July 8, 2025 Village of Jackson - Budget and Finance Committee Meeting Agenda
VILLAGE OF JACKSON
BUDGET AND FINANCE COMMITTEE MEETING AGENDA
Tuesday, July 8, 2025 at 7:00 PM
Jackson Municipal Complex
Village Board Room
N168W19851 Main Street
Jackson, WI 53037
1. Call to Order and Roll Call
2. Approval of Minutes of the Budget and Finance Committee Meeting of June 10, 2025
3. Change Order #1 - Ridgeway Drive and Chestnut Court Reconstruction Project - Advanced
Construction for an increase in the amount of $83,797.32
4. Pay Request #2 - Ridgeway Drive and Chestnut Court Reconstruction Project - Advanced
Construction in the amount of $219,429.58
5. Pay Request #16 - Wastewater Treatment Plant Tertiary Filters and UV Disinfection Project
- J.H. Hassinger in the amount of $99,540.52
6. Clean Water Fund Loan Request #13 - 2024 Wastewater Treatment Plant Project in the
amount of $125,364.57
7. Wastewater Treatment Plant Disk Filter Maintenance - Veolia Water Technologies in the
amount of $113,071.38
8. Review of Bids - Glen Brooke Drive and Jackson Drive Path Project
9. 2025-2026 Contract Amendment #2 - Gremmer & Associates in the amount of $301,825.00
10. Pay Request #13 - Jackson Community Center Expansion Project - Moore Construction in
the amount of $108,416.85
11. Citizens/Village Staff to Address the Budget & Finance Committee
12. Adjourn
Persons with disabilities requiring special accommodations for attendance at the meeting should contact the
Administration Department at the Jackson Municipal Complex at least one (1) business day prior to the
meeting.
It is possible that members of the Village Board may attend the above meeting. No action will be taken by any
governmental body at this meeting other than the governmental body specifically referred to in this meeting
notice. This notice is given so that members of the Village Board may attend the meeting without violating the
open meeting law.
Page 1 of 68
DRAFT
Page 2 of 68
DRAFT
Page 3 of 68
DRAFT
Page 4 of 68
V I LLAG E OF
T�� Lead,,i,n;W�C�y
JACKSON
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Change Order #1 - Ridgeway Drive and Chestnut Court Reconstruction Project
Meeting Date: June 24, 2025
Background and Analysis:
This memo is to inform you of Change Order #1 related to the Ridgeway Drive and Chestnut
Court Reconstruction project for Advanced Construction in the amount of $83,797.32.
This change order reflects necessary adjustments identified during construction. A breakdown
of the additional costs is as follows:
• Sanitary Sewer Amendments approximately $7,200.00 Includes pipe bursting and
related modifications to improve the sanitary sewer line.
• Storm Sewer Lateral Installation approximately $30,000.00 to include additional linear
footage and laterals due to incomplete records of existing infrastructure.
• Storm Sewer Catch Basin Reconstruction approximately $33,500.00 to include
reconstruction of existing catch basins not included in the original bid.
• Underground Utility Conflicts approximately $11,300.00 to include necessary field
changes due to unanticipated underground utility locations, requiring adjustments
primarily related to the water main.
• Miscellaneous Charges of approximately $2,000.00 Includes costs associated with
unanticipated tree removal necessary to complete portions of the work.
These changes were critical to maintaining and ensuring long-term functionality of the utility.
Funding for this Change Order will come from Account Numbers:
600-00-56700-820-001 (Capital Project- Chestnut Court/Ridgeway Drive)
300-00-17600-000-380 (Sewer Construction Work)
200-00-18600-395-000 (Water Construction Work)
Please let me know if you have any questions.
JS
Recommendation:
I recommend the Board approve Change Order #1 in the amount of $83,797.32 to Advanced
Construction.
Page 5 of 68
SECTION 00 63 63
CHANGE ORDER NO.: 1
Owner:
Engineer: Engineer's Project No.:
Contractor: Contractor's Project No.:
Project:
Contract Name:
Date Issued:
Description:
1 =
2 =
3 =
4 =
5 =
6 =
7 =
8 =
9 =
10 =
11 =
12 =
13 =
14 =
15 =
16 =
17 =
18 =
19 =
20 =
21 =
22 =
23 =
24 =
TOTAL =
25 +/(-) 7 Day(s)
26 +/(-) 7 Day(s)
Reason for Change Order:
a)
b)
c)
ADD 88 LF 6" Dia PVC Storm Sewer Pipe @ 65.00/LF $5,720.00
ADD 1 EA 12"x 6" Reducer Fitting @ $275.00 EA $275.00
DELETE 25 Lineal Feet Remove & Replace Curb & Gutter (Bid Item #A2-6) @ $92.00/LF ($2,300.00)
DELETE Lump Sum Lawn Restoration (Bid Item #A2-9) @ $1,250.00 ($1,250.00)
ADD Lump Sum Lawn Restoration @ $2,000.00 $2,000.00
DELETE 515 Lineal Feet 6" PVC Sanitary Sewer Lateral (14 Units)(Bid Item #4) @
$165.50/LF ($85,232.50)
DELETE 761 Lineal Feet 6" PVC Sanitary Sewer Lateral (7 Units)(Bid Item #A1-3) @
$165.50/LF ($125,945.50)
ADD 1560 Lineal Feet 6" HDPE Pipe Bursted Sanitary Sewer Lateral @ $140.00/LF $218,400.00
Change Order Item No. 2: Owner preferred to have water service curb box material furnished by Owner resulting in a
curb box materials credit.
05789-0020
May 22, 2025
ADD 180 Lineal Feet of 4” Dia Storm Lateral (Bid Item #A1-12) @ $60.00/LF
ADD 1 EACH San. MH Barrel Joint Leak Repair – Chemical Grout @ $3,000.00 EA $3,000.00
$10,800.00
ADD 2 EACH Replace Catch Basin Castings w/ 3067 (2'x3') castings @ $838.00 EA $1,676.00
ADD 2 EACH Catch Basin Chimney Reconstruction using 2'x3' rings @ $2,000.00 EA $4,000.00
Change Order Item No. 1: Owner requested that the Contractor perform the connections from the proposed storm
sewer laterals to the existing sump pump discharges.
The Contract is modified as follows upon execution of this Change Order:
Extension of Contract Times - SUBSTANTIAL COMPLETION:
Extension of Contract Times - FINAL COMPLETION:
ADD Lump Sum Water Service Temporary Connections w/ Addtl WTM capping $8,000.00
ADD 15 EACH Storm Lateral/Sump Discharge Connections @ $500.00 EA $7,500.00
($1,168.00)
ADD 7 EACH Catch Basin Chimney Reconstruction using 2' round rings @ $2,000.00 EA
$83,797.32
$3,292.32ADD Lump Sum Investingation of Existing Water Main Location
ADD 2 EA 2'x 3' Catch Basins w/ 3067 Castings @ $3,800.00 EA $7,600.00
Change Order Item Nos. 3-6: Owner directed alterations to proposed storm sewer laterals on Chestnut Court resulting
in additional lateral pipe and cleanouts.
