1. Roll Call
Chair Mike Kaczmarek called the meeting to order at 6:00 PM.
Present: Mike Kaczmarek, Troy Hojnacki, Ben Lasecki, Sarah Brillowski
Absent: Dan Farley
2. Pledge of Allegiance
The Pledge of Allegiance was recited.
3. Approval of July 28, 2026, Public Works and Parks Committee Minutes
Motion by Ben Lasecki, second by Troy Hojnacki, to approve the July 28, 2026 Public Works and
Parks Committee minutes. Mike Kaczmarek abstained due to not being present at the July 28
meeting. Motion carried by unanimous voice vote of those voting.
4. Sherman Avenue Reconstruction Project
The committee reviewed the proposed Sherman Avenue Reconstruction Project and updated project
costs. The estimated project budget increased from approximately $289,000 to $305,000. The increase
was attributed primarily to adjusted quantities, contingency amounts, and the addition of approximately
$6,700 in base aggregate for sidewalks.
Approximately $5,000 of the project is associated with the Green Circle Trail and will be reimbursed to the
Village.
Motion by Sarah Brillowski, second by Ben Lasecki, to delay the Sherman Avenue Reconstruction
Project until 2027 and forward the project to the Finance Committee for inclusion in the 2027
budget. Motion carried by unanimous voice vote.
5. 2027 Equipment Purchases
The committee discussed the replacement of two Village mowers, including a 56-inch zero-turn mower and
a larger utility mower. The larger mower is currently being serviced at Riesterer & Schnell for a sensor-
related issue, with approximately $1,600 in repairs incurred thus far.
Quotes were reviewed for replacement equipment consisting of a 60-inch zero-turn mower and a 72-inch
utility tractor/mower. Pricing from Bobcat, Toro, and John Deere ranged from approximately $54,066 to
$56,410.
The John Deere trade-in estimate for the existing equipment was approximately $8,000 combined. The
existing zero-turn mower was valued at approximately $3,000 due in part to its prior fire history.
The committee noted that approximately $50,000 is currently available in the equipment replacement fund
and discussed purchasing the equipment during the current budget year.
Motion by Ben Lasecki, second by Mike Kaczmarek, to recommend Village Board approval of the
purchase of a John Deere 60” Z955R and John Deere 72”1570TC from Riesterer & Schnell. Jake
and Staff will determine whether disposal of the existing equipment through trade-in or auction
provides the best value to the Village. Motion carried by unanimous voice vote.
6. Moratorium on Possible Data Centers
The committee discussed whether the Village should consider a temporary moratorium on data center
development while additional study is conducted.
Current Village zoning ordinances do not specifically identify data centers within the Village's commercial
or industrial districts. The committee discussed the possibility of future development requests and
approximately 25 acres of industrially zoned property near the mill that could potentially be sold for
development.
Discussion included the Village's proximity to the Wisconsin River and WPS transmission infrastructure
along Tommys Turnpike, as well as potential concerns regarding noise, water usage, electrical demand,
and ownership/development structures.
The committee discussed the need for additional information before determining how data centers should
be addressed through Village zoning and land-use regulations. The Wisconsin League of Municipalities
was suggested as a potential resource for guidance. A committee member also contacted a water
specialist seeking information regarding potential water impacts associated with data center development.
Motion by Sarah Brillowski, second by Troy Hojnacki, to forward the question of a data center
moratorium to the full Village Board for discussion and possible action, including consideration of
an appropriate timeline and obtaining additional expert guidance. Motion carried by unanimous
voice vote.
7. Adjournment
The meeting was adjourned at 6:36 PM.