Town of Hilton Head Island
Town Council Workshop
Tuesday, August 26, 2025, 1:00 PM
1 Town Center Court, Hilton Head Island, SC
Benjamin M. Racusin Council Chambers
The meeting can be viewed on the Town’s YouTube Channel, the Beaufort County
Channel, and Spectrum Channel 1304.
1. Call to Order
2. Adoption of the Agenda
3. Workshop Discussion
a. Capital Improvement Program (CIP) Update
4. Public Comment - Non Agenda Items
5. Adjournment
FOIA Compliance: Public notification of this workshop has been published, posted, and
distributed in compliance with the South Carolina Freedom of Information Act and the
requirements of the Town of Hilton Head Island.
In accordance with the requirements of Title II of the Americans with Disabilities Act of
1990 ("ADA"), the Town of Hilton Head Island will not discriminate against qualified
individuals with disabilities on the basis of disability in its services, programs, or
activities. Auditory accommodations are available. Any person requiring further
accommodation should contact the Town of Hilton Head Island ADA Coordinator as
soon as possible but no later than 48 hours before the scheduled event.
Municipal Association of South Carolina (MASC) Civility Pledge:
“I pledge to build a stronger and more prosperous community by advocating for civil
engagement, respecting others and their viewpoints, and finding solutions for the
betterment of my city or town.”
Page 1 of 50
Stephen G. Riley Municipal Complex
One Town Center Court ⬧ Hilton Head Island ⬧ South Carolina ⬧ 29928
www.hiltonheadislandsc.gov
TOWN OF HILTON HEAD ISLAND
Town Council
TO: Town Council
FROM: Shawn Leininger, AICP, Assistant Town Manager
John Troyer, Finance Director
CC: Marc Orlando, ICMA-CM, Town Manager
DATE: August 20, 2025
SUBJECT: Capital Improvements Program Workshop
SUMMARY:
To advance discussion and direction on the topic of the FY2026 -2030 Capital
Improvements Program (CIP) and funding , Town Staff will provide the attached draft
presentation at the Town Council Workshop on August 26, 2025. This presentation will
review the following topics:
1. FY2026-2028 Strategic Action Plan – Priorities
2. Status of Current FY2026 CIP Projects
3. Planned FY2027-2030 CIP Projects
4. Funding Options to Support Planned CIP Projects
Town Staff anticipates a collaborative discussion with Town Council, to better understand
and how to best advance planned CIP initiatives in accordance with the FY26-28 Town
Council Strategic Action Plan.
ATTACHMENTS:
1. Capital Improvements Program Workshop Presentation (Draft)
Page 2 of 50
TOWN OF HILTON HEAD ISLAND
Capital Improvements
Program Workshop
Town Council
August 26, 2025
Page 3 of 50
1. FY2026-2028 Strategic Action
Plan Priorities
2. Status of Current FY2026 CIP
Projects
3. Planned FY2027-2030 CIP Projects
4. Funding Options to Support
Planned CIP Projects
5. General Discussion
* The Stormwater Program will be discussed at a
Town Council Workshop on September 30, 2025 *
Agenda
TOWN OF HILTON HEAD ISLAND
Page 4 of 50
FY2026-2028 Strategic Action Plan
Priorities
3
Page 5 of 50
I TOWN OF HILTON HEAD ISLAND
Strategic Action Plan Goals
Page 6 of 50
I TOWN OF HILTON HEAD ISLAND
Strategic Action Plan Goals
Page 7 of 50
Status of Current
FY2026 CIP Projects
Page 8 of 50
FY2026 Proposed CIP Uses of Funds
TOWN OF HILTON HEAD ISLAND
Use of Funds
FY 2023
Actual
FY 2024
Actual
FY 2025
Revised
Budget
FY 2026
Proposed
Budget
FY26 to
FY25 Budget
$ Change
FY26 to
FY25 Budget
% Change
% of
Budget
Beach Program 1,153,510$ 2,404,079$ 21,599,000$ 48,820,000$ 27,221,000$ 126.03% 62.84%
Pathway Program 312,853 1,527,321 5,500,000 1,650,000 (3,850,000) -70.00% 2.12%
Roadway Program 4,361,824 2,770,550 10,317,218 5,079,500 (5,237,718) -50.77% 6.54%
Park Program 1,396,152 2,323,598 19,815,273 10,636,000 (9,179,273) -46.32% 13.69%
Facility & Equipment Program 5,036,029 3,623,957 8,402,291 4,721,000 (3,681,291) -43.81% 6.08%
Stormwater Program 133,993 1,088,427 2,193,310 6,350,880 4,157,570 189.56% 8.17%
Fleet Program 480,489 1,071,075 11,750,707 180,000 (11,570,707) -98.47% 0.23%
Land Acquisition & Administration 7,826,584 12,019,174 3,225,000 250,000 (2,975,000) -92.25% 0.32%
