Board of Public Works — Agenda Packet
Village of Jackson · Washington County · Board of Public Works · meeting of Nov 25, 2025 · Agenda packets
Open the original document More from Village of Jackson
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
November 25, 2025 Village of Jackson - Board of Public Works Meeting Agenda
VILLAGE OF JACKSON
BOARD OF PUBLIC WORKS MEETING AGENDA
Tuesday, November 25, 2025 at 6:00 PM
Jackson Municipal Complex
Village Board Room
N168W19851 Main Street
Jackson, WI 53037
1. Call to Order and Roll Call
2. Approval of Minutes for the Board of Public Works Meeting of October 28, 2025
3. Change Order #3 - 2025 Hickory Lane Reconstruction Project - Vinton Construction for an
increase in the amount of $1,046.51
4. Change Order #4 - Final - 2025 Ridgeway Drive and Chestnut Court Reconstruction Project
– Advanced Construction for an increase in the amount of $19,142.61
5. Pay Request #5 - 2025 Hickory Lane Reconstruction Project - Vinton Construction in the
amount of $293,286.04
6. Pay Request #6 - Final - 2025 Ridgeway Drive and Chestnut Court Reconstruction Project –
Advanced Construction in the amount of $44,697.88
7. Approving Completion of 2024 Wastewater Treatment Plant Tertiary Filters and UV
Disinfection Project and Authorizing Closure of the Clean Water Fund Loan
8. 2025-2026 Contract Amendment #3 - Gremmer and Associates in the amount of
$309,667.00
9. Director of Public Works Report
10. Citizens/Village Staff to address the Board of Public Works
11. Adjourn
Persons with disabilities requiring special accommodations for attendance at the meeting should contact the
Administration Department at the Jackson Municipal Complex at least one (1) business day prior to the
meeting.
It is possible that members of the Village Board may attend the above meeting. No action will be taken by any
governmental body at this meeting other than the governmental body specifically referred to in this meeting
notice. This notice is given so that members of the Village Board may attend the meeting without violating the
open meeting law.
Page 1 of 53
October 28, 2025 Village of Jackson - Board of Public Works Meeting Minutes
Page 1 of 3
VILLAGE OF JACKSON
BOARD OF PUBLIC WORKS MEETING
Tuesday, October 28, 2025 at 6:00 PM
Minutes
1. Call to Order and Roll Call
The meeting was called to order at 6:00 PM by Pres. Heckendorf.
Members Present: Pres. Heckendorf, Tr. Engelhardt, Tr. Kruepke, Jeff Mitchell, and Josh
S
andleback
Members Excused: Stephanie Egner
Members Absent: Ryan Ganshow
Staff Present: Police Chief and Interim Administrator Ryan Vossekuil, Public Works
Director Jack Straehler, and Clerk Jackie Schuh
2. Approval of Minutes for the Board of Public Works Meeting of September 30, 2025
The motion to approve Minutes for the Board of Public Works Meeting of September
30,
2025, w
as made by J. Mitchell and seconded by Tr. Engelhardt.
Vote: 5 ayes, 0 nays. Motion carried.
3. Change Order #2 - Final - 2024 Wastewater Treatment Plant Tertiary Filters and UV
Disinfection Project - J.H. Hassinger for a decrease in the amount of $8,470.66
The motion to recommend the Budget and Finance Committee and Village Board approve
Final Change Order #2 for the 2024 Wastewater Treatment Plan Tertiary Filters and UV
Disinfection Project to J.H. Hassinger for a decrease in the amount of $8,470.66 was made
by Tr. Engelhardt and seconded by Tr. Kruepke.
Vote: 5 ayes, 0 nays. Motion carried.
4. Pay Request #18 - 2024 Wastewater Treatment Plant Tertiary Filters and UV Disinfecti
on
P
roject - J.H. Hassinger in the amount of $28,036.59
The motion to recommend the Budget and Finance Committee and Village Board approve
Pay Request #18 for the Wastewater Treatment Plant Tertiary Filters and Disinfection
P
roject to J.H. Hassinger in the amount of $28,036.59 was made by Tr. Engelhardt and
s
econded by J. Mitchell.
V
ote: 5 ayes, 0 nays. Motion carried.
5. Pay Request #19 - Final - 2024 Wastewater Treatment Plant Tertiary Filters and UV
Disinfection Project - J.H. Hassinger in the amount of $230,930.58
The motion to recommend the Budget and Finance Committee and Village Board approve
Final Pay Request #19 for the Wastewater Treatment Plant Tertiary Filters and Disinfection
DRAFT
Page 2 of 53
October 28, 2025 Village of Jackson - Board of Public Works Meeting Minutes
Page 2 of 3
Project to J.H. Hassinger in the amount of $230,930.58 was made by Tr. Engelhardt and
seconded by J. Sandleback.
Director Straehler stated the preliminary numbers indicate the projected outcome of the
project to be $150,000.00 to $200,000.00 under budget.
Vote: 5 ayes, 0 nays. Motion carried.
6. Pay Request #4 - 2025 Hickory Lane Reconstruction Project - Vinton Construction in the
amount of $618,120.14
The motion to recommend the Budget and Finance Committee and Village Board approve
Pay Request #4 for the Hickory Lane Reconstruction Project to Vinton Construction in the
amount of $618,120.14 was made by Tr. Engelhardt and seconded by Tr. Kruepke.
Vote: 5 ayes, 0 nays. Motion carried.
7. Reimbursement Request #15 - 2024 Wastewater Treatment Plant Tertiary Filters and UV
Disinfection Project - Clean Water Fund Loan in the amount of $296,155.05
The motion to recommend the Budget and Finance Committee and Village Board approve
Reimbursement Request #15 for the 2024 Wastewater Treatment Plant Tertiary Filters and
UV Disinfection Project from the Clean Water Fund Loan in the amount of $296,155.05 was
made by Tr. Engelhardt and seconded by J. Mitchell.
Vote: 5 ayes, 0 nays. Motion carried.
8. Authorization to Increase Sewer Utility Rates Effective January 1, 2026
The motion to recommend the Budget and Finance Committee and Village Board approve an
18% increase in Sewer Utility Rates effective January 1, 2026, was made by Pres.
Heckendorf and seconded by Tr. Kruepke.
Pres. Heckendorf stated the increase is to keep the utility solvent.
Vote: 5 ayes, 0 nays. Motion carried.
9. Review 15-Year Capital Road Improvements (2026-2041)
Pres. Heckendorf announced the postponement of this item to the next regular meeting.
10. Director of Public Works Report
Director Straehler provided an overview of projects throughout the Village of Jackson.
Discussion topics included various landscape restoration issues and the placement of wood
and/or fiberglass utility poles. Tr. Engelhardt and Pres. Heckendorf complimented Director
Straehler on the successful completion of the Ridgeway Drive and Chestnut Court project
and his fiscal prudence.
The motion to place the October 2025 Director's Report on file was made by Pres.
Heckendorf and seconded by Tr. Kruepke.
DRAFT
Page 3 of 53
October 28, 2025 Village of Jackson - Board of Public Works Meeting Minutes
Page 3 of 3
Vote: 5 ayes, 0 nays. Motion carried.
11. Citizens/Village Staff to address the Board of Public Works
None.
12. Adjourn
The motion to adjourn the meeting was made by J. Mitchell and seconded by Tr. Engelhardt.
Vote: 5 ayes, 0 nays. Motion carried. The meeting adjourned at 6:24 PM.
Respectfully Submitted,
Jacqueline Schuh
Village Clerk
Village of Jackson
DRAFT
Page 4 of 53
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Change Order #3 – 2025 Hickory Lane Reconstruction Project – Vinton
Construction for an increase in the amount of $1,046.51
Meeting Date: November 25, 2025 - Board of Public Works
Background and Analysis:
This memo is to inform the Board of Change Order #3 associated with the 2025 Hickory
Lane Reconstruction Project.
This change order reflects necessary field modifications and unforeseen conditions
encountered during construction. A breakdown of the net cost adjustments is summarized
below:
• Additional $615.75 for additional stream substrate material required for the 60”
culvert per DNR permit specifications.
• Additional $2,649.50 for modifications to offset the 12” water main that was found to
be in conflict during construction.
• Additional $1,250.00 for installation of a turbidity barrier during construction.
• Reduction of $3,468.74 resulting from Vinton Construction’s request to utilize Village
of Jackson equipment and labor.
Funding for this Change Order will come from Account Numbers:
600-00-56700-400-000 (Capital Projects Repairs/Construction)
300-00-17600-000-380 (Sewer Construction Work)
200-00-18600-395-000 (Water Construction Work)
JS
Recommendation:
Board of Public Works recommends the Budget and Finance Committee and Village Board
approve Change Order #3 for an increase in the amount of $1,046.51 to Vinton
Construction.
Page 5 of 53
Page 6 of 53
Page 7 of 53
Page 8 of 53
Page 9 of 53
Page 10 of 53
Page 11 of 53
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Change Order #4 - Final - 2025 Ridgeway Drive and Chestnut Court
Reconstruction Project – Advanced Construction for an increase in the amount of
$19,142.61
Meeting Date: November 25, 2025 - Board of Public Works
Background and Analysis:
This memo is to inform the Board of Change Order #4 related to the Ridgeway Drive and
Chestnut Court Reconstruction Project.
