Town of Hilton Head Island
Parks and Recreation Commission Meeting
Thursday, September 18, 2025, 3:00 PM
1 Town Center Court, Hilton Head Island, SC
Benjamin M. Racusin Council Chambers
1. Call to Order
2. Pledge to the Flag
3. Adoption of the Agenda
4. Approval of the Minutes
a. Regular Meeting Minutes of May 22, 2025
5. Presentations
a. Island Parks and Recreation Association Update – Frank Soule, Parks and
Recreation Executive Director
b. Fiscal Year 2026 Facilities Landscaping and Park Maintenance Efforts Update
– Derrick Coaxum, Facilities Director
c. Fiscal Year 2026 Capital Improvement Plan Update on the Parks and
Pathways Programs – Jeff Netzinger, Engineering & Projects Director and
Richard Loudin, Public Projects Program Manager
6. Unfinished Business
7. New Business
a. Capital Improvement Plan - Overview of Parks and Pathways Updates to
Discuss the Status of Current Projects Related to Community Parks and
Pathways, Progress, and Any Adjustments to Project Scope or Funding - Jeff
Netzinger, Engineering & Projects Director, and Richard Loudin, Public
Projects Program Manager
8. Public Comment - Non Agenda Items
9. Commission Business
Page 1 of 34
10. Chairman's Report
11. Staff Report
12. Adjournment
FOIA Compliance: Public notification of this meeting has been published, posted, and
distributed in compliance with the South Carolina Freedom of Information Act and the
requirements of the Town of Hilton Head Island.
In accordance with the requirements of Title II of the Americans with Disabilities Act of
1990 ("ADA"), the Town of Hilton Head Island will not discriminate against qualified
individuals with disabilities on the basis of disability in its services, programs, or
activities. Auditory accommodations are available. Any person requiring further
accommodation should contact the Town of Hilton Head Island ADA Coordinator as
soon as possible but no later than 48 hours before the scheduled event.
Municipal Association of South Carolina (MASC) Civility Pledge:
“I pledge to build a stronger and more prosperous community by advocating for civil
engagement, respecting others and their viewpoints, and finding solutions for the
betterment of my city or town.”
Page 2 of 34
Town of Hilton Head Island Parks and Recreation Commission
Meeting Minutes
5/22/2025 Page | 1
Town of Hilton Head Island
PARKS AND RECREATION COMMISSION
MEETING
Thursday, May 22, 2025, 3:00 PM
Minutes
1. Call to Order
Chair Bill Zurilla called the meeting to order at 3:06 p.m.
2. Pledge to the Flag
3. Adoption of the Agenda
A motion to adopt the agenda was made by Ms. Kristian and seconded by Mr. Quigg. The
motion passed unanimously.
4. Approval of the Minutes
a. Regular Meeting Minutes of November 14, 2024
A motion to approve the minutes from the November meeting was made by Mr. Quigg
and seconded by Ms. Kristian. The motion passed unanimously.
5. Presentations
a. Island Parks and Rec Association Update - Frank Soule, Parks and Rec Executive
Director
Frank Soule, Parks and Rec Executive Director provided a broad update on parks and
recreation programming, facility improvements, and budget planning. Outdoor recreation
programs such as surf lessons, kayaking, and summer camps continue to be well
attended, and youth programming is expanding with additional summer offerings in
development. The minimum age for participation in senior programming has been
reduced from 70 to 65. Family Fun Day saw increased participation, which staff attributed
to improved marketing efforts.
b. Fiscal Year 25 Facilities Landscaping Efforts Update - Derrick Coaxum, Facilities
Director
Derrick Coaxum, Facilities Director, provided updates to the commission on the Fiscal
year 2025 facilities landscaping efforts. Financially, the FY26 Parks and Recreation
budget includes $900,000 in planned investments, with $500,000 allocated to soft costs.
Staff confirmed that unspent FY25 funding will carry over into the next fiscal year. More
than $250,000 in scholarships were distributed in the past year, and an additional
$225,000 request has been submitted for aquatics scholarships and pool support.
