LT 58-28S, 12 MM TON 2000 $84.70 $169, 400.00 $83.00 $166,000.00 $81.55 $163,100.00
21 Tack Coat GAL 900 $5.40 $4, 860.00 $3.70 $3,330.00 $3.00 $2,700.00
22 Hot Mix Asphalt Sidewalk 4" - 4 LT 58-28s , 12 MM TON 920 $102.00 $93,840.00 $98.00 $90,160.00 $150.00 $138,000.00
23 Hot Mix Asphalt Pavement - Driveways, Match Up To 5" HMA 4 LT 58-28s, 12 MM TON 130 $101.00 $13,130.00 $97.00 $12,610.00 $150.00 $19, 500.00
24 Shouldering (Traffic Bond) TON 900 $26.16 $23,544.00 $21.00 $18,900.00 $30.50 $27,450.00
25 Replace Concrete Curb and Gutter LF 100 $114.00 $11,400.00 $106.00 $10,600.00 $52.50 $5,250.00
26 New Concrete Curb and Gutter - 30" VF CG LF 2049 $27.77 $56,900.73 $22.50 $46,102.50 $21.50 $44,053.50
27 New Concrete Curb and Gutter - Roll Face/Mount able Curb LF 231 $40.21 $9,288. 51 $34.50 $7,969.50 $35.25 $8,142.75
28 Concrete Curb Ramps and Concrete Wal
k SF 1875 $11.18 $20,962.50 $11.00 $20,625.00 $10.50 $19,687.50
29 Detectable Warning Fields SF 260 $32.92 $8,559.20 $31.50 $8,190.00 $50.00 $13,000.00
30 Pavement Markings Arrows EA 1 $338.00 $338.00 $221.00 $221.00 $232.05 $232.05
31 Pavement Markings Words EA 1 $338.00 $338.00 $226.00 $226.00 $237.30 $237.30
32 Pavement Marking, Stop Line - White 18" , Solid LF 180 $19.24 $3,463.20 $18.00 $3,240.00 $18.50 $3,330.00
33 Pavement Marking, Striping - White 8", Solid LF 220 $1.77 $389.40 $1.10 $242.00 $1.20 $264.00
34 Pavement Marking, Striping - White 4" , Solid LF 6300 $0.87 $5,481.00 $0.40 $2,520.00 $0.50 $3,150.00
35 Pavement Marking, Striping - White 4", Dashed LF 320 $0.87 $278.40 $0.65 $208.00 $0.75 $240.00
36 Pavement Marking, Striping - Yellow 4" LF 60 $12.32 $739.20 $1.00 $60.00 $2.00 $120.00
37 Pavement Marking, Striping - 2x Yellow 4", Solid LF 5450 $0.87 $4,741.50 $0.40 $2,180.00 $0.50 $2,725.00
38 Pavement Marking, Striping - 2x Yello w 4", Passing LF 210 $0.87 $182.70 $0.40 $84.00 $0.50 $105.00
39 Pavement Marking, Striping Crosswalk - Whi te 6", Solid LF 850 $11.70 $9,945.00 $14.50 $12,325.00 $14.50 $12,325.00
Payne & Dolan, Inc. Musson Bros., Inc. Stark Pavement Corp.
Page 18 of 31
Page 2 of 2
Item No. Item Description UofM Quantity Unit Price E xtension Unit Price Exten sion Unit Price Extension
Payne & Dolan, Inc. Musson Bros., Inc. Stark Pavement Corp.
40 Remove & Replace Mailbox EA 3 $208.00 $624.00 $162.00 $486.00 $220.00 $660.00
41 Surface Restoration, Topsoil, Seed, Erosion Ma t, And Watering SY 12000 $8.58 $102, 960.00 $7.80 $93,600.00 $10.00 $120,000.00
42 Sod SY 2450 $17.52 $42,924.00 $11.50 $28,175.00 $20.00 $49,000.00
43 Erosion Control, Silt Fence LF 7250 $1.82 $13,195.00 $1.70 $12,325.00 $2.00 $14,500.00
44 Temporary Water Diversion Structure to Place Rip Rap At B-66-144 LS 1 $39,312.00 $39, 312.00 $89,900.00 $89,900.00 $50,000.00 $50,000. 00
45 Heavy Rip Rap CY 111 $197.60 $21, 933.60 $278.00 $30,858.00 $300.00 $33,300.00
46 Geotextile Fabric HR SY 212 $20.80 $4,409.60 $4.80 $1,017.60 $20.00 $4,240.00
47 Temporary Flow Control for Inter mittent Open Channel Drainage LS 1 $20,800. 00 $20,800.00 $48,300.00 $48, 300.00 $8,700.00 $8,700.00
48 Light Rip-Rap (Keyed-Into Re-Graded Ditch Flowline) CY 31 $135.20 $4,191. 20 $351.00 $10,881.00 $225.00 $6,975.00
49 Erosion Control, E-Mat (Class I, Type A) SY 11400 $1.30 $14,820.00 $1.20 $13,680.00 $1.30 $14,820.00
50 Erosion Control, E-Mat Coconut Ty pe SY 380 $6.03 $2,291.40 $2.40 $912.00 $6.00 $2,280.00
