Foth Slide Deck
City of Isle of Palms · Charleston County · Agendas
Open the original document More from City of Isle of Palms
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Beach Management Alternatives AnalysisApproach, Findings, and Recommendations
September 22, 2026
Chris Creed, P.E.chris.creed@foth.comPresentation to City of Isle of Palms City Council
Page 2
◆Recap of Study Baseline Definition◆Summary of Assumed Initial Conditions§Volume Change Rates§2026 Project◆Alternatives and Expected Performance◆Cost Analysis - Assumptions and Results◆Future Management
Outline
Page 3
◆Baseline Development:§Assumed to represent the primary dune crest of minimum beach position§Identified as the seaward-most occurrence of:•50-ft offset from seaward edge of development,•2017 SCDES Baseline, or•Seaward edge of 2026 dune, where constructed.
Alternatives Study Baseline Definition
Page 4
Alternatives Study Baseline Definition
Development Line(estimated)
2017 SCDES2026 Dune50-ft(min.)
~175 to 200-ft
The “baseline” is assumed to be the primary dune crest that is identified by the seaward most occurrence of;(1)50-ft seaward of development line,(2)the 2017 SCDES line, or(3)the seaward edge of the 2026 constructed dune.
MHHW
Baseline
Page 5
Alternatives Study Baseline Definition
Study Baseline
Seaward Edge of Infrastructure (typ.)50-ft Seaward of Seaward Edge of Infrastructure (typ.)
2017 SCDES Baseline
2026 Dune
Beach MonitoringStations
Atlantic Ocean
BreachInlet
Page 6
Alternatives Study Baseline Definition
Seaward Edge of Infrastructure (typ.)Study Baseline
50-ft Seaward of Seaward Edge of Infrastructure (typ.)
2017 SCDES Baseline
2026 Dune
Beach MonitoringStations
Page 7
Page 7
Initial Conditions
Page 8
Volume Change Rates
“Low Rate”Survey Period: April 2018 – September 2024“High Rate”Survey Period: July 2021 – September 2024
Note: Volume change rates were derived from volume data reported by CSE.
02,0004,000SCALE (FT)
Palm BlvdWaterway BlvdPalmetto DrOcean Blvd14th Ave 41st Ave WildDunesBreachInlet
DeweesInlet
Atlantic Ocean
703
517
PierReach 1Reach 2Reach 3Reach 4Reach 5Reach 6Reach 7
04,0008,00012,00016,00020,00024,00028,00032,00036,00040,000Distance from South End (ft)
-80-60-40-20020406080Volume Change Rate (cy/ft/yr)4+008+0012+0016+0020+0030+0040+0050+0060+0070+0080+0090+00100+00110+00120+00130+00140+00150+00160+00170+00180+00190+00200+00210+00220+00230+00240+00250+00260+00270+00280+00290+00300+00310+00320+00330+00340+00350+00360+00370+00
Jul. 2021 - Sep. 2024 Rate
-303,000 cy/yr (gross)-400,000 cy/yr (gross)
Page 9
Post-2026 Beach Conditions (Projected)
This is the starting condition for the alternatives analysis
Based on June. 2026 Survey
Page 10
Page 10
Alternatives
Page 11
Alternatives◆No-Action (“Do Nothing”)◆Beach Renourishment Only (Low and High Sand Loss Rates)§Scheduled (5-yr, 7-yr, and 10-yr intervals)§Triggered (Interval Required to Protect Baseline Condition)◆USACE Breach Inlet ICWW Maintenance – Reach 1 (150,000 cy every 3 yrs)◆Dewees Inlet Shoal Management – Reaches 5 and 6 (700,000 cy every 7 yrs)◆Terminal Groin (R1)◆T-Groins/Breakwaters and/or Geotubes (R5/R6) – Reaches 5 and 6 (last line of defense)
Page 12
No Action (Low Sand Loss Rate)
Note: Does not consider possible future AICWW beach disposal.
Page 13
No Action (High Sand Loss Rate)
Note: Does not consider possible future AICWW beach disposal.
Page 14
2026 Project PerformanceAssuming recent beach change conditions continue, the 2026 project is expected to maintain beach conditions seaward of the entire assumed beach management baseline for no more than about 3 years.
