hp-26-08-20-calhoun-pl-city.pdf
City of Sumter · Sumter County · Other
Open the original document More from City of Sumter
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
City of Sumter Design Review Board
May 28, 2026
HP-26-08: 20 Calhoun Pl. (City)
I. THE REQUEST
Applicant: Carolina Conditions (Jordan Morphis)
Status of the Applicant: Authorized Agent for Property Owner
Request: Request for Design Review Approval to install a whole -
house backup generator and associated electrical and gas
line connections.
District: Hampton Park Historic District
Location: 20 Calhoun Pl.
Present Use/Zoning: Single Family Residential / Planned Development-PD
Tax Map Reference: 228-81-01-002
Adjacent Property Land
Use and Zoning:
North – Single-Family Residence / PD
South – Single-Family Residence / PD
East – Single-Family Residence / R-6
West – Vacant / PD
II. BACKGROUND
The applicant is requesting Design
Review approval to install a whole-house
backup generator and associated
electrical and gas line connections.
20 Calhoun Pl. shown in the photo to the
right, was purchased by the applicant in
2024. The property currently contains a
+/- 1,917 sq. ft. single-family dwelling on
a +/- 0.10-acre lot.
2
ARCHITECTURAL/HISTORIC CONTEXT:
Under a plan approved in 1991, the property formerly known as 315 W. Calhoun St.
was to be developed for 8 single-family detached units, each on its own parcel.
Since approval of the 1991 development plan, updated guidelines were adopted that
emphasize design standards more compatible with the existing character of Hampton
Park. The residences constructed at 10, 20, and 80 Calhoun Pl. were based on alternate
designs that were more compatible in architectural character and context to the
Hampton Park District.
The residence constructed at 20 Calhoun Pl. in 2022 is not a contributing structure to
the National Register Historic District -eligible Hampton Park Historic District or to
the City-designated Hampton Park Historic Overlay District.
Design review approvals were previously granted for the site via HP-22-20, HP-22-20
(Rev1), HP-24-01, and HP-25-17.
Above: Image from the entrance Above: Image from across the street
Above: Image from the end of the road
PROPOSED SCOPE OF WORK:
3
The proposed project includes:
1. Install whole-house backup generator and associated electrical and gas line
connections.
DESIGN REVIEW:
Design review approval is required prior to the proposed work. The Design Review
Guidelines states:
5.8 Mechanical and Utilities Screening
A. Place site appurtenances in discreet locations to diminish visual impact.
B. Minimize the visibility of Mechanical Equipment.
Place HVAC condensers at the rear of the building or on secondary elevations that are
not visible from the public right of way.
Screen visible mechanical equipment located at grade with wood or brick fencing, lattice
panels, or landscaping.
Do not place mechanical equipment on roofs of residential buildings.
Install window air conditioning units on the rear elevation or side elevations that are
not visible from the public right-of-way
Staff Analysis:
The applicant is proposing to install a whole-house backup generator and associated
electrical and gas line connections. The generator was installed prior to design
review approval, but it is situated to where it is screened by the home and not
readily visible from the street or the internal drive.
This proposed generator and the location of the generator is constant with the
Design Review Guidelines.
III. STAFF RECOMMENDATION
If the Design Review Board makes the findings necessary to approve this request, Staff
recommends no additional conditions.
4
IV. DRAFT MOTION
1) I move the City of Sumter Design Review Board approve HP-26-08 in
accordance with the materials and construction details submitted.
2) I move the City of Sumter Design Review Board deny HP-26-08.
3) I move the City of Sumter Design Review Board enter an alternative motion.
V. DESIGN REVIEW BOARD – May 28, 2026
Source: City of Sumter website. First collected Oct 24, 2026.