1. Call to Order: 6:00 p.m., Village Hall Meeting Room, 122 E. Lincoln Ave., Fall Creek
2. Pledge to Flag
3. Roll Call: Members Present: Village President Chester Goodman, Trustees Joyce Aldrich, Bob
Jenkins, Matt Mattoon (via telephone), Karen Strasburg, Dane Zook. Members Absent: Trustee
Tim Raap. Staff Present: Public Works Director Bryan Kaatz, Clerk-Treasurer Renee Roemhild.
Also Present: Mark Davy, Jim Maloney, Luke Hansen.
4. Certify Open Meeting Law Requirements Have Been Met: A notice of the meeting and an
agenda was posted in the three public places and local newspapers were notified.
5. Adopt Agenda:
▪ MOTION (Strasburg/Jenkins) to adopt the agenda as printed. PASSED, without negative
vote.
6. Consider McKinley Avenue Project, Including Review of Contractor Bids (and Special
Assessment Policy): Village Engineer Mark Davy reported on the bid opening stating the bids
came in very good. In an effort to get good bids this late in the year, there were two options for
contractors to bid on: a base bid and an alternate bid. The base bid scheduled construction to be
completed this year, while the alternate bid scheduled most of the construction this year but left
the road as a gravel surface over the winter to allow some settlement, with the paving to happen
early next year. Discussion took place as to which schedule was preferred, with the consensus of
the Board being they would get a better road if they let the road settle over the winter.
▪ MOTION (Zook/Mattoon) under the advisement of the Engineer and Public Works Director
that the road should be allowed to settle over the winter, to tentatively award the project to
A-1 Excavating at a cost of $663,937. The schedule will be to have sewer, water, and
temporary gravel surface completed by November 22, 2019 and the remaining construction
be substantially completed by June 26, 2020. The award is contingent upon Rural
Development concurrence and contingent upon the special assessment public hearing set for
August 12th. PASSED, roll call vote: Goodman-yes, Jenkins-no, Mattoon-yes, Strasburg-
yes, Zook-yes, Aldrich-yes.
The Board discussed the current special assessment policy and the resulting assessments for the
McKinley Avenue project with the bid prices. It was discussed that even when considering an
inflation factor and with the ordinance change in April (lowering the property owner share for
street, curb, sidewalk from 66% to 50%), these assessments look proportionately so much
higher than past projects due to the high increase in construction prices. An example was given
showing an additional change in the Village/Property Owner cost-share ratio, as well as
continued, updated information as to the policies of neighboring communities. No action was
taken.
7. Luke Hanson from Eau Claire Area Economic Development Corporation: Eau Claire Area
Economic Development Executive Director Luke Hanson updated the Board on the happenings
of the EDC over the last year and on recruiting efforts trying to bring economic development to
the Village of Fall Creek. The biggest challenge has been the absence of public transit enabling
employees to get to their jobs. He will continue to keep the Board apprised of the EDC’s efforts.
8. Adjourn:
▪ MOTION (Jenkins/Zook) @ 7:27 p.m. PASSED, without negative vote.
Renee Roemhild, Clerk-Treasurer