City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. 2026 ISLE OF PALMS RENOURISHMENT City Council Update June 24th, 2026 Isle of Palms, SC Reach 1 Reach 2 Reach 3 City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. BEACH NOURISHMENT •What is beach nourishment? •How will it affect your time at IOP? •How does beach nourishment affect wildlife? •How is public safety ensured? •Other FAQs 2026 PROJECT OVERVIEW •Purpose and goals •Nourishment design •Dune •Sandbags •Schedule SCHEDULE PARTNERS & SUPPORTERS 2. 3. 1. PRESENTATION OUTLINE City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. •The process of dredging sand from offshore or an upland source to place on the beach to provide increased storm protection, wider recreational beaches, and restored habitat •Sand Sources •Sandbar/shoal •Offshore borrow area •Upland mine •Sand is placed on the beach in an engineered template •Design based on current condition and expected erosion trends WHAT IS BEACH NOURISHMENT? City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. •Combat beach erosion •Protect property and infrastructure •Enhance the recreational beach by building a wider beach •Add additional wildlife habitat (Sea Turtle nesting, Shorebird habitat, etc.) •Eliminate the need for emergency erosion control measures •Maintain property value and tax base © USACE WHY DO WE NOURISH BEACHES? City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. WHAT TO EXPECT: •Construction occurs 24/7 everyday until completion •Temporary beach closures •500-1,000 feet at a time •Typically last to 3-5 days at any one location •Access is maintained around and behind the fill areas where possible •Large construction equipment and materials •Bulldozers, Loaders, Excavators, Fuel Trucks •Pipe stacks •Mobile offices •Backup alarms and nighttime lighting •Increased boat traffic and offshore dredge HOW WILL IT AFFECT YOUR TIME AT IOP? CHANGES TO THE BEACH: •Temporary dark material on beach and in ocean •Temporary localized turbidity •Temporary shell accumulation •Access ramps over pipe City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. HOW DOES BEACH NOURISHMENT AFFECT WILDLIFE? Shorebirds •Surveys already completed to monitor shorebird nesting areas •Construction will avoid areas of nesting •Summer work window away from inlets proposed by USFWS to avoid impacts Sea Turtles •Morning surveys and nightly observers to locate turtles/nests •Work with Island Turtle Team to relocate turtle nests in construction areas •Nighttime lighting in accordance with USFWS guidelines •Max construction of 500 feet at night •Limited movement of equipment and materials at night •Offshore impact to turtles is limited as the dredge is slow moving Other Species •Follow guidance of USFWS and SCDNR •Ensure offshore equipment is prepared and maintained correctly One of the project goals is to add more habitat for flora and fauna City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. HOW IS PUBLIC SAFETY ENSURED? Beach Closures •Up to 1,000 ft at a time around active construction •Storage Areas Site security and safety fencing Escorts for heavy equipment Safety equipment •Back-up alarms •Nighttime Lighting Suggestions to the public •Avoid active construction areas •Stay outside safety fencing •Exercise caution around heavy equipment •Avoid sitting between ruts and equipment tracks •No climbing on the pipe •Avoid swimming near pipeline landing sites City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. What should I expect after nourishment? •The beach will be significantly wider, but erosion of the construction berm and scarping can be expected directly after nourishment as the constructed profile adjusts to a natural beach shape. •The sand may appear darker in areas, butwill lighten up to its natural color in time. •The transition into the water (swash zone) may be steeper until the profile is reshaped by waves. •Temporary ponding may occur on the nourished beach after storms or king tides. OTHER FAQs City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. •Owner: City of Isle of Palms & Wild Dunes Community Association •Contractor: Marinex •Engineer: CSE •Project Cost: 21.47 million dollars •Three Reaches •Reach 1: Wild Dunes Property Owners Beach House to theWild Dunes Links Golf Course (900,000 cy) •Reach 2: 53rd Avenue to Wild Dunes Property Owners Beach House (800,000 cy) •Reach 3: Breach Inlet to the Pier (800,000 cy) •Total: 2.5 Million Cubic Yardsor 166,000 dump trucks •Construction Schedule –July-November 2026 2026 PROJECT OVERVIEW City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. •What is a cubic yard (cy)? 