CITY OF BEAUFORT
SPECIAL JOINT WORKSESSION OF COUNCIL WITH THE PLANNING
COMMISSION City Hall, Planning Conference Room
1911 Boundary Street – 1st Floor
July 15, 2025 - 1:00 pm
Meeting will be live streamed on the City of Beaufort’s Facebook Page
STATEMENT OF MEDIA NOTIFICATION
In accordance with South Carolina Code of Laws, 1976, Section 30-4-80(d), as amended, all local media was
duly notified of the time, date, place, and agenda of this meeting.
Please click the link below to join the Webinar
https://us02web.zoom.us/j/85669481294?pwd=NqSCR7CHTpGKumelml0bBGaOidN7LI.1
Passcode:517418 +16469313860 Webinar ID: 856 6948 1294
I. Call to Order
II. Public Comment – Agenda Item only
III. Discussion – Ordinance amending Chapter 7 (Land Development) and Chapter 9
(Development Review Procedures) of the Beaufort Development Code
IV. Adjourn
CITY OF BEAUFORT
DEPARTMENT REQUEST FOR CITY COUNCIL AGENDA ITEM
To: City Council
From: Curt Freese, Community Development Director
Agenda Item Title: Chapter 7-9 – Beaufort Development Code - Revisions
Meeting Date: 7-15-25
Department: Community Development
-----------------------------------------------------------------------------------------------------------------
I. Introduction:
At the request of City Council and the public, the Planning Commission
recommended updates to Chapters 7 and 9 of the Beaufort Development Code.
These changes address infrastructure, traKic impact analysis, open space,
subdivisions, and approval processes to correct errors and modernize development
standards.
II. Background:
a. Following first reading (May 13) and public input, the Chamber of Commerce
submitted comments on July 3. City Council requested an additional review
with the Planning Commission before second reading. StaK met with the
Chair and Vice Chair of the Commission to review Chamber feedback.
Consensus revisions are included; other topics raised—such as plat-stage
design review, gated community restrictions, and vesting—may warrant
future discussion.
b. History of Actions at City Council Meetings
i. May 13, 2025 – First reading, with approval from Council.
1
ii. June 10, 2025 – Second reading on the agenda; Council voted to
postpone second reading until July 8, 2025.
iii. July 8, 2025 – Public hearing and second reading on the agenda;
public hearing was held. After a lengthy discussion, Council voted to
postpone second reading until after a joint meeting with the Planning
Commission.
III. Discussion:
Attachment 1 outlines motions capturing the revisions and Council’s July 8
discussion. Attachment 2 includes the draft ordinance and supporting documents
from that meeting.
IV. Legal Authority:
Per SC Code §6-29-710, these amendments promote public health, safety, and
general welfare through guided development practices.
V. StaG Recommendation:
Council discussion and direction on proposed motions (Attachment 1), with the
goal of preparing final amendments for adoption at the next second reading.
VI. Attachments:
1. Proposed motions for discussion
2. July 8 Agenda Packet:
A. Agenda Memo
B. Ordinance & Exhibits
C. Chapter 7 Summary + Redline
D. Chapter 9 Summary + Redline
2
Motions for Second Reading
Subdivision and Site Plan Standards Section 7.5.1
I hereby make the motion to amend Section 7.5.1 with the following changes:
Ø Remove the words “typical” from Section 7.5.1.
Ø Remove the word “Regulations” and replace with the word “standards” in Section 7.5.1
3
ATTACHMENT 1 - PROPOSED MOTIONS
Subdivision Types and Process Outlines Section 7.5.2
I hereby make the motion to amend Section 7.5.2 with the following changes:
Ø Section 7.5.2 A 2, Remove the “and” replace with “or”.
Ø Section 7.5.2 B 1, Remove the “or”.
Ø Section 7.5.2 B 2, Remove the “and” replace with “or”.
4
ATTACHMENT 1 - PROPOSED MOTIONS
Sketch Plan Section 7.5.3
I hereby make the motion to amend Section 7.5.3 with the following changes:
Ø 7.5.3 A, capitalize Major and Subdivision and add the word “Community”.
Ø 7.5.3 B.1, capitalize Major Subdivision and Applicant.
Ø 7.5.3 B.1, i, remove the word “road”, and replace with “street.”
Ø 7.5.3 B.1, iii, remove preliminary traffic impact and the word “proposed”.
Ø 7.5.3 B.2 capitalize Applicant add Community and capitalize Open.
Ø 7.5.3.B.2 iii, remove OCRM, and replace SCDES
Ø 7.5.3.B.3 ii. Remove “pedestrian shed,” and replace with “distance.”
Ø 7.5.3.B.4 ii. Remove the word “harmonious” and replace with the word “consistent.”
Ø 7.5.3.C: Remove sentence, “The Applicant shall submit a complete sketch plan package
to the City.”
Ø 7.5.3.C 2, remove Title commitment requirement
Ø 7.5.3.C 11, remove the words “public dedication requirements”
Ø 7.5.3.C 12, add “Community”.
Ø 7.5.3.C 16, remove contents of parenthesis.
Ø 7.5.3.C 18, remove word “proposed” and replace with “proposed development.”
Ø 7.5.3.C 24, replace entire sentence with “structure, location, massing and building
designs.”
5
ATTACHMENT 1 - PROPOSED MOTIONS
Preliminary Plat Section 7.5.4
I hereby make the motion to amend Section 7.5.4 with the following changes:
Ø 7.5.4 A 1. Remove “TRC.”
Ø 7.5.4 B 2, xxvi, remove traffic study requirement
Ø 7.5.4 B 3 ii., remove first sentence and word “dedication.”
Ø 7.5.4 B 3 v, remove word “equitable” and replace with “any”
6
ATTACHMENT 1 - PROPOSED MOTIONS
Final Plat Section 7.5.5
I hereby make the motion to amend Section 7.5.5 with the following changes:
Ø 7.5.5 A: remove the words “technical standards of the City” and replace with the word
Code.
Ø 7.5.5 B 1. Iii, Remove entirety of iii, title commitment.
Ø 7.5.5 B 2: Remove word “drawing”
Ø 7.5.5 B 2 viii, remove DHEC reference and replace with SCDES
Ø 7.5.5 B 4 viii, remove entire reference for signature blocks for utility providers.
Ø 7.5.5 B 5 v., remove entire reference for other certificates, etc.
Ø 7.5.5 D, remove word “public” in front of improvements.
7
ATTACHMENT 1 - PROPOSED MOTIONS
Minor Subdivision Section 7.5.6
I hereby make the motion to amend Section 7.5.6 with the following changes:
Ø 7.5.6 C xxii: Remove the words “utility providers”.
8
ATTACHMENT 1 - PROPOSED MOTIONS
Site Plan Section 7.5.7
I hereby make the motion to amend Section 7.5.7 with the following changes:
Ø 7.5.7 B, 3, xii, remove xii, gathering places.
Ø 7.5.7 B, 3, xxxvii, remove words “utility providers” and “as applicable.”
Ø 7.5.7 B, 5, remove Certified references and add words “prepared by a licensed engineer”
Ø 7.5.7 G Add words “Unless otherwise extended as herein provided”
9
ATTACHMENT 1 - PROPOSED MOTIONS
CITY OF BEAUFORT
DEPARTMENT REQUEST FOR CITY COUNCIL AGENDA ITEM
TO: DATE: 5/15/2025
FROM:
AGENDA ITEM
TITLE:
MEETING
DATE:
CITY COUNCIL
Curt Freese, Community Development Director
PUBLIC HEA RING AND SECOND READING - Ord inance amending Chapter 7
(Land Development) and Chapter 9 (Development Review Procedures) of the Beaufort
Development Code
7/8/2025
DEPARTMENT: Community and Economic Development
BACKGROUND INFORMATION:
The land development/subdivision requirements are core functions of the development code. Chapter Seven
includes streets, open space, public utilities, major and minor subdivisions, and site plans. Chapter Nine
includes public notice and approval requirements. Draft changes of each chapter were presented at the May 21,
2024, City Council work session. The drafts of each chapter were first taken to the Planning Commission
Work session in August 2024, and after eight work-sessions and a public hearing, the Planning Commission
unanimously recommended approval to the City Council. The recommended drafts were then sent to the City
Attorney for legal review and revision. A list of the meetings is found below, with each public meeting generally
2-4 hours long, allowing public comment. After Council request, the work-sessions began to be streamed via
zoom, and will now be streamed over Facebook. Minutes for each meeting are attached.
PLACED ON AGENDA FOR: Action
REMARKS:
First Reading was held on May 13, 2025.
ATTACHMENTS:
Description Type Upload Date
Memorandum Backup Material 5/16/2025
Ordinance Ordinance 5/16/2025
Major Changes Chapter 7 Backup Material 5/28/2025
Tracked Changes Chapter 7 Backup Material 5/16/2025
Major Changes Chapter 9 Backup Material 5/28/2025
Tracked Changes Chapter 9 Backup Material 5/16/2025
10
ATTACHMENT 2.A. - AGENDA MEMO
ORDINANCE 2025/14
AMENDING CHAPTER 7 (LAND DEVELOPMENT) AND CHAPTER 9
(DEVELOPMENT REVIEW PROCEDURES) OF THE BEAUFORT DEVELOPMENT
CODE
WHEREAS, the State of South Carolina has conferred to the City of Beaufort (hereinafter “City”)
the power to enact ordinances “in relation to roads, streets, markets, law enforcement, health, and
order in the municipality or respecting any subject which appears to it necessary and proper for
the security, general w
elfare, and convenience of the municipality or for preserving health, peace,
order, and good government in it . . .”
as set forth in S.C. Code Ann. § 5-7-20; and
WHEREAS, the City of Beaufort adopted the Beaufort Development Code (hereinafter “Code”)
on June 27, 2017, as set forth in section 5-6001 of the Code of Ordinances of the City of Beaufort,
South Carolina; and
WHERE
AS, the adoption of certain amendment s of the Code will better enable the City, its
citizens, and other int
erested parties to use the Code “for the general purpose of guiding
development in accorda
nce with existing and future needs and promoting the public health, safety,
morals, convenience, order, appearance, prosperity, and general welfare” in accordance with S.C.
