Utility Packet 10.29.2025
City of Marathon City · Marathon County · meeting of Oct 29, 2025 · Agenda packets
Open the original document More from City of Marathon City
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Andrew Berens.
Utility Commission Chair
Cassie Lang
Village Clerk / Deputy Treasurer
311 Walnut Street | P .O. Box 487
Marathon City, WI 54448
Tel: 715-443-2221
www.marathoncitywi.gov
VILLAGE UTILITY COMMISSION
OFFICIAL NOTICE & AGENDA
Wednesday, October 29, 2025
4:00 pm Public Hearing
Utility Commission Meeting to Follow Public Hearing
Marathon Municipal Center
PUBLIC VIRTUAL ACCESS
Join Teams Meeting: https://www.microsoft.com/en-us/microsoft-teams/join-a-meeting
Meeting ID: 261 174 214 35
Passcode: cY2jA33d
1. CAL
L TO ORDER
UTILITY ROLL CALL: A. BERENS, B. BOHR, M. TELFORD, D. SEILER, K. HANDRICK
JR.
2. P
LEDGE OF ALLEGIANCE
3. R
ECOGNITION OF VISITORS
a. Virtual Meeting Guidelines
i. This meeting will be recorded and available upon request
b. Public Participation at Government Meetings
4. A
PPROVAL OF SEPTEMBER 24, 2025 MEETING MINUTES
5. RE
VIEW AND APPROVAL OF PAYMENT OF BILLS
6. P
UBLIC UTILITY OPERATIONS & FACILITIES REPORT
7. UNF
INISHED BUSINESS
a. Update on Well #5
b. Update on Cure-In-Place-Piping Project
8. NE
W BUSINESS
a. Discuss and Approve 2026 Utility Budget
b. Discuss and Approve Sending Resolution U-2025-11-12 “Authorizing Wastewater
Rate Increases” to the November 12th 2025 Village Board Meeting for Final Approval
9. S
CHEDULED MEETINGS
a. Regular Meeting: Commission to Approve:
i. Wednesday, December 10, 2025 – 4:00 p.m.
OR
ii. Wednesday, December 17, 2025 – 4:00 p.m.
b. Special Meetings as Needed
10. ADJ
OURNMENT
Cassie Lang
Village Clerk / Deputy Treasurer
VILLAGE OF MARATHON CITY, MARATHON COUNTY, WISCONSIN
UTILITY COMMISSION MEETING – HYBRID
VILLAGE HALL – BOARD ROOM
WEDNESDAY, SEPTEMBER 24, 2025 - 4:00 p.m.
MINUTES
_____________________________________________________________________________________
1. CALL TO ORDER at 4:02 pm
UTILITY ROLL CALL: A. BERENS-Present, B. BOHR-Present, M. TELFORD-Absent, D.
SEILER-Present, K. HANDRICK JR.-Present
2. PLEDGE OF ALLEGIANCE
3. RECOGNITION OF VISITORS
a. Virtual Meeting Guidelines
i. This meeting will be recorded and available upon request
b. Public Participation at Government Meetings
No public in attendance.
4. APPROVAL OF MINUTES OF PREVIOUS MEETINGS
a. Discuss and Possible Action on Approval of Minutes for August 27, 2025 Utility
Commission Meeting
MOTION – Approve Minutes from August 27, 2025 Utility Commission Meeting
Motion made by Handrick second by Bohr. Motion passed by voice vote.
5. REVIEW AND APPROVAL OF PAYMENT OF BILLS
The Utility questioned the following bill payments:
Check 48973 – Land Clearing Services – hydrant replacement on 1
st St
MOTION – Approve Payment of Bills
Motion made by Bohr second by Handrick. Motion passed by voice vote.
6. PUBLIC UTILITY OPERATIONS & FACILITIES REPORT
Director of Public Works, Ken Bloom, presented the Commission with a Facilities Report for
September. The report can be found in the Agenda Packet.
7. UNFINISHED BUSINESS
8. NEW BUSINESS
a. Discuss Draft 2026 Utility Budget
Administrator Cherek handed out a Draft Utility Budget to the Commission and began
discussion showing a downward trend in consumption over the past 2 years.
Cherek supplied 2 different Wastewater Budgets based on proposed sewer rates for 2026.
With no change to sewer rates the proposed Wastewater Budget shows a deficit of
$89,665. The Proposed Wastewater Budget for 2026 with a 5% sewer rate increase shows
a deficit of $52,498.
Cassie Lang
Village Clerk / Deputy Treasurer
The Commission and Cherek discussed the Cure-In-Place-Piping project approved with
the Capital Improvement Plan. A rate increase of approximately 8% is needed to cover
costs of project. Cherek noted the Utility has not increased sewer rates to account for
inflation. He believes a 16% increase (8% for CIPP and 8% for inflation) over 3 years
would get the Wastewater Budget closer to the positive, along with checking
consumption numbers to see if they trend back to normal levels.
After discussion the Commission guided Cherek to present them with a 2026 Proposed
Utility Budget reflecting a 5.5% increase to Wastewater Rates and using the Utility Fund
Balance to cover the deficit amount. Cherek will draft a resolution for 5.5% Wastewater
rate increase for the next 2 years and have the Commission review revenue/consumption
values in 2027 to determine the amount to increase rates for 2028. The Resolution and
Utility Budget will be presented for approval at the October 29
th meeting.
9. SCHEDULED MEETINGS
a. Regular Meeting: Wednesday, October 29, 2025 – 4:00 p.m.
b. Special Meetings as Needed
10. ADJOURNMENT at 6:10 pm
Motion made by Bohr second by Handrick. Motion passed by voice vote.
Marathon City Utility Operations & Facilities Report for October 2025
Water Treatment Facility Report
The water facility is operating well and meeting all the testing requirements.
The clearwell at the water treatment facility is scheduled to be physically inspected (entering
inside the tank) sometime in November 2025. This will require us to bypass the clearwell and
obtain 2 safe bac-t drinking water samples, before it can be put back in service. The clearwell is
expected to be out of service for approximately 2-3 days.
UPDATE – We are still waiting on confirmation from Lane Tank Company, as to when this
inspection will be scheduled. In addition to the clearwell, a visual inspection of both the
east and west retention tanks, the backwash basin, and the aeration tank (aerator), will
also be inspected, as required by the DNR.
The pumping equipment and electric motor are to be refurbished for Well #1, and should be
completed sometime this week. Water Well Solutions should be here in the next couple of weeks
to reinstall the equipment and put Well #1 back in service. The Utility declined to proceed with
the smaller 6” screen installation due to costs, required DNR approval, and an uncertain outcome
attributable to obvious risks associated with the procedure (cleaning & installation of the screen).
UPDATE – The pumping equipment in Well 1 was reinstalled by Water Well Solutions on
October 14th. Two safe bac-t water samples were collected on October 14th and 15th. Both
samples came back safe from the laboratory. Well 1 was temporarily put back in service on
October 17th, until Aaron Martin, Waterworks Operator, noticed the check valve was failing
when the pump was off, allowing water to drain back into the well. A new check valve has
been ordered. Once the check valve is replaced, the well will be put back in service. The
well should be put back in service within the next couple of weeks.
Fall watermain distribution flushing began on Wednesday, October 22
nd. Flushing activities are
expected to continue for approximately 2 weeks, through November 5th.
Wastewater Treatment Facility Report
The wastewater treatment plant met all WPDES permit limits for the months of September 2025.
A drawdown test was conducted by Vierbicher Associates on the Trailer Court Lift Station. This
was done to determine GPM@TDH. William Reid will use the design characteristics to match
motor and pump size, to meet those requirements.
UPDATE – 8/25 – The new pumps and motors were installed at the lift station. After start-
up, cavitation was still noticeable on both pumps.
UPDATE – 9/25 – I have forwarded the start-up report to Vierbicher Associates for review.
I have also requested the Pump Test Certification Form from Smith & Loveless. The Utility
will wait for recommendations from either Vierbicher or William Reid on how to proceed.
Wastewater Treatment Facility Report (Continued)
UPDATE – 10/25 – Vierbicher responded after reviewing the start-up reports. They believe
the pumps should be operating farther to the right side of the pump curve (increased flow
or gpm at the same TDH). They also recommended to have a vibration analysis done to see
if the cavitation/vibration is within acceptable industry standards.
