Public Facilities Committee — Agenda Packet
Beaufort County · Beaufort County · Public Facilities Committee · meeting of Sep 21, 2026 · Agenda packets
Open the original document More from Beaufort County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Public Facilities Committee Meeting
Beaufort County, SC
Council Chambers, Administration Building
Beaufort County Government Robert Smalls Complex
100 Ribaut Road, Beaufort
Monday, September 21, 2026
4:00 PM
AGENDA
COMMITTEE MEMBERS:
Logan Cunningham, Chair
Anna Maria Tabernik
Thomas Reitz
David P. Bartholomew, Vice-Chairman
Mark Lawson
Alice Howard, Ex-Officio
1. CALL TO ORDER:
2. PLEDGE OF ALLEGIANCE:
3. STATEMENT OF COMPLIANCE WITH FOIA:
4. APPROVAL OF AGENDA
5. PUBLIC COMMENT PERIOD – 15 MINUTES TOTAL
6. ASSISTANT COUNTY ADMINISTRATOR REPORT
7. AGENDA ITEMS
a. 2018 Sales Tax Quarterly Update (For Information Only) (FISCAL IMPACT: For Information
Only) - Bryan Bauer, PE , Director of Engineering, & Jennifer Bragg, PE, J. Bragg Consulting,
2018 One Cent Sales Tax Program Manager (15 mins)
b. Due diligence regarding the Lobeco Library in coordination with the School District. (FISCAL
IMPACT: ) - Audra Antonacci-Ogden, Assistant County Administrator
c. Approval of task order to Collins Engineers, Inc for the design of improvements and expansion of
the Eddings Point Boat Landing ($233,912.80) (Pending A&H Tax awards on 9/14/26) (FISCAL
IMPACT: The fee for Collins Engineers, Inc. for the design and permitting of improvement
and expansion of the Edding's Point Boat Landing is $212,647.80. Staff recommends a 10%
contingency of approximately $21,265 for a total of $233,912.80. Funding for this project is
from A & H tax with account number 2001-10-0000-57130-EDPT with a balance to be updated
after Council meeting on 9/14/26.) - Bryan Bauer, PE - Director of Engineering (5 min)
d. Approval of a change order to MAJ Enterprises, Inc. for the Shell Point Traffic Calming Project
($53,592.09) (FISCAL IMPACT: The change order for materials and construction in the
amount of $48,720.09 is needed to complete and close out the project. Staff recommends a
10% contingency of $4,872.00 for a total budget increase of $53,592.09. The change order
will be funded from the Capital Projects Fund Account No. 4000-80-1243-54500 with a
Page 1 of 105
balance of $471,245.) - Bryan Bauer, Director of Engineering (5 Minutes)
e. Recommendation to Award a contract to Apac Atlantic, Inc for the Sunset Blvd / Miller Drive
roadway resurfacing and traffic calming project ($739,873.48) (FISCAL IMPACT: The contract fee
for materials and construction is $672,612.25. Staff recommend a contingency of 10%
($67,261.23) bringing the project requested budget to be $739,873.48. The funding for this
project is from Account No. 4705-80-0000-S4500-LIMP with a balance of $26,100,000) - Bryan
Bauer, Director of Engineering (5 min)
f. Approval of a Task Order to HDR Engineering, Inc for the Preliminary Engineering for Alterations to
the Chowan Creek Bridge Approaches ($212,630) (FISCAL IMPACT: The fee for HDR
Engineering, Inc. for the preliminary design and engineering of alterations to the Chowan
Creek Bridge is $193,300. Staff recommends a 10% contingency of approximately $19,330
for a total of $212,630. Funding for this project is from TAG account number 2342-30-0000-
51160 with a balance of $1,868,672.00.) - Bryan Bauer, PE - Director of Engineering (5 min)
g. Omnia contract award for St. Helena Island Library LED retrofit ($200,000). (FISCAL IMPACT: The
contract amount is $189,000, staff recommends $11,000 for contingency; bringing the total
cost to $200,000. The funding source will be the 2025 GL Bond GL account # 4013-80-1310-
54420 which has the account balance of $100,000; and Repairs to Buildings GL account #
1000-30-1310-51130 which has the account balance of $3,000,000.) - Ron Lewis, Senior Project
Manager, 5 min.
h. Recommendation for approval of a change order with Kimley Horn for a Phase 2 Environmental
Site Assessment (ESA) on the Ladys Island Drive Turn Lane at Ribaut Road Project ($42,350)
(FISCAL IMPACT: The change order for the Phase 2 ESA is $38,500. Staff recommends a
10% contingency of $3,850, bringing the total approved budget increase to $42,350. Funding
for this task order will be from Impact Fees North account 2300-30-0000-54500-12303 with a
balance of $4,900,000.00.) - Bryan Bauer, Director of Engineering (5 Min)
i. An Ordinance authorizing the private road acceptance of Bellinger Bluff Road and Bellinger Neck
Road into the County Road Inventory (FISCAL IMPACT: Future impacts - Estimated potential
costs for Public Works of roadside cleaning ≈ $20,000 (Stormwater Infrastructure account #
5025-90-9020-51170); Estimated potential cost for paving (Additional 3% inflation applied
over 10 years) ≈ $1,328,950.81 (TAG account # 2342-30-0000-54500)) - Bryan Bauer, Director of
Engineering (5 minutes)
8. ADJOURNMENT
To watch committee or County Council meetings or for a complete list of agendas and backup packages,
please visit: https://beaufortcountysc.gov/council/council-committee-meetings/index.html
Page 2 of 105
BEAUFORT COUNTY
PUBLIC FACILITIES COMMITTEE
AGENDA ITEM SUMMARY
ITEM TITLE:
2018 SALES TAX QUARTERLY UPDATE (FOR INFORMATION ONLY)
MEETING NAME AND DATE:
Public Facilities Committee September 21, 2026
STAFF RECOMMENDATION / COUNCIL OPTIONS:
For Information Only
PRESENTER INFORMATION:
Bryan Bauer, PE , Director of Engineering, & Jennifer Bragg, PE, J. Bragg Consulting, 2018 One Cent Sales Tax
Program Manager (15 mins)
ITEM BACKGROUND:
In 2018, the citizens of Beaufort County voted to impose a 4 year, $120M referendum for transportation
projects. The projects are as follows: US 278 Corridor Traffic Improvements, Lady’s Island Corridor Traffic
Improvements, Sidewalks and Multi-Use Pathways
FISCAL IMPACT:
For Information Only
APPROVAL HISTORY:
For Information Only
Page 3 of 105
BEAUFORT COUNTY
PUBLIC FACILITIES COMMITTEE
AGENDA ITEM SUMMARY
ITEM TITLE:
DUE DILIGENCE REGARDING THE LOBECO LIBRARY IN COORDINATION WITH THE SCHOOL DISTRICT.
MEETING NAME AND DATE:
Public Facilities Committee September 21, 2026
STAFF RECOMMENDATION / COUNCIL OPTIONS:
PRESENTER INFORMATION:
Audra Antonacci-Ogden, Assistant County Administrator
ITEM BACKGROUND:
At the Finance, Administration, and Economic Development Committee Meeting on August 17, 2026, the
committee directed the County Administrator and staff to conduct due diligence regarding the Lobeco Library
in coordination with the School District.
FISCAL IMPACT:
APPROVAL HISTORY:
Page 4 of 105
BEAUFORT COUNTY
PUBLIC FACILITIES COMMITTEE
AGENDA ITEM SUMMARY
ITEM TITLE:
APPROVAL OF TASK ORDER TO COLLINS ENGINEERS, INC FOR THE DESIGN OF IMPROVEMENTS AND
EXPANSION OF THE EDDINGS POINT BOAT LANDING ($233,912.80) (PENDING A&H TAX AWARDS ON 9/14/26)
MEETING NAME AND DATE:
Public Facilities Committee September 21, 2026
STAFF RECOMMENDATION / COUNCIL OPTIONS:
Staff recommends approval of task order to Collins Engineers, Inc. for the design and permitting of
improvement and expansion of the Edding's Point Boat Landing in the amount of $233,912.80.
PRESENTER INFORMATION:
Bryan Bauer, PE - Director of Engineering (5 min)
ITEM BACKGROUND:
The Edding's Point Boat Landing was identified in the Beaufort County Public Boat Landing Facilities Study as a
high-priority for future expansion. It is one of the busier boat landings in the County and lacks adequate
parking and amenities. The project was selected for FY 2026 ATAX funding.
Collins Engineers, Inc was one of three consultants selected in the competitively bid RFQ # 040726 On-Call
Marine and Coastal Engineering Services
FISCAL IMPACT:
The fee for Collins Engineers, Inc. for the design and permitting of improvement and expansion of the Edding's
Point Boat Landing is $212,647.80. Staff recommends a 10% contingency of approximately $21,265 for a total
of $233,912.80. Funding for this project is from A & H tax with account number 2001-10-0000-57130-EDPT
with a balance to be updated after Council meeting on 9/14/26.
APPROVAL HISTORY:
The project was approved for award of FY 2026 ATAX funding at the August 17, 2026 Finance meeting and
then at County Council on September 14, 2026.
Page 5 of 105
Brian Bauer, PE, ENV SP August 27, 2026
Beaufort County
Director of Engineering
104 Industrial Village Road
Building 3
Beaufort, SC 29906
843-255-2706
RE: Eddings Point Boat Landing Improvement Proposal
Dear Mr. Bauer:
Collins Engineers, Inc. (Collins) is pleased to sub mit this cost proposal to Beaufort County (County) to
provide civil engineering services in support of im provements to the Eddings Point Boat Landing site
located at 511 Eddings Point Road in Beaufort County, South Carolina. The scope of services for this project
shall be subject to the terms and conditions of the On Call Marine and Coastal Engineering Services
contract dated June 10, 2026.
Collins understands that the County has identified Eddings Point Boat Landing for enhancement and
improvements to better serve the residents of Beauf ort County under the 2023 Public Boat Landing
Facilities Study. Key elements of improvements on t his project include the expansion of parking,
improvement of the parking and drive surfaces, crea tion of a walking trail, launch ramp improvements,
shoreline stabilization, consideration for an addit ional fishing pier, dock improvements and direction al
signage. Efforts will be made to incorporate resili ent practices where permissible, such as living/hyb rid
shorelines, stormwater treatment systems, corrosion resistant material selections, staging areas for
emergency response and sea-level rise considerations.
Scope of Work
Following is a summary of the scope of services that Collins anticipates performing:
I. Meetings
A. Project Kickoff Meeting: Collins proposes to meet with Beaufort County stakeholders to kickoff
the design efforts. It is anticipated that the kick off meeting will las no more than 2 hours in
duration. The kickoff meeting will include a discussion regarding permitting and include Beaufort
County permitting and Resource Land Consultants (RLC).
B. Design Submittal Review Meetings : At the conclusion of each design stage, Collins will conduct
a design review meeting to review consolidated comments from Beaufort County stakeholders.
It is assumed Collins will have consolidated comments prior to the review meeting and will come
prepared to discuss any comments requiring greater discussion. It is assumed that each design
review meeting will be 2 hours in duration.
Page 6 of 105
C. Monthly Coordination Calls: Collins will attend monthly meetings with the Beau fort County
Project Manager to discuss the project. Calls are anticipated to average 30 minutes in duration.
Issue tracking and risk register review shall be di scussed during these meetings; Collins will
maintain a list of ongoing issues along with resolutions when developed.
II. 30% Design (Schematic Design)
A. Basis of Design Memorandum: This document will outline the design criteria, assumptions, and
methodologies used in the schematic design phase. It will include:
• Project objectives and scope
• Design assumptions and criteria
• Preliminary design calculations
• List of anticipated drawings and specifications
B. Survey and Geotechnical Investigation: Complete a topographical and site survey of the fu ll
parcel(s), including Jenkins Creek adjacent to the site. A geotechnical investigation will also be
conducted to provide pavement recommendations and evaluate permeability of the site.
C. Schematic Drawings: These drawings will provide a preliminary layout o f proposed
modifications, including:
• General layout of parking and traffic flow
• Proposed drainage scheme
• Critical area impacts
D. Anticipated Drawings and Specifications: A comprehensive list of all drawings and specifications
expected to be developed during the detailed design phase.
E. Cost Estimate: Collins will develop a Class IV estimate as defined by AACE.
F. Schedule: Collins will provide a schedule of design, permitt ing and construction activities
anticipated for the project.
III. 60% Design (Detailed Design)
A. Plans and Specifications: The detailed design phase will produce plans and s pecifications that
are complete to an overall average of 60%, including:
• Detailed layout of parking, staging, traffic and surface improvements
• Storm structure locations and details
• Defined critical area impacts and mitigation plan
• Utility routing
• Final grading
B. Design Review and Coordination: Coordination with Beaufort County and other stakeholders to
review the 60% design documents and incorporate feedback.
Page 7 of 105
C. Cost Estimate: Collins will provide a class II estimate as define d by AACE. The design will be
considered frozen at the conclusion of the 60% design review process. Any changes made after
this may have a significant impact on project schedule and cost.
D. Schedule: Collins will provide an updated schedule at this design submission.
IV. 90% Design (Final Design)
A. Final Plans and Specifications: The final design phase will produce plans and specifications that
are 90% complete and ready for Beaufort County review, including:
• Complete set of construction drawings
• Finalized details
• Draft front-end documents
• Liquidated damages and schedule recommendations
• SWPPP
B. Quality Control and Assurance: Conduct thorough quality control and assurance rev iews to
ensure the design meets all project requirements and standards.
C. Final Design Review: Facilitate a final design review meeting with Beau fort County to address
and remaining comments and finalize the design documents.
D. Cost Estimate: Collins will develop a Class I estimate as defined by AACE. It is anticipated this
cost estimate will be updated during the bid phase of the project.
E. Schedule: Collins will provide an updated schedule at this design submission.
V. 100% Design (Issued for Bid Documents)
A. Sealed Drawing and Specification Set: Collins will provide a sealed set of construction drawings
and specifications for bidding purposes.
B. O & M Manual: Collins will prepare a short and concise O&M Manua l for the County outlining
any requirements listed on construction plans for required maintenance of proposed facilities.
C. Bid Support: Collins will prepare materials for and attend a pr e-bid meeting and support
Beaufort County during the bid process by respondin g to bidder inquiries and issuing any
necessary addenda. Collins will also review the bids for responsiveness and responsibleness and
issue a path forward recommendation letter to Beauf ort County for use in considering and
awarding bids.
D. Cost Estimate: Collins will update the previous Class I estimate during the bid phase.
VI. Permitting
Collins will engage Resource Land Consultants as a subconsultant to manage and execute the permitting
efforts required for the Eddings Point Boat Landing project. The scope of services for permitting will
include the following tasks:
Page 8 of 105
A. Permitting Strategy Development:
a. Initial Assessment: Conduct an initial assessment to identify all nece ssary permits and
regulatory requirements
b. Permitting Plan: Develop a comprehensive permitting plan outlining the steps, timelines,
and responsibilities for obtaining the required permits.
B. Regulatory Coordination:
a. Agency Consultation: Engage in early consultation with relevant regulat ory agencies,
including the U.S. Army Corps of Engineers (USACE), U.S. Coast Guard (USCG), South
Carolina Department of Environmental Services (DES), Coastal Zone Consistency Division
(CZC) Bureau of Coastal Management, and other stakeholders.
b. Pre-applications Meetings: Schedule and conduct pre-application meetings with
regulatory agencies to discuss project scope, poten tial impacts, and permitting
requirements as required.
