2019 Capital Budget
Village of Menomonee Falls · Waukesha County · Budget documents
Open the original document More from Village of Menomonee Falls
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
PROPOSED
FUNDING PLAN
2019 Capital Budget
GENERAL FUNDING GOALS
Maintain our current annual debt levy of about $2.4 million
Maintaining a steady debt levy is a key component of our long-term
financing goals.
The $2 million levy supported borrowing in our 2019 capital budget
fits into our long-term goal.
2.3
2.35
2.4
2.45
2.5
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029
Millions
Projected Debt Levy
RECOMMENDED FUNDING SUMMARY
(for the Proposed 2019 Capital Budget)
New
GO Debt
Cash
on Hand
Impact
Fees To t a l
Public Works & StormUtility (10-year tax levy debt) $ 1,900,000 $ 890,000 $ - 0 - $ 2,790,000
Water Utility (20-year debt paid from user charges) 1,235,000 2,400,000 275,000 3,910,000
Park Projects 1,800,000 350,000 500,000 2,650,000
Sewer Utility (paid from user charges) - 0 - - 0 - 215,000 215,000
T otal proposed 2019capital budget $ 4,935,000 $ 3,640,000 $ 990,000 $9,565,000
Cash from the sale of unused property
$1.7 million to be paid for with future Park Impact Fees
Cash from the sale of the Distribution Center
2019 CAPITAL BUDGET AT A GLANCE 2/7/2019
VILLAGE PROJECTS
Approved Crucial Declaration
Project # DESCRIPTION Life COST EXPLANATION to Recommend of Intent by
Must Do Operations VB on file
In order to reduce potential hazards to pedestrians and to minimize the exposure of the Village to liability for personal injury, the Village
2019 Sidewalk Replacement Program 10+ $150,000 has initiated an on-going program for inspection of existing sidewalks and for repair or replacement of defective sidewalk sections. X
This proposed project is part of the Village’s on-going program to replace defective curb and gutter and repair defective concrete pavements in the
2019 Curb & Gutter Replacement Program 20+ $200,000 Village. The Village initiated the curb a nd gutter replacement program several years ago in conjunction with the Sidewalk Replacement Program and X
has continued this annual program focusing on the most defective and deteriorated curb and gutter sections each year on a rotating basis
throughout the curb and gutter areas of the Village.
The Village also as part of this program replaces of defective concrete pavement on roadways that are maintained by the Village. The Village
maintains several miles of concrete pavement and sections of the pavement have deteriorated to a point that replacement is necessary.
As part of the 2019 Asphalt Paving Program the Engineering Department typically uses two funding sources.
2019 Asphalt Paving Program 10+ $600,000 The first being a portion of the $700,00 0 that the Village Board has appropriated to the Department of X
Public Works 2019 Operating Budget for replacement of deteriorated pavement and the 2nd being the $600,000 that is being asked for
as part of this Capital Budget.
This year as part of the 2019 Asphalt Paving project, the Village will be installing storm sewer that addresses areas of existing roadways
that do not drain properly and are in need of storm sewer and to alleviate sump pump icing issues.
This project would consist of the replacement of the Lilly Road Bridge. The existing structure is a narrow roadway with poor drainage on structure and had
Lilly Road Bridge Replacement 20+ $30,000 significant section loss of deck as detai led in my previous presentations. This section of Lilly Road is an important link in the Village’s Emergency Response X
DESIGN Services to service the north half of the Village. There is also a High School and Elementary School nearby and buses use this route to and from the schools.
The current sufficiency rating is 16.9 based upon the 2016 bridge inspection. On 8/3/09 the asphalt overburden was removed to inspect the concrete deck
and it was discovered that the deck has sustained significant section loss. On a 7-1/2” deck there are in some areas only 2-1/4” remaining with the entire
top rebar being exposed.