Paul Ludwig, William Reid, called me on October 21st. He thinks performing a vibration
analysis is a waste of money. We know the pumps are cavitating, even if it is less than the
cavitation of the previous pumps. He is going to conduct a deeper review of the data
gathered, and consult with Smith & Loveless for their recommendations. He will respond
back to me within the next few weeks.
Wastewater Regulatory Requirements:
1) The Utility received a letter from the DNR requesting additional information, for
determination of eligibility of the Multi-Discharger Phosphorus Variance.
SUMMER 2025 – Strand Associates, on behalf of the Village, submitted a letter to the DNR,
that included any additional information as requested by the DNR.
UPDATE 9/25 – The DNR issued a letter of denial, dated 8/8/25, regarding our application
for the Multi-Discharger Phosphorus Variance. The notification came through an email
from Matt Claucherty, Permits Section - WDNR, on 9/4/25.
UPDATE 10/25 – Nick Lindstrom, WDNR Wastewater Basin Engineer, reached out to me
regarding our Phosphorus Compliance Options. He is requesting the Village select a new
Phosphorus Compliance Option for our next WPDES permit. Since the MDV has been
denied, the only 2 options the Utility has are; meet the effluent phosphorus limit at the
wastewater treatment plant through chemical addition, or convert the contract with
Miltrim Farms to a Water Quality Trade contract. I have requested a meeting with Andy
Johnson, third party administrator between Miltrim Farms and the Village, to discuss future
options, before making any decisions.
2) I have requested a copy of the WPDES draft permit, prior to the 30-day public notice. The
DNR has agreed to send me a copy of the draft permit and fact sheet. As of the meeting, I
have not received a copy of the draft permit, which leads me to suspect they will not
reissue our permit on time. Our current permit is set to expire on September 30
th, 2025. If
the new permit is not reissued on time, we continue operations under our current permit.
UPDATE – Additional effluent zinc testing has been requested by the DNR, due to one
higher than normal result collected during the testing period, conducted during the permit
application process. I am currently in the process of collecting 3 more effluent samples for
zinc analysis.
A Chemical Standard Operating Procedure (SOP) for the addition of Alum, was also
requested by the DNR, in order to reduce our WET (Whole Effluent Toxicity Testing)
frequency in our next permit term. I have completed the SOP and submitted it to the DNR
for review.
Submitted by: Ken Bloom, Director of Public Works & Utilities
MJF:sem\R:\MAD\Documents\Agreements\M\Marathon City, Village of (WI)\TSA.2024\TO\2025\3682.027.25-01.docx
Task Order No. 25-01
Village of Marathon City, Wisconsin (OWNER)
and Strand Associates, Inc.® (ENGINEER)
Pursuant to Agreement for Technical Services dated July 5, 2024
Project Information
Project Name: Well No. 5 Drilling and Well Facility
Services Description: Design , bidding, and construction- related services for implementation of a new
water supply well.
Scope of Services
ENGINEER will provide the following services to OWNER.
Preliminary Engineering and Well Site Investigation Report
1. Evaluate up to three OWNER-selected well sites for adequacy for placement of a well. The
evaluation will include the following:
a. Conduct reconnaissance of the well site and surrounding area.
b. Review areas currently mapped within the 100-year floodway and floodplain.
c. Conduct a review of the Wisconsin Department of Natural Resources (WDNR) Bureau
for Remediation and Redevelopment Tracking System Database and the State of
Wisconsin Department of Safety and Professional Services Storage Tank Database to
review and map past and current potential sources of contamination, in accordance with
State of Wisconsin Administrative Code, Chapter NR 811.
d. Review OWNER -provided maps of storm and sanitary sewer systems including
pumping stations and stormwater detention basins.
e. Conduct a desktop groundwater hydraulic evaluation for the well site.
2. Provide information from the site evaluation to OWNER. Attend one in- person meeting with
OWNER to discuss the evaluation.
3. Conduct a topographic survey of the OWNER -selected well site. Correspond with utility
marking company to locate underground utilities prior to topographic survey.
4. Prepare a Well Site Investigation Report in accordance with State of Wisconsin Administrative
Code, Chapter NR 811.09(4)(1), after site selection by OWNER. The report will include the
following:
a. Well location by quarter-quarter section, township, range, county, longitude, and latitude.
b. The boundaries of the site and the location of the proposed well on the site.
c. The topography of the site.
d. The regional flood elevation.
e. The past and present use of the proposed site.
Docusign Envelope ID: 35F5EF20-E78B-4AC6-9758-B137B2ACCE41
Village of Marathon City, Wisconsin
Task Order No. 25-01
Page 2
October 21, 2025
MJF:sem\R:\MAD\Documents\Agreements\M\Marathon City, Village of (WI)\TSA.2024\TO\2025\3682.027.25-01.docx
f. Potential contamination sources within one-half mile of the well location, as identified
in databases prepared by others and by site reconnaissance.
g. The geological formations from which water will be withdrawn.
h. Well construction details.
i. The proposed well pumping capacity.
j. The direction of groundwater flow.
k. The estimated zone of influence of the proposed well.
l. The estimated recharge areas for the well.
m. Anticipated annual volume of water to be withdrawn.
n. Location and data from existing nearby piezometers.
o. Location of nearby wetlands.
p. The distance and direction of the proposed well from the nearest existing well serving
another water utility.
q. The distance and direction of the proposed well from the nearest private well within
1,200 feet of the proposed well site.
r. The location and distance of surface water and springs.
s. The location of alternative well sites for the proposed well.
t. A summary of the site, including advantages and disadvantages and the potential need
for water treatment.
5. Prepare an Engineering Report in accordance with State of Wisconsin Administrative Code,
Chapters NR 811.09(3) and (4). The report will include the following, as applicable:
a. A brief description of and potential need for the project.
b. A description of the geographic location of the project.
c. A brief description of the topography of the general area and its relation to the area
involved in the project.
d. Past census data and OWNER -provided projected future population to the design year
of the project.
e. The design period used to design system components.
f. The results of the well investigations.
g. Areas of the project within the floodplain.
h. Areas of the project location within a wetland.
6. Prepare preliminary facility layouts, elevation views, site plan, water main routing, equipment
lists, and design criteria for review with OWNER. Attend one meeting with OWNER to discuss
preliminary information.
7. Assist OWNER with procurement of geotechnical services for borings.
8. Assist OWNER with procurement of a radio path survey.
9. Prepare a preliminary opinion of probable construction cost (OPCC).
Docusign Envelope ID: 35F5EF20-E78B-4AC6-9758-B137B2ACCE41
Village of Marathon City, Wisconsin
Task Order No. 25-01
Page 3
October 21, 2025
MJF:sem\R:\MAD\Documents\Agreements\M\Marathon City, Village of (WI)\TSA.2024\TO\2025\3682.027.25-01.docx
10. Prepare a draft report that combines the Well Site Investigation Report, Engineering Report, and
preliminary design into one document. Submit draft report to OWNER for review and
incorporate OWNER’s comments, as appropriate.
11. Prepare a portable document format (PDF) file and three final hard copies of the report and
submit to OWNER. Submit a PDF file of the report to the WDNR for review.
12. Address OWNER and WDNR comments, as appropriate.
Agency Communication
1. Prepare presentation and attend one virtual preapplication meeting with the WDNR and the
Public Service Commission of Wisconsin (PSCW). The presentation will include the following:
a. Background information on the community and water system.
b. Potential need for the project within the community.
c. Project alternatives considered.
d. OWNER’s selection of the alternatives.
e. Project OPCC and proposed funding.
f. Project schedule.
2. Prepare the General Application Checklist for PSCW Construction Authorization in accordance
with the State of Wisconsin Administrative Code, Chapter PSC 184.04[3]. The letter will include
the following:
a. Description of project components, phases, and schedule.
b. Information supporting the purpose and need of the project.
c. Project alternatives considered, including OPCC comparisons.
d. Analysis of the effect of the project on quality and reliability of services.
e. Project accounting with respect to PSCW uniform system of accounts.
f. Project funding.
g. Project estimated operation and maintenance costs.
h. OWNER-planned system facility retirements.
i. Site plan.
j. List of other agency approvals.
k. Alternatives to mitigate the need for the project.
l. Floodplain review.
m. Environmental and historical review, including a Type 3 Environmental Impact
Information (EII) Review. The Type 3 EII will include the following:
(1) Project overview.