Housing 120,851 - - - - 0.00% 0.00%
Transfers Out to Housing - 350,000 - - - 0.00% 0.00%
Debt Service - 220,558 - - - 0.00% 0.00%
Total Use of Funds 20,822,285$ 27,398,738$ 82,802,799$ 77,687,380$ (5,115,419)$ -6.18% 100.00%
Page 9 of 50
FY2026 Proposed CIP Uses of Funds
TOWN OF HILTON HEAD ISLAND
Beach Program
1.7%
Beach Renourishment
61.1%
Pathway Program
2.1%
Roadway Program
6.5%
Park Program
13.7%
Facility & Equipment
Program
6.1%
Stormwater Program
8.2%
Fleet Program
0.2% Land Acquisition &
Administration
0.3%
Page 10 of 50
FY2026 Proposed CIP Sources of Funds
TOWN OF HILTON HEAD ISLAND
Traffic & Park Impact Fees
1.4%
Sunday Liquor Permit Fees
1.3%
Prior Bond Proceeds
0.1%
Capital
4.2%
Grants
9.5%
Beach Preservation Fees
53.1%
Hospitality Tax
12.8%
Tax Increment Financing
(TIF)
2.9%
State ATAX
3.6%
Road Usage Fee
1.7%
Electric Franchise Fee
0.7%
Real Estate Transfer Fee
0.3%
Short Term Rental Permit
Fee
0.2%
Stormwater Utility Fee
8.2%
Page 11 of 50
FY2026 CIP Project Dashboard (https://hiltonheadislandsc.gov/cip/)
TOWN OF HILTON HEAD ISLAND
Page 12 of 50
TOWN OF HILTON HEAD ISLAND
FY2026 CIP Projects Overview
• Current Status of Town Projects
o Planning 55 Projects
o Design 20 Projects
o Construction 3 Projects*
* Mitchelville Road, Coligny Pocket Park are bid and
nearing construction start
• Project Delivery Challenges &
Opportunities
o Easement / Right-of-Way Acquisition
o Contractor Availability / Capacity
o Bid Competition
o Pricing is Exceeding Market Estimates
o Simplify Procurement Strategy
Page 13 of 50
TOWN OF HILTON HEAD ISLAND
FY2026 CIP Project Map –
Current Project Status
Page 14 of 50
Planned FY2027-2030 CIP Projects
Page 15 of 50
FY2027-2030 CIP Projects Overview
PLANNED FY27-30 CIP PROJECTS
• Major investments in all program areas to advance public safety and quality of life
• Project scope and costs are not yet fully defined, especially for those projects later
in the 5-year plan
• Great financial position to execute projects
• Considerations for project delivery include:
o Prioritization (schedule)
o Scope adjustment
o Phasing
o Cash versus debt
• Issues affecting FY2026 project delivery expected to continue and potentially
worsen due to off-island development
Page 16 of 50
Beach Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
BEACH PROGRAM
Beach Park Maintenance & Improvements Maintenance $ 150,000 $ 150,000 Priority Priority Priority Priority ✓
Beach Management & Monitoring Maintenance $ 220,000 $ 220,000 Priority Priority Priority Priority
Beach Renourishment Maintenance $ 47,500,000 $ 47,500,000 ✓
Islanders Beach Park Improvements Discretionary $ - $ - Priority Priority
Folly Field Beach Park Improvements Discretionary $ - $ - Priority
Coligny Beach Park Boardwalk Maintenance Maintenance $ 250,000 $ 250,000 Priority Priority Priority Priority ✓
Harbour Town Dredge Maintenance $ 600,000 $ 600,000 ✓
Beach Program Contingency N/A $ 100,000 $ 100,000 Priority Priority Priority Priority
Total Beach Program $ 48,820,000 $ 48,820,000
FY 2026 Project Schedule
Page 17 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
PATHWAY PROGRAM
Pathway Maintenance & Improvements Maintenance $ 500,000 $ 500,000 Priority Priority Priority Priority ✓
New Pathway Segments
Jonesville Road Pathway
(Western Terminus to Spanish Wells Rd) Discretionary $ 500,000 $ 500,000 Priority ✓ ✓
Dunnagans Alley Pathway
(Wexford Drive to Arrow Road) Discretionary $ 250,000 $ 250,000 Priority ✓ ✓
William Hilton Parkway EB Pathway
(Wexford Drive to Arrow Road) Discretionary $ 300,000 $ 300,000 Priority ✓
South Forest Beach HAWK Signal at Marriott Grande Ocean Discretionary $ - $ - Priority
Lagoon Road Pathway
(Avocet Road to North Forest Beach Drive) Discretionary $ - $ - Priority Priority
Palmetto Parkway Pathway
(Mathews Drive to William Hilton Parkway) Discretionary $ - $ - Priority Priority
Spanish Wells Pedestrian Bridge Maintenance $ - $ - Priority
Fish Haul Road
(Baygall Road to Alice Perry Drive) Discretionary $ - $ - Priority Priority Priority
FY 2026 Project Schedule
Pathway Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 18 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
