Quarterly Capital Projects Workshop — Agenda Packet
City of Beaufort · Beaufort County · General · meeting of Feb 17, 2026 · Agenda packets
Open the original document More from City of Beaufort
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
1
Join from PC, Mac, iPad, or Android:
https://us02web.zoom.us/j/87275938556?pwd=28bY4Zhrj5SBHihGXn3Qb43GFmPei3.1
Passcode:409104 +16469313860 Webinar ID: 872 7593 8556
City of Beaufort
1911 Boundary Street
Beaufort Municipal Complex
Beaufort, South Carolina 29902
(843) 525-7070
City Council Worksession Meeting Agenda
February 17, 2026
Statement of Media Notification
"In accordance with South Carolina Code of Laws, 1976, Section 30-4-80(d), as amended, all
local media was duly notified of the time, date, place and agenda of this meeting."
Worksession Meeting - Planning Conference Room - 5:00 PM
Please note, this meeting will be broadcast via zoom and live-streamed on YouTube. You
can view the meeting at the City's page; City Beaufort SC
I. Call to Order - Philip Cromer, Mayor
II. Discussion
A. Quarterly Capital Improvements Program (CIP) Update
III. Adjourn
Page 1 of 6
City of Beaufort
Department Request for City Council Agenda Item
To: City Council Date: 02/12/2026
From: Brian Ranger, Capital Projects Director
Item Name: Quarterly Capital Improvements Program (CIP) Update
Meeting Date: February 17, 2026
Department: City Managers Office
Background Information:
Introduction:
Air Table will be used to provide an update on Capital Projects.
Background:
Legal Authority:
Staff Recommendation:
Placed on Agenda For:
Attachments:
1. Feb 2026 CIP Quarterly Update
Page 2 of 6
Scott Marshall
CITY MANAGER
843-525-7070
COUNCIL MEMBERS:
Philip E. Cromer, Mayor
Mike McFee, Mayor Pro Tem
Neil Lipsitz
Mitch Mitchell
Josh Scallate
CITY OF BEAUFORT
1911 Boundary Street
BEAUFORT, SOUTH CAROLINA 29902
February 13, 2026
MEMORANDUM
To: City Council
From: Brian Ranger, CIP Director
Re: Capital Improvement Program Quarterly Report- Q-1 CY 2026
I. Summary Report
The Capital Improvement Projects (CIP) Team continues to be actively engaged in
essential coordination meetings with area partners and project contractors for all
active City projects. The CIP Portal on the City’s website has been successfully
updated with the assistance of the newly hired CIP Coordinator, David Gregory. The
City of Beaufort has three active grant awards that impact the City’s Infrastructure
.These projects are included in the active Capital Projects List.
II. Project Updates
King St – Construction activities on King Street have resulted in minor
impacts to local residents. Detour routes and maps have been posted on
the City’s website, and off-site parking arrangements have been
coordinated for residents affected when work reaches individual homes
and driveways. First responders are being continuously updated
regarding road closures.
Work began at the intersection of King Street and Hamilton Street and is
progressing toward Carteret Street. The initial phase involved relocating
underground utilities that conflicted with the installation of new storm
drainage infrastructure, including both gas and water lines. The primary
challenge to date has been managing groundwater conditions. BJW&SA
and Dominion Energy have been onsite working collaboratively with the
contractor.
BJW&SA has requested additional waterline replacement from King &
Hamilton Street , toward Pinckney Street.
Page 3 of 6
Scott Marshall
CITY MANAGER
843-525-7070
COUNCIL MEMBERS:
Philip E. Cromer, Mayor
Mike McFee, Mayor Pro Tem
Neil Lipsitz
Mitch Mitchell
Josh Scallate
CITY OF BEAUFORT
1911 Boundary Street
BEAUFORT, SOUTH CAROLINA 29902
As of February 13, 2026 J.H. Hiers Construction has installed 337 LF of
water line ,125 LF of Sewer Pipe and 184 LF Strom Drain Pipe .
City CIP staff are conducting daily site visits.
Expected Completion Date: June 19, 2026
Charles/Craven – This project has experienced several unforeseen delays,
including significant groundwater intrusion and the discovery of an
existing brick storm drain located within the alignment of the newly
installed storm drainage system. As of February 13, 2026, Gulf Stream
Constructors has installed twenty-three sections of 8-foot by 72-inch
reinforced concrete pipe (RCP) and three major manhole structures.
Due to extremely cold temperatures, the reopening of the Charles Street
and Bay Street intersection has been rescheduled for Monday , February
16, 2026.