1 dumptruck= 15 cy •1 cy per foot of beach equals 1.5 ft of added beach width •Reaches 1-2: Beach width increased by up to 600 ft •Design considers future sediment transport patterns –more sand in center of reach •Reach 3: Average beach width increase of 150 ft •Downcoast spreading of sand expected south of 53rdAve What will it look like? City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. 2026 PROJECT OVERVIEW Reach 1 Reach 2 Reach 3 City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. Wadmalaw Max 50,000 cy a day The Wadmalaw •30 in cutterhead •12,800 hp •Max 50,000 cy/day •Expected 25,000 to 30,000 cy/day •~100-250 feet/day •Anticipated to arrive in July •Pumping at the north end first CUTTERHEAD SUCTION DREDGE City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. REACH 1 –NOURISHMENT •Project Length = 4,800 ft (.9 miles) •Nourishment Volume = 900,000 Cubic Yards •Template Specifications •Average Fill Density = 187.5 cy/ft •Berm Elevation = 6-7 ft NAVD •Dune Elevation = 14 ft NAVD •Max berm width = ~700 ft •Tentative Construction Schedule –Jul-Aug 2026 •No work on or under decks, patios, porches, or erosion control structures •Dune constructed between Shipwatchand Ocean Club •Includes dune planting after the project Reach 1 City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. •Project Length = 5,800 ft (1.1 miles) •Nourishment Volume = 800,000 Cubic Yards •Template Specifications •Average Fill Density = 137.9 cy/ft •Berm Elevation = 6-7 ft NAVD •Dune Elevation = 14 ft NAVD •Max berm width = ~545 ft •Tentative Construction Schedule –Aug-Sep 2026 •No work on or under decks, patios, porches, or erosion control structures •Dune constructed between 57thAve – DunecrestLn •Includes dune planting after project REACH 2 -NOURISHMENT Reach 2 City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. •Project Length = 8,600 ft (1.6 miles) •Nourishment Volume = 800,000 Cubic Yards •Template Specifications •Average Fill Density = 93.0 cy/ft •Berm Elevation = 6-7 ft NAVD •Dune Elevation = 14 ft NAVD •Max berm width = ~325 ft •Construction Schedule –Oct-Early Nov 2026 •No work on or under decks, patios, porches, or erosion control structures •Dune constructed along most areas south of 9th •Includes dune planting after project REACH 3 -NOURISHMENT Reach 3 City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. •Structures will be removed in conjunction with the project by separate contractor •No sand placed on top of or landward of sandbags Sandbags EMERGENCY EROSION CONTROL STRUCTURES City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. •Any work beyond the City’s fill area will require an independent permit from SCDES-BCM. •Minor Dune Nourishment, backfill, plantings, sand fence •This will include any areas landward of the easement line, work under walkovers, or work between structures •Private dune walkovers can be extended without a permit provided they follow BCM guidelines Work along Private Property Additional Work City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. Contractor is aware of all cultural resources in borrow area •Avoidance buffers suggested by the State Historical Preservation Office (SHPO) and the South Carolina Institute of Archeology and Anthropology (SCIAA) •Covers known shipwrecks such as the Constance, Mary Bowers, and Georgiana •Other anomalies identified through CSE’s extensive surveys Contractor will notify SCIAA, City, and CSE if unexpected cultural resources are encountered CULTURAL RESOURCES City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. ANTICIPATED CONSTRUCTION TIMETABLE Tentative Construction Schedule Pre-Construction Meeting 30 June Contractor mobilization July Anticipated First day pumping in Reach 117 July Reach 1 nourishment duration 50 Days Anticipated First day pumping in Reach 29 Sept Reach 2 nourishment duration 45 Days Anticipated First day pumping in Reach 31 Nov Reach 3 nourishment duration 45 Days Demobilization Dec City Council Update for Isle of Palms Renourishment (24 June 2026) Coastal Science & Engineering, Inc. Post- Construction Reach 1 Reach 2 Reach 3 THANK YOU!

Source: City of Isle of Palms website. First collected Oct 26, 2026.