Page 15
[A]Volume LostSeaward ofBaseline(cy)
[B]Volume LostLandward ofBaseline(cy)
[C = A + B]Total Volume Lost(Required RenourishmentVolume FollowingFirst Renourishment)(cy)1 158,300 515,300 673,600 1,188,9002 218,900 11,000 229,900 240,9003 0 0 0 04 60,800 0 60,800 60,8005 675,900 154,700 830,600 985,3006 715,100 289,600 1,004,7001,294,300Total1,829,000 970,600 2,799,6003,770,200
7-Year Project Interval after Completion of 2026 ProjectJuly 2021 - September 2024 ("High" Erosion Rate)Predicted Preformance of 2026 Project after 7 Years
[D = C + B]Volume Required for First Renourishment Event (cy)Reach
[A]Volume LostSeaward ofBaseline(cy)
[B]Volume LostLandward ofBaseline(cy)
[C = A + B]Total Volume Lost(Required RenourishmentVolume FollowingFirst Renourishment)(cy)1 146,300 110,900 257,200 368,1002 155,900 0 155,900 155,9003 0 0 0 04 0 0 0 05 816,100 176,900 993,000 1,169,9006 674,300 41,400 715,700 757,100Total1,792,600 329,200 2,121,8002,451,000
7-Year Project Interval after Completion of 2026 ProjectApril 2018 - September 2024 ("Low" Erosion Rate)
Reach
Predicted Preformance of 2026 Project after 7 Years
[D = C + B]Volume Required for First Renourishment Event (cy)
Renourishment - Scheduled◆Required Future Volume Following Completion of 2026 Project§Restore Minimum AND Maintain Baseline Beach Condition§Future Advance Fill required for 5-, 7-, and 10-year renourishment intervalsExample…
Page 16
Renourishment - Triggered◆Implement renourishment on scheduled intervals regardless of beach condition between intervals
[A]Volume LostSeaward ofBaseline(cy)
[B]Volume LostLandward ofBaseline(cy)
[C = A + B]Total Volume Lost(Required RenourishmentVolume FollowingFirst Renourishment)(cy)1 97,300 13,000 110,300 123,3002 66,800 0 66,800 66,8003 0 0 0 04 0 0 0 05 418,500 7,100 425,600 432,7006 306,700 0 306,700 306,700Total 889,300 20,100 909,400 929,500
Reach
April 2018 - September 2024 ("Low" Erosion Rate)Predicted Preformance of 2026 Project after 3 Years
[D = C + B]Volume Required for First Renourishment Event (cy)
Trigger - 3 Years Until Erosion into Baseline[Between Stations 12+00 and 30+00]
[A]Volume LostSeaward ofBaseline(cy)
[B]Volume LostLandward ofBaseline(cy)
[C = A + B]Total Volume Lost(Required RenourishmentVolume FollowingFirst Renourishment)(cy)1 88,100 8,100 96,200 104,3002 32,900 0 32,900 32,9003 0 0 0 04 8,700 0 8,700 8,7005 118,700 0 118,700 118,7006 141,700 1,900 143,600 145,500Total 390,100 10,000 400,100 410,100
Predicted Preformance of 2026 Project after 1 Year
[D = C + B]Volume Required for First Renourishment Event (cy)
July 2021 - September 2024 ("High" Erosion Rate)
Reach
Trigger - 1 Year Until Erosion into Baseline[Between Stations 12+00 and 30+00]
Page 17
Breach Inlet AICWW Beach Disposal
Note: Concept only.
Goals:•Beneficial use of available dredge material•Supplemental sand source for Reaches 1 and 2•Extend time between required renourishments•Reduce sand need from offshore borrow areasAssumptions:•3 yr interval (more or less)•~150,000 cy/event (equivalent to ~50,000 cy/yr)•All material placed in Reaches 1 and 2•Available material is suitable for beach placement•Material provided at no cost to the City
Breach InletReach 2Reach 1
Atlantic Intracoastal Waterway (AICWW)
Page 18
Dewees Inlet Shoal Management
Note: Concept only.