William Hilton Parkway EB Pathway
(Mathews Drive / Folly Field Road to Shelter Cove Lane) Discretionary $ - $ - Priority
Cross Island Parkway from Coastal Discovery Museum
Access to Spanish Wells Road Discretionary $ - $ - Priority
Muddy Creek Pathway Connection
(Muddy Creek Road to Cross Island Parkway) Discretionary $ - $ - Priority Priority
Subtotal New Pathway Segments $ 1,050,000 $ 1,050,000
Pathway Project Management and Contingency N/A $ 100,000 $ 100,000 Priority Priority Priority Priority
Total Pathway Program $ 1,650,000 $ 1,650,000
FY 2026 Project Schedule
Pathway Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 19 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
ROADWAY PROGRAM
Roadway Maintenance & Improvements Maintenance $ 250,000 $ 250,000 Priority Priority Priority Priority ✓
Town Road Resurfacing Program Maintenance $ - $ - Priority Priority Priority Priority
Signal System Maintenance Maintenance $ 1,100,000 $ 1,100,000 Priority Priority Priority Priority ✓
Landscape, Lighting, and Safety Enhancements Maintenance $ 750,000 $ 750,000 Priority Priority Priority Priority ✓
Dirt Road Paving Program
Mitchelville Road Discretionary $ 910,000 $ 910,000 ✓ ✓
Alice Perry Drive Discretionary $ 50,000 $ 50,000 Priority ✓ ✓
Freddie's Way Discretionary $ 50,000 $ 50,000 Priority ✓ ✓
Alfred Lane Discretionary $ 44,500 $ 44,500 Priority ✓ ✓
Benjamin Drive Discretionary $ 50,000 $ 50,000 Priority ✓ ✓
Christopher Drive Discretionary $ - $ - Priority Priority
Darling Road Discretionary $ - $ - Priority Priority
Manatee Way Discretionary $ - $ - Priority Priority
Pine Field Discretionary $ - $ - Priority Priority
Amelia Court Discretionary $ - $ - Priority Priority
Evelina Road Discretionary $ - $ - Priority Priority
Subtotal Dirt Road Paving Program $ 1,104,500 $ 1,104,500
FY 2026 Project Schedule
Roadway Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 20 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
Island-wide Intersection Pedestrian & Vehicular Safety
Improvements Maintenance $ 250,000 $ 250,000 Priority Priority Priority Priority ✓
Jonesville Road and Spanish Wells Right Turn Lane
Improvements Maintenance $ 100,000 $ 100,000 Priority ✓ ✓
Northpoint Access Improvements Maintenance $ 150,000 $ 150,000 Priority ✓ ✓
Tabby Walk Entrance Relocation Maintenance $ 200,000 $ 200,000 Priority ✓ ✓
William Hilton Parkway Gateway Corridor & Stoney Corridor Discretionary $ 100,000 $ 100,000 ✓
Streetscape Enhancements
Main Street Discretionary $ - $ - Priority Priority Priority Priority
New Orleans Road Discretionary $ - $ - Priority Priority Priority
Old Wild Horse Discretionary $ - $ - Priority Priority
Palmetto Bay Road Discretionary $ - $ - Priority Priority
Pope Avenue Streetscape Improvements Discretionary $ 250,000 $ 250,000 Priority Priority Priority ✓ ✓ ✓
Arrow Road Discretionary $ - $ - Priority Priority
Subtotal Streetscape Enhancements $ 250,000 $ 250,000
FY 2026 Project Schedule
Roadway Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 21 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
William Hilton Parkway Streetscape Enhancements
Segment 1 - Spanish Wells Road / Wild Horse Road to
Wilborn Road / Jarvis Park Road Discretionary $ - $ - Priority
Segment 2 - Wilborn Road / Jarvis Park Road to Beach City
Road / Gardner Drive Discretionary $ - $ - Priority Priority
Segment 3 - Beach City Road / Gardner Drive to Dillon Road Discretionary $ - $ - Priority Priority
Segment 4 - Dillon Road to Mathews Drive / Folly Field
Road Discretionary $ - $ - Priority
Segment 5 - Mathews Drive / Folly Field Road to Shelter
Cove Lane Discretionary $ 300,000 $ 300,000 Priority Priority Priority Priority ✓
Segment 6 - Shelter Cove Lane to Queens Folly Road / King
Neptune Drive Discretionary $ - $ - Priority
Segment 7 - Queens Folly Road / King Neptune Drive to
Wexford Drive / Shipyard Drive Discretionary $ - $ - Priority Priority
Segment 8 - Sea Pines Circle to Wexford Drive / Shipyard
Drive Discretionary $ 350,000 $ 350,000 Priority ✓ ✓ ✓
Subtotal William Hilton Parkway Streetscape
Enhancements $ 650,000 $ 650,000