The bridge has received a Temporary Surface to allow for small vehicle traffic and rated at H8.2 (16,400 lb vehicle weight). There has been a load limit placed
on this bridge until replacement. This consisted of a 6” Thick wood deck with a 3 inch asphalt overlay. This is a temporary solution until a permanent structure
can be constructed. This Temporary Fix is beginning to fail. The wood deck is vibrating and beginning to affect the girders they are placed on. The asphalt
surface is cracking at the wood deck joint. The Village has been crack filling these joints but they are getting worse.
Replace existing structure with a new 38 ft clear Bridge structure including bicycle accommodations and sidewalks for pedestrians with its proximity to one of
the Villages largest parks. Per the replace in kind policy the sidewalk will be 100 percent local unless this changes in the design process.
The 100 year event currently is at the very top of the structure so in order to meet min standards for the 100 year event to clear the bottom of the proposed
structure would need to be just above the 100 year level so the structure may need to go up a little but should not affect the approach lengths. Once the
structure is design and the hydraulic model created it will determine the actual height of the bridge.
This project consists of the reconstruction of Cheyenne Drive from the Cherokee Drive to Blackfoot Drive. The reconstruction will include relaying of the water
Cheyenne Dr - Cherokee Drive to Blackfoot Drive 20+ $440,000 main with appurtenances in Cheyenne Driv e along with the adjusting of sanitary sewer manholes, removal and replacement of curb & gutter and driveway X
WM Relay, Storm Sewer & Street Reconstruction approaches , upsizing of existing storm sewer, installation of additional storm sewer and removal and replacement of the asphalt pavement.
CONSTRUCTION
The existing 8” water main will be replaced due to the age, cast iron material of the water main and the water main breaks in this subdivision.
This Area also has experienced storm water problems and the upsize in storm sewer was recommended as part of the Storm Sewer System Study
completed by Ruekert/Mielke in 2001. The Storm Sewer will also eliminate the poor drainage, sump pump icing, standing water potential damage to the
curb & gutter and asphalt pavement.
2019 CAPITAL BUDGET AT A GLANCE 2/7/2019
VILLAGE PROJECTS
This project consists of the design of the reconstruction of Cheyenne Drive from the Blackfoot Drive to the Village Stand Pipe on the Old Falls Village property.
Cheyenne Dr - Blackfoot Drive to Stand Pipe 20+ $280,000 The reconstruction will include relaying of the water main with appurtenances in Cheyenne Drive along with the adjusting of sanitary sewer manholes, removal X
WM Relay, Storm Sewer & Street Reconstruction and replac ement of curb & gutter and driveway approaches, upsizing of existing storm sewer, installation of additional storm sewer and removal and
DESIGN & WATER MAIN replacement of the asphalt pavement.
The existing 8” water main will be replaced due to the age, cast iron material of the water main and the water main breaks in this subdivision.
This Area also has experienced storm water problems and the upsize in storm sewer was recommended as part of the Storm Sewer System Study
completed by Ruekert/Mielke in 2001. The Storm Sewer will also eliminate the poor drainage, sump pump icing, standing water potential damage to the
curb & gutter and asphalt pavement.
The survey, design and water main relay will be completed in 2019 with the remaining storm sewer and roadway reconstruction being part of future
Capital Budgets.
This project consists of the reconstruction of Sheridan Drive from Ann Avenue to Menomonee Avenue. The reconstruction will include a relay of the existing
Sheridan Drive - Ann Ave to Menomonee Ave 20+ $255,000 water main with appurtenances, reconstru cting of the sanitary sewer manholes, removal and replacement of the curb & gutter and driveway approaches, X
WM Relay, Storm Sewer & Street Reconstruction installati on of storm sewer and removal and replacement of the base course and asphalt pavement. This project will also include the continuation of the
DESIGN & WATER MAIN storm sewer installed in Ann Avenue.
The existing 6” water main will be replaced with an 8” water main due to its age and material as well as due to the proposed size of the storm sewer a
good portion of the water main needs to be offset or moved.
Also as part of this project the Storm Sewer will be sized appropriately to handle the upstream drainage that flows through this area. This is the bottom end
of the storm sewer system that will allow the Village to ultimately extend storm sewer to Menomonee Avenue.
The survey, design and water main relay will be completed in 2019 with the remaining storm sewer and roadway reconstruction being part of future
Capital Budgets.
