WATER AND SEWER COMMITTEE AGENDA
Thursday, May 25, 2017, 8:30 AM
Sullivan’s Island Town Hall
1. Call to Order & Freedom of Information Requirements
The Freedom of Information Requirements having been met, the meeting was called to
order at 8:30 AM. Those present were Committee Members Mark Howard, Bachman
Smith and Susan Middaugh (Chair), Staff Members Greg Gress and Andy Benke.
2. Approval of Minutes of the April 26, 2017 W&S Committee Meeting: Postponed
3. Budget for FY2018: Amendment for Second Reading
The personnel budget for W&S that was approved by First Reading on May 16, 2017,
used a 2.5% average increase instead of the 4.5% average increase in the General budget.
Accordingly, the W&S FY18 Budget is to be amended for second reading.
MOTION: To amend the W&S Budget to increase the salary total by $3392 for each
side, for the Water Budget and for the Sewer Budget.
4. Communications / Additional Items from WWTF Manager, Greg Gress
A long-standing policy of requiring a homeowner to disconnect water and sewer lines during
demolition and construction of a second home on the lot has been questioned on legal
grounds. The intent of this policy has been to protect the Town’s sewer collection system
from excessive I&I. This has raised questions about when, in the construction process, sewer
hookups should occur and a home can be occupied – or reoccupied- in the course of initial
construction, a major addition, an attached addition, or a second home on a lot. This issue
may need to be addressed in the Private Sewer Lateral Policy (pending Item i. below)
5. Review of Active and Pending Projects:
The current status of active and pending projects (a. through k. below) was reviewed. The
items with an asterisk are potential sources of additional revenue.
a. Wastewater Treatment Plant Retrofit: Options & Funding
b. I&I Phase I Follow-up and Capital Improvement Plan
c. I&I Phase II: Funding
d. Poe Avenue sewer line replacement
e. Rate Study & Cost Recovery Program*
f. CWS contract revisions*
g. Station 17 Water Utility Site & CWS Pumping Station*
h. Current Sewer Revenue Bond, ending in FY19*
i. Private Sewer Lateral Policy
j. W&S billing software replacement - August
k. Pre-Disaster Mitigation Grant for submersible pumps
l. ASR: Aquifer Storage and Recovery
6. The next W&S Committee meeting is scheduled for: June 22, 2017, 8:30 AM,
Sullivan’s Island Town Hall.
7. Adjournment: The meeting adjourned at 9:46 AM on a motion by Bachman Smith,
second by Mark Howard, and unanimous vote 3/0.