Goals:•Collect ebb shoal sand before migrating shoals approach IOP shoreline•Place sand along Reaches 5 and 6•Reduce impacts of future shoal attachments•Extend time between required renourishments•Reduce sand need from offshore borrow areasAssumptions:•7 yr interval•700,000 cy/event (equivalent to 100,000 cy/yr)•All material placed in Reaches 5 and 6
-22-20
-18
-16
-16-16
-14
-14-14
-12
-12
-12
-10
-10 -10
-10-10
-8
-8-8 -8-8
-8
-8-8
-6-6-6 -6
-6
-6-6
-6
-6-4-4
-4
-4-4 -4-4
-2
-2-2
-2
0
0
0
0
2
2
4
4
6
6
8
8
8
8
1010
10
10
10
12
12
12
12
14
14
GrandPavilion
2,384,0002,386,0002,388,0002,390,0002,392,0002,394,0002,396,0002,398,0002,400,000Easting (ft-NAD83)350,000
352,000
354,000
356,000
358,000
360,000
01,0002,000SCALE (FT)
Palmetto Dr.
Palm Blvd.
Wild Dunes
Bathymetric Survey: June 2026
Ocean ClubVillas
Beach ClubVillas
-45-40-35-30-25-20-15-10-50510152025
Dredge Access
Positive preliminary feedback from regulatory agencies
Page 19
Renourishment – with AICWW and Shoal Mgt Sand◆Demand on offshore sand can be reduced with use of beach compatible sand from AICWW and Dewees Inlet Shoal Management.◆Proposed sand volume from AICWW beach disposal MAY NOT be sufficient to maintain Baseline conditions along Reach 1 without sand from offshore.◆Available volumes and schedule will need to be confirmed.
[A]VolumeLostSeaward ofBaseline(cy)
[B]VolumeLostLandward ofBaseline(cy)
[C = A + B]TotalVolumeLost(cy)
[D = C + B]Future Volume Required to Restore and Maintain Beach Seaward of Baseline (cy)
Volume Available from AICWW (Reaches 1&2) and Dewees Shoal (Reaches 5&6) (cy)
Sand Volume Needed from Offshore for Full Restoration and Maintenance(cy)1 146,300110,900257,200368,100 174,0002 155,900 0 155,900155,900 03 0 0 0 0 0 04 0 0 0 0 0 05 816,100176,900993,0001,169,900 819,9006 674,30041,400 715,700757,100 407,100Total1,792,600329,2002,121,8002,451,0001,050,0001,401,000
Reach
April 2018 - September 2024 ("Low" Erosion Rate)
700,000
350,000
7-Year Project Interval after Completion of 2026 Project
EXAMPLE
Page 20
Renourishment with Structures◆Terminal Groin (Reach 1)
Page 21
7-Year Condition
VolumeLossBeyondBaseline(typ.)
Post-Project Beach Volume PerformanceRelative to Baseline
“Low” rate (2018-2024)
“High” rate (2021-2024)
Anticipated Sand Loss Landward of Baseline (Reach 1)
Page 22
Reach 1Reach 2
6th Avenue
Area of Highest Erosionand Volume Loss (typ.)
Beach MonitoringStations
Pier14th Avenue
Anticipated Sand Loss Landward of Baseline (Reach 1)
Page 23
Reach 1Reach 2
6th Avenue
Terminal Groin(~1,200 ft)Concept shorelineresponse
14th Avenue
Pier
Goals:•Reduce sand loss from the southern end of the island•Anchor shoreline position away from Baseline•Extend time between required renourishment events•Reduce demand on sand from offshore borrow areasAssumptions:•~1,200 feet long (most of structure to be buried)•~15,000 tons of rock (with stone-filled mattress foundation)•Reduces sand loss:•Reach 1 by 50%•Reach 2 by 25%
Terminal Groin (Reach 1)
Note: Structures shown are conceptual and do not represent a final design. Quantities are assumed.
Page 24
Renourishment with Structures◆Terminal Groin (Reach 1)◆T-Groins/Breakwaters (Reaches 5 and 6)
Page 25
7-Year Condition
VolumeLossBeyondBaseline(typ.)