51 Erosion Control, Inlet Protecti on EA 17 $54.08 $919.36 $115.00 $1,955.00 $55.00 $935.00
52 Erosion Control, Erosion Bale s EA 20 $16.64 $332.80 $14.00 $280.00 $17.00 $340.00
53 Flexible Ads Pipe 8-Inch Dia. LF 60 $16.64 $998.40 $46.50 $2,790.00 $80.00 $4,800.00
54 Culvert Pipe 15-Inch Dia., CMP With Flared En d Metal Sections LF 25 $115.44 $2,886.00 $162.00 $4,050.00 $135.00 $3,375.00
55 Culvert Pipe 18-Inch Dia., CMP With Flared En d Metal Sections LF 50 $120.64 $6,032.00 $161.00 $8,050.00 $155.00 $7,750.00
56 Apron Endwalls for Concrete Culvert Pipe 12-In ch Dia. EA 5 $1,560.00 $7,800.00 $1,000.00 $5,000.00 $1,900.00 $9,500.00
57 Apron Endwalls for Concrete Culvert Pipe 15-In ch Dia. EA 2 $1,712.88 $3,425.76 $1,160.00 $2,320.00 $2,000.00 $4,000.00
58 Apron Endwalls for Concrete Culvert Pipe 24-In ch Dia. EA 2 $2,194.40 $4,388.80 $1,770.00 $3,540.00 $2,250.00 $4,500.00
59 Storm Sewer Pipe Reinforced Concrete Class IV (12-Inch Dia.) LF 239 $111.28 $26, 595.92 $102.00 $24,378.00 $115.00 $27,485.00
60 Storm Sewer Pipe Reinforced Concrete Class IV (24-Inch Dia.) LF 390 $137.28 $53, 539.20 $119.00 $46,410.00 $130.00 $50,700.00
61 Storm Sewer Pipe Reinforced Concrete Class IV (42-Inch Dia.) LF 42 $283.92 $11, 924.64 $278.00 $11,676.00 $350.00 $14,700.00
62 Concrete Collar (42-Inch Dia) EACH 1 $1,248.00 $1,248.00 $808.00 $808.00 $2,650.00 $2,650.00
63 Concrete Collar (24-Inch Dia.) Bu lkhead and Abandon 24-Inch Dia. EACH 1 $1,144.00 $1,144.00 $808.00 $808.00 $3,100.00 $3,100.00
64 Storm Sewer Spot Repair, 15-Inch Dia. Cla ss C Bedding LF 20 $287.04 $5,740.80 $255.00 $5,100.00 $937.50 $18,750.00
65 Medium Rip Rap CY 35 $156.00 $5,460.00 $265.00 $9,275.00 $225.00 $7,875.00
66 Storm Structure Adjustments EA 10 $2, 808.00 $28,080.00 $2,130.00 $21, 300.00 $1,100.00 $11,000.00
67 Storm Inlet and Catch Basin (2x3-Ft) New with Fram e and Grate EACH 9 $5,521.36 $49,692. 24 $3,620.00 $32,580.00 $4,250.00 $38,250.00
68 Storm Inlet and Catch Basin (2x3-Ft) Replacement (Re-Us e Frame and Grate) EACH 4 $4,891. 12 $19,564.48 $2,000.00 $8,000.00 $3,100.00 $ 12,400.00
69 Storm Manhole Structure (48-Inch Dia.) E ACH 5 $7,030.40 $35,152.00 $3,040. 00 $15,200.00 $6,600.00 $33,000.00
70 Reinforced Concrete Structure Box EAC H 1 $43,056.00 $43,056.00 $38,400.00 $38,400.00 $80,000.00 $80,000.00
71 Breaker Run 3-Inch CY 10 $90.27 $902.70 $50.50 $505.00 $120.00 $1,200.00
72 Railing (Pedestrian Safety Type, 2- 1/2 Dia. Inch Stainless Steel Tube) LF 25 $827.80 $20,695.00 $500.00 $12,500.00 $550.00 $13,750.00
73 Flagpole Remove and Reinstall, Including Coordinati on with Owner LS 1 $3,120.00 $3,120. 00 $5,000.00 $5,000.00 $2,500.00 $2,500.00
74 Borrow to Fill at SEC of Hawthorne & NWC Lil ac Hawthorne CY 3600 $8.32 $29,952. 00 $9.30 $33,480.00 $20.50 $73,800.00
75 Adjust Hydrant with Flanged Assembly, 2- Ft EACH 9 $3,151.20 $28,360.80 $2, 720.00 $24,480.00 $5,100.00 $45,900.00
76 Adjust Water Gate Valve Box EACH 2 8 $208.00 $5,824.00 $418.00 $11,704.00 $900.00 $25,200.00
77 Remove And Replace Valve Box EACH 5 $2,714.40 $13,572.00 $970.00 $4, 850.00 $2,000.00 $10,000.00
78 Sanitary Manhole Adjustment EACH 14 $3,432.00 $48,048.00 $639.00 $8, 946.00 $1,600.00 $22,400.00
79 Existing Utility Offsets (Storm) EAC H 5 $6,692.40 $33,462.00 $1,010.00 $5,050.00 $3,600.00 $18,000.00
80 Existing Utility Offsets (Sanitary) EACH 5 $7,592.00 $37,960.00 $589. 00 $2,945.00 $600.00 $3,000.00
