Forestry & Recreation Committee
December 8, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 1:00 PM by Scott Mildbrand.
Members Present: Scott Mildb rand, Gary Beadles, Jim Gebauer, Myron B rooks, and Rollie
Thums.
Members Absent: None.
Other Attendees: Jake Walcisak, Alex Solawetz, Larry Brandl, Nicole Hager, Tanisha Macdonald,
Timothy Allen-DNR County Forest Liaison, Bud Suckow, and Brian Wilson-Star News.
Approve Minutes: Thums moved to approv e the minutes of the November 3 rd meeting;
seconded by Brooks. Motion carried.
Approve Agenda: Thums moved to approv e the agenda of 14 items; se conded by Gebauer.
Motion carried.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Milbrand info rmed the
Committee he would be voting no on the approval of the bills . Mildbrand stated he thinks the
County spends too muc h money on new equipmen t, specifically the Forestry Department.
Mildbrand’s objection was limited to the p urchase of a new ATV by the Forestry Department,
which was budgeted for and previously approved. The Forestry Department ’s current ATV was
passed down to the Buildings/Grounds/P arks Department as the ATV they were using was
handed down from Forestry in the mid 1990 ’s. Brooks moved approve the bills spreadsheet as
presented; seconded by Beadles. Three voting yes, Mildbrand voting no , Thums abstained due
to his relative being one of the payees on the monthly bills. Motion carried.
Chelsea Lake Dam Crop Damage Invoice: Thums moved to approve compensation of $581.46
for crop loss on Mayer Farms property, not including the fee of $125 for crop loss assessment ;
seconded by Gebauer . Discuss ion ensued about Mayer Fa rms hiring Dan Hoffman’s appraisal
services. Mild brand felt that si nce Taylor County did not have a consultant to do a land
assessment on the crop loss ; Mr. Hoffmans services s hould be compensated. Without M r.
Hoffmans appraisal Taylor County would not have be en able to determine the correct
calculations of crop loss/acre. Thums and Gebauer rescinded their pre vious motions. Thums
then moved to approve the compensation of $581.46 t o Mayer Fa rms and $62.50 to Dan
Hoffman appraisal services; seconded by Beadles. Motion carried.
Timber Sales Update: Solawetz provided the following update.
• #688, North Loop Aspen, Czarnezki Forest Products.
▪ This is a 35 -acre aspen, red maple, and black ash sale. The contractor
harvested 21 acres earlier this summer. They moved in a dozer recently and
began freezing down roads . They expect to move in shortly afte r the new
year.
• #695, Funky Chevrons, Wilson Forestry.
▪ Harvesting began Monday October 2 nd. Progress has been slow at times
due to soft ground conditions on access roads and main skid trails. This sale
is 116 acres and has approximately 35-40 acres remaining.
• #708, North Pole, Smola Enterprises.
▪ Harvesting began on Monday October 9th. Skidding was comple ted on
November 29th and only final hauling and payment remains. This was a 53 -
acre sale.
• #711, Oak Awareness, Smola Enterprises.
▪ Harvesting o f this 6 -acer sale began on November 29 th. Harvesting and
skidding we re compl eted on December 1 st and only final ha uling an d
payment remains.
Close Out Timber Sale # 681 Czarnezki Products: Walcisak handed out the revenue report for
this sale. The volume was underr un by 18% while the value was underru n by 13%. All contra ct
items have be en complete d and final in voices have be en paid. No pending items. Gebauer
moved to approve the close out of timber sale #681; seconded by Thums. Motion carried.
Close Out Timber Sale # 705 Smola Enterprises: Walcisak handed o ut the revenue report for
this sale. The volume was overrun by 14% while the value was overrun by 13%. All contract items
have been completed and final in voices have been paid. No pending items. Thums moved to
approve the close out of timber sale #705; seconded by Gebauer. Motion carried.
Approve Timber Sale Bids : Walcisak presented the fall tim ber sale bids. Al l three (3) sales
received qualifying bids with a total bid value of $234,969.50.
• Tract #5-23, Gapportunity: There were four (4) qualifying bids. Czarnezki Forest Products
had the highest bid of $93,499.00.
• Tract #6-23, UWSP: There were four (4) qualifying bids. Czarne zki Forest Products had
the highest bid of $93,662.00.
• Tract #7-23, Spirits Falls: Th ere were four (4) qualifying bids. Cz arnezki Forest Products
had the highest bid of $47,808.50.
• Total bid value of $234,969.50, which is 62.6% over the advertised minimum sale value.
Motion made by Brooks to approve the highest bidder for tracts #5 -23, #6 -23, a nd #7-23;
seconded by Beadles. Motion carried.
Improved Forest Management Carbon Credit Project Development: Walcisak provided an
update for the Committee and highlighted the information provided ove r the last year.
Discussion of pros and cons ensued between the Committee, Walcisak, Finance Director Larry
Brandl and Bud Suckow. Thums moved to not recommend Taylor County’s participation in a
Forest Carbon project at this time; seconded by Gebau er. Three voting yes, Brooks and Beadles
voting no. Motion carried.
DNR Cou nty Forest Liaison Report: Timothy Allen provided the follow ing update . The past
month the DNR have been working on timber sale establishment in Compartment 107 , Stand 5.
In the coming month they will finish that and start work on Compartment 115, Stand 15. County
time standards are approximately 55% complete for the fiscal year so they are in a good
position to fulfil their commitment.
Remote Work R equest: On N ovember 22nd Walcisak s ubmitted a n online request form to
Human Resources Director Nicole Hager to work remote ly 1-4 days per week. On November
30th IT Director Melissa Linda and Hager distributed a draft policy for department heads wishing
to work remotely. Walcisak presented information which detailed the Count y’s current remote
work policy, how he can meet all eligibility requirements of this policy, how it would benefit the
County, and how his past 10 plus years of work p erformance/efficiency prove he is a good
candidate for remote work. Additionally, Walcisak has shown the ability t o be responsive and
available remotely even when he is off work using PTO. This position supervises only one
employee but also utilizes the shared Administrative Support position with Zoning to complete
the department ’s work plan and provide office coverage. Office needs for this position vary
depending on the time of year and project type. During the winter and spring Walcisak is
typically in the office 4-5 days per week with very limited field work. During the summer and fall
Walcisak is in the office 1-3 days per week with an increased amount of fieldwork. Walcisak said
his request for remote work is to be used consistent with the demands of this position as they
change throughout the year and never to exceed 4 days per week. Walcisak stated, “I am asking
that my employer provide an approval consistent with the policies which are in place.
Reiterating the policy which states, Taylor County strives to be flexible in their approach to work
styles and location and offers employees the ability to perform certain job duties away from the
regular workplace.”
Thums moved to deny Walcisak’s request for remote work ; seconded by Gebauer. Three voting
yes, Brooks and Beadles voting no. Motion carried.
Administrator Report: Walcisak Provided the following updates.
• Camp 8 Dam: Dock is nearly complete and will be delivered within a week or two. Repairs
have been made to the boat landing and turn around area. The water level is being held
approximately 2-3 feet below the drop inle t to all for sho reline vegetation management
of willow and cattails. This will occur when the ground is sufficiently frozen.
• Chelsea Lake Dam: As of last week , the water level was 1 to 1.5 inc hes below the dr op
inlet crest.
• On November 8th the Rib Lake Town board passed a resolution to support the purchase
of the Voster ’s property . The Know les-Nelson grant application which Walcisak
submitted for the Voster’s land purchase has been approve d and ranked by the DNR. IT
is now schedules to go before the State – Legislature Joint Finance Committee in early
January for final review/approval.
• Golden Sands Resource Conservation and Development Council is currently pursuing a
candidate to fill an LTE position which will provide 500 hours of work annually to the
Taylor County Forestry Department in 202 4, 2025 and 2026 . This individual is funded
through a United States Forest Service grant awarded to Walcisak in 2023. The individual
is an employee of Golden Sands and will conduct contract labor in the County Forest.
This position is funded 100% through the grant and in-kind labor match.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday,
January 5th, 2024, at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Thums moved to adjourn the meeting; seconded by
Gebauer. Motion carried. The meeting was adjourned at 2:01 PM.
Secretary: Tanisha Macdonald
Forestry & Recreation Committee
November 3rd, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:30 AM by Scott Mildbrand.
Members Present: Scott Mildb rand, Gary Beadles, Jim Gebauer, Myron B rooks, and Rollie
Thums.
Members Absent: None.
Other Attendees: Jake Walcisak , Alex Solawetz, Jim Metz, Larry Brandl, Justin Meyer -County
Land Surveyor, Timothy Allen-DNR County Forest Liaison, and Brian Wilson-Star News.
Approve Minutes: Gebauer moved to approve the minutes of the October 6th, 2023, meeting;
Seconded by Thums. Motion carried.
Approve Agenda: Thums moved to approve the agenda of 11 items; Seconded by Gebauer.
Motion carried.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Brooks moved to approve the
bills spreadsheet as presented; Seconded by Beadles. Motion carried.
LiDAR (Light Detection and Ranging) Data Funding Request: County Land Surveyor Justin
Meyer and Walcisak presented the pro ject and funding request. The C ommittee discussed the
merits of more accurate technology and use cas es the County and its residents could u tilize.
Gebauer moved to fund $9,000 from the County Forestry reserve account for the LiDAR project;
Seconded by Thums. 4 aye, 1 no (Mildbrand). Motion carried.
Timber Sales Update: Solawetz provided the following update.
• #681, Big K West, Czarnezki Forest Products.
▪ All cutting and skidding is complete. Roads have remained in good shape
through recent rains. Final hauling remains.
• #703, Trembling Trout, Gumz Logging.
▪ All cutting and skidding is complete. Dozer work and road cleanup remain
along with final hauling.
• #695, Funky Chevrons, Wilson Forestry.
▪ Sale area is about 1/3 complete. Recent rains and wet conditions have been
slowing progress.
• #708, North Pole, Smola Enterprises.
▪ This sale started on October 9th. The contractor is about 25% complete.
Close Out Timber Sale #706 Smola Enterprises : Walcisak handed out the re venue report for
this sale. The volume overran by 12% while the value overran by 53%. T his was due to logs
cutting out better than antici pated. All wood had been haul ed and the final invoice has been
paid. Close out roadwork was conducted by the contract or and County. N o items pending.
Brooks mov ed to approve the close out of timber sale #706; Seconded by Brooks. Motion
carried.
Approve Timber Sale for Bid: Walcisak presented the fall timber sales for bid. He handed out a
prospectus, fall sale summary, sale location map, individual timber sale maps and individual sale
information sheets. Three sales were pres ented to the Committee for review , for a total of 368
acres containing 5,005 cords of pulp and bolts as well as 396,000 board feet of logs.
• Tract 5-23, Gapportunity: 146 acres of northern hardwood, swamp hardwood, aspen,
red maple and tamarack. Located on Emil Drive. Minimum bid value of $54,939.00.
• Tract 6 -23, UWSP : T his timber sale was establishe d in cooperation with UWSP
professor M ike Demchik and over 20 of his students. 145 acres of northern
hardwood, oak, swamp hardwood and aspen. Located on Camp 8 R oad. Minimum
bid value of $55,479.00.