C. Permit Application:
a. Nationwide Permit: Determine if the project qualifies for a Nationwid e Permit and
prepare the necessary documentation for submission.
b. Additional Permits: Identify and prepare applications for additional p ermits required,
such as local construction permits, water quality c ertifications, and coastal zone
consistency determinations.
D. Public Involvement:
a. Public Notices: Prepare and distribute public notices as required b y regulatory agencies
to inform the public about the project and solicit feedback.
VII. Construction Administration
A. Conformed Document Set: Upon completion of the procurement and contract aw ard process,
Collins will utilize addenda, clarifications and an y negotiations to updated construction
documents to one conformed set with the intention to issue for construction.
B. Meetings: Attend the preconstruction meeting and monthly pro gress meetings for a duration
up to 8 months of construction. Collins will also b e present at and document the substantial
completion inspection, the final completion inspect ion and the warranty inspection (post
construction).
C. RFIs and Submittals: Collins will review, evaluate and respond to up to 10 RFIs and 10 submittals
from the selected contractor.
D. Site Observations: Collins we perform observations of construction pr ogress on site twice
monthly for the duration of the project, up to 8 months from construction NTP.
E. Record Drawings: Upon completion of construction Collins will utili ze redline documents
provided by contractor to update the design drawings and generate record drawings. Collins will
also update the O&M manual with applicable changes applicable since draft issued at 100%
plans.
Page 9 of 105
Project Schedule
The following milestones are proposed, assuming a Notice to Proceed no later than October 1, 2026. Days
are in calendar days.
• Schematic Design: 75 days from NTP
• Detailed Design: 60 days from approval of SDs
• Final Design: 60 days from approval of DDs
• Issued for Construction: 120 days from approval of FDs
• Permitting: 240 days from SDs
• Construction Administration: As needed
Fees
Collins will provide the above scope of services on lump sum basis as follows. All of Collins’ rates are in
accordance with our 2026/2027 rate schedule. A summary of estimated labor hours is also provided.
Design.......................................................................................................... $113,020.00
Permitting ................................................................................................... $17,066.50
Surveying ..................................................................................................... $29,425.00
Geotechnical Investigation ......................................................................... $8,977.30
Construction Administration....................................................................... $41,810.00
Reimbursable Costs (travel, etc.) ................................................................ $2,349.00
Total Base Services ...............................................................................$21 2,647.80
In the event additional services are required, Collins recommends holding a budget of 10% for
unforeseen conditions or client driven change directives. It is proposed that the Additional Services task
will be executed only as authorized by Beaufort County, up to a total of $21,264.78.
Additional Services ............................... ...............................................$ 21 ,264.78
Total Proposed Fee ................................ ..............................................$ 233 ,912.58
Page 10 of 105
Assumptions and Conditions
A. This site lies within 1,500 LF of an active oyster reef and will require retention of the first 1.5”
rainfall on site.
B. Provide COLLINS with access to the site.
C. Provide COLLINS with any available construction and/or repair documents of the structure.
D. Provide COLLINS with a current geotechnical report of the proposed retaining wall site, sufficient
for design of the proposed wall.
E. Provide COLLINS with size, type, material and elevation of all utilities that enter the retaining wall
project area or may impact the retaining wall design.
Exemptions and Services not included
All services not listed under "Services" are consid ered Additional Services. The compensation for the se
services will be in addition to that for "Services." "Additional Services" include, but are not limited to the
following:
A. Visits to the site in excess of those noted in "Services" above.
B. Conducting condition assessments of existing facilities.
C. Engineering services incidental to project scope changes beyond COLLINS' control.
D. Control over or charge of safety procedures, precautions, and programs.
E. Construction administration and construction inspections beyond those listed in scope.
F. Performing site survey for record drawings.
Collins appreciates the opportunity to work with Be aufort County. Please feel free to contact Matthew
Barrow, Regional Manager, at 843-410-3720 or
mbarrow@collinsengr.com if you have any questions or
comments regarding this proposal.
Page 11 of 105
Determination of Price Reasonableness for Solicitation
Procurement Services Department
Solicitation Details
Date/Time:*
Aug 27, 2026 4:59 PM
Preparer:*
Bauer, Bryan
From:*
Bauer, Bryan
Department:*
Engineering
Solicitation Number:*
NA
Purpose:*
Edding's Point Boat Landing Improvement and Expansion
Background
Describe the relevant procurement, including a brief description of the product/service/scope of work.*
Staff requested a proposal from Collins Engineers, Inc under their marine engineering on-call, per the process identified in the on-call policy manual, for the design and permitting of improvement and expansion of the Edding's Point Boat Landing.
State procurement’s significance to the project or County operations.*
The Edding's Point Boat Landing was identified in the Beaufort County Public Boat Landing Facilities Study as a high-priority for future expansion. It is one of the busier boat landings in the County and lacks adequate pakring and amenities. The project was selected for FY 2026 ATAX funding.
Outline the procurement method utilized for this contract: (IFB, RFP, RFQ, Quotes).*
Collins Engineers, Inc was one of three consultants selected in the competitively bid RFQ # 040726 On-Call Marine and Coastal Engineering Services. Staff requested a proposal from Collins Engineers, Inc under their marine engineering on-call, per the process identified in the on-call policy manual, for the design and permitting of improvement and expansion of the Edding's Point Boat Landing.
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 1/5
Page 12 of 105
Price Analysis
Summarize the bid (s)/quotes (s) received with their respective amounts.*
Collins proposal dated August 27, 2026 was for a fee of $206,664.80.
If applicable: note any previous price history for similar procurements.
Staff estimated the budget for the project to be $500,000 when submitting the ATAX application based on similar projects.
Comparisons with substantially similar items.*
The design of the Alljoy Boat Landing with similar scope was $495,000.The design of the Wimbee Creek boat landing with similar scope was $397,000.
Sales of the same item to other purchasers.*
NA
Analysis of the cost elements (e.g. labor rate and estimated hours, material rates, indirect costs, reasonable
profit)*
Projects have been priced as man-hour estimates with a not to exceed cost.
8/27/26, 5:25 PM Nintex Forms for SharePoint Lists
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 2/5
Page 13 of 105
List and explain the benchmarks, market analysis, or other data sources used to evaluate price fairness.*
Price submitted is less than budget allotted and similar in price to previous projects.
Justification of Acceptance of Single Proposal/Bid
Consideration of re-solicitation?
Yes No
Consideration of reasons for a single applicant?
Yes No
Explain:
Collins Engineers, Inc was one of three consultants selected in the competitively bid RFQ # 040726 On-Call Marine and Coastal Engineering Services. Staff requested a proposal from Collins Engineers, Inc under their marine engineering on-call, per the process identified in the on-call policy manual, for the design and permitting of improvement and expansion of the Edding's Point Boat Landing.
Consideration of reasonable search for qualified applicants?
Yes No
Explain:
NA
Cost Analysis (if applicable)
Detail the cost elements (labor, materials, overhead, etc.) provided by the supplier or contractor.
NA
8/27/26, 5:25 PM Nintex Forms for SharePoint Lists
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 3/5
Page 14 of 105
Provide an analysis of the necessity and reasonableness of each cost element.
NA
Vendor's Pricing Strategy (optional)
What is the vendor's pricing strategy?
Department Head Decision
Comments
Approve Disapprov
e
Department Head Signature
Bauer, Bryan
Date/Time
Aug 27, 2026 5:11 PM
Purchasing Decision
8/27/26, 5:25 PM Nintex Forms for SharePoint Lists
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 4/5
Page 15 of 105
Comments
The price of the professional services is fair and reasonable and under the cost estimate. This procurement process complies with our procurement code.
Approve Disapprov
e
Purchasing Signature
Thomas, Dave
Date/Time
Aug 27, 2026 5:21 PM
8/27/26, 5:25 PM Nintex Forms for SharePoint Lists
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 5/5
Page 16 of 105
Page 1 of 2
1. CONTRACT NAME AND NUMBER 2. TASK ORDER NO.: 3. EFFECTIVE DATE:
On-Call Marine and Coastal Engineering
RFQ #040726
Eddings Point Dock September 1, 2026
TASK ORDER FOR SERVICES
4. CONTRACTOR NAME, ADDRESS, PHONE, AND EMAIL:
Collins Engineers Inc.
5955 Core Rd, Suite 522
North Charleston, SC 29406
Matthew Barrow
mbarrow@collinsengr.com
5. ISSUED BY:
Beaufort County Procurement Services
PO Drawer 1228
Beaufort, SC 29901
For Questions Contact:
Gillian Murray
(843) 255-2287
Email: gmurray@bcgov.net
6. PROJECT NAME/TITLE AND DESCRIPTION:
Eddings Point Dock
1. Meetings
2. Schematic Design
3. Detailed Design
4. Final Design
5. 100% Design for bid documents
6. Permitting
7. Construction Administration
7. OTHER PERTINENT INFORMATION OR SPECIAL CONSIDERATIONS:
This task order is issued pursuant to the Scope and Fee Proposal dated August 27, 2026 and attached.
8. PAYMENT TYPE:
Vendor will be paid on a percentage complete basis with the submission of monthly invoices
9. LIQUIDATED DAMAGES
N\A
10. NUMBER OF DAYS/MONTHS
TO COMPLETE PROJECT
315 Days after issuance of Notice to
Proceed
11. TOTAL AWARD AMOUNT:
$212,647.80
12. Project Manager’s Name Mark Johnson
Project Manager’s Email mjohnson@bcgov.net
Project Manager’s Phone 843-255-2739
Page 17 of 105
Page 2 of 2
12. AUTHORIZED SIGNATURE FOR THE VENDOR:
a. SIGNATURE:
b. NAME/TITLE OF SIGNER:
c. DATE SIGNED:
13. AUTHORIZED SIGNATURE FOR THE COUNTY
a. SIGNATURE
b. NAME/TITLE OF SIGNER
c. DATE SIGNED
08/31/2026
Page 18 of 105
BEAUFORT COUNTY
PUBLIC FACILITIES COMMITTEE
AGENDA ITEM SUMMARY
ITEM TITLE:
APPROVAL OF A CHANGE ORDER TO MAJ ENTERPRISES, INC. FOR THE SHELL POINT TRAFFIC CALMING
PROJECT ($53,592.09)
MEETING NAME AND DATE:
Public Facilities Committee September 21, 2026
STAFF RECOMMENDATION / COUNCIL OPTIONS:
Staff recommends approval of a change order to MAJ Enterprises, Inc. for the Shell Point Traffic Calming
Project ($53,592.09)
PRESENTER INFORMATION:
Bryan Bauer, Director of Engineering (5 Minutes)
ITEM BACKGROUND:
On February 18, 2026 Beaufort County published an Invitation for Bid (IFB) # 032326 Shell Point Traffic
Calming requesting competitive bids for materials and installation of traffic calming measures in the Shell
Point neighborhood. Due to a resident complaint, one of the speed humps was moved to be further from their
driveway. Also, a catch basin was discovered at Broad River Drive and Shell Point Road that required a traffic
rated solid lid for the raised intersection. Additionally, construction quantities were substantially higher than
estimated for the Asphalt Surface Course. Due to these factors, the costs have exceeded the contract amount.
FISCAL IMPACT:
The change order for materials and construction in the amount of $48,720.09 is needed to complete and close
out the project. Staff recommends a 10% contingency of $4,872.00 for a total budget increase of $53,592.09.
The change order will be funded from the Capital Projects Fund Account No. 4000-80-1243-54500 with a
balance of $471,245.
APPROVAL HISTORY:
Resolution 2025/13 approved traffic-calming measures in the Shell Point neighborhood. On April 20, 2026 the
Public Facilities Committee approved a contract with M.A.J. Enterprises, Inc. for $170,108.96.
Page 19 of 105
Shell Point Traffic Calming
Estimated
Over/UnderLine Item Description Quantity Unit of MeasureUnit Cost Total Final Quant
1 1031000 Mobilization 1 LS $22,000.00 $22,000.00 1.00 22,000.00 $0.00
2 1032010 Bonds & Insurance 1 LS $8,500.00 $8,500.00 1.00 8,500.00 $0.00
3 1050800 Construction Stakes, Lines & Grades 1 EA $1,000.00 $1,000.00 1.00 1,000.00 $0.00
4 2012000 Clearing & Grubbing Within Roadway 1 LS $1,000.00 $1,000.00 1.00 1,000.00 $0.00
5 2033000 Liquid Asphalt Binder PG64-22 6 TN $366.67 $2,200.02 10.31 3,780.37 $1,580.35
6 4013990 Milling Existing Asphalt Pavement (Variable) 212 SY $16.00 $3,392.00 244.17 3,906.72 $514.72
7 4020320 Asphalt Base Course - Type B 10 TN $550.00 $5,500.00 9.25 5,087.50 -$412.50
8 4040340 Asphalt Surface Course - Type C 82 TN $525.00 $45,100.00 167.82 88,105.50 $45,055.50
9 6011000 Traffic Control 1 LS $15,000.00 $15,000.00 1.00 15,000.00 $0.00
10 6051120 Permanent Construction Signs (Ground Mounted) 496 SF $18.00 $8,928.00 94.00 1,692.00 -$7,236.00
11 6240110 4 In Yellow Solid Lines - Fast Dry Paint 60 LF $10.00 $600.00 324.00 3,240.00 $2,640.00
12 6240020 12 In White Solid Lines - Fast Dry Paint 350 LF $13.00 $4,550.00 400.00 5,200.00 $650.00
13 6240025 24 In White Solid Lines - Fast Dry Paint 50 LF $30.00 $1,500.00 50.00 1,500.00 $0.00
14 6281010 4 In White Solid Lines (edgline), High Build Paint - 25 mils 160 LF $30.00 $4,800.00 188.00 5,640.00 $840.00
15
6281105 4 In Yellow Solid Lines (centerline), High Build Paint - 25
mils 60 LF $35.00 $2,100.00 88.00 3,080.00 $980.00
16
6282020 12 In White Solid Lines, Sgl Comp. Hybridized Polymer - 25
mils 350 LF $50.00 $17,500.00 350.00 17,500.00 $0.00
17
6282025 24 In White Solid Lines, Sgl Comp. Hybridized Polymer- 25
mils 50 LF $60.00 $3,000.00 44.00 2,640.00 -$360.00
18 6510105 Flat Sheet, Type III, Fixed Size & Message Sign 178 SF $41.23 $7,338.94 152.00 6,266.96 -$1,071.98
19 6531210 U-Section Post for Sign Support - 3P 286 LF $10.00 $2,860.00 286.00 2,860.00 $0.00
20 7143618 18 In Smooth Wall Pipe 20 LF $100.00 $2,000.00 19.00 1,900.00 -$100.00
21 7149999 Cleaning Existing Pipe 120 LF $22.00 $2,640.00 34.09 750.00 -$1,890.00
22 7197052 Concrete Collar for up to 24 In Pipe 2 EA $750.00 $1,500.00 2.00 1,500.00 $0.00
23 8109901 Mowing 0.08 AC $6,250.00 $500.00 0.08 500.00 $0.00
24 8152007 Sediment Tube 4 EA $200.00 $800.00 4.00 800.00 $0.00
25 8153000 Silt Fence 100 LF $8.00 $800.00 100.00 800.00 $0.00
26 2031200 Site Excavation (including Borrow) 1 LS $3,500.00 $3,500.00 1.00 3,500.00 $0.00
27 8100102 Permanent Grassing for Resurfacing Projects 0.05 AC $30,000.00 $1,500.00 0.056 1,680.00 $180.00
CO 1 Removal of Speed Hump 1 EA $5,300.00 $5,300.00 1.00 5,300.00 $5,300.00
CO 2 Inlet Top for Storm Drain Structure Under Roadway (discovered) 1 EA $2,050.00 $2,050.00 1.00 2,050.00 $2,050.00
Page 20 of 105
Total $170,108.96 $48,720.09
$216,779.05
Reduced Price from $550 per ton
Page 21 of 105
SHELL POINT TRAFFIC CALMING
Scope of Work
The work will consist of furnishing all materials, labor and equipment for:
Construction of one raised intersection w ith minor improvements at the intersection of
Shell Point Road and Broad River Drive as well as three speed humps on Shell Point Road, five
on Broad River Drive and one on Dogwood Street.
