Change Order Summary
City of Isle of Palms · Charleston County · Agendas
Open the original document More from City of Isle of Palms
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Description Base Bid / Amount Contingency Net Contract Amount Note
Original Contract: 2,815,156$ 75,000$ 2,890,156$
Change Order 1 (49,237)$ 75,000$ 2,840,919$ Miscellaneous change, including eliminating one (1) water line offset
Proposed Change Order 2 (not approved) 427,000$ 75,000$ 3,267,919$ Three (3) additional water line offsets
Revised Proposed Change Order 2 151,337$ -$ 2,992,256$ Three (3) add. water line offsets. Includes using $75,000 contingency to offset cost
(60,000)$ -$ 2,932,256$ Eliminate portions of planned sodding
(57,000)$ -$ 2,875,256$ ** Eliminate replacing certain driveways
(39,000)$ -$ 2,836,256$ ** Eliminate work north of 41st Ave. (Fire Station / Dewees Isl Ferry Parkign Lot)
** Net project cost under awarded contract amount
Potential Future Project Savings
Isle of Palm
Waterway Blvd. Pathway And Flood Mitigation Project (Phase II)
Contract and Change Order Summary
Source: City of Isle of Palms website. First collected Oct 26, 2026.