City of Berlin
2026-2030 Capital Improvement Plan
1
City of
Berlin, Wisconsin
2026-2030 Capital Improvement Plan
ADOPTED OCTOBER 2025
Prepared by:
Robert W. Baird & Co.
Public Finance
777 E. Wisconsin Ave.
Milwaukee, WI 53202
800.792.2473
City of Berlin
2026-2030 Capital Improvement Plan
2
Table of Contents
Long Range Capital Improvement Planning Introduction/Manual .................................................. 3
Berlin CIP Process/Timeline ..................................................................................................................... 5
CIP Components (Tabs) ............................................................................................................................ 6
Capital Improvement Plan Policy Information ..................................................................................... 8
Capital Improvement Plan Summary Information ............................................................................. 12
Capital Improvement Program Department Summaries/Justifications ......................................... 18
Berlin Aquatic Center Potential Project Improvements/Complete Reconstruction ....................95
2026 Capital Improvement Plan Proposed Budget Funding ..........................................................96
Capital Improvement Plan Beyond 2030 .......................................................................................... 104
Important Disclosures ............................................................................................................................ 112
City of Berlin
2026-2030 Capital Improvement Plan
3
Long Range Capital Improvement Planning Introduction/Manual
CIP Introduction
This is an essential management tool for Berlin to utilize in planning for Capital
Improvements over multiple years.
o Allows room for forward thought and discussion.
o Better prepares Berlin for change.
o Creates opportunities that may otherwise be overlooked.
Berlin is faced with increasing Expenditures and limitations on Revenues.
o Creative solutions must be developed to meet these demands.
o Long-range planning is key to Berlin’s success.
o Funding sources and uses are matched over a multiple year timeframe
rather than just one year.
Integrates Capital Improvement Planning (CIP) into annual Budget process.
o CIP is initial step in annual budget process.
o Operational – Staffing, organizational structure, systems (70-80% of
annual budget)
o Capital – Infrastructure, maintenance, and equipment.
Benefits of a CIP
More efficient administration -Assists in making better decisions in how Berlin is
spending resources in coming years.
Administration/Departmental involvement in planning and prioritizing
projects/programs with available funding
Provides a disciplined and financially stable approach to spending over multiple
years.
Provides a way to plan financing of infrastructure projects and equipment
purchases.
o Detailed list of projects and funding sources
o Project descriptions with justifications/rational
Facilitates the planning and funding of a program.
Public document to obtain community support and keep citizens informed on
current needs and future projects.
Focuses attention on objectives and financial capabilities/affordability.
o Identifies most economical means of financing capital projects.
City of Berlin
2026-2030 Capital Improvement Plan
4
o CIP used by financial advisors to structure and time a capital financing
plan borrowing.
o CIP avoids drastic changes in debt service payments.
Positive evaluation factor by credit rating agencies and independent auditors
Capital Improvement Threshold Policy
Individual tangible capital-type items should be capitalized only if they have a
minimum value of $5,000 and have an estimated useful life of more than one
year following the date of acquisition.
The capitalization threshold is to be applied to individual items rather than to
groups of similar items (e.g., desks and tables)
Capital Improvement Planning Process
Establish timeline: Spring-Summer-Fall-Nov/Dec Budget Adoption
City Clerk/Treasurer and City Administrator coordinates and defines Department
responsibilities.
Letter/Memo to begin process of compiling or reviewing the CIP: Sample CIP
templates for use/update.
Organize all parties involved: Dept. Heads/Staff; Elected Officials (involve early);
and public citizens.
Policies: CIP Threshold; Complete Fixed Asset Inventory w/Useful lives/life
remaining; Disposal of Equipment
Develop fixed asset replacement schedule & a adequately funded
equipment/building replacement fund.
Identify the needs for facilities/programs/projects, the timing, costs (uses) and
means of financing (sources) for each.
o Use of CIP template forms for consistency and uniformity
Set priorities/rankings/justifications/budget impacts for each identified CIP
program and project.
Prepare financial proforma forecast analysis for a range of years showing Berlin’s
capacity to afford the CIP.
Execute the plan -Seek review and comment by the public.
Coincide w/Annual budget process: Incorporate first year’s CIP
programs/projects into proposed annual budget.