Wilborn Road & Pembroke Drive Turn Lane Extensions /
Curb and Gutter Improvements Maintenance $ - $ - Priority Priority Priority
Folly Field Road Pedestrian Safety Improvements Maintenance $ 75,000 $ 75,000 Priority ✓ ✓ ✓
Roadway Project Management and Contingency N/A $ 100,000 $ 100,000 Priority Priority Priority Priority
Total Roadway Program $ 5,079,500 $ 5,079,500
FY 2026 Project Schedule
Roadway Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 22 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
PARK PROGRAM
Park Maintenance and Improvements Maintenance $ 250,000 $ 250,000 Priority Priority Priority Priority ✓
Public Art Program Discretionary $ 35,000 $ 35,000 Priority Priority Priority Priority ✓
Island Recreation Association
Rec Center Building Improvements Maintenance $ 233,500 $ 233,500 Priority Priority Priority Priority ✓
Rec Center Pool Improvements Maintenance $ 195,000 $ 195,000 Priority Priority Priority Priority ✓
Basketball Court Improvements Maintenance $ - $ - Priority
Athletic Equipment Improvements Maintenance $ 15,000 $ 15,000 Priority Priority
Event Equipment Improvements Maintenance $ 67,500 $ 67,500 Priority Priority Priority Priority
Subtotal Island Recreation Association $ 511,000 $ 511,000 Priority Priority Priority Priority
Chaplin Community Park Renovation - Phase 1: Parking
Renovation & Expansion Discretionary $ - $ - Priority Priority Priority
Chaplin Community Park Renovation - Phase 2: Soccer
Complex, Facility Upgrades, and Parking Expansion Discretionary $ - $ - Priority Priority Priority
Coligny Circle NW Quadrant Pocket Park Discretionary $ 900,000 $ 900,000 ✓ ✓
Crossings Park Renovation - Phase 1: Pickleball Complex Discretionary $ 1,000,000 $ 1,000,000 Priority Priority Priority ✓ ✓
Crossings Park Renovation - Phase 2: Bristol Sports Arena,
Skate Park, and Pump Track Discretionary $ 750,000 $ 750,000 Priority ✓ ✓
Crossings Park Renovation - Phase 3: Baseball Complex Discretionary $ 250,000 $ 250,000 Priority Priority Priority Priority ✓
FY 2026 Project Schedule
Park Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 23 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
Jarvis Creek Park Improvements Discretionary $ - $ - Priority
Mid-Island Tract Park - Phase 1 Discretionary $ 750,000 $ 750,000 Priority Priority Priority Priority ✓ ✓
Patterson Family Park Discretionary $ 2,590,000 $ 2,590,000 ✓ ✓ ✓
Shelter Cove Community Park Expansion, Phase 2 Discretionary $ - $ - Priority Priority
Taylor Family Park Discretionary $ 2,750,000 $ 2,750,000 ✓ ✓ ✓
Chaplin Linear Park with Treehouse Discretionary $ - $ - Priority Priority Priority
Old Schoolhouse Park Improvements Discretionary $ 750,000 $ 750,000 Priority ✓ ✓ ✓
Barker Field Phase 2 & Mitchelville Property Improvements Discretionary $ - $ - Priority Priority
Marshland Road Racquet Facility Discretionary $ - $ - Priority
Park Project Contingency N/A $ 100,000 $ 100,000 Priority Priority Priority Priority
Total Park Program $ 10,636,000 $ 10,636,000
FY 2026 Project Schedule
Park Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 24 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
FACILITY & EQUIPMENT PROGRAM
Facility Maintenance & Improvements Maintenance $ 500,000 $ 500,000 Priority Priority Priority Priority ✓
Facilities Equipment Maintenance $ 50,000 $ 50,000 Priority Priority Priority Priority
Town Hall Facility Improvements Maintenance $ 200,000 $ 200,000 Priority Priority Priority Priority ✓
4 Office Way Renovations Maintenance $ 1,100,000 $ 1,100,000 ✓ ✓ ✓
IT Equipment & Software Maintenance $ 625,000 $ 625,000 Priority Priority Priority Priority
Fire Hydrant Expansion Maintenance $ 50,000 $ 50,000 Priority Priority Priority Priority ✓
Fire & Medical Systems & Equipment Maintenance $ - $ - Priority Priority Priority Priority
Furniture Replacement Maintenance $ 300,000 $ 300,000 Priority Priority Priority Priority
Security Cameras & Connectivity Maintenance $ 150,000 $ 150,000 Priority Priority Priority Priority
Tree Planting Program Discretionary $ 150,000 $ 150,000 Priority Priority Priority Priority
Coastal Discovery Museum Improvements