All work under this contract shall be done in accordance with the South Carolina Department of
Transportation (SCDOT) Standards (specifications, supplemental specifications, drawings and
supplemental technical specifications); the latest edition of the Manual on Uniform Traffic
Control Devices (MUTCD) and all provisions of SCDOT Encroachment Permit No. 294120.
All materials used in the contract work must be furnished from SCDOT Qualified Products Listing
& Policies for Construction. A ll material certifications and submittals must be approved prior to
incorporation into the work.
It is preferred that the Prime Contractor be pre-qualified by SCDOT. All subcontractors must be
listed in the bid package or approved by the County in writing prior to performing work on the
project.
The contractor shall provide independent third party SCDOT Certified Quality Control
Inspections to include:
• Set-up roller patterns, monitor asphalt placement, verify temperature, receiving load
tickets.
• Document all work and inspections in accordance with SCDOT procedures. Provide
weekly copies of reports to County Project Manager.
• Provide independent SCDOT Certified inspector at plant during batching operations to
monitor and document product and tests in accordance with SCDOT requirements.
Project Administration:
Beaufort County Engineering
104 Industrial Village Rd, Bldg. 3
Beaufort, SC 29906
Project Administration will be provided by Beaufort County. Quality assurance inspection will
be performed by an independent firm hired by Beaufort County.
Page 425 of 522
Page 22 of 105
Contract Type:
Unit Rate
Quantities are approximate and payment shall be for measurements of actual in-place work as
per the plans and specifications. Any quantities exceeding the contract amount shall be requested
by the Contractor in writing, for approval by the County, prior to the work being performed.
Payment will not be made for additional quantities without prior written approval of the County.
The cost associated with any incidental items of construction in which no specific pay items are
set up for shall be included in the overall cost of the project.
Contract Documents:
Contract Documents include the Shell Point Traffic Calming IFB documents, construction plans
and the contract. The technical specifications (SCDOT Standards including Specifications,
Drawings, Supplemental Specifications and Supplemental Technical Specifications) for the
project are available online and are considered part of the contract documents.
Contract Time:
The Contractor shall agree to commence work under this contract within 10 working days after
the Notice to Proceed (NTP) is issued and complete all work within 60 calendar days from NTP.
The Contractor shall work continuously on the project after the Notice to Proceed is issued.
Any punch list work shall be completed within 30 calendar days.
Failure to complete all work within 60 calendar days plus any extension authorized in writing by
the County, or complete punchlist work within 30 calendar days, shall entitle the County to
deduct Liquidated Damages (LDs). LDs shall be deducted from the monies due the Contractor in
the amount of $600 for each calendar day in excess of the authorized construction time as per the
SCDOT schedule for liquidated damages 108.9.
Traffic Control:
Traffic Safety is paramount. The Contractor will be responsible for all traffic control, in
accordance with the Manual on Uniform Traffic Control Devices, SCDOT standards and all
other safety measures that will enhance the safety of the construction site. All costs associated
with this work shall be included in the bid price for traffic control. The Contractor shall submit a
traffic control plan for approval prior to beginning any work. Any changes to the approved traffic
control plan must be submitted and approved in writing.
The contractor shall designate a responsible person with sufficient qualifications who shall be
responsible for administering the traffic control plan. This representative shall have successfully
completed an advanced or supervisor work zone traffic control training program. The
representative shall be on-site anytime work is being performed in or adjacent to the roadway to
ensure proper installation, maintenance and removal of appropriate traffic control devices.
Preconstruction Conference:
The Contractor shall attend a pre-construction conference prior to commencing any work on site.
Page 426 of 522
Page 23 of 105
Construction Schedule:
The Contractor shall prepare a detailed schedule showing the sequence of operation and timeline
of all phases of construction. The schedule must be submitted and approved prior to beginning
work.
Utilities:
The Contractor will be responsible for all utility coordination, including required relocation, and
protection of utility facilities.
As-builts:
Contractor shall submit record drawings (marked with any changes) and post construction survey
invert elevations for the storm drain pipe.
Clarifications
Asphalt indexing using the SCDOT Index will not be utilized for this project.
The milling is intended for the parabolic areas of the raised intersection (6 ft) as well as parabolic
portions of the speed hump s (3 ft) each side to ensure a minimum lift of 150 lb/sy to the joint.
Time between milling and asphalt application will not exceed 5 calendar days.
Apply temporary paint striping, including stop bars and striping for the raised intersection and
speed humps immediately following paving operations.
There is no SWPPP for this project. Silt fence and sediment tubes w ill be installed as necessary
and per the direction of the Engineer.
The Unclassified Value within the contract, as per SCDOT may include but is not limited to:
rock, existing storm drain pipe, soil, relocating suitable materials from one location to another
location less than 3,000 LF, asphalt less than 2 inches thick, etc. Unclassified Value, when cross
sections are provided, will be paid at 100% of this value, divided over the estimated monthly pay
estimates based on the number of contract days. It is the contractor’s responsibility to bring to
the immediate attention (within 1 business day) of the County representative if in-field cross
sections do not conform to plan dimensions in order to be considered for additional payment.
Borrow Values within the contract, as per SCDOT will be quantified by measurement of placed
material. It is recommended the contractor perform elevation verifications prior to, and after
removal of surficial organic matter. After placement of borrow to defined cross sections, post
elevation verifications will be performed by the Couty to verify the placed borrow conforms to
cross sections. If existing elevation verifications are not performed simultaneously with and
agreed upon by county and contractor prior to borrow placement, elevations provided by cross
sections will be used for calculations of placed borrow. If approved in writing by country, truck
count method may be used.
Truck Count Method- A standard quantity of cubic yards per truck will be agreed upon prior to
the work. Daily random checks will be performed by the counties representative to verify the
truck bed dimensions and volume of fill. No payment will be made for volumes exceeding the
standard amount.
Page 427 of 522
Page 24 of 105
Page 428 of 522
Page 25 of 105
Page 429 of 522
Page 26 of 105
Page 430 of 522
Page 27 of 105
1
STATE OF SOUTH CAROLINA )
) CONTRACT
COUNTY OF BEAUFORT ) Shell Point Traffic Calming
THIS CONTRACT (hereinafter the "Contract") entered into this 8th day of April , 2026 , between the
COUNTY OF BEAUFORT, South Carolina, a public body corporate and politic and political subdivision
of the State of South Carolina, (hereinafter "County") and MAJ Enterprises, Inc. , (hereinafter the
"Contractor"), ("Party" as to each; collectively the "Parties")
WITNESSETH:
WHEREAS, the County wishes to contract for Shell Point Traffic Calming (the "Work" and/or
"Services"); and
WHEREAS, the Contractor has represented to the County that its staff is qualified to provide the Work
required in this Contract in a professional, timely manner; and
WHEREAS, the County has relied upon the above representations by the Contractor;
NOW, THEREFORE, in consideration of these premises and covenants set forth herein, it is agreed by and
between the Parties as follows:
SECTION ONE
Contract Documents
The Parties agree that the Contract Documents shall include the following, which are incorporated herein
by reference:
Exhibit A: Contractor's Bid dated March 23, 2026.
Exhibit B: IFB 032326
In the event of any conflict, discrepancy, or inconsistency among any of the documents which make up this
Contract, the following shall control:
As between the Contract and the Contract Documents which make up this Contract, the Contract
shall govern.
In the event of any conflict, discrepancy, or inconsistency among any of the Contract Documents,
the Contractor shall contact the County immediately upon discovery of the same for resolution by
the County.
Any documents not included or expressly contemplated in this Contract do not, and shall not, form
a part of this Contract. The Contract Documents are intended to be complementary, and a
requirement in one document shall be deemed a requirement in all documents.
SECTION TWO
Scope of Work
The Contractor agrees to perform and furnish all labor, supervision, materials, equipment, transportation
and supplies necessary for the completion of the Work required under this Contract in a timely and
Page 432 of 522
Page 28 of 105
2
workmanlike manner, professional in all aspects, and in accord with all applicable laws, rules and
regulations.
The Contractor shall provide the services outlined below in conjunction with the Contractor's Bid dated
March 23, 2026 marked as Exhibit A, that was previously incorporated by reference. The Contractor shall
commence the Work as specified in the Notice to Proceed, when it is issued, but not before it is issued.
Coordination of the Work and administration of this Contract shall be by Beaufort County.
SECTION THREE
Contract Price: Payment Terms
County agrees to pay for the performance of the Work described in this Contract, including all items
necessary to accomplish and complete the Work, in accordance with all terms and conditions as stated
herein on the following basis:
Contract Amount: One Hundred Seventy Thousand One Hundred Eight Dollars and Ninety-Six Cents
($170,108.96)
Payments:
Contractor will be paid on a line item by quantity basis with the submission of monthly invoices.
Monthly payments will be made based on a line item quantities of work in place. Final payment which shall
be paid upon Final Acceptance by the County's authorized representative. Final Acceptance is defined as
the County accepting the Work from the Contractor when the County deems the Work completed in
accordance with the terms of the Contract.
Final Payment is defined as the last payment from the County to the Contractor of the entire unpaid balance
of the Contract as adjusted by any approved change orders.
Application for payment shall be prepared and submitted electronically. All invoices shall be addressed to
Engineering Division, PO Drawer 1228 Beaufort SC 29901.
SECTION FOUR
Time: Term of Contract
The County hereby contracts with Contractor to provide the Work specified herein within Sixty (60)
calendar days after issuance of the Notice to Proceed.
The County reserves the right to extend the term of this Contract, if it is determined to be in its best interest.
The Contractor expressly acknowledges that time is of the essence in completion of this Contract and that
the time limits and dates herein are critical components of the Contract. Therefore, liquidated damages have
been set at $600 per calendar day. The Contractor warrants and represents that it has taken these facts into
consideration and has determined that it can complete the work within these time limits, including time for
likely delays caused by weather or from other sources. The Contractor will not be compensated for any
delays beyond the time set forth herein. The Contractor's only remedy for delays may be an extension of
time to perform the Work. Due consideration will be given to claims for an extension of time due to
extraordinary circumstances only.
Page 433 of 522
Page 29 of 105
3
SECTION FIVE
Insurance Requirements
The Contractor, at its own expense, shall at all times during the term of the Contract, maintain insurance as
included in the solicitation, Insurance Requirements, which is attached hereto and previously incorporated
by reference. The County may contact the Contractor's insurer(s) or insurer(s)' agent(s) directly at any time
regarding the Contractor's coverages, coverage amounts, or other such relevant and reasonable issues
related to this Contract. The Contractor shall also require any subcontractors to ca rry the same coverages
in the same amounts.
The County must be advised immediately of any changes in required coverages.
SECTION SIX
Compliance with Legal Requirements
All applicable federal, state and local laws, ordinances, and rules and regulations of any authorities
(including, but not limited to, any laws, ordinances or regulations relating to the S.C. Department of
Revenue or the S.C. Board of Contractors) shall be binding upon the Contractor throughout the pendency
of the Work. The Contractor shall be responsible for compliance with any such law, ordinance, rule or
regulation, and shall hold the County harmless and indemnify same in the event of non- compliance as set
forth in the Contract.
The Contractor certifies that it will comply with the applicable requirements of Title 8, Chapter 14 of South
Carolina Code of Laws (1976, as amended) and agrees to provide to the State upon request any
documentation required to establish either: (a) that Title 8, Chapter 14 is inapplicable to the Contractor and
its subcontractors or sub -subcontractors; or (b) that the Contractor and its subcontractors or
subsubcontractors are in compliance with Title 8, Chapter 14.
Pursuant to Section 8- 14-60, "A person who knowingly makes or files any false, fictitious, or fraudulent
document, statement, or report pursuant to this chapter is guilty of a felony and, upon conviction, must be
fined within the discretion of the Court or imprisoned for not more than five years, or both."
The Contractor agrees to include in any contracts with subcontractors, language requiring subcontractors
to (a) comply with applicable requirements of Title 8, Chapter 14, and (b) include in its contracts with the
subcontractors language requiring the sub- subcontractors to comply with the applicable requirements of
Title 8, Chapter 14.
The Contractor agrees to and shall certify agreement to abide by the requirements under Title VI of the
Civil Rights Act of 1964, and other non-discrimination authorities under Federal Executive Order Number
11246, as amended, and specifically the provisions of the equal opportunity clause.
The Contractor shall comply with all federal, state and local laws, ordinances, rules and regulations of any
authorities throughout the duration of this Contract. The Contractor shall be responsible for compliance
with any such law, ordinance, rule or regu lation, and shall hold the County harmless and indemnify same
in the event of non-compliance.
Page 434 of 522
Page 30 of 105
4
SECTION SEVEN
Drug-free Workplace Act
The Contractor shall comply with the South Carolina Drug-free Workplace Act, Section 44-107-10 et seq.,
S.C. Code of Laws (1976, as amended). The County requires all contractors executing contracts for a stated
or estimated value of $50,000 or more to sign a Drug-free Workplace Certification form prior to the issuance
of the Notice to Proceed.
SECTION EIGHT
Contractor's Warranties and Representations
The Contractor represents that its staff is knowledgeable about and experienced in performing the Work
required in this Contract and warrants that it will use best skill and attention to provide above described
Work in a professional, timely manner.
The Contractor warrants and represents that it shall be responsible for all subcontractors working directly
for it, as well as for their work product, as though the Contractor had performed the Work itself.
1. If equipment, materials and supplies are to be a part of the service provided, all equipment,
materials, and supplies incorporated in the Work covered by the bid and provided by the
Contractor are to be new and of the most suitable grade for the purpose intended. Unless
otherwise specifically provided in this Contract, reference to any equipment, material, article or
patented process, by trade name, make or catalog number, shall not be construed as limiting
competition. When requested, the Contractor shall furnish to the Purchasing Director, for
approval the name of the manufacturer, the model number, and other identifying data and
information respecting the performance, capacity, nature and rating of the machinery and
mechanical and other equipment which the Contractor contemplates incorporating in the Work.
When required by this Contract or when called for by the Purchasing Director, the Contractor
shall provide full information concerning the material or articles that he contemplates
incorporating in the Work. When so directed, samples shall be submitted for approval at the
Contractor's expense, with all shipping charges prepaid. Machinery, equipment, material and
articles installed or used without the required prior approval of the County shall be at the risk of
subsequent rejection by the County.
2. Any and all manufacturers' warranties on any equipment or materials will be passed on to the
County and copies of said warranties will be furnished by the Contractor to the County upon
completion and final acceptance of the Work.
3. The Purchasing Director may, in writing, require the Contractor to remove from the Work Site
any employee the Purchasing Director deems incompetent, careless or otherwise objectionable.
4. In addition to any manufacturer's warranties, all labor and materials are warranted to be free from
defects for a period of twelve (12) months after the date of Final Payment by the County.