$14,000.00
ADD 2 EACH Remove Trees (Bid Item #A1-34) @ $1,000.00 EA $2,000.00
DELETE 88 LF 12" Dia PVC Storm Sewer Pipe (Bid Item #A2-2) @ $115.00/LF ($10,120.00)
ADD 1 EACH 4” Dia Storm Lateral Cleanout @ $450.00 EA $450.00
ADD 220 Lineal Feet of 6” Dia Storm Lateral @ $65.00/LF $14,300.00
ADD 1 EACH 6” Dia Storm Lateral Cleanout @ $500.00 EA $500.00
ADD 7 EACH Replace Catch Basin Castings w/ 3070 (2'x2') castings @ $900.00 EA $6,300.00
DELETE 16 EACH Water Service Curb Box Material @ $73.00 EA
Village of Jackson
Ridgeway Dr and Chestnut Ct
Reconstruction - REBID
Owner's Project No.
Effective Date of
Change Order:
Advance Construction
Cedar Corporation
Ridgeway Dr and Chestnut Ct
Reconstruction - REBID
May 22, 2025
Page 6 of 68
d)
e)
f)
g)
h)
i)
j)
k)
Attachments:
a)
b)
c)
d)
e)
f)
g)
Change Order Item Nos. 14-19: Revisions to proposed storm sewer/storm sewer inlet off of Willow Ridge Drive.
Revisions associated with Owner's negotiations with property owner to reduce the cost of the improvements.
Change Order Item Nos. 25 & 26: Contract time extension associated with all additional Work items within this contract
change order.
Change Order Item No. 24: Cost associated with the Contractor's additional efforts related to finding the actual
location of the existing water main on Ridgeway Drive by use of conventional and hydoexcavating. Water main location
as indicated on Drawing were based upon on site utility locations which were found to be in error during construction.
Change Order Item Nos. 25 & 26: Contractor's revised construction schedule dated 5/5/25.
Change Order Item No. 1: 1) Engineer's Sump Pump Connection Exhibit dated 3/28/25, 2) Email correspondence
between Engineer & Contractor dated 3/28/25 & 4/17/25 respectively.
Change Order Item No. 2: Email correspondence between Engineer & Contractor dated 3/28/25 & 4/17/25
respectively.
Change Order Item Nos. 20-22: Owner requested to have sanitary sewer lateral replacement extended beyond the
right-of-way to property owner's structures. Changes associated with revising the method of installation from open cut
pipe to pipe bursting.
Change Order Item Nos. 23 & 24: Contractor's Cost Quote dated 5/12/25.
Change Order Item Nos. 3-6: Email correspondence between Engineer & Contractor dated 4/2/25 & 4/17/25
respectively.
Change Order Item Nos. 7-11: Owner decided to have the existing curb catch basin castings replaced which
necessitated the reconstruction of structure chimneys. In addtion, the Owner added the replacement of 2 each catch
basin structures with new castings.
Change Order Item No. 23: Cost associated with the relocation of the proposed watermain and change in sequencing
resulting in additional efforts related to temporary water service connections and additional water main isolations and
capping.
Change Order Item No. 12: Existing sanitary manhole located at Sta. 20+05 was found to contain leaks and therefore,
the Contractor was directed by Owner to repair leaks by use of chemical grout.
Change Order Item No. 13: Additional tree removals found necessary for the purpose of the installation of storm sewer
laterals to adjacent properties.
Change Order Item No. 12: 1) Email correspondence between Owner & Engineer dated 4/2/25, 2) Email
correspondence between Engineer & Contractor dated 4/2/25 & 4/17/25 respectively.
Change Order Item Nos. 7-11, 14-19, 20-22: 1) Email correspondence between Owner & Contractor/Engineer dated
4/30/25 re approvals, 2) Contractor's Cost Quote 422251 dated 4/22/25 (Items 7-11, 3)Owner's Exhibit re revision to
Willow Ridge Dr. storm sewer (Items 14-19), 4) Contractor's Cost Quote 42225 dated 4/22/25 (Items 20-22),
Page 7 of 68
Page 8 of 68
Village of Jackson
Ridgeway Dr & Chestnut Ct
Reconstruction - REBID
PROJECT NO.
DRAWN BY:
SCALE:
DATE:
INSTALL SCH 40
TRANSITION
FITTING WITH
THREADED CAP
COUPLING TO
ACCOMODATE
NEW TO EXISTING
PIPE MATERIALS
05789-0020
DTK
3/28/25
NTS
CHANGE ORDER ITEM NO. 1
Page 9 of 68
1
Doug Kroes
From: Shane Kofler <skofler@advconst.net>
Sent: Thursday, April 17, 2025 9:10 AM
To: Doug Kroes
Cc: Joshua Molter; Logan Myers; jeff.kreutzinger@villageofjacksonwi.gov; Matt Stephan;
Jack Straehler
Subject: RE: Jackson Ridgeway/Chestnut Reconst: Request for Cost Proposals 3/28/25
Follow Up Flag: Follow up
Flag Status: Flagged
Doug,
Here is the pricing requested.
Shane Kofler
Advance Construction Inc
Phone: 920-434-3978 / Fax: 920-434-6228
Direct: 920-593-1016 / Cell: 920-606-5011
From: Doug Kroes <doug.kroes@cedarcorp.com>
Sent: Friday, March 28, 2025 4:25 PM
To: Shane Kofler <skofler@advconst.net>
Cc: Joshua Molter <joshua.molter@cedarcorp.com>; Logan Myers <Logan.Myers@villageofjacksonwi.gov>;
jeff.kreutzinger@villageofjacksonwi.gov; Brian Kober <brian.kober@villageofjacksonwi.gov>; Matt Stephan
<matt.stephan@cedarcorp.com>
Subject: Jackson Ridgeway/Chestnut Reconst: Request for Cost Proposals 3/28/25
Shane:
As discussed at the preconstruction conference, the Owner would like to add Work to the contract associated
with making the connections from the new storm lateral risers to the existing sump pump discharges. Attached
please find an exhibit detailing the ad
ded work item. Based on the same, please provide an EACH unit price for this
work:
ADD 15 EACH Connection to Exist. Sump Pump Discharge @ $______
500.00 __________EA
In addition, the Owner will be furnishing the water service curb box material and therefore, a credit form the same
is warranted. Please provide a credit amount as follows:
DELETE 16 EACH Water Service Curb Boxes @ $__________
73.00 ________EA
Please feel free to contact me should you have any questions.
Thank you,
CHANGE ORDER ITEM NOS. 1 & 2
Page 10 of 68
1
Doug Kroes
From: Shane Kofler <skofler@advconst.net>
Sent: Thursday, April 17, 2025 3:09 PM
To: Doug Kroes
Cc: Josh Martell; Bryan Greisch
Subject: RE: Jackson Ridgeway/Chestnut Reconst.: Revised Drawings/Added Work Items - 2nd
CLARIFICATION
Attachments: R-3070-0010.pdf
Follow Up Flag: Follow up
Flag Status: Flagged
Doug here is the spec sheet on the “other” castings.