Review the capital improvement program annually.
City of Berlin
2026-2030 Capital Improvement Plan
5
Berlin CIP Process/Timeline
June: CIP Introduction
Organize all parties involved: Dept. Heads/Staff and Elected Officials
City Administrator, Clerk-Treasurer, and Baird will coordinate with participants and define
responsibilities to begin the process of compiling the CIP.
Give Depts. 2024-2028 CIP template forms for consistency and uniformity throughout
June/July: CIP Creation Process
Identify the needs for facilities/programs/projects, the timing, costs (uses) and means of
financing (sources) for each.
Set priorities/rankings/justifications/budget impacts for each identified CIP program and
project.
Use of CIP template forms for consistency and uniformity.
Review Established Policies: CIP Threshold; Complete Fixed Asset Inventory w/Useful lives/life
remaining; Disposal of Equipment.
Review fixed asset replacement schedule & adequately funded equipment/building
replacement fund.
July:
CIP Data due to City Clerk-Treasurer and City Administrator for compilation and then,
following review, given back to departments for review and discussion with their respective
standing committees: (City Council, Plan Commission. Park Committee)
August/September:
Distribution to Gov’t Leaders.
Review and comment on recommended projects and priorities through standing committee
meetings.
Board review and approval of CIP with adoption of first year’s projects as a capital budget
item in the proposed annual budget.
Full CIP used as a tool in the annual budget process and adoption.
October:
Budget adoption w/CIP.
Discussions/Planning with Financial Advisors &Bond Counsel for debt issuance to finance
projects.
Submit to Rating Agency to assist with Bond Rating Analysis.
City of Berlin
2026-2030 Capital Improvement Plan
6
CIP Components (Tabs)
Funding Sources Chart
This worksheet graphically shows the funding sources detailed on the bottom of the
chart for each CIP year. The chart is automatically generated by the data contained on
the summary of funds worksheet.
Uses by Category Chart
This worksheet graphically shows the uses by category detailed on the right side of the
chart for each CIP year. The chart is automatically generated by the data contained on
the summary of funds worksheet.
Summary of Funds
This worksheet summarizes the estimated beginning and ending fund balance,
individual funding sources, and individual uses by category for each CIP year. The
worksheet is automatically generated by combining data contained on each individual
category worksheet.
Category Worksheets
A worksheet is created for each individual CIP category. All cells with a black text need
user input and all cells with a blue text have a numeric formula which users cannot
change. The user will need to type in a name at the top of each category tab on line 4
for that category to show properly on the summary and chart tabs. The first year
estimated or actual beginning fund balance for the category needs to be entered. The
combined totals of sources and uses will be calculated from individual project/program
worksheets for each CIP year. The user needs to insert the required number of
program/project lines for each individual CIP category. Formulas from the program or
project description & justification tabs are then created for each individual
program/project name and the year-by-year totals. When the worksheet is printed on
a black and white printer it will display all cells in the same color.
Program or Project Description & Justification
A worksheet is completed for each CIP project or program. The program or project is
identified by category, name, and number. Department, contact, type, useful life,
priority, and purpose are also available for identification. A narrative description and
justification are required for the program or project. For each CIP year, the program or
project total expenditure (uses) and funding sources (detailed by type) are entered in
the black text cells. Blue text cells have a numeric formula which users cannot change.
A narrative budget impact and other relevant information are required at the bottom
of the worksheet.
City of Berlin
2026-2030 Capital Improvement Plan
7
Drop-down menus are available for selection of priority, purpose, and funding sources.
Upon completion of the worksheet, the program or project category name,
identification number, uses and funding sources will be transferred by manually creating
a formula to the individual category tab created by the user.
Proposed Budget Funding
This worksheet gives a detailed listing of the individual program or project for the
proposed budget year by category, identification number, priority ranking, and
purpose. The data entered in these columns will be from the program and project
worksheet. The individual line item is then identified by the requested, defunded, and
final budget dollar amount. The budgeted dollar amounts will tie back to the requested,
defunded, and budget columns found on the individual category worksheet uses by
category section.
Beyond 5-Year Period
This worksheet details individual program and project by category that are beyond the
5-Year CIP timeline. The year planned, ranking criteria, purpose, and estimated cost are
identified.