(2) Project development and alternatives.
(3) Natural resource impact review, including an endangered resources review
(Form 1700-047) prepared by the WDNR.
(4) Historical and archaeological review based on information from the Wisconsin
Historical Society (WHS). OWNER shall pay fees associated with data
collection by the WHS.
Docusign Envelope ID: 35F5EF20-E78B-4AC6-9758-B137B2ACCE41
Village of Marathon City, Wisconsin
Task Order No. 25-01
Page 4
October 21, 2025
MJF:sem\R:\MAD\Documents\Agreements\M\Marathon City, Village of (WI)\TSA.2024\TO\2025\3682.027.25-01.docx
(5) Utility information from previous annual reports.
(6) Estimated rate impact of the project.
3. Prepare information for the Supplemental Checklist for Construction of Water Supply Facilities.
The additional information will be an attachment to the General Application Checklist. The
supplemental information will include the following:
a. Need for the project.
b. Water system capacity analysis.
c. Future demand analysis.
d. WDNR project need.
e. Project alternatives considered, including OPCC.
f. Analysis of large water customers with respect to the project.
4. Submit information from the general and supplemental checklists above to the PSCW for review
and authorization. Address agency comments, as appropriate, and provide additional
supplemental information, if required.
Production Well Design and Bidding-Related Services
1. Prepare Bidding Documents using Engineers Joint Contract Documents Committee C -700
Standard General Conditions of the Construction Contract, 2018 edition, technical
specifications, and engineering drawings. The technical specifications will include one new
shallow aquifer test well and one shallow aquifer production well anticipated to be a minimum
of 90 feet deep, capable of pumping a minimum of 400 gallons per minute. The drawings will
include a site plan with property lines, contours, proposed building location, and a cross section
of the anticipated well construction.
2. Submit Bidding Documents to OWNER for review and input at 60 and 90 percent milestones.
3. Prepare prebid OPCC and submit to OWNER.
4. Submit Bidding Documents to WDNR for review and approval.
5. Distribute Bidding Documents electronically through QuestCDN, available at www.strand.com
and www.questcdn.com. Submit Advertisement to Bid to OWNER for publishing.
6. Prepare addenda and answer questions during bidding.
7. Attend bid opening, tabulate and analyze bid results, and assist OWNER in the award of the
Construction Contract.
8. Prepare two sets of Contract Documents for signature.
Production Well Construction-Related Services
1. Provide contract administration services including attendance at preconstruction conference, review
of up to two iterations of contractor’s shop drawing submittals, review of up to six contractor’s
periodic pay requests, attendance at up to three construction progress meetings, up to three periodic
site visits, and participation in project closeout.
2. Provide resident project representative for part -time observation of construction during well
construction and testing. A total of ten visits for up to 60 hours are included.
Docusign Envelope ID: 35F5EF20-E78B-4AC6-9758-B137B2ACCE41
Village of Marathon City, Wisconsin
Task Order No. 25-01
Page 5
October 21, 2025
MJF:sem\R:\MAD\Documents\Agreements\M\Marathon City, Village of (WI)\TSA.2024\TO\2025\3682.027.25-01.docx
Well House Design and Bidding-Related Services
1. Attend one meeting with OWNER to review preliminary facility layout and equipment included
in the Well No. 5 Preliminary Engineering Report prepared by ENGINEER.
2. Communicate with OWNER on well facility design components and architectural finishes.
Well facility design will include the following components:
a. A single-room masonry well house with a slope roof, roof hatch, and main access door.
b. Well pump and associated piping, metering, valves, and controls to be integrated into
the existing supervisory control and data acquisition (SCADA) system.
c. Site landscaping and grading.
d. Water main to connect the facility to the existing raw water transmission main.
3. Submit draft drawings and technical specifications to OWNER for review and input. Attend one
meeting with OWNER to review draft drawings and technical specifications. Incorporate review
comments, as appropriate.
4. Prepare one prebid opinion of probable construction cost for the well facility.
5. Submit the drawings, technical specifications, and permit forms in portable document format to
the WDNR for review and approval.
6. Prepare Bidding Documents using Engineers Joint Contract Documents Committee C -700
Standard General Conditions of the Construction Contract, 2018 edition, technical
specifications, and engineering drawings.
7. Distribute Bidding Documents electronically through QuestCDN, available at www.strand.com
and www.questcdn.com. Submit Advertisement to Bid to OWNER for publishing.
8. Prepare addenda and answer questions during bidding.
9. Attend virtual bid opening, tabulate and analyze bid results, and assist OWNER in the award of
the Construction Contract.
10. Prepare two sets of Contract Documents for signature.
Well House Construction-Related Services
1. Provide contract administration services including attendance at the preconstruction conference,
review of up to three iterations of contractor’s shop drawings submittals, review of up to eight
contractor’s periodic pay requests, attendance at up to eight construction progress meetings, up to eight
periodic site visits, and participation in project closeout.
2. Provide resident project representative for up to 120 hours of part-time observation of construction.
3. Perform one site visit after contractor’s submittal of a substantial completion request and prepare
a list of items to be completed or corrected. Perform one follow-up site visit to observe contractor’s
completed work.
4. Provide record drawings in electronic format from information compiled from contractor’s records.
ENGINEER is providing drafting Services only for record drawings based on the records presented
to ENGINEER by contractor and OWNER. ENGINEER will not be liable for the accuracy of the
record drawing information provided by contractor and OWNER.
Docusign Envelope ID: 35F5EF20-E78B-4AC6-9758-B137B2ACCE41
Village of Marathon City, Wisconsin
Task Order No. 25-01
Page 6
October 21, 2025
MJF:sem\R:\MAD\Documents\Agreements\M\Marathon City, Village of (WI)\TSA.2024\TO\2025\3682.027.25-01.docx
5. Update existing SCADA computer software, human- machine interface graphics, and reports to
include new signals. Provide site acceptance testing for SCADA additions.
6. Organize and prepare operation and maintenance manuals for the facility based on materials
submitted by contractor. Submit one electronic version and two hard copies.
Well Head Protection Plan (WHPP)
1. Prepare a WHPP update including the following and in accordance with State of Wisconsin
Administrative Code, Chapter NR 811, to incorporate Well No. 5:
a. Evaluate the recharge area for the well.
b. Evaluate the zone of influence for the well.
c. Evaluate the direction of groundwater flow.
d. Inventory existing potential contamination sources within a one -half mile radius of the
well and assess existing potential contamination sources within the recharge area based
on existing database information provided by others.
e. Establish a wellhead protection area for the well.
2. Prepare the WDNR Potential Contaminant Use Inventory checklist form.
3. Provide three copies of the WHPP to OWNER and submit three copies of the WHPP along with
the Potential Contaminant Use Inventory checklist form to the WDNR for review and approval.
Funding Assistance Services
Assist OWNER with the preparation and submittal of the Safe Drinking Water Loan Program (SDWLP)
Financial Assistance application. The application will include the following:
1. Executed copies of engineering agreements for planning and/or design and proposed or executed
engineering agreements for bidding- and construction-related services.
2. Construction drawings and technical specifications for review by WDNR.
3. OWNER-provided financial information required by the loan agencies.
4. Opinions of probable costs including design, planning, financial, and construction costs.
5. OWNER’s resolution authorizing one individual to act as the representative for SDWLP
information.
6. OWNER’s resolution declaring intent to reimburse municipal accounts with financial assistance
proceeds.
7. Proposed user charge system. Application to increase water rates shall be performed and
provided by OWNER or OWNER hired rate consultant.
Compensation
OWNER shall compensate ENGINEER for Services under this Task Order a lump sum of $295,000.