This project consists of the reconstruction of Jacobson Drive & Hiawatha Drive from Appleton Avenue to Mary Court. The reconstruction will include a relay
Jacobson Dr & Hiawatha Dr - Appleton to Mary Ct 20+ $790,000 of the existing water main with appurten ances, reconstructing of the sanitary sewer manholes, removal and replacement of the curb & gutter and driveway X
WM Relay, Storm Sewer & Street Reconstruction approaches , installation of storm sewer and removal and replacement of the base course and asphalt pavement. Any defective sidewalk and
CONSTRUCTION driveway approaches will be replaced.
The existing 6” water main will be replaced with an 8” water main due to the age of the water main and material of the water main. The existing water
main is sandcast with lead joints. The DNR requires that when possible the existing water main with lead joints and lead laterals be removed from service.
This project consists of the design of the reconstruction of Jacobson Drive and Dardis Place from Hiawatha to Dardis. The reconstruction will include a relay
Jacobson Dr & Dardis Pl - Hiawatha to Theodore 20+ $285,000 of the existing water main with appurten ances, reconstructing of the sanitary sewer manholes, removal and replacement of the curb & gutter and driveway X
WM Relay, Storm Sewer & Street Reconstruction approaches , installation of storm sewer and removal and replacement of the base course and asphalt pavement. Any defective sidewalk and driveway
DESIGN & WATER MAIN approaches will be replaced.
The existing 6” water main will be replaced with an 8” water main due to the age of the water main and material of the water main. The existing water main is
sandcast with lead joints. The DNR requires that when possible the existing water main with lead joints and lead laterals be removed from service.
The survey, design and water main relay will be completed in 2019 with the remaining storm sewer and roadway reconstruction being part of a
future Capital Budget.
This project consists of the reconstruction of Ann Avenue from Sheridan Drive to Jacobson Drive. The reconstruction will include a relay of the existing water
Ann Avenue - Sheridan to Jacobson 20+ $420,000 main with appurtenances, reconstructing of the sanitary sewer manholes, removal and replacement of the curb & gutter and driveway approaches, installation X
WM Relay, Storm Sewer & Street Reconstruction of storm s ewer and removal and replacement of the base course and asphalt pavement. This project will also include the construction of the storm sewer into
CONSTRUCTION the Village Park from Ann Avenue as well as the stabilization of the navigable waterway that runs through Village Park to the Box Culvert under the parking
lot of Krueger’s.
The existing 6” water main will be replaced with an 8” water main due to its age and material as well as due to the proposed size of the storm sewer a good
portion of the water main needs to be offset or moved.
Also as part of this project the Storm Sewer will be sized appropriately to handle the upstream drainage that flows through this area. This is the bottom end of
the storm sewer system that will allow the Village to ultimately extend storm sewer to Menomonee Avenue.
2019 CAPITAL BUDGET AT A GLANCE 2/7/2019
VILLAGE PROJECTS
Manhattan Drive - Menomonee Ave to Franklin Dr 20+ $1,040,000 This project consists of a relay of th e water main with appurtenances in Manhattan Drive from Menomonee Ave to Franklin Drive. The existing 6” water
Water Main Relay main will be replaced due to the age of the water main, material of the water main and the number of breaks. X
DESIGN & CONSTRUCTION
Roger Avenue - Grand Ave to Shady Ln 20+ $500,000 This project consists of a relay of the water main with appurtenances in Roger Avenue from Grand Ave to Shady Lane. The existing 6” water main will be
Water Main Relay replaced due to the age of the water main, material of the water main and the number of breaks. X
DESIGN & CONSTRUCTION
Lisbon Road Water Main Extension 20+ $235,000 This project consists of extending appro ximately 670 lineal feet of 12 inch water main along Lisbon Road from East of Pilgrim Road along the
East of Pilgrim along Willowood Preserve Willowood Preserve. This project would finish the water main loop along Lisbon Road of the Village’s water system providing much needed X
CONSTRUCTION redundancy to the water system.
