City of Oconomowoc
Public Services Committee
Aldermen: Ellis, Chairman / McConnell, Secy / Schellpeper
Tuesday, May 19, 2026 - 6:10 PM
City Hall - Conference Room 3
174 E. Wisconsin Ave. Oconomowoc, WI 53066
(Or immediately following Finance Committee)
Notice: If a person with a disability requires that the meeting be accessible or that materials at the
meeting be in accessible format, call the City Clerk at least 48 hours prior to the meeting to request
adequate accommodations. Tel: (262) 569-2186.
1. Call to order and confirmation of appropriate meeting notification
2. Roll Call
3. Committee Business
a. Consider/recommend Resolution 26-R3367 Approving the 2026 Annual Sidewalk
Replacement Program
b. Consider/recommend Resolution 26-R3374 Approving Design Services for Traffic Signals at
Hwy 67 and Olympia Fields Drive
4. Adjourn
Gina Kozlik, City Clerk
City of Oconomowoc
Notice is hereby given that a majority of the Common Council will be present at the above scheduled meeting to gather information
about a subject over which they have decision-making responsibility. This constitutes a meeting of the Common Council pursuant to
State ex rel. Badke v. Greendale Village Board, 173Wis. 2d 553, 494 N.W. 2d 408 (1993) and must be noticed as such, although the
Common Council will not take any formal action at this meeting.
1
1
MEMORANDUM
PUBLIC WORKS
Date: May 19, 2026
To: Mayor, Common Council and Public Services Committee
From: Jason Herzog, Director of Public Works
Re: Consider/act on Resolution 26-R3367 Approving the 2026 Annual Sidewalk Replacement
Program
RELATES TO THE STRATEGIC PLAN
Strategic Goal II Improve and Maintain Our Infrastructure/Facilities; B Maintain our Existing Infrastructure
BACKGROUND
Bids were advertised and opened for the 2026 annual sidewalk program on March 12, 2026. Five bids
were received as follows:
Base Alt #1 Alt #2 Total
J.R. Boehlke LLC $41,070 $640 $1,950 $43,600
Sate Contractors Inc $43,200 $880 $1,980 $46,060
Beardsley Concrete $47,121 $800 $1,500 $49,421
Short Pour Delivery Services $49,605 $596.80 $1,950 $52,151.80
Black Earth Pavement $84,577 $900 $2,292 $87,769
The base bid included sidewalk removal and replacement in various locations throughout the City.
Alternate #1 included detectable warning fields for ADA ramps and Alternate #2 included concrete curb
and gutter.
FINANCIAL IMPACT
The low base bid and Alternate #1 from J.R. Boehlke LLC are under budget for sidewalks/crosswalks
outside services as well as funding from the water & electric utility for their work.
ADDITIONAL ANALYSIS
N/A
RECOMMENDATION
Motion to recommend to the Common Council approval of base bid from J.R. Boehlke LLC. in the sum of
$41,070 plus $640 for alternate items added for an adjusted amount of $41,710.00 plus $4,171.00
contingency for a total of $45,881.00.
SUGGESTED MOTION
Motion to approve Resolution 26-R3367.
2
RESOLUTION NO. 26-R3367
RESOLUTION ADOPTING THE 2026 ANNUAL SIDEWALK PROGRAM
WHEREAS, the City of Oconomowoc 2026 budget provides for an annual sidewalk program; and
WHEREAS, bids for the sidewalk program had been advertised for and were received as follows:
Base Alt #1 Alt #2 Total
J.R. Boehlke LLC $41,070 $640 $1,950 $43,600
Sate Contractors Inc $43,200 $880 $1,980 $46,060
Beardsley Concrete $47,121 $800 $1,500 $49,421
Short Pour Delivery Services $49,605 $596.80 $1,950 $52,151.80
Black Earth Pavement $84,577 $900 $2,292 $87,769
and
WHEREAS, the low base bid and alternate #1 from J.R. Boehlke, LLC is under budget for general
fund - sidewalks; and
WHEREAS, Department of Public Works staff, and the Public Services Committee recommend
that the bid of J.R. Boehlke, LLC be accepted.
NOW THEREFORE, BE IT HEREBY RESOLVED the base bid in the sum of $41,070 plus $640
for alternate items added for an adjustment amount of $41,710 be and the same is hereby accepted, and
appropriate city officials are authorized to enter into a contract with J.R. Boehlke, LLC Contractors for
said projects.
BE IT FURTHER RESOLVED a 10% contingency of $4,171.00, net project cost of $45,881.00, is
allowed for the construction with any expenditures exceeding the approved bid amount plus the
contingency requiring Common Council approval.
BE IT FURTHER RESOLVED that this is a unit price contract with estimated quantities, and
accordingly the actual quantities and therefore the final contract price may vary.
BE IT FURTHER RESOLVED that this resolution not become effective, and no notice of award
be issued unless and until an appropriate performance bond and a certificate of insurance are filed with
the City Clerk.