Docusign Envelope ID: 35F5EF20-E78B-4AC6-9758-B137B2ACCE41
Village of Marathon City, Wisconsin
Task Order No. 25-01
Page 7
October 21, 2025
MJF:sem\R:\MAD\Documents\Agreements\M\Marathon City, Village of (WI)\TSA.2024\TO\2025\3682.027.25-01.docx
Schedule
Services will begin upon execution of this Task Order, which is anticipated the week of October 20, 2025.
Services are scheduled for completion on March 31, 2028.
TASK ORDER AUTHORIZATION AND ACCEPTANCE:
ENGINEER:
STRAND ASSOCIATES, INC.
®
Joseph M. Bunker Date
Corporate Secretary
OWNER:
VILLAGE OF MARATHON CITY,
WISCONSIN
Steven Cherek Date
Village Administrator-Treasurer
Docusign Envelope ID: 35F5EF20-E78B-4AC6-9758-B137B2ACCE41
10/21/2025
10/22/2025
ACTUAL ACTUAL As Of 10/16/2025PROJECTED ADOPTED PROPOSEDYOY Percent
REVENUES 2023 REVENUES2024 REVENUES2025 REVENUESYear End 20252025 REVENUES2026 REVENUESChange
WASTE WATER
Sales - Residential 291,473.49$ 387,104.89$ 402,203.41$ 402,203.41$ 404,947.79$ 430,064.52$ 6.20%
Sales - Commercial 153,298.37$ 224,228.89$ 155,217.95$ 155,217.95$ 231,225.23$ 138,473.99$ -40.11%
Sales - Industrial 179,432.65$ 178,488.16$ 204,486.51$ 204,486.51$ 198,839.94$ 208,516.80$ 4.87%
Sales - Multifamily 18,042.50$ 23,161.24$ 66,872.71$ 66,872.71$ 27,594.09$ 85,708.84$ 210.61%
Sales - Public Auth. 39,097.85$ 46,203.78$ 42,753.02$ 42,753.05$ 49,642.68$ 45,046.76$ -9.26%
Other Sewer Revs. 664,831.95$ 133,620.69$ 7,844.79$ 10,526.72$ 3,500.00$ 12,956.24$ 270.18%
Subtotal - Sewer 1,346,176.81$ 992,807.65$ 879,378.39$ 882,060.35$ 915,749.73$ 920,767.15$ 0.55%
WATER -
Sales - Residential 151,910.99$ 146,763.63$ 149,937.82$ 149,937.82$ 152,679.34$ 151,826.96$ -0.56%
Sales - Commercial 58,464.96$ 71,742.27$ 52,024.22$ 52,024.22$ 62,326.04$ 39,020.22$ -37.39%
Sales - Industrial 100,407.14$ 97,833.17$ 90,424.66$ 90,424.66$ 104,533.35$ 103,456.54$ -1.03%
Sales - Pump House 6,359.38$ 5,593.64$ 6,764.44$ 6,764.44$ 6,303.31$ 6,823.98$ 8.26%
Sales - Public Auth. 21,812.52$ 18,554.24$ 24,287.18$ 24,287.18$ 18,408.02$ 22,651.22$ 23.05%
Sales -Multifamily 8,960.96$ 8,705.99$ 22,004.53$ 22,004.53$ 8,759.96$ 29,147.31$ 232.73%
Fire Protection 174,308.03$ 176,520.83$ 103,974.51$ 177,204.51$ 170,130.00$ 170,244.00$ 0.07%
Other Water Revs. 3,458.82$ 11,935.68$ 48,530.21$ 48,790.07$ 1,850.00$ 1,850.00$ 0.00%
Subtotal - Water 525,682.80$ 537,649.45$ 497,947.57$ 571,437.43$ 524,990.02$ 525,020.23$ 0.01%
Subtotal Rev 1,871,859.61$ 1,530,457.10$ 1,377,325.96$ 1,453,497.78$ 1,440,739.75$ 1,445,787.38$ 0.35%
Proceeds from Borrowing - After 2025
will be in CIP Budget not Utility Budget5,587,247.56$ - $ -$ -$ 150,000.00$ -$ -100.00%
Proceeds From Fund Balance -$ -$ -$ 34,548.32$ -$ 3,753.42$
TOTAL REVENUES 7,459,107.17$ 1,530,457.10$ 1,377,325.96$ 1,488,046.10$ 1,590,739.75$ 1,449,540.80$ -8.88%
VILLAGE OF MARATHON CITY
WATER & WASTE WATER UTILITY
2026 PROPOSED BUDGET - With 5.5% Waste Water Rate Increase
Prepared by Steven Cherek 10/17/2025 Page 1
ACTUAL ACTUAL As Of 10/16/2025PROJECTED ADOPTED PROPOSEDYOY Percent
EXPENDITURES 2023 EXPENSES2024 EXPENSES2025 EXPENSESYear End 20252025 EXPENSES2026 REVENUESChange
WASTE WATER
Board Salaries & Expense 1,375.00$ 1,225.00$ 681.67$ 943.15$ 1,746.88$ 1,746.88$ 0.00%
Employee Wages & Salaries 134,521.91$ 122,991.66$ 107,004.28$ 150,776.13$ 150,991.28$ 161,556.35$ 7.00%
Employee Benefits 49,943.04$ 45,353.04$ 39,229.67$ 49,034.37$ 51,743.33$ 50,548.78$ -2.31%
Maintenance & Operations 136,571.11$ 122,441.19$ 96,758.00$ 113,406.38$ 132,950.00$ 126,563.00$ -4.80%
Admin. & Insurance Expense 22,223.08$ 38,730.83$ 49,786.76$ 55,272.32$ 37,675.00$ 43,135.00$ 14.49%
Debt Service Fund Transfer 99,712.44$ 163,479.05$ 471,198.28$ 551,882.60$ 554,591.48$ 582,077.61$ 4.96%
Capital Project Fund Transfer 5,387,691.83$ 13,229.98$ -$ -$ -$ -$
Subtotal - Sewer 5,832,038.41$ 507,450.75$ 764,658.66$ 921,314.95$ 929,697.97$ 965,627.62$ 3.86%
WATER -
Board Salaries & Expense -$ 503.68$ 726.57$ 988.12$ 1,746.88$ 1,746.88$ 0.00%
Employee Wages & Salaries 90,037.22$ 98,670.85$ 79,364.44$ 110,085.38$ 106,175.41$ 135,377.89$ 27.50%
Employee Benefits 47,670.21$ 42,995.88$ 34,955.70$ 40,626.97$ 40,249.11$ 48,745.41$ 21.11%
Plant Maint. & Ops. 94,482.52$ 86,762.13$ 64,343.24$ 78,393.00$ 78,400.00$ 78,900.00$ 0.64%
Distribution Maint. & Ops. 28,099.28$ 16,716.42$ 44,545.45$ 53,031.46$ 41,000.00$ 41,000.00$ 0.00%
Admin. & Insurance Expense 22,377.10$ 215,415.00$ 31,239.92$ 33,413.57$ 33,850.00$ 30,113.00$ -11.04%
Tax Expense 108,000.00$ 100,375.00$ -$ 108,000.00$ 108,000.00$ 108,000.00$ 0.00%
Debt Service Fund Transfer 37,964.53$ 26,745.12$ 41,646.57$ 71,394.11$ 71,394.12$ 40,030.00$ -43.93%
Capital Project Fund Transfer 339,318.15$ 2,304.84$ 36,558.54$ 70,798.54$ 170,000.00$ -$ -100.00%
Subtotal - Water 767,949.01$ 590,488.92$ 333,380.43$ 566,731.15$ 650,815.52$ 483,913.18$ -25.65%
Subtotal Expenditures6,599,987.42$ 1,097,939.67$ 1,098,039.09$ 1,488,046.10$ 1,580,513.49$ 1,449,540.80$ -8.29%
PROCEEDS to FUND BAL 859,119.75$ 432,517.44$ 279,286.87$ -$ 10,226.26$ -$ -100.00%
TOTAL EXPENDITURES 7,459,107.17$ 1,530,457.10$ 1,377,325.96$ 1,488,046.10$ 1,590,739.75$ 1,449,540.80$ -8.88%
Transfer to TID2 Fund 303,125.00$ 39,176.43$ 23,173.00$ 15,450.91$ 26,713.49$ 72.89%
Transfer to WW Reserve Fund 38,546.00$ -$ 29,960.00$ 38,546.00$ 27,248.00$ -29.31%
ENDING FUND BALANCE 1,749,662.00$ 1,281,505.00$ 1,521,615.45$ 1,193,823.69$ 1,237,734.36$ 1,136,108.78$ -8.21%
Prepared by Steven Cherek 10/17/2025 Page 2
2026 WASTE WATER BUDGET
5.5% Rate Increase
2025 Inactive Accounts - combined/replaced in 2026
ACTUAL ACTUAL As Of 10/16/2025PROJECTED ADOPTED PROPOSEDYOY Percent
