Isle of Palms City Council Meeting
Tuesday, August 25, 2026
Purpose & Process
• Provide the City with the guidance
and resources needed to inform
future decision-making related to
improving safety, accessibility, and
connectivity.
• Three (3) main steps taken:
• Data Collection & Analysis
• Public Engagement
• Field Survey
• Needs Assessment
• Project Recommendations
Public Engagement
Online Public Survey
• Online Public Survey was live
from September 16th to
October 31st
• Consisted of 15 questions
related to mobility, safety,
connectivity, and accessibility
• 463 total participants providing
about 13,700 total responses
In-Person Open House
• Fall Open House held on
October 20th from 5:30pm to
7:30pm at the IOP Rec. Center
• Included several interactive
stations to allow for public
feedback
• Approx. 20 people attended the
event
Public
Survey Map
Results
Field Survey & Mobile App
• Field survey conducted during
Summer 2025
• Involved several in-person site
visits and walkthroughs, providing
firsthand observations of sidewalk
conditions
• Developed an online mobile field
survey application to evaluate and
catalog sidewalk conditions in real
time using a smartphone or tablet
• Summary of the city’s sidewalk
inventory is included as Appendix A
Existing Conditions Inventory
• Roadways
• Parking Facilities
• Transit Routes
• Active Transportation
• Sidewalk Infrastructure
• Bike Facilities
• Network Usage
• Safety Conditions
Sidewalk Conditions
Network
Usage
12,300 Total Daily Trip Takers
• 3,600 were IOP residents
• 9,700 were residents of the
BCD Region *
37,000 Total Daily Trips
• 12,300 were taken by IOP
residents
• 27,600 were taken by
residents of the BCD Region *
* Includes IOP Residents
Safety Conditions
• Sidewalk Safety
Improvements
• Crosswalks &
Intersections
• Recent Crash History
• 10 reported crashes
involving a non-motorist
• 4 Bicyclists
• 6 Pedestrians
Sidewalk Safety Improvements
Activity Generators & Hubs
Places that consistently attract people for a specific
reason or purpose, such as to work, shop, dine, learn,
exercise, worship, or gather.
97 Activity Generators were identified across the island, including:
Dozens of Businesses IOP Recreation Center & Park
40+ Beach Access Points IOP County Park
Places of Worship IOP Marina
Beach Reach Shuttle Stop City Hall
Dewees Island Ferry Terminal City Public Safety Building
Needs Assessment
• Over 60 projects identified based on the needs collected
from the public engagement, field survey, and discussed
with City Staff
• Consolidated into 56 projects and categorized into 6
Project Types based on the type of improvement:
Project Scoring Criteria
Key Factors Max Score
Accessibility 5
Safety 15
Connectivity 16
Universal Design/Conditions 15
Project Feasibility 8
Other Considerations 9
Priorities 10
Total Max Score 78
Note: Not all projects were assigned a score for each metric.
Priority Project Areas
• Five (5) recommended priority project areas were
identified with Planning Commission
• Each priority area includes a list of Quick Build
Improvements and Enhanced Improvements along
with cost estimates to help inform and guide future
decision-making
Project Area A
Palm Boulevard Improvements
(Breach Inlet to IOP Connector)
A1 Restripe existing bike facilities
along Palm Blvd
D1 Extend sidewalk along Palm Blvd
Project Area B
IOP Connector & Intersection
(with Palm Blvd)
A5
Extend bike lanes along both sides
of IOP Connector to connect with
existing facilities/infrastructure
B6
Improve crosswalks and overall
accessibility at IOP Connector
intersection
D4 Extend sidewalk along IOP
Connector to Palm Blvd
Project Area C
Intersection Improvements at Palm
Boulevard “S-Curve”
B7
Improve crosswalk safety by
adding signage/signals at Palm
Blvd & 20th Ave
B8
Improve crosswalk safety and
visibility at Palm Blvd & 21st Ave
intersection
Project Area D
Palm Boulevard Improvements
(IOP Connector to 41st Ave)
A6 Add bike facility along Palm blvd
heading east
C4 Widen sidewalk (or make into a
multi-use path) along Palm Blvd
D6 Connect crosswalks to existing
sidewalks along Palm Blvd
Project Area E
Waterway Boulevard Connectivity
Improvements
A7 Add bike facility along 21st Ave
A9 Add bike facility along Waterway
Blvd
A10 Add bike facility along 41st Ave
B11 New crosswalk across Waterway
Blvd at 28th Ave
B15 Improve crosswalks at Waterway
Blvd & 41st Ave
D7
New sidewalk along 28th Ave from
Waterway Blvd to the IOP Rec
Center