Change Order
City of Isle of Palms · Charleston County · Agendas
Open the original document More from City of Isle of Palms
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Z:\27670\27670.0010\Documents\Construction\Change Orders\Change Order #2\Change Order No 2.docx CO–2
C O N S T R U C T I O N C O N T R A C T
C H A N G E O R D E R
www.thomasandhutton.com
Project: Waterway Blvd. Pathway Construction Contract: Contract I
Change Order Number: 2
Owner: City of Isle of Palms Date Issued: TBD
Contractor: The Bastion Group, LLC Engineer’s Project Number: 27670.0010
The Contract is changed as follows:
• Add 3 water line offsets to the construction cost (previously shown on the plans) and
adjust various unit cost as show on the attached spreadsheet.
Not valid until signed by the Owner, Engineer, and Contractor.
Adjustments in the Contract Sum:
The original Contract Amount was ............................................................................. $ 2,890,156.00
Net change by previously authorized Change Orders............................................ $ -49,23 7.00
The Contract Amount prior to this Change Order was ............................................ $ 2,840,919.00
The new Contract Amount will be ( increased ) (decreased) (unchanged)
by this Change Order in the amount of ........... .................................................. $ 151,337.50
The new Contract Amount including this Change Order will be .......................... $ 2,992,256.50
Adjustments in the Contract Time:
Original Substantial Completion Date ....................................................................... 07/21/2026
Sum of Previously Approved Increases and Decreases ...................... ( 56 ) days
Date of Substantial Completion prior to this Change Order ................................... 09/15/ 2026
The Contract Time will be (increased) (decreased) (unchanged) by (0 ) days
The date of Substantial Completion as a result of this Change Order therefore is 09/15/2026
E
NGINEER RECOMMENDATION
Richard Karkowski, PE, PH, D.WRE 06/26/2026
ENGINEER S IGNATURE D ATE
CONTRACTOR ACCEPTANCE
CONTRACTOR S IGNATURE D ATE
OWNER APPROVAL
Douglas Kerr
OWNER S IGNATURE D ATE
CONTINUATION SHEET AIA DOCUMENT G703
AIA Document G702, APPLICATION AND CERTIFICATION FOR PAYMENT, containing APPLICATION NO: 1
Contractor's signed certification is attached. APPLICATION DATE: 3/24/2026
In tabulations below, amounts are stated to the nearest dollar. BG PROJECT NO: 26.007
Use Column I on Contracts where variable retainage for line items may apply. Change Order Reduction IOP Waterway BLD
A B C D E F F F G H I J K L M N O
Budget DESCRIPTION OF WORK NO. Units Measure Unit Price March May June Unit Remainder SCHEDULED WORK COMPLETE MATERIALS TOTAL % BALANCE RETAINAGE
Line Item BID 1 2 3 VALUE FROM PREVIOUS THIS PERIOD PRESENTLY COMPLETED TO FINISH (IF VARIABLE
APPLICATIONS STORED AND STORED RATE)
(NOT IN TO DATE
I OR J) (I+J+K)
General
1 Mobilization 1 LS 100000.00 100000 0 0 0 100,000.00$ 100,000.00$ -$ 100,000.00$ 100% -$ 10,000.00$
2 Construction Staking 1 LS 20000.00 12000 8000 0 0 20,000.00$ 20,000.00$ -$ 20,000.00$ 100% -$ 2,000.00$
3 Traffic Control 1 LS 18000.00 6000 6000 0 6000 18,000.00$ 12,000.00$ -$ 12,000.00$ 67% 6,000.00$ 1,200.00$
