PUBLIC WORKS COMMITTEE
June 2 3 , 202 6
6: 30 pm
PRESENT : Alderpersons Garza, Rusniak, Kirley, and Turchi
ALSO PRESENT : City Administrator Steve Volkert, City Clerk Shanna Kreilkamp , City Engineer Chris
Walter , and Public Works Director Tim Puestow .
Call to Order – Alderperson Garza called the meeting to order at 6: 30 p.m. in the Common Council
Chambers of Hartford City Hall, 109 North Main Street.
Public Comment Period – No public comment.
Discussion and Consideration to reject a public construction contract for the Wacker Drive
Improvements . - City Engineer Walter stated that three BIDS were received on June 17, 2026. The low
Bid was from Stark Pavement at $609,301.30. All Bids were around $100,000 over projected amount. At
this time City Staff recommends rejecting this public construction contract and going back for BID in
January 2027.
MOTION by Alderperson Kirley , seconded by Alderperson Rusniak to reject a public construction
contract for the Wacker Drive Improvements.
MOTION CARRIED UNANIMOUSLY.
Discussion and Consideration to award a public construction contract for the roadway and utility
extension of Innovation Way . - City Engineer Walter stated that five bids were received on June 18,
2026. The lowest Bid was from Wondra Construction for $2,101,928.12 for a full road build out of
Innovation Way. Engineer Walter informed the Committee that the Bids received were favorable and
aggressively priced.
MOTION by Alderperson Turchi , seconded by Alderperson Rusniak to award a public construction
contract for the roadway and utility extension for Innovation Way.
MOTION CARRIED UNANIMOUSLY.
Discussion and Consideration of authorizing the Public Works Director to purchase one International
HV507-STA dump truck with plow and wing attachments in 2026 for a total purchase price of $297,906
utilizing funding allocated in the 2027 Capital Improvement Program. – Public Works Director Tim
Puestow informed the Committee that in his research it was found that the price for the dump truck
would jump $35,000 in 2027 compared to 2026. With that cost savings it is beneficial for the city to
make the purchase at this time . The truck would be on the roads in approximately one year.
MOTION by Alderperson Kirley , seconded by Alderperson Turchi authorizing the Public Works Director
to purchase one International HV507-STA dump truck with plow and wing attachments in 2026 for a
total purchase price of $297,906 utilizing funding allocated in the 2027 Capital Improvement Program .
MOTION CARRIED UNANIMOUSLY.
Adjournment – Motion by Alderperson Rusniak , seconded by Alderperson Turchi for adjournment at
6 :48 p.m. Motion carried.
Respectfully submitted,
Shanna Kreilkamp, City Clerk
PW JUNE23 .26
Source: City of Hartford website. First collected Oct 18, 2026.