Discovery House Maintenance $ 20,500 $ 20,500 Priority Priority Priority Priority ✓
Armstrong / Hack House Maintenance $ 10,500 $ 10,500 Priority Priority Priority Priority ✓
Pavilion Maintenance $ 4,500 $ 4,500 Priority Priority Priority ✓
Discovery Lab Maintenance $ 4,500 $ 4,500 Priority Priority ✓
Pavilion / Restroom Building Maintenance $ 350,000 $ 350,000 Priority Priority Priority ✓
Horse Barn Maintenance $ 23,000 $ 23,000 Priority Priority Priority ✓
Hay Barn Maintenance $ 50,000 $ 50,000 Priority Priority Priority ✓
Miscellaneous Improvements Maintenance $ 23,000 $ 23,000 Priority Priority Priority Priority ✓
Event Space Improvements Maintenance $ 10,000 $ 10,000 Priority ✓
Subtotal Coastal Discovery Museum Improvements $ 496,000 $ 496,000 Priority Priority Priority Priority
FY 2026 Project Schedule
Facilities & Equipment Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 25 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
Fire Rescue Headquarters Maintenance $ - $ - Priority Priority Priority
Jonesville Horse Barn Maintenance $ 500,000 $ 500,000 ✓
Mitchelville Freedom Park Improvements Discretionary $ 250,000 $ 250,000 Priority ✓ ✓
Wild Wing Café Renovation Discretionary $ - $ -
Aunt Chilada Property Improvements Maintenance $ - $ - Priority
Town Refuse & Recycling Management Improvements Discretionary $ 250,000 $ 250,000 Priority
Fire Radio Replacement Maintenance $ - $ - Priority
Facilities and Equipment Contingency N/A $ 100,000 $ 100,000 Priority Priority Priority Priority
Total Facility & Equipment Program $ 4,721,000 $ 4,721,000
FY 2026 Project Schedule
PLANNED FY27-30 CIP PROJECTS
Facilities & Equipment Program Planned Capital Improvement Projects
Page 26 of 50
TOWN OF HILTON HEAD ISLAND
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
STORMWATER PROGRAM
Stormwater Maintenance & Improvements Maintenance $ 1,800,000 $ 1,800,000 Priority Priority Priority Priority ✓ ✓ ✓
Stormwater Maintenance Agreement Program Maintenance $ 2,000,000 $ 2,000,000 Priority Priority Priority Priority ✓
Moonshell / Folly Field Neighborhood Drainage
Improvements Maintenance $ 60,000 $ 60,000 Priority ✓
75 Helmsman Way Drainage Improvements Maintenance $ 50,000 $ 50,000 Priority ✓
Bryant Road Pond Restoration Maintenance $ 25,000 $ 25,000 ✓
Cordillo Courts Drainage Improvements Maintenance $ 95,880 $ 95,880 ✓
Gum Tree Road Drainage Improvements Maintenance $ 120,000 $ 120,000 ✓
Jarvis Creek Outfall Maintenance $ 50,000 $ 50,000 Priority Priority Priority ✓ ✓
Jarvis Creek Pump Station - Pump Replacements Maintenance $ 300,000 $ 300,000 Priority Priority Priority ✓
Main Street Drainage Improvements Maintenance $ 50,000 $ 50,000 Priority Priority Priority ✓
Old Woodlands-26 Indian Trail Drainage Improvements Maintenance $ 80,000 $ 80,000 Priority ✓ ✓
FY 2026 Project Schedule
Stormwater Program Planned Capital Improvement Projects
Page 27 of 50
TOWN OF HILTON HEAD ISLAND
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
Palmetto Hall Outfall Improvements Maintenance $ 150,000 $ 150,000 Priority Priority ✓
Water Level Monitoring Maintenance $ 75,000 $ 75,000 Priority Priority Priority Priority
Weather Monitoring Maintenance $ 50,000 $ 50,000 Priority Priority Priority Priority
Central Island Pump Station Overhaul and Resiliency
Improvements Maintenance $ 750,000 $ 750,000 Priority ✓ ✓
Ashmore Channel Resilience/278 Backflow Prevention Port
Royal Maintenance $ - $ - Priority Priority Priority Priority
Gum Tree Channel Capacity Improvements at Chinaberry
Crossing Maintenance $ 120,000 $ 120,000 Priority ✓ ✓
24 Pope Avenue Outfall to Shipyard Maintenance $ - $ - Priority Priority
25 Dunnagans Alley Parking Lot Drainage Improvements Maintenance $ - $ - Priority
Airport Outfall Ditch Relocation Maintenance $ - $ - Priority Priority Priority
Arrow Road Laydown Yard Improvements Maintenance $ 75,000 $ 75,000 Priority ✓
Arrow Road Outfall at Greenery Maintenance $ - $ - Priority Priority Priority
Burkes Beach Area Drainage Improvements Maintenance $ - $ - Priority Priority Priority
FY 2026 Project Schedule
Stormwater Program Planned Capital Improvement Projects
Page 28 of 50
TOWN OF HILTON HEAD ISLAND
