Public Works Committee — Minutes
City of Pewaukee · Waukesha County · General · meeting of Mar 5, 2026 · Minutes
Open the original document More from City of Pewaukee
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
City of Pewaukee
W240 N3065 Pewaukee Road
Public Works Committee Meeting Minutes
Thursday, March 5, 2026
In Attendance:
Mayor Steve Bierce, Alderman Jerry Wamser, Michael Kreiter, Jim Blackwood
Also In Attendance:
Director of Public Works M. Wagner, City Engineer M. Gabbey, Chief Engineer—Utilities R.
Wirtz, Utility Manager J. Mueller, Utility Assistant Manager R. Kincaid, Administrative Assistant
H. Jacobs
1. Call to Order and Pledge of Allegiance
Mayor Bierce called the meeting to order at 4:00 p.m. and called for everyone to stand for
the Pledge of Allegiance.
2. Public Comment - Please limit your comments to two minutes. If further time for discussion
is needed, please contact your District Alderperson prior to the meeting.
There were no public comments.
3. Discussion and Action Regarding the Minutes
3.1 Discussion and possible action to adopt Jan 22 2026 meeting minutes.
Motion was made and seconded (M. Kreiter, J. Blackwood) to approve the
January 22, 2026 meeting minutes. The motion passed unanimously.
4. Water and Sewer Division
4.1 Presentation and Discussion Related to Ehlers 2025 Sewer Rate Study Phase 1.
[Wagner/Mueller]
Ms. Mueller presented information about the Ehlers sewer rate study, which had been
presented to the Common Council the previous month. The study evaluated the
Utility's current financial condition and identified the need for a rate increase in 2026.
Ms. Mueller explained that the Utility has begun drawing on its reserve funds and
emphasized that Ehlers standard of practice follows a philosophy of maintaining a 1.4
debt coverage ratio. This means the Utility should generate $1.40 in revenue for every
$1.00 of debt, ensuring both debt obligations are met, and adequate reserves are
maintained. Ms. Mueller noted that, without a rate increase, reserves will continue to
decline. She also highlighted that recent rate increases from the Lake Pewaukee
Sanitary District (LPSD) and the City of Waukesha have compounded the need for
this financial strategy.
Restoring the Utility to long-term fiscal stability remains a priority, with careful
consideration given to both financial sustainability and the potential impacts on
community members.
Phase 1 of the study confirmed the need for rate increases. Phase 2 will determine
developing specific rate structures, with recommendations to be brought back to the
Council. The goal is to implement new rates by June 2026.
Mr. Blackwood asked whether the 1.4 ratio is standard practice. Ms. Mueller
confirmed that Ehlers applies this guideline across all municipalities it serves. She
added that the Council could consider a stepped approach to implementing the rate
increases if there is concern about the immediate impact, allowing for continued use
of reserves.
Mr. Blackwood also inquired about the current coverage ratio and noted the
substantial projected increases of 14.7% annually over four years—totaling nearly
60%. Alderman Wamser expressed concern about the burden such increases would
place on residents who are not receiving comparable wage increases.
Ms. Wagner emphasized the importance of considering that sewer rates have
remained unchanged since 2021, while many residents have experienced wage
increases during that period. She also pointed out that LPSD has implemented nearly
double-digit rate increases over the past three years—costs that are outside the City’s
control. Additionally, the City of Waukesha also had significant increases after the City
of Pewaukee adopted its current rates.
Ms. Wagner noted that previous attempts to create different rate zones were not
feasible due to state statutes requiring uniform rates across the service area. The
discussion also touched on frustrations with regulatory constraints and their impact on
Utility costs.
Ms. Mueller clarified that while the projected increases are not driven by any single
major capital project, but rather by a range of anticipated infrastructure needs included
in the study. While some projects may ultimately proceed and others may not, the 1.4
coverage philosophy provides for ongoing infrastructure needs. She also noted that a
significant portion of the City still lacks municipal sewer service, and future septic relief
plans could result in additional capital projects.
The Committee acknowledged the inevitability of infrastructure replacement costs,
referencing the recent Gun Club lift station replacement as an example of necessary
but costly improvements. Ms. Mueller confirmed that the Council has requested rate
comparisons from other Waukesha County communities for future meetings. Ms.
Wagner added that the City of Pewaukee’s system’s spread-out nature with areas
separated by unsewered land results in higher per-capita costs compared to more
compact communities.
4.2 Presentation and discussion related to SEWRPC Sanitary Sewer Service Area
Update. [Mueller/Wagner]
Ms. Mueller provided an update on the City's work with Southeastern Wisconsin
Regional Planning Commission (SEWRPC) regarding the sewer service area plan.
She explained that SEWRPC had previously allowed communities to make smaller
regional amendments to their sewer service plans; however, due to the length of time
since the last comprehensive update, SEWRPC has decided against processing
individual amendments.
In response, the City has requested that SEWRPC conduct a comprehensive review
of the remaining unmapped areas within the City. Ms. Wagner clarified that this effort
specifically includes the Ryan Road area, which is currently not mapped by
SEWRPC’s plan despite being included in the Brookfield treatment plant's capacity
calculations.