BE IT FURTHER RESOLVED all of the work described in this resolution is within the budget with
cost allocation as follows:
Account
Name
Account
Number
Project
Number
Contract
Quantities
Sidewalks 100-505-5345-210 N/A $ 36,950.00
3
Water 602-573-7000-210 226004 $ 3,570.00
Electric 603-573-6594-340 N/A $ 1,190.00
TOTAL $ 41,710.00
DATED: May 19, 2026
CITY OF OCONOMOWOC
By:___________________________
Matt Rosek, Mayor
ATTEST:
___________________________
Gina Kozlik, Clerk
4
1
MEMORANDUM
PUBLIC WORKS
Date: May 19, 2026
To: Mayor, Common Council and Public Services Committee
From: Jason Herzog, Director of Public Works
Re: Consider/act on Resolution 26-R3374 Approving Design Services for Traffic Signals at Hwy 67
and Olympia Fields Drive
RELATES TO THE STRATEGIC PLAN
Strategic Goal-
Section II: Improve and Maintain Our Infrastructure and Facilities
Part B: Maintain Our Existing Infrastructure
BACKGROUND
A Request for Proposals (RFP) was completed for the design of the traffic signals and intersection
modifications for STH 67 and Olympia Fields Drive. Proposals were sent to 27 engineering firms. We
received 5 proposals on Monday April 20, 2026.
The scope of services in the RFP included the following tasks:
Task 1 Permanent Traffic Signal Installation Plans & Bid Package
Task 2 Project Bidding / Post Bid Tasks
The RFP required a Not-to-Exceed (NTE) cost for the tasks associated with the design work. We utilize
the hybrid QBS (Qualifications Based Selection) process to evaluate proposals. This hybrid evaluation
process includes a technical evaluation consisting of 80% of points and cost evaluation consisting of 20%
of points. The consultant with the highest combined total of points will be recommended to Council for
approval with the not to exceed cost plus authorization for staff to execute a 10% contingency. Consultants
may not perform construction management services for projects their firm designed.
ADDITIONAL ANALYSIS
Proposals were reviewed and scored by Heath Brozovich, Assistant Director of Public Works, Mark Frye,
City Administrator, and Jason Herzog, Director of Public Works. Four of the five firms obtained more than
the 80% point requirement for further consideration. The scoring summary and the not-to-exceed cost
information is shown below.
5
2
City staff recommend taking the #1 ranked/scored consultant, TADI (Traffic Analysis and Design Inc.)
FINANCIAL IMPACT
Based on the proposal received from TADI. a Not-to-Exceed cost of $74,585.00 plus a 10% contingency
of $7,458.50 for a total of $82,043.50. The design and installation of a traffic signal at this intersection
was included in the original TIF 7 plans.
COMMITTEE RECOMMENDATION
Motion to recommend to the Common Council acceptance of the Not-to-Exceed proposal from TADI a
Not-to-Exceed cost of $74,585.00 plus a 10% contingency of $7,458.50 for a total of $82,043.50.
SUGGESTED MOTION
Motion to approve Resolution 26-R3374.
City of Oconomowoc
May 19th 2026
Total
Points
Average
Points Rank
Baxter & Woodman 254 84.7 3
Graef 195 65.0 5 <-Eliminated from Cost Review
Kapur 244 81.3 4
raSmith 272 90.7 1
Tadi 265 88.3 2
Total Possible Points 300 100
Quality and
Completeness
Proposed
Methodology
Past Similar
Experience
Staff
Qualifications
and Experience
Contract
Cost
Points
Total
Points Proposal Cost
% Cost
Points Rank
Baxter & Woodman 22.3 22.3 20.7 19.3 23.5 108.1 79,460.00$ 94% 3
Kapur 19.0 19.3 20.7 22.3 21.0 102.4 88,585.00$ 84% 4
raSmith 21.7 21.3 24.3 23.3 21.7 112.4 85,840.00$ 87% 2
Tadi 22.0 20.3 23.0 23.0 25.0 113.3 74,585.00$ 100% 1
STH 67 Traffic Signals at Olympia Fields Drive
Technical Score
Average Technical Score with Pricing Factor
6
RESOLUTION NO. 26-R3374
RESOLUTION AWARDING TRAFFIC SIGNAL DESIGN AT STH 67 & OLYMPIA FIELDS
DRIVE
WHEREAS, design engineering services are required for the traffic signal installation at
STH 67 & Olympia Fields Drive; and
WHEREAS, Department of Public Works representatives prepared a Request for
Proposal advertisement, published the same, and based thereon received five proposals; and
WHEREAS, City Staff followed Procurement Policy for professional services and used a
combined approach to evaluate proposals by weighing 80% of the points for the technical
evaluation and 20% for cost, so cost is incorporated as a factor; and
WHEREAS, based on the evaluation process completed by the Director of Public Works,
Assistant Director of Public Works, and City Administrator, the top three firms were ranked as
follows:
1. Traffic Analysis & Design, Inc. (TADI)
2. raSmith
3. Baxter & Woodman
WHEREAS, the proposal from TADI to complete the design engineering services, and
survey services for the traffic signal installation at STH 67 & Olympia Fields Drive is $74,585.00;
and
WHEREAS, City staff and the Public Services Committee recommend that the proposal
of TADI in the amount of $74,585 for design engineering services and survey services for the
traffic signal installation at STH 67 & Olympia Fields Drive.
NOW THEREFORE, BE IT HEREBY RESOLVED the proposal of TADI in the sum of
$74,585.00 be and the same is hereby accepted, and appropriate City officials are authorized to
enter into a contract with them for said work.
BE IT FURTHER RESOLVED this is a Not-to-Exceed price proposal with a 10%
contingency of $7,458.50 for a total cost of $82,043.50.
BE IT FURTHER RESOLVED the project cost will be allocated and charged to TID 7.
DATED: May 19, 2026 CITY OF OCONOMOWOC
By:_________________________
Matt Rosek, Mayor
ATTEST:
_____________________________
Gina Kozlik, Clerk
7