This change order addresses necessary field modifications and revisions to material sizes
and quantities encountered during construction. It provides the final reconciliation of all
quantities associated with the project.
Funding for this Change Order will come from Account Numbers:
600-00-56700-400-000 (Capital Projects Repairs/Construction)
300-00-17600-000-380 (Sewer Construction Work)
200-00-18600-395-000 (Water Construction Work)
JS
Recommendation:
Board of Public Works recommends the Budget and Finance Committee and Village Board
approve Change Order #4 for an increase in the amount of $19,142.61 to Advanced
Construction.
Page 12 of 53
SECTION 00 63 63
CHANGE ORDER NO.: 4
Owner:
Engineer: Engineer's Project No.:
Contractor: Contractor's Project No.:
Project:
Contract Name:
Date Issued:
Description:
1 =
TOTAL =
Reason for Change Order:
a)
Attachments:
a)
Original Contract Price Original Contract Times:
Substantial completion (date):
$ Ready for Final Payment (date):
[Increase] from previous approved [Increase] from previous approved
Change Orders No. 1 to No. : Change Orders No. 1 to No. 3
Substantial Completion (days):
$ Ready for Final Payment (days):
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial completion (date):
$ Ready for Final Payment (date):
[Increase] this Change Order: [Increase][Decrease] this Change Order:
Substantial Completion (days):
$ Ready for Final Payment (days):
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial completion (date):
$ Ready for Final Payment (date):
Recommended by Engineer (if required) Accepted by Contractor
By:
Title:
Date:
Authorized by Owner Approved by Funding Agency (if applicable)
By:
Title:
Date:
$19,142.61
Effective Date of
Change Order:
Advance Construction
Cedar Corporation
Ridgeway Dr and Chestnut Ct
Reconstruction - REBID
November 4, 2025
05789-0020
November 4, 2025
The Contract is modified as follows upon execution of this Change Order:
FINAL
Village of Jackson
Ridgeway Dr and Chestnut Ct
Reconstruction - REBID
Owner's Project No.
ADD Reconciliation of Installed Quantities $19,142.61
3
119,295.07
19,142.61
1,755,738.12
14
September 15, 2025
September 12, 2025
CHANGE IN CONTRACT TIMES:CHANGE IN CONTRACT PRICE:
August 29, 2025
14
0
September 12, 2025
September 29, 2025
0
1,774,880.73
Senior Construction Manager
Change Order Item No. 1: Final Reconciliation of Installed Quantities (Extimated (Bid) Vs Installed)
11/4/2025
September 29, 2025
1,636,443.05
1) Change Order Item No. 1: Engineer's Unit Price Quantity Summary dated 10/20/25.
Project Manager
11/5/2025
Page 13 of 53
UNIT PRICE QUANTITY SUMMARY
Village of Jackson
Ridgeway Dr./Chestnut Ct. Reconst. REBID
Advance Construction
QUANTITIES VALUES
Installed Estimated Installed Estimated VS
Quantities VS Installed Values Installed
1 0 -1 -$ (2,000.00)$
2 53.01 -2.99 29,155.50$ (1,644.50)$
3 853.5 12.5 179,235.00$ 2,625.00$
4 147.58 147.58 24,424.49$ 24,424.49$
5 509.53 0.53 5,095.30$ 5.30$
6 1 0 500.00$ -$
7 341.5 -11.5 44,736.50$ (1,506.50)$
8 493 -7 81,345.00$ (1,155.00)$
9 1 0 2,562.00$ -$
10 1 0 4,580.00$ -$
11 264.66 235.66 52,932.00$ 47,132.00$
12 218.99 -203.01 16,862.23$ (15,631.77)$
13 3 0 25,560.00$ -$
14 396 0 2,772.00$ -$
15 490 0 6,370.00$ -$
16 2 0 2,000.00$ -$
17 1192.83 572.83 71,569.80$ 34,369.80$
18 2400 0 52,800.00$ -$
19 275.09 -50.91 962.82$ (178.19)$
20 4003 0 2,401.80$ -$
21 8656 1139 57,129.60$ 7,517.40$
22 2 0 3,000.00$ -$
23 1710 0 9,405.00$ -$
24 1710 0 34,200.00$ -$
25 704 0 422.40$ -$
26 2790.25 -488.75 23,438.10$ (4,105.50)$
27 567 0 2,835.00$ -$
28 340 -3 2,856.00$ (25.20)$
29 375.5 -21.5 1,858.73$ (106.43)$
30 374 -23 12,342.00$ (759.00)$
31 5 0 37.50$ -$
32 151.6 -88.4 3,486.80$ (2,033.20)$
33 266.95 -213.05 4,271.20$ (3,408.80)$
34 1896.72 -59.28 30,347.52$ (948.48)$
35 580.72 -52.28 52,409.98$ (4,718.27)$
36 322.68 -18.32 30,977.28$ (1,758.72)$
37 2 0 600.00$ -$
38 1 0 80,000.00$ -$
39 5 0 5,000.00$ -$
40 1 0 13,000.00$ -$
41 10 0 650.00$ -$
A1-1 71.83 -2.17 41,661.40$ (1,258.60)$
A1-2 465 -3 120,900.00$ (780.00)$
A1-3 0 0 -$ -$
A1-4 466 -20 76,890.00$ (3,300.00)$
A1-5 0 -1 -$ (7,035.00)$
A1-6 43.33 6.33 8,666.00$ 1,266.00$
A1-7 141.3 43.3 10,880.10$ 3,334.10$
A1-8 1 0 8,520.00$ -$
A1-9 1 0 1,000.00$ -$
A1-10 1 0 3,500.00$ -$
A1-11 16.75 -9.25 1,926.25$ (1,063.75)$
A1-12 361 -232 21,660.00$ (13,920.00)$
A1-13 3 1 1,500.00$ 500.00$
A1-14 960 10 21,120.00$ 220.00$
A1-15 223 12 825.10$ 44.40$
A1-16 2376 0 1,425.60$ -$
Storm Lateral Cleanout
Common Excavation (Including Pavement Removal)
Saw Cutting Roadway & Driveways
Remove Concrete Sidewalk
1 1/4" Water Service & Curb Stop & Box (3 Units)
Hydrant Assembly
Salvage Hydrant and Valve
Nyloplast Yard Inlet Manhole with Grate
12" Dia PVC Storm Sewer Pipe
4" Dia. Storm Lateral (5 Units)
48" Sanitary Manhole (4 Units)
8" PVC Sanitary Sewer Pipe
6" PVC Sanitary Sewer Lateral (7 Units)
12" PVC Water Main Pipe
8" Tapping Gate Valve
4" PVC Water Service & Valve & Box (2 Unit)
10/20/2025
7" Concrete Driveway
Remove Asphalt Driveway
Asphalt Driveway
Gravel Driveway
Excavation Below Subgrade (EBS)
4" Concrete Sidewalk
Curb Ramp Type 1
Remove Curb & Gutter
30" Curb & Gutter Type "D"
Remove Concrete Driveway Apron
7" Concrete Driveway Apron & Sidewalk
Abandon 12" Water Main
Salvage Hydrant and Valve
4" Dia. Storm Lateral (10 Units)
Common Excavation (Including Pavement Removal)
Client
Project
Contractor
EBS Backfill 1 1/4" Dense
1 1/4" Dense Crushed Aggregate Base Course
Lower Layer HMA Pavement 3-1/4"
Upper Layer HMA Pavement 1-3/4"
Relocate Sign
Traffic Control
Remove Trees
Lawn Restoration
Inlet Protection
Remove Concrete Driveway
ESTIMATED VS INSTALLED
Bid Items
Sanitary Manhole Chimney & Casting Replacement
48" Sanitary Manhole (4 Units)
Project No.
Date
05789-0020
Saw Cutting Roadway & Driveways
Remove Concrete Sidewalk
8" Gate Valve
12" Gate Valve
4" PVC Water Service & Valve & Box (1 Unit)
1 1/4" Water Service & Curb Stop & Box (13 Units)
Hydrant Assembly
Abandon 6" Water Main
8" PVC Sanitary Sewer Pipe
6" PVC Sanitary Sewer Lateral (14 Units)
Abandon 8" Sanitary Sewer
Sanitary Lateral Cleanout
8" PVC Water Main Pipe
12" PVC Water Main Pipe
Community Infrastructure • Architecture • Environmental Services
Cedarburg • Green Bay • Madison • Menomonie 1 of 3
Page 14 of 53
UNIT PRICE QUANTITY SUMMARY
Village of Jackson
Ridgeway Dr./Chestnut Ct. Reconst. REBID
Advance Construction
QUANTITIES VALUES
Installed Estimated Installed Estimated VS
Quantities VS Installed Values Installed
10/20/2025
Client
Project
Contractor
ESTIMATED VS INSTALLED
Bid Items
Sanitary Manhole Chimney & Casting Replacement
Project No.