Page 435 of 522
Page 31 of 105
5
SECTION NINE
Retention of Records
The Contractor agrees to maintain for three (3) years from the date of Final Payment, or until the end of
any audit or closure of all pending matters under this Contract, whichever is later, all books, documents,
papers, and records pertinent to this Contract. The Contractor agrees to provide to the County, any federal
grantor agency, the Comptroller General of the United States, any state gantor agency, any assignee, or any
of their duly authorized representatives access to such books, documents, papers, a nd records for the
purpose of examining, auditing, and copying them. The Contractor further agrees to include these
provisions in any subcontracts issued in connection with this Contract.
SECTION TEN
State and Local Taxes
Except as otherwise provided, Contract prices shall include all applicable state and local taxes.
The Contractor shall calculate that portion of the Contract that is subject to the six percent (6%) South
Carolina sales and/or use tax, and this amount shall be itemized and shown on all invoices, and shall be
paid to the SCDOR by Contractor. If Contractor is a non- South Carolina Company, the County will
withhold said amount from all invoices and remit payment to the SCDOR, unless the Contractor furnishes
the County with a valid South Carolina Use Tax Registration Certificate Number.
The Contractor shall indemnify and hold harmless the County for any loss, cost, or expense incurred by,
levied upon or billed to the County as a result of the Contractor's failure to pay any tax of any type due in
connection with this Contract.
The Contractor shall ensure that the above sections are included in all subcontracts and sub -subcontracts,
and shall ensure withholding on out of state sub and sub-subcontractors to which withholding is applicable.
SECTION ELEVEN
Independent Contractor
The Contractor is an independent contractor and shall not be deemed the agent or employee of the County
for any purpose whatsoever. Contractor shall not hold himself out as an employee of the County, and shall
have no power or authority to bind or obligate the County in any manner, except the County shall make
payment to the Contractor for work and expenses as herein provided. The Contractor shall obtain and
maintain all licenses and permits required by law for performance of this Contract by him or his employees,
agents, and servants. The Contractor shall be liable for and pay all taxes required by local, state or federal
governments, including but not limited to social security, Workers' Compensation, employment security,
and any other taxes and licenses or insurance premiums required by law. No employee benefits of any kind
shall be paid by the County to or for the benefit of the Contractor or its employees, agents, or servants by
reason of this Contract.
SECTION TWELVE
Other Contracts
The County reserves the right to undertake or award other contracts for additional work/services, and may
elect to complete portions of the Work/Services included in this Contract using its own forces or through
other contracts, and the Contractor shall fully cooperate with such other contractors, County employees and
Page 436 of 522
Page 32 of 105
6
carefully fit its own work/services to such work/services as may be directed by the County. The Contractor
shall not commit or permit any act by its forces or subcontractors which will interfere with the performance
of work/services by any other contractor or by County and or Department employees
SECTION THIRTEEN
Permits and Licenses
The Contractor shall, without additional expense to the County, be responsible for obtaining and
maintaining all necessary licenses and permits required by the State of South Carolina, a municipality or
the County or any other authority having jurisdiction. Prior to execution of a contract, the Contractor may
be required to provide a copy of its current applicable Contractor's License issued by the State of South
Carolina and business license issued by the County. Contractor's (and or any subcontractor's) L icense
Number, Person's Name and Business Name must all be shown on all required licenses.
SECTION FOURTEEN
Safety, Health, and Security Precautions
The Contractor shall take proper safety, health and security precautions to protect its workers and the
County's property, workers and the public at all times during the term of this Contract. All materials shall
be stored securely, protected from theft or damage.
SECTION FIFTEEN
Inspection and Acceptance
All Work shall be subject to inspection and test by the County at all reasonable times and places. The
Contractor shall, without charge, correct any workmanship found by the County not to conform to the
Contract requirements.
SECTION SIXTEEN
Conditions Affecting the Work
The Contractor shall be responsible for having taken steps reasonably necessary to ascertain the nature and
location of the Work, and the general and local conditions that can affect the Work or the cost thereof. Any
failure by the Contractor to do so will not relieve the Contractor from responsibility for successfully
performing the Work without additional expense to the County. The County assumes no responsibility for
any understanding or representations concerning conditions made by any of its officers o r agents prior to
the execution of this Contract, unless such understandings or representations by the County are expressly
stated in this Contract.
SECTION SEVENTEEN
Cleanup Work: Repair of Damages
During the performance of the Work, the Contractor shall continuously keep County-provided work space
(the "Work Site") and areas adjacent thereto in an orderly condition, free and clear from debris and
discarded materials.
Contractor will restore or replace, when and as directed by the County, any public or private property
damaged or destroyed by Contractor's work, equipment or employees to a condition at least equal to that
existing immediately prior to the beginning of the Work.
Page 437 of 522
Page 33 of 105
7
SECTION EIGHTEEN
Damages
The Contractor expressly agrees that if the Work, or any part thereof, is not performed or completed in a
timely or professional manner in accordance with this Contract or any amendment thereto, the Contractor
and its sureties shall be liable to the County for actual damages that relate to the Contractor's failure to
perform or complete the Work in the manner described above. If actual damages are agreed to by the County
and the Contractor or awarded by the Court, the County shall have the right to deduct f rom and retain out
of monies, which may be then due or which may become due and payable to the Contractor, the amount of
such actual damages; and if the amount so retained by the County is not sufficient to pay in full such actual
damages, the Contractor and/or its sureties shall pay to the County the amount necessary to effect payment
in full of such actual damages.
SECTION NINETEEN
Suspension of Work
The Purchasing Director may order, in writing, the Contractor to suspend, delay, or interrupt all or any part
of the Work for such period of time as he may determine to be appropriate for the convenience of the
County. The County may suspend performance of its obligations under this Contract in good faith for the
convenience of the County or to investigate matters arising in the Work.
The Purchasing Director may order suspension of the Work in whole or in part for such time as he deems
necessary because of the failure of the Contractor to comply with any of the requirements of this Contract,
and the Contract's completion date shall not be extended on account of any such suspension of Work.
When the Purchasing Director orders any suspension of the Work under the paragraph above, the Contractor
shall not be entitled to any payment for Work with respect to the period during which such Work is
suspended and shall not be entitled to any costs or damages resulting from such suspension.
The rights and remedies of the County provided in this Section are in addition to any other rights and
remedies provided by law or under this Contract.
SECTION TWENTY
Modification of Contract
The County's Purchasing Director has the unilateral right to modify this Contract, within the general scope
of work described above and in Exhibit B, when the modification is in the best interest of the County,
provided however, the Contractor is given wri tten notice of any such modification and the County is
responsible for paying Contractor for any additional expenses incurred by the Contractor that relate to the
modification. Subject to the above, the Contractor shall immediately notify the County in wri ting of any
proposed adjustment in its fee and the schedule for performance. The Contractor is obligated to perform
the revised contract when so directed by the Purchasing Director, and the County is obligated to pay for the
work performed pursuant to the modification. No claim by the Contractor for an adjustment hereunder shall
be allowed if asserted after Final Payment under this Contract.
SECTION TWENTY-ONE
Termination
Page 438 of 522
Page 34 of 105
8
1. For Convenience
The Purchasing Director, by advance written notice, may terminate this Contract when it is in the
best interests of the County. If this Contract is so terminated, the Contractor shall be compensated
for all necessary and reasonable direct costs of performing the Work actually accomplished. The
Contractor will not be compensated for any other costs in connection with a termination for
convenience. The Contractor will not be entitled to recover any damages in connection with a
termination for convenience.
2. For Default
If the Contractor refuses or fails to perform the Work or any separable part thereof in a timely or
workmanlike manner in accordance with the Contract Documents, or otherwise fails, in the sole
opinion of the County, to comply with any of the terms and conditions of the Contract Documents
deemed, in the sole opinion of the County, to be material (including, without limitation, the
requirement that Contractor obtain and maintain in force all necessary permits), such refusal or
failure shall be deemed a default under this Contract.
In the event of a default under this Section, the County shall have the right to inform the
Contractor of the default and demand that the Contractor immediately deliver a plan to remedy
the default. If the Contractor does not respond with a timely or reasonably achievable plan, the
County may terminate forthwith this Contract by additional written notice to the Contractor. In
the event of such default, the advance notice period for termination is waived and the Contractor
shall not be entitled to any costs or damages resulting from a termination under this Section.
Whether or not the Contractor's right to proceed with the Work is terminated, it and its sureties
shall be liable for any damage to the County resulting from the Contractor’s default. Any
wrongful termination for default shall be deemed by the Parties a termination for convenience.
3. Termination for Non-Appropriation of Funds
The Purchasing Director, by written advance notice, may terminate this Contract in whole or in
part in the event that sufficient appropriation of funds from any source (whether a federal, state,
County or other source) are not made or sufficient funds are otherwise unavailable, in either case,
to pay the charges under this Contract. If this Contract is so terminated, the Contractor shall be
compensated for all necessary and reasonable direct costs of performing the Work actually
provided to the date of such termination. The Contractor will not be compensated for any other
costs in connection with a termination for non-appropriation. The Contractor will not be entitled
to recover any damages in connection with a termination for non-appropriation, including, but not
limited to, lost profits.
4. Rights Cumulative
The rights and remedies of the County provided in this Section are in addition to any other rights
and remedies provided by law or under this Contract.
SECTION TWENTY-TW0
Indemnification
Except for expenses or liabilities arising from the negligence or intentional acts of the County, the
Contractor hereby expressly agrees to indemnify and hold the County harmless against any and all expenses
Page 439 of 522
Page 35 of 105
9
and liabilities arising out of the negligent or intentionally wrongful performance, action or inaction of the
Contractor in conduct of this Contract, as follows:
For matters other than those arising from the rendering or failure to render professional services, the
Contractor expressly agrees to the extent that there is a causal relationship between its negligence, action
or inaction, or the negligence, action or inaction of any of its employees or any person, firm or corporation
directly or indirectly employed by the Contractor and any damage, liability, injury, loss or expense (whether
in connection with bodily injury or death or property damage) that is suffered by the County and/or its
officers or employees or by any member of the public, to indemnify and save the County and its officers
and employees harmless against any and all liabilities, penalties, demands, claims, lawsuits, losses,
damages, costs, and expenses arising out of the negligence, action or inaction of the Contractor, regardless
of whether such liabilities, penalties, demands, claims, lawsuits, losses, damages, costs and expenses are
caused in part by the County. Such costs are to include, without limitation, defense, settlement and
reasonable attorney's fees incurred by the County and its employees. This promise to indemnify shall
include, without limitation, bodily injuries or death occurring to the Contractor's employees and any person,
directly or indirectly employed by the Contractor (including, without limitation, any employee of any
subcontractor), the County's officers or employees, the employees of any other independent contractors, or
occurring to any member of the public. When the County s ubmits notice, the Contractor shall promptly
defend any aforementioned action.
For matters arising out of the rendering or failure to render professional services, the Contractor will
indemnify and save the County and its officers and employees harmless from and against all liabilities,
penalties, demands, claims, lawsuits, losses, d amages, costs and expenses arising out of or resultant from
any negligent act, error or omission of the Contractor in the rendering or failure to render professional
services under this Contract. Such costs are to include, without limitation, defense, sett lement and
reasonable attorneys' fees incurred by the County and its officers and employees. This promise to indemnify
shall include, without limitation, bodily injuries or death occurring to the Contractor's employees and any
person, directly or indirectly employed by the Contractor (including, without limitation, any employee of
any subcontractor), the County's officers or employees, the employees of any other independent contractors,
or occurring to any member of the public. When the County submits notic e of a claim that triggers the
indemnity, the Contractor shall promptly defend any aforementioned action.
The limits of insurance required in this Contract shall not limit the Contractor's obligations under this
Section. The terms and conditions contained in this Section shall survive the termination of the Contract or
the suspension of the Work hereunder. To the extent that any liabilities, penalties, demands, claims,
lawsuits, losses, damages, costs and expenses are caused in part by the acts of the County, the Contractor’s
obligations shall be reduced in proportion to the County's fault. The obligations herein shall also extend to
any actions by the County to enforce this indemnity obligation. The recovery of costs and fees all extend
to those incurred in the enforcement of this indemnity.
SECTION TWENTY-THREE
Gratuities and Kickbacks
Gratuities. It shall be unethical for any person to offer, give or agree to give any employee or former
employee, or for any employee or former employee to solicit, demand, accept, or agree to accept from
another person a gratuity or an offer of employment in connection with any decision, approval, disapproval,
recommendation, preparation or any part of a program requirement or a purchase request, influencing the
content of any specification or procurement standard, rendering of advice, investigation, auditing, or in any
other advisory capacity in any proceeding or application, request for ruling, determination, claim or
Page 440 of 522
Page 36 of 105
10
controversy, or other particular matter pertaining to any program requirement of a contract or subcontract,
or to any solicitation or proposal therefore.
Kickbacks. It shall be unethical for any payment, gratuity, or offer of employment to be made by or on
behalf of a subcontractor under a contract to the prime contractor, or to hire any subcontractor or any person
associated therewith, as an inducement for the award of a subcontract or order.
Violation of this clause may result in Contract termination.
SECTION TWENTY-FOUR
Labor: Subcontractors
No subcontracts shall be allowed without the prior written approval of the County. The Contractor shall not
contract with a proposed person or entity to whom the County has made reasonable and timely objections.
The Contractor shall not be required to contract with anyone to whom the Contractor has made reasonable
and timely objection.
The Contractor shall enforce strict discipline and good order among its employees and other persons
carrying out the performance of the Contract.
Employment of labor by the Contractor shall be effected under conditions which are satisfactory to the
County. The Contractor shall remove or cause to have removed from the project any employee or employees
who are considered unsatisfactory by the County.
The Contractor assumes the responsibility for assuring that its working forces are compatible with the
County employees and the Contractor is responsible for making itself aware of those forces. The Contractor
will furnish a competent representative who is to be kept available to represent the Contractor for the
purpose of receiving notices, orders and instruction. No substitutions shall be made of such Contractor’s
representative without the approval of the County and a replacement by someone with comparable, skills,
experience and talent.
SECTION TWENTY-FIVE
Assignment
The Contractor shall not assign in whole or in part the Contract without the prior written consent of the
County or its Assignee. The Contractor shall not assign any money due or that may become due to it under
said the Contract without the prior written c onsent of the County or its Assignee. Each Party binds itself,
its successors, assigns, executors, administrators or other representatives to the other Party hereto and to
successors, assigns, executors, administrators or other representatives of such other Party in connection
with all terms and conditions of the Contract.
SECTION TWENTY-SIX
Controlling Law
The laws of South Carolina shall govern this Contract. All litigation arising under this Contract shall be
litigated only in a nonjury hearing in the Court of Common Pleas, Fourteenth Judicial Circuit, Beaufort
County, South Carolina.
Page 441 of 522
Page 37 of 105
11
SECTION TWENTY-SEVEN
Entire Contract
This Contract constitutes the entire understanding and contract between the Parties hereto and supersedes
all prior and contemporaneous written and oral contracts between the Parties and their predecessors in
interest regarding the subject matter of this Contract. This Contract may not be changed, altered, amended,
modified, or terminated orally, except as specifically provided, and any such change, alteration,
amendment, or modification must be in writing and executed by the Parties hereto.
SECTION TWENTY-EIGHT
Severance
Should any part of this Contract be determined by a Court of competent jurisdiction to be invalid, illegal,
or against public policy, said offending Section shall be void and of no effect and shall not render any other
Section herein, nor this Contract as a whole, invalid. Any terms which, by their nature, should survive the
suspension, termination or expiration hereof shall be deemed to so survive.