• Tract 7-23, Spirit Falls: 77 acres of northern hardwood, swamp hardwood, aspen and
red maple. 74 acres of this sale are resold from a previously defaulted contract, (tract
6-18 Northwest Hardwoods). Minimum bid value of $34,090.00.
Bids will be accepted until Thursday December 7th at 3:00 pm and opened immediately. Beadles
moved to approve the three timber sales for adver tisement as presented; Seconded by Brooks.
Motion carried.
DNR County Forest Liaison Report: Timothy Allen provided the following update. The majority
of his and DNR Forestry Technician Jonathan Knusta’ s work over the past month has been spent
on timber sale establishment . Allen and Knusta will continue to work on the timber sale
establishment of the Gapporunity and UWSP County timber sales which will be advertised this
month.
Administrator Report: Walcisak Provided the Following Updates.
• Recent priorities have been timber sale a dministration, timber sale establishment,
dam reconstruction, road/gravel contracts. This aligns with our annual work plan and
forest management plan priorities. Trail mowing, wildlife projects and recreation
projects have not been accomplished in acco rdance with our plans. Staff time
limitations.
• Camp 8 Dam Update: The water level reached the drop inlet on October 9 th.
Shoreline and boat landing work had not yet bee n completed and the lake was
lowered approximately 4 feet until this work is done.
• All contracted gravel and road project s have been completed for t he season. This
includes improvements to Brad’s Blvd, Camp 8 ATV Trails and the Zuther Mill Grade.
Walcisak will continue to work on road and trail maintenance as weather allows.
• Corp Counsel is working with Mayer Farms Inc. to resolve crop damage payment for
use of their field during construction of the Chelsea Lake Dam.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday
December 8th, 2023 at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Gebauer moved to adjourn the meeting; Seconded by
Beadles. Motion carried. The meeting was adjourned at 11:04 am.
Secretary: Jake Walcisak
Forestry & Recreation Committee
October 6th, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:30 AM by Scott Mildbrand.
Members Present: Scott Mildb rand, Gary Beadles, Jim Gebauer, Myron B rooks, and Rollie
Thums.
Members Absent: None.
Other Attendees: Jake Walcisak , Alex Solawetz, Jim Metz, Larry Brandl, Timothy A llen-DNR
County Forest Liaison, and Brian Wilson-Star News.
Approve Minutes: Gebauer moved to approve t he minutes of the September 1st, 2023,
meeting; Seconded by Brooks. Motion carried.
Approve A genda: Thums moved to approve the agenda of 12 items; Seconded by Brooks.
Motion carried.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Brooks moved to approve the
bills spreadsheet as presented; Seconded by Beadles. Motion carried.
Timber Sales Update: Solawetz provided the following update.
• #681, Big K West, Czarnezki Forest Products.
▪ All cutting and skidding is complete. Roads have remained in good shape
through recent rains. Final hauling remains.
• #703, Trembling Trout, Gumz Logging.
▪ All cutting and skidding is complete. Dozer work and road cleanup remain
along with final hauling.
• #695, Funky Chevrons, Wilson Forestry.
▪ Pre-sale meeting was held Monday October 2nd. Harvesting began later that
day.
• #708, North Pole, Smola Enterprises.
▪ Contractor asked to start this sale. Alex and Timothy did a walk through
yesterday to assess the current conditions. Walcisak and Solawetz will
conduct a pre-sale meeting with the contractor on Monday October 9th.
• Fall timber sales will be presented to the Forestry Committee in November.
▪ Three sales for 379 acres.
o One re-sale of 80 acres. Default by NWH.
▪ 2023 sale establishment of 492 new acres and 80 re-sale acres.
Chelsea Lake Dam – Ayres Contract Amendment R equest: Walcisak presented a wr itten
contract amendment request submitted by Ayres Associates. This request was due to Pember
Companies contract non-compliance and failure to repeatedly not meet contract specifications.
This necessitated Ayres to cond uct several more sit e vis its than was accounted for in their
contract with Taylor County for the administration of this project. The increase in cost was in no
way caused by A yres Associates. Ayre’s diligence in this matter resulted in successful contract
completion by Pember Companies. Ayres has requested an additional $5,000.00 for the services
they provided above and beyon d their contract with Taylor County. The Committee generally
felt Ayres d eserved to be paid for the necessary extra work they conducted but that Pember
Companies should be the liability party rather than the County. Gebauer moved for Walcisak to
consult with corp counsel to possibly withhold $5,000.00 from Pember Companies final payment
to pay Ayres their amendment request; Seconded by Thums. Motion carried.
DNR County Forest Liaison Report: Timothy Allen provided the following update. The majority
of his and DNR Forestry Technician Jonathan Knusta’ s work over the past month has been spent
on timber sale establishment . Allen and Knusta will continue to w ork on the timber sale
establishment of the Gapporunity and UWSP County timber sales which will be advertised next
for sale next month.
Administrator Report: Walcisak Provided the Following Updates.
• Recent priorities have been timber sale a dministration, timber sale establishment,
dam reconstruction, road/gravel contracts. This aligns with our annual work plan and
forest management plan priorities. Trail mowing, wildlife projects and recreation
projects have not been accomplis hed in acco rdance with our pl ans. Staff time
limitations.
• Camp 8 Dam Update: Final walk through with engineer and contractor on September
13th. Substantial completion was met prior to the September 15 th contract deadline.
Today two of the final items will be completed. Install dam warning sign and staff
gauge. Silt fence will be removed when turf is sufficiently established. The water
elevation is approximately 7’ low currently. Walcisak is working with the Taylor
County Sportsmen club on the funding and purchase of a new dock. Also, Walcisak is
in the process of making improvements to the boat landing at Camp 8 Campground.
Rib Lake Fish and Game club would like to work with the County on installing about 4
fish cribs this winter.
• Chelsea Lake Dam Update: Final walk through with engineer and contractor on
September 13th. Substantial completion was met prior to the September 15th contract
deadline. Silt fence will be removed when turf is suf ficiently established. Walcisak will
work with County Land Surveyor to re -establish one disturbed benchmark. The
current water level is approximately 7” below normal pool. The land transfer and
easement with Mayer Farms Inc has been completed and recorded with the Register
of Deeds.
• Walcisak was given the State Forest Productivity Award for an unprecedented 6th year
in a row. Walcisak and staff have won this award each year since he has taken over
the Taylor County Forestry Department.
• Walcisak was invited by DNR to be an instructor yeste rday at a grant writing
workshop in Wausau. Over 80 people atten ded both in person and online. County,
City and Village staff from all over Wisconsin were represented.
• The land appraisal for the Voster’s property has been completed. Walcisak was able
to work through our realtor and the landowners to reduce the purchase price by
$11,600. The appraisal cost $3,000 and is a requirement of the Knowles -Nelson
Stewardship grant application. Additionally, t he grant has been submitted to the
DNR for review.
The Forestry Committee may go into Clos ed Session by taking a roll ca ll vote pursuant to
Section 19.85(1)(e), Wisconsin State Statutes, for deliberating, negotiating, or conducting
other specified pub lic business, whenever competitive or bargaining reasons require a
closed session . RE: The C limate Trust proposal for the Taylor C ounty Forest enrollment
into a forest carbon project. Walcisak provided the C ommittee a proposal from The Climate
Trust at the end of their September meeting for review with action occurring at this meeting.
The Committee discussed the merits of stayi ng in open session. W alcisak informed the
Committee that they did not need to go into closed session. This agenda item was posted in this
way so that they may go into closed session if they want ed to do so. The Comm ittee chose to
stay in open session for the discussion of this agenda item. The Committee discussed the large
revenue potential of this project, ($6 million) while also providing some concerns such as the 40-
year contract period with the American Carbon Registry and apprehension about the perception
for the American Carbon Regis try to cha nge the rul es during the contract period. Walcisak
provided ad ditional supporting information for enrollment in the p roject as well as an
explanation that the County would be locking into a specific protocol a t the time of enrollment,
and this could not change with the Am erican Carbon Registry during our 40-year contract. To-
date, nearly 1 million acres of the W isconsin County Fore sts 2.4 million acres statewide are
enrolled in this p rogram, comprised of nine counties. This means that nine county boards, nine
corporation counsels, DNR Forestry Division and DNR legal counsel have already reviewed and
approved of this pro gram. The Forestry Committee felt it necessary to educate the full county
board and pass this d ecision onto them without making a formal recommendation at th e
committee level. Mildbrand moved for Walcisak to present info rmation about the potential for
Taylor County to enroll in to a forest carbon project on the American Car bon Registry with
project development by The C limate Trust. Voting on the proposal by The Climate Trust would
happen later when the full County B oard is brought up to speed on forest carbon project
information; Seconded by Brooks. Motion carried.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday
November 3rd, 2023 at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Gebauer moved to adjourn the meeting; Seconded by
Beadles. Motion carried. The meeting was adjourned at 11:09 am.
Secretary: Jake Walcisak
Forestry & Recreation Committee
September 1st, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:30 AM by Scott Mildbrand.
Members Present: Scott Mildbrand, Gary Beadles, Jim Gebauer, Myron Brooks.
Members Absent: Rollie Thums – excused.
Other Attendees: Jake Walcisak , Jim Metz, Larry Brandl, Timothy A llen-DNR County Forest
Liaison, Bud Suckow, and Brian Wilson-Star News.
Approve Minutes: Brooks moved to approve the minutes of the August 7th, 2023, meeting;
Seconded by Gebauer. Motion carried.
Approve Agenda: Gebauer moved to approve the agenda of 12 items; Seconded by Beadles.
Motion carried.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Brooks moved to approve the
bills spreadsheet as presented; Seconded by Beadles. Motion carried.
Timber Sales Update: Walcisak provided the following update.
• #681, Big K West, Czarnezki Forest Products.
▪ High quality work continues. Roads are in grea t shape. Harvesting is about
three weeks from completion.
• #703, Trembling Trout, Gumz Logging.
▪ Job continues to go very well. Snowmobile trail will need dozer work prior
to sale close-out. Harvesting is planned for completion in late September.
• #705, Technician Tirade, Smola Enterprises.
▪ All cutting and skidding is complete. Approximately 100 cords of wood are
on the landing to haul. Remaining items include: culvert repair/replacement,
bucking high stumps, town road shoulder cleanup.
DNR County Forest Liaison Report: Timothy Allen provided the following update. The majority
of his and DNR Forestry Technician Jonathan Knusta’ s work over the past month has been spent
on timber sale establishment . Allen and Knusta both have upcoming annual training a nd will
continue to work on the timber sale establishment of the Gapporunity and UWSP County timber
sales.
Update County Code Chapter 2.08(2) Forestry and Recreatio n Committee : On June 22 nd,
2023, HR Director Nico le Hager re quested that each department head lo ok at their portion of
County Code Chapter 2 for potential updates. On Friday August 7th, Walcisak presented updates
which bring this chapter into compliance with existing State Statute and departmental practices.
