Village of Whiting Utilities Committee Meeting
August 4th, 2026
Place of Meeting: Whiting Municipal Center
1. Roll Call – Meeting called to order by Chairman Lutz at 5 PM. Committee members Kevin Lutz, Jeanna
Trzebiatowski, Karen Curtis, and Mark Zalewski were present. Mike Daniels was absent. Superintendent
of Utilities and Public Works, Jake Wilcox, and Village Resident; Diana Szymkowiak, and Sara Brillowski
were also present.
2. People wishing to address the committee. - As Needed.
3. Approval of July meeting minutes. – Minutes were not available.
4. Discussion and possible action re. Multiple vouchers. - Motion made by Curtis to approve multiple
vouchers for July as presented. Second, by Trzebiatowski. Motion carried unanimously by voice vote.
5. Operations and Maintenance report. Supt. Wilcox submitted the following report:
• The water and wastewater treatment plant did meet all requirements for July.
• Village of Whiting Pumpage: ▪ Treated – 5,321,000
Total – 7,833,000
• Neenah Paper Pumpage: o #5 – 16,294,984
o #6 – 37,789,000
o Total – 54,086,984
• We received the final disbursement from the DNR for the Nitrate Tank Replacement Project. This
project is now officially complete.
• The final disbursement request for the Sherman Avenue Sewer Replacement Project was submitted to
the DNR.
• LW Allen has been onsite several times to diagnose the repair control issues we’ve been experiencing
with the influent screen at the wastewater treatment facility.
• The private well permitting program is underway with positive participation so far.
• JG Ahern was at the water treatment facility to replace a leaking flange and pipe fitting on the
treatment system piping for Tank 4.
• Superintendent Wilcox and staff have been preparing for Lead & Copper sampling as required by the
US EPA. This will occur during the second week of August.
• The WI DNR recently added PFAS testing requirements for our wastewater sludge through a statewide
general permit. Superintendent Wilcox is working with the DNR to ensure all requirements of the new
permit are understood and met.
• We received notification that our WPDES permit for the wastewater treatment facility is due for
renewal in 2027. Over the next few months, we will be working to complete all of the required
additional testing and reporting that is needed to renew the discharge permit.
• T-Mobile has submitted an application to replace failed radio units that were installed on our water
tower as part of their recent upgrade project.
• Salt was delivered to the water treatment facility.
• The engineers for the Sludge Replacement project are currently working to finalize the design for the
project and everything for that project remains on schedule.
6. Correspondence. None.
7. Such other matters as permitted by law. Lutz questioned how our Cyber security was looking in light
of the current Water and Waste Water attacks that have occurred recently. Superintendent Wilcox is
currently checking with our provider.
8. Adjourn. Trzebiatowski made a motion to adjourn. Second by Curtis. Motion carried by voice vote to
adjourn at 5:14 pm.
Respectfully Submitted
Kevin Lutz Recording Secretary