Post-Project Beach Volume PerformanceRelative to Baseline
“Low” rate (2018-2024)
“High” rate (2021-2024)
Anticipated Sand Loss Landward of Baseline (Reaches 5 &6)
Page 26
Reach 5Reach 6
Area of Highest Erosion (typ.)
2026 Beach Fill
Wild Dunes Resort
Anticipated Sand Loss Landward of Baseline (Reaches 5 &6)
Page 27
Breakwater (typ.)T-groin (typ.)
2026 Beach Fill
Reach 5Reach 6Wild Dunes Resort
T-Groins and Breakwaters (Reaches 5 and 6)
Note: Structures shown are conceptual and do not represent a final design. Quantities are assumed.
Goals:•Provide last line of defense to upland•Anchor shoreline position at Baseline under most eroded conditions•Maintain recreational beach seaward of BaselineNote: Not intended to reduce sand loss rate from renourishment but may allow for smaller fill volumes and longer periods between renourishments
Assumptions:•Reach 5 (5, T-groins and 2, breakwaters)•Reach 6 (2, T-groins and 2, breakwaters)•T-Groin = 2,800 tons with foundation•Breakwater = 1,600 tons with foundation
Page 28
T-Groins and Breakwaters (Reach 5)
Note: Structures shown are conceptual and do not represent a final design.
Concept of Intended Residual Shoreline (typ.)
Reach 5Reach 6
Page 29
Renourishment with Structures◆Terminal Groin (Reach 1)◆T-Groins/Breakwaters (Reaches 5 and 6)◆Sand filled Geotubes (Reaches 5 and 6)
Page 30
Geotubes (Reaches 5 and 6)
Geotubes (typ.)
2026 Beach Fill
Reach 5Reach 6Wild Dunes Resort
Note: Structures shown are conceptual and do not represent a final design. Quantities are assumed.
Goals:•Provide last line of defense to upland•Anchor shoreline position at Baseline under most eroded conditionsNote: Not intended to maintain recreational beach seaward of Baseline
Assumptions:•Reach 5 = 3,300 feet•Reach 6 = 1,700 feet
Page 31
Beach Management Elements Summary
Note: Concept. Does not represent a final design.
RenourishmentRenourishment
AICWW Beach Disposal
Dewees Inlet Shoal MgtT-Groins/Breakwatersor GeotubesOffshore Borrow Areas
Breach InletReach 2Reach 1 Reach 5Reach 6Terminal Groin
Page 32
Known Offshore Sand Sources
Sand Availability: no more than ~25 Mcy (pre-2026) (ref: CSE)◆Depleted: A, B, C, F◆Partially Depleted: E◆Available: D, G◆2026 Project: Area 1◆Future: Area 2-5
Sand Demand:PlanningPeriod(yrs)
TotalSandDemand(cy)
Total SandDemand with20% Contingency(cy)
Low303,000 50 15,150,000 18,200,000
High400,000 50 20,000,000 24,000,000
AnnualSand Loss(cy/yr)
Page 33
◆Offshore sand for continued renourishment§Mob/Demob = $1.5M§Sand = $9/cy (ref: recent Marinex proposal to City of IOP)§As needed◆Dewees Inlet Shoal Management§Mob/Demob = $1.0M (assumed)§Sand = $7.5/cy (assumed)§700,000 cy every 7 years (equivalent to 100,000 cy/yr – Reaches 5 and 6 only)◆Breach Inlet AICWW Beach Disposal§No cost to the City of IOP (ref: communications between USACE and City of IOP)§150,000 cy every 3 years (equivalent to 50,000 cy/yr – Reaches 1 and 2 only)
Cost Assumptions - Sand
Page 34
◆Rock - Effective “all-in” unit cost = $275/ton (recent market conditions in SC & NC)§Terminal Groin (Reach 1) ~$4.5 to $5.5M§T-Groins/Breakwaters (Reach 5) ~$4 to $5M§T-Groins/Breakwaters (Reach 6) ~$3.5 to $4M
◆Geotubes – Effective “all-in” unit cost = $570/ft (recent market conditions in NC)§Reaches 5 & 6 (~5,000 feet) ~$2.9M
Cost Assumptions - Structures
~$7.5 to $9M
Page 35
◆Planning, Engineering, and Design (PED) = 5% of construction cost◆Const. Eng. and Inspection (CEI) = 7% of construction cost◆Contingency = 10% (Note: The assumed costs are based upon proposals from industry and recent market examples, so only 10% contingency is applied to accommodate uncertainties with future required quantities.)