81 Existing Utility Offsets (Water) E ACH 5 $3,468.40 $17,342.00 $589.00 $2,945.00 $600.00 $3,000.00
Base Bid Total: $2,128, 590.12 $2,397,799. 60 $2,402,772.10
Page 19 of 31
Division Road Reconstruction Project
Cost Estimate-Based on Bid Set
5-27-26 Updated per Addendum
ITEM DESCRIPTION UNIT ǪTY TOTAL
1 TRAFFIC CONTROL LS 1 $50,000.00
2 PORTABLE CHANGEABLE MESSAGE SIGNS DAYS 30 $30,000.00
3 CLEARING AND GRUBBING STA 5 $5,000.00
4 TREE REMOVALS IN-DIA 100 $5,000.00
5 REMOVE SMALL PIPE CULVERTS EA 6 $4,500.00
6 SAWCUT PAVEMENT LF 500 $2,500.00
7 PULVERIZE PAVEMENT SY 16000 $160,000.00
8 REMOVE ASPHALT PAVEMENT, DRIVEWAYS SY 400 $2,000.00
9 REMOVE ASPHALT PAVEMENT, SIDEWALKS SY 2450 $12,250.00
10 REMOVE CURB AND GUTTER SF 750 $11,250.00
11 REMOVE CONRETE CURB RAMPS SF 640 $4,480.00
12 COMMON EXCAVATION (+/- 3,600 CY) LS 1 $300,000.00
13 EXCAVATION BELOW SUBGRADE (EBS) CY 3300 $115,500.00
14 UNSUITABLE SOIL REMOVAL CY 150 $15,000.00
15 GEOGRID TYPE SR SY 3000 $9,000.00
16 BASE AGGREGATE 3" DENSE TON 6500 $195,000.00
17 BASE AGGREGATE 1" CLEAR STONE TON 20 $3,000.00
18 BASE AGGREGATE 1-1/4" DENSE TON 5650 $113,000.00
19 HOT MIX ASPHALT PAVEMENT 3" BINDER COURSE - 3 LT 58-28S, 19 mm TON 3150 $236,250.00
20 HOT MIX ASPHALT PAVEMENT 2" SURFACE COURSE - 4 LT 58-28S, 12 mm TON 2000 $170,000.00
21 TACK COAT GAL 900 $4,500.00
22 HOT MIX ASPHALT SIDEWALK 3" - 4 LT 58-28S, 12 mm TON 920 $115,000.00
23 HOT MIX ASPHALT PAVEMENT - DRIVEWAYS, MATCH UP TO 5" HMA 4 LT 58-28S, 12 mm TON 130 $13,000.00
24 SHOULDERING (Traffic Bond) TON 900 $45,000.00
25 REPLACE CONCRETE CURB AND GUTTER LF 100 $4,500.00
26 NEW CONCRETE CURB AND GUTTER - 30" VFCG LF 2049 $71,715.00
27 NEW CONCRETE CURB AND GUTTER - Roll Face/Mountable Curb LF 231 $9,240.00
28 CONCRETE CURB RAMPS AND CONCRETE WALK SF 1875 $28,125.00
29 DETECTABLE WARNING FIELDS SF 260 $13,000.00
30 PAVEMENT MARKINGS ARROWS EA 1 $500.00
31 PAVEMENT MARKINGS WORDS EA 1 $500.00
32 PAVEMENT MARKING, STOP LINE - WHITE 18", SOLID LF 180 $3,600.00
33 PAVEMENT MARKING, STRIPING - WHITE 8", SOLID LF 220 $440.00
34 PAVEMENT MARKING, STRIPING - WHITE 4", SOLID LF 6300 $9,450.00
35 PAVEMENT MARKING, STRIPING - WHITE 4", DASHED LF 320 $480.00
36 PAVEMENT MARKING, STRIPING - YELLOW 4" LF 60 $90.00
37 PAVEMENT MARKING, STRIPING - 2X YELLOW 4", SOLID LF 5450 $8,175.00
38 PAVEMENT MARKING, STRIPING - 2X YELLOW 4", PASSING LF 210 $315.00
39 PAVEMENT MARKING, STRIPING CROSSWALK - WHITE 6", SOLID LF 850 $2,125.00
40 REMOVE & REPLACE MAILBOX EA 3 $1,500.00
41 SURFACE RESTORATION, TOPSOIL, SEED, EROSION MAT, AND WATERING SY 12000 $96,000.00
42 SOD SY 2450 $7,350.00
43 EROSION CONTROL, SILT FENCE LF 7250 $29,000.00
44 Temporary Water Diversion Structure to Place Rip Rap at B-66-144 LS 1 $30,000.00
45 Heavy Rip Rap CY 111 $11,100.00
46 Geotextile Fabric HR SY 10 $250.00
47 Temporary Flow Control for Intermittent Open Channel Drainage LS 1 $30,000.00
48 Light Rip-Rap (Keyed-Into Re-graded Ditch Flowline) CY 31 $5,425.00
49 Erosion Control, E-mat (Class I, Type A) SY 11400 $22,800.00
50 Erosion Control, E-mat Coconut Type SY 380 $1,140.00
51 Erosion Control, Inlet Protection EA 17 $1,360.00
52 Erosion Control, Erosion Bales EA 20 $2,000.00
53 Flexible ADS Pipe 8-Inch Dia. LF 60 $4,500.00
54 Culvert Pipe 15-inch dia., CMP with Flared End Metal Sections LF 25 $3,750.00
55 Culvert Pipe 18-inch dia., CMP with Flared End Metal Sections LF 50 $8,750.00