This mapping is essential for obtaining WI Department of Natural Resources (DNR)
approvals for any future development. This process will involve SEWRPC reviewing
environmental areas throughout the community and consulting with the adjacent
communities. Ms. Mueller noted that this effort is expected to take a minimum of one
year to complete.
Ms. Wagner further explained there is a developer interested in the area known as
Winklemann Farms for potential industrial development. SEWRPC is aware of this
interest and has indicated a willingness to work with the City to accommodate
potential approvals ahead of the full plan update, depending on project timing.
The developer's progress to date has been inconsistent, facing multiple hurdles.
Originally, sewer service to the area was expected to be provided through the
Kopmeier lift station; however, the City has since been working with the Village of
Pewaukee to identify a new, more efficient connection point that would require fewer
infrastructure upgrades.
Ms. Wagner noted that while some sewer upsizing will still be necessary, the extent of
those improvements will not be known until further studies are completed. The
developer has not been willing to fund these required studies to date.
Alderman Wamser asked about notification requirements to neighboring communities.
Ms. Mueller confirmed that, as a part of SEWRPC’s process, notification letters were
sent to surrounding communities last summer. Two rounds of letters were completed,
and no communities requested amendments to their respective plans.
5. Engineering Division
5.1 Discussion and possible action regarding the Intergovernmental Agreement Between
the City of Pewaukee and Waukesha County Regarding the Municipal Recycling
Dividend Program. [Wagner]
Ms. Wagner provided a comprehensive overview of the recycling program's history
and current challenges. Waukesha County has served as the designated responsible
unit for recycling for 25 communities, including the City of Pewaukee, since 1990.
From 2015 until May 2023, recycling was processed at a joint Materials Recovery
Facility (MRF) co-owned by Milwaukee and Waukesha County.
A fire in May 2023 gutted the entire facility, making it financially unfeasible to restore
operations. The county subsequently dissolved its agreement with Milwaukee and
issued a Request for Proposal for recycling processing services, which was awarded
to Waste Management. All recycling is now processed at Waste Management's facility
in Germantown.
Ms. Wagner noted that the new facility is highly automated and efficient, noting it was
recently upgraded in 2021-2022. The county requested that all communities execute
updated Intergovernmental Agreements (IGAs) to reflect the new location and revised
provisions.
However, several concerning changes were made to the agreement. The original IGA
included language stating that if recycling needed to be taken to another location with
additional costs, the county would cover those costs. This language was removed,
with the county asserting that its contract with Waste Management covers all
processing costs and that communities are included under the term "county."
Ms. Wagner expressed concern with this interpretation and requested either
reinstatement of the original language or explicit inclusion of municipalities in the cost
coverage provision. The county declined both requests.
A second concern involved the county's control over working capital limits. The county
maintains a floor and ceiling limit with a $400,000 range. If the balance falls below the
floor, communities will be charged tipping fees; if it exceeds the ceiling, communities
receive dividend payments based on recycling tonnage. The county retains authority
to adjust these limits without community consultation, despite Ms. Wagner's request
for a subcommittee process to review and justify such changes.
Ms. Wagner also requested greater transparency regarding the county's education
program and budget. While the county agreed to share educational information, they
refused to include this commitment in the IGA. Similarly, requests to include budget
transparency language were denied, with the county directing communities to its
website instead.
Throughout approximately a year of discussions, Ms. Wagner stated that the county
was uncooperative and took advantage of the fact that state law provides no opt-out
mechanism for communities designated under a responsible unit in 1990.
Communities are required to deliver recycling to the county regardless of whether they
sign the IGA.
The IGA primarily serves to designate the delivery location and establish the dividend
program, which the county claims is unique nationally. However, the City of Pewaukee
has not received dividends for several years, and Ms. Wagner does not anticipate any
in the near future based on current market conditions. She noted that communities
may eventually be required to pay tipping fees for recycling.
Despite these concerns, Ms. Wagner recommended approval of the IGA to maintain
eligibility for potential future dividends, as communities that do not sign would forfeit
that opportunity.
Alderman Wamser expressed frustration with the situation, comparing it to
communities that simply landfill everything rather than deal with recycling
complexities. Ms. Wagner acknowledged the program's benefits, noting Waste
Management's efforts to find markets for difficult materials such as plastic bags and its
acceptance of #4 plastics, which were not processed at the previous facility.
She highlighted City of Pewaukee's strong recycling performance, with a residual rate
of 12% compared to the national average of 30%, demonstrating effective community
participation and county messaging. Ms. Wagner praised Waste Management's
ongoing efforts to find new markets for recyclable materials but reiterated her
disappointment with the county's unwillingness to cooperate or address community
concerns.
The Committee acknowledged it had no real alternative given state law requirements.
Motion was made and seconded (J. Wamser, J. Blackwood) to recommend
approval of the Intergovernmental Agreement between the City of Pewaukee
and Waukesha County regarding the Municipal Recycling Dividend Program.
The motion carried unanimously.
6. Public Comment - Please limit your comments to two minutes. If further time for discussion
is needed, please contact your District Alderperson prior to the meeting.
There were no public comments
7. Adjournment
Motion was made and seconded (J. Blackwood, M. Kreiter) to adjourn the meeting at
4:34 p.m. The motion passed unanimously.
Respectfully Submitted
Magdelene Wagner
Director of Public Works