REVENUES 2023 REVENUES2024 REVENUES2025 REVENUESYear End 20252025 REVENUES2026 REVENUESChange
200-00-46410-000-450 Sales - Residential 291,473.49$ 387,104.89$ 402,203.41$ 402,203.41$ 404,947.79$ 430,064.52$ 6.20%
200-00-46410-000-451 Sales - Commercial 153,298.37$ 224,228.89$ 155,217.95$ 155,217.95$ 231,225.23$ 138,473.99$ -40.11%
200-00-46410-000-452 Sales - Industrial 179,432.65$ 178,488.16$ 204,486.51$ 204,486.51$ 198,839.94$ 208,516.80$ 4.87%
200-00-46410-000-453 Sales - Multifamily 18,042.50$ 23,161.24$ 66,872.71$ 66,872.71$ 27,594.09$ 85,708.84$ 210.61%
200-00-46410-000-454 Sales - Public Auth. 39,097.85$ 46,203.78$ 42,753.02$ 42,753.05$ 49,642.68$ 45,046.76$ -9.26%
200-00-46410-000-510 Other Revenues -$
SUBTOTAL WATER SALES 681,344.86$ 859,186.96$ 871,533.60$ 871,533.63$ 912,249.73$ 907,810.91$ -0.49%
200-00-46410-000-455 Cust. Penalties 1,763.91$ 2,097.93$ 1,649.31$ 2,140.77$ 1,500.00$ 2,000.00$ 33.33%
200-00-46410-000-500 Interest Income -$ -$ 6,195.48$ 8,385.95$ -$ 10,956.24$
200-00-46410-200-000 Commercial Sewer Drop off 130.00$ -$ -$ 1,500.00$ -$ -100.00%
200-00-46410-000-510 Other Sewer Rev
200-00-46420-000-635 MISC Rev 252,640.04$ 8,627.76$ -$ -$ 500.00$ -$ -100.00%
200-00-49110-000-000 Short-term Borrowing
200-00-47500-100-001 CWLF PROCEEDS 5,230,247.56$ -$
200-00-48400-000-421 CONTRIBUTED PLANT SEWER410,428.00$ 122,765.00$
SUBTOTAL - OTHER WATER REV5,895,079.51$ 133,620.69$ 7,844.79$ 10,526.72$ 3,500.00$ 12,956.24$ 270.18%
TOTAL WASTE WATER REVENUES 6,576,424.37$ 992,807.65$ 879,378.39$ 882,060.35$ 915,749.73$ 920,767.15$ 0.55%
Prepared by Steven Cherek 10/17/2025 Page 1
ACTUAL ACTUAL As Of 10/16/2025PROJECTED ADOPTED PROPOSEDYOY Percent
EXPENDITURES 2023 EXPENSES2024 EXPENSES2025 EXPENSESYear End 20252025 EXPENSES2026 EXPENSESChange
200-00-53111-000-001 Board Wages 1,375.00$ 750.00$ -$ -$
200-00-53111-110-001 WW U. Board Wages 475.00$ 674.00$ 924.00$ 1,625.00$ 1,625.00$ 0.00%
200-00-53111-130-001 WW Board FICA & Medicare 7.67$ 19.15$ 121.88$ 121.88$ 0.00%
SUBTOTAL - BOARD WAGES & EXP1,375.00$ 1,225.00$ 681.67$ 943.15$ 1,746.88$ 1,746.88$ 0.00%
200-00-53111-110-000 Waste Water Wages 99,506.78$ 139,894.32$ 140,134.98$ 150,040.92$ 7.07%
200-00-53111-130-000 WW FICA/Medicare 2,754.48$ 7,459.25$ 10,881.81$ 10,856.30$ 11,515.43$ 6.07%
200-00-53111-000-100 Utility Superintendent 95,092.75$ 89,413.65$
200-00-53111-000-105 FICA & Medicare 10,825.23$ 8,603.71$ 38.25$
200-00-53111-000-110 Administrator Wages 7,464.93$ 6,412.50$
200-00-53111-000-115 Clerical Wages 20,503.00$ 18,561.80$
200-00-53111-000-820 SALARIES & WAGES (53.00)$
200-00-53300-000-408 Fica & Medicare 689.00$
200-00-53500-000-120 PENSION & BENEFITS
SUBTOTAL - WAGES 134,521.91$ 122,991.66$ 107,004.28$ 150,776.13$ 150,991.28$ 161,556.35$ 7.00%
200-00-53111-140-000 WW Retirement 6,580.14$ 9,503.73$ 9,520.46$ 10,568.14$ 11.00%
200-00-53111-150-000 WW HEALTH INSURANCE 32,453.91$ 39,170.04$ 41,408.33$ 39,170.04$ -5.41%
200-00-53111-160-000 WW Life Insurance 112.87$ 210.60$ 214.54$ 210.60$ -1.84%
200-00-53111-000-116 Benefits 14,560.18$ 7,675.47$ 34.75$ -$
200-00-53500-000-120 Benefits
200-00-53800-000-428 Sewer Pension / Benefites 35,382.86$ 37,534.09$
200-00-53200-135-000 wwtp Uniform Allowance 143.48$ 48.00$ 150.00$ 600.00$ 600.00$ 0.00%
SUBTOTAL - BENEFITS 49,943.04$ 45,353.04$ 39,229.67$ 49,034.37$ 51,743.33$ 50,548.78$ -2.31%
200-00-53111-000-821 Power for Pumps 38,997.51$ 37,480.99$ 35,578.69$ 44,964.00$ 39,000.00$ 46,313.00$ 18.75%
200-00-53111-000-822 MDV Phosphorus Payment -$ 25,051.00$ 11,489.00$ 11,489.00$ 25,100.00$ 14,000.00$ -44.22%
200-00-53111-000-826 Chemicals - Treatment 9,509.21$ 12,843.58$ 13,547.54$ 13,547.54$ 10,000.00$ 14,000.00$ 40.00%
200-00-53111-000-827 Supplies & Exp 39,260.86$ 31,665.30$ 22,089.68$ 26,707.00$ 35,000.00$ 29,000.00$ -17.14%
200-00-53111-000-828 Transportation Exp 157.35$ 1,333.02$ 16.99$ 100.00$ 2,000.00$ 1,000.00$ -50.00%
200-00-53111-000-829 Gasoline 334.67$ 478.39$ 204.99$ 400.00$ 750.00$ 750.00$ 0.00%
200-00-53300-000-831 Maint Collection System 4,775.72$ 303.59$ 374.31$ 374.31$ 5,500.00$ 5,000.00$ -9.09%
200-00-53300-000-832 Maint Lift Stations 14,023.61$ 7,905.60$ 2,573.06$ 3,430.75$ 10,000.00$ 9,000.00$ -10.00%
200-00-53300-000-833 Maint Tre & Disp 27,850.25$ 3,896.61$ 4,530.12$ 6,040.16$ 3,500.00$ 3,500.00$ 0.00%
200-00-53300-000-834 Maint GP STR & EQ 1,661.93$ 1,483.11$ 6,353.62$ 6,353.62$ 1,500.00$ 4,000.00$ 166.67%
200-00-83300-000-835 Maint Meters -$ -$ -$ -$ 600.00$ -$ -100.00%
SUBTOTAL - MAINT & OPS 136,571.11$ 122,441.19$ 96,758.00$ 113,406.38$ 132,950.00$ 126,563.00$ -4.80%
200-00-53500-000-857 Debt PMT Prinicpal -$ 0.02$ 387,213.27$ 387,213.27$ 388,663.73$ 396,573.04$ 2.04%
200-00-53500-000-858 Debt Payment Int 99,712.44$ 163,479.03$ 83,985.01$ 164,669.33$ 165,927.75$ 185,504.57$ 11.80%
SUBTOTAL - DEBT PAYMENTS 99,712.44$ 163,479.05$ 471,198.28$ 551,882.60$ 554,591.48$ 582,077.61$ 4.96%
200-00-53300-500-000 Accrued Sick Leave
200-00-53311-000-856 MISC EXP
200-00-53400-000-840 Billing & Accounting 226.73$ 429.62$ 114.57$ 152.76$ 1,000.00$ 200.00$ -80.00%
200-00-53400-000-842 Meter Reading
200-00-53400-000-843 Uncollectable A/R
200-00-53500-000-851 Supplies 4,969.91$ 9,211.56$ 5,994.33$ 7,731.08$ 9,000.00$ 9,000.00$ 0.00%
200-00-53500-000-852 Outside Services 3,528.28$ 13,711.08$ 26,416.57$ 28,416.57$ 12,000.00$ 15,500.00$ 29.17%
200-00-53500-000-853 Insurance 12,504.49$ 13,939.09$ 16,060.08$ 17,513.00$ 15,200.00$ 16,935.00$ 11.41%
200-00-53500-000-855 Regulatory Exp 527.32$ -$ -$ -$
200-00-53500-000-856 Misc Exp 466.35$ 1,439.48$ 1,201.21$ 1,458.91$ 475.00$ 1,500.00$ 215.79%
200-00-53600-000-403 Other Expenditures #DIV/0!