56 Apron Endwalls for Culvert Pipe 12-Inch Dia. EA 5 $2,500.00
57 Apron Endwalls for Culvert Pipe 15-Inch Dia. EA 2 $1,300.00
58 Apron Endwalls for Culvert Pipe 24-Inch Dia. EA 2 $1,500.00
59 Storm Sewer Pipe Reinforced Concrete Class IV (12-inch dia.) LF 239 $29,875.00
60 Storm Sewer Pipe Reinforced Concrete Class IV ( 24-inch dia.) LF 390 $58,500.00
61 Storm Sewer Pipe Reinforced Concrete Class IV ( 42-inch dia.) LF 42 $16,800.00
62 Concrete Collar (42-inch dia) EACH 1 $1,500.00
63 Concrete Collar (24-inch dia.) Bulkhead and Abandon 24-inch dia. EACH 1 $1,250.00
64 Storm Sewer Spot Repair, 15-inch dia. Class “C” Bedding LF 20 $5,000.00
65 Medium Rip Rap CY 35 $5,250.00
66 Storm Inlet Structure Adjustments EA 10 $15,000.00
67 Storm Inlet and Catch Basin (2x3-ft) NEW with frame and grate EACH 9 $54,000.00
68 Storm Inlet and Catch Basin (2x3-ft) REPLACEMENT (Re-use Frame and grate) EACH 4 $20,000.00
69 Storm Manhole Structure (48-inch dia.) EACH 5 $35,000.00
70 Reinforced Concrete Structure Box EACH 1 $10,000.00
71 Breaker Run – 3-inch CY 10 $500.00
72 Railing (Pedestrian Safety Type, 2-1/2 dia. inch Stainless Steel Tube) LF 25 $5,000.00
73 Flagpole coordination with owner LS 1 $1,500.00
74 Borrow to Fill at SEC of Hawthorne & NWC Lilac Hawthorne CY 3600 $72,000.00
75 ADJUST HYDRANT WITH FLANGED ASSEMBLY, 2-FT EACH 9 $13,500.00
76 ADJUST Water Gate Valve Box EACH 28 $14,000.00
77 REMOVE AND REPLACE VALVE BOX EACH 5 $25,000.00
78 Sanitary Manhole Adjustment EACH 14 $21,000.00
79 EXISTING UTILITY OFFSETS (STORM) LS 1 $10,000.00
80 EXISTING UTILITY OFFSETS (SANITARY) LS 1 $10,000.00
81 EXISTING UTILITY OFFSETS (WATER) LS 1 $10,000.00
$2,468,385.00
$1,500.00
$500.00
$10,000.00
$10,000.00
$10,000.00
$5,000.00
$1,500.00
$10,000.00
$50.00
$200.00
$1,500.00
$20.00
$150.00
$1,500.00
$6,000.00
$5,000.00
$7,000.00
$150.00
$400.00
$1,500.00
$1,250.00
$250.00
$175.00
$650.00
$750.00
$125.00
$500.00
$3.00
$80.00
$75.00
$100.00
$150.00
$100.00
$25.00
$30,000.00
$175.00
$2.00
$500.00
$8.00
$3.00
$4.00
$30,000.00
$1.50
$1.50
$1.50
$1.50
$2.50
$500.00
$500.00
$20.00
$2.00
$1.50
$45.00
$35.00
$40.00
$15.00
$50.00
$85.00
$5.00
$125.00
$100.00
$50.00
$3.00
$30.00
$150.00
$20.00
$75.00
Construction Total
UNIT PRICE
$50,000.00
$1,000.00
$1,000.00
$50.00
$750.00
$5.00
$10.00
$5.00
$5.00
$15.00
$7.00
$300,000.00
$35.00
$100.00
Page 20 of 31
May 29, 2026
Mr. Tim Zimmerman, Director of Public Works
Village of Germantown
N112 W117001 Mequon Road
Germantown, WI 53022
Re: Letter of Recommendation
Division Road: From Mequon Rd to Jefferson Creek (#10205153)
Dear Mr. Zimmerman:
In accordance with your Official Notice to Bidders, bids for the above reference d project were received until 11:00
a.m. on May 28, 2026.
A total of three (3) bids were received for this project. The base bids ranged from $2,128,590.12 to
$2,402,772.10. The low base bid of $$2,128,590.12 was submitted by Payne and Dolan, Inc. The engineer’s
estimate for the project was $2,468,385.
Payne and Dolan, Inc., provided a responsive bid, they are pre-qualified and along with their subs, have either
completed or are currently working on similar projects within the Village. They have completed similar projects in
a satisfactorily manner and they have been on time and on budget. Therefore, we recommend awarding the
project to Payne and Dolan, Inc. in the amount of $2,128,590.12.