◆Planning period (n) = 50 years◆Discount rate (i) = 3.25% (2026 USACE planning guidance)
Cost Assumptions - Other
Page 36
Alterna(ve
FutureRenourish-mentEventVolume(cy)
FutureRenourish-mentEventCost($)
Supplemental Volume from Dewees Inlet and AICWW(cy)
Dewees InletShoal Mgt($)
Breach InletAICWW Beach Disposal($)
TerminalGroin(Rch 1)($)
T-Groins/Breakwater(Rch 5/6)($)
Average Annual Equivalent Cost(AAEC)($/yr)
5-Yr Interval (Low)1,515,600 18,652,973$ - -$ -$ -$ -$ 6,442,200$
5-Yr Interval (High)1,999,700 24,020,674$ - -$ -$ -$ -$ 8,440,800$
7-Yr interval (Low)2,121,800 25,374,518$ - -$ -$ -$ -$ 6,208,500$
7-Yr Interval (High)2,799,600 32,889,965$ - -$ -$ -$ -$ 8,282,300$
10-Yr Interval (Low)3,031,300 35,459,054$ - -$ -$ -$ -$ 6,357,200$
10-Yr Interval (High)3,999,500 46,194,456$ - -$ -$ -$ -$ 8,628,400$
3-Yr Interval (Low)909,400 11,931,427$ - -$ -$ -$ -$ 6,636,500$
1-Yr Interval (High)400,100 6,284,309$ - -$ -$ -$ -$ 10,915,400$
7-Yr Internval (Low)1,071,800 13,732,118$ 1,050,000 7,700,000$ -$ -$ -$ 5,266,000$
7-Yr Interval (High)1,749,600 21,247,565$ 1,050,000 7,700,000$ -$ -$ -$ 7,339,800$
7-Yr Interval (Low)1,008,000 13,024,704$ 1,050,000 7,700,000$ -$ 5,082,000$ 8,808,800$ 5,605,700$
7-Yr Interval (High)1,295,000 16,206,960$ 1,050,000 7,700,000$ -$ 5,082,000$ 8,808,800$ 7,687,800$
Renourishment - Scheduled Interval - Offshore Sand / Supplemental Sand / Terminal Groin (Reach 1) & T-Groins/Breakwaters (Reaches 5 & 6)
Renourishment - Scheduled Interval - Offshore Sand Supplemented with Breach Inlet AICWW and Dewees Inlet Shoal Management
Renourishment Only - Scheduled Interval - Offshore Sand
Renourishment Only - Triggered Interval - Offshore Sand
Cost Summary (Escalated Future Costs; 2.5%)
Details provided on following slideNote: Future nourishment event volume and “cost” applies to all renourishments after first event. The volume of the first renourishment event is increased to offset initial losses landward of Baseline.