Shane Kofler
Advance Construction Inc
Phone: 920-434-3978 / Fax: 920-434-6228
Direct: 920-593-1016 / Cell: 920-606-5011
From: Shane Kofler
Sent: Thursday, April 17, 2025 11:50 AM
To: 'Doug Kroes' <doug.kroes@cedarcorp.com>
Cc: Josh Martell <jmartell@advconst.net>; Bryan Greisch <bryan.greisch@cedarcorp.com>
Subject: RE: Jackson Ridgeway/Chestnut Reconst.: Revised Drawings/Added Work Items - 2nd CLARIFICATION
Doug,
Please find pricing below.
Shane Kofler
Advance Construction Inc
Phone: 920-434-3978 / Fax: 920-434-6228
Direct: 920-593-1016 / Cell: 920-606-5011
From: Doug Kroes <
doug.kroes@cedarcorp.com >
Sent: Wednesday, April 2, 2025 7:23 PM
To: Shane Kofler < skofler@advconst.net >
Cc: Josh Martell < jmartell@advconst.net >; Bryan Greisch < bryan.greisch@cedarcorp.com >
Subject: RE: Jackson Ridgeway/Chestnut Reconst.: Revised Drawings/Added Work Items - 2nd CLARIFICATION
EXTERNAL EMAIL - This email was sent by a person from outside your organization. Exercise caution when clicking links, opening
attachments or taking further action, before validating its authenticity.
Shane, one more time… (gotta go home
) Corrections Below in RED font:
Shane:
CHANGE ORDER ITEM NOS. 3-6,12 & 13
Page 11 of 68
2
Attached please find revised Drawing 4/2/25. The revised Drawings include revisions as requested by the Owner.
These revisions will add some work items in which we are requesting unit prices. Items added that have
established bid unit prices will have the additional quantities recorded within their respective bid items.
Therefore, in addition to the items we have requested unit costs for previously (within attached email of 3/28/25),
please provide all-inclusive unit price costs for the following items:
New Items:
ADD 1 EACH 4” Dia Storm Lateral Cleanout @ $_______
450.00 _______EA
ADD 220 Lineal Feet of 6” Dia Storm Lateral @ $_______ 65.00 ________/LF
ADD 1 EACH 6” Dia Storm Lateral Cleanout @ $_______500.00 _______EA
ADD 1 EACH Replace Storm Catch Basin 2’x3’ w/ Casting & Chimney (Salvage Casting for Owner) @
$_______ 3800.00 _________EA This is for the stand alone inlets (not for structures built over the pipe)
ADD 8 EACH Replace Catch Basin Castings (Salvage Casting for Owner) @ $________ 838.00 ____________EA This is
for the 3067 2x3. Cost for the alternate casting more suited for round rings R – 3070 cost would be $900 Each
ADD 8 EACH Catch Basin Chimney Reconstruction @ $________ 4750.00 _______EA If rebuilding using R3070 with
round rings cost would be $4000.00
ADD 1 LUMP SUM San. MH Barrel Joint Leak Repair – Chemical Grout @ $__ 3000.00 ___________ LS (Photo
Attached – Intersection of Ridgeway & Willow Ridge – STA 20+00)
Established Bid Items :
ADD 180 Lineal Feet of 4” Dia Storm Lateral (Bid Item #17) @ $60.00/LF
ADD 27 Square Feet of Concrete Sidewalk Removal (Bid Item #20) @ $0.60/SF
ADD 27 Square Feet of 4” Concrete Sidewalk (Bid Item #21) @ $6.60/SF
ADD 2 EACH Remove Trees (Bid Item #39) @ $1,000.00 EA
ADD 27 Square Yard Remove Asphalt Driveway (Bid Item #29) @ $4.95/SY
ADD 27 Square Yard Asphalt Driveway (Bid Item #30) @ $33.00/SY
Please feel free to contact me if you have any questions.
Thank you,
Doug Kroes
Senior Construction Manager
W61 N497 Washington Avenue | Cedarburg | WI | 53012
Office: 262-204-2360 ext 1403 | TF: 800-472-7372
Cell: 920-246-6326
doug.kroes@cedarcorp.com
www.cedarcorp.com | LinkedIn | Facebook | Twitter
This e-mail and any attachments may contain proprie tary and confidential information from Cedar Corpor ation. Please visit our website at
http://www.cedarcorp.com/disclaimer for more details.
Page 12 of 68
1
Doug Kroes
From: Jack Straehler <jack.straehler@villageofjacksonwi.gov>
Sent: Wednesday, April 30, 2025 11:47 AM
To: Doug Kroes; Matt Stephan; skofler@advconst.net
Cc: Logan Myers
Subject: Ridgeway Drive & Chestnut Court
Follow Up Flag: Follow up
Flag Status: Completed
Team,
I have a few updates to share.
1. The alternative scope of work to include Pipe Bursting has been discussed with our Village Administrator
and Village President. We are in agreement with accepting this change. Doug can you please draft the
proper paperwork necessary to reflect this change?
2. The alternative scope of work to include using 2' x'2 castings and round rings where necessary when
reconstructing Storm Sewer catch basin has been discussed with our Village Administrator and Village
President. Again, we are all in agreement with accepting this change. Doug can you please draft the proper
paperwork necessary to reflect this change?
3. The alternative bid item for W198N17022 Ridgeway Drive has been discussed with our Village
Administrator and the property owner. The property owner has agreed to pay the second bid provided by
Advanced Construction as a special assessment. The property owner has also given the Village and its
contractor written permission to access the private property and perform the work without an easement.
Please let me know if you have any questions.
Thanks,
Jack B. Straehler II
Director of Public Works
Village of Jackson
W194 N16660 Eagle Drive
Jackson, WI 53037
Office: 262-677-0707
Cell: (262) 305-5012
CHANGE ORDER ITEM NOS. 7-11, 14-19, 20-22
Page 13 of 68
Advance Construction, Inc.
2141 Woodale Ave Quote # 422251
Green Bay, WI 54313 DATE: April 22 2025
Phone: (920) 434-3978
Fax: (920) 434-6228
Quote terms
Prices Good for
90 Days
Quantity Unit Unit Price Amount
2 EA 3,800.00 7,600.00$
-$
2 EA 838.00 1,676.00$
7 EA 900.00 6,300.00$
-$
2 EA 2,000.00 4,000.00$
7 EA 2,000.00 14,000.00$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
Subtotal 33,576.00$
Mark Up -$
Job
Storm Pricing
QUOTE
Bill To:
Village of Jackson
Replace Catch Basin Casting with 3070 (2x2)
Chimney Rebuild Catch Basin with round rings
Chimney Rebuild Catch Basin with 2x3 rings
Replace Catch Basin Casting with 3067 (2x3)
Description
Advance Construction Rep
Shane Kofler
Install new 2x3 inlet (takes 3067 casting)
CHANGE ORDER ITEM NOS. 7-11
Page 14 of 68
CHANGE ORDER ITEM NOS.14-19
Page 15 of 68
Advance Construction, Inc.
2141 Woodale Ave Quote # 42225
Green Bay, WI 54313 DATE: April 22, 2025
Phone: (920) 434-3978
Fax: (920) 434-6228
Quote terms
Prices Good for
90 Days
Quantity Unit Unit Price Amount
1560 LF 140.00 218,400.00$
-$
-$
1276 LF -165.50 (211,178.00)$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
Subtotal 7,222.00$
Mark Up -$
Description
Advance Construction Rep
Shane Kofler
Pipe Burst existing sanitary sewer laterals from property
to newly installed sewer main.