Code Ann. § 6-29-710; and
WHEREAS, the Planning Commission has the duty to review and make recommendations to the
City Council regarding amendments to the text of the Code pursuant to Section 10.2.A.3.b. of the
Code; and
WHEREAS, the Planning Commission has reviewed and made recommendations for the
amendment of Chapter 7 (Land De
velopment) and Chapter 9 (Development Review Procedures) of
the Code, as shown on Exhibit A a
nd B, hereto, respectively; and
WHEREAS, the amendments to Chapter 7 (Land Development) are for the general purpose of guiding
development in accordanc
e with existing and future needs and promoting the public health, safety,
morals, convenience, order
, appearance, prosperity, and general welfare;
WHEREAS, the am
endments to Chapter 9 (Development Review Procedures), allow for greater
transparency, public involvement, and clearer and more predictable development outcomes;
WHEREAS a public hearing before the Beaufort City Council was held regarding changes to the
recommended amendments on May 13, 2025 and June 10th, with notice of the hearing publi shed
in The Beaufort Gazette on April 14, 2025, and May 9th, 2025;
NOW, THEREFORE, BE IT ORDAINED by the City Council of the City of Beaufort, South
Carolina, duly assembled and by authority of same, pursuant to the power vested in the Council
by S.C. Code
Ann. § 6-29-760 and the Code of Ordinances of the City of Beaufort, South
Carolina, that the Code by
striking Chapter 7 of the Code in its e ntirety and replacing it with the
amended Chapter as shown on Exhibit A and by striking Chapter 9 of the Code in its entirety and
replacing it with the amended Chapter as shown on Exhibit B.
11
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
This ordinance shall become effective July 8, 2025.
PHILIP E. CROMER, MAYOR
ATTEST:
TRACI GULDNER, CITY CLERK
1st Reading
2nd Reading & Adoption
Reviewed as to form by Ben Coppage, City Attorney
12
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
EXHIBIT A
(Chapter 7)
13
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
7: LAND DEVELOPMENT
7.1: IMPROVEMENT REQUIREMENTS
7.1.1 PURPOSE
The purpose of these land development requirements is to:
A. Encourage economically sound and environmentally sensitive development.
B. Assure the timely provision of required streets, utilities, and other facilities and services to new land
developments.
C. Assure the adequate provision of safe and convenient vehicular and pedestrian traffic access and
circulation in and through new land developments.
D. Assure the provision of needed open spaces and building sites in new land developments through the
dedication or reservation of land for recreational, educational, and other public purposes.
E. Assure, in general, the wise and timely development of new areas, in harmony with the Comprehensive
Plan of the city.
F. Encourage new subdivision developments that complement the City's historic development pattern.
G. Promote compact, well-defined, sustainable neighborhoods that enhance the City's character.
H. Create livable neighborhoods that foster a sense of community and reduce dependency on vehicles.
I. Encourage the proper arrangement of new streets in relation to existing or planned streets and
ensure streets facilitate safe, efficient, and pleasant walking, biking and driving.
7.1.2 APPLICABILITY
A. Unless noted otherwise in this section, all new development projects shall be required to have public
sewer and underground wiring, and shall comply with Section 7.2.3 (Lot Access Standards).
B. Installation or construction of the improvements specified in the Table of Required Improvements
(Section 7.1.3) is required for all development projects, except those which (1) are subject to the Minor
Development Design Review or Minor Subdivision provisions of this Code or are located in the Historic
District and (2) affect less than one whole Block Face.
C. The applicant, developer, and real property owner shall be responsible for the installation and
construction of required improvements according to the provisions of this Code, except as may
otherwise be specifically provided herein or by agreement.
D. A Final Subdivision Plat shall not be approved unless the improvements required by this Chapter have
been installed or constructed or the applicant has made improvement guarantees, pursuant to Section
7.1.5, to the satisfaction of the City, for the installation of said improvements.
14
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
7.1.3 TABLE OF REQUIRED IMPROVEMENTS
ZONING DISTRICT
REQUIRED
IMPROVEMENTS3
SECTION
REFERENCE
T1 T3-
S
T3-
N
T4-
HN
T4-
N
T5-
DC
T5-
UC
RMX IC LI MHP
Public Water and
Hydrants
7.1.3.B □ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Public Sewer 7.1.3.B □ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Paved Streets1 7.2.4 □ ■ ■ ■ ■ ■ ■ ■ ■
Streetscape2 Appendix C □ ■ ■ □ ■ ■ ■ ■ ■ ■ ■
Underground
Drainage
7.1.3.A □ ■ ■ ■ ■ ■ ■ ■ ■ ■ □
Curb and Gutter Appendix C □ □ □ □ ■ ■ ■ ■ ■ ■ □
Sidewalks 7.2.4.C □ □ □ □ ■ ■ ■ ■ ■ ■ □
Street Trees 7.2.5 □ □ ■ ■ ■ ■ ■ ■ ■ □ □
Street Lights n/a □ □ □ □ ■ ■ ■ ■ ■ ■ ■
Street Signs
(private streets)
n/a ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Underground
Wiring On-Site
7.1.3.C ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Community
Green Space and
Open Space
Space
7.4 □ ■ ■ □ ■ □ ■ ■ ■ □ □
■ required improvements by
district
□ may be required at the discretion of the Planning Commission
based on existing conditions, surrounding context, and Street
Infrastructure Plans (Appendix C)
1 Rear lanes/alleys may be permitted to be paved with pervious material, such as gravel, depending
on the location.
2 Complete street requirements shall be coordinated with the Street Infrastructure Plans in Appendix
C.
3 For Infill and development of Redevelopment Areas or Redevelopment Districts, the installation or
construction of these improvements are required to the extent feasible based on existing conditions
including roads, utilities and adjacent buildings.
A. Street Improvements: Land designated for public streets shall be cleared and filled in accordance with
the latest edition of the " Standard Specifications for Highway Construction" issued by the South
Carolina State Department of Transportation, or as determined appropriate by the Administrator. No
land may be disturbed until a Building Permit has been issued (Section 9.5). See Section 5.4 for Tree
Removal Standards. See Section 7.2 for more standards on street location. See Appendix C for Street
Regulating Plan and Design Standards.
B. Water and Sewer Facilities: Water and sewer facilities shall be provided in accordance with the
standard procedures and policies of the water and sewer provider and the South Carolina Department
of Environmental Services (SCDES) and shall be approved by the water and sewer provider.
15
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
C. Utility lines: All utility lines within a development site shall be installed underground. The Planning
Commission may approve an exception only in cases where there are existing above- ground lines that
serve the property.
7.1.4 SURVEY AND ENGINEERING
A. Installation of Permanent Reference Points: Permanent reference points shall be placed in accordance
with the following requirements:
1. General Standards: Boundary surveys shall be performed, in accordance with the state minimum
standards published by the State Board of Registration for Professional Engineers and Land
Surveyors, unless more stringent requirements are specified. A minimum of two points in an y
survey must be tied to the state plane coordinate system. The survey may be done on the
horizontal ground distance and tied back to the state plane coordinates.
2. Control Monuments: Vertical control monuments shall be placed in or near the centerline of
pavement of subdivision streets at a minimum of 1 per 4 acres. Where practical, control
monuments shall be placed at points of curvature and points of tangency of curves. The control
monument may be poured on the job or be a concrete marker of the type commonly used in the
area: at least 3 feet long and tapered with a 12-inch long, ¼-inch diameter brass or bronze rod
embedded in the top. Control monuments shall be placed in a cast iron water main valve type
box with a cover flush with the pavement.
3. Property Marker: A steel or wrought iron pipe, rebar, or the equivalent, not less than 0.5 inches
in diameter and at least 24 inches in length shall be set at all property corners and points of
curves, except those located by monuments. They shall be flush with the ground.
4. Accuracy: Land surveys within the city limits shall be Class A surveys, set at an accuracy of at least
1:10000.
7.1.5 IMPROVEMENT GUARANTEES
A. Types Allowed: Prior to approval of a Final Subdivision Plat the applicant shall provide a performance
guarantee to ensure the completion of required improvements within a period of time as agreed upon
by the Administrator and the applicant, and expressed in the guarantee. Such guarantee may be in the
form of a performance bond, a surety bond, a cash deposit, or a letter of credit. A performance
guarantee shall be posted in the amount of 125% of the total cost of improvements.
1. Performance/Surety Bonds and Letters of Credit: The performance or surety bond, or letter of
credit, shall be in a form acceptable to the City. It shall include a pledge by the bank, insurance
company or other bonding/lending institution that the funds necessary to carry out the terms of
the agreement are guaranteed for payment and will be released only upon receipt of written
instruction from the city.
2. Cash Deposits: If the surety is in the form of a cash deposit with the City, proportional parts
thereof shall be refundable in relation to progress payments less retainage, subject to approval of
the City and subject to a minimum deposit balance of 25% of the project cost.
3. Maintenance Guarantees: If the applicant completes all required improvements and complies
with all conditions of the subdivision agreement as determined by the City , the remainder of
monies retained by a financial institution or by the City may be released to the applicant or his
successor in title. Prior to release, the applicant shall provide the City, prior to the issuance of any
building permit, a performance bond, a surety bond, or a cash deposit equal to the amount
16
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
determined by the City to be necessary to ensure the repair of any damage to the existing
improvements during the course of any construction, but in no case will the amount of the
security be less than $1,000.00 for each individual building lot. Prior to the issuance of any
certificate of occupancy, the city shall determine whether or not any breakage or damage has
occurred. If no damage to any off-site improvements has occurred, then the city may release the
security to the applicant or his successor in title. If damages have occurred, they shall be
repaired, or the city may draw on the security before it is released.
7.1.6 EASEMENT AND UTILITY STANDARDS
A. Multiple installations within easements: Easements shall be designed so as to provide efficient
installation of utilities. Public utility installations shall be located as to permit multiple installations
within the easements. The developer will establish final utility grades prior to utility installations. Public
utility easement dedication shall be required with any minor or major subdivision action.
B. Underground utilities: Telephone lines, electric lines, cable television lines and other like utility services
shall be placed underground. The applicant and developer shall be responsible for complying with the
requirements of this Section and shall make the necessary arrangements including any construction or
installation charges with each utility provider for the installation of such underground facilities.