Page 3 of 34
Town of Hilton Head Island Parks and Recreation Commission
Meeting Minutes
5/22/2025 Page | 2
6. Unfinished Business
7. New Business
a. Capital Improvement Plan - Overview of Parks and Pathways Updates to Discuss the
Status of Current Projects Related to Community Parks and Pathways, Progress,
and Any Adjustments to Project Scope or Funding - Jeff Netzinger, Engineering &
Projects Director, and Richard Loudin, Public Projects Program Manager
Richard Loudin, Public Projects Program Manager, and Jeff Netzinger, Engineering &
Projects Director, reviewed the Town’s broader Capital Improvement Program, which
totals $77 million and includes roads, beach renourishment, equipment, and parks—
highlighting the impact of inflation and the role of construction cost indices in project
forecasting.
Several park projects are advancing. Crossings Park Phase 1 improvements, including
pickleball and a skate pump track, are scheduled for FY27. Chaplin Park is slated for
design in FY27 and construction in FY28. Other park updates include sidewalk and
playground improvements at Jarvis Creek, soccer field enhancements at Barker Field,
and ADA and court upgrades at Green Shell Park. Islander’s Beach Park upgrades are
delayed due to the beach renourishment staging area. Phase 2 of Shelter Cove
Community Park has been deferred to FY27, and Patterson Family Park’s design
continues with Shoreline Construction recently awarded the contract. At Mitchelville
Freedom Park, archaeological work continues, with permit applications underway for the
road and parking area.
Pathway and infrastructure projects are also moving forward. Jonesville Road Pathway
design is being revised to minimize tree impacts and easement needs, and the
Dunnigan’s Alley Pathway has been awarded for design following the receipt of a
Transportation Alternatives Program (TAP) grant. Staff also reviewed a proposed Main
Street Corridor pathway between the school and hospital, though funding has not yet
been identified.
Operationally, staff are piloting a new court reservation system and will collect usage data
to guide future decisions. Commissioners were also asked to provide input on
maintenance standards to help define and budget for sustainable upkeep across parks
and facilities.
Finally, staff shared updates on strategic planning and financing efforts. Current Tax
Increment Financing (TIF) is committed through FY26, and conversations are ongoing
regarding a potential new TIF district. Commissioners emphasized the importance of
aligning all projects with the 2019 Strategic Plan and expressed strong support for
continued collaboration with the Island Recreation Association to ensure staffing and
program success at new or expanded facilities.
Page 4 of 34
Town of Hilton Head Island Parks and Recreation Commission
Meeting Minutes
5/22/2025 Page | 3
8. Public Comment - Non Agenda Items
9. Commission Business
Commission members volunteered to assist in expanding programming and park facilities.
10. Chairman's Report
11. Staff Report
12. Adjournment
The meeting adjourned at 5:03 p.m.
Page 5 of 34
Capital Improvement Program
Parks Program FY26 Update
September 18, 2025
Parks and Recreation Commission Meeting
Town of Hilton Head Island
Richard Loudin
Public Projects Program Manager
Page 6 of 34
Town of Hilton Head Island
PARKS PROGRAM FY26 UPDATE – PRESENTATION OVERVIEW
Presentation Overview
1. FY 2026 Budget Overview
2. Park Project Updates
a. Barker Field Renovations
b. Chaplin Community Park Renovations
c. Coligny Circle Pocket Park
d. Crossings Park Renovations
e. Fords Shell Ring Improvements
f. Jarvis Creek Park Renovations
g. Mid-Island Tract
h. Patterson Family Park
i. Shelter Cove Community Park
j. Taylor Family Park
k. Old Schoolhouse Park Improvements
Park Locations
Page 7 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – FY2026 BUDGET OVERVIEW
Project P
M Status FY26
Budget
FY27
Priority
FY28
Priority
FY29
Priority
FY30
Priority
Barker Field Renovations, Phase 1 SB Construction Nearing
Completion
Barker Field Renovations, Phase 2 &
Mitchelville SB Identified X X
Chaplin Community Park Renovations, Phase
1 SB Design X X X
Chaplin Community Park Renovations, Phase
2 SB Design X X X
Coligny Circle Pocket Park SH Construction 1,400,000
Crossings Park Renovations, Phase 1 NE Design 1,000,000 X X
Crossings Park Renovations, Phase 2 NE Design 750,000 X X
Crossings Park Renovations, Phase 3 NE Design 250,000 X X X X
Fords Shell Ring Improvements SB Permitting
Jarvis Creek Park Improvements SB Identified X
Mid-Island Tract Park, Phase 1 SH Design 750,000 X X X X
Patterson Family Park SH Design 3,400,000 X
Taylor Family Park SH Design 3,500,000 X
Shelter Cove Community Park Expansion,
Phase 2 SB Design X X
Old Schoolhouse Park Improvements NE Design 750,000
Page 8 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – BARKER FIELD RENOVATIONS, PHASE 1
Barker Field Extension Site Improvements Plan (April 2025)
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Renovation of the existing soccer field including improving field drainage,
installation of a new irrigation system, new lighting, bleachers, a new storage
facility, and new fencing.