This project consists of a relay of the water main with appurtenances in St. Regiss Drive from St Franics Drive to the west limit of St. Regis Drive.
St. Regis Drive - St Francis to West Limit 20+ $350,000 X
Water Main Relay The existing 8” water main will be replaced due to the age of the water main, material of the water main and number of breaks in the Shepherd Hills
DESIGN & CONSTRUCTION Addn No. 2 subdivision.
This project consists of relaying the existing 8 inch water main in Fox Ridge Court and Stonefield Drive from Wells #8 & #9 to Maple Crest Lane with a
StoneField Drive - Wells #8 & #9 to Maple Crest Ln 20+ $370,000 12 inch water main. In 2014 the Village hired Ruekert & Mielke to analyze the Village’s water system in the southwest area of the Village. The study came X
Water Main Relay back with some recommendations on improvements that should be made to the system. This project is one of the recommendations that should be done
DESIGN & CONSTRUCTION because due to the smaller diameter water main going to Wells #8 & #9, the velocity and headloss in the water main exceed industry standards when the
pump station is in operation.
This project consists of the first phase of the redevelopment of Village Park into a Specialty Park. In the Fall of 2018 the buildings along Mill Street were
Village Park - Specialty Park Phase I 20+ $2,200,000 demolished in preparation for this red evelopment of Village Park. Phase I will consist of the removal of the softball diamond and lights, removal of the sand X
CONSTRUCTION volleyball court & skate park amenities, the reconstruction of Mill Street and the existing parking lot, creation of the plaza area with bathroom facilities at Mill
Street and Garfield Drive, grading of the east end of the park, construction of an amphitheater and construction of paths & lighting.
This project consists of the following capital improvements to various Community Parks in the Village of Menomonee Falls:
Various Park Improvement Projects 10+ $450,000 X
DESIGN & CONSTRUCTION Willowood Park – Resurface the tennis courts includi ng new paint, new lines, new fencing and new tennis nets and posts.
Oakwood Park – Reset frost heaved posts and fencing around tennis courts and basketball court, paint additional pickleball courts on the existing tennis
courts, reset the frost heaved basketball hoop posts and tennis court net posts, repair the ball diamond fencing and reset fencing posts that have frost
heaved, replace both ball diamond scoreboards, regrade/fill low spots in the ball diamond outfield, install a concrete slab in front of the dumpster enclosure
and paint all four picnic pavilions in the park.
Rotary Park – Renovation of the Fond du Lac Avenue restroom facility including reconfiguration to ADA standards, new flooring, new fixtures, new
furnishings and new lighting.
On March 6, 2017, the Village Board adopted Resolution No. 1148-R-17 authorizing the Village Manager to implement a program to dispose of certain
Village Owned Properties. As stated in this Resolution, “the Board of Trustees finds that the disposal of parcels identified on Exhibit A could further the
public interest and the following goals: generating additional funds for other possible capital projects of the Village; returning the properties to the property
tax rolls; reducing the Village’s property maintenance responsibilities; and furthering economic development and redevelopment in the Village;”. In
accordance with Resolution No. 1148-R-17, our intent is to utilize the proceeds from the disposal of these Village Owned Properties to fund a portion of the
various capital park projects as described above.
This project consists of the acquisition of the necessary sanitary, water and construction easements in order to construct the sanitary sewer and water main
Crossroads Shopping Center 20+ $490,000 conversion of the Cross Roads Shopping Ce nter and adjacent businesses. The Crossroads Shopping Center is located on the south side of County Line X
Sanitary Sewer & Water main Conversion Road between Appleton Avenue and Bancroft Drive. Currently the sanitary Sewer and water for the Crossroads Shopping Center and the adjacent
ACQUISITION businesses on County Line Road and Bancroft Drive is provided by the Village of Germantown. New sanitary sewer and water main will be installed in order
for these Village Businesses to be moved from the Germantown systems to the Menomonee Falls Systems.
