Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
cc: Village of Jackson Village Board
From: Jack Straehler, Director of Public Works
Subject: 2026 Eagle Drive Proposed Sidewalk
Meeting Date: June 10, 2025
Background and Analysis:
As part of planning for the proposed 2026 Eagle Drive reconstruction project, I want to bring to
the Board’s attention a potential enhancement to the scope of work. The current project
estimate is approximately $2.2 million, which includes full roadway reconstruction with, drainage
ditching, a 5’ paved should and street lights.
I propose that we consider adding a sidewalk along either the east or west side of Eagle Drive
as part of this project. The additional cost for this sidewalk work is estimated at $150,000, not
including land acquisition. The specific side would be determined based on where it is most
practical and cost-effective to acquire the necessary right-of-way.
For comparison, if sidewalk installation were deferred and completed as a standalone project in
the future, the estimated cost would rise to approximately $350,000 plus land acquisition, due to
mobilization and construction efficiencies lost outside of a full reconstruction.
Including sidewalk installation during the planned road reconstruction offers both cost savings
and long-term community benefit.
Please let me know if you have any questions.
JS
Recommendation:
I recommend the Board consider incorporating this addition into the 2026 Eagle Drive project
scope and direct staff to move forward with obtaining an engineering services agreement.
Taking the lead in Washington County
STAFF MEMO Village of Jackson Public Works
To: Brian Heckendorf, Village President
Jen Heidtke, Village Administrator
cc: Village of Jackson Village Board
From: Jack Straehler, Director of Public Works
Subject: 2026 WWTP Upgrades
Meeting Date: June 10, 2025
Background and Analysis:
As part of our ongoing review of the Capital Improvement Plan (CIP), we have updated the
projected costs for the 2026 Wastewater Treatment Plant upgrade originally listed in the CIP at
$5.3 million.
Based on the most current estimates, the revised project cost is approximately $4 million:
• Construction: $3,200,000
• Design & Engineering: $255,000
• Construction Engineering: $200,000
This updated projection represents a reduction of approximately $1.3 million from the original
CIP estimate.
Additionally, the 2025 Wastewater Treatment Plant UV Disinfection Tertiary Filter project,
originally budgeted at $5.7 million, is now projected to come in at around $5.2 million—roughly
$500,000 under budget. The project is also ahead of schedule by approximately six months,
with final completion expected in July 2025.
Please let me know if you have any questions
JS
Recommendation:
No action necessary