Please feel free to call me if you have any questions or comments regarding the above.
Sincerely,
raSmith
Troy T. Hartjes, P.E.
Senior Project Manager
Enclosure: Bid Summary
Page 21 of 31
BUSINESS OF THE PUBLIC WORKS & HIGHWAYS COMMITTEE
MEETING DATE: June 3, 2026
PLACEMENT: Action Item
ITEM TITLE: Professional Services Agreement – Division Road Phase 1 -
Inspection, Staking, and Administration
SUBMITTED BY: Tim Zimmerman – Director of Public Works
SUMMARY EXPLANATION:
Construction inspection, staking, and contract administration for Division Rd. Phase 1
will far exceed the village engineering department’s capabilities.
ATTACHMENT: ORDINANCE RESOLUTION OTHER___X____
RECOMMENDATION:
Staff requests the PWHC recommend to the Village Board approval of a Professional
Services Agreement with ra Smith in the amount of $168,000.00. and include a 10%
contingency $16,800.00 for the total amount of $184,800.00. Money included in 40-
561000-5316400.
COMMITTEE ACTION:
Proper parliamentary procedure to deny a request is to have a motion made in the
affirmative and by voting NAY would deny the request if a majority vote.
Page 22 of 31
May 29, 2026
Timothy K. Zimmerman
Department of Public Works
Village of Germantown
W130N10200 Town 9 Parkway
Germantown, WI 53022-0337
Re: Proposal for Division Road Phase 1
Dear Mr. Zimmerman:
Thank you for allowing raSmith to provide you with a proposal for Division Road Phase 1. We strive to develop a
long-term, mutually beneficial relationship with our clients and are committed to understanding your challenges
and developing solutions that meet your needs. We look forward to working with the Village of Germantown.
Scope of Services
raSmith will provide services associated with construction-related activities. Mike Mentzel will be the Resident
Lead full-time construction inspector. A second inspector will be appointed only during times when multiple crews
are completing work.
1. Construction Administration to include preconstru ction meeting attendance, shop drawing and materials
review, recommendation of payments, progress meetings, review change order requests, review requests
for information by the contractor, project walk-throughs, compile punch lists and project closeout.
2. We will provide construction observ ation when the contractor is on site performing work. Generally, there
is one inspector per crew that is working. Observations include checking delivered materials to make sure
they are in compliance with the specifications, check traffic control devices during the project, recording of
elevation and locations of all underground appurtenances with a survey grade GPS, track all quantities
that are installed for payment, and take daily pictures of ongoing operations. Observations will be
documented in electronic format, and a pdf copy will be e-mailed to Village staff.
3. Weekly erosion inspections and after 0.5” ra in event will be completed per WDNR requirements
4. Record Drawings for the storm sewer will be completed and data sent to the Village to update your GIS
system.
5. Construction staking will be performed for site cont rol, storm sewer, red tops for CABC grades, slope
stakes, curb and gutter, sidewalk and handicap ramps. A cutsheet will be provided to the inspector and
contractor as necessary.
Completion Schedule
Work is anticipated during the 2026 construction season.
Page 23 of 31
Timothy K. Zimmerman
Director of Public Works
Page 2 / May 29, 2026
Professional Fees
The above-described services will be provided on an hourly and expense basis. Based on normal production
rates, the estimate of fees for Division Road Phase 1 is $168,000. Fees will be invoiced monthly as the project
proceeds. The Resident Lead Inspector will be available at a rate of $125 per hour and additional inspector at a
rate of $114 per hour. As Construction Manager is available at a rate of $174 per hour and a CADD Technician at
a rate of $125 per hour.
A two-person survey crew will be available for construction staking at a rate of $260 per hour ($130 per person)
and a Survey Project Manager at a rate of $145 per hour.
Usual and customary expenses such as mileage, postage, delivery, and applicable taxes will be invoiced at cost.
Client Responsibilities/Assumptions
A. The terms and conditions set forth herein are valid for 365 days from the date of this proposal and are
conditioned upon our completion of all services within 18 months from the date of authorization.
B. The professional fee hourly rates are subject to change on an annual basis.
C. No Geotechnical or Materials Testing work is included in this proposal.
D. No additional design services are included in this proposal.
If you would like to authorize raSmith to proceed with your project, please sign the attached Professional Services
Agreement between Client and Professional, and forward a signed copy of the entire Agreement to our office.
Once received, we will execute and return a copy for your records. We look forward to working with the Village of
Germantown.
Sincerely,
raSmith
Jennifer Starr, CISEC
Assistant Director of Construction Services
Enclosure: Professional Services Agreement (Contract)
BTH:I:\Proposals\2026\Germantown\Division Road\EP 260529 Zimmerman Division Road Phase 1.docx
Page 24 of 31
Page 1 of
PROFESSIONAL SERVICES AGREEMENT
BETWEEN CLIENT AND PROFESSIONAL
THIS IS AN AGREEMENT effective as of ("Effective Date") between ("Client")
and R.A. Smith, Inc. ("Professional").
Client’s Project, of which Professional’s services under this Agreement are a part, is generally identified as follows:
("Project").
Professional’s services under this Agreement are generally identified as follows:
("Services").