Bruceton Manor Subdivision 20+ $480,000 This project consists of the replacement of undersized and deteriorating corrugated Metal Pipes along Bette Drive in the Bruceton Manor Subdivision. The
Bette Drive Culvert Replacement existing CMP Pipes are undersized, the bottoms have rusted out and the configuration is on proper for efficient flow of way along Better Drive. This project X
DESIGN & CONSTRUCTION would install properly sized 4’ X 10’ box culverts with headwalls and railings.
2019 CAPITAL BUDGET AT A GLANCE 2/7/2019
VILLAGE PROJECTS
Total 2019 Capital Budget $9,565,000
Village of Menomonee Falls
2019 Capital Budget Funding Summary
NEW GO DEBT CASH ON HAND
Capital Park Impact Water Current GO Dist Center Village Land Park Water Water Sewer CASH GRAND
Project # Description Projects Fees Utility TOTAL Sale Proc Sale Proc Impact Fees Utility Impact Fees Impact Fees TOTAL TOTAL Comments
Public Works Projects
41213 2019 Sidewalk Program 150,000 150,000 150,000
41214 2019 Curb & Gutter Program 200,000 200,000 200,000
41215 2019 Roads Program 600,000 600,000 600,000 Slag seal & crack filling in
Operating Budget
Transportation Projects
41216 Lilly Rd Bridge (Replacement)
Design 30,000 30,000 30,000
41212 Cheyenne Dr (Cherokee Dr to Blackfoot Dr)
Street, Water, Sewer, Storm Construction 440,000 440,000 440,000
41217 Cheyenne Dr (Blackfoot Dr to Vil. Standpipe)
Design & Watermain Construction 280,000 280,000 280,000
41218 Sheridan Dr (Ann Ave to Meno Ave)
Design & Watermain Construction 255,000 255,000 255,000 Water Utility cash from
change to 20-yr debt
41211 Jacobson/Hiawatha (Appleton to Mary Ct)
Construction 790,000 790,000 790,000 Cash from sale of
Distribution Center
41219 Jacobson/Dardis Ave (Theodore to Dardis Pl)
Design & Watermain Construction 285,000 285,000 285,000 Water Utility cash from
change to 20-yr debt
41197 Ann Ave (Village Park to Sheridan Dr)
Street, Water, Sewer, Storm Construction 100,000 320,000 420,000 420,000 Water Utility cash from
change to 20-yr debt
Parks Projects
64072 Village Park (Specialty Park - Phase I)
Construction 1,700,000 1,700,000 500,000 500,000 2,200,000 GO debt to be paid from
future Park Impact Fees
64073 Park Improv (Willowood, Oakwood, Rotary)
Construction 100,000 100,000 350,000 350,000 450,000 Cash from sale of unused
properties
Water Utility Projects
72063 Manhattan Dr (Meno Ave to Franklin Dr)
Design & Construction 1,040,000 1,040,000 1,040,000 Water Utility cash from
change to 20-yr debt
72064 Roger Ave (Grand Ave to Shady Ln)
Design & Construction 500,000 500,000 500,000 Water Utility cash from
change to 20-yr debt
72065 Lisbon Rd (Ext along Willowood Preserve)
Construction 235,000 235,000 235,000
72066 St Regis Dr (St Francis to West Limit)
Design & Construction 350,000 350,000 350,000
72067 Stonefield Dr (Wells #8,#9 to Maple Crest Ln)
Design & Construction 370,000 370,000 370,000
Sewer Utility Projects
73042 Crossroads Shop Ctr (Sewer/Water Convrsn)
Acquisition 275,000 215,000 490,000 490,000
Storm Utility Projects
74015 Bruceton Manor (Culvert Replacement)
at Bette Drive 480,000 480,000 480,000
2,000,000 1,700,000 1,235,000 4,935,000 890,000 350,000 500,000 2,400,000 275,000 215,000 4,630,000 9,565,000
2/20/2019 10:47 AM Page 1 of 1
VILLAGE OF MENOMONEE FALLS
PROPOSED FIVE YEAR CAPITAL PLAN
2019-2023 2/12/2019
Proposed Proposed Proposed Proposed Proposed 5 Year