No authorities w ere c reated or changed as compared to the current versi on. The Committee
discussed these items and directed Walcisak to make specific changes and bring it back to them
for review at today ’s meeting. Walcisak presented the reque sted updates as directed by the
Committee. Brooks moved to approve the updates to Chapter 2.08(2) Forestry and Recreation
Committee as presented and s end onto the C ounty Board; Seconded by Gebauer. Motion
carried.
2022 Annual Ac complishment Report: Walcisak distributed the report via email prior to the
meeting. Walcisak presented the report and discussed it with the Committee. 2022 was a record
high year for Forestry revenue which is generated from the sale of tim ber, firewood permits,
bough permits, and equipment use on grant funded projects. Total department revenue in 2022
was $771,037. Seven new timber sales were sold for a total of 469 acres. There were 16 timber
sales with activity and 11 timb er sales completed in 2022. Twenty-three grants were active in
2022 with a value of $708,759. Seven grants were closed out in 2022 with a value of $263,695. A
record high severance payment to towns was made in 2022 with $68,556.93 to Rib Lake and
$4,350.30 to Westboro. State statute dictates that 10% of all timber revenue must be paid to the
towns with C ounty Forest property. Additionally, a record high was set in 2022 for the amount
provided to the General Fund at $479,096. In 2022 the Forestry Department return ed 72% of
generated revenue to local units of government (Taylor County, Rib Lake, W estboro) for
$552,003. Gebauer moved to a pprove the 2022 Annual Accomplishme nt Report as presented;
Seconded by Beadles. Motion carried.
2024 Annual Work Plan: Walcisak distributed the 2024 annual work plan to the Committee via
hard copy mail prior to the meeting. Walcisak reviewed the work plan with the Committee and
answered several questions. Brooks moved to approve the 2024 Annual Work Plan as presented
and send onto the County Board; Seconded by Beadles. Motion carried. A resolution was signed
by all Committee members present.
Chelsea Lake Dam and Camp 8 Dam Upd ates: Walcisak provided the follow ing information.
Chelsea Lake Dam is scheduled for completion the week of September 4th. The coffer dams and
pumps were removed on August 9 th. The water level is currently 9 inches b elow the full pool.
Chelsea Lake is re -watering as mother nature allows. County Board Supervisor Bud Suckow was
present and asked several questions regarding grants, field restoration and water levels.
Camp 8 Da m dewatering began on J uly 20 th with a draw down of no more than 6 ” per day.
Groundbreaking occurred on Thursday August 1 7th. Substantial c ompletion was achieved on
Thursday August 31st. The pumps were removed that day and Camp 8 Dam is also re-watering
as mother nature allows. Final landscaping , seeding, mulching, etc. will be completed the week
of September 11th.
Administrator Report: Walcisak Provided the Following Updates.
• Awarded Sustainable Forestry Grant for logging road storm damage clean up $6,500.
• Awarded $266,668 in ATV and Snowmobile trail grants at the DNR Fundings
meetings held on August 30th and 31st in Weston, WI.
▪ In 2023, Walcisak has applied for and recei ved 15 state or federal grants for
a total of $787,274. This is a single year all-time high. In addition, $13,972 in
grants are pending approval.
• Completed onsite visit of pote ntial rifle range on the County Forest with Range
Consultant Jeff Nass. He supports the location and has provided recommendations
for development.
• Voster’s land appraisal has been completed. Waiting on the report.
• WCFA Board of Directors meeting on Tuesd ay September 26 th at 10:00 am in
Hayward at the Flat Creek Lodge.
• Ribbon cutting of the newly developed IAT segment which includes a portion of the
County Forest on Sunday October 1st.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday
October 6th, 2023 at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Brooks moved to adjourn the meeting; Seconded by
Beadles. Motion carried. The meeting was adjourned at 10:45 am.
Secretary: Jake Walcisak
Forestry & Recreation Committee
August 7th, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:30 AM by Scott Mildbrand.
Members Present: Scott Mildbrand, Gary Beadles, Rollie Thums, Jim Gebauer, Myron Brooks.
Members Absent: N/A
Other Attendees: Jake Walcisak , Alex Solawetz , Jim Metz, Larry Brandl, Timothy A llen-DNR
County Forest Liaison, Bud Suckow, Shawn McSherry, and Brian Wilson-Star News.
Approve Minutes: Thums moved to approve t he minutes of the July 7 th, 2023, meeting;
Seconded by Gebauer. Motion carried.
Approve Agenda: Gebauer moved to approve the agenda of 12 items; Seconded by Brooks.
Motion carried.
The Climate Trust – Forest Carbon Project Development: Jeremy Koslowski from The Climate
Trust addressed the Committee with a presentation which included company history, company
strategic plan, carbon cre dit background, steps of a n Improved Fore st Management (IFM)
carbon development project, estimated costs /revenues, and project mo nitoring. The Cl imate
Trust is a non profit which was developed in 1997 and holds strong to conservation and
stewardship of natural resources . Th ey are guided by a strategic plan w hich prioritizes their
partner with likeminded landowners and the selling of carbon credits to likeminded buyers. The
Climate Trust Strate gic P lan 20 22-2027 wi ll be distri buted to C ommittee members as a PDF
document via em ail. “The C limate Trust e nsures carbon offsets that are delivered and retired
meet rigorous, third -party standards to provide t angible benefits for communities and the
environment.”
Forest Carbon is another forest pro duct such as logs, pul p, firewood, and b oughs. The free
market has determined this product to have significant value. Only sustainably managed forests
are el igible t o enroll and s ell carbon credits. Forest landowners must show proof of a state
approved forest management plan. W hich T aylor C ounty does possess. The other eligibility
requirement is the landowner can not harvest more timber th an they grow. T his is often a
definition for sustainable forest management. The Taylor County Forest was created in 1935 and
has shown evidence of sustainable forest management since its inception.
Carbon cre dits developed from IFM projects are marketed on the Ame rican Carbon Registr y
(ACR). The ACR requires a 40-year commitment from landowners when marketing and selling
carbon credits. Under the current pro posal, Taylor County would be eligible to enroll a ll
productive forest land within the Taylor County Forest (14,813 acres) into this project. All entities
marketing carbon credits on the ACR must submit approximately 15% of all credits issue d to a
shared insurance pool. This insurance poo l co vers p articipating lan downers who experience
unavoidable carbon removals such as natural disasters.
Net revenue for Taylor County is estimated at $6 million. Credit issuance and payments to the
County span a period of year one to year 20. The distribution of funds is heavily weighted to the
first four years, with Taylor County receiving $3 to $4 million during that short period.
The landowner is required to monitor the project area and re -inventory the forest once every
five years. Duri ng the fir st 20 y ears this is the respo nsibility of The C limate Trust under their
current proposal. During the second 20 years the landowner must either conduct inventories o n
their own or contract with a company capable of doing the inventor ies. The Climate Trus t
recommends escrowing approximately $200,000 to pay for the required monitoring between
year 2 1 and 4 0. The expected duration of project establishment and issuance/sale of c arbon
credits is 18-24 months.
The Committee asked Koslowski several questions and discussed each thoroughly.
The Climate Trust will be providing a confidential propo sal to Walcisak for review. The Forestry
Committee will consider this proposal at a future meeting.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Brooks moved to approve the
bills spreadsheet as presented; Seconded by Beadles. Motion carried.
Update County Code Chapter 2.08(2) Forestry and Recreatio n Committee : On June 22 nd,
2023, HR Director Nico le Hager re quested that each department head look at their portion of
County Code Ch apter 2 for potential upda tes. Walcisak present ed updates which bring this
chapter into compliance with existing State Statute and departmental pr actices. No authorities
were c reated or changed as compared to the current versi on. Mildbrand opposed several of
these proposed changes. His c oncern in some of these instances was granting the Wisconsin
DNR more authority. Walcisak assured Mildbrand these proposed changes in no way expand the
scope of DNR authority over the Forestry program and will simply bring us into compliance with
State Statute. Most notably, Wisconsin §28.11 Administration of County Forests. The Committee
further discussed these items and directed Walcisak to make specific changes and bring it back
to the Committee for another review at the next meeting.
Timber Sales Update: Walcisak provided the following update.
• #681, Big K West, Czarnezki Forest Products . This s ale was approximately 50%
complete September 2022. On July 25th, 2023, Czarnezki moved from County Forest
sale #688, with harvesting commencing immediately. Czarnezki plans to stay on this
job until completion. Excellent woodmanship and high-quality work.
• #688, North Loop Aspen, Czarnezki Forest Products. Czarnezki completed all summer
ground harvest areas. Approximately 60% of this sale is complete with 14 of 35 acres
remaining. They will return to complete the remainder of this sale when the ground is
frozen.
• #703, Trembling Trout, Gumz Logging. Dry conditions have allowed harvest
operations even though this was sold as a winter job. This sale is approximately 70%
complete. High-quality work and a conscientious contractor.
• #705, Technician Tirade, Smol a Enterprises. The contractor star ted t his job on J uly
10th, 2023 . The harvest area is approximately 50% complete. Several contract non-
compliance issues have developed. Walcisak is actively working with the contractor
to gain compliance in these areas.
• #706, DaVinci, Smola Enterprises. This job is complete. Final hauling and road work
have been completed. Future close-out pending final invoice and payment.
Chelsea Lake Dam and Camp 8 Dam Upd ates: Walcisak provided the follow ing information.
Chelsea Lake Dam is very near completion. Sub standard imp orted embankment fill has slowed
progress recently and caused a de lay of about 2 w eeks. New fill has been located w hich meets
the construction specifications. It is estimated that construction will be completed either the last
week of August of the first week of September . Chelsea Lake shoreline resident and C ounty
Board Supervisor, Bud Suckow, attended the meeting and had several questions regarding the
water levels.
Camp 8 Da m dewatering began on J uly 20 th with a draw down of no more than 6 ” per day.
Equipment will be mobilized to the site the week of August 14 th and e arthwork will begin
immediately. This project must be substantially complete no later th an September 15th per our
contract with Minger Construction . Thums invited Walcisak to attend the upcoming Rib Lake
Fish and Game Club meetin g on S eptember 7 th at 7 :00 pm to discuss the club financially
supporting fishing pier and fish habitat projects at Camp 8 Flowage.
Proposed 2024 Department Budget: Walcisak presented a proposed department budget with
operations increasing only $450.00 or 0.49% from 2023. Several changes were made to re flect
historic trends and averages. The most notable budget reduc tions were to Dam
Repair/Maintenance (-$1,500.00), and Equipment Usage Revenue (-$2,000.00) as compared to
2023. The most no table budget increases were to ATV Outlay and Vehicle Outlay a t $1,000.00
each as well as Paint /Forestry Supplies and Forestry Equip ment Outlay at $500.00 each as
compared to 2023. The following amendments were made: decrease Social Security and
Retirement line items of the C ounty Forest Administrator to reflect actual expenses, decrease all
wage and benefits items for Assistant Forest Administrator to reflect actual expenses, decrease
Secure Rural Schools Title III revenue from $10,0 00 to $5,000 as intended. Thums moved to
approve t he proposed 202 4 Forestry Departmen t budget as amended ; Seconded by Brooks.