Transformers, switching boxes, meter cabinets, pedestals, ducts and other facilities necessarily
appurtenant to such underground utilities shall be placed underground or on the surface but not
on utility poles. Screening or fencing is required and subject to approval of the City. Electric
transmission and distribution feeder lines and necessary appurtenances thereto may not be placed
above ground unless they are carrying greater than 115 kV. Upon approval of the City , such facilities
shall be placed within easements or rights-of-way provided for particular facilities.
7.2: STREET NETWORK AND DESIGN STANDARDS
7.2.1 STREET INFRASTRUCTURE PLANS
A. Purpose and Intent: The Street Infrastructure Plans in Appendix C provide diagrams of the City's street
network and establish the ideal alignment, hierarchy and design characteristics - including total right-
of-way width, sidewalk and streetscape amenities, parking lanes, travel lanes and other geometric and
urban design details - for all existing streets, proposed streets that have been adopted as part of an
Official Map, and new potential streets in the City.
B. Official Street Network Plan: Pursuant to S.C. Code § 6-7-1210, et seq. (1976), as amended, the City
has previously adopted several Official Maps. An Official Street Network Plan is incorporated into this
Code in Appendix C.2 to represent a composite of these previously-adopted Official Maps.
1. Purpose: This plan represents a composite of all Official Maps, to date, in the City. The map
designates existing or proposed streets or ways within the City that are targeted for creation,
expansion or other improvements. The Official Street Network Plan shall in itially consist of a
series of four (4) separate maps, included in Appendix C, which shall be deemed a part of this
Code.
2. Modification: The Official Street Network Plan may be modified or supplemented pursuant to
the procedure for Text & Map Amendments (Section 9.16). In addition, the maps will be
17
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
automatically updated as additional Official Maps are approved pursuant to the appropriate
process required by state law.
C. Street Frontage Requirements: The provisions regarding street sections in Appendix C show specific
street designs for the purpose of identifying future improvements by both the City and fronting
property owners. These sections depict the ideal arrangement and design of street elements.
1. Applicability: For any project that is considered part of a Major Subdivision Site Plan , requires a
Certificate of Appropriateness as a Major project type (Section 9.10.2.A.2.), and/or which affects
one whole Block Face, the fronting property owner shall install all prescribed streetscape
improvements as part of the development project. The installation of street frontage
improvements shall be a condition of Final Plat approval for Major Subdivisions, and Certificates
of Occupancy for Site Plans.
Exception: If similar elements as prescribed in the street section exist — e.g., on-street parking,
sidewalk, tree plantings — the requirement to install the streetscape element(s) shall be waived
if those items meet the intent of the prescribed street section, even if the existing items do not
meet the exact requirements of that street section. Example Scenarios: If a street section
prescribes a 5-foot sidewalk, but a 4-foot sidewalk already exists, the existing sidewalk will satisfy
the sidewalk requirement. However, if the street section requires a 5-foot planting strip between
the curb and the sidewalk, and the 4-foot sidewalk is directly adjacent to the curb, this would not
satisfy the intent of the street section and would need to be reconstructed per the prescr ibed
standards.
2. Scope of Improvements: Street frontage improvements shall be installed along the entire
frontage of the property to the centerline of the street or, if a multi-lane street, the affected
lane, at the sole cost of the applicant as directed by the Administrator . The Administrator may
permit modification of street improvement standards where the required street improvements
are not, in the opinion of the Administrator, roughly proportionate to the impact, type, scale and
cost of the proposed development action.
a. Street frontage improvements may include the following: curb, gutter, sidewalk, storm
drainage, street lighting, traffic signal equipment, utility installation , extension, or relocation,
landscaping strip, street trees and landscaping, irrigation, street widening, pavement overlay or
reconstruction, and channelization.
b. In addition to required frontage improvements, the applicant shall provide ramps from the
new sidewalk or walkway to the existing shoulder, across streets and pavement and
channelization tapering back to the existing pavement and channelization as required to address
safety concerns.
D. Dedication of Right-of-Way:
1. Dedication of Right-of-Way. In the case of a street section adopted as part of an Official Map,
where the width of the existing right-of-way is insufficient to install the prescribed street section,
the fronting property owner shall be required to reserve the appropriate amount of right-of-way
(as measured from the centerline of the existing street). The future right-of-way shall conform to
all of the street network requirements of Section 7.2.2. Where a new right -of-way that is not
shown in the Street Regulating Plan is required as part of a new development, it shall be
designed with appropriate elements based on its proposed location and zoning district. (See
Appendix C).
a. In the case of a street section that is not part of an Official Map, where the width of the
existing right-of-way is insufficient to install the prescribed street section, the property
18
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
owner shall reserve the appropriate amount of right-of-way to complete the desired street
section. If the owner dedicates and installs the complete right-of-way, the cost of the
improvements may be borne by the City (see Section 7.2.1 E).
b. Where an area is designated as a future right-of-way and identified on an Official Map, new
development shall reserve this area for the new street in the future. If access is needed to
the site in that location, the street shall be constructed in the general location shown.
c. Exceptions and Alternatives: Where the available rights-of-way — do not functionally permit
the full section to be constructed due to existing structures or topographic conditions limited
to wetlands, specimen and landmark trees, the Administrator may adjust the requirements
for the street section.
E. Compensation: When a project is required to make off-site improvements within the existing right-of-
way, dedicate and/or improve a street with insufficient right-of-way, or install a new street (be it
public or private) per the requirements in Section 7.2.1.C., above, compensation of the developer for
the costs associated with such improvements may be available at the City’s discretion. To the extent
that the City has the authority and the ability to do so, the Traffic Impact fee for the project shall be
reduced by the assessed value of the dedicated land and/or construction cost of the right -of-way
improvement. This may be done either as a direct reduction, rebate, or reimbursement of fees .
7.2.2 STREET NETWORK REQUIREMENTS
A. Continuation of Adjoining Street System: The proposed street layout shall be coordinated with the
street system of the surrounding area to form an interconnected street pattern, formalized by a
platted public access easement. The adequacy of street connectivity shall be assessed by the Technical
Review Committee (“TRC”) based on the ability of the proposed alignments to:
1. Permit multiple routes between origin and destination points;
2. Diffuse traffic; and
3. Shorten walking distances.
B. Block Sizes: Blocks shall be compact so that they are comfortably walkable and appropriate for their
context.
1. In T3-S zones, block sizes are flexible, but the perimeter shall not exceed 2,640 linear feet (½
mile). An average block perimeter of less than 2,000 feet is preferred.
2. In T3-N zones, block sizes are flexible, but the perimeter shall not exceed 1,700 linear feet . An
average block perimeter of less than 1,500 feet is preferred.
3. In T4, T5 and RMX zones, blocks shall be no more than 400 feet on any side. An average block
length of 250 to 300 feet is preferred. The block perimeter shall not exceed 1,320 linear feet (¼ -
mile).
4. Exceptions may be made for natural elements such as wetlands, trees, topography, and cultural
resources, to be incorporated into the site design.
C. Street Stubs: New developments shall connect to any existing street stubs from adjacent properties
and stub to all adjacent properties.
1. Exemptions: Street stubs shall not be required where the Planning Commission finds the
conditions listed below would prevent connections:
a. Topographical conditions: pre-development slopes of 18% or greater.
19
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
b. Environmental conditions: marshes, floodplains, specimen and landmark trees, etc.
c. Property shape that would not allow for street stubs.
d. Property accessibility: existing platted subdivision with no stubs.
e. Incompatible adjacent land uses.
2. Location: Where multiple connection opportunities exist, street stub connections shall be
prioritized in the site design as follows:
a. Adjacent parcels 20 acres or greater in size.
b. Adjacent parcels that abut or are traversed by existing or proposed streets.
c. T he Street Network Diagram recommends a street connection (indicated as a proposed
street).
3. Design:
a. Stub streets and streets intended for extension during future phases shall be constructed
to extend to the property line for constructability to adjoining property.
b. Stub streets shall not exceed 150 feet in length without a paved turnaround (permanent or
temporary).
c. Disclosure: The Final Subdivision Plat shall be recorded depicting that future connection is
required at any stub streets and streets intended for extension during future phases. A
clearly visible street sign shall be erected at the end of the stub street stating that the
street is planned to connect to a future street.
D. Cul-de-sacs and Dead-end Streets: Dead-end streets and cul-de-sacs are prohibited, except in T-3 and
LI zoning districts, where cul-de-sacs or other turn-arounds may be approved by the Planning
Commission. Compliance with the following standards must be met in all circumstances:
1. Permanent dead-end streets shall be no longer than 300 feet and shall be provided with a turn-
around such as a cul-de-sac or close.
2. Temporary dead-end streets shall be provided with a temporary turnaround area which shall be
designed considering traffic usage, maintenance, and removal.
20
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
3. Alternative design solutions, such as a close (first preference), or a loop road cul -de-sac (second
preference) are preferable to a typical cul-de-sac.
4. Cul-de-sacs shall have a minimum right-of-way radius of 50 feet and minimum paved radius of 40
feet. When ample radii space exists, cul-de-sacs shall contain a central planted median.
5. Whenever cul-de-sac roads are created, at least one pedestrian access easement shall be
provided, to the extent practicable, between each cul-de-sac head or road turnaround and the
sidewalk system of the closest adjacent road or pedestrian pathway. The access easement shall
be direct with a minimum width of 12 feet.
E. Gated Streets: New gated streets are prohibited with the following exceptions:
1. A t the discretion of the Planning Commission, in T3-S zoning districts where connection to the
existing street grid is not practicable due to topography or existing surrounding conditions.
2. At the discretion of the Planning Commission when the access proposed to be gated is an alley or
rear lane and is not the primary building frontage.
F. Street Naming and Renaming: New street names and street renaming are subject to the requirements
of S.C. Code § 6-29-1200. Proposed Street names and number systems shall be reviewed by and
subject to the approval of the Administrator and the Beaufort County Emergency Management
Department. No duplicate/similar names are allowed, as determined by these agencies.
G. Reserved Strips Prohibited: Reserved strips at the terminus of a new street shall be prohibited.
21
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
7.2.3 LOT ACCESS STANDARDS
A. Applicability: Any development that requires one or more access point s for purposes of ingress and/or
egress shall be subject to the provisions of this section. All new access points must be approved by the
appropriate permitting authority. Access points may not be installed on undeveloped property less
than 2 acres.