Page 37
Example of Event Cost and 50-yr Cost Stream for Computation of AAEC (preliminary)
EVENT COST
COST STREAM
AAECExample is for 7-Year periodic renourishment, supplemental sand, Terminal Groin (Reach 1), and Groins/Breakwater (Reaches 5 & 6)
ItemQuantityUnit CostUnitsTotalDredge Mob/Demob1 1,500,000.00$ LS1,500,000.00$ Sand 1,227,000 9.00$ cy11,043,000.00$ 12,543,000.00$ 5%627,150.00$ 7%878,010.00$ 14,048,160.00$ 10%1,404,816.00$ 15,452,976.00$
ItemQuantityUnit CostUnitsTotalDredge Mob/Demob1 1,500,000.00$ LS1,500,000.00$ Sand 1,008,000 9.00$ cy9,072,000.00$ 10,572,000.00$ 5%528,600.00$ 7%740,040.00$ 11,840,640.00$ 10%1,184,064.00$ 13,024,704.00$
ItemQuantityUnit CostUnitsTotalDredge Mob/Demob1 1,000,000.00$ LS1,000,000.00$ Sand 700,000 7.50$ cy5,250,000.00$ 6,250,000.00$ 5%312,500.00$ 7%437,500.00$ 7,000,000.00$ 10%700,000.00$ 7,700,000.00$
ItemQuantityUnit CostUnitsTotalTerminal Groin15,000 275.00$ tons4,125,000.00$ 4,125,000.00$ 5%206,250.00$ 7%288,750.00$ 4,620,000.00$ 10%462,000.00$ 5,082,000.00$
ItemQuantityUnit CostUnitsTotalBreakwaters6,400 275.00$ tons1,760,000.00$ T-groins19,600 275.00$ tons5,390,000.00$ 7,150,000.00$ 5%357,500.00$ 7%500,500.00$ 8,008,000.00$ 10%800,800.00$ 8,808,800.00$
Contingency
Future Maintenance (Normal Advance Fill after First Renourishment)
subtotal ConstructionPED/PermittingCEI/Monitoringsubtotal Project
CEI/Monitoring
Total
Terminal Groin (Reach 1)
subtotal ConstructionPED/PermittingCEI/Monitoringsubtotal ProjectContingencyTotalT -Groins/Breakwaters (Reaches 5 and 6)
subtotal ConstructionPED/Permitting
CEI/Monitoringsubtotal ProjectContingencyTotal
subtotal ProjectContingencyTotal
Dewees Shoal Dredging
subtotal ConstructionPED/Permitting
ContingencyTotal
Restore Baseline and Replace Advance Fill with First Renourishment
subtotal ConstructionPED/PermittingCEI/Monitoringsubtotal Project
Base Costs
TotalCostRenourisment (Offshore Sand)TerminalGroin(Reach 1)T-Groins/Breakwaters(Reaches 5 & 6)DeweesShoalMgtCostEscolation FactorRenourisment (Offshore Sand)TerminalGroin(Reach 1)T-Groins/Breakwaters(Reaches 5 & 6)DeweesShoalMgtRenourisment (Offshore Sand)TerminalGroin(Reach 1)T-Groins/Breakwaters(Reaches 5 & 6)DeweesShoalMgtPresentWorthCost02026-$ -$ -$ -$ -$ 1260.04-$ -$ -$ -$ -$ -$ -$ -$ -$ 12027-$ -$ 1292.80-$ -$ -$ -$ -$ -$ -$ -$ -$ 220285,082,000$ -$ 5,082,000$ 1326.42-$ 5,349,724$ -$ -$ -$ 5,018,200$ -$ -$ 5,018,200$ 320298,808,800$ -$ 8,808,800$ 1360.90-$ -$ 9,513,901$ -$ -$ -$ 8,643,500$ -$ 8,643,500$ 42030-$ -$ 1396.29-$ -$ -$ -$ -$ -$ -$ -$ -$ 52031-$ -$ 1432.59-$ -$ -$ -$ -$ -$ -$ -$ -$ 62032-$ -$ 1469.84-$ -$ -$ -$ -$ -$ -$ -$ -$ 7203323,152,976$ 15,452,976$ 7,700,000$ 1508.0518,494,540$ -$ -$ 9,215,569$ 14,784,700$ -$ -$ 7,367,000$ 22,151,700$ 82034-$ -$ 1547.26-$ -$ -$ -$ -$ -$ -$ -$ -$ 92035-$ -$ 1587.49-$ -$ -$ -$ -$ -$ -$ -$ -$ 102036-$ -$ 1628.77-$ -$ -$ -$ -$ -$ -$ -$ -$ 112037-$ -$ 1671.12-$ -$ -$ -$ -$ -$ -$ -$ -$ 122038-$ -$ 1714.56-$ -$ -$ -$ -$ -$ -$ -$ -$ 132039-$ -$ 1759.14-$ -$ -$ -$ -$ -$ -$ -$ -$ 14204020,724,704$ 13,024,704$ 7,700,000$ 1804.8818,656,573$ -$ -$ 11,029,472$ 11,922,600$ -$ -$ 7,048,500$ 18,971,100$ 152041-$ -$ 1851.81-$ -$ -$ -$ -$ -$ -$ -$ -$ 162042-$ -$ 1899.96-$ -$ -$ -$ -$ -$ -$ -$ -$ 172043-$ -$ 1949.35-$ -$ -$ -$ -$ -$ -$ -$ -$ 182044-$ -$ 2000.04-$ -$ -$ -$ -$ -$ -$ -$ -$ 192045-$ -$ 2052.04-$ -$ -$ -$ -$ -$ -$ -$ -$ 202046-$ -$ 2105.39-$ -$ -$ -$ -$ -$ -$ -$ -$ 21204720,724,704$ 13,024,704$ 7,700,000$ 2160.1322,328,699$ -$ -$ 13,200,375$ 11,407,000$ -$ -$ 6,743,600$ 18,150,600$ 222048-$ -$ 2216.29-$ -$ -$ -$ -$ -$ -$ -$ -$ 232049-$ -$ 2273.92-$ -$ -$ -$ -$ -$ -$ -$ -$ 242050-$ -$ 2333.04-$ -$ -$ -$ -$ -$ -$ -$ -$ 252051-$ -$ 2393.70-$ -$ -$ -$ -$ -$ -$ -$ -$ 262052-$ -$ 2455.94-$ -$ -$ -$ -$ -$ -$ -$ -$ 272053-$ -$ 2519.79-$ -$ -$ -$ -$ -$ -$ -$ -$ 28205420,724,704$ 13,024,704$ 7,700,000$ 2585.3026,723,570$ -$ -$ 15,798,554$ 10,913,700$ -$ -$ 6,452,000$ 17,365,700$ 292055-$ -$ 2652.52-$ -$ -$ -$ -$ -$ -$ -$ -$ 302056-$ -$ 2719.73-$ -$ -$ -$ -$ -$ -$ -$ -$ 312057-$ -$ 2788.65-$ -$ -$ -$ -$ -$ -$ -$ -$ 322058-$ -$ 2859.31-$ -$ -$ -$ -$ -$ -$ -$ -$ 332059-$ -$ 2931.77-$ -$ -$ -$ -$ -$ -$ -$ -$ 342060-$ -$ 3006.06-$ -$ -$ -$ -$ -$ -$ -$ -$ 35206120,724,704$ 13,024,704$ 7,700,000$ 3082.2331,860,172$ -$ -$ 18,835,232$ 10,401,500$ -$ -$ 6,149,200$ 16,550,700$ 362062-$ -$ 3160.33-$ -$ -$ -$ -$ -$ -$ -$ -$ 372063-$ -$ 3240.41-$ -$ -$ -$ -$ -$ -$ -$ -$ 382064-$ -$ 3322.52-$ -$ -$ -$ -$ -$ -$ -$ -$ 392065-$ -$ 3406.71-$ -$ -$ -$ -$ -$ -$ -$ -$ 402066-$ -$ 3493.03-$ -$ -$ -$ -$ -$ -$ -$ -$ 412067-$ -$ 3581.55-$ -$ -$ -$ -$ -$ -$ -$ -$ 42206820,724,704$ 13,024,704$ 7,700,000$ 3672.3037,959,606$ -$ -$ 22,441,122$ 9,906,900$ -$ -$ 5,856,800$ 15,763,700$ 432069-$ -$ 3765.35-$ -$ -$ -$ -$ -$ -$ -$ -$ 442070-$ -$ 3860.77-$ -$ -$ -$ -$ -$ -$ -$ -$ 452071-$ -$ 3958.60-$ -$ -$ -$ -$ -$ -$ -$ -$ 462072-$ -$ 4058.90-$ -$ -$ -$ -$ -$ -$ -$ -$ 472073-$ -$ 4161.75-$ -$ -$ -$ -$ -$ -$ -$ -$ 482074-$ -$ 4267.21-$ -$ -$ -$ -$ -$ -$ -$ -$ 49207520,724,704$ 13,024,704$ 7,700,000$ 4375.3445,226,739$ -$ -$ 26,737,337$ 9,435,900$ -$ -$ 5,578,300$ 15,014,200$ 502076-$ -$ 4486.21-$ -$ -$ -$ -$ -$ -$ -$ -$ 78,772,300$ 5,018,200$ 8,643,500$ 45,195,400$ 137,629,400$ 3.25%3.25%3.25%3.25%3.25%50505050500.04073 0.04073 0.04073 0.04073 0.04073 3,208,400$ 204,400$ 352,100$ 1,840,800$ 5,605,700$ Avg Annual Equivalent Cost
Year
Escalated CostsPresent Worth
Total Present WorthDiscount RateAmortization Period (years)Capital Recovery Factor
Page 38
Cost Summary (No Escalation of Future Costs)
Note: “Future nourishment event volume and “cost” applies to all renourishments after first event. The volume of the first renourishment event is increased to offset initial losses landward of Baseline.