A drop-down menu is available for the ranking criteria and purpose.
City of Berlin
2026-2030 Capital Improvement Plan
8
Capital Improvement Plan Policy Information
Capital Asset Policy
Purpose: The purpose of this policy is to establish a consistent methodology for
recording in the financial records of the City of Berlin (“City”), the
capitalization and depreciation of capital assets, consistent with current
reporting requirements as determined by the State of Wisconsin and the
Governmental Accounting Standards Board (“GASB”).
General: The City of Berlin holds certain capital assets which include land, buildings,
vehicles, machinery and equipment, parks and roads infrastructure,
furniture, and fixtures, and all other tangible or intangible assets, which are
used in operations and that have initial useful lives extending beyond a
one-year period.
These assets must be accounted for at historical cost or estimated historical
cost and be fairly represented in the City of Berlin’s Annual Financial
Report.
Valuation: All costs shall be documented, including methods and sources used to
establish such cost basis.
1. Purchased assets: the recording of purchased assets shall be made
based on actual costs, including all ancillary costs, based on the vendor
invoice or other supporting documentation.
2. Self-constructed assets: all direct costs (including labor) associated with
the construction project shall be included in establishing a self-
constructed asset valuation. If the City is unable to identify all direct
costs, an estimate of the direct cost is acceptable but must be
supported by a reasonable methodology.
3. Donated assets: assets acquired by gift, donation, or payment of a
nominal sum not reflective of the asset’s fair market value shall be
assigned a cost equal to the fair market value at the time of acquisition.
4. Leased property: capital lease property shall be recorded as an asset
and depreciated as though it had been purchased.
5. Dedicated assets: requires installation by developers of public
improvements, including but not limited to sanitary sewer mains,
manholes, laterals, water mains, hydrants, valves, storm and sanitary
sewers, streets, curb and gutter, streetlights, street signs, sidewalks will
be dedicated to the City upon completion. Recording of infrastructure
assets will be made based on actual costs, including ancillary costs,
City of Berlin
2026-2030 Capital Improvement Plan
9
based on vendor invoice or other supporting documentation provided
by the developer.
6. Shared purchases: assets shared with other municipalities or entities
shall be made based on the City’s share of actual costs, including
ancillary costs, based on vendor invoice or other supporting
documentation.
Ancillary costs: Ancillary costs are to be included in the capitalized cost of a fixed asset.
However, minor costs, not measurable at the time a fixed asset is recorded
in the City’s fixed asset inventory system, may be expensed.
Ancillary costs include:
Buildings and Improvements: professional fees of architects, attorneys,
appraisers, financial advisors, etc.; damage claims; costs of fixtures
permanently attached to a building or structure; insurance premiums
and related costs incurred during construction; and other expenditures
necessary to place a building or structure into its intended state of
operation.
Equipment: transportation charges, installation costs, and any other
normal and necessary expenditures required to place the asset into its
intended state of operation.
Land: legal and title fees, surveying fees, appraisal and negotiation
fees, damage payments, site preparation costs, and costs related to
demolition of unwanted structures.
Classification: Capital assets include items with useful lives greater than one year, land, land
improvements, buildings, building improvements, construction work in progress, machinery
and equipment, vehicles, infrastructure, easements, and works of art and historic treasures. A
capital asset is to be reported and, with certain exceptions, depreciated in government-wide
statements. Assets that are not capitalized are expended in the year of acquisition.
Infrastructure assets are long-lived assets that normally can be preserved
for a significantly greater number of years than most capital assets and that
are normally stationary in nature. Examples include roads, bridges,
drainage systems, and water systems. Infrastructure assets do not include
buildings, drives, parking lots, or any other examples given above that are
incidental to property or access to the property.
Long-term assets can be classified into the following:
Furniture and equipment: office furniture; office, data processing, and
special department equipment
City of Berlin
2026-2030 Capital Improvement Plan
10
Vehicles and equipment: vehicles, operating and mechanical
equipment.
Land: land, land improvements.
Buildings: buildings, building improvements.
Infrastructure: streets, bridges, water and sewer systems, drainage
systems, sidewalks, curb, and gutter, etc.