Date
05789-0020
Community Infrastructure • Architecture • Environmental Services
A1-17 2422 -1656 15,985.20$ (10,929.60)$
A1-18 1 0 1,500.00$ -$
A1-19 905 0 4,977.50$ -$
A1-20 924 19 18,480.00$ 380.00$
A1-21 348 0 208.80$ -$
A1-22 2547.97 1473.97 21,402.95$ 12,381.35$
A1-23 33 0 165.00$ -$
A1-24 12 0 100.80$ -$
A1-25 99 -3 490.05$ (14.85)$
A1-26 56 -130 1,848.00$ (4,290.00)$
A1-27 16 0 120.00$ -$
A1-28 23.42 -76.58 538.66$ (1,761.34)$
A1-29 46.84 -153.16 749.44$ (2,450.56)$
A1-30 1267.99 227.99 20,287.84$ 3,647.84$
A1-31 312.7 -24.3 28,221.18$ (2,193.08)$
A1-32 173.75 -7.25 16,680.00$ (696.00)$
A1-33 1 0 16,000.00$ -$
A1-34 1 -2 1,000.00$ (2,000.00)$
A1-35 1 0 5,500.00$ -$
A1-36 4 0 260.00$ -$
A2-1 1 0 3,500.00$ -$
A2-2 0 0 -$ -$
A2-3 1 0 500.00$ -$
A2-4 1 0 500.00$ -$
A2-5 50 0 1,300.00$ -$
A2-6 0 0 -$ -$
A2-7 0 -20 -$ (150.00)$
A2-8 1 0 200.00$ -$
A2-9 0 0 -$ -$
A2-10 2 0 130.00$ -$
Bid Item Totals = 1,455,251.40$ 46,025.35$
CO1 23 8 11,500.00$ 4,000.00$
CO1 14 -2 (1,022.00)$ 146.00$
CO1 1 0 450.00$ -$
CO1 202.17 -17.83 13,141.05$ (1,158.95)$
CO1 2 1 1,000.00$ 500.00$
CO1 2 0 1,676.00$ -$
CO1 4 -3 3,600.00$ (2,700.00)$
CO1 7 0 14,000.00$ -$
CO1 2 0 4,000.00$ -$
CO1 1 0 3,000.00$ -$
CO1 81 -7 5,265.00$ (455.00)$
CO1 1 0 275.00$ -$
CO1 1 0 2,000.00$ -$
CO1 1366 -194 191,240.00$ (27,160.00)$
CO1 2 0 7,600.00$ -$
CO1 1 0 3,292.32$ -$
CO1 1 0 8,000.00$ -$
CO2 1087 37 (2,174.00)$ (74.00)$
CO2 34 0 3,230.00$ -$
CO2 1 0 7,040.00$ -$
CO2 1 0 5,280.00$ -$
CO3 78 0 16,380.00$ -$
Temporary Water Service Connections - Ridgeway Dr.
CREDIT Sanitary Lateral Pipe Bursting (6" Vs 4" Material Credit)
ADD 34 Lineal Feet of 12” Dia RCP Storm Sewer Pipe
ADD Lump Sum Investingation of Existing Water Main Location 6/11/25
ADD Lump Sum Cutting & Capping Existing 12" Water Main 6/12/25
6" PVC Water Service & Valve & Box (1 Unit)
ADD 88 LF 6" Dia PVC Storm Sewer Pipe @ 65.00/LF
ADD 1 EA 12"x 6" Reducer Fitting @ $275.00 EA
ADD Lump Sum Lawn Restoration @ $2,000.00
ADD 1560 Lineal Feet 6" HDPE Pipe Bursted Sanitary Sewer Lateral @
ADD 2 EA 2'x 3' Catch Basins w/ 3067 Castings @ $3,800.00 EA
Site Investigation - Existing WTM Location - Ridgeway Dr
#REF!
Gravel Driveway Restoration
Traffic Control
Lawn Restoration
Inlet Protection
Nyloplast Yard Inlet Manhole with Grate
12" Dia PVC Storm Sewer Pipe
Storm Cleanout
Connection to Existing Catch Basin
Remove & Replace Concrete Sidewalk
Remove & Replace Curb & Gutter
Lower Layer HMA Pavement 3-1/4"
Upper Layer HMA Pavement 1-3/4"
Traffic Control
Remove Trees
Lawn Restoration
Inlet Protection
Remove Asphalt Driveway
Asphalt Driveway
Gravel Driveway
Excavation Below Subgrade (EBS)
EBS Backfill 1 1/4" Dense
1 1/4" Dense Crushed Aggregate Base Course
Remove Curb & Gutter
30" Curb & Gutter Type "D"
Remove Concrete Driveway Apron
7" Concrete Driveway Apron & Sidewalk
Remove Concrete Driveway
7" Concrete Driveway
4" Concrete Sidewalk
Curb Ramp Type 1
Storm Lateral/Sump Discharge Connections
Delete Water Service Curb Box
ADD 1 EACH 4” Dia Storm Lateral Cleanout
ADD 220 Lineal Feet of 6” Dia Storm Lateral
ADD 1 EACH 6” Dia Storm Lateral Cleanout
Replace Storm Catch Basin 2’x3’ w/ Casting & Chimney (Salvage Casting
Replace Catch Basin Castings 3070 (Salvage Casting for Owner)
Catch Basin Chimney Reconstruction 2' Round
Catch Basin Chimney Reconstruction 2'x3'
CHANGE ORDER ITEMS: NEW ITEMS
Cedarburg • Green Bay • Madison • Menomonie 2 of 3
Page 15 of 53
UNIT PRICE QUANTITY SUMMARY
Village of Jackson
Ridgeway Dr./Chestnut Ct. Reconst. REBID
Advance Construction
QUANTITIES VALUES
Installed Estimated Installed Estimated VS
Quantities VS Installed Values Installed
10/20/2025
Client
Project
Contractor
ESTIMATED VS INSTALLED
Bid Items
Sanitary Manhole Chimney & Casting Replacement
Project No.
Date
05789-0020
Community Infrastructure • Architecture • Environmental Services
CO3 119.17 0.17 13,466.21$ 19.21$
CO3 143 0 6,327.75$ -$
CO3 24 0 1,062.00$ -$
0 0 0 -$ -$
0 0 0 -$ -$
0 0 0 -$ -$
1,774,880.73$ 19,142.61$
0
2" Water Service & Curb Stop & Box (3 Units)
Remove/Replace Concrete Curb & Gutter (Driveway Corrections)
Remove/Replace Concrete Curb & Gutter (Owner Changes)
0
0
0
FINAL PROJECT TOTALS =
Cedarburg • Green Bay • Madison • Menomonie 3 of 3
Page 16 of 53
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Pay Request #5 – 2025 Hickory Lane Reconstruction Project - Vinton
Construction in the amount of $293,286.04
Meeting Date: November 25, 2025 – Board of Public Works
Background and Analysis:
This memo is to inform the Board of Pay Request #5 from Vinton Construction in the
amount of $293,286.04 for work completed on the Hickory Lane Reconstruction Project.
The work has been reviewed and verified for accuracy and completion in accordance with
the project contract documents and schedule.
Funding for this payment will come from Account Numbers:
600-00-56700-400-000 (Capital Projects Repairs/Construction) $97,762.01
300-00-17600-000-380 (Sewer Construction Work) $97,762.01
200-00-18600-395-000 (Water Construction Work) $97,762.02
If you have any questions, please let me know.
JS
Recommendation:
Board of Public Works recommends the Budget and Finance Committee and Village Board
approve Pay Request #5 for Vinton Construction in the amount of $293,286.04.
Page 17 of 53
November 18, 2025
Village of Jackson
W194 N16660 Eagle Drive
Jackson, WI 53037
Atte
ntion: Jack Straehler
Director of Public Works
Subj
ect: Project: VOJ 25-01
Hickory Lane Reconstruction
Pay Request #5
Dear
Mr. Straehler:
Enc
losed you will find Pay Request #5 for the Hickory Lane Reconstruction project in the Village
of Jackson. The total amount, due to the contractor, included a retainage reduction to equal 2% of
the total Work completed upon Substantial Completion. This is per Article 6.02.A.2 Progress
Payments; Retainage, of Contract Document 00500, Agreement:
Wor
k completed, Pay Request #5 = $281,088.36
Retainage Reduction, Pay Request #5 = $12,197.68
Amount due to Contractor, Pay Request #5 = $293,286.04
If
you have any questions or comments, please contact me at (262) 343-0351.
Si
ncerely,
Et
han Wedemayer
Project Inspector
Gremmer & Associates, Inc.