Open Trench new sewer laterals, new main to
right of way. (plan quantity footage)
Job
Ridgeway Dr - Pipe Bursting
QUOTE
Bill To:
Jack Straehler
Village of Jackson
CHANGE ORDER ITEM NOS. 20 - 22
Page 16 of 68
1
Doug Kroes
From: Doug Kroes
Sent: Wednesday, April 2, 2025 3:23 PM
To: Logan Myers; skofler@advconst.net; Joshua Molter; Matt Stephan
Cc: Jack Straehler; Jeff Kreutzinger
Subject: RE: Ridgeway/Chestnut Project - Additional work request
Logan:
Did you consider a chemical grout approach for addressing the leak in the joint? This has been proven as an
eective method of addressing leaks such as this.
Doug Kroes
Senior Construction Manager
W61 N497 Washington Avenue | Cedarburg | WI | 53012
Office: 262-204-2360 ext 1403 | TF: 800-472-7372
Cell: 920-246-6326
doug.kroes@cedarcorp.com
www.cedarcorp.com | LinkedIn | Facebook | Twitter
This e-mail and any attachments may contain proprie tary and confidential information from Cedar Corpor ation. Please visit our website at
http://www.cedarcorp.com/disclaimer for more details.
From: Logan Myers <Logan.Myers@villageofjacksonwi.gov>
Sent: Wednesday, April 2, 2025 2:08 PM
To: Doug Kroes <doug.kroes@cedarcorp.com>; skofler@advconst.net; Joshua Molter <joshua.molter@cedarcorp.com>;
Matt Stephan <matt.stephan@cedarcorp.com>
Cc: Jack Straehler <jack.straehler@villageofjacksonwi.gov>; Jeff Kreutzinger <jeff.kreutzinger@villageofjacksonwi.gov>
Subject: Ridgeway/Chestnut Project - Additional work request
All,
The Village has inspected the northernmost sanitary manhole at the intersection of Ridgeway and Willow Ridge
and noticed a large amount of infiltration and leaking from at least two joints. See attached photo. We would like
Advance Construction to disassemble, re-grout, and re-wrap this manhole to address this issue. Please account
for the additional time when scheduling work. Let me know if you have any questions or concerns.
Thank you,
Logan Myers
Engineering Technician
Village of Jackson
W194 N16660 Eagle Drive
Jackson, WI, 53037
Oice: (262) 677-0707 ext. 513
Mobile: (414) 573-9137
CHANGE ORDER ITEM NO. 12
Page 17 of 68
Advance Construction, Inc.
2141 Woodale Ave Quote #
Green Bay, WI 54313 DATE: May 12, 2025
Phone: (920) 434-3978
Fax: (920) 434-6228
Quote terms
Prices Good for
90 Days
Quantity Unit Unit Price Amount
6.5 HR 306.51 1,992.32$
-$
6.5 HR 200.00 1,300.00$
-$
1 LS 8,000.00 8,000.00$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
Subtotal 11,292.32$
Mark Up -$
Job
Ridgeway Dr
QUOTE
Bill To:
Village of Jackson
This includes 5 water service reconnects, and cutting
and capping the existing main 2 times.
$1000 per service & $1500 each for cut and cap.
Temporary reconnect of water services and cap existing
water main to allow for sewer install.
Hydro Vac Truck 4/9 & 4/10
Description
Advance Construction Rep
Shane Kofler
Crew Investigating and locating existing water 4/9 & 4/10
CHANGE ORDER ITEM NOS. 23 & 24
Page 18 of 68
Jackson - Ridgeway Dr 5-5-25
31-Mar 7-Apr 14-Apr 21-Apr 28-Apr 5-May 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 2-Sep
Traffic Control
Erosion Control
Tree Removal
Sanitary Mainline - Ridgeway Dr
Sanitary Mainline - Chestnut Ct
Water Main - Ridgeway Dr
Water Main - Chestnut Dr
Water Serices/Transfers
Sanitary Laterals Pipe Burst
Storm Sewer
Grading
Curb & Gutter
Sidewalks & Driveways
Restoration
Asphalt Pavement
Advance
Gordon Work Zones
Homer
Sommers
AllWays
Payne & Dolan
M&E
CHANGE ORDER ITEM NOS. 25 & 26
Page 19 of 68
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Pay Request #2 – Ridgeway Drive and Chestnut Court Reconstruction Project
Meeting Date: June 24, 2025
Background and Analysis:
This memo is to inform the Board of Pay Request #2 from Advance Construction in the amount
of $219,429.58 for work completed on the Ridgeway Drive and Chestnut Court Reconstruction
Project.
The work has been reviewed and verified for accuracy and completion in accordance with the
project contract documents and schedule.
Funding for this payment will come from Account Numbers:
600-00-56700-820-001 (Capital Project – Chestnut Court/Ridgeway Drive) $73,143.20
300-00-17600-000-380 (Sewer Construction Work) $73,143.19
200-00-18600-395-300 (Water Construction Work) $73,143.19
If you have any questions, please let me know.
JS
Recommendation:
I recommend the Board approve Pay Request #2 for Advanced Construction in the amount of
$219,429.58 as part of the ongoing financial management and progress of this capital
improvement project.
Page 20 of 68
Cedarburg • Green Bay • Madison • Menomonie
Community Infrastructure • Architecture • Environmental Services
W61N497 Washington Avenue
Cedarburg, WI 53013
262-204-2360
www.cedarcorp.com
May 30, 2025
Village of Jackson
N168 W20733 Main Street
PO Box 637
Jackson, WI 53037
Attn: Mr. Jack Straehler II, Director of Public Works
Subject: Contractor’s Application for Payment No. 2
Ridgeway Drive & Chestnut Court Reconstruction - REBID
Cedar Project No. 05789-0020
Dear Mr. Straehler:
Enclosed for your use in payment to Advance Construction in the amount of $219,429.58 is Contractor’s
Application for Payment No. 2.
Please Note: As the Contractor has not yet received payment from the Village related to their Application for
Payment No. 1, this application does not include lien waivers from subcontractors and/or material suppliers
associated with Application No. 1. These lien waivers will be submitted upon the Contractor’s receipt of
payment for the same.
Following your review and approval, please complete the application for payment forms within the areas reserved
for the Owner. Thereafter, retain one copy for your records, provide the second copy to the Contractor with
payment and provide the third copy to our office.
Should you have any questions, please feel free to contact me at our Cedarburg office.
Sincerely,
CEDAR CORPORATION
Douglas T. Kroes
Senior Construction Manager
Enclosed: As Noted
Cc: Shane Kofler, Advance Construction
Page 21 of 68
5/30/25
Page 22 of 68
Page 23 of 68
Page 24 of 68
Page 25 of 68
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Pay Request #16 – Wastewater Treatment Plant Tertiary Filters and UV Disinfection
Project
Meeting Date: June 24, 2025
Background and Analysis:
This memo is to inform the Board of Pay Request #16 from J.H. Hassinger in the amount of
$99,540.52 for work completed on the Wastewater Treatment Plant Tertiary Filters and UV
Disinfection project.
The work has been reviewed and verified for accuracy and completion in accordance with the
project contract documents and schedule.