Client and Professional further agree as follows:
1.01 Basic Agreement and Period of Service
A. Professional shall provide or furnish the Services solely for the benefit of Client as set forth in this Agreement and in the attached proposal.
If authorized by Client, or if required because of changes in the Project, Professional shall furnish services in addition to those set forth
above (“Additional Services”).
2.01 Payment Procedures
A. Invoices: Professional shall prepare invoices in accordance with its standard invoicing practices and submit the invoices to Client on a
monthly basis. Invoices are due and payable within 30 days of invoice date. If Client fails to make any payment due Professiona l for
Services, Additional Services, and expenses within 30 days after receipt of Professional’s invoice, then (1) the amounts due Professional
will be increased at the rate of 1.0% per month (or the maximum rate of interest permitted by law, if less) from said thirtieth day, and (2) in
addition Professional may, after giving seven days written notice to Client, suspend Services under this Agreement until Professional has
been paid in full all amounts due for Services, Additional Services, expenses, and other related charges. Client waives any and all claims
against Professional for any such suspension.
B. Payment: As compensation for Professional providing or furnishing Services and Additional Services, Client shall pay Professional as set
forth in this agreement. If Client disputes an invoice, either as to amount or entitlement, then Client shall promptly advise Professional in
writing of the specific basis for doing so, may withhold only that portion so disputed, and must pay the undisputed portion.
2.02 Basis of Payment
A. Client shall pay Professional for Services in the amount and manner provided in the attached proposal.
B. Additional Services: Unless specified in the attached proposal, for Additional Services, Client shall pay Professional an amount equal to
the cumulative hours charged in providing the Additional Services by each class of Professional’s employees, times standard hourly rates
for each applicable billing class; plus reimbursement of expenses incurred in connection with providing the Additional Services and
Professional’s consultants’ charges, if any.
3.01 Suspension and Termination
A. The obligation to continue performance under this Agreement may be suspended:
1. By Client: Client may suspend the Project for up to 90 days upon seven days written notice to Professional.
2. By Professional: Professional may, after giving seven days written notice to Client, suspend services under this Agreement if Client
has failed to pay Professional for invoiced services and expenses, as set forth in this Agreement.
B. The obligation to continue performance under this Agreement may be terminated:
1. For cause,
a. By either party upon 14 days written notice in the event of substantial failure by the other party to perform in accordance with
the Agreement’s terms through no fault of the terminating party. Failure to pay Professional for its services is a substantial
failure to perform and a basis for termination.
b. By Professional:
1) upon seven days written notice if Client demands that Professional furnish or perform services contrary to Professional’s
responsibilities as a licensed professional; or
2) upon seven days written notice if the Professional’s Services are delayed for more than 90 days for reasons beyond
Professional’s control, or as the result of the presence at the Site of undisclosed Constituents of Concern.
c. By Client, for convenience, effective upon Professional's receipt of written notice from Client
Village of Germantown
Page 25 of 31
Page 2 of
d. Professional shall have no liability to Client on account of a termination for cause by Professional.
e. Notwithstanding the foregoing, this Agreement will not terminate as a result of a substantial failure under this section if the party
receiving such notice begins, within seven days of receipt of such notice, to correct its substantial failure to perform and
proceeds diligently to cure such failure within no more than 30 days of receipt of notice; provided, however, that if and to the
extent such substantial failure cannot be reasonably cured within such 30 day period, and if such party has diligently attempted
to cure the same and thereafter continues diligently to cure the same, then the cure period provided for herein shall extend up
to, but in no case more than, 60 days after the date of receipt of the notice.
C. In the event of any termination under this section, Professional will be entitled to invoice Client and to receive full payment for all Services
and Additional Services performed or furnished in accordance with this Agreement, plus reimbursement of expenses incurred through the
effective date of termination in connection with providing the Services and Additional Services, and Professional’s consultants’ charges, if
any.
4.01 Successors, Assigns, and Beneficiaries
A. Client and Professional are hereby bound and the successors, executors, administrators, and legal representatives of Client a nd
Professional are hereby bound to the other party to this Agreement and to the successors, executors, administrators, and legal
representatives (and said assigns) of such other party, in respect of all covenants, agreements, and obligations of this Agreement.
B. Neither Client nor Professional may assign, sublet, or transfer any rights under or interest (including, but without limitati on, money that is
due or may become due) in this Agreement without the written consent of the other party, except to the extent that any assignme nt,
subletting, or transfer is mandated by law. Unless specifically stated to the contrary in any written consent to an assignment, no assignment
will release or discharge the assignor from any duty or responsibility under this Agreement.
C. Unless expressly provided otherwise, nothing in this Agreement shall be construed to create, impose, or give rise to any duty owed by
Client or Professional to any Constructor, other third-party individual or entity, or to any surety for or employee of any of them. All duties
and responsibilities undertaken pursuant to this Agreement will be for the sole and exclusive benefit of Client and Professional and not for
the benefit of any other party.
5.01 General Considerations
A. Standard of Care
The standard of care for all professional engineering and related services performed or furnished by Professional under this Agreement
will be the care and skill ordinarily used by members of the subject profession practicing under similar circumstances at the same time
and in the same locality. Professional makes no warranties, express or implied, under this Agreement or otherwise, in connection with any
services performed or furnished by Professional. Subject to the foregoing standard of care, Professional and its consultants may use or
rely upon design elements and information ordinarily or customarily furnished by others, including, but not limited to, specialty contractors,
manufacturers, suppliers, and the publishers of technical standards.