SECTION TWENTY-NINE
Non-waiver
Any waiver of any default by either Party to this Contract shall not constitute waiver of any subsequent
default, nor shall it operate to require either Party to waive, or entitle either Party to a waiver of, any
subsequent default hereunder.
Page 442 of 522
Page 38 of 105
Page 443 of 522
Page 39 of 105
BEAUFORT COUNTY
PUBLIC FACILITIES COMMITTEE
AGENDA ITEM SUMMARY
ITEM TITLE:
RECOMMENDATION TO AWARD A CONTRACT TO APAC ATLANTIC, INC FOR THE SUNSET BLVD / MILLER DRIVE
ROADWAY RESURFACING AND TRAFFIC CALMING PROJECT ($739,873.48)
MEETING NAME AND DATE:
Public Facilities Committee September 21, 2026
STAFF RECOMMENDATION / COUNCIL OPTIONS:
Staff recommends approval to award contract to APAC Atlantic for the Sunset Blvd / Miller Drive roadway
resurfacing and traffic calming project ($739,873.48)
PRESENTER INFORMATION:
Bryan Bauer, Director of Engineering (5 min)
ITEM BACKGROUND:
This project is part of the 2018 Sales Tax Program and is governed by an encroachment permit between
SCDOT and Beaufort County. Project includes resurfacing of 0.35 miles of Sunset Boulevard (S-186) & Miller
Drive West (S-187) Project. (Sunset blvd from Sea Island Parkway to intersection of Miller Drive West and
Miller Drive West from Sunset Boulevard to Sam’s Point Road). Traffic calming installation within the project
roadways is also included within the scope of work.
FISCAL IMPACT:
The contract fee for materials and construction is $672,612.25. Staff recommend a contingency of 10%
($67,261.23) bringing the project requested budget to be $739,873.48. The funding for this project is from
Account No. 4705-80-0000-S4500-LIMP with a balance of $26,100,000
APPROVAL HISTORY:
Resolution 2025/46 Project redefined (by council) July 14, 2025
Page 40 of 105
Beaufort County, SC
Procurement
David Thomas, Director
PO Box 1228, Beaufort, SC 29902
EVALUATION TABULATION
IFB No. 082626
Sunset-Miller Resurfacing &Traffic Calming
RESPONSE DEADLINE: August 26, 2026 at 3:00 pm
Report Generated: Wednesday, August 26, 2026
SELECTED VENDOR TOTALS
Vendor Total
APAC Atlantic, Inc. $672,612.25
TABLE 1
APAC Atlantic, Inc.
Selected Line Item Description Quantity Unit of
Measure
Unit Cost Total
X 1031000 MOBILIZATION 1 LS $52,000.00 $52,000.00
X 1032010 BONDS AND INSURANCE 1 LS $5,000.00 $5,000.00
X 1050800 CONSTRUCTION STAKES, LINES & GRADES 1 EA $10,000.00 $10,000.00
X 2012000 CLEARING & GRUBBING WITHIN ROADWAY 1 LS $23,000.00 $23,000.00
X 2016010 LIMB TRIMMING 1 LS $60,000.00 $60,000.00
X 2025000 REMOVAL & DISPOSAL OF EXISTING ASPHALT PAVEMENT 180 SY $34.00 $6,120.00
X 2031000 UNCLASSIFIED EXCAVATION 31 CY $200.00 $6,200.00
X 2033000 BORROW EXCAVATION 6 CY $440.00 $2,640.00
Page 41 of 105
EVALUATION TABULATION
IFB No. 082626
Sunset-Miller Resurfacing &Traffic Calming
EVALUATION TABULATION
Invitation For Bid - Sunset-Miller Resurfacing &Traffic Calming
Page 2
APAC Atlantic, Inc.
Selected Line Item Description Quantity Unit of
Measure
Unit Cost Total
X 2081001 FINE GRADING 186 SY $23.00 $4,278.00
X 2091000 SELECT MATERIAL FOR SHOULDERS & SLOPES 100 CY $78.00 $7,800.00
X 4011004 LIQUID ASPHALT BINDER PG64-22 91 TON $800.00 $72,800.00
X 4012060 FULL DEPTH ASPH. PAV. PATCHING 6" UNIF. 500 SY $85.00 $42,500.00
X 4013110 MILLING EXISTING ASPHALT PAVEMENT 1.0" 4459 SY $5.50 $24,524.50
X 4013115 MILLING EXISTING ASPHALT PAVEMENT 1.5" 4877 SY $5.35 $26,091.95
X 4013990 MILLING EXISTING ASPHALT PAVEMENT (VARIABLE) 270 SY $52.00 $14,040.00
X 4020320 ASPHALT BASE COURSE - TYPE B 56 TON $200.00 $11,200.00
X 4030330 ASPHALT INTERMEDIATE COURSE TYPE C 33 TON $275.00 $9,075.00
X 4040340 ASPHALT SURFACE COURSE TYPE C 1268 TON $148.00 $187,664.00
X 6011000 TRAFFIC CONTROL 1 LS $71,000.00 $71,000.00
X 6051120 PERMANENT CONSTRUCTION SIGNS (GROUND MOUNTED) 240 SF $10.00 $2,400.00
X 6240010 4" WHITE SOLID LINES (PVT EDGE LINES) - FAST DRY PAINT 9288 LF $0.20 $1,857.60
X 6240015 8" WHITE SOLID LINES (CROSSWALK&CHANNELIZATION)-FAST DRY
PAINT
1848 LF $0.20 $369.60
X 6240020 12" WHITE SOLID LINES - FAST DRY PAINT 864 LF $0.30 $259.20
Page 42 of 105
EVALUATION TABULATION
IFB No. 082626
Sunset-Miller Resurfacing &Traffic Calming
EVALUATION TABULATION
Invitation For Bid - Sunset-Miller Resurfacing &Traffic Calming
Page 3
APAC Atlantic, Inc.
Selected Line Item Description Quantity Unit of
Measure
Unit Cost Total
X 6240025 24" WHITE SOLID LINES (STOP/DIAG LINES)-FAST DRY PAINT 600 LF $1.25 $750.00
X 6240110 4" YELLOW SOLID LINES (PVT. EDGE LINES) FAST DRY PAINT 402 LF $0.20 $80.40
X 6271010 4" WHITE SOLID LINES (PVT EDGE LINES) - THERMO. -90 MIL. 3096 LF $1.00 $3,096.00
X 6271015 8" WHITE SOLID LINES THERMOPLASTIC - 125 MIL. 616 LF $3.75 $2,310.00
X 6271020 12" WHITE SOLID LINES - THERMO. - 125 MIL. 288 LF $5.50 $1,584.00
X 6271025 24" WHITE SOLID LINES (STOP/DIAG LINES)-THERMO.-125 MIL. 200 LF $11.50 $2,300.00
X 6271074 4" YELLOW SOLID LINES (PVT. EDGE LINES) THERMO.-90 MIL. 6465 LF $1.00 $6,465.00
X 6301100 PERMANENT YELLOW PAVEMENT MARKERS BI-DIR.- 4"X4" 45 EA $12.50 $562.50
X 6510105 FLAT SHEET, TYPE III, FIXED SZ. & MSG. SIGN 134 SF $30.00 $4,020.00
X 6531210 U-SECTION POST FOR SIGN SUPPORTS - 3P 242 LF $12.00 $2,904.00
X 8100101 PERMANENT GRASSING FOR SMALL PROJECTS 1.02 ACRE $4,225.00 $4,309.50
X 8151201 HYDRAULIC EROSION CONTROL PRODUCT (HECP) - TYPE 1 0.09 ACRE $12,500.00 $1,125.00
X 8153000 SILT FENCE 381 LF $6.00 $2,286.00
Total $672,612.25
VENDOR QUESTIONNAIRE PASS/FAIL
Page 43 of 105
EVALUATION TABULATION
IFB No. 082626
Sunset-Miller Resurfacing &Traffic Calming
EVALUATION TABULATION
Invitation For Bid - Sunset-Miller Resurfacing &Traffic Calming
Page 4
Question Title APAC Atlantic, Inc.
Certification Pass
Contact information of authorized representative? Pass
Please Provide Licenses and Certificate of Insurance Pass
100% Labor and Material Payment Bond Pass
Bidder Confirmation Pass
Communications Pass
Are you submitting this bid as a local vendor? Pass
Local Vendor Preference - Participation Affidavit Pass
Non-Collusion Affidavit of Prime Bidder Pass
Will you be using subcontractors? Pass
Non-Collusion Affidavit of Subcontractor Pass
Certification By Contractor Regarding Non-Segregated Facilities Pass
Business Organization
Type of Business Organization: Pass
If you selected "Other" for your type of business, please explain: Pass
If applicable, please provide name of partners and additional information
below:
Pass
If your agency is a Corporation: Pass
Are you a Subchapter S Corporation? Pass
Please provide Subchapter S Shareholders: No Response
If individually owned: Pass
Have you ever operated under another name? Pass
Page 44 of 105
EVALUATION TABULATION
IFB No. 082626
Sunset-Miller Resurfacing &Traffic Calming
EVALUATION TABULATION
Invitation For Bid - Sunset-Miller Resurfacing &Traffic Calming
Page 5
Question Title APAC Atlantic, Inc.
Please provide all other business names and addresses of principal place of
business for each business:
Pass
Bonding
Bid Bond Pass
Please provide the Bonding information: Pass
Do you intend to use any alternative form of security Pass
Indicate the form of security you intend to use and the name, address, point of
contact, and telephone number of the banks, savings and loan, or surety you
intend to use. (NOTE: Prequalification will not assure acceptance of any form
of security.)
No Response
Have any Performance or Payment Bond claims ever been paid by any surety
on behalf of your organization?
Pass
State the name of the project(s); the date; the name, address, telephone
number, and contact person for the claimant; the surety satisfying the claim;
the size of the claim; and the circumstances giving rise to the claim.
No Response
Have you ever arbitrated or litigated a claim with an Owner, Architect, or
Engineer in the last five years?
Pass
State the name of the project(s); the date; the name, address, telephone
number, and contact person for the claimant; the surety satisfying the claim;
the size of the claim; and the circumstances giving rise to the claim. (Provide
attachments if necessary.)
No Response
Have you or any officer, partner, or owner of your organization, in any state or
territory of the United States, or with respect to any agency of the Federal
government:
In the last in the last five years, received any fines or citations for building code
violations which were unrelated to design?
Pass
Page 45 of 105
EVALUATION TABULATION
IFB No. 082626
Sunset-Miller Resurfacing &Traffic Calming
EVALUATION TABULATION
Invitation For Bid - Sunset-Miller Resurfacing &Traffic Calming
Page 6
Question Title APAC Atlantic, Inc.
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
Ever been found to be guilty of charges relating to conflicts of interest: Pass
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
Ever been convicted on charges related to any criminal activity relating to
construction means, methods, or techniques; bidding or bid rigging; or
bribery?
Pass
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
In the last five years, been found guilty of any minority contracting law
violations?
Pass
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
In the last five years, pleaded no contest in any criminal proceeding related to
contracting?
Pass
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
Ever been disbarred from doing Federal, state, or local government work for
any reason?
Pass
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
Ever been terminated on a contract due to your default? Pass
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
In the last five years, paid liquidated damages for being late on a project? Pass
Page 46 of 105
EVALUATION TABULATION
IFB No. 082626
Sunset-Miller Resurfacing &Traffic Calming
EVALUATION TABULATION
Invitation For Bid - Sunset-Miller Resurfacing &Traffic Calming
Page 7
Question Title APAC Atlantic, Inc.
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
In the last five years, been subject to tax collection proceedings? Pass
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
In the last seven years, filed for bankruptcy? Pass
Provide the name, address, telephone number, contact person, and
circumstances relating to the question.
No Response
Under what chapter of bankruptcy did you file? No Response
If you filed under Chapter 11 Reorganization, how long did you operate under
this status?
No Response
Are you operating under Chapter 11 status now? No Response
Safety
Have you, in the last three years, been cited for willful violations for failure to
abate, or for repeated violations, by the United States Occupational Safety and
Health Administration or by the South Carolina Occupational Safety and Health
Administration or by any other governmental body?
Pass
State date, name, address, telephone number, and contact person for agency
issuing citation and the nature of the violation. Also, advise the amount of
fines paid, if any. Provide attachments if necessary.
No Response
List your worker’s compensation experience modifier for the last three years. No Response
References
Provide at least two references from each industry group listed. Provide other
references as requested. Provide current names, addresses, telephone
numbers, and contacts.
Pass
Page 47 of 105
EVALUATION TABULATION
IFB No. 082626
Sunset-Miller Resurfacing &Traffic Calming
EVALUATION TABULATION
Invitation For Bid - Sunset-Miller Resurfacing &Traffic Calming
Page 8
Question Title APAC Atlantic, Inc.
Certification regarding Debarment, Suspension, Ineligibility, and Voluntary
Exclusion:
The contractor certifies: Pass
Explain fully if it has been involved in any litigation involving performance. No Response
Small and Minority Business Participation Program
Are you a Small or Minority Business ? Pass
Upload your Small/Minority Documentation No Response
Are you self-performing 100%? Pass
Self-Performing 100% Affidavit No Response
Good Faith Agencies Distribution List Pass
Page 48 of 105
Determination of Price Reasonableness for Solicitation
Procurement Services Department
Solicitation Details
Date/Time:*
Aug 31, 2026 3:24 PM
Preparer:*
Sloan, Robert
From:*
Sloan, Robert
Department:*
Engineering
Solicitation Number:*
IFB - 082626
Purpose:*
Sunset Blvd / Miller Drive Resurfacing and traffic calming
Background
Describe the relevant procurement, including a brief description of the product/service/scope of work.*
Resurfacing of 0.35 miles of Sunset Boulevard (S-186) & Miller Drive West (S-187) Project. ( Sunset blvd from Sea Island Parkway to the intersection of Miller Drive West and Miller Drive West from Sunset Boulevard to Sam’s Point Road). “Traffic calming” installation within the project roadways is also included within the Scope of Work.
State procurement’s significance to the project or County operations.*
This project is part of the 2018 Sales Tax Program and is governed by an intergovernmental agreement and encroachment permit between SCDOT and Beaufort County.
Outline the procurement method utilized for this contract: (IFB, RFP, RFQ, Quotes).*
On July 24, 2026 Beaufort County published an invitation to bid (IFB 082626) . One bid was received by the deadline of August 26, 2026 and was within expected project cost estimates as determined by a qualified engineering and construction consultant (ICE).
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 1/5
Page 49 of 105
Price Analysis
Summarize the bid (s)/quotes (s) received with their respective amounts.*
One bid submittal was received from APAC Atlantic Inc. Total Bid was $672,612.25 as compared to Engineers pre-bid estimate of $705,869.64
If applicable: note any previous price history for similar procurements.
Beaufort County has used APAC Atlantic previously and have achieved satisfactory results.
Comparisons with substantially similar items.*
Consultant J. Bragg evaluated the bid as compared to projects of similar scope and size.
Sales of the same item to other purchasers.*
substantially similar pricing
Analysis of the cost elements (e.g. labor rate and estimated hours, material rates, indirect costs, reasonable
profit)*
project was bid by unit rates
9/1/26, 4:20 PM Nintex Forms for SharePoint Lists
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 2/5
Page 50 of 105
List and explain the benchmarks, market analysis, or other data sources used to evaluate price fairness.*
pricing within the ranges of similar project work
Justification of Acceptance of Single Proposal/Bid
Consideration of re-solicitation?