Description 2019 2020 2021 2022 2023 Total
VILLAGE PROJECTS
Ann Ave - Village Park - Sheridan Dr - Water main, Stm Swr & Street Reconst 420,000 $420,000
Appleton, Pilgrim & Menomonee Intersection Reconstruction - Intersection Mod., Traffic Signal
Replacement, Overhead Light Removal & Electrical Upgrade $521,000 $521,000
Asphalt Paving Program $600,000 $600,000 $600,000 $600,000 $600,000 $3,000,000
Blackfoot Dr. - Cheyenne Dr to Cherokee Dr - Water, Storm & Street Reconst $280,000 $430,000 $710,000
Bruceton Manor Subdivision - Bette Drive Culvert Replacement $480,000 $480,000
Cheyenne Dr - Blackfoot Dr to Village Standpipe - Water, Storm & Street Reconst $280,000 $320,000 $600,000
Cheyenne Dr - Cherokee Dr to Blackfoot Dr - Water, Storm & Street Reconst $440,000 $440,000
Chippewa Dr. - Cheyenne Dr to Cherokee Dr - Water, Storm & Street Reconst $270,000 $480,000 $750,000
Crossroad Shopping Center - Sanitary Sewer & Water main Conversion $490,000 $1,420,000 $1,910,000
Curb & Gutter Replacement Program $200,000 $200,000 $200,000 $200,000 $200,000 $1,000,000
Forest Dr - Grand to Shady Ln - Water main Relay $495,000 $495,000
Graysland Storm Sewer Replacement $275,000 $275,000
Hayes Ave - Main St to Roosevelt - Water main Rela y $440,000 $440,000
Hiawatha Dr - Mary Ct to Men Ave & Mary Ct - Water main, Storm & Street Reconst $300,000 $527,000 $827,000
Highland Court - Shady Ln to East - Water main Relay $220,000 $220,000
Jacobson Dr - Appleton to Hiawatha & Hiawatha Dr Jacobson to Mary Ct & Dardis Pl-
Water, Storm & Street Reconst $790,000 $790,000
Jacobson Dr - Hiawatha to Theodore & Dardis Ave - Jacobson to Dardis Pl - Water, Storm
& Street Reconst $285,000 $530,000 $815,000
Jacobson Dr - Theodore Dr to Ann Ave - Water, Storm & Street Reconst $196,000 $300,000 $496,000
Kenwood Blvd. - Patton Dr to Park Blvd - Water main, Storm & Road Reconst $620,000 $620,000
Laurel Lane - Grand Ave to West - Water main Relay $230,000 $230,000
Lilly Road Bridge Reconstruction $30,000 $50,000 $265,000 $345,000
Lisbon Road Water Main Extension - East of Pilgrim along Willowood Preserve $235,000 $235,000
Madison Drive - Main St to Roosevelt - Water main Relay $302,000 $302,000
Main Street - Fond du lac Ave to Rozanne Dr - 8" to 12" Wm Relay $250,000 $250,000
Main Street - Parking Improvements - Phase III $360,000 $360,000
Manhattan Dr. - Men Ave to Franklin Drive - Water m ain Relay $1,040,000 $1,040,000
Menomonee Ave -Library Ln to Norman Dr - Water main Relay $450,000 $450,000
Norman Drive - Menomonee to Manhattan - Water main Relay $450,000 $450,000
Ridgeview Drive - Cherokee to Pilgrim Rd - Water m ain, Storm & Road Reconst $290,000 $400,000 $690,000
Rivers Edge Park Path Extension - Lilly Rd to Rivers Edge Park $140,000 $140,000
Roger Ave - Grand to Shady Ln - Water main Relay $500,000 $500,000
Roosevelt Dr. - St. Francis Dr to North Limit - Wa ter main Relay $270,000 $270,000
Sheridan Dr - Ann Ave to Men Ave - Water main, Sto rm & Road Reconst $255,000 $820,000 $1,075,000
Sheridan Dr - Hillcrest to Ann Ave & Village Park - Water main, Storm & Road Reconst $525,000 $525,000
Sidewalk Replacement Program $150,000 $150,000 $150,000 $150,000 $150,000 $750,000
St. Francis Dr. - Roosevelt Dr to W. St Regis - Wa ter main & Storm Sewer Relay $475,000 $475,000
St. Regis Dr. - St. Francis Dr to West Limit - Wat er main Relay $350,000 $350,000