B. Maximum Number: For single-family and two- and three-family dwellings, only one driveway shall be
permitted per lot. In T3-S, circular driveways may be permitted on lots greater than 100 feet in width,
where no sidewalk exists. Driveways may only be installed when rear access is not possible or required.
For double frontage lots, one curb cut per street may be permitted. For all other building types, the
maximum number of driveways allowed for any property is outlined in the table below.
FRONTAGE
WIDTH
MAXIMUM PERMITTED ACCESS POINTS (CURB CUTS)
PER STREET FRONTAGE
Less than 150 feet 1
150 feet or more 2 - Additional access points (in excess of 2) shall be permitted only after the applicant
successfully demonstrates the necessity for such additional access points, as determined
by the appropriate design review body. Along arterial roads and thoroughfares, such
additional access points shall be "right-in, right-out" driveways only.
C. Location and Spacing:
1. Street Intersection: No curb cut or other access point shall be located closer than:
a. 20 feet from the intersecting point of the 2 street right-of-way property lines involved (or
such lines extended in case of a rounded corner);
b. 25 feet from the intersection of the 2 curb lines involved (or such lines extended in case of
a rounded corner), whichever is the least restrictive.
2. Spacing: All access points shall have a minimum separation from certain features as follows:
FEATURE MINIMUM SEPARATION1
Adjacent Property Line (does not apply to shared or
joint-use driveways)
0 ft
Another Curb Cut (driveway or street intersection) on
all roads except Major Thoroughfares
25 ft
Another Curb Cut (driveway or street intersection) on
Major Thoroughfares (streets with the Street Section
designation of Major Thoroughfare, or the Robert
Smalls Parkway, Sea Island Parkway/Lady's Island
Drive, or Boundary Street Specific Street Section) —
Dependent on posted speed limit as follows:
Speed Limit Separation
< 35 mph 100 ft
35 mph 200 ft
40 mph 250 ft
45 mph2 300 ft
45 mph2 300 ft
55+ mph2 500 ft
22
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
1 Minimum separation is measured from centerline
2 On Robert Smalls Parkway (Hwy 170) west of Parris Island Gateway, a minimum of 500 ft. separation distance
is required
3. Corner Lots: Access points on corner lots shall be from the side (or secondary) street, unless a
shared curb cut on the main thoroughfare is existing or proposed.
4. Access to Lots from Major Thoroughfares: Driveways serving individual residential lots shall not
have direct access onto streets identified as Major Thoroughfares — as identified on the second
row of the chart in Section 7.2.3 C.2. — unless no alternative means of access, such as alleys or
parallel access roads, exist, and it is unreasonable or impractical to require an alternative means
of access.
5. Shared Access: See Section 5.7.7 C.
6. Rear Access Required/No Front Access: For lots developed in the transect zones of T-3N, T-4, and
T-5 UC, all new access points shall be from a rear alley and/or road, except for lots within the
historic district. Exemptions to allow front loaded access points where connection to the existing
street grid is not practicable due to topography or existing surrounding conditions shall be at the
discretion of the Planning Commission with approval of major subdivisions, and the Codes
Administrator for individual lots.
D. Size:
1. Alleys: Alley pavement width may be a maximum of 24 feet wide for two -way traffic and 16 feet
wide for one-way traffic. For more design standards, see Appendix C.
2. Driveways:
a. Driveways for single-family and 2- and 3-family uses may not exceed 12 feet wide, except in
T3-S district, where they may be a maximum of 20 feet wide.
b. Tandem Parking: Tandem parking is allowed in all zones for all residential uses if:
i. Both tandem parking spaces satisfy the parking requirement of one residential
unit; and
ii. Neither of the tandem parking spaces shall be for required accessible parking
spaces.
c. Driveways to other uses and parking areas shall not exceed 24 feet in width for 2 -way
drives or 12 feet in width for one-way drives, except those with turn lanes required by the
City or SCDOT.
E. Access to Lots from Alleys/Rear Lanes:
1. Specific to T3-N, T4, and T5 districts: Alleys/rear lanes shall be provided along the rear property
lines of lots as follows:
a. In new subdivisions greater than 1 acre, alleys shall be provided for newly created lots that
meet any of the following criteria:
23
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
i. The lots are part of a Block Face with an average lot width of 60 feet or less at
the building setback line (excluding lots on cul-de-sacs).
ii. The lots are arranged around a Common Open Space.
iii. The lots front a collector or arterial road, regardless of the average lot width.
iv. The lots are intended for multi-family dwellings and/or mixed-use buildings.
b. For Infill developments, the same standards apply as specified in the immediately
preceding subsection, but only for developments that include 4 or more contiguous lots,
where one lot is a corner lot. In the Historic District, the standards apply only to the
Beaufort Conservation District; the requirement may be waived at the discretion of the
Historic Review Board.
F. Specific to Commercial Developments and Subdivisions:
1. Out-parcels: Out-parcels for shopping, office, or industrial centers shall be limited to internal
access to the center, unless otherwise approved as part of a master development plan. All
driveways shall be paved from the road to the property line.
2. Abandoned Driveways: Abandoned driveways (i.e., curb cuts that are no longer used for
vehicular access and are physically blocked by structures) shall be closed, and the area shall be
restored to the typical cross section of the right-of-way.
7.2.4 STREET DESIGN STANDARDS
A. Street Section Design: The elements and widths of all proposed streets shall be in conformity with the
appropriate street section designated in the Street Infrastructure Plans (Section 7.2.1 and Appendix C).
B. Traffic Control and Signs: The type and location of traffic control devices used on City streets must be
approved by the Administrator or the Administrator’s designee, and traffic control on private streets
shall be included and approved as part of the major subdivision or site plan. Traffic signals should be
used where warranted, but alternative means of traffic control such as roundabouts should be
considered first. When it can be shown that a particular zoning action, master plan, or development
plan impacts the street system to a point that a traffic signal is warranted according to the latest
version of the United States Department of Transportation’s Manual on Uniform Traffic Control
Devices (“MUTCD”) and approved by the Administrator or the Administrator’s designee, , the developer
shall be responsible for all or a portion of the signal installation.
C. Sidewalks/Multi-use Paths: Where required by the provisions of Appendix C, all sidewalks or multi-use
paths must be constructed concurrently with the street or, if the street is already constructed, prior to
acceptance of any improvements. Exceptions to the requirement to install a sidewalk may be granted
by the Planning Commission if:
1. Alternative pedestrian paths/bikeways have been or will be provided outside of the normal right -
of-way.
2. There are unusual topographic, vegetative, or other natural conditions that would render strict
adherence to the requirements of this section unreasonable and not consistent with the
purposes and goals of this Code.
D. Utility Easements: Utility easements which require a width of 8 feet or more shall be located in rear
alleys or adjacent to rear lot lines. Special permission to install utility easements in other locations may
be requested by the utility companies and is subject to approval by the appropriate design review
body.
24
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
E. Special Consideration for Protected Resources and other Natural Features: Street layout and design
shall give additional consideration to preserving protected resources and enabling natural areas to be
protected or minimally disturbed. Where streets are built in areas that have protected resources or
natural features, all utilities shall be placed within the street right-of-way and under the street to avoid
additional destruction of the natural features.
7.2.5 STREET TREE PLANTING REQUIREMENTS
A. Planting Areas: Planting strips and tree wells shall be established in accordance with the width and
plantings designated in the appropriate Street Section of the Street Infrastructure Plans (7.2.1 and
Appendix C).
B. Location and Number: Street trees shall be planted in the location and per the spacing specified for the
corresponding street classification in Appendix C. However, in specific cases, where due to the location
of utilities or other site constraints, the Planning Commission may allow street trees to be planted on
private property adjacent to the right-of-way.
C. Tree Species: The species of overstory and understory trees listed in Appendix A.2 may be used for
street tree planting
D. Minimum Tree Size: At the time of planting, young trees should be 2.5 inch caliper, with the lower side
of the crown a minimum of 6 feet above grade.
7.3: STREET ENGINEERING STANDARDS
7.3.1 STREET DESIGN, CERTIFICATION, AND CONSTRUCTION SPECIFICATIONS
A. Design Drawings and Certification: Professional engineers, registered in the State of South Carolina,
shall prepare plans, profiles, cross sections, and specifications for all subdivision roads and streets. The
engineers shall certify that the roads/streets are built to comply with the approved plans and
specifications. Cross sections shall be developed every 100 feet at intersections and break points in
grade. Cross sections shall show the complete rights-of-way including travel lanes, shoulders, ditches,
curb and gutter, and sidewalks and utility locations, as applicable.
B. Construction Specifications for Paved Streets: Street construction specifications for paved streets shall
comply with the South Carolina Department of Transportation Standards.
7.3.2 TRAFFIC IMPACT ANALYSIS
A. Applicability: A Traffic Impact Analysis (“TIA”) shall be required for any development that is shown to
generate more than 50 trips during the peak hour on the adjacent street(s) in the most recent Institute
of Transportation Engineers (“ITE”) Trip Generation Manual or any alternative, approved at the
discretion of the Planning Commission or the TRC, or by the engineering department .
1. A second phase, second subdivision, or addition that generates traffic beyond this threshold,
when taken as a whole, shall also require a TIA, even though that development may not qualify
on its own.
2. A use shall not be changed without conducting a new TIA if the new use would generate traffic
beyond the 50 trips during peak hour threshold referenced above. The Planning Commission may
waive this requirement.
25
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
3. Exception: Development on lots included in the Boundary Street Master Plan, adopted on August
28, 2006, and lots in the area bounded by Calhoun Street, Carteret Street, Bay Street, and Ribaut
Road, and lots zoned Limited Industrial (LI), shall not be subject to the requirements of this
section. This exception does not apply to Educational Facilities with greater than 100 students.
B. Traffic Access Management Analysis: As part of the TIA process, the proposed development shall have
an "access analysis" undertaken by the administrator to ensure that sufficient access to all proposed
developments and subdivisions is achieved.
1. The standards in the South Carolina Department of Transportation's "Access and Roadside
Management Standards Manual" (“ARMS Manual”) shall serve as a guide for this analysis, which
shall include identification of the following:
a. Access improvements, such as deceleration lanes, that the applicant must install at the
applicant’s own;
b. The location of any curb cuts based on, but not limited to, sight distances, existing roadway
infrastructure, opposing driveways locations, and shared access;
c. Requirements for adequate driveway design, including, but not limited to, turning radius
and stacking distance.