Capitalization: Capital asset value thresholds for capitalization are to be applied to
individual capital assets rather than to groups of similar capital assets.
Capital assets must have an initial value of $10,000 or more. This will be
known as the “capitalization threshold” for reporting purposes in the
Annual Financial Report.
Repair and maintenance costs are expenditures that keep the property in
ordinary efficient operating condition. The cost of the repair does not add
to the value or prolong the life of the asset. All repair and maintenance
costs to capital assets are to be treated as an annual operating expense
and charged to the appropriate department and fund.
Improvements are expenditures for additions, alterations, and renovations
that appreciably prolong the life of the asset, materially increase its value,
or adapt it to a different use. Improvement costs of $10,000 or more to an
individual capital asset are to be capitalized.
Depreciation: All long-term assets (except for land, certain land improvements, and
construction in progress) identified in the capital assets policy will be
depreciated/amortized. Regardless of the month the asset is placed in
service, a full year of depreciation/amortization will be recorded in the first
year. Once the asset has been fully depreciated, the asset will be kept on
the books until disposed of. When the asset is disposed of prior to the end
of its useful life, the remaining “book” value will be written off as
depreciation unless it will materially affect the City’s financial statements.
Useful Life: To determine the useful life of an asset for depreciation purposes, the City
shall consider an asset’s present condition and how long it is expected to
meet its service demands in addition to applying applicable industry
standards for useful life.
City of Berlin
2026-2030 Capital Improvement Plan
11
Inventory: An inventory of all long-term assets should be reviewed and updated
annually.
Capital Assets Policy
Developed: August 2025
Adopted: September 2025
City of Berlin
2026-2030 Capital Improvement Plan
12
Capital Improvement Plan Summary Information
Components
Summary of Funds
This worksheet summarizes the estimated beginning and ending fund balance,
individual funding sources, and individual uses by category for each CIP year.
The worksheet is automatically generated by combining data contained on each
individual category worksheet.
Funding Sources Charts
These graphically show the funding sources detailed on the bottom of the charts
for each CIP year. The charts are automatically generated by the data contained
on the summary of funds worksheet.
Uses by Category Charts
These graphically show the uses by category detailed on the bottom of the
charts for each CIP year. The charts are automatically generated by the data
contained on the summary of funds worksheet.
City of Berlin
2026-2030 Capital Improvement Plan
13
City of Berlin
2026-2030 Capital Improvement Plan
14
$2,615,082
$1,258,500 $1,505,000
$607,500
$11,369,925
$3,213,657
$229,416
$318,000
$298,000 $298,000
$298,000
$308,000
0
2000000
4000000
6000000
8000000
10000000
12000000
14000000
1 2 3 4 5
Funding by Sources
TOTAL SOURCES CAPITAL PROJECTS TAX LEVY GENERAL FUND TAX LEVY BOND PROCEEDS
W/S BONDS PROCEEDS GRANTS GENERAL FUND RESERVE OTHER SOURCE
City of Berlin
2026-2030 Capital Improvement Plan
15
BOND PROCEEDS,
$17,356,007
W/S BONDS PROCEEDS,
$3,443,073
OTHER SOURCE,
$1,520,000
Funding by Sources
BOND PROCEEDS W/S BONDS PROCEEDS GRANTS GENERAL FUND RESERVE OTHER SOURCE
City of Berlin
2026-2030 Capital Improvement Plan
16
$- $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000
City Administration
Fire Department
Cemetery
EMS
Library
Public Works
Parks and Facilities
Police Department
Utilities
2026-2030 Department Yearly Costs
2030 2029 2028 2027 2026
City of Berlin
2026-2030 Capital Improvement Plan
17
City Administration, $40,000
Fire Department,
$851,000
Cemetery, $95,000
Library, $185,000
Public Works, $13,715,007
Parks and Facilities,
$1,730,000
Police Department,
$350,000
Utilities, $4,953,073
Uses by Category
City Administration Fire Department Cemetery EMS Library Public Works Parks and Facilities Police Department Utilities
City of Berlin
2026-2030 Capital Improvement Plan
18
Capital Improvement Program Department Summaries/Justifications
Department Summary Categories
A worksheet is created for each individual CIP Department with sources and uses categories. The first year estimated or
actual beginning fund balance for the category needs to be entered. The combined totals of sources and uses will be
calculated from individual project/program worksheets for each CIP year.
