Utility Packet 12.17.2025
City of Marathon City · Marathon County · meeting of Dec 17, 2025 · Agenda packets
Open the original document More from City of Marathon City
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Andrew Berens.
Utility Commission Chair
Cassie Lang
Village Clerk / Deputy Treasurer
311 Walnut Street | P .O. Box 487
Marathon City, WI 54448
Tel: 715-443-2221
www.marathoncitywi.gov
VILLAGE UTILITY COMMISSION
OFFICIAL NOTICE & AGENDA
Wednesday, December 17, 2025
4:00 pm
Marathon Municipal Center
PUBLIC VIRTUAL ACCESS
Join Teams Meeting: https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting
Meeting ID: 261 174 214 35
Passcode: cY2jA33d
1. CALL TO ORDER
UTILITY ROLL CALL: A. BERENS, B. BOHR, M. TELFORD, D. SEILER, K. HANDRICK
JR.
2. PLEDGE OF ALLEGIANCE
3. RECOGNITION OF VISITORS
a. Virtual Meeting Guidelines
i. This meeting will be recorded and available upon request
b. Public Participation at Government Meetings
4. APPROVAL OF OCTOBER 29, 2025 MEETING MINUTES
5. REVIEW AND APPROVAL OF PAYMENT OF BILLS
6. PUBLIC UTILITY OPERATIONS & FACILITIES REPORT
7. UNFINISHED BUSINESS
a. Update on Well #5
b. Update on Cure-In-Place-Piping Project
8. NEW BUSINESS
9. SCHEDULED MEETINGS
a. Regular Meeting: Wednesday, January, 28, 2026 – 4:00 pm
b. Special Meetings as Needed
10. ADJOURNMENT
VILLAGE UTILITY COMMISSION
MINUTES
Wednesday, October 29, 2025
PUBLIC HEARING called to order at 4:01 pm.
Administrator Cherek discussed the need for a stepped sewer rate increase of 5.5% for the next
2 years, stating the Commission has not considered the rate of inflation in many years and the
Commission and Village Board approved a cure-in-place piping project with its Capital Improvement
Plan earlier in the year requiring an 8% increase to cover project costs. Cherek believes the 11%
increase in the next 2 years will get the Wastewater Budget closer to the positive. The Commission will
revisit the Wastewater Revenues and consumption during the 2027 Budget review to determine if an
additional rate increase is needed.
No residents present. No public comments made.
1. CALL TO ORDER at 4:06 pm
UTILITY ROLL CALL: A. BERENS-Present, B. BOHR-Present, M. TELFORD-Present, D. SEILER-
Present, K. HANDRICK JR.-Present
2. PLEDGE OF ALLEGIANCE
3. RECOGNITION OF VISITORS
a. Virtual Meeting Guidelines
i. This meeting will be recorded and available upon request
b. Public Participation at Government Meetings
Attending Virtually: Kevin O’Brien – Record Review
4. APPROVAL OF SEPTEMBER 24, 2025 MEETING MINUTES
MOTION – Approve Minutes for September 24, 2025 Meeting
Motion made by Bohr second by Handrick. Motion passed by voice vote.
5. REVIEW AND APPROVAL OF PAYMENT OF BILLS
Commission members questioned the following bill payments:
Check 49048: SJE, Inc. – Well 3 Repairs
Check 49080: Public Service Commission of WI – 2025-2026 Advance Assessment
Check 49096: Systems Technologies – Internet update to the Water Department
MOTION – Approve Payment of Bills
Motion made by Telford second by Seiler. Motion passed by voice vote.
6. PUBLIC UTILITY OPERATIONS & FACILITIES REPORT
Director of Public Works, Ken Bloom, presented the Commission with a Facilities Report for
October. The report can be found in the Agenda Packet.