B. Design Without Construction Phase Services
Professional shall not at any time supervise, direct, control, or have authority over any Constructor’s work, nor shall Professional have
authority over or be responsible for the means, methods, techniques, sequences, or procedures of construction selected or used by any
Constructor, or the safety precautions and programs incident thereto, for security or safety at the Project site, nor for any f ailure of a
Constructor to comply with laws and regulations applicable to such Constructor’s furnishing and performing of its work. Professional shall
not be responsible for the acts or omissions of any Constructor. Professional neither guarantees the performance of any Constructor nor
assumes responsibility for any Constructor’s failure to furnish and perform its work.
C. Opinions of Cost
Professional’s opinions (if any) of probable construction cost are to be made on the basis of Professional’s experience, qualifications, and
general familiarity with the construction industry. However, because Professional has no control over the cost of labor, materi als,
equipment, or services furnished by others, or over contractors’ methods of determining prices, or over competitive bidding or market
conditions, Professional cannot and does not guarantee that proposals, bids, or actual construction cost will not vary from opinions of
probable construction cost prepared by Professional. If Client requires greater assurance as to probable construction cost, then Client
agrees to obtain an independent cost estimate. Professional shall not be responsible for any decision made regarding the construction
contract requirements, or any application, interpretation, clarification, or modification of the construction contract documents other than
those made by Professional or its consultants.
D. Use of Documents
All documents prepared or furnished by Professional are instruments of service, and Professional retains an ownership and property
interest (including the copyright and the right of reuse) in such documents, whether or not the Project is completed. Client shall have a
limited license to use the documents on the Project, extensions of the Project, and for related uses of the Client, subject to receipt by
Professional of full payment due and owing for all Services and Additional Services relating to preparation of the documents and subject
to the following limitations:
1. Client acknowledges that such documents are not intended or represented to be suitable for use on the Project unless complete d
by Professional, or for use or reuse by Client or others on extensions of the Project, on any other project, or for any other use or
purpose, without written verification or adaptation by Professional;
Page 26 of 31
Page 3 of 5
2. Any such use or reuse, or any modification of the documents, without written verification, completion, or adaptation by Professional,
as appropriate for the specific purpose intended, will be at Client’s sole risk and without liability or legal exposure to Professional or
to its officers, directors, members, partners, agents, employees, and consultants;
3. Client shall indemnify and hold harmless Professional and its officers, directors, members, partners, agents, employees, and
consultants from all claims, damages, losses, and expenses, including attorneys’ fees, arising out of or resulting from any use, reuse,
or modification of the documents without written verification, completion, or adaptation by Professional; and
4. Such limited license to Client shall not create any rights in third parties.
E. Liability Intentionally Deleted
To the fullest extent permitted by Laws and Regulations, and notwithstanding any other provision of this Agreement, the total liability, in
the aggregate, of Professional and Professional’s officers, directors, employees, and Consultants, to Client and anyone claiming by,
through, or under Client for any and all injuries, claims, losses, expenses, costs, or damages whatsoever arising out of, resulting from, or
in any way related to the Project, Professional’s or its Consultants services or this Agreement from any cause or causes whatsoever,
including but not limited to the negligence, professional errors or omissions, strict liability, breach of contract, indemnity obligations, or
warranty express or implied of Professional or Professional’s officers, directors, employees, or Consultants shall not exceed the total
amount of $100,000 or the total compensation received by Professional under this Agreement, whichever is less.
F. Indemnification Intentionally Deleted
To the fullest extent permitted by Laws and Regulations, Client shall indemnify and hold harmless Professional and Professional’s officers,
directors, employees, and Consultants from and against any and all claims, costs, losses and damages (including but not limited to all
fees and charges of Professionals, architects, attorneys, and other professionals, and all court, arbitration, or other dispute resolution
costs) arising out of or relating to the Project, provided that any such claim, cost, loss, or damage is attributable to bodily injury, sickness,
disease, or death or to injury to or destruction of tangible property (other than the Work itself), including the loss of use resulting therefrom,
but only to the extent caused by any negligent act or omission of the Client or Client’s officers, directors, members, partners, agents,
employees, consultants, or others retained by or under contract to the Client with respect to this Agreement or to the Project.
E. Indemnification and Liability
1. To the fullest extent permitted by law, Professional shall indemnify and hold harmless Client, Client’s officers, directors, partners,
and employees from and against costs, losses, and damages (including but not limited to reasonable fees and charges of engineers,
architects, attorneys, and other professionals, and reasonable court or arbitration or other dispute resolution costs) caused solely by
the negligent acts or omissions of Professional or Professional’s officers, directors, partners, employees, and consultants in the
performance of Professional’s services under this Agreement.
2 To the fullest extent permitted by law, Client shall indemnify and hold harmless Professional, Professional’s officers, direc tors,
partners, employees, and consultants from and against costs, losses, and damages (including but not limited to reasonable fees and
charges of engineers, architects, attorneys, and other professionals, and reasonable court or arbitration or other dispute resolution
costs) caused solely by the negligent acts or omissions of Client or Client’s officers, directors, partners, employees, and consultants
with respect to this Agreement.