Carry Forward
$1,100,0000
Beach Fee and Hospitality Tax
Page 9 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CHAPLIN COMMUNITY PARK RENOVATIONS, PHASE 1
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Expansion of parking facility to add approximately 236 parking spaces to
existing northern and southern parking lots.
Timeline
Schematic Design Complete
Page 10 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CHAPLIN COMMUNITY PARK RENOVATIONS, PHASE 2
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Renovation of soccer fields, tennis courts, and dog park; construction of new
pavilion, multi-use facility with restroom, pickleball courts, and playground.
Timeline
Schematic Design Complete
Page 11 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – COLIGNY CIRCLE POCKET PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Improvements include plaza amenity space, landscaping, and a multi-use
path.
FY26 Budget
$1,400,000
Capital
Page 12 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CROSSINGS PARK RENOVATIONS, PHASE 1
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Construct new pickleball complex to include 20 courts, clubhouse with
meeting area and restrooms, parking lot, landscaping and pathway
connection to Bristol Sports Area.
Phase 1 Construction Drawings 50% complete
FY26 Budget
$1,000,0000
Hospitality Tax
Page 13 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CROSSINGS PARK RENOVATIONS, PHASE 2
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Renovation to Bristol Sports Arena with new cover and fencing over arena,
new skate park, and pump track.
Phase 2 Construction Drawings underway.
FY26 Budget
$750,000
Hospitality Tax
Page 14 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CROSSINGS PARK RENOVATIONS, PHASE 3
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Construction of 2 new baseball fields, restroom, parking lot and Champions
Plaza; renovation of 3 existing baseball fields, concessions, training facility,
parking lot.
FY26 Budget
$250,000
TBD
Page 15 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – FORD SHELL RING IMPROVEMENTS
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
CDBG project; Design and permitting for improvements to supplement
Beaufort's County's construction project
TIF Rev
Page 16 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – JARVIS CREEK PARK IMPROVEMENTS
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Replacement of playground equipment.
TBD
Page 17 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – MID-ISLAND TRACT PARK, PHASE 1
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 11.22
Project Funding
Project Scope
Improvements to stormwater and lagoon systems, pathways, parking lot off
Union Cemetery Road, and restrooms (site stabilization).
MKSK to provide proposal for Phase 1 Construction Drawings
FY26 Budget
$750,000
Hospitality Tax
Page 18 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – PATTERSON FAMILY PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C C ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 12.23
Project Funding
Project Scope
Construction of new Neighborhood Park on Marshland Road providing a
pavilion, lawn area, viewing platform overlooking Broad Creek, pedestrian
connectivity, parking, and other associated site amenities.
FY26 Budget
$3,400,000
Hospitality Tax and Grants
Page 19 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – TAYLOR FAMILY PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C C ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 11.23
Project Funding
Project Scope
Construction of new Neighborhood Park on Wild Horse Road providing a
pavilion, lawn area, recreational play amenities, pedestrian connectivity,
parking, and other associated site amenities.
FY26 Budget
$3,500,000
Hospitality Tax and Grant
Page 20 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – SHELTER COVE COMMUNITY PARK EXPANSION,
PHASE 2
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.23
Project Funding
Project Scope
Installation of Best Buddies playground followed by future construction of a
Broad Creek boardwalk and viewing platform and landscaping.
TBD
Page 21 of 34
Town of Hilton Head Island
PARKS PROGRAM UPDATE – OLD SCHOOLHOUSE PARK IMPROVEMENTS
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Landscape & site improvements including ADA parking and sidewalks,
pickleball court replacement, restroom, shade, signage, seating, landscaping,
etc.