Page 18 of 53
11/18/2025
$293,286.04
Page 19 of 53
Page 1 of 4Unit Cost Breakdown Project: Jackson Hickory Lane VOJ-25-01
Contractor: Vinton Construction Company
Application Date: 11/13/25
VCC Job# 25057 Payment Application #: 5 REVISED
ITEM DESCRIPTION OF WORK Scheduled Vs. Percent
NO. Actual Complete
Quantity UOM Unit Price Amount
Quantity Amount Quantity Amount Quantity Amount Add(Deduct)
Section 100 Roadway Items
1 100-01 Clearing & Grubbing 1 LS $ 10,000.00 $ 10,000.00 1.00 10,000.00$ - -$ 1.00 10,000.00$ -$ 100.0%
2 100-02 Removing Curb & Gutter 665 LF $ 5.00 $ 3,325.00 665.00 3,325.00$ - -$ 665.00 3,325.00$ -$ 100.0%
3 100-03 Removing Concrete Driveways and Sidewalk 740 SY $ 6.30 $ 4,662.00 603.00 3,798.90$ - -$ 603.00 3,798.90$ 863.10$ 81.5%
4 100-04 Removing Guardrail 311 LF $ 2.00 $ 622.00 311.00 622.00$ - -$ 311.00 622.00$ -$ 100.0%
5 100-05 Excavation Common 7,315 CY $ 24.09 $ 176,218.35 7,315.00 176,218.35$ - -$ 7,315.00 176,218.35$ -$ 100.0%
6 100-06 Excavation Below Subgrade 1,508 CY $ 18.25 $ 27,521.00 - -$ - -$ - -$ 27,521.00$ 0.0%
7 100-07 Base Aggregate Dense 3/4-Inch 470 TON $ 34.20 $ 16,074.00 384.00 13,132.80$ 228.00 7,797.60$ 612.00 20,930.40$ (4,856.40)$ 130.2%
8 100-08 Base Aggregate Dense 1 1/4-Inch 8,475 TON $ 16.55 $ 140,261.25 7,498.00 124,091.90$ 128.00 2,118.40$ 7,626.00 126,210.30$ 14,050.95$ 90.0%
9 100-09 Base Aggregate Dense 3-Inch 3,320 TON $ 19.47 $ 64,640.40 - -$ - -$ - -$ 64,640.40$ 0.0%
10 100-10 Concrete Driveway 7-Inch 115 SY $ 72.00 $ 8,280.00 125.00 9,000.00$ - -$ 125.00 9,000.00$ (720.00)$ 108.7%
11 100-11 Drilled Tie Bars 52 EA $ 10.00 $ 520.00 39.00 390.00$ 14.00 140.00$ 53.00 530.00$ (10.00)$ 101.9%
12 100-12 HMA Pavement 3 LT 58-28 S 2,615 TON $ 65.80 $ 172,067.00 1,835.00 120,743.00$ 903.00 59,417.40$ 2,738.00 180,160.40$ (8,093.40)$ 104.7%
13 100-13 HMA Pavement 4 LT 58-28 S 1,745 TON $ 71.80 $ 125,291.00 1,405.00 100,879.00$ 607.00 43,582.60$ 2,012.00 144,461.60$ (19,170.60)$ 115.3%
14 100-14 Asphaltic Surface Driveways 9 TON $ 120.00 $ 1,080.00 11.00 1,320.00$ - -$ 11.00 1,320.00$ (240.00)$ 122.2%
15 100-15 Concrete Curb & Gutter 24-Inch 335 LF $ 33.75 $ 11,306.25 157.00 5,298.75$ 100.00 3,375.00$ 257.00 8,673.75$ 2,632.50$ 76.7%
16 100-16 Concrete Curb & Gutter 30-Inch Type D 835 LF $ 33.75 $ 28,181.25 498.00 16,807.50$ 438.00 14,782.50$ 936.00 31,590.00$ (3,408.75)$ 112.1%
17 100-17 Concrete Sidewalk 4-Inch 9,580 SF $ 6.50 $ 62,270.00 7,544.00 49,036.00$ 258.00 1,677.00$ 7,802.00 50,713.00$ 11,557.00$ 81.4%
18 100-18 Concrete Sidewalk 6-Inch 965 SF $ 7.50 $ 7,237.50 1,048.00 7,860.00$ 236.00 1,770.00$ 1,284.00 9,630.00$ (2,392.50)$ 133.1%
19 100-19 Curb Ramp Detectable Warning Field Natural Patina 190 SF $ 28.00 $ 5,320.00 150.00 4,200.00$ 40.00 1,120.00$ 190.00 5,320.00$ -$ 100.0%
20 100-20 Mobilization 1 EA $ 95,500.00 $ 95,500.00 0.85 81,175.00$ 0.15 14,325.00$ 1.00 95,500.00$ -$ 100.0%
21 100-21 Silt Fence 3,515 LF $ 2.05 $ 7,205.75 3,435.00 7,041.75$ - -$ 3,435.00 7,041.75$ 164.00$ 97.7%
22 100-22 Temporary Ditch Checks 72 LF $ 8.00 $ 576.00 72.00 576.00$ - -$ 72.00 576.00$ -$ 100.0%
23 100-23 Culvert Pipe Checks 42 EA $ 25.00 $ 1,050.00 4.00 100.00$ 38.00 950.00$ 42.00 1,050.00$ -$ 100.0%
24 100-24 Inlet Protection Type B 20 EA $ 70.00 $ 1,400.00 20.00 1,400.00$ - -$ 20.00 1,400.00$ -$ 100.0%
25 100-25 Inlet Protection Type C 25 EA $ 73.00 $ 1,825.00 25.00 1,825.00$ - -$ 25.00 1,825.00$ -$ 100.0%
26 100-26 Topsoil, Seed, Fertilizer, and Mulch 10,000 SY $ 6.59 $ 65,900.00 - -$ 7,840.00 51,665.60$ 7,840.00 51,665.60$ 14,234.40$ 78.4%
27 100-27 Topsoil, Seed, Fertilizer, and Erosion Mat 1,100 SY $ 9.99 $ 10,989.00 - -$ 3,160.00 31,568.40$ 3,160.00 31,568.40$ (20,579.40)$ 287.3%
28 100-28 Riprap Medium w/ Geotextile Fabric Type HR 30 CY $ 120.00 $ 3,600.00 45.00 5,400.00$ 4.00 480.00$ 49.00 5,880.00$ (2,280.00)$ 163.3%
Previous Request This Request To Date
Scheduled- Work Completed Total Completed/Stored
Page 20 of 53
Page 2 of 4Unit Cost Breakdown Project: Jackson Hickory Lane VOJ-25-01
Contractor: Vinton Construction Company
Application Date: 11/13/25
VCC Job# 25057 Payment Application #: 5 REVISED
ITEM DESCRIPTION OF WORK Scheduled Vs. Percent
NO. Actual Complete
Quantity UOM Unit Price Amount
Quantity Amount Quantity Amount Quantity Amount Add(Deduct)
Previous Request This Request To Date
Scheduled- Work Completed Total Completed/Stored
29 100-29 Geotextile Fabric Type SAS 4,524 SY $ 1.75 $ 7,917.00 - -$ - -$ - -$ 7,917.00$ 0.0%
30 100-30 Traffic Control 1 LS $ 6,000.00 $ 6,000.00 0.85 5,100.00$ 0.15 900.00$ 1.00 6,000.00$ -$ 100.0%
31 100-31 Permanent Signing 1 LS $ 2,300.00 $ 2,300.00 - -$ 1.00 2,300.00$ 1.00 2,300.00$ -$ 100.0%
32 100-32 Marking Line Epoxy 4-Inch 13,795 LF $ 0.63 $ 8,690.85 - -$ 13,795.00 8,690.85$ 13,795.00 8,690.85$ -$ 100.0%
33 100-33 Marking Stop Line Epoxy 18-Inch 150 LF $ 13.50 $ 2,025.00 - -$ 150.00 2,025.00$ 150.00 2,025.00$ -$ 100.0%
34 100-34 Marking Crosswalk Epoxy Transverse Line 6-Inch 725 LF $ 10.50 $ 7,612.50 - -$ 725.00 7,612.50$ 725.00 7,612.50$ -$ 100.0%
35 100-35 Sawing Asphalt 468 LF $ 4.00 $ 1,872.00 483.00 1,932.00$ - -$ 483.00 1,932.00$ (60.00)$ 103.2%
36 100-36 Sawing Concrete 124 LF $ 5.00 $ 620.00 74.00 370.00$ - -$ 74.00 370.00$ 250.00$ 59.7%
37 100-37 Remove Fallen Trees from Cedar Creek 1 LS $ 5,000.00 $ 5,000.00 1.00 5,000.00$ - -$ 1.00 5,000.00$ -$ 100.0%
Section 200 Storm Sewer Items
38 200-01 Removing Manholes 20 EA $ 515.00 $ 10,300.00 6.00 3,090.00$ - -$ 6.00 3,090.00$ 7,210.00$ 30.0%
39 200-02 Removing Inlets 13 EA $ 305.00 $ 3,965.00 26.00 7,930.00$ - -$ 26.00 7,930.00$ (3,965.00)$ 200.0%
40 200-03 Removing Storm Sewer 3,207 LF $ 29.00 $ 93,003.00 2,848.00 82,592.00$ 63.00 1,827.00$ 2,911.00 84,419.00$ 8,584.00$ 90.8%
41 200-04 Abandoning Storm Sewer 40 CY $ 255.00 $ 10,200.00 40.00 10,200.00$ 27.00 6,885.00$ 67.00 17,085.00$ (6,885.00)$ 167.5%
42
200-05 Apron Endwalls for Culvert Pipe Reinforced Concrete
15-Inch 2 EA $ 1,225.00 $ 2,450.00 2.00 2,450.00$ - -$ 2.00 2,450.00$ -$ 100.0%
43
200-06 Apron Endwalls for Culvert Pipe Reinforced Concrete
18-Inch 1 EA $ 1,515.00 $ 1,515.00 1.00 1,515.00$ - -$ 1.00 1,515.00$ -$ 100.0%
44
200-07 Apron Endwalls for Culvert Pipe Reinforced Concrete
24-Inch W/ Pipe Grate 1 EA $ 3,565.00 $ 3,565.00 1.00 3,565.00$ - 1.00 3,565.00$ -$ 100.0%
45
200-08 Apron Endwalls for Culvert Pipe Reinforced Concrete
60-Inch 1 EA $ 4,060.00 $ 4,060.00 1.00 4,060.00$ - -$ 1.00 4,060.00$ -$ 100.0%
46
200-09 Apron Endwalls for Culvert Pipe Reinforced Concrete
Horizontal Elliptical 38x60-Inch W/ Pipe Grate 1 EA $ 6,545.00 $ 6,545.00 1.00 6,545.00$ - -$ 1.00 6,545.00$ -$ 100.0%
47 200-10 Concrete Masonry Endwall 1 EA $ 17,678.00 $ 17,678.00 1.00 17,678.00$ - -$ 1.00 17,678.00$ -$ 100.0%
48