Motion carried.
DNR County Forest Liaison Report: Timothy Allen provided the following update. The majority
of his and DNR Forestry Technician Jonathan Knusta’ s work over the past month has been spent
on timber sale establishment. DNR will continue to work on timber sale establishment and assist
with sale administration as requested.
Administrator Report: Walcisak Provided the Following Updates.
• Walcisak introduced newly hire d County F orest As sistant Administrator Alex Solawetz.
His first day was Friday A ugust 4th. Alex provided the Committee with his education ,
experience, and background.
• Seasonal mowing of the Pine Line Trail shoulders has been completed.
• A DNR Timber Sale audit occurs once every five yea rs. This was conducted on July 25 th
and we passed with commendations.
• Walcisak has spent a significant amount of time recently on managing the workload of
2+ staff, dam replacement projects, filling staff vacancy, and training new staff. This work
is well above and beyond the typical requirements of the Departmen t’s annual work
plan. Task prioritization and project completion has been challenging.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday
September 1st, 2023 at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Thums moved to adjourn the meeting; Seconded by
Gebauer. Motion carried. The meeting was adjourned at 11:03 am.
Secretary: Jake Walcisak
Forestry & Recreation Committee
July 7th, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:30 AM by Scott Mildbrand.
Members Present: Scott Mildbrand, Gary Beadles, Rollie Thums, Jim Gebauer, Myron Brooks.
Members Absent: N/A
Other Attendees: Jake Walcisak, Jordan Lutz, Jim Metz, Ruthann Koch-County Corp Counsel,
Brian Wi lson-Star News, Jeff S cheirer-DNR Fisheries Biologist, Ad am Schneider – Ayres
Associates, Bruce Ommen – Ayres Associates, Keith Langenhahn Wisconsin Counties Association
- Zoom.
Approve Minutes: Thums moved to approve the minutes of the June 2nd and June 19 th, 2023,
meetings; Seconded by Gebauer. Motion carried.
Approve Agenda: Mildbrand requested to strike item 14 and address it at a later date. Thums
moved to approve the agenda of 14 items, striking item 14; Seconded by Brooks. Moti on
carried.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Brooks moved to approve the
bills spreadsheet as presented; Seconded by Gebauer. Motion carried.
Ayres A ssociates Inc : Ayres Presiden t Bruce Ommen and engineer Adam Schneider were in
person to pr esent a check for $ 30,000 to the Forestry and Rec reation Committee for the
settlement of a Municipal Dam Grant application omission dating back to 2020. The Committee
and Walcisak were very appreciat ive for the ir appearance in person an d for the high-quality
work provided by Ayres outside of this matter. C orp Counsel Koch pr esented Jim Metz with a
settlement agreement release for his signature. Formalizing the finality of this matter between
Ayres Associates Inc. and Taylor County. Metz signed the agreement promptly.
Timber Sales Update: Lutz provided the following update.
• #688, North Loop Aspen, Czarnezki Forest Products. Pre-sale meeting was held Thursday
July 6th with work starting immediately.
• #703, Trembling T rout, Gumz Logging. P rogress is consistent and they are doing a
quality job. The ground is staying firm with no concerns at this time.
• #705, Technician Tirade, Smola Enterprises. Pre-sale meeting scheduled for Monday July
10th.
• #706, DaVinci, Smola Enterprises. Felling by th e hot saw has been completed. Only
harvesting, skidding and trucking remain. They will bring a dozer onsite to clean up
roads and main skid tr ails. Large lo g overrun. There have been n on-compliance issues
with residual damage to saplings and overstory trees. This matter has been improving.
Request to F ill Assistant Administrator Vacancy: Walcisak h anded out the position
description and job posting. The position was posted on June 14 th and is open until July 17 th.
Interviews are anticipated in the week of July 24th with an ideal start in the week of August 14th.
Walcisak read the following, “Jordan has provided Taylor County nearly 6 years of service with
unmatched accomplishments in the forest industry. His great depth of knowledge and unrivaled
productivity have made him effectively irreplaceable. Jordan is, without a doubt, one of the top
field foresters in the state of Wisconsin. Over the last 5 years Taylor County has benefited from
Jordan’s silvicultural knowledge, outstanding work ethic, reliability, and the pride he takes in his
work. While I am certainly s ad to see Jordan go, I am extremely happy to watch him take this
next step of his career in forestry. Simply saying thank you doesn’t seem like enough.”
Thums question ed the need to re place the po sition. Noting that last yea r ther e was talk of
reducing the department by one position and they could now make the cut due to attrition.
Walcisak provided excerpts of supportive information he had offered to County Board members
last September and October. He also responded by saying last fall the full county board vot ed
on the issue of cutting the Forestry Department down to one position and it only received three
votes. Walcisak believes he has illustrated the need for two positions within this department and
has received the support of the full county board to maintain this staffing level. County Forest
Programs are governed by Wisconsin §28.11 . The primary objective of the County Fo rest Law is
to provide for the optimum production of forest products. This requires 1.35 full-time
equivalents ( FTE) to conduct all necessary forestry related work. The remaining 0.65 FTE is
dedicated to wildlife man agement, recreation, and watershed protection. This is defined in the
TCF 15 -year Management Plan and Annual W ork Plans. Both documents are reviewed and
approved by the full County Board.
Brooks moved to a pprove filling the Forestry Assistant Administrator position as presented ;
Seconded by Beadles. Thums requested a roll call vote. Mildbrand, Gebauer, Brooks and Beadles
voting yes. Thums voting no. Motion carried.
Camp 8 Flowage Draw down for Replacement – Fisheries and Recreation: Walcisak provided
an up date for the dam project. Dewatering will begin Thursday July 20 th. The draw down will
take approximately 25 days while only removing 6 inches of water per day to better allow fish to
move upstream . DNR Fisheries Biologist Jeff Scheirer provided a summary of the F all 2022
electroshocking survey and a nswered questions regarding the effects of the draw down to the
fish community and fish habitat. Scheirer is not expecting significant fish mortality due to the
draw down. Scheirer supports/recommends a fishing p ier, fish cribs within casting distance of
the pier and tree drops along the steep eastern shore. These features would increase the rate of
catch for anglers and i mprove the quality and q uantity of fish habitat within the flow age. The
Forestry Department has secu red quo tes for a fishing pier within the range of $13,000 to
$22,500. The preferred design is a floa ting 30’-40’ boardwalk with a “T” end section w hich has
two benches and rail ing. The Rib Lake Fish and Game Club and the Taylor County Sportsmen’s
Club ha ve both showed interest in providing funding to this project. While the Forest ry
Committee does not have a budget to purchase this pier, they are supportive of providing long-
term maintenance if local fund raising can cover the initial cost.
Sustainable Forestry Grant Applicat ion – Logging Road Storm Damage Cleanup: Walcisak
handed out a project map and grant application for Committee review and discussion. The
December 2022 ice, snow, and windstorm caused significant damage to Taylor County Forest ’s
logging road system of over 12 5 miles. This grant application is for the c leanup of the most
important and well used 54 miles of logging roads. Project total $1 4,000. Grant request
$10,150.00. Thums moved to a pprove the Sustainable Forestry Grant Applic ation as presented;
Seconded by Gebauer. Motion carried.
Resolution Authorizing the P urchase of Land for Entry into the Taylor County Forest:
Walcisak pres ented a resolution formalizing the Committee’s motion from June 2 nd, 2023, to
purchase 119.8 acres from Vosters et al for $263,560.00 plus associated costs such as appr aisal,
realtor and closing fees, contingent upon re ceiving Knowles Nelson Steward ship funding for
50% of the p urchase and associated costs plus simple majority approval by the County Board.
Gebauer moved to approve the resolution as presented; Seconded by Brooks. Roll call vote cast.
Mildbrand, Gebauer, Brooks and Beadles voting yes. Thums voting no. Motion carried.
DNR County Forest Liaison Report: Walcisak provided the following update. The bulk of DNR’s
work over the past month has been spent on timber sale establishment . They’ve also spent a
small amount of time on sale administration and a few hour s in meetings to discuss the
upcoming Asst. Admin. vacancy and how DNR can best as sist in moving f orward. DNR will
continue to work on timber sale establishment and assist with sale administration as requested.
Administrator Report: Walcisak provided an update on several items:
• Chelsea Lake Dam project started on We d June 28 th. Equipment and materials were
mobilized to the site starting Wed June 21st. Construction completion is expected in mid-
August.
• Dewatering is expected to start at Camp 8 Dam on July 20 th and take approximately 25
days. Substantial completion of the dam replaceme nt mus t be accom plished by
September 15th.
• Walcisak met with the Rib Lake Fish and Game Club and RLPD again on June 16th to look
at two potential sites. Site #1 was preferred by the group. Walcisak will meet with range
consultant Jeff Nass on August 18 th. Rib Lake Fish and Game and RLPD have been
invited.
• Walcisak has signed an NDA with The Climate Trust to continue discussions regarding a
future carbon offset project on the Taylor County Forest. The Climate Trust would like to
address the Committee at our August meeting to provide information.
• The shared Administrative Assistant position between Zoning and Forestry will be vacant
soon as the individual has accepted a position with another County office. This position
has traditionally contributed between 1.5 and 8 hour s of work per week to the Forestry
Department, depending on the individual’s skillset and availabil ity. The Forestry
Committee would like to see the Forestry Department and Forestry Committee i nvolved
in discussions regarding proposed chan ges to this posit ion and the
posting/hiring/interview/selection process.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be
Monday August 7th, 2023 at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Thums moved to adjourn the meeting; Seconded by
Gebauer. Motion carried. The meeting was adjourned at 10:54 am.
Secretary: Jake Walcisak
Forestry & Recreation Committee
June 19th, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 3:31 PM by Scott Mildbrand.
Members Present: Scott Mildbrand, Gary Beadles, Rollie Thums, Jim Gebauer, Myron Brooks.
Members Absent: N/A
Other Attendees: Jake Walcisak , Jordan Lutz, Brian Wi lson-Star News, Larry Brandl -County
Finance Director, Steve Mayer, and Rod Mayer (via zoom)-Spokesman for Mayer Farms Inc.
Approve A genda: Thums moved to approve the agenda of 4 items; Seconded by Gebauer.
Motion carried.
Chelsea Lake Dam (land transfer and easement) – Requested by Mayer Farms Inc: Walcisak
handed out three maps illustrating the requests. The following are the requests ma de by Rod
Mayer for Mayer Farms Inc. in exchange for the ability of Pember Companies to be able to utilize
the crest of field, within easement 2, for dam replacement and construction.
1. Mayer Farm, Inc. (MFI) to deed the land under the present and proposed new Dam, plus
a buffer of 10'. Approximately 0.1 to 0.125 acres. This transfer is to ensure that MFI does
not own any land under the Dam, groin, deck and/or toe. Therefore, removing MFI of
any perceived liability. Crop damage from access through the crest of the field would
result in reimbursement to MFI estimated to be approximately $300-$400 total.
Recording and survey fees for the land transfer to be paid by Taylor County.
