City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
2026 ISLE OF PALMS
RENOURISHMENT
City Council Update
June 24th, 2026
Isle of Palms, SC
Reach 1
Reach 2
Reach
3
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
BEACH NOURISHMENT
•What is beach nourishment?
•How will it affect your time at IOP?
•How does beach nourishment affect wildlife?
•How is public safety ensured?
•Other FAQs
2026 PROJECT OVERVIEW
•Purpose and goals
•Nourishment design
•Dune
•Sandbags
•Schedule
SCHEDULE
PARTNERS & SUPPORTERS
2.
3.
1.
PRESENTATION OUTLINE
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
•The process of dredging sand from
offshore or an upland source to place
on the beach to provide increased
storm protection, wider recreational
beaches, and restored habitat
•Sand Sources
•Sandbar/shoal
•Offshore borrow area
•Upland mine
•Sand is placed on the beach in an
engineered template
•Design based on current condition
and expected erosion trends
WHAT IS BEACH NOURISHMENT?
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
•Combat beach erosion
•Protect property and infrastructure
•Enhance the recreational beach by building a
wider beach
•Add additional wildlife habitat
(Sea Turtle nesting, Shorebird habitat, etc.)
•Eliminate the need for emergency erosion
control measures
•Maintain property value and tax base
© USACE
WHY DO WE NOURISH BEACHES?
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
WHAT TO EXPECT:
•Construction occurs 24/7 everyday until completion
•Temporary beach closures
•500-1,000 feet at a time
•Typically last to 3-5 days at any one location
•Access is maintained around and behind the
fill areas where possible
•Large construction equipment and materials
•Bulldozers, Loaders, Excavators, Fuel Trucks
•Pipe stacks
•Mobile offices
•Backup alarms and nighttime lighting
•Increased boat traffic and offshore dredge
HOW WILL IT AFFECT YOUR TIME AT IOP?
CHANGES TO THE BEACH:
•Temporary dark material on beach and in ocean
•Temporary localized turbidity
•Temporary shell accumulation
•Access ramps over pipe
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
HOW DOES BEACH NOURISHMENT AFFECT WILDLIFE?
Shorebirds
•Surveys already completed to monitor shorebird nesting areas
•Construction will avoid areas of nesting
•Summer work window away from inlets proposed by USFWS to avoid impacts
Sea Turtles
•Morning surveys and nightly observers to locate turtles/nests
•Work with Island Turtle Team to relocate turtle nests in construction areas
•Nighttime lighting in accordance with USFWS guidelines
•Max construction of 500 feet at night
•Limited movement of equipment and materials at night
•Offshore impact to turtles is limited as the dredge is slow moving
Other Species
•Follow guidance of USFWS and SCDNR
•Ensure offshore equipment is prepared and maintained correctly
One of the project goals is to add more habitat for flora and fauna
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
HOW IS PUBLIC SAFETY ENSURED?
Beach Closures
•Up to 1,000 ft at a time around active construction
•Storage Areas
Site security and safety fencing
Escorts for heavy equipment
Safety equipment
•Back-up alarms
•Nighttime Lighting
Suggestions to the public
•Avoid active construction areas
•Stay outside safety fencing
•Exercise caution around heavy equipment
•Avoid sitting between ruts and equipment tracks
•No climbing on the pipe
•Avoid swimming near pipeline landing sites
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
What should I expect after nourishment?
•The beach will be significantly wider, but erosion of the
construction berm and scarping can be expected
directly after nourishment as the constructed profile
adjusts to a natural beach shape.
•The sand may appear darker in areas, butwill lighten
up to its natural color in time.
•The transition into the water (swash zone) may be
steeper until the profile is reshaped by waves.
•Temporary ponding may occur on the nourished beach
after storms or king tides.
OTHER FAQs
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
•Owner: City of Isle of Palms & Wild Dunes Community
Association
•Contractor: Marinex
•Engineer: CSE
•Project Cost: 21.47 million dollars
•Three Reaches
•Reach 1: Wild Dunes Property Owners Beach House to
theWild Dunes Links Golf Course (900,000 cy)
•Reach 2: 53rd Avenue to Wild Dunes Property Owners
Beach House (800,000 cy)
•Reach 3: Breach Inlet to the Pier (800,000 cy)
•Total: 2.5 Million Cubic Yardsor 166,000 dump trucks
•Construction Schedule –July-November 2026
2026 PROJECT OVERVIEW
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
•What is a cubic yard (cy)? 1 dumptruck= 15 cy
•1 cy per foot of beach equals 1.5 ft of added beach width
•Reaches 1-2: Beach width increased by up to 600 ft
•Design considers future sediment transport patterns –more
sand in center of reach
•Reach 3: Average beach width increase of 150 ft
•Downcoast spreading of sand expected south of 53rdAve
What will it look like?