2. The access requirements approved by the Planning Commission or the TRC shall be incorporated
on development or subdivision plans prior to their approval.
3. If an applicant is required to provide site-related traffic improvements, the cost of implementing
such improvements shall be borne by the applicant, and no such costs shall be eligible for a credit
or offset from any transportation impact fees unless specifically permitted by the Development
Fee Procedures as stated in the Beaufort County Code of Ordinances, Chapter 82, Article II or
most recent version.
C. Traffic Impact Analysis Plan Preparation:
1. The TIA shall be conducted by an engineer registered in South Carolina who is experienced in the
conduct of traffic analysis.
2. Prior to beginning the TIA, the applicant shall supply the City with the following:
a. A written narrative describing the proposed land use(s), size, and projected opening date of
the project and all subsequent phases.
b. A site location map showing surrounding development within a one -half mile radius of the
property under development consideration.
c. A proposed site plan or preliminary subdivision plat illustrating access to public or private
roads and connectivity to other contiguous developments.
3. Prior to beginning the TIA, the applicant shall receive, in writing, the parameters to be followed in
the study, including the directional split of driveway traffic, trip distribution, background traffic
growth rate, previously approved but not completed projects, and the intersections to be
analyzed, along with any associated turning movement counts that are available or discussed and
approved by the TRC.
4. To review the TIA, the Planning Commission and TRC will require current trip generation
information, available information on land use, travel patterns, and traffic conditions, and shall
consult with the SCDOT.
26
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
D. Plan Contents:
Background information Requirement
List of all nonexistent transportation improvements
assumed in the analysis
Required
Map of site location, description of the parcel,
general terrain features, and location within the
jurisdiction and region. R
equired
Description of geographic scope/ limits of study
area.
Within half mile/2,640 feet of site and any roadway
on which 50 or more of the new peak hour vehicle
trips generated by the proposal are distributed.
At the discretion of the TRC or Planning Commission,
a larger study area may be required.
Plan at an engineering scale of the existing and
proposed site uses.
Required
Description and map or diagram of nearby uses,
including parcel zoning.
Required
Description and map or diagram of existing
roadways.
Required
Description and map or diagram of programmed
improvements to roadways, intersections, and
other transportation facilities within the study
area.
R equired
Analysis of Existing Conditions
Collected daily and peak hour of the generator
traffic volumes, tabulated and presented on
diagrams with counts provided in an appendix.
R
equired
Analyses for intersections and roadways identified
by SCDOT. Delay and Level of Service (LOS) are
tabulated and LOS is presented on diagrams for
each lane group.
R
equired
27
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
When the type of development proposed would
indicate significant potential for walking, bike or
transit trips either on - or off - site, analyses of
pedestrian and bicycle facilities, and bus route or
routes and segment or segments, tabulated and
presented on diagrams, if facilities or routes exist.
Within half mile/2,640 feet of site and any roadway
on which 50 or more of the new peak hour vehicle
trips generated by the proposal are distributed –
At the discretion of the TRC or Planning Commission,
a larger study area may be required.
Incorporation of all Traffic Impact Analysis studies
and Trip Generation from approved developments
or vested unbuilt developments within mile radius
at time of proposal.
Required (submitted for any jurisdiction, including
the Town of Port Royal, and County of Beaufort)
Speed Study If requested by City
Crash history near site If requested by City
Sight distance If requested by City
Analysis of Future Conditions without Development
Description of and justification for the method and
assumptions used to forecast future traffic volumes.
Required
Analyses for intersections and roadways as identified
by SCDOT. Delay and Level of Service (LOS) are
tabulated and LOS is presented on diagrams for each
lane group.
Required
When the type of development proposed would
indicate significant potential for walking, bike or
transit trips either on - or off - site, analyses of
pedestrian and bicycle facilities, and bus route or
routes and segment or segments tabulated and
presented on diagrams, if facilities or routes exist or
are planned.
Within half mile/2,640 feet of site and any roadway
on which 50 or more of the new peak hour vehicle
trips generated by the proposal are distributed.
At the discretion of the TRC or Planning Commission,
a larger study area may be required.
Trip Generation
Site trip generation, with tabulated data, broken out
by analysis year for multi- phase developments, and
including justification for deviations from ITE rates, if
appropriate.
Required
Description and justification of internal capture
reductions for mixed use developments and pass-by Required
28
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
trip reductions, if appropriate, including table of
calculations used.
1. Phased Developments: All phases of a development are subject to review, and all traffic plans for
the entire development shall be integrated with the overall traffic analysis. A TIA for a specific
phase of development shall be applicable to the phase of development under imme diate review.
However, each phase of development shall expand and provide detailed analysis at the
development plan stage beyond the estimates provided for at the concept plan or master plan
stage.
2. Infrastructure Analysis: The adequacy of the roads that the development will be accessed from
shall be assessed in the TIA. Recommendations for improvements to these roads shall be made.
The relative share of the capacity created shall be broken down as follows: development share,
other developments' share, any existing overcapacity, and capacity available for future growth.
3. Required Elements of the TIA:
a. A site plan or subdivision plat identifying access points to and from existing or proposed
streets and intersections, along with all opposing intersections across adjacent streets.
b. Description of the proposed development, including the type and intensity of proposed
land use(s) including, but not limited to: the number of residential units by type, the
number of existing and proposed lots, the type of proposed nonresidential devel opment
and the amount of such development measured by gross floor area or other appropriate
unit of measurement, the general size and type of accessory development or facilities, and,
for nonresidential development, adequate information to identify the appropriate land use
category for trip generation.
c. Projected vehicular trips to and from the completed development during a.m. and p.m.
peak hour — trip rates shall be taken from ITE Manual or alternatively, an applicant may
elect to perform, at his own expense, a trip generation study which may be submitted as
part of the TIA plan. The trip generation study shall be subject to the review and
verification of the TRC and engineer. For proposed uses not specifically listed in the ITE
Manual, and for which a trip generation study has not been performed, the designated
engineer(s) shall determine the most appropriate trip generation rate. The TRC shall make
the determination of the appropriate trip generation rate, from whatever the source. The
percentage of pass-by trips, if used in the plan, shall be included, as well as the source of
this information.
d. A written narrative setting forth the assumptions upon which any projection was made in
developing the TIA plan shall be included in the analysis. If the assumptions are derived
from the ITE Manual, the materials shall be referenced and properly cited. If the
assumptions are not from the ITE Manual, appropriate excerpts from other reliable
transportation planning resources shall be included in the study, and reasons underlying
the assumptions shall be stated in the narrative.
e. The TIA shall review access to the site. The adequacy of the entrance design shall be
evaluated, and recommendations made on acceleration and deceleration lanes, left -turn
lanes, or signalizations shall be part of the TIA. Educational facilities shall include pick -up
and drop-off plans and analysis of the impact on the surrounding streets and interse ctions.
29
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
f. The TIA shall review the number and types of curb cuts that are permitted. In particular,
the TIA shall assess the connection of the property to adjoining properties. Where the use,
scale of development, or size of adjoining properties is such that trip s would be anticipated
between the proposed use and the other properties, the TIA shall make recommendation
on interconnections. The TIA shall recommend interconnections to provide a smooth flow
of traffic between uses along arterials and collector roads to ensure that as much traffic as
possible uses secondary roads, rather than major roads, for short trips.
g. The TIA shall be based on intersection analysis procedures for signalized intersections as
identified in the most current edition of the Transportation Research Board's Highway
Capacity Manual, and/or the last update that analyzes and emulates these procedures by
means of computer software, if available. The results of any required analysis/computer
analysis shall, at a minimum, indicate compliance or variance from the Traffic Service Level
Goals (Section 7.3.2.M.).
h. The intersections that must be analyzed in the study are identified as:
i. Any intersection that serves as a development's point of access. This will
include intersections of public and/or private roads with major arterials, and
driveways offering direct access.
ii. The first major intersection as identified by the city engineer on both side of
the development's point of access.
iii. Other intersections on major arterials if development generates more than 50
a.m. or p.m. peak hour trips to that intersection, or if the intersection's level of
service or demand is significantly impacted by site related traffic.
iv. Unsignalized intersections and access drives — these shall be considered if
development impacts are anticipated. The plan must include the results of an
analysis of the operating conditions of critical intersections and/or all
intersections identified in the concept plan. The analysis shall reflect the
projected condition of these intersections and movements, based on the
scheduled opening date of the development. Other phases of the development,
if they can be reasonably determined, shall be considered as well.
E. Mitigation Plan Required: If the initial analysis indicates that the city's adopted Traffic Service Level
Goals (Section 7.3.2.M.) will not be met, a mitigation plan must be prepared, based on additional
analysis. The mitigation plan must show how the city's Traffic Service Level Goals are addressed as
mitigated. Applicants will be responsible for mitigating the traffic impacts at any intersection affected
by a proposed development.
1. If a traffic signal is recommended, the TIA shall provide information that:
a. Clearly indicates the need for a traffic signal.
b. Assesses the ability of other existing, planned, or proposed public roads to accommodate
the new traffic at a location other than the main highway in the vicinity of the proposed
development.
c. Describes in detail how a specific development will affect the study area transportation
system.
d. Provides documentation of appropriate South Carolina Manual of Uniform Traffic Control
Devices signal warrant satisfaction.
30
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
e. Gives design geometry of the private road that is consistent with that of public road
intersections, including curbs, appropriate lane widths, pavement markings, and vertical
alignment. Other roadway factors to be considered include, but are not limited to, speed,
type of highway, grades, sight distance, existing level of service, conflicting accesses, and
the effect of future traffic signal systems.
f. Provides an approach-throat length for the road to ensure the movement of vehicles
entering the site will not be impeded by conditions within the development and ensure
that all signal-spacing requirements are adequately met.
2. The desirable spacing of signalized intersections on principal arterials is the SCDOT, county, or
City standards. The TRC may recommend to SCDOT the installation of a traffic signal at locations
where, using SCDOT standards, spacing is inappropriate due to topography, existing or proposed
road layout, documented accident history, unique physical constraints, existing or proposed land
use patterns, or requirements to achieve specific objectives for highway segment designations, as
shown in any locally adopted land use or transportation plan, approved City or county
transportation plan, or approved transportation policy.