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
Gardner Channel Capacity Improvements at 278 Maintenance $ - $ - Priority Priority Priority
Marshland Road Pathway Drainage Issues Maintenance $ - $ - Priority Priority Priority
Muddy Creek South Outfall Maintenance $ - $ - Priority Priority
North Forest Beach Pipe Replacements Maintenance $ - $ - Priority Priority Priority
Shipyard Pump Station Overhaul Maintenance $ - $ - Priority Priority Priority
Squire Pope Outfalls-Backflow Prevention (2) Maintenance $ - $ - Priority Priority
The Links at Port Royal Improvements Maintenance $ - $ - Priority Priority Priority
Woodlake Villas/Mathews Drive Outfall Improvements Maintenance $ - $ - Priority Priority Priority
Woodward Ave Pipe Rehabilitation Maintenance $ - $ - Priority Priority Priority
Arrow Road Powerline Channel Excavation - Capacity
Improvements Maintenance $ - $ - Priority
Stormwater Contingency N/A $ 500,000 $ 500,000 Priority Priority Priority Priority
Total Stormwater Program $ 6,350,880 $ 6,350,880
FY 2026 Project Schedule
Stormwater Program Planned Capital Improvement Projects
Page 29 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
FLEET PROGRAM
Staff Vehicle Replacement Maintenance $ 80,000 $ 80,000 Priority Priority Priority Priority
Engine/Pumper Replacement/Quint Company
Replacement Maintenance $ - $ -
Support Vehicle Replacement Maintenance $ - $ - Priority
Ladder Truck Replacement Maintenance $ - $ - Priority
New Staff Vehicles Maintenance $ - $ -
Specialty Vehicles Maintenance $ - $ - Priority Priority
Battalion 1 Replacement Maintenance $ - $ - Priority
Medic Unit Replacement Maintenance $ - $ - Priority
Fleet Contingency N/A $ 100,000 $ 100,000 Priority Priority Priority Priority
Total Fleet Program $ 180,000 $ 180,000
FY 2026 Project Schedule
Fleet Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 30 of 50
Project Project Type
FY 2026
Proposed
Budget
FY 2026
Priority 1
FY 2027
Priority 2
FY 2028
Priority 3
FY 2029
Priority 4
FY 2030
Priority 5
FY 2026
Planning
Commission
Priority
Design Permitting Construction
LAND ACQUISITION PROGRAM
Land Acquisition Administration Discretionary $ 250,000 $ 250,000 Priority Priority Priority Priority
Total Land Acquisition Program $ 250,000 $ 250,000
Total Capital Improvements Program Fund $ 77,687,380 $ 77,687,380 Priority Priority Priority Priority
FY 2026 Project Schedule
Land Acquisition Program Planned Capital Improvement Projects
PLANNED FY27-30 CIP PROJECTS
Page 31 of 50
CIP Funding Strategy
Page 32 of 50
CIP Funding Strategy
TOWN OF HILTON HEAD ISLAND
• Potential Funding Sources
• Cash - Balances by Key Fund
• Beach Renourishment: Review
• Total Outstanding Debt by Fiscal Year
• Debt Service Fund’s Accumulated Balance
• Potential General Obligation Debt
• Various Payback Scenarios
• Possible Schedule: G.O. Bonds
• Stormwater Utility Fund Option
• Tax Increment Financing (TIF) Overview
• Grants
Page 33 of 50
• Beach Preservation Fee Fund
• Debt Service Fund Accumulated Balances
• General Obligation Property Debt Service Tax
Millage
• Stormwater Utility Fee Fund (9/30/25
Workshop)
• Potential Establishment of New Tax Increment
Finance (TIF) District
• Cash-on-Hand in Various Funds
Potential Funding Sources of
Capital Projects
TOWN OF HILTON HEAD ISLAND
Page 34 of 50
CIP Funding Source: Cash
Estimated FY25 Revenues, & Fund Balances & Minimum Fund Balance Policy by
Key Fund
Fund
Estimated
FY25
Revenues
Preliminary Non-
Encumbered Fund
Balance as of 6/30/2025*
Min Fund
Balance
Reserve Policy
General ** $ 50,828,891 $ 23,901,948
Stormwater $ 5,400,000 $ 14,235,324 $ 5,000,000
Real Estate Transfer $ 5,200,000 $ 13,976,146 $ 1,000,000
Beach Preservation $ 13,000,000 $ 44,075,488 $ 20,000,000
Htax $ 10,500,000 $ 28,803,714 $ 5,000,000
Disaster Fund ** $ 37,543,869 $ 36,000,000
Palmetto Electric $ - $ 1,273,557
Debt Service $ 6,600,000 $ 14,243,513
Total $ 204,980,502 $ 90,901,948
* Town investments held at SC Local Government Investment
Pool (LGIP) + Wells Fargo Securities
** Multiple Revenue Sources
All Current Fund Balances are above the Minimum Fund Balance
Policies adopted via the 2026 Budget Ordinance