Funding for this payment will come from Account Number:
300-00-17600-000-380 (Sewer Construction Work)
If you have any questions, please let me know.
JS
Recommendation:
I recommend the Board approve Pay Request #16 for J.H. Hassinger in the amount of
$99,540.52 as part of the ongoing financial management and progress of this capital
improvement project.
Page 26 of 68
Page 27 of 68
Page 28 of 68
Page 29 of 68
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Clean Water Fund Loan Request Loan Request #13 – Wastewater Treatment Plant
Tertiary Filters and UV Disinfection Project
Meeting Date: June 24, 2025
Background and Analysis:
This memo is to inform the Board of the Clean Water Fund Loan Reimbursement Request #13
in the amount of $125,364.57 for work completed on the Wastewater Treatment Plant Tertiary
Filters and UV Disinfection Project.
The work has been reviewed and verified for accuracy and completion in accordance with the
project contract documents and schedule.
Funding from this payment will reimburse Account Number:
300-00-17600-000-380 (Sewer Construction Work)
If you have any questions, please let me know.
JS
Recommendation:
I recommend the Board approve the Clean Water Fund Loan Reimbursement Request #13 in
the amount of $125,364.57 as part of the ongoing financial management and progress of this
capital improvement project.
Page 30 of 68
Page 31 of 68
Page 32 of 68
Page 33 of 68
Page 34 of 68
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Wastewater Treatment Plant Disk Filter Maintenance
Meeting Date: June 24, 2025
Background and Analysis:
As Part of ongoing Wastewater Treatment Plant Maintenance this memo is to inform the Board
of the reasoning behind receiving a single-source proposal from Veolia Water Technologies.
Veolia Water Technologies is the original manufacturer of this equipment. As such, they are
uniquely trained and qualified to perform the required 5-year maintenance. This scheduled
maintenance program is a standard manufacturer recommended service that, to my
understanding, has not yet been completed since the system’s original installation. Completion
of this program is important to preserve the performance, safety, and longevity of the
equipment.
According to information provided by Veolia, the company will not honor warranty coverage if
parts are purchased or installed by a third party. Therefore, to ensure the integrity of the system
and to maintain warranty protections, it is necessary to have Veolia perform this work directly.
Additionally, the Village’s Purchasing and Authority Policy and Procedures allows for sole
source procurement under circumstances where only one vendor can provide the required
service or product due to proprietary or warranty-related reasons. For these reasons, I received
a single-source proposal from Veolia which was reviewed with staff and our consultant
Engineering firm Town and Country.
Funding for this project will come from Account Numbers:
300-00-57320-831-000 (Sewer Collection System Maintenance) $56,535.69
300-00-57320-833-000 (Sewer Equipment Maintenance) $56,535.69
Please let me know if you have any questions.
JS
Recommendation:
I recommend the Board approve this sole source purchase proposal from Veolia Water
Technologies in the amount of $113,071.38, to carry out the five-year maintenance program.
Page 35 of 68
KRUGER | 1500 Garner Rd. Raleigh NC 27610
Veolia Codes: PS
QUOTEFROM
QUOTE NO:
1500 Garner Road, Suite C QUOTE DATE:
Raleigh, North Carolina 27610 USA EXPIRATION DATE:7/1/2025
CLE Jackson WWTP, WI In Stock
2 PRIPHT374989SPACER WASHER D235/179X15 - AXIAL BEARING $214.18 $428.36
4 PRIPHT374976SLIDE BUSHING D178.4 $1,318.54 $5,274.16
2 PRIPHT375120RBR SEAL HSF22/26 REAR BRG $88.29 $176.58
2 PRIPHT361142RBR SEAL HSF22/26 FRONT BRG $126.10 $252.20
2 PRIPHT377653EFF CTR SHAFT 22/26 WELD $3,892.90 $7,785.80
2 PRIPHT375113BRG HOUSE HSF22/2600 316L REAR $4,711.02 $9,422.04
2 PRIPHT377652INF CTR SHAFT 22/26 ASSY S32205 W/O FC (or #PRIPHT365737) $6,036.50 $12,073.00
2 PRIPHT375114BRG HOUSE 2200-HN INL 316L WELD $5,146.98 $10,293.96
2 PRIPHT377077SPACER WASHER D177/166.9X10 - V-RING SLEEVE $118.00 $236.00
2 SEVRRU343948V-SEALING V-180A INF V-RING $55.91 $111.82
2 PRIPHT361469SWIV CONN 2 INCH D9-BALL ASSY S32205 W/ STOP SCREW STR NIP $1,295.82 $2,591.64
2 PRIPHT374961RBR LIP SEAL HSF17/21/2200 $394.05 $788.10
2 SEORRU343088O-SEALING 180X4 $17.63 $35.26
2 IMPSGG325347MANOMETER 0-16 BAR PSI KR ¼" $133.53 $267.06
2 CFCFGU201095SCREEN,WIRE,200 MICRON WEAVE $175.92 $351.84
2 PRIPHT370971HUB SPROCKET DO150 DI45 316L $1,417.29 $2,834.58
2 PRIPHT371733HUB FLG DO150 DI80 316L $313.56 $627.12
2 PRIPHT375296SPACER BW WHEEL HSF2200-N $451.06 $902.12
2 PRIPHT375295WHEEL BW HEADER HSF2200-N $410.06 $820.12
2 PRIPHT377786SPACER WASHER D340/231X16 PA6 $541.48 $1,082.96
2 FXSCYR337597SCREW MSK6SS M8X50 A4 DIN916 - SET SCREW FOR HUB $4.78 $9.56
2 FXSCYP337628SCREW M6S M6X55 A4 - SMALL SCREW ON BW WHEEL $0.78 $1.56
2 PRIPHT377783SPROCKET Z=12 HSF2200 $532.95 $1,065.90
2 PRIPHT377784SPROCKET Z=32 HSF2200 $1,811.75 $3,623.50
2 PRIPHT364472CHAIN HT78 47 LINKS 316L/PLASTIC $1,427.98 $2,855.96
2 FXWAYP337486WASHER RB 6.4X18X1.6 A4 - WASHER BW WHEEL $0.27 $0.54
10 FXSCYZ337620SCREW M6S M16X120 - SCREW BW WHEEL & REAR CENTER SHAFT PLATE $24.30 $243.00
34 FXWAYT337489WASHER RB 10.5X20X2 - HUB WASHER $0.49 $16.66
14 PRIPHT369554WASHER W/ LOCKING DEVICE SET 316L HSF2200/HSF2600 $175.81 $2,461.34
14 FXSCYZ337165SCREW M6S M16X90 - SPROCKET SCREWS $81.85 $1,145.90
2 SEVRRU343913V-SEALING NBR V-45A (SEAL ON SEW SHAFT) $10.84 $21.68
16 FXSCYT336408SCREW M6S M10X60H - HUB SCREWS $5.30 $84.80
16 FXNUYT336018NUT NYLOC M6NM M10 - HUB NUT $1.52 $24.32
24 FXWAZA337493WASHER RB 17X30X3 $1.52 $36.48
58 FXNUYZ336020NUT NYLOC M6NM M16 $4.84 $280.72
12 FXSCYP337502SCREW M6S M6X16H (REAR BRG SEAL) $0.55 $6.60
12 FXWAYP337485WASHER RB 6.4X12X1.6 - REAR HOUSING SEAL WASHER $0.27 $3.24
8 FXSCYZ337581SCREW M6S M16X60 - FRONT INF SHAFT $12.67 $101.36
16 FXSCYP337064SCREW MK6S M6X16 - REAR HOUSING SEAL SCREW $2.07 $33.12