3. Signal spacing concerns may be ameliorated in the following ways:
a. A proposed private road that may otherwise be considered for the installation of a traffic
signal may be replaced by an on-site route or a frontage road that directs traffic to or from
a nearby public road.
b. A private road that is being considered for traffic signal installation may be required to
connect to the existing or planned local road system to allow uses of surrounding
properties.
c. An existing or proposed intersection may be relocated.
d. A shared private road may be required to serve the needs of the multiple properties.
4. A traffic signal progression analysis is required if the proposed location is closer than the SCDOT
standards, given the presence of existing signals or the possible existence of identified future
signals proposed as part of a highway signal system. A traffic signal progression analysis for all
new, revised, or planned traffic signal systems on state highways shall be performed using
methods, models, computer software, data sources, roadway segment length, and assumptions
approved by the TRC. The roadway segment, analyzed to the extent possible, shall include all
traffic signals in the existing or future traffic signal system. The progression analysis shall:
a. Demonstrate acceptable existing and future traffic signal systems operation that may
include the morning peak, evening peak, midday period, and other appropriate time period
during any day of the week, adjusted for peak season, for cycle lengths and tra vel speeds
approved by the TRC.
b. Provide for a progressed traffic band speed no more than 5 mph (8 km/h) below the
existing posted speed for both directions of travel during the off-peak periods, nor more
than 10 mph (16 km/h) below the existing posted speed during peak periods. Approv al by
the TRC is required where speeds deviate more than the above.
c. Demonstrate that sufficient vehicle storage is available at all locations within the traffic
signal system without encroaching on the functional boundaries of adjacent lanes and
signalized intersections. The functional boundary of an intersection shall be determined in
discussion with the TRC, based on existing or projected conditions.
31
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
d. Provide a common cycle length with adequate pedestrian crossing times at all signalized
intersections.
e. Provide a progression bandwidth as large as that required, or as presently exists, for
through traffic on the federal or state highway at the most critical intersection within the
roadway segment. The most critical intersection is the intersection carrying the highest
through volume per lane.
5. The traffic signal progression analysis shall be supplemented by a traffic engineering report that
also considers highway capacity and safety of the roadway segment under consideration. Traffic
volumes, intersection geometry, and lane balance, considered at all locations, shall be
appropriate for the present and identified future conditions, which are usually considered to
include the year of completion, and 5 years into the future.
F. Summary: A clear and concise summary of recommended improvements that can serve as an
executive summary is required.
G. TIA Review: The TRC shall review all TIAs as part of the applicable Design Review phase. Final TIAs shall
be approved prior to the applicant submitting a Project Permit application (Section 9.5).
H. Application: A TIA shall be submitted to the TRC. Coordination with other entities in the county
government or South Carolina Department of Transportation (SCDOT) shall be the responsibility of the
City.
I. Completeness: The Planning Commission and/or TRC shall determine whether a TIA is complete.
Thorough and complete TIAs are the responsibility of the applicant. Failure by the applicant to provide
a complete TIA may result in review delays for its plat or plan.
J. Action on TIA: The TRC must first approve the TIA in regard to completeness and accuracy. Following
review of the required impact analysis plan, TRC shall recommend to the Planning Commission action
as follows:
1. Approval of the TIA as submitted;
2. Approval of the TIA with conditions or modifications as part of the development review and
approval process. An acceptable TIA with traffic mitigation measures may include the reduction
of the density or intensity of the proposed development, phasing of the proposed development
to coincide with state and/or county-programmed transportation improvements, applicant-
provided transportation improvements, fees in lieu of construction, or any other reasonable
measures to ensure that the adopted traffic service-level goals are met. If mitigation is required,
it shall be required as a condition of any approval from the city.
K. Timing of Implementation: If a traffic mitigation program is part of an approved TIA, the developer
may be required to place a performance bond on all traffic mitigation improvements required as a
result of the project. This requirement may arise if the timing of the improvements needs to be
synchronized with other scheduled improvements anticipated for the area.
L. Responsibility for Costs of Improvements: The costs of implementation of an approved mitigation
program shall be the responsibility of the applicant. No certificates of zoning compliance or building
permits shall be issued unless provisions of the TIA are met.
M. Traffic Service Level Goals: The average stop time delay in seconds per vehicle for each intersection
determined to be critical to the TIA for the proposed development shall be compared to the City's
traffic service level goal of "D" for the average delay for all vehicles at any signalized intersection during
the a.m. and p.m. peak hours.
32
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
7.4: COMMUNITY GREEN SPACE AND COMMUNITY OPEN SPACE
7.4.1 PURPOSE AND INTENT
A. Intent: Community Green Space and Community Open Space are intended for the use and enjoyment
of a development's residents, employees, or users. These spaces serve to preserve natural areas,
ensure access to open areas and recreation, reduce the heat island effect, enhance stormwater quality,
and provide community health benefits. Community Green Space and Community Open Spaces are
not, by definition, required to be deeded or to be granted via easement to any public entity or
municipality. See Section 7.4.5 for ownership information.
B. Purpose: The purpose of this section is to provide a set of Community Green Space and Community
Open Space types and their associated standards to use within all districts. Community Green Space
and Community Open Space types in this section are distinct from those areas that are environmentally
sensitive and must be otherwise protected as regulated through Chapter 8 (Environmental Protection).
C. Applicability: See Section 7.1.2.
D. Community Green Space Definition: an area of grass, trees, parks, trails or multi-use pathways, or
other vegetation set apart for recreational or aesthetic purposes with in a development. It can be
privately or publicly owned.
E. Community Open Space Definition: Open space is land or water that is undeveloped and not used for
residential, commercial, industrial, or institutional purposes. It can be privately or publicly owned, and
can include areas like forests, farms, parks, and coastal lands.
7.4.2 COMMUNITY GREEN SPACE AND COMMUNITY OPEN SPACE REQUIREMENT
A. Minimum Requirements: Development in all districts shall preserve the minimum amounts of
Community Green Space and Open Space as identified below (see following page):
33
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
B. Areas to be Included in Community Green Space and Community Open Space Calculations: The features and areas identified in Section 7.4.3 shall
be credited towards the open space requirements for the purposes of complying with this Chapter .
C. Areas not to be Included in Community Green Space and Community Open Space Calculations: The following areas shall not be counted toward
open space requirements:
1. Private yards which are not subject to an open space or conservation easement.
2. Public road rights-of-way or private street easements, including sidewalks located within those rights -of-way or easements.
3. Open parking areas and driveways for dwellings.
4. Land covered by structures not designated for active recreational uses.
5. Designated outdoor storage areas.
OPEN/CIVIC SPACE REQUIREMENT
SIZE T1 T3-S T3-N T4-HN T4-N T5-DC T5-UC RMX IC LI MHP 1
Less than 3
acres See footnote (3)
3 acres—
10 acres 50% 20% 15% exempt 10% exempt 10% 10% 15% exempt
10 acres—15
acres 50% 20% 15% exempt 10% exempt 10% 15% 20% exempt 10%
15 acres—40
acres 50% 20% 15% n/a 15% exempt 15% 20% 20% exempt 10%
Greater
than
40 acres
50% 25% 20% n/a 20% exempt 20% 25% 25% exempt 10%
1 Each Manufactured Home Park shall have a minimum total area of 2,500 square feet set aside for common recreational open space , or at least 100
square feet of space for each mobile home lot, whichever is greater.
2 Specific to TND Overlay Projects: The open space requirement may be calculated comprehensively or by specific Transect zones. The requirements of
2.8.3.E must be met in addition to the requirements of this table.
3 For properties less than 3 acres, community green space and community open space shall be at the discretion of the approving authority, i.e., Codes
Administrator or Planning Commission.
34
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
7.4.3 COMMUNITY GREEN SPACE AND COMMUNITY OPEN SPACE TYPES
The majority of Community Green Space and Community Open Space shall conform to one of the 8 types in the table below. If 75% or more of the types listed
below are utilized for required open space, a 20% increase in number of dwelling units is permitted.
CIVIC/
OPEN
SPACE TYPE
DIAGRAM DESCRIPTION PERMITTED
DISTRICTS
SERVICE AREA/
SIZE CHARACTER TYPICAL FACILITIES
Regional
Park/Natural
Preserve
A natural preserve that is
available for unstructured
recreation. It may contain
small civic buildings and
areas of structured activity,
but is primarily left natural.
These areas may include
forests as well as wetlands
and regional retention areas
if they are treated as
amenities (e.g. Port Royal's
Cypress Wetlands).
T1 Regional
Min: 200 acres*
Max: None
*Natural
preserves with
no structured
activity have no
minimum size.
Frontage:
Independent
Disposition:
Natural, formal
or informal
Passive and active
recreation, drinking
fountains,
Community facility <
7,500 gross square
feet, paths and trails
Sport Complex
An open space that
consolidates heavily
programmed athletic fields
and associated facilities.
T1, IC, RMX Regional
Min: 25 acres
Max: None
Frontage:
Independent
Disposition:
Formal or
informal
Passive and active
recreation, drinking
fountains, community
facility < 7,500 gross
square feet, paths
and trails
Community
Park
An open space that is
available for unstructured
recreation and a limited
amount of structured
recreation. It may contain a
limited amount of athletic
fields.
T3, T4, T5,
RMX, IC
Multiple
Neighborhoods
Min: 8 acres
Max: None
Frontage:
Independent
Disposition:
Informal
Passive and active
recreation, drinking
fountains, community
facility < 5,000 gross
square feet, paths
and trails
35
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
CIVIC/
OPEN
SPACE TYPE
DIAGRAM DESCRIPTION PERMITTED
DISTRICTS
SERVICE AREA/
SIZE CHARACTER TYPICAL FACILITIES
Greenway A linear open space that may
follow natural corridors, a
greenway provides
unstructured and limited
amounts of structured
recreation.
T1, T3, T4,
T5, RMX, IC
Multiple
Neighborhoods
Min: 8 acres or 1
mile
Max: None
Frontage:
Independent or
building
Disposition:
Natural or
informal
Passive and active
recreation, drinking
fountains, community
facility < 5,000 gross
square feet, paths
and trails
Square/Green An open space that is
available for civic purposes,
unstructured, and limited
amounts of structured
recreation. It can be located
along waterfronts.