Yes No
Consideration of reasons for a single applicant?
Yes No
Explain:
Price proposal was within the expected costs of the project as bid.
Consideration of reasonable search for qualified applicants?
Yes No
Explain:
Project was put out for public bid.
Cost Analysis (if applicable)
Detail the cost elements (labor, materials, overhead, etc.) provided by the supplier or contractor.
9/1/26, 4:20 PM Nintex Forms for SharePoint Lists
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 3/5
Page 51 of 105
Provide an analysis of the necessity and reasonableness of each cost element.
Vendor's Pricing Strategy (optional)
What is the vendor's pricing strategy?
Department Head Decision
Comments
J. Bragg, the 2018 Sales Tax Program manager, has evaluated the bid and recommended approval. The contractors bid is approximately 7% less than the engineers estimate.
Approve Disapprov
e
Department Head Signature
Bauer, Bryan
Date/Time
Sep 1, 2026 8:12 AM
Purchasing Decision
9/1/26, 4:20 PM Nintex Forms for SharePoint Lists
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 4/5
Page 52 of 105
Comments
Approve Disapprov
e
Purchasing Signature
Thomas, Dave
Date/Time
Sep 1, 2026 8:35 AM
9/1/26, 4:20 PM Nintex Forms for SharePoint Lists
https://wus-srv-ufo.nintexo365.net/runtime/aad?ctype=0x010067538D3D0D6C2243A7E3698E8EFB131400D4512833729ED54A91C809F9DD964505… 5/5
Page 53 of 105
Page 54 of 105
Page 55 of 105
Page 56 of 105
Page 57 of 105
Page 58 of 105
Page 59 of 105
Page 60 of 105
Page 61 of 105
Page 62 of 105
Page 63 of 105
Page 64 of 105
Page 65 of 105
BEAUFORT COUNTY
PUBLIC FACILITIES COMMITTEE
AGENDA ITEM SUMMARY
ITEM TITLE:
APPROVAL OF A TASK ORDER TO HDR ENGINEERING, INC FOR THE PRELIMINARY ENGINEERING FOR
ALTERATIONS TO THE CHOWAN CREEK BRIDGE APPROACHES ($212,630)
MEETING NAME AND DATE:
Public Facilities Committee September 21, 2026
STAFF RECOMMENDATION / COUNCIL OPTIONS:
Staff recommends approval of task order to HDR Engineering, Inc. for the preliminary design and engineering
of alterations to the Chowan Creek Bridge in the amount of $212,630.
PRESENTER INFORMATION:
Bryan Bauer, PE - Director of Engineering (5 min)
ITEM BACKGROUND:
The Chowan Creek bridge has been noted as a choke point along US 21 on St. Helena Island in emergency
situations. The bridge was also identified in the Beaufort County Roadway Vulnerability Study completed in
2025. The project has been included in the 2026 Transportation Sales Tax referendum. This task order will
enable the County to begin preliminary engineering and design for alterations to provide congestion relief
during emergency situations. The concept will be to restipe the bridge to allow for a center median and widen
the approaches on both sides for the additional lane width requirements.
HDR Engineers, Inc was one of ten consultants selected in the competitively bid RFQ # 032626 On-Call
Transportation Roadway Design.
FISCAL IMPACT:
The fee for HDR Engineering, Inc. for the preliminary design and engineering of alterations to the Chowan
Creek Bridge is $193,300. Staff recommends a 10% contingency of approximately $19,330 for a total of
$212,630. Funding for this project is from TAG account number 2342-30-0000-51160 with a balance of
$1,868,672.00.
APPROVAL HISTORY:
Page 66 of 105
hdrinc.com
1201 Main Street, Suite 800, Columbia, SC 29201-3271
(803) 509-6600
September 3, 2026
Bryan Bauer
Director of Engineering
Beaufort County Engineering
100 Ribaut Road
Beaufort, SC 29902
Re: US 21 @ Chowan Creek Preliminary Plans
2026 On-Call Transportation Roadway Design
Task Order #1
HDR # 10473069
Dear Mr. Bauer:
HDR Engineering, Inc. (HDR) appreciates this opportunity to provide Beaufort County with a proposal to
provide engineering services associated with the preliminary plans for the US21 at Chowan Creek
widening. Based on the scope of services, deliverables and schedule outlined below, HDR, and its sub-
consultant will survey the project, develop preliminary engineering plans, and assist with moving forward.
The Scope of Services is outlined below:
PURPOSE
Beaufort County wishes to obtain preliminary plans for US 21 at Chowan Creek . These modifications
include but are not limited to adding a center two way left turn lane (TWLTL) from 750’ south of Chowen
Creek Bluff to 500’ north of Warsaw Road. This will include re-striping the existing 510’ long bridge. HDR
will coordinate surveys, study the proposed typical section, and develop preliminary plans. Assumptions for
the project are as follows:
• Preliminary plans will include typical elements from the SCDOT Roadway Design Manual,
• Utility coordination will include early utility coordination and contact, but no SUE will be acquired.
• Environmental studies will be limited to wetland delineation to evaluate potential impacts.
• Typical section studies will be performed to determine lane widths, shoulder widths, and drainage
alternatives. Potential design exceptions or variances will be noted but not acquired.
• No geotechnical investigations will be conducted regarding these plans.
• Survey will occur for 75’ from the existing centerline for a length of 75’. No underwater survey will
be conducted.
• Plans will be provided to County review 3 months from NTP.
For this proposal, HDR Engineering Inc. will be referred to as the CONSULTANT. McKim and Creek will be
referred to as the SUBCONSULTANT . The widening plans will be referred to as the PROJECT , and
Beaufort County, SC will be referred to as the CLIENT.
Docusign Envelope ID: B08FEC3B-167F-8A95-80B0-151ED0500083
Page 67 of 105
Page 2 of 5
Scope of Services
1. PROJECT MANAGEMENT
The CONSULTANT will coordinate with the CLIENT to prepare a schedule for the proposed project.
Coordination meetings will occur monthly during the life of the project. The CONSULTANT will coordinate
with the CLIENT for ny specific design standards. Invoicing will occur monthly. The CONSULTANT will
coordinate with the SUBCONSULTANT for survey needs.
2. SURVEYS
Field surveys will be performed to determine accurate elevations and locations of existing facilities, e.g.,
roadways, bridges, culverts, utilities, and other physical feature needed for design and to provide ground
controls for all design surveys. Surveys along the entire project will include the items listed below:
1. All surveys will be based on SC State Plane Coordinate System using NAD-83 and
elevations on NAVD 1988 datum.
2. Survey Control Points shall be distributed throughout the project at 500-foot intervals.
Survey control points shall be inter-visible from two other survey control points. A
minimum of 4 survey control points shall be established along the survey corridor and
shall be established outside the physical limits of disturbance.
3. Survey existing centerline alignment of US-21.
4. Cross-sections will be taken at 50’ intervals from the existing roadway centerline to 75’
left and right for 3,000’ US-21.
5. Locate all planimetric features such as edge of pavement, structures, utilities, residential
trees, residential shrubs, tree lines, streams, fences, driveways, and mailboxes from the
centerline to 75’ left and right. Locate all specimen trees as required by the County.
Surveyor shall contact PUPS 811 design location service to mark all utility lines.
The surveyor will be provided with existing utility and right of way plans prior to
beginning survey work if available. Surveyor shall locate marked existing utilities
and utility ROW based on plans, if provided.
6. Locate all drainage and sanitary sewer structures from the centerline to 75’ left and right.
Locate the system upstream, whether a ditch or pipe. All pipes shall be located and
elevations, types, and size shall be provided.
7. Horizontally and vertically locate all potential outfall drainage ditches and streams. At all
outfalls obtain cross-sections 100 feet upstream and/or 100 feet downstream using a 40’
corridor (20’ on either side of the ditch centerline).
8. Public records research of all properties (approximately 10 tracts) that may be impacted
by the construction of the proposed project will be conducted. Where available in the
public record, the current owner’s name, address, tax map number, total area of parcel,
and corresponding Plat Book with page and/or Deed Book with page Number(s) for the
property owners as listed on the Tax Assessor’s records will be provided. This
information will be provided to the COUNTY in the form of a Microsoft Excel, with one
copy each of the electronic and hardcopy versions of the file. Search and survey all
detectable property corners and pins of tracts that may be impacted. The location and
bearings of property lines intersecting the proposed right of way will be determined by
surveyed corners or by data from available records where corners cannot be found.
Information used to compute property lines will be limited to data that is part of the public
Docusign Envelope ID: B08FEC3B-167F-8A95-80B0-151ED0500083
Page 68 of 105
Page 3 of 5
record. This property strip map is considered a partial survey and does not constitute a
full boundary survey.
9. An electronic property strip map which will include the names of property owners and
their tax map number and will be prepared in Openroads format.
3. ROADWAY DESIGN
Design will be completed in accordance with the policies and practices of SCDOT as described in the
SCDOT Roadway Design Manual and Standard Specifications for Road Construction. Items not covered
by these sources will be as provided by the American Association of State Highway and Transportation
Officials (AASHTO).
Plans will be developed at a 1”=20’ scale.
1. Preliminary Plans
Preliminary plans will be developed by the CONSULTANT to illustrate the alignment, grades, cross
sections, construction limits, relevant dimensions, and location of existing features and proposed
improvements. A typical section of the proposed improvements will be pr epared to provide the
standard section of improvement, pavement types and application rates, cross slopes, and limits
of improvement. The plan, profile, and cross section sheets will show information necessary to
permit construction stakeout and to indicate and delineate details necessary for construction.
2. Design Refinement & Comment Resolution
Comments generated by the CLIENT’s review of the preliminary plans will be consolidated into a
matrix to track the resolution of comments. The CONSULTANT will revise the project design and
resubmit the plans in accordance with the accepted resolution to each comment generated by the
CLIENT.
Deliverables: Preliminary plans will be provided electronically in PDF format.
4. DRAINAGE DESIGN
The CONSULTANT will develop drainage calculations, as necessary to facilitate preliminary plans. The
stormwater design will be prepared in accordance with the SCDOT Requirements for Hydraulic Design
Studies manual dated May 26, 2009.
The CONSULTANT will review the stormwater runoff for quantity and quality and make recommendations
based on potential impacts. The CONSULTANT will not include a stormwater permit application.
The locations of proposed drainage features will be shown on the roadway plan sheets.
Deliverables: Drainage calculations and plans will be provided in PDF format.
5. ENVIRONMENTAL
The CONSULTANT will not include obtaining any permits needed to construct the project. Only wetland
delineation and threatened and endangered (T&E) habitat surveys will occur. GPS located wetlands will
be shown on the plans.
Deliverables: Wetland delineation survey and T&E Survey Memo.
Docusign Envelope ID: B08FEC3B-167F-8A95-80B0-151ED0500083
Page 69 of 105
Page 4 of 5
6. UTILITY COORDINATION
Preliminary utility coordination will occur with the appropriate utility owners by contacting them
and reviewing documents provided. We assume that up to five utilities will be within the project
limits. They will be contacted during the development of preliminary design plans. We assume
that up to two field visits will be necessary during preliminary utility coordination. A preliminary
report containing an assessment of the effected utility owners and a review of their possible prior
rights will be submitted to the CLIENT.
Deliverables: Preliminary Utility Contact Report will be provided in PDF format.
Items Not Included In Scope
• Geotechnical Engineering
• Pavement Design
• Subsurface Utility Engineering (SUE)
• Utility Relocation Design
• Environmental Resource Surveys (Haz-Mat, Cultural Resources)
• Wetland Permitting
• Right of Way Staking
• Right of Way Acquisition
• Construction Engineering and Inspection
• Permitting Fees
SCHEDULE
Survey will be completed within one ( 1) month of NTP. Submittal of the preliminary plans to the CLIENT
will be two (2) months from completion of the survey.
FEE
HDR proposes to perform the tasks described in this proposal as outlined below:
Task 1 PROJECT MANAGEMENT $ 29,900.00 (122 manhours)
Task 2 SURVEYS $ 39,800.00 (16 manhours)
Task 3 ROADWAY DESIGN $ 67,700.00 (340 manhours)
Task 4 DRAINAGE DESIGN $ 30,500.00 (204 manhours)
Task 5 ENVIRONMENTAL $ 9,200.00 (66 manhours)
Task 6 UTILITY COORDINATION $ 16,200.00
(64 manhours)
Total
$ 193,300.00 (812 manhours)
Docusign Envelope ID: B08FEC3B-167F-8A95-80B0-151ED0500083
Page 70 of 105
Page 5 of 5
Once again, HDR appreciates this opportunity to provide assistance to the Beaufort County. We look
forward to working with you on this project. Please call 803-509-6626 with any questions or comments
you may have.
Sincerely,
HDR ENGINEERING, INC.
__________________________
Phillip Hutcherson, P.E.
Project Manager
________________________
Jennifer Mustar, P.E. VP
South Carolina Area Manager
Docusign Envelope ID: B08FEC3B-167F-8A95-80B0-151ED0500083
Page 71 of 105
Page 1 of 2
1. CONTRACT NAME AND NUMBER 2. TASK ORDER NO.: 3. EFFECTIVE DATE:
On Call Transportation Engineering
Services (Design) RFQ 032626
FY27 Chowen Creek September 3, 2026
TASK ORDER FOR SERVICES
4. CONTRACTOR NAME, ADDRESS, PHONE, AND EMAIL:
HDR
1201 Main Street, Suite 800, Columbia, SC 29201
803-509-6600
Phillip Hutcherson
Phillip.Hutcherson@hdrinc.com
5. ISSUED BY:
Beaufort County Procurement Services
PO Drawer 1228
Beaufort, SC 29901
For Questions Contact:
Gillian Murray
Senior Buyer
(843) 255-2295
Email: gmurray@bcgov.net
6. PROJECT NAME/TITLE AND DESCRIPTION:
US 21 @ Chowen Creek Preliminary Plans
Task 1: Project Management
Task 2: Surveys
Task 3: Roadway Design
Task 4: Drainage Design
Task 5: Environmental
Task 6: Utility Design
7. OTHER PERTINENT INFORMATION OR SPECIAL CONSIDERATIONS:
This task order is issued pursuant to the Scope and Fee Proposal dated September 3, 2026 and attached.
8. PAYMENT TYPE:
Contractor will be paid on a percentage complete basis with the submission of monthly invoices
9. LIQUIDATED DAMAGES
N\A
10. NUMBER OF DAYS/MONTHS
TO COMPLETE PROJECT
3 Months after issuance of Notice to
Proceed. No work shall begin prior to
issuance of Notice to Proceed
11. TOTAL AWARD AMOUNT:
$193,300.00
12. Project Manager’s Name Bryan Bauer
Project Manager’s Email frederick.bauer@bcgov.net
Project Manager’s Phone 843-255-2706
Docusign Envelope ID: 0AEF5F96-6FDC-89E2-80E4-D8C2C9FD99B2
Page 72 of 105
Page 2 of 2
12. AUTHORIZED SIGNATURE FOR THE VENDOR:
a. SIGNATURE:
b. NAME/TITLE OF SIGNER:
c. DATE SIGNED:
13. AUTHORIZED SIGNATURE FOR THE COUNTY
a. SIGNATURE
b. NAME/TITLE OF SIGNER
c. DATE SIGNED
Docusign Envelope ID: 0AEF5F96-6FDC-89E2-80E4-D8C2C9FD99B2
9/4/2026
Jennifer G. Mustar Vice President
Page 73 of 105
BEAUFORT COUNTY
PUBLIC FACILITIES COMMITTEE
AGENDA ITEM SUMMARY
ITEM TITLE:
OMNIA CONTRACT AWARD FOR ST. HELENA ISLAND LIBRARY LED RETROFIT ($200,000).