2. MFI to r eceive an easement across the cr est of Chelsea Lake Dam for motorized use of
vehicles up to 10,000 lbs. Motorized use of any kind will be prohibited from March 1st to
May 1st. This easement is intended to remain with the land regardless of future
ownership.
Mildbrand called for a motion to re-consider these requests. Motion made by Thums to approve
the requests as p resented; land transfer of approximately 1/8 acre from MFI to Taylor County
with the approved Corp Counsel language which protects the County from any future precedent
of a landowner giving land to the County. Taylor County to pay costs of surveying and recording
new parcel. Also, to approve the easement to MFI to utilize the crest of the dam. A roll call vote
was taken. All five (5) members voting in favor of the motion.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday
July 7th, 2023, at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Thums moved to adjourn the meeting; Seconded by
Gebauer. Motion carried. The meeting was adjourned at 3:58 pm.
Secretary: Jordan Lutz and Jake Walcisak
Forestry & Recreation Committee
June 2nd, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:32 AM by Scott Mildbrand.
Members Present: Scott Mildbrand, Gary Beadles, Rollie Thums, Jim Gebauer, Myron Brooks.
Members Absent: N/A
Other Attendees: Jake Walcisak, Jim Metz, Ruthann Koch-County Corp Counsel, Brian Wilson-
Star News, Emma Hans en-DNR Wildlife Biolog ist. Timothy Allen -DNR County Fo rest Liaison ,
Larry Brandl-County Finance Director.
Approve Minutes: Thums moved to approve t he minutes of the May 5 th, 2023, meeting;
Seconded by Gebauer. Motion carried.
Approve A genda: Brooks moved to approve the agenda of 18 items; Seconded by Beadles.
Motion carried.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Gebauer provided information
pertaining to culvert pricing and future purchasing of culverts through the Highway Department.
Gebauer moved to a pprove the bills spreadsheet as presented; Seconded by Gebauer. Motion
carried.
Chelsea Lake Dam (land transfer and easement) – Requested by Mayer Farms Inc: Walcisak
handed out a written request from Mayer Farms Inc and two maps illustrating the requests. The
following are the requests made by Rod Mayer for Mayer Farms Inc.
3. “it is the strong preference of Mayer Farm, Inc. (MFI) to deed the land under the present
and proposed new Dam, plus a buffer of approximately 10'.” Approximately 0.1 to 0.12
acres. “The goal of this transfer is to ensure that MFI does not own any land under the
Dam, groin, deck and/or toe.”
4. “it is our preference to swap this land for the area North of the Dam, again, outside the
area consisting of the Dam deck, groin and toe, from a line North of the Dam (as
sketched) to our Southern to our East/West property line. ” Approximately 2 acres of
upland and Chelsea Lake shoreline.
5. Receive an easement across the crest of Chelsea Lake Dam for motorized use of vehicles
up to 10,000 lbs.
6. “it is our goal to have this land swap AND the easement from Taylor County over the
Dam be accomplished prior to the start of Dam construction.” The construction schedule
from Pember Companies has indicated a start date of approx. July 5th.
Discussion occurred between the Committee, Rod Mayer, Walci sak and Cor p Counsel Ruthann
Koch. Corp Counsel provide d the following Wisconsin Administrative Code for Committee
review. NR 335.03(20) “Owner" means any municipality or lake district which holds the permit or
approval under chapter 31, Stats., to a dam and fee title ownership or permanent leg al access
for the purposes of operation and maintenance to the specific piece of land on which a dam is
physically located . Taylor Count y is the owner of the Chelsea Lake Dam and holds the dam
permit. Wisconsin State Statute and Administrative Code does no t require a dam owner to also
own the land benea th the dam. These are separate ownerships in Wisconsin. However, statute
and code does require the dam owner to have the legal right for access, maintenance, and
reconstruction of the dam. This has been accom plished through the deed recorded easement
between Mayer Farms Inc. and Taylor County, document #364648, October 25th, 2017.
Specifically, “It is intended by these parties that these easements include the right of Grantee to
use the portion of the Chelsea Lake Dam located on Grantor’s land, and to maintain, repair, and
re-construct such area, and any immediately adjoining areas alongside the dam, to the extent
determined by Grantee to be necessary in connection with Grantees use and maintenance of the
dam.”
Mildbrand suggested the Committee handle each of these items separately. Mildbrand called
for a motion to transfer approximately 2 acres of County owned land, north of the dam, to
Mayer Farms Inc. No motion was made. Mildbrand called for a motion to grant a motorized
easement across the crest of C helsea Lake Dam to Mayer Farms I nc. No motion was m ade.
Mildbrand called for a motion for the County to acquire the approximate 0.1 – 0.12 acres of
Mayer Farms Inc. land beneath the dam. No motion was made.
Discussion occurred between Walcisak , Corp Counsel Ruthann Koch and the Committee to
clarify the Committee’s position by taking action to affirm their position on these issues. Motion
by Thums to deny Mayer Farms Inc.’s request for the County to transfer approximately 2 acres of
County owned land, north of the dam, to Mayer Farms Inc ; seconded by Gebauer. All (5) voting
yes. Motion carried.
Motion by Gebauer to deny Mayer Farms Inc. request for an easement ac ross the crest of
Chelsea Lake Dam for vehicles up to 10,000 lbs ; seconded by Mildbrand. Roll call vot e cast.
Three (3) voting yes, Mildbrand, Gebauer, and Thums. Two (2) voting no, Brooks and Beadles.
Motion by Brooks to entertain a cquiring approximately 0.1 – 0.12 acres of Mayer Farm Inc. land
beneath the Taylor County owned dam with the stipulation that Corp Counsel provides verbiage
which protects the County from the pre cedent of a landowner being able to give the County
land which th e County doesn’t want or need; seconded by Gebauer. Roll call vot e cast. All (5)
voting yes . Corp Coun sel will produce deed language as requested by the Committee and
provide Mayer Farms Inc. with this language for their review. Taylor County will survey the parcel
with Taylor County staff at the time agreeable terms of land transfer are met.
Wildlife of Taylor County - Emma Hansen, Wisc onsin DNR Wil dlife Biologist: Hansen
presented a PowerPoint hi ghlighting common game animals found in Tayl or County. She
covered population dynamics, monitoring, health and harvest data for White-tailed Deer, Ruffed
Grouse, Wild Turk ey, Otter, and Black B ear. This included discussions on Winter Severity index
for deer, gamebird brood surveys, carnivore tracking, Snapshot Wisconsi n and Operation Deer
Watch. The Committee engaged with Hansen on several questions.
Timber Sales Update:
• Walcisak provided a report from Lutz. On Tuesday May 30th Lutz had a pre-sale meeting
with Smola Enterprises for tim ber sale #706. Harvest operations began the same day.
This is the fir st County sale harveste d by Smola Ente rprises. They have a large mixed
hardwood pulp contract which is not typical for this industry currently.
• Overall, pulp markets are limited in both volume and price.
• 2022 tree planting survival check for the Porky/Trout site. Good survival of 84% at 750
trees per acre. The site will be checked again in approximately 2 years.
Timber Sale Extension Requests:
2. #688, North Loop Aspen, Czarnezki Forest Products. 1-year extension request. This is the first
request from this contractor on sale #688. This would put the contract expiration date at 4
years old. This sale requires frozen ground and there has been limited frozen ground
conditions the last two winters. Also, pulp markets are limited. A motion was made by Thums
to approve the timber sale extension request for sale #688; seconded by Gebauer. Motion
carried.
3. #695, Funky Chevrons, Wilson Forestry. 1-year extension request. This is the first request
from this contractor on sale #695. This would put the contract expiration date at 3 years old.
Limited pulpwood markets. A motion was made by Gebauer to approve the timber sale
extension request for sale #695; seconded by Brooks. Motion carried.
Approve Timber Sale Bids: Walcisak presented the spring timber sale bids. All four (4) sales
received qualifying bids with a total bid value of $171,202.95 on 193 acres.
• Tract #1-23, North Pole : The re wer e six (6) qualif ying bids. Smola Enter prises (Jason
Smola) had the highest bid of $63,778.75.
• Tract # 2-23, Clifford: There were seven (7) qualifying bids. Lakeland Forestry (Brandon
Crank) had the highest bid of $56,247.00.
• Tract #3-23, Shay Hills: There was one (1) qualifying bid. Smola Enterprises (Jason Smola)
had the highest bid of $48,645.60.
• Tract #4-23, Oak Awareness: There was one (1) qualifying bid . Smola Enterprises (Jason
Smola) had the highest bid of $2,531.60.
• Total bid value of $171,202.95, which is 71% over the adverti sed min imum sale value
with a sold value of $887/acre.
Motion made by Brooks to approve the highest bidder for tracts #1-23, #2-23, #3-23 and #4-23;
seconded by Thums. Motion carried.
Administrator Report: Walcisak provided an update on several items:
• Conducted brushing and road repairs on all 18 miles of gas-tax County Forest Roads,
3 miles of major (non-gas tax) logging roads, and 15 miles of ATV trails on the
County Forest. More brushing and road repairs are needed on non-gas tax roads.
• ATV trails opened county-wide on Friday May 12th.
• Improvements have been completed to the Chelsea Lake Dam access road.
▪ Removed 36 yards of top dirt from the original road surface. Reshaped
roadbed. Removed 8 loads of brush and trees with a one-ton dump truck.
Applied 15 yards of 3” crushed rock and 120 yards of 1.25” crushed gravel.
Non-reimbursable expenses equal $1,738. A gate will be installed near the
town road in the future.
• Work is expected to start on Chelsea Lake Dam and Camp 8 Dam immediately after
July 4th.
• Lutz and Walcisak attended a Water Quality-Best Management Practices training in
Merrill on May 18th.
• Walcisak met with the Rib Lake Fish and Game Club, Rib Lake Police Department and
Rollie Thums on May 19th to consider a location for a potential shooting range on the
County Forest. Meeting again on June 16th to discuss further.
• Pine Line grading was completed on May 26th.
• Walcisak has recently met with two carbon developers. US Ventures and The Climate
Trust. Both are interested in developing a carbon project with Taylor County.
• The first annual road grading of all County Forest roads has been completed by Jeff
Peterson at the County Highway Department.
• The gravel project on Camp 8 road was completed on May 31st. 800 cubic yards of
¾” gravel. This was a one-day project by Randy Thums and covered approximately 1
mile.
• WCFA Board of Directors and Legislative/Certification committee meetings will be
held Tuesday June 20th in Mauston. Brooks and Walcisak will attend.
• WCFA Summer Tour June 21st and 22nd in Juneau County (Mauston) and Vernon
County (Viroqua). Walcisak and Lutz will attend.
• Mildbrand informed the Committee that the Taylor County Sportsmen Club has
committed to funding a fishing pier at the Camp 8 Flowage and potential funding for
a shooting range on the County Forest.
DNR County Forest Liaison Re port: Timothy Allen gave an update on County For est time
standard hours as well as current workload . Current projects include forest reconnaissance,
timber sale establishment and timber s tand improvements. The end of the state fiscal year for
County Forest time standards is June 17th. Only 8-10 hours remain this year.
