Clean Rivers Project – Piney Branch Tunnel
ANC 4E - Monthly Meeting
September 29, 2026
0
Moussa Wone, Chief Engineer and Vice President
1
Clean Rivers Project
The project is required by a
Consent Decree signed by the
Environmental Protection
Agency, Department of Justice,
District of Columbia, & DC Water
▪ 1/3 of District is served by combined
sewers (12,478 acres)
▪ Combined Sewer Overflow (CSO) outfalls
• 15 to Anacostia River
• 10 to Potomac River
• 23 to Rock Creek
▪ 25 yr implementation (2005 – 2030)
▪ 96% reduction in CSOs
▪ Approx. 1 million lbs./yr nitrogen
reduction
Click to edit Master title style
Tunnel Fact s
• Approximately0.5miles of 22-foot
finished diameter reinforced
concrete tunnel
• Tunnel will be excavated by drill
and shoot and mechanized means
• Intercept and store overflow
during rain event
• Discharge to sewer system by gravity
after storm passes
• Construction 2025 to 2029
• Two ShaftLocations
1. Piney Branch Stream (CS0 049)
2. Park Road
4
Piney Branch Tunnel Site Project Overview
Piney Branch Tunnel Site & Project Overview
PINEY BRANCH TUNNEL
PINEY BRANCH STREAM
(CSO 049) Site
PARK ROAD SITE
How Does It Flow?
How The System Works
• DC Water’ sCleanRiversProjecthasbuilta series
of tunnelsanddiversionfacilities that move
sewageand stormwaterto the tunnel duringa
stormevent.
Diversion Facility Components
• Diversionchamber:constructedalongthe
existingsewerto divertflowfrom the
combinedsystemwhencapacityis exceeded.
• Diversionsewer/approachchannel:
constructedto conveyflowsawayfromthe
existingsewer .
• Dropshaft:constructedto conveyflowsfrom the
diversionsewerto tunnel depth.
• Adit:connectsthe dropshaftto the tunnel.
4
Piney Branch Stream (CSO 049) Construction Site
Excavating the Shaft to Begin the Tunnel
▪Controlled underground blasting is necessary to dig a deep shaft for the start of the tunnel
system at the Piney Branch Stream (CSO 049).
▪Following completion of the shaft construction will begin on the tunnel which will also require
controlled underground blasting.
Public Safety & Outreach
Notification and Protection
▪ There is no danger to residents, businesses, or
visitors.
▪ The blast operations will occur in a controlled
manner under strict safety protocols.
▪ Our team works closely with DC FEMS, MPD,
and NPS to ensure every operation is safe and
well-coordinated.
▪ A Public Notice will be distributed a day in
advance of the anticipated date of the
controlled blast.
▪ Blast mats and shaft covers will be utilized to
reduce noise, dust and possible debris.
▪ Noise and ground vibrations are monitored to
ensure safety and compliance.
Controlled Underground Blasting
What to Expect
▪ Before each blast, there will be an air horn
signal 5 minutes before the blast.
▪ Flaggers will enforce temporary closures to
stop traffic on the parkway and 17th Street
and pedestrians on the nearby trail.
▪ During the blast, there will be a series of
discharges lasting approximately 5 seconds.
▪ Residents and businesses in the vicinity may
hear moderate noise and feel mild ground
vibrations.
▪ After the blast, another air horn will signal
the “All Clear” to allow the trail to reopen
and traffic to resume.
Shaft Blasting Frequency and
Duration:
▪ Blasting of the shaft to start Fall 2026
• 1 to 2 blasts per week
• 4 to 6 total blasts
• Approximately 2 months for shaft
blasting
▪ No blasting on Sundays
▪ While we aim to keep the schedule as
consistent as possible, blast dates may
shift as field conditions or coordination
needs arise
Project Hauling
• Monday – Friday 9:30 am – 3:30 pm.
• Monday – Friday 7 pm – 5 am.
Ha uling Hours
• Monday – Friday 7 am – 7 pm.
• Hauling Saturday as needed.
Monitoring Noise & Vibration
▪ A monitoring program will measure and
document movements.
▪ Instrumentation data is routinely reviewed
by engineers from the Contractor and DC
Water.
▪ A Right of Entry between DC Water and
the Owner is required for survey targets to
be installed and monitored on private
property.
▪ Survey targets will only be placed on
the exterior of structures.
▪ Survey targets will be measured daily
when excavation occurs nearby.
▪ Noise and Vibration Specialist
▪ Conducts daily monitoring
▪ Implements mitigation
measures
▪ Contractor held to DCMR limit of
80 dBA during weekday days
▪ Nighttime limit 55 dBA
▪ Weekend limit 60 dBA
Impacts Mitigation
Adjacent
Properties
▪ Conduct preconstruction surveys of the project area before mobilization
▪ Provide advanced notifications to affected residents and businesses to facilitate
adequate preparation for anticipated impacts.
Traffic
▪ Ensure that crews are setting up the traffic control as approved by DDOT/NPS
▪ Coordinate with DDOT/NPS on distribution of traffic advisories, including lane closures
and detours.
▪ Provide signage and barriers to safely direct motorists around work zones
▪ Trucks will follow dedicated DDOT/NPS approved haul routes and hours
Construction Site Mitigations
Sidewalk/
Trail Closure
▪ Provide safe paths/trails for pedestrians and bicyclists segregated from construction
site.
▪ Proactively notify the community of trail and sidewalk closures and duration
Noise &
Vibration
▪ Noise and vibration monitored to meet DC Municipal & Regulations (DCMR) regulations.
▪ Implement noise and vibration mitigation measures as needed.
Site
Maintenance
▪ Implement site security measures.
▪ Placement of dust and rodent control measures
▪ Construction lighting shielded and directed away from residents
http://www.errin.eu/sites/default/files/userfiles/user-10/water-drop.png
Contact Information
11
Project Email: dcpineybranch@dcwater.com
Project Website: www.dcwater.com/pbt
Hotline: (240) 200-4623
Contact Information