200-11 Storm Sewer Pipe Reinforced Concrete Class III 42-
Inch 310 LF $ 194.50 $ 60,295.00 310.00 60,295.00$ - -$ 310.00 60,295.00$ -$ 100.0%
49
200-12 Storm Sewer Pipe Reinforced Concrete Class III 48-
Inch 325 LF $ 240.00 $ 78,000.00 295.00 70,800.00$ 34.00 8,160.00$ 329.00 78,960.00$ (960.00)$ 101.2%
50
200-13 Storm Sewer Pipe Reinforced Concrete Class III 60-
Inch 60 LF $ 356.95 $ 21,417.00 60.00 21,417.00$ - -$ 60.00 21,417.00$ -$ 100.0%
51
200-14 Storm Sewer Pipe Reinforced Concrete Class IV 12-
Inch 34 LF $ 84.00 $ 2,856.00 33.00 2,772.00$ - -$ 33.00 2,772.00$ 84.00$ 97.1%
52
200-15 Storm Sewer Pipe Reinforced Concrete Class IV 15-
Inch 61 LF $ 84.50 $ 5,154.50 55.00 4,647.50$ - -$ 55.00 4,647.50$ 507.00$ 90.2%
53
200-16 Storm Sewer Pipe Reinforced Concrete Class IV 18-
Inch 207 LF $ 89.60 $ 18,547.20 202.00 18,099.20$ - -$ 202.00 18,099.20$ 448.00$ 97.6%
54
200-17 Storm Sewer Pipe Reinforced Concrete Class IV 24-
Inch 43 LF $ 135.00 $ 5,805.00 44.00 5,940.00$ - -$ 44.00 5,940.00$ (135.00)$ 102.3%
55
200-18 Storm Sewer Pipe Reinforced Concrete Class IV 48-
Inch 242 LF $ 278.00 $ 67,276.00 228.00 63,384.00$ - -$ 228.00 63,384.00$ 3,892.00$ 94.2%
Page 21 of 53
Page 3 of 4Unit Cost Breakdown Project: Jackson Hickory Lane VOJ-25-01
Contractor: Vinton Construction Company
Application Date: 11/13/25
VCC Job# 25057 Payment Application #: 5 REVISED
ITEM DESCRIPTION OF WORK Scheduled Vs. Percent
NO. Actual Complete
Quantity UOM Unit Price Amount
Quantity Amount Quantity Amount Quantity Amount Add(Deduct)
Previous Request This Request To Date
Scheduled- Work Completed Total Completed/Stored
56
200-19 Storm Sewer Pipe Reinforced Concrete Horizontal
Elliptical Class HE-IV 38x60-Inch 426 LF $ 357.00 $ 152,082.00 420.00 149,940.00$ - -$ 420.00 149,940.00$ 2,142.00$ 98.6%
57 200-20 Storm Sewer Pipe Class III-A 12-Inch 186 LF $ 87.35 $ 16,247.10 190.00 16,596.50$ - -$ 190.00 16,596.50$ (349.40)$ 102.2%
58 200-21 Storm Sewer Pipe Class III-A 15-Inch 188 LF $ 76.30 $ 14,344.40 198.00 15,107.40$ - -$ 198.00 15,107.40$ (763.00)$ 105.3%
59 200-22 Storm Sewer Pipe Class III-A 18-Inch 152 LF $ 90.85 $ 13,809.20 137.00 12,446.45$ - -$ 137.00 12,446.45$ 1,362.75$ 90.1%
60 200-23 Storm Sewer Pipe Class III-A 24-Inch 506 LF $ 113.00 $ 57,178.00 506.00 57,178.00$ - -$ 506.00 57,178.00$ -$ 100.0%
61 200-24 Storm Sewer Pipe Class III-A 30-Inch 25 LF $ 109.20 $ 2,730.00 24.00 2,620.80$ - -$ 24.00 2,620.80$ 109.20$ 96.0%
62 200-25 Storm Sewer Pipe Class III-A 36-Inch 576 LF $ 130.00 $ 74,880.00 582.00 75,660.00$ - -$ 582.00 75,660.00$ (780.00)$ 101.0%
63 200-26 Storm Sewer Pipe PVC 4-Inch 49 LF $ 35.00 $ 1,715.00 691.00 24,185.00$ - -$ 691.00 24,185.00$ (22,470.00)$ 1410.2%
64 200-27 Storm Sewer Pipe PVC 6-Inch 12 LF $ 35.00 $ 420.00 15.00 525.00$ - -$ 15.00 525.00$ (105.00)$ 125.0%
65 200-28 Storm Sewer Pipe PVC 15-Inch 7 LF $ 127.00 $ 889.00 - -$ - -$ - -$ 889.00$ 0.0%
66 200-29 Storm Sewer Pipe PVC 18-Inch 5 LF $ 155.00 $ 775.00 6.00 930.00$ - -$ 6.00 930.00$ (155.00)$ 120.0%
67 200-30 Catch Basins 4-FT Diameter w/ Casting 6 EA $ 3,820.00 $ 22,920.00 7.00 26,740.00$ - -$ 7.00 26,740.00$ (3,820.00)$ 116.7%
68 200-31 Catch Basins 5-FT Diameter w/ Casting 1 EA $ 5,870.00 $ 5,870.00 1.00 5,870.00$ - -$ 1.00 5,870.00$ -$ 100.0%
69 200-32 Catch Basins 2.5x3-FT w/ Casting 13 EA $ 3,670.00 $ 47,710.00 12.00 44,040.00$ - -$ 12.00 44,040.00$ 3,670.00$ 92.3%
70 200-33 Manholes 4-FT Diameter w/ Casting 6 EA $ 3,995.00 $ 23,970.00 6.00 23,970.00$ - -$ 6.00 23,970.00$ -$ 100.0%
71 200-34 Manholes 5-FT Diameter w/ Casting 1 EA $ 5,961.00 $ 5,961.00 1.00 5,961.00$ - -$ 1.00 5,961.00$ -$ 100.0%
72 200-35 Manholes 6-FT Diameter w/ Casting 3 EA $ 7,414.00 $ 22,242.00 3.00 22,242.00$ - -$ 3.00 22,242.00$ -$ 100.0%
73 200-36 Manholes 7-FT Diameter w/ Casting 3 EA $ 9,734.00 $ 29,202.00 3.00 29,202.00$ - -$ 3.00 29,202.00$ -$ 100.0%
74 200-37 Manholes 8-FT Diameter w/ Casting 3 EA $ 12,662.00 $ 37,986.00 3.00 37,986.00$ - -$ 3.00 37,986.00$ -$ 100.0%
75 200-38 Inlets Median 2 Grate w/ Casting 2 EA $ 4,172.00 $ 8,344.00 1.00 4,172.00$ 1.00 4,172.00$ 2.00 8,344.00$ -$ 100.0%
76 200-39 Bulkhead Storm Sewer 15-Inch 4 EA $ 175.00 $ 700.00 2.00 350.00$ - -$ 2.00 350.00$ 350.00$ 50.0%
77 200-40 Connect to Existing Storm Sewer Lateral 3 EA $ 195.00 $ 585.00 23.00 4,485.00$ - -$ 23.00 4,485.00$ (3,900.00)$ 766.7%
78 200-41 Connect to Existing Storm Sewer Structure 1 EA $ 325.00 $ 325.00 1.00 325.00$ - -$ 1.00 325.00$ -$ 100.0%
79 200-42 Connect to Existing Storm Sewer Pipe 2 EA $ 850.00 $ 1,700.00 2.00 1,700.00$ - -$ 2.00 1,700.00$ -$ 100.0%
Section 300 Water Main Items
80 300-01 Connect to Existing Water Main Pipe 2 EA $ 2,635.00 $ 5,270.00 7.00 18,445.00$ - -$ 7.00 18,445.00$ (13,175.00)$ 350.0%
81 300-02 Remove and Replace Water Service Curb Box 2 EA $ 1,170.00 $ 2,340.00 2.00 2,340.00$ - -$ 2.00 2,340.00$ -$ 100.0%
82 300-03 Water Main PVC 8-Inch 16 LF $ 72.00 $ 1,152.00 66.50 4,788.00$ - -$ 66.50 4,788.00$ (3,636.00)$ 415.6%
Page 22 of 53
Page 4 of 4Unit Cost Breakdown Project: Jackson Hickory Lane VOJ-25-01
Contractor: Vinton Construction Company
Application Date: 11/13/25
VCC Job# 25057 Payment Application #: 5 REVISED
ITEM DESCRIPTION OF WORK Scheduled Vs. Percent
NO. Actual Complete
Quantity UOM Unit Price Amount
Quantity Amount Quantity Amount Quantity Amount Add(Deduct)
Previous Request This Request To Date
Scheduled- Work Completed Total Completed/Stored
83 300-04 Water Service Pipe 1-Inch 42 LF $ 95.00 $ 3,990.00 - -$ - -$ - -$ 3,990.00$ 0.0%
84 300-05 Water Gate Valve 8-Inch 2 EA $ 3,080.00 $ 6,160.00 2.00 6,160.00$ - -$ 2.00 6,160.00$ -$ 100.0%
85 300-06 Adjusting Water Valve 17 EA $ 300.00 $ 5,100.00 9.00 2,700.00$ 9.00 2,700.00$ 18.00 5,400.00$ (300.00)$ 105.9%
86 300-07 Offset Water Main 4 EA $ 7,950.00 $ 31,800.00 5.00 39,750.00$ - -$ 5.00 39,750.00$ (7,950.00)$ 125.0%
Section 400 Sanitary Sewer Items
87 400-01 Sanitary Sewer Manhole Covers Type J-Special 13 EA $ 1,440.00 $ 18,720.00 13.00 18,720.00$ - -$ 13.00 18,720.00$ -$ 100.0%
88
400-02 Sanitary Sewer Manhole Covers Type J-Special -
Anchored 1 EA $ 1,540.00 $ 1,540.00 1.00 1,540.00$ - -$ 1.00 1,540.00$ -$ 100.0%
89 400-03 Reconstructing Sanitary Sewer Manhole 63 VF $ 450.00 $ 28,350.00 34.80 15,660.00$ - -$ 34.80 15,660.00$ 12,690.00$ 55.2%
90 400-04 Connect to Existing Sanitary Sewer Pipe 1 EA $ 1,325.00 $ 1,325.00 - -$ - -$ - -$ 1,325.00$ 0.0%
91 400-05 Sanitary Sewer PVC 12-Inch 5 LF $ 88.00 $ 440.00 - -$ - -$ - -$ 440.00$ 0.0%
Change Orders
CO1 Added Watermain Work @ Hickory Land & Eagle Drive 1 LS $ 39,952.00 $ 39,952.00 1.00 39,952.00$ - -$ 1.00 39,952.00$ -$ 100.0%
CO2 6" Natural Habitat Stream for 60" Cross Pipe 1 LS $ 5,950.00 $ 5,950.00 1.00 5,950.00$ - -$ 1.00 5,950.00$ -$ 100.0%