200-00-53600-130-000 Sewer Fringe Benefits #DIV/0!
200-00-53800-000-000 Tax Equivalent
SUBTOTAL - ADMIN COSTS 22,223.08$ 38,730.83$ 49,786.76$ 55,272.32$ 37,675.00$ 43,135.00$ 14.49%
200-00-51510-210-105 WWTP Engineering
200-00-56100-100-500 General Construction 5,387,691.83$ 13,229.98$
SUBTOTAL - Capital Project Fund Transfer5,387,691.83$ 13,229.98$ -$ -$ -$ -$ 0.00%
TOTAL EXPENDITURES 5,832,038.41$ 507,450.75$ 764,658.66$ 921,314.95$ 929,697.97$ 965,627.62$ 3.86%
TO (FROM) RESERVE 744,385.96$ $485,356.91 $114,719.73 ($39,254.60) ($13,948.24) ($44,860.47)221.62%
Prepared by Steven Cherek 10/17/2025 Page 2
5.5% Rate Increase
ACTUAL ACTUAL As Of 10/16/2025PROJECTED ADOPTED #REF! YOY Percent
REVENUES #REF! #REF! 2025 REVENUESYear End 20252025 REVENUES2026 REVENUESChange
SANITARY SALES 681,344.86 $ 859,186.96$ 871,533.60$ 871,533.63$ 912,249.73$ 907,810.91$ -0.49%
OTHER REVENUE 664,831.95$ 133,620.69$ 7,844.79$ 10,526.72$ 3,500.00$ 12,956.24$ 270.18%
PROCEEDS FROM BORROWING 5,230,247.56$ -$ -$ -$ -$ -$
TOTAL REVENUE 6,576,424.37$ 992,807.65$ 879,378.39$ 882,060.35$ 915,749.73$ 920,767.15$ 0.55%
ACTUAL ACTUAL As Of 10/16/2025PROJECTED ADOPTED #REF! YOY Percent
EXPENDITURES #REF! #REF! 2025 EXPENSESYear End 20252025 EXPENSES #REF! Change
BOARD WAGES & EXPENSE 1,375.00 $ 1,225.00$ 681.67$ 943.15$ 1,746.88$ 1,746.88$ 0.00%
WAGES 134,521.91$ 122,991.66$ 107,004.28$ 150,776.13$ 150,991.28$ 161,556.35$ 7.00%
BENEFITS 49,943.04$ 45,353.04$ 39,229.67$ 49,034.37$ 51,743.33$ 50,548.78$ -2.31%
PLANT MAINTENANCE & OPS 136,571.11$ 122,441.19$ 96,758.00$ 113,406.38$ 132,950.00$ 126,563.00$ -4.80%
ADMINISTRATIVE COSTS 22,223.08$ 38,730.83$ 49,786.76$ 55,272.32$ 37,675.00$ 43,135.00$ 14.49%
Debt Service Fund Transfer 99,712.44$ 163,479.05$ 471,198.28$ 551,882.60$ 554,591.48$ 582,077.61$ 4.96%
Capital Project Fund Transfer 5,387,691.83$ 13,229.98$ -$ -$ -$ -$
TOTAL EXPENDITURES 5,832,038.41$ 507,450.75$ 764,658.66$ 921,314.95$ 929,697.97$ 965,627.62$ 3.86%
TO (FROM) RESERVE 744,386$ 485,357$ 114,720$ (39,255)$ (13,948)$ (44,860)$ 221.62%
2026 WASTE WATER BUDGET SUMMARY
Prepared by Steven Cherek 10/17/2025 Page 3
12,956.24$
3 Year Waste Water Trends
3,400,0003,600,0003,800,0004,000,0004,200,0004,400,0004,600,0002023 2024 2025Residential0500,0001,000,0001,500,0002,000,0002,500,0003,000,0002023 2024 2025Industrial0200,000400,000600,000800,0001,000,0001,200,0001,400,0001,600,0001,800,0002,000,0002023 2024 2025Commercial0100,000200,000300,000400,000500,000600,000700,000800,0002023 2024 2025Public Authority0200,000400,000600,000800,0001,000,0001,200,0002023 2024 2025Multifamily7,000,0007,500,0008,000,0008,500,0009,000,0009,500,00010,000,0002023 2024 2025Waste Water Billed Consumption by Quarter
Prepared by Steven Cherek 10/17/2025 Page 4
2026 WATER DEPARTMENT BUDGET
2025 Inactive Accounts - combined/replaced in 2026
ACTUAL ACTUAL As Of 10/16/2025 Projected Adopted PROPOSEDYOY Percent
REVENUES 2023 REVENUES2024 REVENUES2025 REVENUES2025 Year End2025 Budget 2026 BUDGET Change
200-00-46411-000-450 Sales - Residential 151,910.99$ 146,763.63$ 149,937.82$ 149,937.82$ 152,679.34$ 151,826.96$ -0.56%
200-00-46411-000-451 Sales - Commercial 58,464.96$ 71,742.27$ 52,024.22$ 52,024.22$ 62,326.04$ 39,020.22$ -37.39%
200-00-46411-000-452 Sales - Industrial 100,407.14$ 97,833.17$ 90,424.66$ 90,424.66$ 104,533.35$ 103,456.54$ -1.03%
200-00-46411-000-453 Sales - Pump House 6,359.38$ 5,593.64$ 6,764.44$ 6,764.44$ 6,303.31$ 6,823.98$ 8.26%
200-00-46411-000-454 Sales - Public Auth. 21,812.52$ 18,554.24$ 24,287.18$ 24,287.18$ 18,408.02$ 22,651.22$ 23.05%
200-00-46411-000-455 Sales Multifamily 8,960.96$ 8,705.99$ 22,004.53$ 22,004.53$ 8,759.96$ 29,147.31$ 232.73%
200-00-46411-000-462 Fire Protection 150,638.03$ 152,736.83$ 80,190.51$ 153,420.51$ 146,460.00$ 146,460.00$ 0.00%
200-00-46411-000-463 Priv Fire Prot 23,670.00$ 23,784.00$ 23,784.00$ 23,784.00$ 23,670.00$ 23,784.00$ 0.48%
SUBTOTAL WATER SALES 522,223.98$ 525,713.77$ 449,417.36$ 522,647.36$ 523,140.02$ 523,170.23$ 0.01%
200-00-46420-000-415 Jobbing
200-00-46412-000-419 Interest Income -$ -$ -$ -$
200-00-46412-000-470 Cust. Penalties 1,114.38$ 1,021.15$ 877.70$ 1,137.56$ 850.00$ 850.00$ 0.00%
200-00-46412-000-632 Serv Laterals -$
200-00-46412-000-635 MISC 2,344.44$ 10,914.53$ 47,652.51$ 47,652.51$ 1,000.00$ 1,000.00$ 0.00%
200-00-49110-000-000 DEBT PROCEEDS 357,000.00$ -$ -$ 150,000.00$ -$ -100.00%
SUBTOTAL - OTHER WATER REV360,458.82$ 11,935.68$ 48,530.21$ 48,790.07$ 151,850.00$ 1,850.00$ -98.78%
TOTAL WATER REVENUES 882,682.80$ 537,649.45$ 497,947.57$ 571,437.43$ 674,990.02$ 525,020.23$ -22.22%
ACTUAL ACTUAL As Of 10/16/2025 Projected Adopted PROPOSEDYOY Percent
EXPENDITURES 2023 EXPENSES2024 EXPENSES2025 EXPENSES2025 Year End2025 Budget 2026 BUDGET Change
200-00-57520-000-110 Board Wages
200-00-57520-110-001 Water U. Board Wages 475.00$ 675.00$ 925.00$ 1,625.00$ 1,625.00$ 0.00%
200-00-57520-130-001 Water U. Board FICA/Medicare 28.68$ 51.57$ 63.12$ 121.88$ 121.88$ 0.00%