7. UNFINISHED BUSINESS
a. Update on Well #5
Administrator Cherek informed the Commission that he signed a contract with Strand
Associates for the engineering for Well #5. The signed contract can be found in the Agenda
Packet. Cherek, along with assistance from Strand, submitted the Safe Drinking Water Loan
application before the deadline. Strand requested extra data needed to do site testing and
analysis to meet DNR requirements. Cherek and Bloom will get required data to Strand. Cherek
stated this will remain Unfinished Business going forward to keep Commission updated on
progress.
b. Update on Cure-In-Place-Piping Project
Cassie Lang
Village Clerk / Deputy Treasurer
Cherek provided the signed contract with Vierbicher Associates, Inc. for the engineering
services on the cure-in-place piping project which can be viewed in Agenda Packet. Vierbicher
provided the Record Review with bid publications to run for 2 weeks. The project is now open
for bids and will close on November 13th, 2025 at 10:00 am. Updates will continue at each
meeting going forward.
8. NEW BUSINESS
a. Discuss and Approve 2026 Utility Budget
Administrator Cherek presented, in detail, the 2026 Utility Budget reflecting the
recommended 5.5% sewer rate increase. The proposed 2026 Budget projects $1,449,540.80 in
Revenues and Expenditures with $3,753.42 in proceeds from the Fund Balance. After Fund
Balance transfers to TID 2 of $26,713.49 and to the Waste Water Reserve Fund of $27,248.00
the projected ending Utility Fund Balance is $1,136,108.78.
Key points discussed:
• 3rd Quarter consumption levels were strong helping bring Water revenue
projected to end near 2025 budgeted amount. Waste Water revenue still
expected to fall short due to lower concentrations in industrial contributors. Lower
concentrations result in reduced rates based on test results. Cherek adjusted
2026 revenue projections to account for recent consumption trends.
• Utility Wages increased close to 7% for Waste Water with an approved 3.5%
employee wage increase and adjusted OT hours based on the Utility
Department’s current practices.
• Administrator wages have been reallocated to shift expenditures off the TIDs.
With the Village refinancing this year, the Water Budget has more capacity to
help with shifting of wages, resulting in a 27.5% increase in Water wage
expenditures.
Full 2026 Utility Budget details can be found in the Agenda Packet.
MOTION – Approve 2026 Utility Budget
Motion made by Handrick second by Berens. Motion passed by voice vote.
b. Discuss and Approve Sending Resolution U-2025-11-12 “Authorizing Wastewater Rate
Increases” to the November 12
th 2025 Village Board Meeting for Final Approval
Approval of the 2026 Utility Budget with the 5.5% Sewer Rate increase requires the Village to
pass a Resolution stating terms of the rate increases. Utility Commission approval is needed
before Village Board approval.
MOTION – Approve Sending Resolution U-2025-11-12 “Authorizing Wastewater Rate
Increases” to the November 12th 2025 Village Board Meeting for Final Approval
Motion made by Handrick second by Seiler. Motion passed by voice vote.
9. SCHEDULED MEETINGS
a. Regular Meeting: Commission to Approve:
i. Wednesday, December 10, 2025 – 4:00 p.m.
OR
ii. Wednesday, December 17, 2025 – 4:00 p.m.
MOTION – Approve December 17, 2025 – 4:00 pm as Next Regular Commission Meeting
Motion made by Bohr second by Telford. Motion passed by voice vote.
b. Special Meetings as Needed
10. ADJOURNMENT at 5:46 pm
Motion to adjourn made by Handrick second by Telford. Motion passed by voice vote.
Marathon City Utility Operations & Facilities Report
for November/December 2025
Water Treatment Facility Report
The water facility is operating well and meeting all the testing requirements.
The clearwell at the water treatment facility is scheduled to be physically inspected (entering
inside the tank) sometime in November 2025. This will require us to bypass the clearwell and
obtain 2 safe bac-t drinking water samples, before it can be put back in service. The clearwell is
expected to be out of service for approximately 2-3 days.
UPDATE 12/25 – Lane Tank Company, is scheduled to be onsite on Monday, December 15th
to inspect the clearwell. In addition to the clearwell, a visual inspection of both the east
and west retention tanks, the backwash basin, and the aeration tank (aerator), will also be
inspected, as required by the DNR. The clearwell is anticipated to be back in service by
Wednesday or Thursday, December 17th or 18th.