FY26 Budget
$750,000
TIF Revenue
Page 22 of 34
Capital Improvement Program
Beach Program FY26 Update
September 18, 2025
Parks and Recreation Commission Meeting
Town of Hilton Head Island
Richard Loudin
Public Projects Program Manager
Page 23 of 34
Town of Hilton Head Island
BEACH PROGRAM UPDATE – FY2026 BUDGET OVERVIEW
Project PM Status FY26 Budget FY27
Budget
FY28
Priority
FY29
Priority
FY30
Priority
Islanders Beach Park Improvements NE Design X
Page 24 of 34
Town of Hilton Head Island
BEACH PROGRAM UPDATE – ISLANDERS BEACH PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C C C
Project Schedule
Project Status
Master Plan Approval Date: 5.23
Project Funding
Project Scope
Parking area expansion and renovation, building improvements, stormwater
infrastructure improvements, playground equipment replacement,
construction of new pathways, landscaping and signage improvements, and
boardwalk repairs.
TBD
Page 25 of 34
Capital Improvement Program
Facility & Equipment Program FY26 Update
September 18, 2025
Parks and Recreation Commission Meeting
Town of Hilton Head Island
Richard Loudin
Public Projects Program Manager
Page 26 of 34
Town of Hilton Head Island
FACILITY & EQUIPMENT PROGRAM UPDATE – FY2026 BUDGET OVERVIEW
Project PM Status FY26 Budget FY27
Budget
FY28
Priority
FY29
Priority
FY30
Priority
Mitchelville Freedom Park Improvements SB Permitting 250,000 X
Page 27 of 34
Town of Hilton Head Island
Facility & EQUIPMENT PROGRAM UPDATE – MITCHELVILLE FREEDOM PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.23
Project Funding
Project Scope
Construction of drive and parking improvements to add dedicated parking and
install site electricity to support events.
Brockington moving forward with Phase 3 Archaeological Recovery
FY26 Budget
$250,000
State ATAX
Page 28 of 34
Capital Improvement Program
Pathway Program FY26 Update
September 18, 2025
Parks and Recreation Commission Meeting
Town of Hilton Head Island
Jeff Netzinger
Engineering & Projects Director
Page 29 of 34
Town of Hilton Head Island
PATHWAY PROGRAM UPDATE – FY2026 BUDGET OVERVIEW
Project PM Status FY26 Budget FY2Y
Priority
FY28
Priority
FY29
Priority
FY30
Priority
Jonesville Road Pathway
(Western Terminus to Spanish Wells Rd) SB Design 500,000 X X
Dunnagans Alley Pathway
(Wexford Drive to Arrow Road) SB Identified 250,000 X
William Hilton Parkway Eastbound Pathway
(Village at Wexford to Arrow Road) SB Design 300,000 X X
South Forest Beach Drive HAWK Signal
( at Marriott’s Grand Ocean Resort) SB Identified X X
Lagoon Road Pathway
(Avocet Road to North Forest Beach Drive) SH Identified X X
Palmetto Parkway Pathway
(Mathews Drive to William Hilton Parkway) NE Identified X X
Spanish Wells Road Pedestrian Bridge NE Identified X
Fish Haul Road
(Baygall Road to Alice Perry Drive) NE Identified X X X
William Hilton Parkway Eastbound Pathway
(Mathews Dr / Folly Field Rd to Shelter Cove Ln) SB Identified X
Cross Island Parkway
(Coastal Discovery Museum to Spanish Wells
Rd)
SB Identified X
Muddy Creek Pathway Connection
(Muddy Creek Road to Cross Island Parkway) SH Identified X X
Page 30 of 34
Town of Hilton Head Island
PATHWAY PROGRAM UPDATE – JONESVILLE ROAD PATHWAY
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Construction of new (1.2 mile) pedestrian facility along Jonesville Road
beginning at the western terminus and connecting to the existing multiuse
pathway along Spanish Wells Road.
FY26 Budget
$500,000
Sunday Liquor Permit Fee
Page 31 of 34
Town of Hilton Head Island
PATHWAY PROGRAM UPDATE – DUNNAGANS ALLEY PATHWAY
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C C C ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Construction of new pedestrian pathway that will provide separation from
traffic by adding green space and trees along Dunnagans Alley from Wexford
Drive to Arrow Road.
FY26 Budget
$250,000
Sunday Liquor Permit Fee
Page 32 of 34
Town of Hilton Head Island
PATHWAY PROGRAM UPDATE – WHP EB PATHWAY (WEXFORD DR TO ARROW RD)
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
C
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Construction of new pathway from Village at Wexford to Arrow Road.
SC DOT TAP Grant Project.
State ATAX
Page 33 of 34
Town of Hilton Head Island
Page 34 of 34