Village of Fall Creek Special Board Meeting Minutes
8/8/2019 Page 1 of 2
1. Call to Order: 6:40 p.m., Village Hall Meeting Room, 122 E. Lincoln Ave., Fall Creek
2. Pledge to Flag
3. Roll Call: Members Present: Village President Chester Goodman, Trustees Joyce Aldrich, Bob
Jenkins, Matt Mattoon (via telephone), Karen Strasburg, Dane Zook. Members Absent: Trustee
Tim Raap. Staff Present: Police Chief Chad Dachel, Public Works Director Bryan Kaatz, Clerk-
Treasurer Renee Roemhild. Also Present: 1 citizen.
4. Certify Open Meeting Law Requirements Have Been Met: A notice of the meeting and an
agenda was posted in the three public places and local newspapers were notified.
5. Adopt Agenda:
▪ MOTION (Strasburg/Zook) to adopt the agenda as printed. PASSED, without negative vote.
6. Consider Special Assessment Policy (and McKinley Ave Project): President Chester Goodman
thanked the members for coming to yet another meeting. He requested further discussion before the
McKinley Avenue assessments were finalized. The concerns and factors that these proposed
assessments have brought to light warrant additional consideration. The realization that the wide
fluctuation of construction prices can disproportionately elevate the cost of improvements
compared to prior construction projects is of primary concern. Since household incomes may
not keep pace at the same level, this could result in “special assessing” property owners out of their
home. More broadly, the adverse effects on the entire community could result in blighted areas and
decreased appeal for new residents to make the Village of Fall Creek their home. The Village
Board takes seriously its responsibility to determine not only the appropriate way to spend money,
but also the proper way to collect money.
Wisconsin State Statutes allows a municipality to special assess private properties for local
improvements (ex.-street, curb/gutter, sidewalk, etc.) because there is a special benefit to involved
properties of a capital improvement project above the benefit to the entire community. Statutes
outline two methods in which a municipality may do this: taxing power or police power. “Taxing
power” means the assessment is based on the actual benefit accruing to the involved property.
“Police power” is done by figuring a unit cost for the improvement and multiplying it by either the
front footage or area (or a combination of both) of the property. In this way, the assessment is
calculated by “measuring” the special benefit to be received by the abutted property. The Village of
Fall Creek has traditionally used the “police power” method for all reconstruction projects.
Chapter 206 of the Code of the Village of Fall Creek specifies the “cost-sharing” ratio in which
this special benefit will be calculated. For many years, this ratio has been 34% Village/
66% Property Owner for cost-sharing street, sidewalk, curb and drive approach improvements.
Extensive work was done in the spring of this year analyzing the special assessment policy in
relation to other communities and in relation to the effect construction costs have had on that cost
sharing percentage. An amendment was made to the ordinance in spring 2019 changing the cost-
sharing ratio to 50% Village/50% Property Owner. Continued analysis, along with receiving the
bid prices for the McKinley Reconstruction project, gave a better view of the concerns originally
voiced in the spring.
The concern was highlighted by a comparison of past projects to the proposed project with respect
to the cost assessed in relation to the property values. This comparison was done for each of the
capital reconstruction projects within the last 15 years. What we found was that the 2006 Lincoln
Village of Fall Creek
Minutes of Special Village Board Meeting
August 8, 2019
Village of Fall Creek Special Board Meeting Minutes
8/8/2019 Page 2 of 2
Avenue, 2009 Liberty Street, and 2013 State Street capital projects showed an AVERAGE*
assessment of 5-7% of assessed property values. *Average being defined as residential single
family and duplex properties that are not on a corner lot and not vacant land. The same calculation
for the proposed McKinley Avenue project resulted in assessments averaging 11% of property
values. This indicated that increased construction costs had a greater impact on the McKinley
Project. Not only does a comparison like this take into consideration the disproportionate effect
construction costs can have, it can also be used to help equalize the differences in specific projects.
There are factors that impact individual projects in different ways. For example, the McKinley
Avenue project is going to have additional cost (above a standard project) in order to bring
uniformity to the street widths. The State Street project had lower costs due to the County paying a
share. Likewise, the Lincoln Avenue project had lower costs due to the State paying a share.
If the Board were to use the above calculated 5-7% of property values as a guideline in determining
the cost-share percentages for each project, that may be a method that would better withstand the
test of time and take into consideration fluctuating construction costs.
The current ordinance already states the Village Board “may, in its discretion, deviate from the
cost-sharing standards set forth in (the ordinance) and attribute a lesser or greater proration of the
identified cost of a public improvement project to benefitted properties”. Therefore, if the Board
were to decide tonight that they wanted to take into consideration the comparison described above
for determining the special benefit for the McKinley Avenue Project, it would be within their
discretion to do that.
▪ MOTION (Zook/Strasburg) to make a change to the Special Assessment Policy to consider the
fluctuation of construction costs in relation to inflation. The Village will continue to assess
construction projects using police power. PASSED, roll call vote: Goodman-yes, Mattoon-no,
Raap-yes, Strasburg-yes, Zook-yes, Aldrich-yes.
▪ MOTION (Zook/Aldrich) acting on that policy and after review of past projects, we find
construction costs have increased at a rate higher than inflation. Therefore, motion to set the
cost-share rate for the McKinley Avenue Project at 75% Village/25% Property Owner and to
retract the 4/8/19 motion (regarding a reduction in the property owner street share because of
varying street widths) because the new policy takes that into consideration. PASSED, roll call
vote: Mattoon-no, Raap-yes, Strasburg-yes, Zook-yes, Aldrich-yes, Goodman-yes.
▪ MOTION (Zook/Mattoon) directing the Clerk-Treasurer to prepare a first reading to amend
Chapter 206 to state the Village Board’s new policy to consider the fluctuation of construction
costs. PASSED, without negative vote.
7. Adjourn:
▪ MOTION (Raap/Strasburg) @ 8:23 p.m. PASSED, without negative vote.
Renee Roemhild, Clerk-Treasurer
Source: Village of Fall Creek website. First collected Oct 20, 2026.