4 Erosion Conrol 1 LS 78500.00 16000 16000 16000 30500 78,500.00$ 32,000.00$ 16,000.00$ 48,000.00$ 61% 30,500.00$ 4,800.00$
5 As-Built Construction Plans 1 LS 12000.00 0 0 0 12000 12,000.00$ -$ -$ -$ 0% 12,000.00$ -$
Earthwork 0
6 Selected Clearing and Grubbing 2.400 AC 7650.00 0.15 0.50 0.50 1.25 18,360.00$ 4,972.50$ 3,825.00$ 8,797.50$ 48% 9,562.50$ 879.75$
7 Milling Existing Asphalt Pavement 1770 SY 11.55 0 0 0 1770 20,443.50$ -$ -$ -$ 0% 20,443.50$ -$
8 Removal & Disposal of Existing Pavement 6685 SY 11.65 0 2312 1500 2873 77,880.25$ 26,934.80$ 17,475.00$ 44,409.80$ 57% 33,470.45$ 4,440.98$
9 Removal & Disposal of Existing Concrete 600 SY 20.15 0 0 0 600 12,090.00$ -$ -$ -$ 0% 12,090.00$ -$
10 Controlled Fill - Borrow Material 750 CY 49.95 0 0 250 500 37,462.50$ -$ 12,487.50$ 12,487.50$ 33% 24,975.00$ 1,248.75$
11 Grading 11400 SY 5.95 730 3265 3000 4405 67,830.00$ 23,770.25$ 17,850.00$ 41,620.25$ 61% 26,209.75$ 4,162.03$
Roadway and Pathway 0
12 Graded Aggregate Base Course (8" Rooads and Driveways) 2191 SY 45.00 0 0 120 2071 98,595.00$ -$ 5,400.00$ 5,400.00$ 5% 93,195.00$ 540.00$
13 Graded Aggregate Base Course(4" for Pathway) 7715 SY 22.65 0 2700 1500 3515 174,744.75$ 61,155.00$ 33,975.00$ 95,130.00$ 54% 79,614.75$ 9,513.00$
14 Hot Mix Asphalt Intermmediate Course Type B 244 TON 223.00 0 0 0 244 54,412.00$ -$ -$ -$ 0% 54,412.00$ -$
15 Hot Mix Asphalt Surface Course Type B 1145 TON 223.00 0 0 500 645 255,335.00$ -$ 111,500.00$ 111,500.00$ 44% 143,835.00$ 11,150.00$
16 Concrete Curb and Gutter (1'-6") Vertical Face 367 LF 72.00 0 92 0 275 26,424.00$ 6,624.00$ -$ 6,624.00$ 25% 19,800.00$ 662.40$
17 Detectable Warning Surface 385 SF 54.00 0 0 0 385 20,790.00$ -$ -$ -$ 0% 20,790.00$ -$
18 Concrete Driveway (6") 550 SY 113.00 0 0 0 550 62,150.00$ -$ -$ -$ 0% 62,150.00$ -$
19 Gravel Drive 220 SY 40.80 0 0 0 220 8,976.00$ -$ -$ -$ 0% 8,976.00$ -$
Striping 0
20 4" White Solid Lines (Pvt. Edge Lines) Thermo 90 MIL 870 LF 3.00 0 0 0 3 2,610.00$ -$ -$ -$ 0% 2,610.00$ -$
21 24" White Solid Lines (Stop/Diagonal Lines) Thermo 125 MIL 100 LF 17.70 0 0 0 18 1,770.00$ -$ -$ -$ 0% 1,770.00$ -$
22 8" White Solid Lines (Crosswalk) Epoxy Paint Slow Cure 540 LF 5.00 0 0 0 5 2,700.00$ -$ -$ -$ 0% 2,700.00$ -$
23 4" Yellow Solid Lines (Pvt. Edge No Passing Zone) Thermo 90 MIL1410 LF 3.00 0 0 0 3 4,230.00$ -$ -$ -$ 0% 4,230.00$ -$
24 Reset Sign 45 EA 142.00 0 0 0 142 6,390.00$ -$ -$ -$ 0% 6,390.00$ -$
Drainage 0 -$
25 15" RC Pipe 151 LF 142.00 139 0 0 12 21,442.00$ 19,738.00$ -$ 19,738.00$ 92% 1,704.00$ 1,973.80$
26 18" RC Pipe 1558 LF 158.00 58 98 333 1069 246,164.00$ 24,648.00$ 52,614.00$ 11,995.00$ 89,257.00$ 36% 156,907.00$ 8,925.70$
27 Junction Box 2 EA 5750.00 2 11,500.00$ -$ -$ -$ 0% 11,500.00$ -$
28 Manhole 7 EA 5750.00 1 1 0 5 11,500.00$ 11,500.00$ -$ 11,500.00$ 100% -$ 1,150.00$
29 Catch Basin - Type 9 4 EA 5750.00 4 23,000.00$ -$ -$ -$ 0% 23,000.00$ -$
30 Drop Inlet (24" x 36") 22 EA 5750.00 5 5 3 9 126,500.00$ 57,500.00$ 17,250.00$ 42,585.00$ 117,335.00$ 93% 9,165.00$ 11,733.50$
31 Check Valve (15" In-Line) - Installation Only 1 EA 700.00 1 700.00$ -$ -$ -$ 0% 700.00$ -$