Wedges will be used to transition from road surface, 2-inch drops for
horses and vehicular traffic until final surface is installed.
Gulf Stream Constructors anticipates improved productivity once work
progresses beyond Port Republic Street, as this represents the most
technically challenging portion of the project.
The next BJWSA water shutdown is anticipated for mid-February,
pending confirmation of affected merchants and residents. Brockington
Archaeological Services has been onsite over the past several weeks to
monitor construction activities in archaeologically sensitive areas.
The Charles Street Drainage Project webpage—approved by SCOR, the
City of Beaufort, and McCormick Taylor—is available at:
scor.sc.gov/Beaufort.
City staff continue to provide regular updates to local merchants and
affected residents and are coordinating detours, alternative parking
arrangements, and trash collection services as needed.
Expected Completion Date: December 31, 2026
Page 4 of 6
Scott Marshall
CITY MANAGER
843-525-7070
COUNCIL MEMBERS:
Philip E. Cromer, Mayor
Mike McFee, Mayor Pro Tem
Neil Lipsitz
Mitch Mitchell
Josh Scallate
CITY OF BEAUFORT
1911 Boundary Street
BEAUFORT, SOUTH CAROLINA 29902
Waterfront Park – McSweeney Engineering is continuing work on the
next phase of this project and anticipates presenting conceptual design
materials for the future promenade to the Waterfront Advisory
Committee by the end of the third quarter. These concepts will reflect
prior discussions between the Committee and the engineering team.
Day Dock – McSweeney Engineering is currently designing and
permitting modifications to the Day Dock. The permit application has
been submitted, and the preliminary design phase is complete. FME
Consultants are conducting a pile analysis using data from Phase I to
support the final design. Upon receipt of this analysis, construction
documents will be finalized.
Washington St. Park – Phase I is 100 percent complete. All site
furnishings and playground equipment have been ordered. Concrete
work began in January and is scheduled for completion by the end of
February. Landscaping is anticipated to begin during the first week of
March.
Next weekly onsite meetings are scheduled for February 24, 2026.
Projected Completion Date: April 25, 2026
Southside Park Phase 2 – The project has been divided into five
construction phases. The City is currently awaiting an updated cost
estimate from Davis & Floyd. The Phase II layout is under staff review,
and a proposed plan will be presented to staff and City Council. The
engineering and architectural team has effectively allocated appropriate
spacing for elements outlined in the master plan. Upon approval, Phase II
will be advertised for bidding. Phase 2 consists of Disc Golf, Dog Park
Improvements, ADA Parking Improvements , and Water Service
upgrades in dog park.
1st SCVAD – The City and its stakeholders continue productive
discussions as this project gains momentum toward planning and design.
The City and County are working collaboratively. A survey of the
property was completed on January 26, 2026, and a contract with Davis &
Floyd was executed on February 6, 2026.
Page 5 of 6
Scott Marshall
CITY MANAGER
843-525-7070
COUNCIL MEMBERS:
Philip E. Cromer, Mayor
Mike McFee, Mayor Pro Tem
Neil Lipsitz
Mitch Mitchell
Josh Scallate
CITY OF BEAUFORT
1911 Boundary Street
BEAUFORT, SOUTH CAROLINA 29902
Next Meeting: March 12, 2026
Duke St – Davis & Floyd anticipates completing ‘’All necessary
permitting documents ‘’ by the end of February. Coordination with
SCDOT and local utility providers is ongoing, as several utility conflicts
must be resolved prior to permitting. BJW&SA is currently finishing up
drafting of their potential utility relocation plans.
Pigeon Point Landing – The permitting process begun on November
1,2026, the review and issuing of the permit could take up to one year.
Once the regulatory agencies permit process is completed, the plans will
be presented to City Council and the City for approval. The city is aware
of the neighborhood concerns regarding the proposed kayak launch and
the potential increase in vehicular traffic. The City of Beaufort is currently
pursuing Funding sources.
Bayard St. – Project addresses failing drainage infrastructure serving
Bayard, Duke, New, and East Streets. The city is awaiting final
engineering and design plans from Davis & Floyd before proceeding with
regulatory permitting and bidding. A wetland impact study is currently
under review with SCDEWS. Comments from the U.S. Army Corps of
Engineers regarding the Regional General Permit are also pending. John
Gray of Davis & Floyd has completed and recorded all necessary
Easement documents.
Pigeon Point Stormwater Study – The City issued a Request for
Qualifications (RFQ) for this project and is currently in the consultant
selection phase, with the intent to move into bidding thereafter.
Page 6 of 6