MEETING NAME AND DATE:
Public Facilities Committee September 21, 2026
STAFF RECOMMENDATION / COUNCIL OPTIONS:
Staff recommends the approval of the Omnia contract for Graybar Electric in the amount of $200,000.
PRESENTER INFORMATION:
Ron Lewis, Senior Project Manager, 5 min.
ITEM BACKGROUND:
The interior lighting system at St. Helena Library is very complex and in need of repair; the parts are obsolete
and no longer available. Completing an LED lighting retrofit is the only solution available to restore the
interior lighting to working condition. Two local and one national vendors declined to provide a proposal due
to the complexity of the project. We were able to secure one proposal with Graybar through an Omnia based
contract.
FISCAL IMPACT:
The contract amount is $189,000, staff recommends $11,000 for contingency; bringing the total cost to
$200,000. The funding source will be the 2025 GL Bond GL account # 4013-80-1310-54420 which has the
account balance of $100,000; and Repairs to Buildings GL account # 1000-30-1310-51130 which has the
account balance of $3,000,000.
APPROVAL HISTORY:
N/A
Page 74 of 105
Omnia Contract
Qty
Type
Mfg
Model Number & Notes
Lead Time
1
INCLUDED
RETROFIT/UPGRADE
LIGHTING FIXTURES.
(INTERIOR). MATERI
ALS/LABOR/EQUIPM
ENT DISPOSAL
-
-
-
Omnia Contract Subtotal
$189,000.00
Grand Total
$189,000.00
Project Notes:
Note: this will be performed utilizing the Omnia Contract
Graybar to co-ordinate project upon award.
Dominion Rebate to be provided through Graybar and 100 % of rebate to be paid to Beaufort County .
Job Name :
St. Helena Library lighting Upfit
Quote Number :
485114-969412-1
Bid Date :
May 28, 2026
Expiration Date :
Jun 27, 2026
Quote Start
1
Page 75 of 105
General Terms & Conditions
Graybar Standard Terms and Conditions Apply. https://www.graybar.com/standard-terms-and-
conditions
Job Name :
St. Helena Library lighting Upfit
Quote Number :
485114-969412-1
Bid Date :
May 28, 2026
Expiration Date :
Jun 27, 2026
Quote Start
2
Page 76 of 105
Page 77 of 105
Page 78 of 105
Page 79 of 105
Page 80 of 105
Page 81 of 105
Page 82 of 105
Page 83 of 105
Page 84 of 105
Page 85 of 105
BEAUFORT COUNTY
PUBLIC FACILITIES COMMITTEE
AGENDA ITEM SUMMARY
ITEM TITLE:
RECOMMENDATION FOR APPROVAL OF A CHANGE ORDER WITH KIMLEY HORN FOR A PHASE 2
ENVIRONMENTAL SITE ASSESSMENT (ESA) ON THE LADYS ISLAND DRIVE TURN LANE AT RIBAUT ROAD
PROJECT ($42,350)
MEETING NAME AND DATE:
Public Facilities Committee September 21, 2026
STAFF RECOMMENDATION / COUNCIL OPTIONS:
Staff recommend approval of a change order with Kimley Horn for a Phase 2 ESA on the Ladys Island Drive at
Ribaut Road project. ($42,350)
PRESENTER INFORMATION:
Bryan Bauer, Director of Engineering (5 Min)
ITEM BACKGROUND:
The task order with Kimley Horn for design services of a right turn lane on Ladys Island Drive to Ribaut Road
requires right of way from the adjacent property where a gas station was previously operated. The Phase 1
Environmental Site Assessment found that contamination is likely, which requires a Phase 2 ESA to determine
the extent of the contamination and potential mitigation.
FISCAL IMPACT:
The change order for the Phase 2 ESA is $38,500. Staff recommends a 10% contingency of $3,850, bringing
the total approved budget increase to $42,350. Funding for this task order will be from Impact Fees North
account 2300-30-0000-54500-12303 with a balance of $4,900,000.00.
APPROVAL HISTORY:
The task order with Kimley Horn for design services of a turn lane on Ladys Island Drive at Ribaut was
approved by PFC on March 16, 2026.
Page 86 of 105
Page 5
kimley-horn.com 1080 Morrison Drive, Suite 240, Charleston, SC 29403 843-737-6390
access to all areas of the site and that the site reconnaissance shall be conducted as a single event.
Should an additional site reconnaissance be required due to access limitations, the additional site
reconnaissance shall be considered additional services.
We assume one day to complete the reconnaissance of the Subject Property.
Interviews
Consistent with ASTM E 1527-21, 10.5.2.3 and 10.5.4, Kimley-Horn will make a reasonable attempt
to conduct the following interviews:
1. Kimley-Horn will attempt to interview current and past owners, operators and occupants of
the property that have or are likely to have material information regarding uses, physical
characteristics, and the potential for recognized environmental conditions (RECs) at the
subject property consistent with ASTM E 1527-21 sections 10.5.1, 10.5.2, 10.5.2.1, 10.5.2.2,
and 10.5.4.
2. In the case of abandoned properties as defined in ASTM E 1527-21, 3.2.1, where there is
evidence of uncontrolled access or unauthorized uses, Kimley-Horn will attempt to interview
current neighboring or nearby property owners (ASTM E 1527-21, 10.5.5).
3. Kimley-Horn will attempt to interview one or more of the following state or local agencies:
a. Local fire department
b. Local health agency
c. Local environmental regulatory agency
Report Preparation
Upon completion of the tasks, Kimley-Horn will prepare a summary report of the results of the Phase I
ESA. Kimley-Horn will provide the report to the Client in electronic format (PDF). Kimley-Horn will
prepare a separate cover letter to accompany the Phase I ESA Report. The cover letter will include
recommendations based on the findings of the Phase I ESA.
Task 8 – Phase II Environmental Site Assessment (If Required)
The Subject Property has historically been used as a fuel station. As such, we assume that a Phase I
ESA may reveal evidence of recognized environmental conditions that would warrant completion of a
Phase II ESA to confirm whether localized contamination is present.
The following Phase II ESA scope of services is based on our current knowledge of potential
contamination concerns for the Subject Property. It may be necessary to adjust the scope of services
pending the results of the Phase I ESA. If that is the case, Kimley-Horn will discuss the proposed
changes and corresponding costs with the Client prior to initiating the Phase II ESA.
Soil and Groundwater Sampling
Kimley-Horn will collect representative soil and groundwater samples from the Subject Property to
determine whether historical activities have contributed to localized contamination. We assume up to
Page 87 of 105
Page 6
kimley-horn.com 1080 Morrison Drive, Suite 240, Charleston, SC 29403 843-737-6390
20 soil samples and 5 groundwater samples will be collected from the Site. The actual number of
samples to be collected from the Site will be contingent upon the findings of the Phase I ESA.
We will engage a drilling sub-consultant to install up to 20 soil borings and 5 temporary monitoring
wells to facilitate the soil and groundwater sampling. The soil borings and monitoring wells will be
installed using direct-push technology (DPT). The soil borings will be advanced to a maximum depth
of 12 feet below land surface (bls). Continuous soil samples will be collected from the land surface to
the termination depth at each borehole. The soil samples will be screened on two-foot intervals for the
presence of volatile organic compounds using a photoionization detector (PID). One soil sample will
be retained for laboratory analysis from each soil boring based on the results of the PID screening.
Lithologic logs will be prepared for each soil boring.
The temporary monitoring well will be installed to a maximum depth of 30 feet bls, depending on the
depth at which groundwater is encountered. If groundwater is not encountered within 30 feet of the
land surface, monitoring wells will not be installed on the property. The temporary monitoring wells
will be constructed of 1-inch diameter, schedule 40 PVC casing with 10-feet of machine slotted well
screen. Individual monitoring well construction logs will be prepared for each temporary monitoring
well. Kimley-Horn will use low-flow techniques to collect groundwater samples from each monitoring
well.
Pursuant to state regulations, Kimley-Horn will notify and obtain approval from the South Carolina
Department of Environmental Services (SCDES) to install and sample temporary monitoring wells on
the Subject Property. The Client acknowledges that in accordance with state regulations, Kimley-Horn
will forward copies of the well construction logs and groundwater analytical data to SCDES upon
completion of the Phase II ESA.
All field activities will be performed in general accordance with the SCDES Standard Operating
Procedures (SOP). The northing and easting coordinates and approximate land surface elevation of
the soil borings and temporary groundwater monitoring wells will be surveyed with a handheld GPS
unit.
The soil and groundwater samples collected from the Subject Property will be analyzed for one or
more of the following parameters:
x Arsenic, barium, cadmium, chro mium, lead, mercury, selenium, and silver (8 RCRA Metals) by
EPA Method 6010 and 7000 series
x Volatile organic compounds (VOCs) by EPA Method 8260
x Semi-volatile organic compounds (SVOC) by EPA Method 8270
If the groundwater screening samples are turbid, Kimley-Horn will collect both total and dissolved
metals samples for analysis. The dissolved metals samples will be filtered by the laboratory. The soil
and groundwater samples collected by Kimley-Horn will be analyzed by a laboratory accredited by the
NELAC Institute and certified by the state of South Carolina. Sample analysis is anticipated to be on
the laboratories normal 10 to 14-day turnaround time.
All soil borings and temporary monitoring wells will be abandoned following the completion of the
sampling activities. The soil borings will be abandoned using soil cuttings and bentonite. Similarly, the
Page 88 of 105
Page 7
kimley-horn.com 1080 Morrison Drive, Suite 240, Charleston, SC 29403 843-737-6390
temporary monitoring well casings and screens will be removed from the ground and the
corresponding boreholes will be abandoned with soil cuttings and hydrated bentonite.
Phase II ESA Report
Kimley-Horn will prepare a Phase II ESA Report upon receipt of the soil and groundwater analytical
data from the laboratory. The purpose of the Phase II ESA is to determine whether the historical use
of the Subject Property have contributed to localized soil or groundwater impacts. As such, the report
is not intended to delineate the full extent of contamination, if present. The report will include a
summary and interpretation of the analytical data. The Phase II ESA report will include the following:
x Written narrative of the sampling methodology
x Summary of the data quality objectives
x Tabular summaries of the soil and analytical data
x An interpretation of the analytical data
x Maps depicting the sample locations and analytical data
x Soil boring logs
x Monitoring well construction logs
x Laboratory data sheets
The Phase II ESA report will include our recommendations based on the results of the soil and
groundwater quality data. We will provide the client with one copy of the report in electronic (PDF)
format.
Task 9 – Meetings and Coordination
Kimley-Horn will coordinate, facilitate, and document up to four (4) meetings with Beaufort County
Staff. The meetings are assumed to be in person at Beaufort County offices and consist of two (2)
Kimley-Horn personnel.
Task 10 – Survey and Subsurface Utility Exploration (SUE) – By Others
At the direction of the Client, Kimley-Horn will contract with Atlas to provide survey and SUE
coordination services. Kimley-Horn will coordinate and manage the effort of the survey and SUE
subconsultant(s) as described in the attached proposals provided by the subconsultant(s). Kimley-
Horn will endeavor to coordinate the subconsultants’ scope of work, schedules, and provide a cursory
review of their deliverables on behalf of the Client.
The Client/Owner acknowledges that Kimley-Horn will not be reviewing the work product of
Subconsultant(s) in detail and will not be liable for it in any way. If the Client has any future claim
related to these services, Client will pursue Subconsultant directly and not Kimley-Horn.
Task 11 – Utility Coordination – By Others
At the direction of the Client, Kimley-Horn will contract with Triton Utility Coordinating to provide utility
coordination services. Kimley-Horn will coordinate and manage the effort of the utility coordination
subconsultant(s) as described in the attached proposals provided by the subconsultant(s). Kimley-
Page 89 of 105
Page 9
kimley-horn.com 1080 Morrison Drive, Suite 240, Charleston, SC 29403 843-737-6390
FEE AND BILLING
Kimley-Horn will perform the services listed above for the fee below. All permitting, application, and
similar project fees will be paid directly by the Client.
Task Fee Type Fee
Task 1 – Capacity Analysis Lump Sum $5,525
Task 2 – Roadway Design Lump Sum $25,985
Task 3 – Drainage Design and Report Lump Sum $18,525
Task 4 – Signal Design Lump Sum $11,675
Task 5 – Permitting Lump Sum $18,275
Task 6 – Opinion of Probable Construction Cost (OPCC) Lump Sum $3,335
Task 7 – Phase 1 ESA Lump Sum $5,620
Phase 1 ESA Expenses Lump Sum $6,500
Task 8 – Phase 2 ESA (If Required) Lump Sum $13,500
Allowance for Phase II ESA Drilling and Laboratory
Subcontractor Expense
Lump Sum $25,000*
Task 9 – Meetings and Coordination Lump Sum $7,175
Task 10 – Survey and SUE - by Others Lump Sum $21,900
KH Survey subconsultant Coordination Lump Sum $3,730
Task 11- Utility Coordination – by others Lump Sum $20,000
KH Utility subconsultant Coordination Lump Sum $2,960
Total Without Task 8 $151,205
Total with Task 8 $189,705
*An allowance has been provided for general budgetary purposes for the laboratory and drilling sub-
consultant expense for the Phase II scope of work. Actual fees will be dependent on the number of
borings needed. Once those have been identified, Kimley-Horn will coordinate with the boring
subconsultant for a proposal for the exact scope of work. Kimley-Horn will then add a 15% markup to
cover administrative efforts. The Client can elect to contract with the boring subconsultant directly for
this scope of work to avoid this markup.
Lump sum fees will be invoiced monthly based upon the overall percentage of services performed.
Payment will be due within 25 days of your receipt of the invoice and should include the invoice
number and Kimley-Horn project number.
CLOSURE
In addition to the matters set forth herein, our Proposal shall include and be subject to, and only to, the
terms and conditions in the attached modified Standard Provisions, which are incorporated by
Page 90 of 105
Phase I Environmental Site Assessment
Lady’s Island Site
Project No. 012716030
5
1.0 EXECUTIVE SUMMARY
Kimley-Horn and Associates, Inc. (Kimley-Horn) was retained by Beaufort County Engineering (the “Client”)
to conduct a Phase I Envi ronmental Site Assessment (ESA) for an approximate 0.6-acre parcel (PIN #
R110 009 000 0031 0000) located within Lady’s Island, Beaufort County, South Carolina (referred to herein
as the “Site” or “Subject Property”). This Phase I ESA was performed in general accordance with (1) the
United States Environmental Protection Agency (USEPA) Standards and Practices for All Appropriate
Inquiries (AAI), 40 CFR Part 312 and (2) guidelines established by the American Society for Testing and
Materials (ASTM) in the Standard Practice for Environmental Site Assessments: Phase I Environmental
Site Assessment Process/Designation E1527-21 (ASTM Standard Practice E1527-21). The ESA was
conducted under the supervision or responsible charge of Mr. Ben Lawson, Environmental Professional.