SUBTOTAL - BOARD WAGES & EXP -$ 503.68$ 726.57$ 988.12$ 1,746.88$ 1,746.88$ 0.00%
200-00-57520-000-100 DPW #3 54,586.38$ 50,963.75$ -$
200-00-57520-000-105 FICA & Medicare 6,107.91$ 5,572.67$ -$
200-00-57520-000-110 Administrator Wages 8,839.93$ 7,162.50$ -$
200-00-57520-000-115 Clerical Wages 20,503.00$ 18,308.20$ -$
200-00-57520-000-100 PT Laborer Wages -$ -$
200-00-57520-110-000 Water Dept Wages 16,087.24$ 73,973.57$ 102,225.82$ 98,593.71$ 125,687.27$ 27.48%
200-00-57520-130-000 Water FICA/Medicare 576.49$ 5,390.87$ 7,859.56$ 7,581.70$ 9,690.62$ 27.82%
SUBTOTAL - WAGES 90,037.22$ 98,670.85$ 79,364.44$ 110,085.38$ 106,175.41$ 135,377.89$ 27.50%
200-00-57520-135-000 Uniform 379.32$ 200.00$ 248.00$ 500.00$ 500.00$ 500.00$ 0.00%
200-00-57520-140-000 Water Retirement 4,993.03$ 6,963.44$ 6,633.34$ 8,814.67$ 32.88%
200-00-57520-150-000 WATER HEALTH INSURANCE 29,643.39$ 32,902.83$ 32,902.83$ 39,170.04$ 19.05%
200-00-57520-160-000 Water Life Insurance 53.46$ 260.70$ 212.94$ 260.70$ 22.43%
200-00-57520-000-120 Benefits 6,294.35$ 3,755.58$ 17.82$ -$
200-00-57520-000-125 Benefits 40,996.54$ 39,040.30$
SUBTOTAL - BENEFITS 47,670.21$ 42,995.88$ 34,955.70$ 40,626.97$ 40,249.11$ 48,745.41$ 21.11%
200-00-57520-000-200 Plant & Operations - UTL 5,047.87$ 5,252.68$ 4,160.52$ 5,266.95$ 5,500.00$ 5,500.00$ 0.00%
200-00-57520-000-620 Power for Pumps 28,137.75$ 24,566.00$ 24,628.73$ 28,364.44$ 25,000.00$ 29,000.00$ 16.00%
200-00-57520-000-660 Transportation Exp 3,300.38$ 71.72$ 501.96$ 550.00$ 250.00$ 500.00$ 100.00%
200-00-57520-000-700 Gasoline 1,712.81$ 2,002.20$ 1,225.13$ 1,542.49$ 1,500.00$ 1,650.00$ 10.00%
200-00-57520-000-710 Office Supplies -$ 1,412.50$ 252.22$ 252.22$ 150.00$ 250.00$ 66.67%
200-00-57520-000-800 Maint WTP 8,857.91$ 21,731.46$ 9,056.91$ 13,665.66$ 12,000.00$ 12,000.00$ 0.00%
200-00-57530-000-630 Chemicals - Treatment 30,395.22$ 12,735.95$ 12,885.68$ 17,058.24$ 15,000.00$ 17,500.00$ 16.67%
200-00-57530-000-640 Supplies & Exp 17,030.58$ 18,989.62$ 11,632.09$ 11,693.00$ 19,000.00$ 12,500.00$ -34.21%
SUBTOTAL - PLANT MAINT & OPS 94,482.52$ 86,762.13$ 64,343.24$ 78,393.00$ 78,400.00$ 78,900.00$ 0.64%
Prepared by Steven Cherek 10/17/2025 Page 1
page 3 ACTUAL ACTUAL As Of 10/16/2025 Projected Adopted PROPOSEDYOY Percent
EXPENDITURES 2023 EXPENSES2024 EXPENSES2025 EXPENSES2025 Year End2025 Budget 2026 BUDGET Change
200-00-57540-000-626 Main Construction -$ -$ -$
200-00-57540-000-650 Maint Reservoirs 568.31$ 1.61$ -$ 1,500.00$ 1,500.00$ 1,500.00$ 0.00%
200-00-57540-000-651 Maint Mains 3,651.84$ 4,991.48$ 4,565.33$ 9,565.33$ 18,000.00$ 18,000.00$ 0.00%
200-00-57540-000-652 Maint Services 3,589.88$ 1,908.80$ 2,910.70$ 2,910.70$ 3,000.00$ 3,000.00$ 0.00%
200-00-57540-000-653 Maint Meters 11,507.94$ 5,752.73$ 6,518.95$ 6,518.95$ 12,000.00$ 12,000.00$ 0.00%
200-00-57540-000-654 Maint Hydrants 5,545.88$ 3,139.89$ 22,567.39$ 22,553.40$ 5,000.00$ 5,000.00$ 0.00%
200-00-57540-000-655 Maint Wells 2,805.55$ 728.05$ 6,369.97$ 6,369.97$ 1,500.00$ 1,000.00$ -33.33%
200-00-57541-000-655 Maint Wells 429.88$ 193.86$ 1,613.11$ 3,613.11$ -$ 500.00$
SUBTOTAL - DISTRIBUTION MAINT & OPS28,099.28$ 16,716.42$ 44,545.45$ 53,031.46$ 41,000.00$ 41,000.00$ 0.00%
200-00-57580-000-426 Debt PMT Prinicpal 0.41$ 0.47$ 31,958.29$ 61,705.83$ 55,365.62$ 25,000.00$ -54.85%
200-00-57580-000-427 Debt Payment Int 37,964.12$ 26,744.65$ 9,688.28$ 9,688.28$ 16,028.50$ 15,030.00$ -6.23%
SUBTOTAL - DEBT PAYMENTS 37,964.53$ 26,745.12$ 41,646.57$ 71,394.11$ 71,394.12$ 40,030.00$ -43.93%
200-00-57580-000-681 Supplies -$ -$ -$
200-00-57580-000-682 Outside Services 6,933.00$ 20,077.25$ 11,909.38$ 12,548.77$ 15,000.00$ 15,000.00$ 0.00%
200-00-57580-000-683 Billing & Accounting 297.73$ 383.62$ 41.70$ 41.70$ 1,500.00$ 500.00$ -66.67%
200-00-57580-000-684 Insurance 12,867.13$ 13,565.03$ 13,892.24$ 15,154.00$ 15,000.00$ 11,663.00$ -22.25%
200-00-57580-000-688 Regulatory Exp (PSC) -$ -$ 1,113.54$ 1,113.54$ -$ 600.00$
200-00-57580-000-689 Misc Exp 2,206.74$ 5,605.10$ 4,283.06$ 4,555.56$ 2,250.00$ 2,250.00$ 0.00%
200-00-57580-000-690 Uncollectable A/R -$ -$ -$ -$
200-00-57580-393-000 Blood Work - New Hire 72.50$ -$ -$ 100.00$ 100.00$ 0.00%
200-00-57580-500-000 Accrued Sick Leave -$
200-00-57595-000-403 Depreciation 88,505.00$
200-00-57595-000-426 Dep On Contr Plant 87,279.00$
200-00-59000-000-000 Interest Exp -$
SUBTOTAL - ADMIN COSTS 22,377.10$ 215,415.00$ 31,239.92$ 33,413.57$ 33,850.00$ 30,113.00$ -11.04%
200-00-57595-000-408 Tax Equivalent 108,000.00$ 100,375.00$ -$ 108,000.00$ 108,000.00$ 108,000.00$ 0.00%
SUBTOTAL - TAX EQUIVALENT108,000.00$ 100,375.00$ -$ 108,000.00$ 108,000.00$ 108,000.00$ 0.00%
ACTUAL ACTUAL As Of 10/16/2025 Projected Adopted PROPOSEDYOY Percent
200-00-56300-000-000 Capital Projects 2023 EXPENSES2024 EXPENSES2025 EXPENSES2025 Year End2025 Budget 2026 BUDGET Change
Hydrant replacement - car damage, inc paid 339,318.15$ 6,037.50$ 6,037.50$
SCADA - Water Side -$ 2,304.84$
Well 1 Replacement Study including test well if needed -$ 29,193.00$ 63,433.00$ 150,000.00$ -$ -100.00%
Water Tower, Resivor, Inspection 20,000.00$ -$