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
2026 PROJECT OVERVIEW
Reach 1
Reach 2
Reach 3
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
Wadmalaw
Max 50,000 cy a
day
The Wadmalaw
•30 in cutterhead
•12,800 hp
•Max 50,000 cy/day
•Expected 25,000 to 30,000
cy/day
•~100-250 feet/day
•Anticipated to arrive in July
•Pumping at the north end first
CUTTERHEAD SUCTION DREDGE
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
REACH 1 –NOURISHMENT
•Project Length = 4,800 ft (.9 miles)
•Nourishment Volume = 900,000 Cubic Yards
•Template Specifications
•Average Fill Density = 187.5 cy/ft
•Berm Elevation = 6-7 ft NAVD
•Dune Elevation = 14 ft NAVD
•Max berm width = ~700 ft
•Tentative Construction Schedule –Jul-Aug
2026
•No work on or under decks, patios, porches,
or erosion control structures
•Dune constructed between Shipwatchand
Ocean Club
•Includes dune planting after the project
Reach 1
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
•Project Length = 5,800 ft (1.1 miles)
•Nourishment Volume = 800,000 Cubic Yards
•Template Specifications
•Average Fill Density = 137.9 cy/ft
•Berm Elevation = 6-7 ft NAVD
•Dune Elevation = 14 ft NAVD
•Max berm width = ~545 ft
•Tentative Construction Schedule –Aug-Sep
2026
•No work on or under decks, patios, porches,
or erosion control structures
•Dune constructed between 57thAve –
DunecrestLn
•Includes dune planting after project
REACH 2 -NOURISHMENT
Reach 2
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
•Project Length = 8,600 ft (1.6 miles)
•Nourishment Volume = 800,000 Cubic
Yards
•Template Specifications
•Average Fill Density = 93.0 cy/ft
•Berm Elevation = 6-7 ft NAVD
•Dune Elevation = 14 ft NAVD
•Max berm width = ~325 ft
•Construction Schedule –Oct-Early Nov
2026
•No work on or under decks, patios,
porches, or erosion control structures
•Dune constructed along most areas south
of 9th
•Includes dune planting after project
REACH 3 -NOURISHMENT
Reach
3
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
•Structures will be removed in
conjunction with the project by separate
contractor
•No sand placed on top of or landward of
sandbags
Sandbags
EMERGENCY EROSION CONTROL STRUCTURES
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
•Any work beyond the City’s fill area will require an independent permit from
SCDES-BCM.
•Minor Dune Nourishment, backfill, plantings, sand fence
•This will include any areas landward of the easement line, work under
walkovers, or work between structures
•Private dune walkovers can be extended without a permit provided they
follow BCM guidelines
Work along Private Property
Additional Work
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
Contractor is aware of all cultural resources in
borrow area
•Avoidance buffers suggested by the State
Historical Preservation Office (SHPO) and the
South Carolina Institute of Archeology and
Anthropology (SCIAA)
•Covers known shipwrecks such as the
Constance,
Mary Bowers, and Georgiana
•Other anomalies identified through CSE’s
extensive surveys
Contractor will notify SCIAA, City, and CSE if
unexpected cultural resources are encountered
CULTURAL RESOURCES
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
ANTICIPATED CONSTRUCTION TIMETABLE
Tentative Construction Schedule
Pre-Construction Meeting 30 June
Contractor mobilization July
Anticipated First day pumping in Reach 117 July
Reach 1 nourishment duration 50 Days
Anticipated First day pumping in Reach 29 Sept
Reach 2 nourishment duration 45 Days
Anticipated First day pumping in Reach 31 Nov
Reach 3 nourishment duration 45 Days
Demobilization Dec
City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc.
Post-
Construction
Reach 1
Reach 2
Reach
3
THANK YOU!