CO3.1 Non-Native Materal for Strem Substrate in 60" Culvert 1 LS $ 615.75 $ 615.75 - -$ 1.00 615.75$ 1.00 615.75$ -$ 100.0%
CO3.2 12" WM Offiset - Material Cost & 1 Hr Labor 1 LS $ 2,649.50 $ 2,649.50 - -$ 1.00 2,649.50$ 1.00 2,649.50$ -$ 100.0%
CO3.3 Turbidity Barrier installed 1 LS $ 1,250.00 $ 1,250.00 - -$ 1.00 1,250.00$ 1.00 1,250.00$ -$ 100.0%
CO3.4 Credit VOJ Hyrdro Vac Truck & Operator 1 LS $ (3,468.74) $ (3,468.74) - -$ 1.00 (3,468.74)$ 1.00 (3,468.74)$ -$ 100.0%
Total: 2,203,312.01$ 1,861,859.80$ 281,088.36$ 2,142,948.16$ 60,363.85$
Less: 5% Retainage up to first 50% of contract 55,056.64$ (12,197.68)$ 42,858.96$
Total: 1,806,803.16$ 293,286.04$ 2,100,089.20$
Amount Previously Requested 1,806,803.16$ -$ 1,806,803.16$
Amount DueThis Request -$ 293,286.04$ 293,286.04$
Page 23 of 53
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Pay Request #6 - Final - 2025 Ridgeway Drive and Chestnut Court
Reconstruction Project – Advanced Construction in the amount of $ 44,697.88
Meeting Date: November 25, 2025 – Board of Public Works
Background and Analysis:
This memo is to inform the Board of Pay Request #6 for Advanced Construction in the
amount of $44,697.88 for work completed on the Ridgeway Drive and Chestnut Court
Reconstruction Project.
The work has been reviewed and verified for accuracy and completion in accordance with
the project contract documents and schedule.
Funding for this payment will come from Account Numbers:
600-00-56700-400-000 (Capital Projects Repairs/Construction) $14,899.29
300-00-17600-000-380 (Sewer Construction Work) $14,899.29
200-00-18600-395-000 (Water Construction Work) $14,899.30
If you have any questions, please let me know.
JS
Recommendation:
Board of Public Works recommends the Budget and Finance Committee and Village Board
approve Pay Request #6 for Advanced Construction in the amount of $ 44,697.88.
Page 24 of 53
Cedarburg • Green Bay • Madison • Menomonie
Community Infrastructure • Architecture • Environmental Services
W61N497 Washington Avenue
Cedarburg, WI 53012
262-204-2360
www.cedarcorp.com
November 7, 2025
Village of Jackson
N168 W20733 Main Street
PO Box 637
Jackson, WI 53037
Attn: Mr. Jack Straehler II, Director of Public Works
Subject: Contractor’s Application for Payment No. 6 FINAL
Ridgeway Drive & Chestnut Court Reconstruction - REBID
Cedar Project No. 05789-0020
Dear Mr. Straehler:
We have reviewed the above referenced project and find it in order. Therefore, it is our recommendation that
the Village of Jackson issue final payment associated with the Ridgeway Drive & Chestnut Court Reconstruction -
REBID project.
Enclosed for your use in payment to Advance Construction in the amount of $44,697.88 is Contractor’s
Application for Payment No. 6 (Final). Also enclosed are the following documents:
• Final Lien Waivers
• Consent of Surety to Final Payment
• Contractor Certificate of Completed Operations Insurance
Following your review and approval, please complete the application for payment form within the areas reserved
for the Owner. Thereafter, retain one copy for your records, provide the second copy to the Contractor with
payment, and provide the third copy to our office.
Should you have any questions, please feel free to contact me at our Cedarburg office.
Sincerely,
CEDAR CORPORATION
Douglas T. Kroes
Senior Construction Manager
Encl: As Noted
Cc: Shane Kofler, Advance Construction
Page 25 of 53
11/7/25
Page 26 of 53
Page 27 of 53
Page 28 of 53
Page 29 of 53
Page 30 of 53
Page 31 of 53
Page 32 of 53
Page 33 of 53
Page 34 of 53
Page 35 of 53
Page 36 of 53
Page 37 of 53
Page 38 of 53
Page 39 of 53
Page 40 of 53
Page 41 of 53
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC
: Board of Public Works; Budget and Finance; Village Board
F
rom: Jack Straehler, Director of Public Works
S
ubject: Approving Completion of 2024 Wastewater Treatment Plant Tertiary Filters and
UV Disinfection Project and Authorizing Closure of the Clean Water Fund Loan
M
eeting Date: November 25, 2025 – Board of Public Works
Background and Analysis:
This memo is to inform the Board of the requirements issued by the Wisconsin Department
of Natural Resources (WDNR) related to the 2024 Wastewater Treatment Plant Tertiary
Filters and UV Disinfection Project.
As part of the project’s final closeout process, the WDNR requires formal acknowledgment
from the Village Board confirming the project and its completion. In addition, the final
closeout documents for the Clean Water Fund loan must be signed by the Village
Administrator.
If you have any questions, please let me know.
JS
Recommendation:
Board of Public
Works recommends the Budget and Finance Committee and Village Board
accept the completed 2024 Wastewater Treatment Plant Tertiary Filters and UV
Disinfection Project and authorize the Village Administrator to sign the documents for
closure of the clean water fund loan.
.
Page 42 of 53
Taking the lead in Washington County.
www.villageofjacksonwi.gov
The undersigned officials of the Village of Jackson (the "Municipality") hereby certify that, for all
expenditures made for construction of DNR Project No. 4266-04 (the "Project"), the
Municipality has met the prevailing wage rate requirements of the Davis-Bacon Act.
The Municipality further certifies that, after taking into account any national or project-specific
waivers approved by the U.S. Environmental Protection Agency, DNR Project No. 4266-04 has
met the requirements for the Use of American Iron and Steel contained in Section 608 of the
Federal Water Pollution Control Act, as amended.
The above certification is determined, after due and diligent inv estigation, to be true and
accurate to the best of my knowledge.
By: Dated as of:
Jen Heidtke, Village Administrator
Attest: Dated as of:
Jacqueline Schuh, Village Clerk
N168W19851
Main Street
Jackson, WI 53037
Phone: 262-677-9001
Fax: 262-677-1710
Page 43 of 53
State of Wisconsin
Department of Natural Resources
Bureau of Community Financial Assistance
101 S. Webster St., PO Box 7921
Madison WI 53707-7921
Phone (608) 266-7555
Fax (608) 267-0496
Environmental Improvement Fund (EIF)
Project Acceptance Certification
Form 8700-280 (R 1/11)
Notice: This form is authorized by ss. 281.58 and 281.61, Wis. Stats. Submittal to the Department of a completed form is mandatory for
all recipients of EIF loans. A separate form is required for each prime contractor. Failure to submit a completed form shall result in the
denial of final disbursement of loan funds.
Personally identifiable information provided on this form will be used to determine compliance with closeout procedures as outlined in
the Financial Assistance Agreement and may be made available upon request under Wisconsin's Open Records laws (ss. 19.32-19.39,
Wis. Stats.) and requirements.