3. To the fullest extent permitted by law, Professional’s total liability to Client and anyone claiming by, through, or under Client for any
injuries, losses, damages and expenses caused in part by the negligence of Professional and in part by the negligence of Client or
any other negligent entity or individual, shall not exceed the percentage share that Professional’s negligence bears to the tot al
negligence of Client and all other negligent entities and individuals.
4. Nothing contained within this Agreement is intended to be a waiver or estoppel of the contracting municipality Client or its insurer to
rely upon the limitations, defenses, and immunities contained within Wisconsin law, including those contained within Wisconsin
Statutes §§ 893.80, 895.52, and 345.05. To the extent that indemnification is available and enforceable, the municipality Client or
its insurer shall not be liable in indemnity or contribution for an amount greater than the limits of liability for municipal c laims
established by Wisconsin Law.
F. Dispute Resolution
Client and Professional agree to negotiate each dispute between them in good faith during the 30 days after written notice of dispute. If
negotiations are unsuccessful in resolving the dispute, then the dispute shall be mediated. If mediation is unsuccessful, then the parties
may exercise their rights at law. The venue for all disputes shall be the state of Wisconsin. Attorney fees will be borne by the non-
prevailing party.
G. Governing Law
This Agreement is to be governed by the law of the state of Wisconsin.
Page 27 of 31
Page 4 of 5
6.01 Agreement
A. This Agreement (including any expressly incorporated attachments), constitutes the entire agreement between Client and Profes sional
and supersedes all prior written or oral understandings. This Agreement may only be amended, supplemented, modified, or canceled by
a duly executed written instrument. Nothing in this Agreement between Professional and Client shall create a contractual relationship
between either Professional and Client and an outside third party.
7.01 Lien Notice
A. As required by the Wisconsin construction lien law, Professional hereby notifies Client that persons or companies performing, furnishing,
or procuring labor, services, materials, plans, or specifications for the construction on Client's land may have lien rights on Client's land
and buildings if not paid. Those entitled to lien rights, in addition to the undersigned Professional, are those who contract directly with the
Client or those who give the Client notice within 60 days after they first perform, furnish, or procure labor, services, materials, plans or
specifications for the construction. Accordingly, Client probably will receive notices from those who perform, furnish, or procure labor,
services, materials, plans, or specifications for the construction, and should give a copy of each notice received to the mortgage lender, if
any. Professional agrees to cooperate with the Client and the Client's lender, if any, to see that all potential lien Professionals are duly
paid.
Page 28 of 31
Page 5 of 5
IN WITNESS WHEREOF, the parties hereto have executed this Agreement, the Effective Date of which is indicated on page 1.
P r o j e c t N a m e :
C
l i e n t : P r o f e s s i o n a l :
By: By:
P r i n t n a m e : P r i n t n a m e :
T i t l e : T i t l e :
Date Signed: Date Signed:
Address for Client’s receipt of notices: Address for Professional’s receipt of notices:
R . A . S m i t h , I n c .
16745 West Bluemound Road
Brookfield, WI 53005
Client's Phone: Professional's Phone:
C l i e n t ' s E m a i l : P r o f e s s i o n a l ' s E m a i l :
Page 29 of 31
Directors Report – May 2026
Engineering
Road program including 2026 Roads along with seal coating program
Beginning Mid-June
Pleasant View culvert replacement, ARIP road project Lovers Lane South
to Freistadt. (design being finalized, summer Ad, fall construction tentative)
Maple Rd. Bridge repair over Willow Creek. Repair of deteriorated west
beam addresses remaining lifespan of the structure. (Quotes for repair
being requested, budget and program bridge replacement/pursue grant
funding)
CTH Q & STH 175 Intersection Signal Replacements. Improvements
planned for advertisement this late summer for work in early 2027.
New engineering Technician Mark Johnson started Monday, June 1
Highways, Parks, Buildings, and Grounds
Full spring mode with mowing operations, mowing operations will transition
to summer help as they onboard
Mastic application to address road settlement around manholes, inlets and
water valves
Brush pick up began Monday, June 1 approximately 4 weeks in duration
Street light fixture replacement underway will be on-going throughout the
summer
Many road culvert failures due to August and April extreme rain events
Highway line item is exhausted, but work will continue to make the roads
safe for the public. Culvert replaced on Indian Pkwy. Last week
Shelter repair at Fireman’s Park is underway and will be completed by July
4th.
Flower Source Remediation and demo will resume June 9th. Should be
completed by months end.
Page 30 of 31
Down 1 operator due to retirement
Water Utility
Hydrant flushing completed
Commercial Meter replacements
400 residential meter replacements
On going hydrant repair throughout the Village
Valve exercising
Wastewater Utility
Wet Well cleaning
System Jetting area 3
Yard Waste upkeep/material processing
SSSA under DNR review letter forthcoming
Collection System Facilities Plan – Submitted to DNR on hold pending
SSSA
Main St. and Old Farm Facilities Plan – Submitted to DNR on hold pending
approval of the SSSA, and CSFP
Down 1 operator due to promotion
Page 31 of 31