32 Check Valve (18" In-Line) - Installation Only 4 EA 700.00 4 2,800.00$ -$ -$ -$ 0% 2,800.00$ -$
33 Check Valve (24" In-Line) - Installation Only 1 EA 700.00 1 700.00$ -$ -$ -$ 0% 700.00$ -$
Water and Sewer Relocations 0 -$
34 Waterway Blvd. near 22nd Ave. – 12” WM horiz. offset 1 LS 179500.00 -150000 29500 0 29,500.00$ 29,500.00$ -$ 29,500.00$ 100% -$ 2,950.00$
35 23rd Ave. near Waterway Blvd – 8” WM vert. offset 1 LS 117250.00 117250 0 117,250.00$ 117,250.00$ -$ 117,250.00$ 100% -$ 11,725.00$
36 23rd Ave. near Waterway Blvd – 8” FM vert. offset with ARV 1 LS 117250.00 -5650 111600 0 111,600.00$ 111,600.00$ -$ 111,600.00$ 100% -$ 11,160.00$
37 3107 Waterway Blvd. – 8” FM horz. offset 1 LS 95200.00 95200 0 95,200.00$ -$ 95,200.00$ 95,200.00$ 100% -$ 9,520.00$
38 Waterway Blvd. near 32nd Ave. – 8” FM vert. offset with ARV1 LS 117250.00 -5150 0 112100 -$ -$ -$ -$ #DIV/0! -$ -$
39 3605 Waterway Blvd. – 8” FM vert. offset with ARV 1 LS 137250.00 -5150 132100 -$ -$ -$ -$ #DIV/0! -$ -$
40 4001 Waterway Blvd. – 8” FM vert. offset with ARV 1 LS 137250.00 5150 142400 136,687.50$ -$ -$ -$ 0% 136,687.50$ -$
41 Water Service Relocations/Replacements 6 EA 4950.00 6 29,700.00$ -$ -$ -$ 0% 29,700.00$ -$
42 Adjust Sewer Manhole Ring & Cover with Concrete Collar 17 EA 1250.00 3 17 21,250.00$ -$ 3,750.00$ 3,750.00$ 18% 17,500.00$ 375.00$
43 8" Sewer in 16" Steel Casing 58 LF 1785.00 58 103,530.00$ -$ -$ -$ 0% 103,530.00$ -$
Miscellaneous 0
44 Sodding 7 MSY 12800.00 12800 92,800.00$ -$ -$ -$ 0% 92,800.00$ -$
45 CMU Wall - Fire Station 313 LF 238.00 238 74,494.00$ -$ -$ -$ 0% 74,494.00$ -$
Owner Controlled Allowance 0
46 Miscellaneous 1 LS 75000.00 75000 -$ -$ -$ -$ #DIV/0! -$ -$
Change Order #1 Additional Line Items 0
Survey Revisions 1 LS 6000.00 6000 6000 6,000.00$ 6,000.00$ 6,000.00$ 100% -$ 600.00$
Testing 1 LS 18496.00 18496 0 18,496.00$ -$ -$ 0% 18,496.00$ -$
12" Watermain in Swale 1 LS 6000.00 6000 0 6,000.00$ 6,000.00$ 6,000.00$ 100% -$ 600.00$
Sewer Lateral in 12" Steel Casing 10 LF 500.00 500 5,000.00$ -$ -$ 0% 5,000.00$ -$
Permit Delays Management and Overhead 7 WKS 5000.00 0 35,000.00$ 35,000.00$ 35,000.00$ 100% -$ 3,500.00$
Structure Adjustments 1 LS 1000.00 1000 0 1,000.00$ 1,000.00$ 1,000.00$ 100% -$ 100.00$
Field Coordination Delays (incorrect utility locates, etc.) 12 LS 500.00 6000 0 6,000.00$ 6,000.00$ 6,000.00$ 100% -$ 600.00$
Revision Printing Costs 1 LS 500.00 5000 0 500.00$ 500.00$ 500.00$ 100% -$ 50.00$
Change Order #2 Additional Line Items 0
3102 Waterway Blvd 12" WM Vertical and Horizontal Offset 1 LS 179500.00 0 179500 0 179,500.00$ -$ -$ -$ 0% 179,500.00$ -$
32nd Ave. near Waterway Blvd – 8” WM vert. offset 1 LS 117250.00 0 117250 0 117,250.00$ -$ -$ -$ 0% 117,250.00$ -$
3200 Waterway Blvd 12" WM Verticall Offset 1 LS 179500.00 179500 0 179,500.00$ -$ -$ -$ 0% 179,500.00$ -$
Asphalt Price increase (14 and 15) 1 LS 9029.00 9029 0 -$
GRAND TOTALS 2,992,256.50$ 713,692.55$ 387,326.50$ 54,580.00$ 1,155,599.05$ 39% 1,836,657.45$ 115,559.91$
AIA DOCUMENT G703 · CONTINUATION SHEET FOR G702 · 1992 EDITION · AIA · © 1992
THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVENUE, N.W. WASHINGTON, D.C. 20006-5292 l G703-1992
Source: City of Isle of Palms website. First collected Oct 26, 2026.