T3, T4, T5,
RMX, IC
Neighborhood
Min: 0.5 acres
Max: 5 acres
Frontage:
Building
Disposition:
Formal
Passive and active
(unstructured or
structured)
recreation, accessory
structure, drinking
fountains, community
facility < 5,000 gross
square feet, paths
and trails
Plaza A formal open space
available for civic purposes
and commercial activities, a
plaza is typically hardscaped
and can be located along
waterfronts.
T4, T5, RMX,
IC
Neighborhood
Min: 0.5 acres
Max: 2.5 acres
Frontage:
Building
Disposition:
Formal
Passive recreation,
accessory structure,
drinking fountains,
paths and trails
Pocket
Park/Pocket
Plaza
An open space that is
available for informal
activities in close proximity
to neighborhood residences.
Pocket plazas are usually
paved.
T3, T4, T5,
IC, RMX
Neighborhood
Min: 4,000
square feet
Max: 0.5 acre
Frontage:
Building
Disposition:
Formal or
informal
Passive recreation,
accessory structure,
drinking fountains,
paths and trails
36
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
CIVIC/
OPEN
SPACE TYPE
DIAGRAM DESCRIPTION PERMITTED
DISTRICTS
SERVICE AREA/
SIZE CHARACTER TYPICAL FACILITIES
Playground
An open space designed and
equipped for the recreation
of children. A playground
may be fenced and may
include an open shelter.
Playgrounds may be included
within other civic spaces.
T3, T4, T5,
IC, RMX
Neighborhood
Min: None
Max: None
Frontage:
Independent or
building
Disposition:
Formal or
informal
Accessory structure,
drinking fountains,
paths and trails
Notes:
1. The illustration and description of each civic space type is illustrative in nature and not regulatory.
2. The Permitted Districts may be modified per a plan if the project is utilizing the Traditional Neighborhood Development Floating Overlay District
(Section 2.8.3).
37
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
The following provisions apply to the eight (8) Community Green Space and Community Open Space Types listed in
the table:
A. Playgrounds and Community Gardens: These may be incorporated into any of the other Community
Green Space and Community Open Space types - except Natural Preserve - or may stand alone.
B. Waterfront: When Community Green Space and Community Open Space is required, per Section 7.4.2,
developments that contain waterfront access should include some type of common access to at least
25% of the waterfront. This counts towards the Community Green Space and Community Open Space
requirement. When open space is required, for every 10% of the waterfront that is allocated for public
access, a 5% increase in number of dwelling units shall be permitted, up to a maximum of a 20%
increase.
C. Illustrative Standards: The columns titled "Diagram," "Description," and "Typical Facilities" of the table
of Community Green Space and Community Open Space Types are illustrative only.
D. Regulatory Standards: The following elements shall be regulatory:
1. Service Area: Describes how the space relates to the city as a whole and the area that will be
served by the Community Green Space and Community Open Space.
2. Size: The permitted size for each Community Green Space and Community Open Space.
3. Frontage: The relationship along property lines of a Community Green Space and Community
Open Space to adjacent buildings or lots.
a. Building: Community Green Space and Community Open Spaces that are listed as having a
"building" frontage shall have the fronts of buildings, either attached to the park or across
a street, facing onto the space for a minimum of 75% of the perimeter.
b. Independent: Community Green Space and Community Open Spaces that are listed as
having an "independent" frontage shall have the fronts of buildings, either attached to the
park or across a street, facing onto the space to the maximum extent possible, but may
have the side or rear of a building or lot front onto the space. The side or rear of a building
or lot fronting onto the Community Green Space and Community Open Space shall be
designed with a secondary frontage and entrance along the space.
4. Disposition: The character of the design of the Community Green Space and Community Open
Space.
a. Natural: Civic spaces with natural character are designed in a natural manner with no
formal arrangement of elements.
b. Formal: Civic spaces with a formal character have a more rigid layout that follows
geometric forms and have trees and other elements arranged in formal patterns.
c. Informal: Civic spaces with an informal character have a mix of formal and natural
characteristics.
5. Food Production: Community Gardens and other Community Green Space and Community Open
Spaces may be used to grow food. See Section 8.5.3 for specifications and requirements.
38
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
7.4.4 DESIGN OF COMMUNITY GREEN SPACE AND COMMUNITY OPEN SPACES
A. Design Standards for Community Green Space and Community Open Space: Land used as Community
Green Space and Open Space shall meet the following design standards:
1. Location:
a. Where relevant and appropriate, the land shall be located so as to be readily accessible and
usable by residents and users of the development. To the maximum extent practicable, a
portion of the open space shall provide focal points for the development.
b. Common space set aside for children's play areas and other recreational activities shall be
clearly visible from the dwelling units on the site.
c. The land shall, to the maximum extent practicable, be located to adjoin, extend, and
enlarge any open areas, trails, parks, or other open space resources that exist or are
planned within or adjacent to the development.
2. Provision in Multi-Phase Developments: In multi-phase developments, open space Manuals may
be calculated either by phases, or by collectively looking at the development s as a whole.
B. Accessory Structure Standards: All accessory structures within parks and open spaces — including, but
not limited to, restrooms, open-air pavilions, gazebos, picnic shelters, and outdoor theaters — shall not
be subject to the physical requirements of the building form or siting standar ds in Chapter 2 (Map and
Districts). They shall be designed to be consistent with the character of the district in which they are
located. Such consistency may require accessory structures to maintain building setbacks, frontage,
massing, disposition, and character similar to adjacent development as determined by the
administrator.
7.4.5 OWNERSHIP AND MAINTENANCE OF COMMUNITY GREEN SPACE AND COMMUNITY
OPEN SPACE
A. Open space areas or other community facilities shall be preserved and maintained in accordance with
the approved:
1. Development Design, in accordance with Section 9.8;
2. ZBOA Special Exception, in accordance with Section 9.13; or
3. Subdivision, in accordance with Section 9.9, whichever is appropriate.
B. Provision must be made by the property owner to ensure preservation and long term maintenance and
management of Community Green Space and Community Open Spaces through one of the following
mechanisms:
1. Conveyance of the land to a property owners' or homeowners' association that holds the land in
common ownership and will be responsible for managing and maintaining it for its intended
purposes.
2. Conveyance of the land to a third-party beneficiary, such as a nonprofit environmental or civic
organization, that is organized for, capable of, and willing to accept responsibility for managing
and maintaining the land for its intended purpose.
3. Dedication of the land to the city or other appropriate public agency that is organized for,
capable of, and willing to accept responsibility for managing and maintaining the land for its
intended purposes.
39
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
C. All methods utilizing private ownership shall require deed restrictions, covenants, or other legal
instruments that ensure continued use of the land and facilities for their intended uses, and provide for
the continued and effective management, operation, and maintenance of the land and facilities.
D. Failure to maintain Community Green Space and Community Open Space areas or other community
facilities shall be a violation of this Code subject to the remedies and penalties in Chapter 12 (Violations
and Enforcement).
E. If the owner of a Community Green Space and/or Community Open Space fails to maintain it in
reasonable condition, and in accordance with approved plans, and fails to correct deficiencies cited by
the City, the City shall have the authority to correct the deficiencies per at the owners expense. ).
7.5: SUBDIVISION AND SITE PLAN STANDARDS
7.5.1 GENERAL PROVISIONS
The provisions of this Section shall apply to any and all subdivision of land, or site plan within the municipal
boundaries of the City, unless expressly and specifically exempted or provided otherwise in this Code. No
development shall be undertaken without prior approval or authorization pursuant to the terms of this Code.
All development shall comply with the applicable terms, conditions, requirements, standards and procedures
established in this Section and the Code. The submittal of an application for approval pursuant to the
provisions of these Subdivision Regulations constitutes consent to, and agreement to comply with , all of its
applicable provisions.
This Section establishes procedural and substantive rules for obtaining the necessary approval to develop
land and construct buildings and structures. Development applications will be reviewed for compliance with
the City’s Comprehensive Plan, Civic Master Plan, Beaufort Preservation Manual, and this Code.
Scheduling of the review of development applications before Staff, TRC, the Planning Commission or City
Council is at the discretion of the City. Any change to a development application by an Applicant after formal
submittal of that application to the City constitutes a decision by the Applicant that may result in the City
deciding to vacate a decision reached during or following a hearing and/or void the pending application. The
City may then reschedule or cancel the review of the development application at its discretion.
Prior to formal submittal of any subdivision application identified in this Section, the Planning Department
will typically provide to an applicant an individualized submittal checklist indicating the documents and
information needed, quantities of those documents to be submitted, and the referral agencies that will be
involved in the review process. The applicants are responsible for being fully familiar with all applicable
provisions of these Subdivision Regulations. Upon determination by staff that a submittal constitutes a
complete development application, the City will forward the packets to each referral agency.
7.5.2 SUBDIVISION TYPES AND PROCESS OUTLINES
Methods of land subdivision. There are two ways to subdivide land based on the magnitude of scale: Minor
Subdivision and Major Subdivision.
A. Minor Subdivisions.
Definition. A Minor Subdivision is a subdivision, or amendment to a subdivision which has been previously
platted, which includes no additional public right-of-way dedication, and includes one or more of the
following:
40
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
1. The boundaries of five or fewer lots are created from one parent tract or lot, cumulatively and not
more than 3 acres;
2. Any lot line adjustment; and
3. A consolidation of multiple lots into one when a new street or street change is not involved.
B. Major Subdivisions.
Definition. A Major Subdivision is a subdivision which includes one or more of the following:
1. Dedication of public right-of-way, public infrastructure or other public tracts, or a private road;
2. The subdivision consists of six or more lots or tracts; and
3. The creation of lots on property which have never previously been platted.
7.5.3 SKETCH PLAN
A. P urpose. The Sketch Plan is a conceptual design of the development submitted with a major subdivision
application, that depicts what the applicant envisions for the overall development, including zoning,
transportation, pedestrian network, parks, tree canopy, open space, and other amenities. The purpose is
to allow the Applicant, the Planning Commission, and the community the opportunity to discuss the
conceptual subdivision before it goes through the major subdivision platting process.
B. Requirements. A Sketch Plan shall be submitted and provided to staff in advance of any public and/or
community meeting for all major subdivisions. Major proposed changes to any approved preliminary
plat(s) may require a new Sketch Plan approval if the Code Administrator determines the changes are
significantly different from the Sketch Plan discussed at the public meeting.