The Forestry Committee may go into Closed Session by taking a roll call vote pursu ant to
Section 19.85(1)(e), Wisconsin State Statutes, for deliberating or negotiating the
purchasing of public properties, the investing of public f unds, or conducting other
specified pub lic business, whenever competitive or bargaining reasons require a cl osed
session. RE: Vosters et al Land Acquisition. Motion by Gebauer, seconded by Brooks, to go
into closed session at 11:17 AM. A roll call vote cast; Beadles, Brooks, Mildbrand, and Gebauer
voting yes. Thums voting no. Motion carried.
The meeting will reconvene in Open Session pursuant to Section 19.83, Wisconsin St ate
Statutes, to take any necessary action on the matter discussed in Closed Session . At 11:45
AM the Committee reconvened in open session. A motion was made by Gebauer to purchase
119.8 acres of the Vosters et al property for $263,560 with the contingencies of full county board
approval (simple majority) and successful award of Knowles-Nelson Stewardship Funding for up
to 50% of the apprais ed land value and miscellaneous acquisition costs. Seconded by Brooks.
Beadles, Brooks, Mildbrand, and Gebauer voting yes. Thums voting no. Motion carried.
The Forestry Committee may go into Closed Se ssion by taking a roll call vo te pursuant to
Wis. Stat. s. 19.85(1 )(e) for the purpose of deliberating or negotiating public business
related to an informal settlement offer, for which a closed session is required to preserve
the County’s negotiating strategy. Motion by Thums, seconded by Gebauer, to go into closed
session at 11:46 AM. A roll call vote cast: all (5) voting yes, motion carried.
The meeting will reconvene in Open Session pursuant to Section 19.83, Wisconsin St ate
Statutes, to take any necessary action on the matter disc ussed in Closed Session. At 11:58
AM the Committee reconvened in open session. A motion was made by Thums to accept Ayres
Associates Inc.’s current offer to settle the Camp 8 Dam and Chelsea Lake Dam grant application
matter from 2020; seconded by Gebauer. Motion carried. Corp Counsel will assist with this
process.
The Forestry Committee may go into Closed Session by taking a roll call vote pursuant to
Wis. Stat. s. 19.85(1)(e) for the purpose of deliberating or negotiating public business
related to deed restrictions and access easements on private land that impact County land,
for which a closed session is required to preserve the County’s competitive and bargaining
strategies. Motion by Thums, seconded by Brooks, to go into closed session at 1 2:00 PM. A roll
call vote cast: all (5) voting yes, motion carried.
The meeting wil l reconvene in Open Session pursuant to Section 19.83, Wisconsin St ate
Statutes, to take any necessary action on the matter discussed in Closed Session . At 12:24
PM the Committee reconvened in open session. A motion was made by Thums for Walcisak and
Corp Counsel to continue pursuing the protection of the County’s and public’s rights of access
on the Belter deed; seconded by Gebauer. Motion carried.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday
July 7th, 2023 at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Thums moved to adjourn the meeting; Seconded by
Gebauer. Motion carried. The meeting was adjourned at 12:25 pm.
Secretary: Jake Walcisak
Forestry & Recreation Committee
May 5th, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:31 AM by Scott Mildbrand.
Members Present: Scott Mildbrand, Gary Beadles, Rollie Thums, Jim Gebauer, Myron Brooks.
Members Absent: N/A
Other A ttendees: Jake Walcisak, Jordan Lutz , Jim Metz, Brian Wi lson-Star News, Timothy
Allen-DNR, Paul Lukewich. Joined via zoom: Joe Paul.
Approve Minutes: Gebauer moved to approve the minutes of the April 14th, 2023 , meeting;
Seconded by Thums. Motion carried.
Approve Agenda: Brooks moved to approve the agenda of 12 items, striking item 5 as Emma
Hansen was unable to attend, moving item 11 (Administrator Report), and item 12 (DNR County
Forest Liaison Report) above the closed session; Seconded by Beadles. Motion carried.
Approve Bills: Walcisak presented the monthly bill sp readsheet. Some disc ussion occurred
pertaining to purchasing new truck tires for the 2023 F -250. Brooks moved to approve the bills
spreadsheet as presented; Seconded by Gebauer. Motion carried.
Timber Sales Update: Lutz gave updates o n timber sales. There ar e no active sal es, weight
restrictions were lifted May 1 st. Lutz also gave an update on the UWSP student collaboration
project. A field marking day was conducted on Saturday Apr il 29 th, with 21 students and 10
resource professionals attending. The students were split into small groups and switched group
leaders throughout the day. Approximately 74 of the 148 acres of marking was completed.
Approved Timber Sales for Bid: Lutz presented four timber sales for the spring 2023 offering:
• Tract#1-23, 53 acres, minimum bid of $35,953.50
• Tract#2-23, 74 acres, minimum bid $31,395
• Tract#3-23, 60 acres, minimum bid $29,985
• Tract#4-23, 6 acres, minimum bid $2,531.60
With combined minimum bid value of $99,845.60, on four sales, totaling 193 acres. A motion
was made by Thums to approve the timber sales, as presented, for advertisement; seconded by
Brooks. Motion carried.
Reconsider Gravel Project Award: Walcisak received notice from Haas Inc that the gravel
contract they were awarded was bid in tons, not cubic yards. Therefore, making their bid much
cheaper compared to the other bidders. The County bid advertisement specified cubic yards.
The Haas Inc. bid sheet did not contain reference to tons as the volume mea sure. Walcisak
handed out an updated bid results spreadsheet with the Haas Inc. bid converted to cubic yards.
The Haas Inc. bid increased from $29,595.20 to $44,392.80. Walcisak gave a recommendation to
terminate the contract with Haas Inc and award the project to the second lowest bidder, Randy
Thums Trucking.
A motion was made by Brooks to terminate the gravel contract award with Haas Inc. and award
Randy Thums Trucking the bid of $ 37,827.50; seconded by Gebauer. A roll call vote was cast per
request of Thums. Members in favor: Mildbrand, Brooks, Gebauer; Abstain: Thums; Opposed:
Beadles. Motion carried.
Administrator Report: Walcisak and Lutz provided an update on several items:
• Lutz presented on the completion of the reforestation project for the “Field Pine” site.
Superior Forestry handplanted 10,500 red pine seedlings on 11 acr es in two hours for an
expense of $1,100.00.
• Walcisak gave an update on the Pine Line Commission meeting, I ce Age Trail Alliance
mobile skills event, and the recent County Deer Advisory Council meeting.
DNR County Forest Liaison Re port: Timothy Allen gave an update on County For est time
standard hours as well as current workload.
The Fo restry & Recreation Committee will go into closed session pursuant to Section
19.85(1)(e), Wisconsin State Statutes, for delib erating or negotiating the purchasing of
public properties, the investing of public funds, or conducting other specified public
business, whenever competitive or bargai ning reasons require a clos ed session. RE:
Vosters et al Land Acquisition. Thums informed the committee that he would not be voting to
support a land acquisi tion by the County. A motion was made by Brooks to move into closed
session. Walcisak suggested that he present the project to the committee in open session and
go into closed session only when land valuation and purchase prici ng was to be discussed.
Brooks r escinded his motion. Walcisak presented details o n the Vosters pr operty such as
location, current MFL enrollment, timber quality, access, taxes, and acreage.
Closed Session: Motion by Brooks, seconded by Gebauer, to go into closed session at 10:18
AM. A roll call vote was requested by Thu ms. Beadles, Brooks, Mildbrand, and Gebauer voting
yes. Thums voting no. Motion carried.
Open Session: At 11:18 AM the Committee reconvened in open session. A motion was made by
Mildbrand to authorize Walcisak to negotiate the best price, for Taylor County and its residents,
to purchase up to 160 acres of the Vosters property. Seconded by Br ooks. A roll call vo te was
requested by T hums. Beadles, Brooks, Mildbrand, and Gebauer voting yes . Thums voting no .
Motion carried.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday
June 2nd at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Gebauer moved to adjourn the meeting; Seconded by
Beadles. Motion carried. The meeting was adjourned at 11:23 am.
Secretary: Jake Walcisak and Jordan Lutz
Forestry & Recreation Committee
April 14th, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:31 A.M. by Scott Mildbrand.
Members Present: Scott Mildbrand, Gary Beadles, Rollie Thums, Jim Gebauer, Myron Brooks.
Members Absent: N/A
Other Attendees: Jake Walcisak, Jordan Lutz, Jim Me tz, Larry Brandl, Brian Wilson -Star News,
Lynn Rosemeyer, Mike Bub, Timothy Allen -DNR, Dan Judnic, Bill Vach, William Clough, and
Daren Debban. Joined via zoom: Peter J, Jeff Heine, and Adam Keeling
Approve Minutes: Gebauer moved to approve the minutes of the March 3rd, 2023, meeting;
Seconded by Brooks. Motion carried.
Approve Agenda: Thums moved to approve the agenda of 11 ite ms; Secon ded by Brooks.
Motion carried.
Closed Session: The Forestry Committee may go into Closed Session by taking a roll call vote at
approximately 9:35 a.m. pursuant to Sections 19.85(1)(f), considering financial, medical, social, or
personal histories or disciplinary data of specific persons, pr eliminary consideration of specific
personnel problems or the investigation of charges against specific persons except where par.(b)
applies which, if discussed in public, would be likely to have a substantial adverse effect upon
the reputation of any pers on referred to in such histories or data, or involved in such problems
or inve stigations. Expenses submitted for Wisconsin County Forests Association meeting -
Rothschild March 22 and March 23, 2023: Motion by T hums, seconded by Gebauer, to go into
closed session at 9:37 a.m. A roll call vote cast, five (5) voting aye, the motion carried.
Walcisak made a request that due to this closed session’s statutory exemption protecting his
rights, this item be held in o pen sessi on. Discussion regarding Walcisak’s re quest occurred
between Mike Bub, who was in the audience, and the Forestry Com mittee. Mildbrand chose to
enter closed session, but assured Walcisak he could present whatever information he would like
once the committee reconvened in open session. Mildbrand asked everyone except coun ty
board members and Andria Farrand to leave the me eting room during the closed session.
Walcisak and Nicole Hager were asked back into closed session at approximately 10:05 AM.
The committee reconvened in open session at 10:25 AM. A motion was made by Brooks to
follow guidance discussed in closed session ; seconded by Thums. Motion carried. Brian Wilson
asked for the motion which was made in closed session. Mildbrand denied Wilson’s request,
referencing guidance from Taylor County Corp Counsel Koch.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Gebauer moved to approve the
bills spreadsheet as presented; Seconded by Brooks. Motion carried.
Timber Sales Update: Lutz gave updates on timber sales. There are cur rently no active sales.
Road restrictions were put on March 13th. One contract or has expressed interest in summer
logging so far. Lutz also gave an update on the timber sale project collaboration with UWSP.
Timber Sale Close Out -#675 – Pending Final Haul ing and Payment: Total sale revenue was
$41,889.77, which came to a 9% volume underrun and a 1% value underrun. There is one
outstanding invoice and about one load of pulp remaining to be hauled. A motion was made by
Thums to close out the sale pending fin al hauling and payment; seconded by Gebauer. Motion
carried.