Project Information
Municipality Name
Vi II age of Jackson
Prime Contractor
J. H. Hassinger, Inc.
Contract Number
2024 Improvements - Tettiary Filters and Disinfection
Upon final inspection and approval of all change order(s), all work performed by the awarded contractor(s) and subcontractor(s) (if any)
has been constructed according to the plans and specifications approved by the Department of Natural Resources (DNR).
DNR Plan and Specification Approval Number
S-2023-0758
Project Description
Date Approved
11/06/2023
Tertiary Filter Building- Construct an approximate 40" x 54' addition to the Village's existing Te1tiary Filter Building to
house new filter equipment. The building construction generally consists of masonry construction on a new concrete
foundation adjacent to the building. Work also includes renovations and modifications to the existing structure, as well as
HY AC and plumbing, and upgrades to the electrical systems in the building.
Remove the existing chemical disinfection equipment and modify the tank for a new UV disinfection system. The work
also includes covering the existing channels with aluminum grating, addition of a framed shelter, and electrical upgrades
associated with the new equipment.
Engineer Certification
On behalf of the engineering consulting firm contracted by the above named municipality, I hereby certify to the best of my knowledge
that the above mentioned project has been constructed and inspected to conform to the referenced specifications.
Name of Engineer
Gregory J. Droessler
Signature of Engineer
Name of Engineering Firm
Town and Country Engineering, Inc.
Date Signed
// 1<; t.o�
The above named municipality has accepted at its regular meeting of officials the above mentioned project from the contractor and
engineer.
Name of Authorized Representative
Jen Heidtke
Signature of Authorized Representative
Title
Village Administrator
Date Signed
Page 44 of 53
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: 2025-2026 Contract Amendment #3 – Gremmer and Associates in the amount of
$309,667.00
Meeting Date: November 25, 2025 – Board of Public Works
Background and Analysis:
This memo is to inform the Board of Contract Amendment #3 for the engineering and
design cost of $7,842.00 associated with streetlight design for Hawthorne Drive, Aspen
Drive, and Linden Drive.
The Village currently holds a professional services agreement with Gremmer and
Associates in the amount of $301,825.00 for engineering and design services related to
the 2026 street reconstruction of Eagle Drive, Hawthorne Drive, Aspen Drive, and Linden
Drive.
Contract Amendment #3 proposes to expand the scope of services to include streetlight
engineering and design for the 2026 reconstruction of Hawthorne Drive, Aspen Drive, and
Linden Drive. The previously approved Contract Amendment #2 included engineering and
design of streetlights along Eagle Drive.
Funding for this contract will come from the following accounts:
600-00-56700-400-000 (Capital Projects Repairs/Construction) $103,222.33
300-00-17600-000-380 (Sewer Construction Work) $103,222.33
200-00-18600-395-000 (Water Construction Work) $103,222.34
If you have any questions, please let me know.
JS
Recommendation:
Board of Public Works recommends the Budget and Finance Committee and Village Board
approve Contract Amendment #3 for Gremmer and Associates in the amount of
$309,667.00.
Page 45 of 53
November 14, 2025
Village of Jackson
W194 N16660 Eagle Drive
Jackson, WI 53037
Attention: Mr. Jack Straehler
Director of Public Works
Subject: Hickory Lane
Contract Amendment No. 3
Dear Mr. Straehler:
The following is Contract Amendment No. 3 for the subject project. The original contract dated October
26, 2023, Amendment No. 1 dated 12/11/2024, and Amendment No. 2 dated 7/9/2025 is amended as
follows:
REVISED SCOPE OF SERVICES
6. Street Lighting design (sublet to KL Engineering).
c. Preliminary and final design for continuous street lighting along alternating sides of
Linden Drive, Aspen Drive and Hawthorn Drive.
d. Preliminary and final design for parking lot lighting at the Village of Jackson Department
of Public Works north parking lot and driveway.
COMPENSATION
ENGINEER will be compensated by the OWNER for work outlined in the Revised Scope of Services a lump
sum amount of $7,842.
Contract Amendment No. 3 increases the lump sum fee for the project from $301,825 (Original w/
Amendment No. 1 and Amendment No. 2) to $309,667.
AUTHORIZATION AND TIMING
A receipt of a signed copy of the CONTRACT AMENDMENT shall be considered as authorization to proceed
with the services described.
Submitted by the ENGINEER Accepted by the OWNER
_________________________________ ___________________________________
Jeff Chvosta, Vice President Jack Straehler
Gremmer & Associates, Inc. Director of Public Works
___11/14/2025_____________________ ___________________________________
Date Date
Page 46 of 53
Page 47 of 53
1
Public Works Report
November 25, 2025
Wastewater Treatment Plant - Designed Capacity – 1.69 million gallons per day
Peak Flow Capacity – 6.0 million gallons per day
Wastewater Treatment Plant - Year 2023
Month Average Flow Minimum Flow Maximum Flow
January 1.247 MGD 1.010 MGD 1.560 MGD
February 1.351 MGD 950,000 GPD 3.130 MGD
March 1.762 MGD 1.250 MGD 2.560 MGD
April 1.594 MGD 980,000 GPD 3.290 MGD
May 1.094 MGD 780,000 GPD 1.520 MGD
June 875,333 GPD 750,000 GPD 1.050 MGD
July 841,935 GPD 680,000 GPD 1.050 MGD
August 1.022 MGD 710,000 GPD 2.070 MGD
September 968,667 GPD 740,000 GPD 1.270 MGD
October 1.154 MGD 770,000 GPD 1.900 MGD
November 1.080 MGD 870,000 GPD 1.720 MGD
December 1.1146 MGD 850,000 GPD 1.440 MGD
Wastewater Treatment Plant - Year 2024
Month Average Flow Minimum Flow Maximum Flow
January 1.337 MGD 980,000 GPD 2.260 MGD
February 1.440 MGD 1.090 MGD 2.250 MGD
March 1.502 MGD 950,000 GPD 2.590 MGD
April 1.427 MGD 980,000 GPD 3.220 MGD
May 1.325 MGD 980,000 GPD 1.990 MGD
June 1.544 MGD 980,000 GPD 2.500 MGD
July 1.146 MGD 850,000 GPD 1.560 MGD
August 1.027 MGD 760,000 GPD 1.550 MGD
September 884,333 GPD 700,000 GPD 1.400 MGD
October 795,484 GPD 670,000 GPD 0.990 MGD
November 997,000 GPD 720,000 GPD 1.610 MGD
December 935,806 GGD 730,000 GPD 1.460 MGD
Wastewater Treatment Plant - Year 2025
Month Average Flow Minimum Flow Maximum Flow
January 880,645 GPD 750,000 GPD 1.160 MGD
February 890,714 GPD 730,000 GPD 1.030 MGD
March 1.356 MGD 840,000 GPD 2.300 MGD
April 1.443 MGD 1.0005 MGD 3.5300 MGD
May 1.279 MGD 830,000 GPD 2.5300 MGD
June 1.100 MGD 830,000 GPD 1.8900 MGD
July 993,225 GPD 860,000 GPD 1.2800 MGD
August 1.446 MGD 800,000 GPD 5.6700 MGD
September 953,333 GPD 820,000 GPD 1,210,000 MGD
October 1.038 MGD 730,000 GPD 1,420,000 MGD
November
December
Page 48 of 53
2
2023 Wastewater Treatment Plant – Holding & Septage Receiving Annually by Month
Month Holdings Grease Grease
Decant
Septage Septage
Decant
Total
Billed
January 1,232,950
Gallons
1,000
Gallons
2,800
Gallons
72,460
Gallons
$11,841.10
February 1,299,600
Gallons
1,000
Gallons
27,000
Gallons
$11,121.30
March 849,250
Gallons
18,800
Gallons
62,550
Gallons
$9,203.75
April Primary Clarifiers offline for new diffusers
May 1,011,750
Gallons
44,350
Gallons
121,650
Gallons
$13,131.00
June 1,089,100
Gallons
44,100
Gallons
148,950
Gallons
$14,421.05
July 928,350
Gallons
3,500
Gallons
6,000
Gallons
110,500
Gallons
$12,546.00
August 1,212,400
Gallons
8,000
Gallons
121,800
Gallons
$15,649.00
September 1,083,000
Gallons
10,400
Gallons
100,350
Gallons
$13,962.75
October 1,148,850
Gallons
8,200
Gallons
280,750
Gallons
$18,999.25
November 1,020,400
Gallons
16,500
Gallons
302,800
Gallons
$18,764.00
December 1,263,300
Gallons
2,000
Gallons
198,000
Gallons
17,693.00
2024 Wastewater Treatment Plant – Holding & Septage Receiving Annually by Month
Month Holdings Grease Grease
Decant
Septage Septage
Decant
Total
Billed
January 1,240,050
Gallons
500
Gallons
62,900
Gallons
$14,003.00
February 1,236,550
Gallons
2,300
Gallons
63,100
Gallons
$14,081.00
March 1,139,150
Gallons
4,500
Gallons
141,500
Gallons
$15,200.25
April 1,135,752
Gallons
3,600
Gallons
225,950
Gallons
$17,972.27
May 982,150
Gallons
14,800
Gallons
274,550
Gallons
$17,573.25
June 734,178
Gallons
2,000
Gallons
175,950
Gallons
$11,860.53
July 1,374,900
Gallons
11,300
Gallons
285,450
Gallons
$21,563.25