The pumping equipment and electric motor are to be refurbished for Well #1, and should be
completed sometime this week. Water Well Solutions should be here in the next couple of weeks
to reinstall the equipment and put Well #1 back in service. The Utility declined to proceed with
the smaller 6” screen installation due to costs, required DNR approval, and an uncertain outcome
attributable to obvious risks associated with the procedure (cleaning & installation of the screen).
UPDATE 10/25– The pumping equipment in Well 1 was reinstalled by Water Well Solutions
on October 14
th. Two safe bac-t water samples were collected on October 14th and 15th.
Both samples came back safe from the laboratory. Well 1 was temporarily put back in
service on October 17th, until Aaron Martin, Waterworks Operator, noticed the check valve
was failing when the pump was off, allowing water to drain back into the well. A new
check valve has been ordered. Once the check valve is replaced, the well will be put back
in service. The well should be put back in service within the next couple of weeks.
UPDATE 12/25 – The check valve was replaced and the well was put back in service on
November 18
th. On November 24th, an issue with the refurbished motor wiring caused the
starter to burn out. The well was taken out of service again and the starter was replaced.
Water Well Solutions was contacted and was onsite on December 1st to repair the electric
motor wiring. Well 1 was put back in service on December 2nd.
A water leak of approximately 15,000 – 20,000 gallons/day was identified on the high-pressure
zone in early November. Wisconsin Rural Water Association (WRWA) assisted the Village in
identifying what was causing the water loss. A leak on the watermain was located at 8th &
Hemlock Streets. A pipe repair clamp from a previous watermain break in 2020 was the issue.
The pipe repair clamp broke, releasing compression around the water main pipe, causing the
water leak. The pipe repair clamp was replaced , and the leak was fixed.
Water Treatment Facility Report (Continued)
On November 9th, the fire hydrant on the south side of 4th Street, just west of Pheasant Lane, was
hit by a vehicle, completely breaking off the hydrant and associated piping from the underground
watermain. PGA was hired to install a new fire hydrant and 2 new service valves. This was
completed by PGA on December 8th. An insurance claim, on behalf of the Utility, will be submitted
to cover the costs of the repair.
The potassium permanganate mixing/transfer pump has failed at the Water Treatment Plant. The
pump is the original pump that was installed at the time the Water Plant was built in 2000. They
no longer manufacture parts for this make and model of pump. A new Grundfos transfer pump
was ordered through Brabazon Pump & Compressor. Village/Utility Staff will install the new pump
at the Water Plant.
Wastewater Treatment Facility Report
The wastewater treatment plant met all WPDES permit limits for the months of October and
November 2025.
A drawdown test was conducted by Vierbicher Associates on the Trailer Court Lift Station. This
was done to determine GPM@TDH. William Reid will use the design characteristics to match
motor and pump size, to meet those requirements.
UPDATE – 8/25 – The new pumps and motors were installed at the lift station. After start-
up, cavitation was still noticeable on both pumps.
UPDATE – 9/25 – I have forwarded the start-up report to Vierbicher Associates for review.
UPDATE – 12/25 – Steve Cherek and I had a conference call on December 4th, with Darrin
Pope, Vierbicher Associates, regarding the current lift station issues. We conveyed that
Vierbicher should take the lead on finding a solution to the cavitation issue and work
closely with Paul Ludwig from William/Reid. In addition, I directly emailed Smith &
Loveless (twice) voicing my disappointment in the fact they have not stepped up to help
address the pump cavitation issue and find a solution to the problem. S&L did respond in
an email on Friday, December 12th. The have provided a list of recommendations. I have
asked William Reid to verify that these recommendations have been completed.
I also had a discussion with Paul Ludwig, William Reid, about the possibility of installing
submersible pumps at this lift station to eliminate the cavitation issue all together. More
details (design, costs, etc.) need to be determined before I or Paul present anything to the
commission for discussion and/or approval. This possible back-up plan/option, will not
stop the effort to find a solution to the current pump cavitation issue, with the recently
installed S&L pumping equipment.