42 FXSCYZ336887SCREW M6S M16X65 - SPOKE SCREWS $7.06 $296.52
84 FXWAZB336888WASHER 18X30X8.0 - SPOKE WASHERS $4.89 $410.76
4 FXSCYP337508SCREW M6S M6X50 $1.03 $4.12
4 FXSCYR337597SCREW MSK6SS M8X50 $5.09 $20.36
1 PRIPHT364205TEST TUBE ASSY CAPACITY CTRL OF FLTR PNL $229.91 $229.91
Veolia Water Technologies, Inc. Chris Evans
919.455.1522
PHONE 888-578-4378 FAX 919-661-4568 Chris.Evans@veolia.com
Contact Name:Chad Russ Company:Village of Jackson
Phone:262-893-0855 Address:W194 North 16658 Eagle Drive
Jackson, WI 53037Email:chad.russ@villageofjacksonwi.gov
Sales
Person Job EQUIPMENT SERIAL #. Payment Terms DELIVERY TERMS DELIVERY SCHEDULE
Net 30 Days DAP, Prepaid & Add
Destination*
QTY PART NUMBER DESCRIPTION UNIT PRICE LINE TOTAL
06062025
6/6/2025 Aftermarket Sales Manager - Hydrotech Filtration, Kruger
This quote is valid for 25 days
Page 36 of 68
KRUGER | 1500 Garner Rd. Raleigh NC 27610
2
VEOLIA HYDROTECH 2210 DISC FILTER (QTY 1) 2 VEOLIA TECHS ONSITE
FOR UP TO 2 DAYS TO COMPLETE A 5 YEAR KIT REBUILD
SCOPE
TRAVEL TO JACKSON, WI
SAFTEY MEETING
LOTO UNIT
REHAB DISC FILTER WITH 5 YEAR SERVICE KIT
REMOVE LOTO
TEST RUN UNIT
TURN UNIT BACK OVER TO PLANT OPERATORS
CLIENT RESPONSIBILITES
1. UNIT DRIANED AND WASHED OUT.
2. PROVIDE ACCESS TO WATER HOSE
$20,944.38 $41,888.75
[[Confidential, Do not share with third parties]]
$1,850.00
If Applicable
ALL PRICES SUBJECT TO COST AND AVAILABILITY AT TIME OF ORDER.
PRICES EXCLUDES PACKAGING, FREIGHT (INTERNATIONAL & DOMESTIC),CUSTOMS, DUTIES,
BROKERAGE, FEES AND APPLICABLE TAXES.
PRICES EXCLUDES INSTALLATION LABOR, STARTUP, & TRAINING
SHIPPING CHARGES ARE PREPAID AND ADDED TO THE INVOICE ORYOUR FREIGHT ACCOUNT.
MINIMUM ORDER $50.00.
^THESE ITEMS MAY BE AFFECTED BY INTERNATIONAL TARIFFS.
SUBTOTAL $111,221.38
ESTIMATED FREIGHT*
Sales Tax
Total USD $113,071.38
*If customer's shipping method is preferred (FOB), enter your freight carrier & account number:
A SIGNED QUOTATION IS REQUIRED TO PROCESS ORDER. PLEASE SIGN BELOW.
Signed By:______________________________________________________________________________ Date:_______________________
Click or browse to URL(s) below for applicable Terms and Conditions
https://www.veoliawatertech.com/sites/g/files/dvc3601/files/document/2025/03/Parts%20and%20Service%20Terms%20%281%29.pdf
Page 37 of 68
KRUGER | 1500 Garner Rd. Raleigh NC 27610
QUOTE NO:06062025 QUOTE
Company information -
(OPTIONAL) Credit Card Section -
Signed by: Date:
Printed Name: Title:
Please complete this section if you have not previously provided this information.
Company Name:
Shipping Address:
City/State/Zip:
Telephone number:
Fax number:
Please complete this section if you prefer to pay by credit card.
Card Number:
Expiration Date:
Authorization (CID) #:
Card Holder Name:
Card Holder Phone #:
Company Name:
Billing Address:
City/State/Zip:
Visa MasterCard AMEX
I/We understand that the part(s), invoice(s) or sales orders(s) ordered / listed above will be charged to the credit card noted upon order acknowledgement.
Additionally, items ordered will not be processed until confirmation/authorization of charge is made. If the charge is for labor, a charge
confirmation/authorization will be performed prior to labor commencement. If the credit card is denied, Veolia will notify the cardholder to obtain an
alternative form of payment prior to processing the order
3 digit # located on back of card
My signature below is my company’s acknowledgement and acceptance of this order including all stated terms and conditions, is an acknowledgement
that I am authorized to sign this document on behalf of my company, and further authorizes Veolia to use the information entered in this section (if any)
to process credit card payment for this order.
•IF YOU SUBMIT A PO, PLEASE REFERENCE VEOLIA WATER TECHNOLOGIES, INC. QUOTATION NUMBER TO PROCESS ORDER.
•The Buyer is responsible for inspecting the equipment upon delivery and documenting any damage in writing on the delivery tickets. Signing
delivery tickets without the notation of damage or missing items deems the equipment acceptable.
•The pricing is expressly contingent upon the items in this quotation & is subject all terms stated herein, including all attached Veolia Water
Technologies, Inc. Standard Terms of Sale. No additional terms contained within Owner's and/or Engineer's Plans, Specifications & Purchase Orders
shall apply to nor become a part of this Quote.
•Except in the case where there are active, applicable, and mutually executed terms and conditions in place between Veolia and Purchaser prior to
issuance of this Quotation, the Parts and/or Services provided are subject to the terms and conditions linked above. These terms and conditions will
not change, but please print and include with your records if necessary.
Page 38 of 68
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: Review of Bids – Glen Brooke Drive and Jackson Drive Path Project
Meeting Date: June 24, 2025
Background and Analysis:
As part of the 2025 Capital Improvement Plan (CIP), $125,000 was budgeted for the
reconstruction of the Jackson Drive path. Additionally, the CIP includes a proposed budget of
$140,000 in 2029 for the future reconstruction of the Glen Brooke Drive path.
Upon review and on-site inspection of both paths, it is my determination that the Glen Brooke
Drive path is currently in worse condition and should be prioritized for reconstruction this year.
Bids were received from four contractors for the reconstruction of both pat hs. In addition, I
asked all four contractors to submit proposals for preventative maintenance services specific to
the Jackson Drive path.
Funding for this project will come from Account Number:
600-00-56700-400-000 (Capital Projects Repair / Construct)
Recommendation:
I recommend the Village proceed as follows:
• Award the reconstruction of the Glen Brooke Drive path to Poblocki Paving in the
amount of $88,505.00 with as needed undercutting at $48.00/Ton.
• Award preventative maintenance work for the Jackson Drive path to Johnson and Sons
Paving in the amount of $7,300.00.