Award Gravel Bid: Walcisak presented three gravel bids:
• Haas Inc. $29,595.20
• Randy Thums Trucking $37,827.50
• Wisco Materials $44,975.00
A motion was made by Thums to award the lowest bid in the amount of $29,595.20 to Haas Inc.;
seconded by Gebauer. Motion carried.
Administrator Report: Walcisak provided an update on several items:
• Storm damage applications to the DNR Snowmobile and ORV Councils for $81,620
were successfully awarded for Snowmobile and ATV trails.
• Budget Review Committee reviewed the Forestry budget on April 3rd. Walcisak handed
out the same packet presented to the Budget Review committee. Additional topics
being further pursued as additional revenue are, carbon offset projects and maple
syrup tapping. No action taken, just gathering information.
• Reimbursement was received for the Miller Dam sluice gate project for $57,369.
• Walcisak assisted with an SRS Title III application for the Jump River Fire Dept for a UTV
trailer purchase.
• Walcisak participated in Government days at MASH on March 7th.
• Pre-construction meetings for both Camp 8 and Chelsea Dam were held on March 8th.
•The new 2023 F-250 was delivered on April 4th. Truck was originally ordered October
4th, 2022. The 2017 Ford F-150 was sold to Buildings, Grounds, and Parks Dept. for
$15,000.
• County Deer Advisory Council (CDAC) meeting will be held Monday May 1st at 7 pm at
the MASH library.
• Tree seedling order is scheduled for pick up on May 1st in Hayward.
DNR County Forest Liaison Report: Timothy Allen gave an update on County Forest time
standard hours as well as current workload. Current time st andards indicate approximately 100
hours remaining.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday
May 5th at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Gebauer move d to adjourn the meeting; Seconded by
Beadles. Motion carried. The meeting was adjourned at 10:59 am.
Secretary: Jake Walcisak and Jordan Lutz
Forestry & Recreation Committee
March 3rd, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:31 A.M. by Myron Brooks.
Members Present: Gary Beadles, Rollie Thums, Jim Gebauer, Myron Brooks.
Members Absent: Scott Mildbrand-excused.
Other Attendees: Jake Walcisak, Jordan Lutz, Jim Metz, Larry Brandl, Brian Wilson Star News,
Timothy Allen DNR.
Approve Minutes: Thums moved to approve the minutes of the February 3rd, 2023, meeting;
Seconded by Gebauer. Motion carried.
Approve Agenda: Gebauer moved to approve the agenda of 11 items; Seconded by Beadles.
Motion carried.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Beadles moved to approve the
bills spreadsheet as presented; Seconded by Gebauer. Motion carried.
Timber Sales Update: Lutz gave updates o n timber sales. There is only one (1) active timber
sale.
• #675 Steve Dassow
o Pre-hauled approx. 1.5 l oads t o E mil D rive. All ot her decked wood has been
hauled. Contractor was able to load burned forwarder on a low bo y. The low boy
was driven all the way into timber sale.
Sustainable Forestry Grant Application: Walcisak presented an application for the Sustainable
Forestry Grant which is administered by th e Wisconsin DNR . The application is for damage
sustained from the winter storm event o n December 13 th, 2022. Heavy snowfall in combination
with freezing rain ca used severe tree damag e, both s eedlings and saplings, across the coun ty
forest. The workload is for approximately 40 miles of non -gas tax logging roads clean-up for
$12,000. The work will be completed by both contractors and county staff/equipment. Walcisak
also stated that this work will need to occur whether the grant application is successful or not.
The Sustainable Forestry Grant is funded with Wisconsin GPR allocated to the DNR segregated
account.
Motion mad e by Thums to approve the Sustainable Forestry Grant ap plication as presented,
seconded by Gebauer. Motion carried.
Lake States Bat Habitat Conservation P lan Enrollment (LSBHCP): Walcisak presented the
LSBHCP. The LSBHCP (summarized) pertains to the following items:
1. Three bat species (northern long-eared, tri-colored, and little brown) are covered within
the LSBHC P. The northern long eared is currently a federally listed spec ies, while the
other two are anticipated to be listed in the near future.
a. These bats exist within T aylor County. However, there are no known hibernacula
or maternity roost trees on the Taylor County Forest.
2. All landowners must comply with the Endangered S pecies A ct of 1 973. Any taking of
endangered species or their habitat is punishable by law.
3. Enrollment in the LSBHCP provides the landowner with an incidental take permit
providing the landowner is adhering to mandatory conservation actions within the plan.
4. Covered activities include:
a. Timber harvest and related forest practices.
b. Prescribed fire.
c. Maintenance of existing permanent forest roads an d recreational trails on public
lands.
d. Construction of new permanent forestry roads and recreational trails on pub lic
lands.
The Taylor County F orest is alr eady adhering to the conservation actions pertaining t o these
species. The LSBHCP enrollment was developed over the last several years and included experts
from the following state and feder al forestry and wildlif e agencies WI, MN, MI , US F ish and
Wildlife Service, and US Forest Service. Planning participa nts also included Taylor County,
Wisconsin County Forests Association, and private forest industry.
Discussion occurred if this pla n would fu rther restrict fores t management and what enr ollment
into the plan means for the Taylor County Forest. Lutz a nd Walcisak further explained that all
guidance is bein g adhered to already and that because they are a federally protected species,
we are required to follow the cons ervation measures of the LSBHCP, re gardless of our
enrollment into the plan. The inc idental permit allows Taylor County to continue forestry
operations, while protecting the County from future litigation of the federally listed bat species.
Currently, without an incidental take permit, the Endangered Species Act of 1973 would apply,
and a violation could result in a $25,000 fine and/or up to 6 months imprisonment.
Motion made by Gebauer to approve the resolution as re sented and enroll into the Lake States
Bat Habitat Conservation Plan, seconded by Beadles. All roll call vote was taken: Brooks, Beadles,
Gebauer- In favor, Thums-Opposed. Motion carried. (Mildbrand-Absent).
Approve Gravel Bid Advertisement: Walcisak presented a gravel project for 800 cubic yards of
0.75” crushed gravel, 1,770 cubic yards of 2” crushed gravel for 0.8 miles of County Forest Road,
0.6 miles o f logging road , and 1.4 miles of state funded ATV trail. The estimated bid value is
$42,000 with approximately 70% ($28,500) of gravel costs being paid through grants and aids.
Motion made by Gebauer to approve the gravel bid a dvertisement as presented, seconded by
Beadles. Motion carried.
Administrator Report: Walcisak provided an update on several items.
• Walcisak gave an update pertaining to the Ayres Engineering negotiation of Camp 8 and
Chelsea Dams. Co rp Counsel i s pursuing reimbursement for 100% of actual loss for
Camp 8 and 50% of actual loss for Chelsea.
• Walcisak was r ecently reque sted to speak before the House and Senate Joint
Committees on Forestry . Walcisak was one of 5 s peakers on February 21 st which also
included: Chief State Forester Heather Berklund, Wisconsin Count y Forests Association
Executive Director Rebekah Luedtke, Governor’s Council on Forestry Chairman Tom
Hittle, Gr eat Lakes Timber Professionals Association E xecutive Director Henry
Scheinebeck. Walcisak spoke on the challe nges facing the W isconsin forest industry as
well as state budget priorities most impactful to the County Forest program.
• An adjacent landowner proposed a land sale to Taylor County. The land is approximately
158 acres , enrolled in MFL op en, and falls within the d esignated forest management
blocking/acquisition boundary. The forestry d ept will gather more information for the
Committee and present their findings at future meetings.
• WCFA Board of Directors meeting March 21st in Rothschild. Brooks has a conflict and will
not be able to attend. Walcisak will attend.
• WCFA Forest Administ rator Me eting Marc h 22 nd and 23 rd in R othschild. Walcisak, Lutz
and Beadles will attend.
DNR County Forest Liaison Re port: Timothy Allen gave an update on County Forest time
standard hours as well as current workload. Current tim e standard accomplishment is
approximately 73%.
Next Committee Meeting: The next Forestry and Recreation Committee meeting will be Friday
April 14th at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Gebauer moved to adjourn the meeting; Seconded by
Thums. Motion carried. The meeting was adjourned at 10:36 am.
Secretary: Jake Walcisak and Jordan Lutz
Forestry & Recreation Committee
February 3rd, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:31 am by Scott Mildbrand.
Members Present: Scott Mildbrand, Gary Beadles, Rollie Thums, Jim Gebauer, Myron Brooks.
Members Absent: N/A
Other Attendees: Jake Walcisak, Jordan Lutz, Jim Metz, Larry Brandl, Brian Wilson Star News,
Timothy Allen DNR, and Rebekah Luedtke Wisconsin County Forests Assoc.
Approve Minutes: Thums moved to approve the minutes of the January 6th, 2023, meeting;
Seconded by Gebauer. Motion carried.
Approve A genda: Brooks moved to app rove the agenda of 10 items; Seconded b y Thums.
Motion carried.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Brooks moved to approve the
bills spreadsheet as presented; Seconded by Beadles. Motion carried.
Timber Sales Update: Lutz gave updates on timber sales. There are two (2) active timber sales.
• #700 Central WI Lumber
o About 1 load to be hauled and waiting on final payment.
• #675 Steve Dassow
o Steve has about 4 acres remaining to be cut and skid , s hould finish early next
week. Cold temperatures last week have helped freeze down haul roads.
Approve Tree Planting Bids: Lutz presented tree planting bid s. One bid was received from
Superior Forestry Service Inc for $100 per acre with a total b id of $1,100 for the 11-acre site.
Motion mad e by Gebauer to approve the tree p lanting bid from S uperior Fo restry Inc, as
presented, seconded by Thums. Motion carried.
Wisconsin County Forest Association Membership (WCFA): Request was made to add this
agenda item, as it was brough t up at the January 18th, 2023, Personnel and Finance Committee
meeting by Rollie Thums as he had concerns over membership fees.
Walcisak present ed a members benefit docu ment provided by WCFA Executiv e Director
Rebekah Luedtke and gave an ove rview of the benefits WCFA pro vides. A few highlights
pertaining to WCFA:
• There are 30 Counties in Wisconsin with a county forest pr ogram. All 30 Counties are
members of WCFA.
• Taylor County has been a n active participant since at least 1969 and ha s been a payi ng
member since at least 1971.
• Taylor County has ha d a representative on the WCFA Bo ard of Directors continuously
since 1988.
o In recent ye ars this has included Myron Brooks, Ch uck Zenner, a nd Herbert
Bergmann.
• Current dues are $2,663.68 , however the Wisconsin DNR County Forest Administration
Grant covers $ 698.56. T his br ings the total cost down to $1,965.12 . This is down 21%
since 2018.
There was discussion surrounding the benef its of WCFA from Thums compared to the cost.