The Phase I ESA summary is provided below. Specific details were not included or fully developed in this
section, and the Phase I ESA must be reviewed in its entirety for a comprehensive understanding of the
results. This report represents our services as of the report date and constitutes our final document; its text
may not be altered after final issuance. Findings in this report are based upon the Subject Property’s current
utilization; information derived from the most recent reconnaissance and from other activities described
herein; such information is subject to change. Certain indicators of the presence of hazardous substances
or petroleum products may have been latent, inaccessible, unobservable, or not present during the most
recent reconnaissance and may subsequently become observable (such as after property renovation or
development). Further, these services are not to be construed as legal interpretation or advice.
Viability of this report is subject to ASTM E1527-21 Section 4.6. As listed in Section 4.6 of the ASTM
Standard Practice E1527-21, an environmental site assessment meeting or exceeding this practice is
presumed to be viable when it is conducted within 180 days prior to the date of acquisition or transaction
of the Subject Property.
Table 1.0-1 Summary Phase I ESA Component Dates
Component Date
Interviews
User Questionnaire was sent to Mr. Bryan Bauer and Ms. Pamela Bernard with
Beaufort County, on June 9, 2026. Ms. Bernard completed the User
Questionnaire on June 26, 2026
Property Owner Interview Questionnaire was sent to Mr. Bryan Bauer and Ms.
Pamela Bernard with Beaufort County, on June 9, 2026, for coordination with
the current property owner. Ms. Bernard completed the Property Owner
Interview Questionnaire on June 26, 2026.
Review of Government Records May 19, 2026
Visual Inspection May 20, 2026
Declaration by Environmental
Professional July 2, 2026
Subject Property Description and Use
The Subject Property is located in Lady’s Island in Beaufort County, South Carolina. The Site is currently
utilized as a cleared and graded lot.
The approximately 0.6-acre Subject Property is composed of one parcel (PIN#: R110 009 000 0031 0000)
currently owned by Drayton-Parker Companies, LLC. Information was obtained from the Beaufort County
Parcel Search (accessed June 1, 2026) and is attached in Appendix F. However, according to the current
property owner interview, the parcel is owned by Beaufort County. The Subject Property is currently zoned
as T4 - Urban Center under the Town of Porty Royal. The Subject Property is located within the Beaufort,
Page 91 of 105
Phase I Environmental Site Assessment
Lady’s Island Site
Project No. 012716030
6
Parris Island, and Fort Fremont, South Carolina United States Geological Survey (USGS) 2024, 7.5-minute
topographic quadrangle maps presented in Figure 2.
Historical Information
Historical aerial photographs indicate that the Subject Property was established primarily as agricultural
land with a portion of forested land along the western boundary prior to 1951. By 1968, the Site is primarily
composed of forested land. By 1994, a gas station was constructed in the center of the Site with a portion
of forested land along the eastern boundary. No significant changes were observed between 1994 and
2023. According to the Site reconnaissance, between 2023 to present day, the gas station was removed.
Prior to 1951, the Subject Property vicinity was primarily composed of agricultural land, with scattered
single-family homes, commercial buildings, pockets of forested land, marsh land, and the Beaufort River.
Additionally, Ribaut Road, Johnny Morrall Circle, and the Naval Base were established prior to 1951. By
1968, multiple commercial properties were developed to the north, and a multi-family residential
neighborhood was constructed to the west. Between 1968 and 1983, commercial properties continued to
be developed to the north, and all agricultural fields were revegetated in all directions. Additionally, Ladys
Island Drive was constructed to the east, multiple commercial properties were developed to the south, and
multiple single-family homes and commercial properties were developed to the west. By 1994, multiple
docks were constructed along the Beaufort River, and multiple commercial properties were developed to
the east. By 2006, multiple commercial properties were developed to the west. By 2011, multiple
commercial properties were developed to the south. By 2015, Ladys Island Drive expanded to a 4-lane
road. No significant changes were observed between 2015 and 2023.
Records Review
Kimley-Horn reviewed select federal and state environmental regulatory databases, as well as responses
from state and local regulatory agencies. Review of these databases and responses did identify a REC
associated with the Subject Property.
Table 1.0-2 Summary of Record Review Dates
Records
Reviewed Date of Review Results of Review
Historical Aerials May 12, 2026
x No RECs,
HRECs, or
CRECs
x BERs identified
Topographic
Maps
May 11, 2026 x No RECs
City Directories May 12, 2026 x No RECs
Sanborn Fire
Insurance Maps May 11, 2026
No fire insurance maps
are available for the
Subject Property.
Interviews
User Questionnaire was sent to Mr. Bryan Bauer and Ms.
Pamela Bernard with Beaufort County, on June 9, 2026. Ms.
Bernard completed the User Questionnaire on June 26, 2026
Property Owner Interview Questionnaire was sent to Mr.
Bryan Bauer and Ms. Pamela Bernard with Beaufort County,
on June 9, 2026, for coordination with the current property
owner. Ms. Bernard completed the Property Owner Interview
Questionnaire on June 26, 2026.
Government Officials: FOIA request May 19, 2026
x REC identified
Site Recon May 21, 2026 x REC identified
x BERs identified
Page 92 of 105
Phase I Environmental Site Assessment
Lady’s Island Site
Project No. 012716030
7
Site Reconnaissance
On May 21, 2026, Ms. Skylar Cole Kimley-Horn, under the supervision of Mr. Ben Lawson, PWS, qualified
environmental professional, visited the Subject Property. Ms. Cole was not escorted during the completion
of site reconnaissance of the Subject Property. No interior observations were made during the completion
of this Phase I ESA as part of this investigation. A summary of exterior observations from the site
reconnaissance are as follows:
x The Site was observed to be primarily composed of a cleared and graded lot.
x Three monitoring wells were observed within the Site.
x Overhead powerlines and pole-mounted transformers were observed transecting the northern
boundary of the Site. The pole-mounted transformers appeared to be corrosive.
x One closed drum labeled “non-hazardous waste” was observed within the eastern portion of the
Site. The contents inside are unknown, however no leaking, soil staining, or odor was observed.
Kimley-Horn did identify a REC associated with three monitoring wells located within the Subject Property
during the site reconnaissance.
Adjoining Properties
The Subject Property is bordered to the north by a maintained roadway (Johnny Morrall Cir) followed by a
religious facility. The Site is bordered to the west by a maintained roadway (Ribaut Road) followed by
commercial developments. The Site is bordered to the south by a maintained roadway (Ladys Island Dr)
followed by commercial developments. The Site is bordered to the east by commercial developments.
Opinions and Conclusions
Kimley-Horn has performed a Phase I Environmental Site Assessment (ESA) in conformance with the
scope and limitations of ASTM Practice E1527-21 for the approximately 0.6-acre property (PIN# R110 009
000 0031 0000) located within Lady’s Island, Beaufort County, SC, the Subject Property. This assessment
has revealed no controlled recognized environmental conditions or historical recognized environmental
conditions in connection with the Subject Property.
The following Recognized Environmental Conditions (RECs) were identified in association with the
Subject Property:
x During the site reconnaissance, three monitoring wells were observed within the Subject Property.
The monitoring wells appear to be in connection with the remediation of EDR record Piedmont
Petroleum Corp / Happy Mart #33 (Exxon) / Parkers 76 located within the Subject Property. The
Subject Property is listed as a historical gasoline service station with multiple UST leaks and
groundwater contamination. The EDR database search has limited information on the status of the
monitoring wells or the status of the remediation efforts. The Client provided Kimley-Horn with a
prior Limited Phase 2 ESA where further coordination with SCDHEC (now SCDES) was
recommended. Due to the known Site contamination, the unknown status of the morning wells and
remediation effort, and the potential requirement to close and/or relocate the monitoring wells, the
Subject Property is considered a REC.
x EDR record NAVSUPPFAC Beaufort SC/ US Naval Hospital is located approximately 0.046-miles
south of the Subject Property and approximately 0.407-miles southeast of the Subject Property.
The NAVSUPPFAC Beaufort SC/ US Naval Hospital is recorded for multiple UST leaks. Due to the
known contamination and the proximity to the Subject Property, the facility is considered a REC for
the Subject Property.
Page 93 of 105
Phase I Environmental Site Assessment
Lady’s Island Site
Project No. 012716030
8
The following Business Environmental Risks (BERs) were identified in association with the Subject
Property:
x Portions of the Site have been historically utilized for agricultural purposes from prior to 1951 until
prior to 1961. The historical land uses presumably included the legal and common application of
herbicides, fertilizers, and/or pesticides for crop cultivation. The legal application of these
compounds over time can result in localized impacts to the soil and/or groundwater. There was no
evidence observed during the site reconnaissance to indicate that these compounds had been
improperly applied to the Site. Earthwork or soil disturbance associated with future uses may
uncover or expose original soil. Based on historical land use, the potential for agrichemicals to be
present in the soil and groundwater is considered a BER.
x A drum labeled “non-hazardous waste” was observed in the eastern portion of the Site. The drum
appeared to closed and no leaking, soil staining, or odor was observed. However, due to the exact
contents and duration of the material remaining unknown, the drum is considered a BER.
x Evidence of overhead powerlines and associated pole-mounted transformers observed along the
northern boundary of the Site. The utilities may need to be moved or relocated as part of
development within the Site. Additionally, during the site reconnaissance, majority of the pole
mounted transformers appeared to be corrosive and may warrant further investigation. The
overhead powerlines and pole-mounted transformers are considered a BER.
Page 94 of 105
BEAUFORT COUNTY
PUBLIC FACILITIES COMMITTEE
AGENDA ITEM SUMMARY
ITEM TITLE:
AN ORDINANCE AUTHORIZING THE PRIVATE ROAD ACCEPTANCE OF BELLINGER BLUFF ROAD AND BELLINGER
NECK ROAD INTO THE COUNTY ROAD INVENTORY
MEETING NAME AND DATE:
Public Facilities Committee September 21, 2026
STAFF RECOMMENDATION / COUNCIL OPTIONS:
Road Acceptance procedures outlined in Policy Statements 15 and 17 and the County’s posted Road
Acceptance Procedures have been met to either accept or deny Bellinger Bluff Road and Bellinger Neck Road
into the County Road Inventory.
Motion to approve/deny request for Private Road Acceptance of Bellinger Bluff Road and Bellinger Neck Road
into the County Road Inventory. A Majority Vote for Acceptance by Committee would move the item forward
to final acceptance by full County Council vote.
PRESENTER INFORMATION:
Bryan Bauer, Director of Engineering (5 minutes)
ITEM BACKGROUND:
Bellinger Bluff Road and Bellinger Neck Road are unpaved private roads and have a combined estimated
length of approximately 0.35 miles. The Engineering Department estimates that paving costs could be
$1,328,950.81. This is based on the County's most recent dirt road paving cost averages and an additional 3%
inflation applied over 10 years. The Public Works Department has determined the estimated roadside cleaning
costs for the roads can cost up to $20,000. The abutting property owners have petitioned the County to bring
the private roads of Bellinger Bluff Road and Bellinger Neck Road into the County’s Road inventory.
FISCAL IMPACT:
Future impacts - Estimated potential costs for Public Works of roadside cleaning ≈ $20,000 (Stormwater
Infrastructure account # 5025-90-9020-51170); Estimated potential cost for paving (Additional 3% inflation
applied over 10 years) ≈ $1,328,950.81 (TAG account # 2342-30-0000-54500)
APPROVAL HISTORY:
Page 95 of 105
ORDINANCE 2026/____
AN ORDINANCE AUTHORIZING THE PRIVATE ROAD ACCEPTANCE OF BELLINGER
BLUFF ROAD AND BELLINGER NECK ROAD INTO THE COUNTY ROAD INVENTORY
WHEREAS, the abutting property owners of Bellinger Bluff Road and Bellinger Neck
Road have requested that the private roads be brought into County Road Inventory; and
WHEREAS, Bellinger Bluff Road and Bellinger Neck Road have met the requirements in
Policy Statements 15 & 17 and are more specifically identified on attached Exhibit “A”; and
WHEREAS, the abutting property owners of the two private roads have requested that the
rights-of-way be conveyed to Beaufort County (“County”); and
WHEREAS, County Council has been presented with this request and has evaluated the
associated costs with the roads and the roads have met the simple majority acceptance by the Public
Facilities Committee and by full County Council to be brought into the County Road Inventory;
and
WHEREAS, County Council finds it appropriate to authorize the County Administrator
to execute any necessary conveyance or related documents should the roads be determined to meet
applicable County standards and acceptance criteria;
NOW, THEREFORE, BE IT ORDAINED that Beaufort County Council authorize the
County Administrator to execute any and all documents associated with conveyance of Bellinger
Bluff Road and Bellinger Neck Road into the County Road Inventory, identified in attached
Exhibit “A”.
Page 96 of 105
DONE this ____ day of ______________ 2026.
COUNTY COUNCIL OF BEAUFORT COUNTY
By: ______________________________________
Alice G. Howard, Chair
ATTEST:
___________________________
Sarah W. Brock, Clerk to Council
Third and Final Reading:
Public Hearing:
Second Reading:
First Reading:
Page 97 of 105
Page 98 of 105
Page 99 of 105
Page 100 of 105
Page 101 of 105
Page 102 of 105
Page 103 of 105
Page 104 of 105
Bellinger Bluff Road & Bellinger Neck Road
Estimated Costs
Public Works Dept: Roadside Ditch Engineering Dept: Estimated
Cleaning/Scheduled Maintenance Paving Costs
1. Initial Roadside Ditch Cleaning
• Crew: 4-person team
• Equipment: Excavator, dump truck, and crew truck
• Duration: 5 days
• Estimated Cost: $2,500 per day
• Total Estimated Cost: $12,500
2. Scheduled Maintenance (5–7 Year Cycle)
• Crew: 4-person team
• Equipment: Excavator, dump truck, and crew truck
• Duration: 3 days
• Estimated Cost: $2,500 per day
• Total Estimated Cost: $7,500
Total Estimated Cost Over One 5–7 Year Cycle:
$20,000
The estimated cost to pave Bellinger Neck Rd and Bellinger Bluff Rd is
based on:
• County's most recent dirt road paving cost averages
• Additional 3% inflation applied over 10 years
Cost Breakdown:
Bellinger Neck Rd:
• Length: 0.15 miles
• Design: $71,386.30
• Construction: $365,126.61
• Total: $436,512.92
Bellinger Bluff Rd:
• Length: 0.20 miles
• Design: $95,181.74
• Construction: $486,835.49
• Total: $582,017.22
Inflation-Adjusted 10-Year Projection:
2026: Bellinger Neck Rd = $436,512.92, Bellinger Bluff Rd = $582,017.22
2027: Bellinger Neck Rd = $449,608.30, Bellinger Bluff Rd = $599,477.74
2028: Bellinger Neck Rd = $463,096.55, Bellinger Bluff Rd = $617,462.07
2029: Bellinger Neck Rd = $476,989.45, Bellinger Bluff Rd = $635,985.93
2030: Bellinger Neck Rd = $491,299.13, Bellinger Bluff Rd = $655,065.51
2031: Bellinger Neck Rd = $506,038.11, Bellinger Bluff Rd = $674,717.48
2032: Bellinger Neck Rd = $521,219.25, Bellinger Bluff Rd = $694,959.00
2033: Bellinger Neck Rd = $536,855.83, Bellinger Bluff Rd = $715,807.77
2034: Bellinger Neck Rd = $552,961.50, Bellinger Bluff Rd = $737,282.00
2035: Bellinger Neck Rd = $569,550.35, Bellinger Bluff Rd = $759,400.46
Total Estimated Paving Cost (10-Year Inflation Applied):
$1,328,950.81
Total Estimated Maintenance Cost:
$1,348,950.81
Page 105 of 105
Source: Beaufort County website. First collected Oct 24, 2026.