Village of Whiting Utilities Committee Meeting
June 2, 2026
Place of Meeting: Whiting Municipal Center
1. Roll Call – Meeting called to order by Chairman Lutz at 5 PM. Committee members
Kevin Lutz, Mike Daniels, Karen Curtis, and Mark Zalewski were present. Jeanna
Trzebiatowski was absent. Superintendent of Utilities and Public Works, Jake Wilcox,
and Village Resident; Diana Szymkowiak, were also present.
2. People wishing to address the committee. - As Needed.
3. Approval of May meeting minutes. – Motion made by Daniels to approve minutes for
May as presented. Second, by Curtis. Motion carried unanimously by voice vote.
4. Discussion and possible action re. 2025 Compliance Maintenance Annual
Report. - Motion made by Daniels to send the compliance maintenance annual report
to the village board for approval. Second, by Curtis. Motion carried unanimously by
voice vote.
5. Discussion and possible action re. Water System Parts Inventory. Discussion
that we need to restock our inventory of hydrants and various spare parts. Motion
made by Curtis to move forward with purchasing the hydrants Core and Main in the
amount of $7,188 and purchase the miscellaneous spare parts from Ferguson in the
amount of $3,587.50. Second, by Lutz. Motion carried unanimously by voice vote.
6. Discussion and possible action re. Sludge Press Replacement Project. Discussion
was held on the sludge press replacement project. There will be an increase in the
project to $694,000. This project will be discussed at a public hearing at the monthly
Village Board meeting 6/9/26 at 6 pm.
7. Discussion and possible action re. Multiple vouchers. - Motion made by Curtis to
approve multiple vouchers for April and as presented. Second, by Daniels. Motion
carried unanimously by voice vote.
Motion made by Daniels to approve multiple vouchers for May as presented. Second,
by Curtis. Motion carried unanimously by voice vote.
8. Operations and Maintenance report. Supt. Wilcox submitted the following report:
• The water and wastewater treatment plant did meet all requirements for April. A
complete set of results for May is not available yet.
• Village of Whiting Pumpage:
▪ Treated – 4,109,000
Total - 6,185,000
• Neenah Paper Pumpage:
o #5 – 16,537,088
o #6 – 38,749,000
o Total – 55,286,088
• The Sherman Avenue sewer replacement project loan successfully closed and we’ve
received our first project disbursement for approximately $217,000. This will
replenish funds used to pay contractor invoices.
• I attended the Portage County Groundwater Citizens Advisory Committee meeting.
• Sam Janssen and Will Verstegen took multiple DNR Operator exams to obtain the
required licenses.
• I have been working with multiple vendors to obtain price quotes for restocking our
water system parts inventory as many parts were utilized in 2025 as a result of fire
hydrant installations and a water main break.
• I have been working on the final disbursement requests and project close-outs for the
Nitrate Tank Replacement project.
• Village staff have started our annual sewer jetting program and we will be working
on the southern portion of the Village’s collection system.
• The 2025 Compliance Maintenance Annual Report (CMAR) for the sewer utility was
completed.
• Quarterly nitrate and raw bacteriological testing was completed.
• I have been working with Joel Lemke in Stevens Point and Matt Saloun in Plover to
make improvements to wellhead protection ordinances in relation to areas of their
respective communities that are within our 5-year time of travel.
• GiTi Development LLC has submitted a request to the Village Board for a variance to
allow them to utilize Stevens Point’s water supply for a portion of the Phase 1 lots.
• The proposed Circle K development at the intersection of Post Road & McDill
Avenue has officially been abandoned. This project will not be proceeding any
further as a result of a shift in Circle K’s Wisconsin Development Strategy.
• Sam Janssen and I have been working to improve our existing utility GIS mapping
system.
Motion made by lutz to approve report as presented. Second by Daniels. Motion
carried unanimously by voice vote.
9. Correspondence. None.
10. Such other matters as permitted by law
11. Adjourn. Daniels made a motion to adjourn. Second by Curtis. Motion carried by
voice vote to adjourn at 5:29 pm.
Respectfully Submitted
Mike Daniels
Recording Secretary