August 1,362,350
Gallons
15,800
Gallons
272,200
Gallons
$21,376.50
September 990,600
Gallons
1,000
Gallons
237,550
Gallons
$15,904.75
October 1,044,550
Gallons
6,400
Gallons
228,3650
Gallons
$16,545.75
November 987,500
Gallons
5,800
Gallons
195,350
Gallons
$15,106.75
December 960,550
Gallons
2,750
Gallons
107,300
Gallons
$12,453.00
Page 49 of 53
3
2025 Wastewater Treatment Plant – Holding & Septage Receiving Annually by Month
Month Holdings Grease Grease
Decant
Septage Septage
Decant
Total
Billed
January 1,008,400
Gallons
1,500
Gallons
40,650
Gallons
$11,190.25
February 905,450
Gallons
1,400
Gallons
41,250
Gallons
$10,169.75
March 1,237,500
Gallons
3,100
Gallons
72,450
Gallons
$14,372.25
April 1,1317,750
Gallons
3,200
Gallons
168,650
Gallons
$15,545.75
May 1,174,850
Gallons
17,900
Gallons
194,850
Gallons
$17,693.75
June 1,084,900
Gallons
15,800
Gallons
223,750
Gallons
$17,390.75
July 1,037,150
Gallons
15,000
Gallons
168,550
Gallons
$15,485.25
August 1,184,950
Gallons
22,700
Gallons
187,850
Gallons
$17,907.75
September 1,292,700
Gallons
800
Gallons
2,500
Gallons
268,400
Gallons
$19,819.00
October 1,700,600
Gallons
4,500
Gallons
17,400
Gallons
479,250
Gallons
$30,211.25
November
December
Wastewater Treatment Plant – Holding & Septage Receiving Annually
Year
Collected
Amount
Collected
Year
Collected
Amount
Collected
Year
Collected
Amount
Collected
Year
Collected
Amount
Collected
2005 $7,562.01 2006 $101,115.11 2007 $152,201,07 2008 $210,441.47
2009 $183,815.34 2010 $197,653.66 2011 $220,576.28 2012 $236,224.70
2013 $235,336.46 2014 $203,938.32 2015 $210,644,47 2016 $220,473.17
2017 $232,358.23 2018 $245,767.74 2019 $219,822.80 2020 $204,656.11
2021 $209,083.10 2022 $251,109.46 2023 $157,332.20 2024 $194,954.27
2025
Municipal Well Pump Information – Well Number and Pumping Capacity
Well #1 400 GPM Well #3 900 GPM Well #4 1,200 GPM Well #5 1,100 GPM Well #6 800 GPM
Summary of Municipal Water Consumption
2010 Total Pumpage 239,326,000 gallons 2011 Total Pumpage 240,268,000 gallons
2012 Total Pumpage 253,492,000 gallons 2013 Total Pumpage 228,371,000 gallons
2014 Total Pumpage 230,973,000 gallons 2015 Total Pumpage 222,621,000 gallons
2016 Total Pumpage 254,531,000 gallons 2017 Total Pumpage 251,387,000 gallons
2018 Total Pumpage 241,322,000 gallons 2019 Total Pumpage 253,427,000 gallons
2020 Total Pumpage 259,413,000 gallons 2021 Total Pumpage 242,216,000 gallons
2022 Total Pumpage 222,033,000 gallons 2023 Total Pumpage 229,997,000 gallons
2024 Total Pumpage 233,155,000 gallons 2025 Total Pumpage 000,000,000 gallons
Page 50 of 53
4
Municipal Water Consumption - Year 2023
Month Average Pumpage Highest Pumpage Total Pumpage
January 544,810 GPD 716,000 gallons 16,889,000 gallons
February 576,070 GPD 762,000 gallons 16,130,000 gallons
March 532,060 GPD 713,000 gallons 16,494.000 gallons
April 597,230 GPD 869,000 gallons 17,917,000 gallons
May 651,650 GPD 1,243,000 gallons 20,201,000 gallons
June 850,070 GPD 1,018,000 gallons 24,152,000 gallons
July 793,870 GPD 944,000 gallons 24,610,000 gallons
August 737,060 GPD 1,019,000 gallons 22,849,000 gallons
September 616,330 GPD 790,000 gallons 18,490,000 gallons
October 611,900 GPD 986,000 gallons 18,969,000 gallons
November 531,570 GPD 728,000 gallons 15,947,000 gallons
December 549,970 GPD 770,000 gallons 17,049,000 gallons
Municipal Water Consumption - Year 2024
Month Average Pumpage Highest Pumpage Total Pumpage
January 560,000 GPD 733,000 gallons 17,486,000 gallons
February 554,550 GPD 711,000 gallons 16,082,000 gallons
March 541,840 GPD 731,000 gallons 16,797.000 gallons
April 609,130 GPD 903,000 gallons 18,274,000 gallons
May 609,870 GPD 762,000 gallons 18,906,000 gallons
June 661,830 GPD 817,000 gallons 19,855,000 gallons
July 731,480 GPD 988,000 gallons 22,676,000 gallons
August 693,740 GPD 881,000 gallons 21,506,000 gallons
September 739,570 GPD 972,000 gallons 22,187,000 gallons
October 722,810 GPD 1,021,000 gallons 22,407,000 gallons
November 565,450 GPD 816,000 gallons 17,529,000 gallons
December 627,420 GPD 889,000 gallons 19,450,000 gallons
Municipal Water Consumption - Year 2025
Month Average Pumpage Highest Pumpage Total Pumpage
January 607,970 GPD 781,000 gallons 18,847,000 gallons
February 682,680 GPD 820,000 gallons 19,115,000 gallons
March 693,900 GPD 769,000 gallons 21,201.000 gallons
April 707,070 GPD 1,122,000 gallons 21,212,000 gallons
May 716,450 GPD 917,000 gallons 22,210,000 gallons
June 842,170 GPD 999,000 gallons 25,265,000 gallons
July 856,450 GPD 1,066,000 gallons 26,550,000 gallons
August 784.940 GPD 970,000 gallons 24,209,000 gallons
September 837,530 GPD 1,269,000 gallons 25,126,000 gallons
October 813,520 GPD 1,196,000 Gallons 25,219,000 Gallons
November
December
Page 51 of 53
5
Midwest Fiber Network
Installation of equipment continues throughout the Village. Below is a summary of current progress by area:
• Twin Creeks Subdivision: All underground pipes, structures, restoration and main line are
complete. Splicing and lateral work TBD.
• Creekwood Circle: All underground pipes, structures, restoration and main line are complete.
Splicing and lateral work TBD.
• Sherman Parc Subdivision: All underground pipes, structures, and restoration are complete. Fiber
installation on the main line is in progress with splicing and lateral work TBD.
• Cedar Run South: All underground pipes, structures, and restoration are complete. Fiber
installation on the main line, splicing and lateral work TBD.
• Cedar Run North: All underground pipes and structures are complete. Crews will begin working on
the main line next week with restoration to follow. Splicing and lateral work TBD.
• Sherman Creeks Condo: Crews began installing pipe and structures the week of November 17th
and is approximately 50% completed. Fiber installation on the main line, splicing and lateral work
TBD.
• Cranberry Creek: Door hangers have been hung. Work will begin in the coming weeks.
Ridgeway Drive and Chestnut Court Reconstruction Project
All work has been completed in accordance with the contract, and the project remains under the one- year
warranty period. After the reconciliation of all 2025 projects and an evaluation of how they aligned with the
budget, a discussion regarding streetlighting within the project limits will take place.
Hickory Lane Reconstruction Project
All work has been substantially completed per the contract, and crews remain on- site addressing minor
punch-list items. The project has now entered its one- year warranty period.
WWTP 2024 Tertiary Filters and UV Disinfection
All work has been substantially completed per the contract. Crews continue to work through minor punch- list
items. We expect to receive a revised and completed Operation and Maintenance Manual before the end of
the year. Upon its completion, the Board should expect to see the final Clean Water Fund reimbursement
request at the January meeting.
Cedar Run Park – Dog Park Project
A pre-construction meeting was held, and Village staff have walked the site and marked trees to be
preserved during the clearing process. Lowe Underground has installed the tracking pad for equipment and
will begin work on the project. Completion is expected in late spring to early summer.
Morning Meadows Subdivision
Phase 1 - No recent updates
Phase 2 - No recent updates - Homeowner’s sump pumps are still running continuously. Dye -testing was
performed last fall in stormwater detention ponds, and no trace was detected. The investigation is ongoing.
Phase 3 - No recent updates – Final lift of asphalt and Streetlights have not yet been installed.
Maple Fields Subdivision
Phase 1 - No recent updates. We are still working through punch list items.
Phase 2 - No recent updates. We are still working through punch list items.
Phase 3 – A preconstruction meeting was held on November 13, 2025. Village staff is working with Clark
Dietz to finalize all submittals. Work is scheduled to begin in late November.
Next Generation Housing
Hillcrest Builders and Harbor Homes still have outstanding sidewalk repairs to complete. New home
construction continues.
Page 52 of 53
6
Cedar Creek Townhomes
We are still awaiting the televising report for the sanitary sewer main. There are no other updates currently.
Respectfully submitted, Jack Straehler, Director of Public Works
Page 53 of 53