Program or Project Description & Justification
A worksheet is completed for each CIP project or program. The program or project is identified by category, name, and
number. Department, contact, type, useful life, priority, and purpose are identified. A narrative description and justification
are required for the program or project. A narrative budget impact and other relevant information are required at the
bottom of the worksheet.
City of Berlin
2026-2030 Capital Improvement Plan
19
City of Berlin
2026-2030 Capital Improvement Plan
20
City of Berlin
2026-2030 Capital Improvement Plan
21
City of Berlin
2026-2030 Capital Improvement Plan
22
City of Berlin
2026-2030 Capital Improvement Plan
23
City of Berlin
2026-2030 Capital Improvement Plan
24
City of Berlin
2026-2030 Capital Improvement Plan
25
City of Berlin
2026-2030 Capital Improvement Plan
26
City of Berlin
2026-2030 Capital Improvement Plan
27
City of Berlin
2026-2030 Capital Improvement Plan
28
City of Berlin
2026-2030 Capital Improvement Plan
29
City of Berlin
2026-2030 Capital Improvement Plan
30
City of Berlin
2026-2030 Capital Improvement Plan
31
City of Berlin
2026-2030 Capital Improvement Plan
32
City of Berlin
2026-2030 Capital Improvement Plan
33
City of Berlin
2026-2030 Capital Improvement Plan
34
City of Berlin
2026-2030 Capital Improvement Plan
35
City of Berlin
2026-2030 Capital Improvement Plan
36
City of Berlin
2026-2030 Capital Improvement Plan
37
City of Berlin
2026-2030 Capital Improvement Plan
38
City of Berlin
2026-2030 Capital Improvement Plan
39
City of Berlin
2026-2030 Capital Improvement Plan
40
City of Berlin
2026-2030 Capital Improvement Plan
41
City of Berlin
2026-2030 Capital Improvement Plan
42
City of Berlin
2026-2030 Capital Improvement Plan
43
City of Berlin
2026-2030 Capital Improvement Plan
44
City of Berlin
2026-2030 Capital Improvement Plan
45
City of Berlin
2026-2030 Capital Improvement Plan
46
City of Berlin
2026-2030 Capital Improvement Plan
47
City of Berlin
2026-2030 Capital Improvement Plan
48
City of Berlin
2026-2030 Capital Improvement Plan
49
City of Berlin
2026-2030 Capital Improvement Plan
50
City of Berlin
2026-2030 Capital Improvement Plan
51
City of Berlin
2026-2030 Capital Improvement Plan
52
City of Berlin
2026-2030 Capital Improvement Plan
53
City of Berlin
2026-2030 Capital Improvement Plan
54
City of Berlin
2026-2030 Capital Improvement Plan
55
City of Berlin
2026-2030 Capital Improvement Plan
56
City of Berlin
2026-2030 Capital Improvement Plan
57
City of Berlin
2026-2030 Capital Improvement Plan
58
City of Berlin
2026-2030 Capital Improvement Plan
59
City of Berlin
2026-2030 Capital Improvement Plan
60
City of Berlin
2026-2030 Capital Improvement Plan
61
City of Berlin
2026-2030 Capital Improvement Plan
62
City of Berlin
2026-2030 Capital Improvement Plan
63
City of Berlin
2026-2030 Capital Improvement Plan
64
City of Berlin
2026-2030 Capital Improvement Plan
65
City of Berlin
2026-2030 Capital Improvement Plan
66
City of Berlin
2026-2030 Capital Improvement Plan
67
City of Berlin
2026-2030 Capital Improvement Plan
68
City of Berlin
2026-2030 Capital Improvement Plan
69
City of Berlin
2026-2030 Capital Improvement Plan
70
City of Berlin
2026-2030 Capital Improvement Plan
71
City of Berlin
2026-2030 Capital Improvement Plan
72
City of Berlin
2026-2030 Capital Improvement Plan
73
City of Berlin
2026-2030 Capital Improvement Plan
74
City of Berlin
2026-2030 Capital Improvement Plan
75
City of Berlin
2026-2030 Capital Improvement Plan
76
City of Berlin
2026-2030 Capital Improvement Plan
77
City of Berlin
2026-2030 Capital Improvement Plan
78
City of Berlin
2026-2030 Capital Improvement Plan
79
City of Berlin
2026-2030 Capital Improvement Plan
80
City of Berlin
2026-2030 Capital Improvement Plan
81
City of Berlin
2026-2030 Capital Improvement Plan
82
City of Berlin
2026-2030 Capital Improvement Plan
