RecordWell Data

DC Water - PIney Branch Tunnel - ANC 4E Meeting Sept 29, 2026.pdf

Advisory Neighborhood Commissions · District of Columbia County · meeting of Sep 29, 2026 · Notices

Open the original document More from Advisory Neighborhood Commissions

This document is no longer listed on Advisory Neighborhood Commissions's website. We kept the copy we read.

Text

Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.

1 Clean Rivers Project – Piney Branch Tunnel ANC 4E - Monthly Meeting September 29, 2026 0 Moussa Wone, Chief Engineer and Vice President 1 Clean Rivers Project The project is required by a Consent Decree signed by the Environmental Protection Agency, Department of Justice, District of Columbia, & DC Water ▪ 1/3 of District is served by combined sewers (12,478 acres) ▪ Combined Sewer Overflow (CSO) outfalls • 15 to Anacostia River • 10 to Potomac River • 23 to Rock Creek ▪ 25 yr implementation (2005 – 2030) ▪ 96% reduction in CSOs ▪ Approx. 1 million lbs./yr nitrogen reduction Click to edit Master title style Tunnel Fact s • Approximately0.5miles of 22-foot finished diameter reinforced concrete tunnel • Tunnel will be excavated by drill and shoot and mechanized means • Intercept and store overflow during rain event • Discharge to sewer system by gravity after storm passes • Construction 2025 to 2029 • Two ShaftLocations 1. Piney Branch Stream (CS0 049) 2. Park Road 4 Piney Branch Tunnel Site Project Overview Piney Branch Tunnel Site & Project Overview PINEY BRANCH TUNNEL PINEY BRANCH STREAM (CSO 049) Site PARK ROAD SITE How Does It Flow? How The System Works • DC Water’ sCleanRiversProjecthasbuilta series of tunnelsanddiversionfacilities that move sewageand stormwaterto the tunnel duringa stormevent. Diversion Facility Components • Diversionchamber:constructedalongthe existingsewerto divertflowfrom the combinedsystemwhencapacityis exceeded. • Diversionsewer/approachchannel: constructedto conveyflowsawayfromthe existingsewer . • Dropshaft:constructedto conveyflowsfrom the diversionsewerto tunnel depth. • Adit:connectsthe dropshaftto the tunnel. 4 Piney Branch Stream (CSO 049) Construction Site Excavating the Shaft to Begin the Tunnel ▪Controlled underground blasting is necessary to dig a deep shaft for the start of the tunnel system at the Piney Branch Stream (CSO 049). ▪Following completion of the shaft construction will begin on the tunnel which will also require controlled underground blasting. Public Safety & Outreach Notification and Protection ▪ There is no danger to residents, businesses, or visitors. ▪ The blast operations will occur in a controlled manner under strict safety protocols. ▪ Our team works closely with DC FEMS, MPD, and NPS to ensure every operation is safe and well-coordinated. ▪ A Public Notice will be distributed a day in advance of the anticipated date of the controlled blast. ▪ Blast mats and shaft covers will be utilized to reduce noise, dust and possible debris. ▪ Noise and ground vibrations are monitored to ensure safety and compliance. Controlled Underground Blasting What to Expect ▪ Before each blast, there will be an air horn signal 5 minutes before the blast. ▪ Flaggers will enforce temporary closures to stop traffic on the parkway and 17th Street and pedestrians on the nearby trail. ▪ During the blast, there will be a series of discharges lasting approximately 5 seconds. ▪ Residents and businesses in the vicinity may hear moderate noise and feel mild ground vibrations. ▪ After the blast, another air horn will signal the “All Clear” to allow the trail to reopen and traffic to resume. Shaft Blasting Frequency and Duration: ▪ Blasting of the shaft to start Fall 2026 • 1 to 2 blasts per week • 4 to 6 total blasts • Approximately 2 months for shaft blasting ▪ No blasting on Sundays ▪ While we aim to keep the schedule as consistent as possible, blast dates may shift as field conditions or coordination needs arise Project Hauling • Monday – Friday 9:30 am – 3:30 pm. • Monday – Friday 7 pm – 5 am. Ha uling Hours • Monday – Friday 7 am – 7 pm. • Hauling Saturday as needed. Monitoring Noise & Vibration ▪ A monitoring program will measure and document movements. ▪ Instrumentation data is routinely reviewed by engineers from the Contractor and DC Water. ▪ A Right of Entry between DC Water and the Owner is required for survey targets to be installed and monitored on private property. ▪ Survey targets will only be placed on the exterior of structures. ▪ Survey targets will be measured daily when excavation occurs nearby. ▪ Noise and Vibration Specialist​ ▪ Conducts daily monitoring​ ▪ Implements mitigation measures​ ▪ Contractor held to DCMR limit of 80 dBA during weekday days​ ▪ Nighttime limit 55 dBA​ ▪ Weekend limit 60 dBA Impacts Mitigation Adjacent Properties ▪ Conduct preconstruction surveys of the project area before mobilization ▪ Provide advanced notifications to affected residents and businesses to facilitate adequate preparation for anticipated impacts. Traffic ▪ Ensure that crews are setting up the traffic control as approved by DDOT/NPS ▪ Coordinate with DDOT/NPS on distribution of traffic advisories, including lane closures and detours. ▪ Provide signage and barriers to safely direct motorists around work zones ▪ Trucks will follow dedicated DDOT/NPS approved haul routes and hours Construction Site Mitigations Sidewalk/ Trail Closure ▪ Provide safe paths/trails for pedestrians and bicyclists segregated from construction site. ▪ Proactively notify the community of trail and sidewalk closures and duration Noise & Vibration ▪ Noise and vibration monitored to meet DC Municipal & Regulations (DCMR) regulations. ▪ Implement noise and vibration mitigation measures as needed. Site Maintenance ▪ Implement site security measures. ▪ Placement of dust and rodent control measures ▪ Construction lighting shielded and directed away from residents http://www.errin.eu/sites/default/files/userfiles/user-10/water-drop.png Contact Information 11 Project Email: dcpineybranch@dcwater.com Project Website: www.dcwater.com/pbt Hotline: (240) 200-4623 Contact Information

Source: Advisory Neighborhood Commissions website. First collected Oct 6, 2026.