Clear Well Bypass
Flouride updates -$ 1,328.04$ 1,328.04$
Sensus Meter Reading Package -$
Scales and Pumps in Chemical Room -$ -$
New Boilers in Water Plant -$
SUBTOTAL - Capital Project Fund Transfer339,318.15$ 2,304.84$ 36,558.54$ 70,798.54$ 170,000.00$ -$ -100.00%
TOTAL EXPENDITURES 767,949.01$ 590,488.92$ 333,380.43$ 566,731.15$ 650,815.52$ 483,913.18$ -25.65%
TO (FROM) RESERVE 114,733.79$ (52,839.47)$ 164,567.14$ 4,706.28$ 24,174.50$ 41,107.05$ 70.04%
Prepared by Steven Cherek 10/17/2025 Page 2
ACTUAL ACTUAL As Of 10/16/2025 Projected Adopted PROPOSEDYOY Percent
REVENUES 2023 REVENUES2024 REVENUES2025 REVENUES2025 Year End2025 Budget 2026 BUDGET Change
WATER SALES 522,223.98 $ 525,713.77$ 449,417.36$ 522,647.36$ 523,140.02$ 523,170.23$ 0.01%
OTHER WATER REVENUE 3,458.82$ 11,935.68$ 48,530.21$ 48,790.07$ 1,850.00$ 1,850.00$ 0.00%
PROCEEDS FROM BORROWING 357,000.00$ -$ -$ -$ 150,000.00$ -$ -100.00%
-$ 1.00$ -$
TOTAL REVENUE 882,682.80$ 537,650.45$ 497,947.57$ 571,437.43$ 674,990.02$ 525,020.23$ -22.22%
ACTUAL ACTUAL As Of 10/16/2025 Projected Adopted PROPOSEDYOY Percent
EXPENDITURES 2023 EXPENSES2024 EXPENSES2025 EXPENSES2025 Year End2025 Budget 2026 BUDGET Change
BOARD WAGES & EXPENSE - $ 503.68$ 726.57$ 988.12$ 1,746.88$ 1,746.88$ 0.00%
WAGES 90,037.22$ 98,670.85$ 79,364.44$ 110,085.38$ 106,175.41$ 135,377.89$ 27.50%
BENEFITS 47,670.21$ 42,995.88$ 34,955.70$ 40,626.97$ 40,249.11$ 48,745.41$ 21.11%
PLANT MAINTENANCE & OPS 94,482.52$ 86,762.13$ 64,343.24$ 78,393.00$ 78,400.00$ 78,900.00$ 0.64%
DISTRIBUTION MAINTENANCE & OPS 28,099.28$ 16,716.42$ 44,545.45$ 53,031.46$ 41,000.00$ 41,000.00$ 0.00%
ADMINISTRATIVE COSTS 22,377.10$ 215,415.00$ 31,239.92$ 33,413.57$ 33,850.00$ 30,113.00$ -11.04%
TAX EQUIVALENT 108,000.00$ 100,375.00$ -$ 108,000.00$ 108,000.00$ 108,000.00$ 0.00%
Debt Service Fund Transfer 37,964.53$ 26,745.12$ 41,646.57$ 71,394.11$ 71,394.12$ 40,030.00$ -43.93%
Capital Project Fund Transfer 339,318.15$ 2,304.84$ 36,558.54$ 70,798.54$ 170,000.00$ -$ -100.00%
-$
TOTAL EXPENDITURES 767,949.01$ 590,488.92$ 333,380.43$ 566,731.15$ 650,815.52$ 483,913.18$ -25.65%
TO (FROM) RESERVE 114,733.79$ (52,838.47)$ 164,567.14$ 4,706.28$ 24,174.50$ 41,107.05$ 70.04%
2026 WATER DEPARTMENT BUDGET SUMMARY
Prepared by Steven Cherek 10/17/2025 Page 3
Past 3 Year Water Trends
01,000,0002,000,0003,000,0004,000,0005,000,0006,000,0002023 2024 2025Residential01,000,0002,000,0003,000,0004,000,0005,000,0006,000,0007,000,0008,000,0009,000,00010,000,0002023 2024 2025Industrial0500,0001,000,0001,500,0002,000,0002,500,0002023 2024 2025Commercial0200,000400,000600,000800,0001,000,0001,200,0001,400,0001,600,0001,800,0002,000,0002023 2024 2025Public Authority0100,000200,000300,000400,000500,000600,0002023 2024 2025Pump House0200,000400,000600,000800,0001,000,0001,200,0001,400,0001,600,0002023 2024 2025Multifamily02,000,0004,000,0006,000,0008,000,00010,000,00012,000,00014,000,00016,000,00018,000,00020,000,0002023 2024 2025Past Total Water Billed Consumption by Quarter
Prepared by Steven Cherek 10/17/2025 Page 4
RESOLUTION NO. U-2025-11-12, VILLAGE OF MARATHON CITY,
MARATHON COUNTY, WISCONSIN AUTHORIZING WASTEWATER RATE
INCREASES
WHEREAS, the Village owns and operates a Wastewater Utility providing wastewater
services to the Village of Marathon City; and
WHEREAS, the revenues and rate of return for the Wastewater Utility must be sufficient
to meet the Clean Water Loan Fund (CWLF) requirements for the term of the loan; and
WHEREAS, the revenues and rate of return for the Wastewater Utility must be sufficient
to meet the Wastewater Utility portion of the 2025A Series General Obligation Promissory
Note requirements for the term of the loan; and
WHEREAS, the Wastewater Utility has implemented a stepped rate increase schedule
consisting of two increases beginning with the 4th quarter 2025 billing cycle (reflected on
the January 1, 2026 bill), and the 4th quarter 2026 billing cycle (reflected on the Januar y
1, 2027 bill); and
WHEREAS, an additional rate increase, to be determined during the 2027 budget review,
will be required for the 4th quarter 2027 billing cycle (reflected on the January 1, 2028 bill)
to meet 2025A Series General Obligation Promissory Note requirements based on the
anticipated loan amount.
NOW, THEREFORE, BE IT RESOLVED AS FOLLOWS:
As required by Ordinance 6.2.82, the Village Board of Trustees authorizes:
• A 5.5% wastewater rate increase effective for the 4th quarter 2025 billing cycle, to
be reflected on the January 1, 2026 bill.
• An additional 5.5% wastewater rate increase effective for the 4th quarter 2026
billing cycle, to be reflected on the January 1, 2027 bill.
The foregoing Resolution was duly adopted by the Marathon City Village Board of
Trustees by a vote of ___ in favor, ___ against and ___ abstained, on this 12
th day of
November, 2025.
VILLAGE OF MARATHON CITY
By: ___________________________________
Kurt Handrick, President
ATTEST:
______________________________________
Cassie Lang, Village Clerk