Alterna(ve
FutureRenourish-mentEventVolume(cy)
FutureRenourish-mentEventCost($)
Supplemental Volume from Dewees Inlet and AICWW(cy)
Dewees InletShoal Mgt($)
Breach InletAICWW Beach Disposal($)
TerminalGroin(Rch 1)($)
T-Groins/Breakwater(Rch 5/6)($)
Average Annual Equivalent Cost(AAEC)($/yr)
5-Yr Interval (Low)1,515,600 18,652,973$ - -$ -$ -$ -$ 3,539,700$
5-Yr Interval (High)1,999,700 24,020,674$ - -$ -$ -$ -$ 4,685,700$
7-Yr interval (Low)2,121,800 25,374,518$ - -$ -$ -$ -$ 3,378,400$
7-Yr Interval (High)2,799,600 32,889,965$ - -$ -$ -$ -$ 4,575,300$
10-Yr Interval (Low)3,031,300 35,459,054$ - -$ -$ -$ -$ 3,352,600$
10-Yr Interval (High)3,999,500 46,194,456$ - -$ -$ -$ -$ 4,635,700$
3-Yr Interval (Low)909,400 11,931,427$ - -$ -$ -$ -$ 3,794,500$
1-Yr Interval (High)400,100 6,284,309$ - -$ -$ -$ -$ 6,288,700$
7-Yr Internval (Low)1,071,800 13,732,118$ 1,050,000 7,700,000$ -$ -$ -$ 2,871,900$
7-Yr Interval (High)1,749,600 21,247,565$ 1,050,000 7,700,000$ -$ -$ -$ 4,068,900$
7-Yr Interval (Low)1,008,000 13,024,704$ 1,050,000 7,700,000$ -$ 5,082,000$ 8,808,800$ 3,261,400$
7-Yr Interval (High)1,295,000 16,206,960$ 1,050,000 7,700,000$ -$ 5,082,000$ 8,808,800$ 4,898,100$
Renourishment - Scheduled Interval - Offshore Sand / Supplemental Sand / Terminal Groin (Reach 1) & T-Groins/Breakwaters (Reaches 5 & 6)
Renourishment - Scheduled Interval - Offshore Sand Supplemented with Breach Inlet AICWW and Dewees Inlet Shoal Management
Renourishment Only - Scheduled Interval - Offshore Sand
Renourishment Only - Triggered Interval - Offshore Sand
AAEC
Page 39
Cost Summary - Comments◆Cost-effectiveness benefits derived from…§Frequent, no cost sand from USACE AICWW Maintenance dredging§Potentially lower cost sand from Dewees Inlet shoal management compared to cost of sand from offshore§Reduced sand loss from terminal groin at southern end of the island§Potential increase in time between required renourishment along Reaches 5 & 6 with structural protection
Page 40
◆Establish appropriate beach management baseline◆Pursue agreement with Marinex for proposed renourishment pricing◆Pursue agreement with USACE to provide beach compatible sand to Reaches 1 and 2 from Breach Inlet AICWW Maintenance Dredging◆Investigate in more detail the feasibility, scope, and cost of Dewees Inlet Shoal Management (Consider a test project)◆Investigate in more detail the feasibility, scope, and cost of a Terminal Groin at the southern end of Reach 1◆Consider last line of defense structural solutions in Reaches 5 and 6 to compliment Dewees Inlet Shoal Management
Recommendations for Consideration
Beach Management Alternatives AnalysisApproach, Findings, and Recommendations
September 22, 2026
Chris Creed, P.E.chris.creed@foth.comPresentation to City of Isle of Palms City Council
Source: City of Isle of Palms website. First collected Oct 26, 2026.