83
City of Berlin
2026-2030 Capital Improvement Plan
84
City of Berlin
2026-2030 Capital Improvement Plan
85
City of Berlin
2026-2030 Capital Improvement Plan
86
City of Berlin
2026-2030 Capital Improvement Plan
87
City of Berlin
2026-2030 Capital Improvement Plan
88
City of Berlin
2026-2030 Capital Improvement Plan
89
City of Berlin
2026-2030 Capital Improvement Plan
90
City of Berlin
2026-2030 Capital Improvement Plan
91
City of Berlin
2026-2030 Capital Improvement Plan
92
City of Berlin
2026-2030 Capital Improvement Plan
93
City of Berlin
2026-2030 Capital Improvement Plan
94
City of Berlin
2026-2030 Capital Improvement Plan
95
Berlin Aquatic Center Potential Project Improvements/Complete Reconstruction
On July 28, 2025, City Administrator Jessi Balcom provided the common council with a staff report detailing information regarding the options for the future of the Berlin Aquatic Center. In 2024 the city
was provided with an estimate of structural/maintenance deficiencies needed to be undertaken by Ramaker for a cost estimate of around $2,000,000. The common council in subsequent meetings
reviewed scenarios ranging from the city borrowing completely to undertake the repairs, fully funded via donations/community funding, combination of borrowing and donations, as well as consideration
of demolishing the existing pool and reconstruction of a new upgraded facility. The above project sheet is intended to be a resource for the council and the community to continue to discuss the
possible funding of structural/maintenance deficiencies and or complete reconstruction of the Berlin Aquatic Cener to determine the potential inclusions with the five-year capital improvement plan or
long-term planning for the future.
City of Berlin
2026-2030 Capital Improvement Plan
96
2026 Capital Improvement Plan Proposed Budget Funding
A detailed department by department listing of the individual program or project for the
proposed budget year by category, identification number, priority ranking, and purpose. The
data entered in these worksheets will be from the program and project worksheet. The
individual line item is then identified by the requested, defunded, and final budget dollar
amount. The budgeted dollar amounts will tie back to the amounts found on the individual
category worksheet uses by category section.
City of Berlin
2026-2030 Capital Improvement Plan
97
City of Berlin
2026-2030 Capital Improvement Plan
98
City of Berlin
2026-2030 Capital Improvement Plan
99
City of Berlin
2026-2030 Capital Improvement Plan
100
City of Berlin
2026-2030 Capital Improvement Plan
101
City of Berlin
2026-2030 Capital Improvement Plan
102
City of Berlin
2026-2030 Capital Improvement Plan
103
City of Berlin
2026-2030 Capital Improvement Plan
104
Capital Improvement Plan Beyond 2030
This section details department by department individual program and projects by category
that are beyond the 5-Year CIP timeline. The year planned, ranking criteria, purpose, and
estimated cost are identified.
City of Berlin
2026-2030 Capital Improvement Plan
105
City of Berlin
2026-2030 Capital Improvement Plan
106
City of Berlin
2026-2030 Capital Improvement Plan
107
City of Berlin
2026-2030 Capital Improvement Plan
108
City of Berlin
2026-2030 Capital Improvement Plan
109
City of Berlin
2026-2030 Capital Improvement Plan
110
City of Berlin
2026-2030 Capital Improvement Plan
111
City of Berlin
2026-2030 Capital Improvement Plan
112
Important Disclosures
Robert W. Baird & Co. Incorporated is providing this information to you for discussion
purposes. The materials do not contemplate or relate to a future issuance of municipal
securities. Baird is not recommending that you take any action, and this information is not
intended to be regarded as “advice”’ within the meaning of Section 15B of the Securities
Exchange Act of 1934 or the rules thereunder.