By proceeding with these two proposals, the Village will address both path segments this year
appropriately based on current conditions and will complete the work for a total cost of
approximately $95,805, which is approximately $29,000.00 under the 2025 budgeted amount.
By completing work on both paths this year, we can reevaluate allocations of path funds in
future years.
If you have any questions, please let me know.
JS
Page 39 of 68
Taking the lead in Washington County
Bid Tabulation
Address / Location Work Type Contractor Price
Glen Brooke Drive Path Complete Reconstruction Poblocki Paving $88,505.00 $48/Ton Undercutting
Glen Brooke Drive Path Complete Reconstruction Johnson & Sons $89,229.00 $55/Ton Undercutting
Glen Brooke Drive Path Complete Reconstruction PLM Paving $109,340.00 $72/Ton Undercutting
Glen Brooke Drive Path Complete Reconstruction Pro2Pave $117,044.00 $45/Ton Undercutting
Glen Brooke Drive Path Profile Mill / Pave PLM Paving $77,756.00
Address / Location Work Type Contractor Price
Jackson Drive Path Maintenance Johnson & Sons $7,300.00
Jackson Drive Path Maintenance PoblockI Paving $9,803.00
Jackson Drive Path Maintenance PLM Paving $9,300.00 or $9,900.00
(Depending on scope of work)
Jackson Drive Path Maintenance Pro2Pave $13,500.00
Address / Location Work Type Contractor Price
Jackson Drive Path Complete Reconstruction Poblocki Paving $63,174.00 $48/Ton Undercutting
Jackson Drive Path Complete Reconstruction Johnson & Sons $66,251.00 $55/Ton Undercutting
Jackson Drive Path Complete Reconstruction PLM Paving $78,685.00 $72/Ton Undercutting
Jackson Drive Path Complete Reconstruction Pro2Pave $88,744.00 $45/Ton Undercutting
Jackson Drive Path Profile Mill / Pave PLM Paving $58,525.00
Page 40 of 68
Taking the lead in Washington County
Bid Tabulation Address / Location Work Type Contractor Price Glen Brooke Drive Path Complete Reconstruction Poblocki Paving $88,505.00 $48/Ton UndercuttingGlen Brooke Drive Path Complete Reconstruction Johnson & Sons $89,229.00 $55/Ton UndercuttingGlen Brooke Drive Path Complete Reconstruction PLM Paving $109,340.00 $72/Ton UndercuttingGlen Brooke Drive Path Complete Reconstruction Pro2Pave $117,044.00 $45/Ton Undercutting Glen Brooke Drive Path Profile Mill / Pave PLM Paving $77,756.00Address / Location Work Type Contractor Price Jackson Drive Path Maintenance Johnson & Sons $7,300.00Jackson Drive Path Maintenance PoblockI Paving $9,803.00Jackson Drive Path Maintenance PLM Paving $9,300.00 or $9,900.00(Depending on scope of work) Jackson Drive Path Maintenance Pro2Pave $13,500.00Address / LocationWork TypeContractor PriceJackson Drive Path Complete ReconstructionPoblocki Paving $63,174.00 $48/Ton UndercuttingJackson Drive Path Complete ReconstructionJohnson & Sons$66,251.00 $55/Ton UndercuttingJackson Drive Path Complete ReconstructionPLM Paving$78,685.00 $72/Ton UndercuttingJackson Drive Path Complete ReconstructionPro2Pave $88,744.00 $45/Ton UndercuttingJackson Drive Path PLM Paving$58,525.00
Page 41 of 68
Page 42 of 68
Page 43 of 68
Page 44 of 68
Page 45 of 68
Page 46 of 68
Page 47 of 68
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
CC: Board of Public Works; Budget and Finance; Village Board
From: Jack Straehler, Director of Public Works
Subject: 2025-2026 Contract Amendment #2 – Gremmer and Associates
Meeting Date: June 24, 2025
Background and Analysis:
This memo is to inform the Board of the estimated engineering and design cost associated with
the proposed 2026 Eagle Drive reconstruction project.
The Village currently holds a professional services agreement with Gremmer and Associates in
the amount of $193,450 for engineering and design services related to the 2026 street
reconstruction of Hawthorn, Aspen, and Linden.
This Contract Amendment #2 proposes to expand the scope of services to include design and
construction engineering for the proposed 2026 Eagle Drive reconstruction project. Gremmer
and Associates has provided the following options and associated fees for this additional work
scope:
• Rural reconstruction: $78,175.00
• Rural reconstruction with sidewalk: $93,990.00
• Urban reconstruction with sidewalk and storm sewer: $108,375.00
Funding for this contract will come from Account Numbers:
600-00-56700-000-000 (Miscellaneous Capital Projects)
300-00-17600-000-380 (Sewer Construction Work)
200-00-18600-395-000 (Water Construction Work)
After reviewing the proposed alternatives, urban reconstruction with sidewalk and storm sewer
will provide the most comprehensive long-term benefit and align with the Village’s infrastructure
standards and goals.
If you have any questions, please let me know.
JS
Recommendation:
I recommend the Board approve the 2025-2026 contract amendment #2 with Gremmer &
Associates for engineering services for a total amount of $301,825.00.
Page 48 of 68
June 18, 2025
Village of Jackson
W194 N16660 Eagle Drive
Jackson, WI 53037
Attention: Mr. Jack Straehler
Director of Public Works
Subject: Hickory Lane
Contract Amendment No. 2
Dear Mr. Straehler:
The following is Contract Amendment No. 2 for the subject project. The original contract dated October
26, 2023, and Amendment No. 1 dated 12/11/2024 is amended as follows:
SCOPE OF SERVICES – ALT. 1 (RURAL RECONSTRUCT – NO SIDEWALK)
1. Survey.
a. Topographic/utility/right-of-way survey and corresponding base map for Eagle Drive from
Hickory Lane to STH 60.
2. Preliminary and final roadway and drainage design/plans for the reconstruction of Eagle Drive
from approximately 350’ north of Hickory Lane to the southern roundabout limits at STH 60.
a. Scope assumes a rural roadway section with 5’ paved shoulders.
b. Scope assumes the roadway will continue to be drained via roadside ditches (no storm
sewer).
c. Scope assumes the existing culverts under Eagle Drive just north of Spruce Street will
not be replaced or extended.
3. Preliminary and final sanitary sewer and water main design
a. Sanitary sewer design/plans scope is limited to removal and replacement of the existing
sanitary sewer manhole cone including castings (no improvements to the mainline pipe
or laterals).
b. Water main design/plans scope is limited to removal and replacement of existing curb
stop boxes, and adjustment of water valve boxes.
7. WDNR/USACE coordination.
a. Add the additional Eagle Drive reconstruction project to the WDNR Notice of Intent for
Stormwater Discharges (NOI) for the 2026 let project.
b. Prepare and submit WDNR/USACE General Permit for the let 2026 project. Scope
assumes any wetland impacts will be able to be permitted via the General Permit; and
that wetland determination, mitigation, jurisdictional determination and/or artificial
wetland exemption/classification will not be required. Individual permits will be
considered additional services.