TOWN OF HILTON HEAD ISLAND
Page 35 of 50
Beach Renourishment: Review of
Funding Option
TOWN OF HILTON HEAD ISLAND
• Approximately $47.5M in Expected Capital
Expenditures
• Cash Financed: Approximately $28.5M (60%)
• Debt Financed: Approximately $19M (40%)
• Source of Repayment: Future Beach Preservation Fee
Revenues
• Term: 7 Years
• Approximate Annual Payment: $3.1M
• Series 2017 Beach Preservation Fee Bonds:
$30,075,000 in Principal,10 Year Term, Annual
Payments of $4.0M
• Annual Beach Preservation Fee Revenues:
o FY2017:$6,860,758
o FY2024: $13,889,049
• Closing Date: Late November 2026
Page 36 of 50
Beach Renourishment:
Anticipated Bond Issuance Schedule
• 9/23/25: Finalize Supplemental
Ordinance/Bank RFP
• 9/30/25: F&A Committee: Review Plan of
Finance/Ordinance
• 10/7/25: Town Council Meeting: 1st Reading
of Ordinance
• 10/8/25: Send RFP to Bidders
• 10/21/25: Town Council Meeting: 2nd
Reading of Ordinance
• 10/29/25: Bank Bids Due
• 11/13/25: Closing
• 8/1/26: First Principal & Interest Payment
Due
TOWN OF HILTON HEAD ISLAND
Page 37 of 50
Total Debt Outstanding by Fiscal Year
$180,605,264
$168,360,387
$150,377,438
$132,790,172
$115,254,939
$98,338,702
$80,307,766
$-
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
$160,000,000
$180,000,000
$200,000,000
2018 2019 2020 2021 2022 2023 2024
TOWN OF HILTON HEAD ISLAND
Page 38 of 50
Debt Service Fund’s Accumulated
Balance as a Source of General
Obligation (GO) Debt Payment
• Debt Service Fund balances can only be used to
pay back debt
• Fund Balance has grown to $14.2M (anticipated
balance as of 9/1/25) over the past several years
due to conservative Debt Service Property Tax
Millage Projections and No New Debt
• $2.5 Million is Reasonable Minimum Balance to
Maintain if future debt service property tax
collections were to come in below estimates
• Town can set policy to maintain a future Debt
Service Fund Minimum Balance in $2.5M range
• Thus, a Potential GO Bond Issue can utilize
approximately $11.7 million in Debt Service Funds
to pay back a portion of the Proposed 2026 Debt
Issuance
TOWN OF HILTON HEAD ISLAND
Page 39 of 50
• Debt Repayment Source: Debt Service Fund’s Existing
Excess Balance pays back approximately $11.7M (about
May 1, 2026)
• Debt Repayment Source: Debt Service Millage Capacity
(approximately 2 Mills)
• Debt Service Millage is not to exceed the current 5.1 Mills
over payback period
• Debt Payback Scenarios include 1, 5, 10, 15, 20, & 25-
Year (see following slide)
• Possible Closing Date: Late February 2026
• Critical Timeline: First Principal & Interest Payment
Occurs in FY26 to Justify the 5.1 Debt Service Millage to
be collected in FY26
TOWN OF HILTON HEAD ISLAND
Potential General Obligation Debt
Funding Strategy for a Portion of Planned
Capital Projects
Page 40 of 50
Various Payback Scenarios if Issuing
Debt and Paying Back via 2 Mills of
Debt Service Millage
Payback
Period
(Years)
Estimated
Interest Rate
Bond
Proceeds
(Millions)
1 2.75% $2.6
5 3.00% $12.2
10 3.50% $22.2
15 4.00% $29.6
20 4.35% $35.1
25 4.65% $38.9
TOWN OF HILTON HEAD ISLAND
Page 41 of 50
General Obligation Bond Issue:
Possible Schedule
TOWN OF HILTON HEAD ISLAND
• 10/30/25: F&A Committee: Review Plan of
Finance/Ordinance
• 11/4/25: Town Council Meeting: 1st Reading of
Ordinance
• 12/9/25: Town Council Meeting: 2nd Reading of
Ordinance
• 2/3/25: Publish Preliminary Notice of
Competitive Sale
• 2/10/25: Pricing Bonds via Municipal Finance
Buyside Market
• 2/26/25: Closing
• 5/1/26: First Principal & Interest Payment,
including approximately $11.7 million in
Principal Paid back via Accumulated Debt
Service Fund Balance
• Activities throughout Timeline: Offering
Document Production/ Distribution, Rating
Agency Preparation
Page 42 of 50
Tax Increment Financing (TIF) Overview
What is a TIF District?
• A TIF is a unique local government funding structure that “freezes” property taxes received by various
“partner” taxing bodies (school districts, counties, etc.) within a specified geographic area.
• The incremental property taxes collected post-TIF formation are used solely for the benefit of public
infrastructure projects within the TIF.
