Beach Renourishment Project Update Slides
City of Isle of Palms · Charleston County · Agendas
Open the original document More from City of Isle of Palms
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Isle of Palms – Jan 29 2026
Isle of Palms
Beach Renourishment
Jan 2026 Update
Isle of Palms – Jan 29 2026
Current Beach Conditions
Exposed Shoal
Isle of Palms – Jan 29 2026
Current Beach Conditions
Mud Balls Near 6th Ave
Near 6th Ave
Near 4th Ave
Isle of Palms – Jan 29 2026
Project Scope – Beach Fill
• Reach 1:
• Wild Dunes Property Owners
Beach House to 18th Green (Station
280 to 328)
• Base: 600k cy
• Alternative: 900k cy
• Reach 2:
• 53rd Avenue to Wild Dunes
Property Owners Beach House
(Station 222 to 280)
• Base: 600k cy
• Alternative: 900k cy
• Reach 3:
• Breaches Inlet to Isle of Palms Pier
(Station 0 to 86)
• Base: 400k cy
• Alternative: 800k cy
• 3-4 months for construction,
possibly 2 months depending on
dredge and weather
• Sandbag Removal
*Design may change based conditions before construction
Isle of Palms – Jan 29 2026
Project Scope – Borrow Area
• 2.5 miles SE of the Pier
• 650 acres of Permitted Area
• ~383 acres of Priority Area
with a 10-foot cut
• 10.59 MCY (6.18 MCY of
Priority)
• ~121 acres of Supplemental
Areas (1.27 MCY)
• 4 Buffer Areas around Cultural
Resources
Isle of Palms – Jan 29 2026
FWS Programmatic Biological Opinion (PBO)
• Aims to reduce the need for individual consultation and expedite
permit review
• Established three work zones:
• Zone 1: Shorebird Nesting ~1 mile of an inlet
• Zone 2: Critical Sea T urtle Nesting Habitat
• Zone 3: Beachfront Property that can be used for turtle nesting
• Work Windows
• Zone 1: June 1 to November 30
• Zone 2: October 1 to April 30
• Zone 3: Year round
• Should be finalized the end of this week
Isle of Palms – Jan 29 2026
Zone 1
Zone 1
Zone 3
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Zone 1
Zone 2
Zone 3
US Fish and Wildlife Work Windows
Isle of Palms – Jan 29 2026
Project Timeline
• Bid released around ~February
13th
• Pre-Bid Conference March 2nd
• Questions due March 11th
• Bid Opening March 18th
• Construction start June 1st or
earlier
*Project schedule is tentative and
subject to change
Isle of Palms – Jan 29 2026
Next Steps
• Apply for FWS Tier 2 review
• Finalize construction documents and specifications
• Coordinate with USACE and SCDES-BCM to
finalize permit documents
• Expect State permit end of March or early April
• Expect USACE permit Mid April
• Currently conducting pre-project bird monitoring
• Survey scheduled next week
• Coordinate with Island T urtle T eam
Source: City of Isle of Palms website. First collected Oct 26, 2026.