St. Stevens Dr. & Ct. - St. Francis Dr to West - Wa ter main Relay $200,000 $200,000
St. Thomas Dr - Roosevelt to Shady Lane - Water mai n Relay $150,000 $150,000
Stonefield Dr - Wells #8 & #9 to Maple Crest Lane - Water main Relay $370,000 $370,000
Theodore Dr - Jacobson Dr to Ann Ave - Water main, Storm & Road Reconst $225,000 $280,000 $505,000
Townline Road Water Tower $1,450,000 $1,450,000
Various Park Improvement Projects $450,000 $450,000
Village Park - Specialty Park Reconstruction $2,200,000 $1,100,000 $1,310,000 $4,610,000
GRAND TOTAL PROJECT COSTS $9,565,000 $7,919,000 $5,825,000 $3,807,000 $3,865,000 $30,981,000
VILLAGE OF MENOMONEE FALLS
LEVY DEBT PROJECTION
Amount Rate 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034
Current levy debt (P&I) 2,401,198 2,114,772 1,861,659 2,594,184 2,357,415 2,049,965 894,940 666,595 442,850 233,450
2019 CIP Principal 2,000,000 2.3% 230,000 235,000 80,000 80,000 80,000 245,000 250,000 260,000 255,000 285,000
2019 CIP Interest 66,355 38,008 34,385 32,545 30,705 26,968 21,275 15,410 9,488 3,278
2020 CIP Principal 2,000,000 2.8% 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000
2020 CIP Interest 81,200 47,600 42,000 36,400 30,800 25,200 19,600 14,000 8,400 2,800
2021 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000
2021 CIP Interest 87,000 51,000 45,000 39,000 33,000 27,000 21,000 15,000 9,000 3,000
2022 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000
2022 CIP Interest 87,000 51,000 45,000 39,000 33,000 27,000 21,000 15,000 9,000 3,000
2023 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000
2023 CIP Interest 87,000 51,000 45,000 39,000 33,000 27,000 21,000 15,000 9,000 3,000
2024 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000
2024 CIP Interest 87,000 51,000 45,000 39,000 33,000 27,000 21,000 15,000 9,000 3,000
2025 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000
2025 CIP Interest 87,000 51,000 45,000 39,000 33,000 27,000 21,000 15,000 9,000
2026 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000
2026 CIP Interest 87,000 51,000 45,000 39,000 33,000 27,000 21,000 15,000
2027 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000 200,000 200,000 200,000
2027 CIP Interest 87,000 51,000 45,000 39,000 33,000 27,000 21,000
2028 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000 200,000 200,000
2028 CIP Interest 87,000 51,000 45,000 39,000 33,000 27,000
2029 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000 200,000
2029 CIP Interest 87,000 51,000 45,000 39,000 33,000
2030 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000 200,000
2030 CIP Interest 87,000 51,000 45,000 39,000
2031 CIP Principal 2,000,000 3.0% 200,000 200,000 200,000
2031 CIP Interest 87,000 51,000 45,000
2032 CIP Principal 2,000,000 3.0% 200,000 200,000
2032 CIP Interest 87,000 51,000
2033 CIP Principal 2,000,000 3.0% 200,000
2033 CIP Interest 87,000
2034 CIP Principal 2,000,000 3.0%
2034 CIP Interest
Interest earnings (20,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000) (15,000)
Municipal Facilities Cash (830,000) (830,000) (765,000) = $2,425,000 (Total Cash Needed)
Projected Tax Levy 2,381,198 2,396,127 2,400,867 2,398,169 2,404,960 2,400,070 2,404,708 2,403,070 2,404,860 2,399,938 2,399,678 2,314,800 2,315,000 2,315,000 2,315,000 2,315,000
2/15/2019 2:40 PM Page 1 of 1