How TIFs Work?
• The Town creates the TIF District and identifies specific public infrastructure: Capital projects to be
funded in the TIF Redevelopment Plan.
• The base property value is recorded and “frozen” for all overlapping taxing districts in the TIF. The
participating districts continue to receive annual property tax revenues assessed on this base value only.
• Overlapping “Partner” Local Taxing Districts must agree on specific terms of participation.
• Future property value increases represents the “Incremental” Tax Revenue that is used to pay for the TIF
public infrastructure projects. TIF bonds are often issued and are paid back via these incremental
revenues.
• The Town manages the TIF for the benefit of all the partner districts (including the Town itself) and their
constituents.
TOWN OF HILTON HEAD ISLAND
Page 43 of 50
Tax Increment Financing (TIF) Overview
What are the TIF Benefits?
• Public infrastructure improvements without new taxes.
• Stimulates Investment: The Public infrastructure investment
encourages private development that might not occur
otherwise.
• Helps improve neighborhoods and communities that
otherwise may not have seen public and private investment
without the existence of the TIF.
• Post-TIF: Increased property values resulting from the TIF
will provide long-term benefits to all local taxing districts.
What are the TIF Risks?
• Revenue Uncertainty: If property values don’t rise as
expected, there may not be enough revenue to repay TIF
debts.
• Impact on Other Services: Other taxing bodies may be
concerned about lack of growth in their tax revenues for the
duration of the TIF (typically 20–30 years).
• Transparency and Oversight: Requires clear goals, project
guidelines, and public accountability.
TOWN OF HILTON HEAD ISLAND
Page 44 of 50
Examples of Infrastructure
Improvements Financed by the
Prior Hilton Head Island TIF
• USCB Campus
• Lowcountry Celebration Park
• Coligny Beach Park
• Coligny Circle Reconfiguration
• Mathews Drive Widening
• Land Acquisitions for Various
Projects, including Parks & Beach
Parking
TOWN OF HILTON HEAD ISLAND
Page 45 of 50
Hilton Head Island TIF
District Elements
• All Capital Projects to be located
within the prospective Hilton Head
Island TIF Boundaries can be funded
with TIF revenues
• TIF projects must benefit all the
participating TIF Partners
• Potential TIF partners: Beaufort
County, Beaufort County School
District, Hilton Head PSD(s)
• As the Property Values within the TIF
District increase, these incremental
property tax revenues pay for the
Capital Projects within the TIF District
TOWN OF HILTON HEAD ISLAND
Page 46 of 50
TAX INCREMENT FINANCE (TIF) DISTRICT FORMATION - CRITICAL EVENTS
TOWN OF HILTON HEAD ISLAND
1. Preparation of Redevelopment Plan
2. Meeting to discuss TIF and other financings
3. Discuss strategy on how to approach other Taxing Districts and begin negotiations
4. Adoption of Resolution (Notice of Public Hearing and Notice to Taxing Districts)
5. Notice to Taxing Districts (not less than 45 days before Public Hearing)
6. Publication of Notice of Public Hearing in The State (not less than 15 or more than 30 days prior to Public
Hearing)
7. Additional negotiations; reach agreement on Intergovernmental Agreement (IGA)
8. Public Hearing
• ** Sec. 31-6-80 of SC Code: if Taxing District does not file objection to redevelopment plan at or prior to date
of Public Hearing, Taxing District is deemed to have consented to Redevelopment Plan and issuance of
Bonds **
9. Enactment of Ordinance /Adoption of Resolution by other Taxing Districts approving IGA
10.First reading of Ordinance approving Redevelopment Plan and IGA and first reading of Bond Ordinance
11.Second reading and enactment of Ordinance approving Redevelopment Plan and IGA and second reading of
Bond Ordinance
12.Publication of notice of adoption of Ordinance approving Redevelopment Plan in The State (starts 20 day
challenge period)
13.County Auditor certifies initial assessed values in the TIF District
14.Sale and issuance of Bonds
Page 47 of 50
Other Capital Projects Funding Sources – Grants
Grant Funds Received FY25
Grantor/Program Capital Project(s) Amount Received
HUD/CDBG Taylor Park $ 160,266
HUD/CDBG Ford Shell Ring Park $ 7,163
HUD/CDBG Patterson Park $ 109,632
Grant Funds Applied for in FY25, Potentially Awarded in FY26
Grantor/Program Capital Project(s) Amount Applied for
Senator Graham's Earmarks Northpoint Housing $ 2,600,000
Senator Graham's Earmarks
Central Island Stormwater Pump
Station $ 9,000,000
Transportation Set-aside Program (TAP) Wexford Pathway Project $ 958,332
TOWN OF HILTON HEAD ISLAND
Page 48 of 50
General Discussion
Page 49 of 50
TOWN OF HILTON HEAD ISLAND
Capital Improvements
Program Workshop
Town Council
August 26, 2025
Page 50 of 50