M E M O R A N D U M
TO: Ways and Means Committee/City Council
FROM: Eric Vinson, City Administrator
DATE: November 5, 2021
SUBJECT: Hospitality and Accommodations Tax Revenue Bond Issuance for Poinsett
Corridor Project
The financing plan for Poinsett Corridor Streetscape project includes the issuance of a
Hospitality & Accommodations Revenue Bond not to exceed $1.5M. The bond ordinance is
included for your consideration. This ordinance will require two readings and approval by
Council.
The overall financing plan for this project is as follows:
County Transportation Committee - $2.25M
Hospitality and Accommodations Tax Revenue Bond - $1.25M
Cash on Hand - $650K
ARP Funds -$400K
Hospitality Fund Balance -$200K
Total City Commitment - $2.5M__________________________
Total Project Cost – $4.7M
Project Description:
The City funded the Poinsett Corridor Master Plan in 2017, identifying this project as a priority economic
development and safety project. Plan recommendations include extending Main Street down Poinsett
Highway to allow for additional commercial development opportunities in Downtown Travelers Rest. This
project focuses on improving 2,500 linear feet of North Poinsett Highway from South Poinsett/Center
Street Intersection to North Poinsett at Hawkins Road Intersection. Corridor improvements include
safety and roadway improvements, repaving, turning lanes and traffic light with signalized crosswalks at
Tubbs Mountain Road intersection, bike lanes, sidewalks, stormwater infrastructure, curb and gutter,
landscaping, and enhanced street lighting.