The mechanical seal failed on pump 2 at the Trail Court Lift Station due to excessive pump
cavitation, causing the seal to fail prematurely. William Reid will be onsite, Monday,
December 15th, to replace the mechanical seal and get the pump back in service. We are
currently operating on only one pump at this lift station, with no back-up.
Wastewater Treatment Facility Report (Continued)
Wastewater Regulatory Requirements:
1) The Utility received a letter from the DNR requesting additional information, for
determination of eligibility of the Multi-Discharger Phosphorus Variance.
UPDATE 9/25 – The DNR issued a letter of denial, dated 8/8/25, regarding our application
for the Multi-Discharger Phosphorus Variance. The notification came through an email
from Matt Claucherty, Permits Section - WDNR, on 9/4/25.
UPDATE 10/25 – Nick Lindstrom, WDNR Wastewater Basin Engineer, reached out to me
regarding our Phosphorus Compliance Options. He is requesting the Village select a new
Phosphorus Compliance Option for our next WPDES permit. Since the MDV has been
denied, the only 2 options the Utility has are; meet the effluent phosphorus limit at the
wastewater treatment plant through chemical addition, or convert the contract with
Miltrim Farms to a Water Quality Trade contract. I have requested a meeting with Andy
Johnson, third party administrator between Miltrim Farms and the Village, to discuss future
options, before making any decisions.
UPDATE 12/25 – Andy Johnson (3
rd Party Administrator), Tina Sebold (Strand), and myself
met to discuss the MDV denial letter from the DNR, on October 27th. In order to continue
using Miltrim Farms for phosphorus credits, the Village would have to convert to a Water
Quality Trading Plan, which would cost additional money to develop. Miltrim Farms may
also want a yearly fee for providing available phosphorus credits (as a back-up plan), even if
the Utility does not use those credits. After our discussion, we notified Andy Johnson that
the Utility plans on meeting our phosphorus limit at the treatment plant, and would not
utilize phosphorus credits from Miltrim Farms during our next permit term. Andy Johnson
was going to have a discussion with the staff at Miltrim Farms prior to our next meeting.
We plan to meet again in January to review any options. As of now, the Utility plans to
meet our phosphorus limit at the treatment plant through chemical addition. This will be
our phosphorus compliance option for our next permit term. However; it should be noted
that if the Village continues to expand and grow, there may be a need for future
phosphorus credits (WQT Plan) with Miltrim Farms.
2) I have requested a copy of the WPDES draft permit, prior to the 30-day public notice. The
DNR has agreed to send me a copy of the draft permit and fact sheet. As of the meeting, I
have not received a copy of the draft permit, which leads me to suspect they will not
reissue our permit on time. Our current permit is set to expire on September 30th, 2025. If
the new permit is not reissued on time, we continue operations under our current permit.
UPDATE 10/25– Additional effluent zinc testing has been requested by the DNR, due to
one higher than normal result collected during the testing period, conducted during the
permit application process. I am currently in the process of collecting 3 more effluent
samples for zinc analysis.
Wastewater Treatment Facility Report (Continued)
UPDATE 12/25 – The 3 Zinc samples collected in October 2025, were higher than the
effluent limit set by the DNR; therefore, the DNR has requested that I take additional
samples, for a total of 11 samples, collected 3 days apart from one another. From those 11
samples, the DNR will determine whether an effluent Zinc limit is appropriate, and whether
a limit will be included in our next wastewater permit. The DNR also contacted Marathon
Industrial Finishing and Aluminum Fabricated Products to inquire about their operations,
but was informed that neither of these facilities generate any wastewater from their
production lines. If effluent zinc concentrations remain an issue at the wastewater
treatment plant, the DNR will then schedule a site visit with these industries, to verify their
operations.
Submitted by: Ken Bloom, Director of Public Works & Utilities