Page 49 of 68
-2-
6. Street Lighting design (sublet to KL Engineering).
a. Preliminary and final design for continuous street lighting along one side of Eagle Drive
from Hickory Lane to STH 60.
b. Street lighting poles and fixtures will match the recent Village of Jackson poles/fixtures
installed along Spruce Street.
7. Bid documents and bidding
a. Scope assumes the Eagle Drive reconstruction will be added to the project specific
specifications and bid related documents for the 2026 construction project along Linden
Drive, Aspen Drive and Hawthorn Drive.
SCOPE OF SERVICES – ALT. 2 (RURAL RECONSTRUCT – WITH SIDEWALK ALONG EAST SIDE)
1. Same scope of services as Alt. 1, except for the following modifications:
a. Add sidewalk along the east side of Eagle Drive.
b. Add a two-parcel r/w plat for any required land acquisition (permanent r/w or
easements) from the Piggly Wiggly and Ace Hardware properties.
SCOPE OF SERVICES – ALT. 3 (URBAN RECONSTRUCT)
1. Same scope of services as Alt. 1, except for the following modifications:
a. Scope is based on an urban section with curb and gutter, storm sewer, and sidewalk
along the east side of the road.
b. Stormwater management planning/design for the Eagle Drive corridor, in order to
comply with any applicable post-construction performance standards (either WDNR or
Village of Jackson standards). The scope of the project assumes the post-construction
performance standards will be accomplished through catch basins, grass swales, or
biofilters within the limits of the project corridor. Design of an offsite detention pond is
not included in the scope.
c. Prepare a two-parcel r/w plat for any required land acquisition (permanent r/w or
easements) from the Piggly Wiggly and Ace Hardware properties.
d. Water main design/plans scope is limited to offsets required for storm sewer conflicts,
removal and replacement of existing curb stop boxes, and adjustment of water valve
boxes.
Page 50 of 68
-3-
COMPENSATION
ENGINEER will be compensated by the OWNER for work outlined in the Scope of Services a lump sum
amount for the selected alternative as follows:
Alt. 1: Rural reconstruct – no sidewalk = $78,175 (includes $17,871 sublet to KL Engineering)
Alt. 2: Rural reconstruct – with sidewalk = $93,990 (includes $17,871 sublet to KL Engineering)
Alt. 3: Urban reconstruct = $108,375 (include $17,871 sublet to KL Engineering)
Contract Amendment No. 2 increases the lump sum fee for the project from $193,450 (Original w/
Amendment No. 1) to the following (based on the selected alternative):
Alt. 1: Rural reconstruct – no sidewalk = $271,625
Alt. 2: Rural reconstruct – with sidewalk = $287,440
Alt. 3: Urban reconstruct = $301,825
AUTHORIZATION AND TIMING
A receipt of a signed copy of the CONTRACT AMENDMENT shall be considered as authorization to proceed
with the services described.
For the ENGINEER Accepted by the OWNER
__________________________________ ___________________________________
Jeff Chvosta, Vice President Jack Straehler
Gremmer & Associates, Inc. Director of Public Works
___6/18/25_____________________ ___________________________________
Date Date
Page 51 of 68
Village of Jackson Community Center Addition
Application and Certification for Payment
June 2025 Summary
W146 N5650 Enterprise Avenue | Menomonee Falls, WI 53051 | P: 262-345-1280 | F: 262-345-1281
www.moore-cs.com
Village of Jackson
Parks and Recreation Department
N165W20330 Hickory Lane
Jackson, Wisconsin 53037
Attn: Tyler Mentzel, Parks and Recreation Director
RE: Jackson Community Center Addition
Project Pay Application #13
MCS Project # 23033
Enclosed for your use in payment to Moore Construction Services is Pay Application #13 for
$108,416.85.
Moore Construction Services has verified the work completed by project contractors and
approved the amounts included in column G of the AIA G702 and G703 Application and
Certification for Payment.
Following your review and approval, please complete the application for payment forms within
the areas reserved for the OWNER. Thereafter, retain one copy for your records, provide the
second copy to Moore Construction Services.
Please feel free to contact me with any questions or concerns.
Regards,
Jason M. Kruchko
Moore Construction Services
Project Manager
Enclosed: AIA G702-1992 Application and Certificate for Payment #13 dated June 23, 2025
Page 52 of 68
Page 53 of 68
Page 54 of 68
Page 55 of 68
Page 56 of 68
Page 57 of 68
Page 58 of 68
Page 59 of 68
Page 60 of 68
Page 61 of 68
W146 N5650 Enterprise Avenue | Menomonee Falls, WI 53051 | P: 262-345-1280
PARTIAL LIEN WAIVER AND RELEASE Check Date: 6-18-2025 This Partial Lien Waiver and Release is submitted pursuant to the Subcontractor Agreement between Moore nefit of Village of Jackson and Circle Electric, Inc. as Jackson Community Center (the located at N168W20330 Hickory Lane, Jackson, Wisconsin work to be performed by Subcontractor . This Partial Lien Waiver and Release is also submitted pursuant to Subc Payment for low voltage labor, materials and equipment installed in or furnished for the Project TO DATE and Subcontractor hereby waives the y or through the Application Date, on the Project, except as set forth below. (1) The Subcontractor has performed all Work through the date of the Application for Payment, pursuant to the terms and conditions of the Subcontract Documents. (2) Any and all subcontractors, laborers, suppliers and materialmen that have provided labor, material or services to the Subcontractor for use or incorporation into the construction of the improvements to the Property are listed in Subc for Payment. (3) All sums due by Subcontractor to subcontractors or any other party for labor, materials or services used or incorporated into the improvements to the Property, and for which Subcontractor has previously received payment, have been paid and satisfied in full, and there are no outstanding claims of any character arising out of, or related to, Subc activities on, or improvements to, the Property, except as set forth below. (4) Subcontractor is not aware of any claims which may arise against Contractor and/or Owner for damages resulting from injury or death to any employees, subcontractors, or the public at large arising out of any of Subcor construction work on the Property. (5) There are no known Claims of Lien, Preliminary Notices of Lien, or any suits or claims for payment, loss or damage of any kind, nature or description which might constitute a lien upon the Property as of the date of this Partial Lien Waiver and Release Upon Payment, except as set forth below. (6) This Partial Lien Waiver and Release constitutes a representation by the undersigned, for and on behalf of the Subcontractor, that the payment referenced above constitutes full and complete payment for all work performed through the date of the Application for Payment, except as set forth below. (7) Subcontractor will indemnify and save harmless Contractor and Owner from any claim, demand, lien or right to lien, and to defend all actions arising out of the same, and to pay any costs, expenses and attorneysContractor and/or Owner in connection therewith. (8) The Subcontractor certifies and represents that there are sufficient funds remaining in the Subcontract Sum to complete the Project in accordance with the Subcontract Documents. (9) Below is a list of items which serve as an exception to the representations set forth herein (items not listed are waived irrevocably): The undersigned warrants and represents that he or she has full authority to execute this Partial Lien Waiver and Release. SUBCONTRACTOR: Please sign and return this form via: E-Mail: rachael@moore-cs.com Signature: Name & Title: Ryan Kastanek, President Date: 6.19.2025
Page 62 of 68
Page 63 of 68
Page 64 of 68
Page 65 of 68
Page 66 of 68
Page 67 of 68
Page 68 of 68