Thums stated that he believes these same benefits would be available to Taylor County even if
we weren’t a member of WCFA. Members Beadles, Brooks, Gebauer, and Chairman Metz spoke
in favor of the benefits WCFA provides and continued membership. Walcisak clarified that many
of these benef its are exclu sive to members. This inc ludes but i s not limite d to collaboration,
communication, and training between member cou nties. A statewide organization, such as
WCFA, can address much larger issues than a single county can handle. This includes legislation,
administrative code, DNR and Federal program guidance, and state budge ts. Walcisak further
stated he does not recommen d dropping WCFA membership . He believes Taylor County
receives more in value than what is paid in due s. Walcisak s tated it would be improper to
terminate memb ership, continue to benefit from statewide WCFA efforts, and le ave all other
member counties to absorb the cost. Motion made by Brooks to continue as a paying member
of WCFA. Mildbrand struck the motion as he felt no action was needed.
Administrator Report: Walcisak provided an update on several items.
• Chelsea Lake Dam : is now un der contract with P ember Co mpanies. Construction is
scheduled for 2023. Substantial completion deadline is Septe mber 15 th, 2023. Contract
extensions are possible but should not be relied upon. Current pool elevation is 1,531.0
feet mean sea level. Construction plans call for lowering the water level to achie ve a
construction pool of 1,530.5 feet (6” below the normal pool).
• No updates from Corp Counsel currently regarding 2020 dam grant applications with
Ayres.
• Snowmobile Trails: Governor’s Snowmobile Council meeting yesterday. Taylor County
Snowmobile Council meeting last night. Trails are in good to excellent condition. Recent
cold temperatures have firmed up all wetlands and water crossings.
o Storm Damage expense to date $74,112.51. Any expenses exceeding our
maintenance agreement with DNR will be submitted under a separate storm
damage grant application. Total funds available for non-grooming work within
the snowmobile program comes to $86,775.
• 2018 Skid Steer is having new tracks and some other worn undercarriage components
replaced. One track severely torn. Track warranty of 2 years.
• USFS Title III Allocation to Jump River Fire Department after 45-day public comment
period. No comments received. $3,386 towards replacing a water fill station at a project
expense of $11,286.45.
DNR County Forest Liaison Re port: Timothy Allen gave an update on County Forest time
standard hours as well as current workload . Current tim e s tandard accomplishment is
approximately 65%.
Next Committee Meeting: The next Forestry and Recreation committee meeting will be Friday
March 3rd at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Beadles moved to adjourn the meeting; Seconded by
Brooks. Motion carried. The meeting was adjourned at 10:18 am.
Secretary: Jake Walcisak and Jordan Lutz
Forestry & Recreation Committee
January 6th, 2023
County Board Room-3rd Floor
Call Meeting to Order: The meeting was called to order at 9:30 am by Scott Mildbrand.
Members Present: Scott Mildbrand, Gary Beadles, Rollie Thums, Jim Gebauer, Myron
Brooks.
Members Absent: N/A
Other Attendees: Jake Walcisak, Jordan Lutz, Jim Metz, Chuck Zenner, Lester Lewis, Larry
Brandl, Brian Wilson Star News, Timothy Allen DNR. Attending virtually: Adam Schneider (Ayres
Associates).
Approve Minutes: Thums moved to approve the minutes of the December 2nd, 2022,
meeting; Seconded by Brooks. Motion carried.
Approve Agenda: Gebauer moved to approve the agenda of 12 items; Seconded by
Thums. Motion carried.
Approve Bills: Walcisak presented the monthly bill spreadsheet. Thums moved to approve the
bills spreadsheet as presented; Seconded by Brooks. Motion carried.
Timber Sales Update: Lutz gave updates on timber sales. There are two (2) active timber sales.
• #700 Central WI Lumber
o Harvesting and forwarding has concluded. Final hauling, invoicing,
and payment remain.
• #675 Steve Dassow
o Steve’s double bunk forwarder started on fire and completely burned.
This has significantly s lowed progress down. Steve only has one single bunk
forwarder but plans to sub-contract to finish the sale. This sale will expire in
June 2023, meaning this is his last winter to finish the sale. In June of 2023 the
sale will be 4 y ears old. Discussion was had about automatically extending his
sale without a request. Lutz recommended we wait and see how sale
progresses. Lutz is working with the insurance company to get the machine
moved as soon as possible.
Approve Tree Planting Bids for Advertisement: Lutz presented a tree planting bid packet
for an 11-acre site that is to be reforested into red pine this spring. The site was harvested
(rotated) in 2021 and with DNR dozer assistance slash piles were consolidated. The slash piles
will be burned in the coming weeks, while snow is present. The planting site will use 8,640 (1-0)
red pine seedlings already purchased from PRT at a 8’ by 6’ spacing. Bids will be accepted until
3:00 pm on February 2nd, 2023.
Motion made by Gebauer to approve the tree planting bid packet for advertisement, as
presented, seconded by Beadles. Motion carried.
Truck Purchase with WI Dept of Administration:
• Background: 2022 Forestry truck order. Awarded bid to Medford Motors
October 2021 for $38,000. Truck not built and order has been cancelled by
Ford.
• 2023 Pricing/Quote
▪ Medford Motors quote $49,546.00 December 8th, 2022.
▪ Wisconsin Department of Administration fleet purchasing contract with
Ewald Ford of Hartford, WI $46,593.00 December 5th, 2022.
▪ Vehicle outlay account balance $42,000.00
▪ Sell 2017 truck to Buildings, Grounds and Parks Department for
$15,000.00. Fair market value $26,000.00.
▪ Total account balance for 2023 truck purchase $57,000.00
• A motion was made by Gebauer to approve purchasing a truck via WI Dept of
Administration pricing through Ewald Ford of Hartford, seconded by Brooks. A roll call vote
was taken: Gebauer-yes, Beadles-yes, Brooks-yes, Mildbrand-No, Thums- no. Motion carried
with a 3-2 vote.
Review and Approve Chelsea Lake Dam Replacement Bids: Discussion was had regarding
the bids for both dam projects and the lack of performance by Ayres Associates in 2020.
Chelsea Lake Dam bid came in $95,390 higher than Ayres 2020 opinion of probable cost. An
opinion of probable cost is not a bid value, but an estimate prepared by an engineer for
the anticipated cost of construction. Ca mp 8 Dam bid came in $50,555 higher than Ayres
2020 opinion of probable cost. This totals $145,945 over the 2020 opinion of probable cost
for Chelsea and Camp 8 combined. However, the County is only responsible for half of that
cost due to being awarded funding through the Wisconsin DNR Municipal Dam Grant
Program. The total increase to the County from 2020 to current day is $72,972.50.
Concerns were expressed by Mildbrand and Lewis regarding adherence to a county
resolution which states no committee may exceed estimated costs by more than $100,000
without approval from full County Board. Discussion made it clear that the actual cost increase
to the County of $72,972.50 does not exceed the $100,000 resolution cap and is not applicable
in this situation. The Taylor County Dam Maintenance Account is adequate to cover
approximately half of these increased expenses while running a deficit of $37,131.60.
Additionally, 2022 timber revenue exceeded budgeted revenue and is sufficient to cover the
expected deficit of approximately $37,131.60. Mildbrand and Lester Lewis sp oke in
opposition of approving the dam bids without first resolving the matter with Ayres a nd
bringing the increased costs to full County Board. Walcisak stated that each bid is valid for only
45 days from the time of bid opening and once a bid is approved the County must sign the
DNR grant award letter within 30 days to secure funding. T hese deadlines limit the time
available to delay a bid approval. Any delay in the bidding process would need to have been
initiated prior to bid advertisement. Chelsea Lake Dam bids are valid only until Sunday January
22nd. This would only allow two weeks to resolve the situation with Ayres and would not be
enough time in Walcisak’s opinion. Walcisak suggested that bid approval and resolution with
Ayres be handled as two separate i tems. While they follow a parallel track, they are not
dependent upon each other. Brooks and Beadles spoke in support of treating these two items
as separate issues and moving forward with bid approval. Walcisak is already scheduled to
meet with County Corp Counsel this afternoon to begin discussing a resolution with Ayres.
Mildbrand proposed reviewing the possibility of changing Chelsea Lake Dam design plans
to the less expense option discussed in 2020. Walcisak informed the Committee that the less
expensive design option would net an approximate savings of $15,000. While the change
in design itself would save approximately $30,000 there would be added costs for the new
design, re-bidding and inflationary costs of losing another year in construction. Also, the less
expensive design option has a life expectancy of only 45 years while the more expensive design
option has a life expectancy of 85 plus years. Brooks and Thums voiced concern over delaying
the bid approval and not accepting the lowest bids. T hums and Beadles were particularly
concerned wi th losing the favorable Pember C onstruction bid on Chelsea Lake Dam if
rebidding occurred, resulting in a much higher cost.
Below is a summary of the upcoming dam replacement expenses as approved and
compared to the current Taylor County Dam Maintenance Account.
▪ Cost to complete as bid $624,527.50
▪ Dam grant reimbursement $312,263.60
▪ Reimbursable to date $103,414.24
▪ Dam account balance $171,717.76
▪ Funds needed to complete as bid $37,131.60
Walcisak presented bids for the Chelsea Lake Dam replacement project. Three bids were
received. Michels Construction $ 424,954.75. Janke General Contractors $ 409,422.00. P ember
Companies $270,269.00. Bids were opened on December 8th, 2022.
Motion was made by Brooks, seconded by Gebauer to accept the lowest bid of $270,269 from
Pember Companies. A roll call vote was taken: Gebauer-yes, Beadles-yes, Brooks-yes,
Mildbrand-No, Thums-yes. Motion carried with a 4-1 vote.
Review and Approve Camp 8 Dam Replacement Bids: Walcisak presented bids for the
Camp 8 Dam replacement project. Three bids were received. Nordic Underwater Services
$396,350.00. Pember Companies $381,589.00. Minger Construction Companies
$320,986.00. Bids were opened on January 5th, 2023.
Motion was made by Brooks, seconded by Gebauer to accept the lowest bid of $344,016 from
Minger Construction Companies. A roll call vote was taken: Gebauer-yes, Beadles-yes, Brooks-
yes, Mildbrand-No, Thums-yes. Motion carried with a 4-1 vote.
Administrator Report:
• Walcisak provided an update on snowmobile trail status. Approximately, 95% of all
trails have been brushed and signed. Trails are anticipated to open Friday the 13th pending
weather conditions.
Assistant Administrator Report:
• Pirus was closed Wednesday for the season.
• Northwest Hardwoods paid full restitution for failure to complete sale #668. Payment
was received on Thursday January 5th, 2023.
DNR County Forest Liaison Report: Timothy Allen introduced himself and gave an update on
County Forest time standard hours as well as current workload, which includes starting timber
sale establishment for 2023 and recon. Current time standard accomplishment is
approximately 443 hours or 56%. Allen began on Monday, November 7th, 2022.
Next Committee Meeting: The next Forestry and Recreation committee meeting will be
Friday February 3rd at 9:30 AM in the County Board Room, third floor.
Adjournment: With no further business, Thums moved to adjourn the meeting; Seconded by
Gebauer. Motion carried. The meeting was adjourned at 10:43 am.
Secretary: Jake Walcisak and Jordan Lutz