The Sketch Plan shall consist of the following elements:
1. Road plan: The applicant shall provide a preliminary traffic plan that addresses the following
elements:
a. The proposed street network and connectivity to the existing road network, including all
proposed access points.
b. The location and layout of all arterial and collector roads within the development.
c. A current preliminary traffic impact study prepared by a licensed traffic engineer which
evaluates proposed access points, the existing street system, and any need for any road
improvements (including off-site improvements) created by the proposed development.
2. Open space plan: The applicant shall provide a preliminary open space plan that depicts compliance
with Section 7.4 of this code, with the following elements:
a. Proposed open space distribution and location, including percentage of open space.
b. Compliance with Section 7.4.2, Community Green Space and Community Open Space
Requirement.
c. Required buffer areas as per Section 5.5.1.
d. Wetland areas and setbacks as determined by SCDES-BCM, if applicable.
e. Proposed park locations, acreage, and types of parks as per Section 7.4.
3. Pedestrian network:
a. Location of all trails within development, and connection to existing trail network.
b. Connectivity of sidewalks to the existing pedestrian system, including any off -site sidewalk
improvements. This includes planning for a one-quarter mile pedestrian shed.
c. Depiction of any bike lanes or any other multi-modal features.
41
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
4. Zoning/Design:
a. The location of zoning boundaries shall be provided with the application and depicted on the
Sketch Plan.
b. The plan should show how the development is harmonious with the surrounding area, and
within the property itself.
c. Conceptual building design and massing.
5. Overall utility plan:
a. A letter from the appropriate utility, confirming the existing capacity of the surrounding
utility system, and the future capacity of the utility system for the proposal. Utility plans for
the interior of the development (such as water and sewer service lines) are not required as
part of this process.
b. Proposed connections to the existing utility system.
C. Sketch Plan application submittal. The applicant shall submit a complete Sketch Plan application package
to the City. The application package shall include the following items:
1. Development application form and fee.
2. Title commitment. The title commitment must be dated no more than 9 0 days from the date of
Sketch Plan application submittal.
3. Title of project.
4. North arrow, scale (not greater than one inch equals 200 feet), and date of preparation.
5. Vicinity map.
6. Legal description.
7. Acreage of property; acreage in each zoning district; acreage in parks; and acreage in open space.
8. USGS topographic contours.
9. Location and approximate acreage of proposed land uses.
10. Existing easements and rights-of-way on or adjacent to the property.
11. Existing streets on or adjacent to the property (show and label street name s).
12. Note or table indicating how public dedication requirements will be met.
13. Table providing the following information for each proposed land use area: total acreage; proposed
density; and proposed number of dwelling units and/or commercial buildings.
14. Location and acreage of proposed open space and parks as per Section 7.4., trails, regional trail
connections, playgrounds, and schools or other public uses.
15. Proposed street system depicting the location and layout of all arterial and collector roads within
the development.
16. A preliminary traffic study prepared by a licensed traffic engineer which evaluates proposed access
points, the existing street system, and any need for any road improvements (including off -site
improvements) created by the proposed development.
17. Floodplain boundary with a note regarding the source of information (if a floodplain does not exist
on the property, this must be stated).
18. Zoning on adjoining properties.
42
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
19. A letter from the appropriate utility, confirming the existing capacity of the surrounding utility
system, and the future capacity of the utility system for the proposal. Utility Plans for the interior
of the development (such as water and sewer service lines) are not required as part of this process.
20. Proposed connections to the existing utility system.
21. The location of any proposed or required lift stations.
22. Design rationale — description of how the development is integrated with surrounding area, how it
responds to site features/constraints and how it is consistent with this Code.
23. General description of plan for drainage and storm water management, including any regional
drainage solutions.
24. Description of how the proposed development complies with the City ’s Comprehensive Plan.
25. Design: (i) Concept of lot impact study regarding structure location and massing design on typical
lots and (ii) Concept design representations of structures.
D. Application certification of completion. Within 30 days, staff shall either certify the application is
complete and in compliance with all submittal requirements or reject it as incomplete and notify the
applicant of any deficiencies. Applicant shall then correct any deficiencies in the application package and
re-submit the application to the City.
E. Sketch Plan Process.
1. Planning Commission Meeting. The Planning Commission shall hold a public meeting to review and
provide comments on the Sketch Plan.
2. Notice to neighboring property owners. The City shall send advance notice of the Planning
Commission meeting by regular mail to neighboring property owners within 500 feet of the
property per this Code.
F. Sketch Plan review criteria. The Planning Commission shall use the following criteria in addition to other
applicable provisions of this Code to evaluate the applicant's application:
1. The land use mix within the project conforms to Beaufort's Zoning District Map and Comprehensive
Plan Preferred Land Use Map and furthers the goals and policies of the Comprehensive Plan.
2. The Sketch Plan represents a functional system of land use and is consistent with the rationale and
criteria set forth in this Chapter, the City’s Comprehensive Plan, and the Civic Master Plan as
amended.
3. The preliminary traffic, open space, park, utility, and pedestrian design is adequate and functional
given the existing and planned capacities of each system, and meets the standards found in this
Code.
4. The conceptual design and massing proposed is consistent with the requirements of the
Development Code.
G. Timeframe related to approval of Sketch Plan. After a period of 12 months has passed without submittal
of a Preliminary Plat application, the Administrator may require an applicant to submit a new Sketch Plan
application for Planning Commission review.
H. Minor amendments. A minor amendment to the Sketch Plan may be approved administratively if it:
1. Does not change any land use, or location of any land use.
2. Does not change the number of lots or density by more than ten percent.
43
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
3. Does not contain significant changes in arterial or collector street alignment and/or access points,
or other major public elements such as drainage improvements, utility lines or facilities.
4. Does not change any measurable standard (other than above), such as open space or park area, by
more than ten percent.
7.5.4 PRELIMINARY PLAT
A. Purpose. The purpose of the preliminary plat is to provide the City with an overall plat and the associated
preliminary engineering for the proposed development.
B. Application process.
1. Pre-application conference. A pre-application conference with the City/TRC is required before the
applicant may submit a preliminary plat application. Topics to be discussed will include:
a. The provisions of this Code and the applicable requirements;
b. The application and review process;
c. Submittal requirements; and
d. Changes or modifications based on direction from the Planning Commission at Sketch Plan
approval.
2. Application submittal. Following review of the Sketch Plan, the applicant may submit the complete
preliminary plat application to the City. The preliminary plat application package shall be formatted
and packaged per the application submittal checklist provided by the City and include the following
items in both printed and electronic formats:
a. Development application form;
b. Application fee;
c. Title commitment. The title commitment must be current and dated no more than 120 days
from the date of preliminary plat application submittal; and
d. The preliminary plat that shall provide the following information:
i. Title of project.
ii. North arrow, scale (not greater than one inch equals 100 feet) and date of preparation.
iii. Vicinity map.
iv. Names and addresses of owners, applicant, engineers, and surveyors.
v. Legal description.
vi. Total acreage of property.
vii. Existing contours at two-foot intervals (based on USGS datum).
viii. Name and location of abutting subdivisions or owners of abutting property (if land is not
platted).
ix. Lots, blocks, and street layout (with cross-sections), dimensions and square footage for
each lot. Dimensions and square footages may be rounded to the nearest whole
number.
x. Consecutive numbering of all lots and blocks.
xi. Existing and proposed easements (including rights-of-way) on and adjacent to the
property.
xii. Existing and proposed zoning on and adjacent to property.
xiii. Approximate location and size of existing sewer lines, water lines and fire hydrants.
Approximate location of proposed sewer lines, water lines, and fire hydrants with a
letter from BJWSA and the Fire Marshall.
44
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
xiv. Location by field survey or aerial photography of existing and proposed water courses
and bodies of water such as irrigation ditches and lakes. Water courses shall include
direction of flow.
xv. Tree Survey with Existing Tree Canopy Survey.
xvi. Floodplain boundary with a note regarding source of information (if a floodplain does
not exist on the property, state this on the plan).
xvii. The boundaries of proposed phases of the subdivision if the final plat is intended to be
submitted in multiple phases.
xviii. General location of existing surface improvements such as buildings, fences, or other
structures which will remain on the property as part of the subdivision.
xix. Location and acreage of proposed parks, trails, playgrounds, schools or other public
uses.
xx. Location, function, ownership and manner of maintenance of any private open space.
xxi. Land use table including land uses, approximate acreage of each land use type,
percentage of each land use type density (net and gross) and how public dedication
requirement will be met.
xxii. Total number of lots.
xxiii. Number of each type of dwelling unit proposed.
xxiv. An AutoCad drawing file of the Preliminary Plat in a format specified by the City
Engineer or Codes Administrator.
xxv. Surveyor's certificate.
xxvi. Traffic impact analysis (if applicable) as per the requirements found in
this Code.
3. Drawing standards. The preliminary plat drawing shall comply with the following standards:
a. The preliminary plat shall be prepared by or under the direct supervision of a registered land
surveyor, architect and/or engineer, shall be signed and stamped by said surveyor, architect
and/or engineer, and shall meet applicable State of South Carolina requirements.
b. Except for parcels separated by easements (including public rights -of-way), public tracts, or
railroads, parcels not contiguous with each other shall not be included in one plat, nor shall
more than one plat be made on the same sheet. Contiguous parcels owned by different parties
may be included on one plat, provided that all owners join in the dedication and
acknowledgment.
c. Lengths on the preliminary plat boundary shall be shown to the nearest hundredth of a foot and
bearings shall be shown in degrees, minutes, and seconds.
d. Bearings, distances and curve data of all perimeter boundary lines shall be indicated outside the
boundary line, not inside, with the lot dimensions.
e. Names and signatures of all owners of equitable interest in the property shall be on the
preliminary plat and shall be made in black drawing ink.
4. Explanation of how the plat is consistent with this Code, the Comprehensive Plan, the Civic
Master Plan, and the Sketch Plan.
5. Preliminary grading and drainage plan and report. This plan and report must be certified by a
South Carolina registered professional engineer or Land Surveyor and include approximate
earthwork quantities (how earthwork on the site is "balanced"), storm drainage concepts such as
locations of pipe and other conveyance facilities, locations for on-site detention or downstream
structural improvements, and soil erosion and sedimentation control plans and specifications. It
must also discuss the impacts on and to any existing floodways and/or floodplains both on and
adjacent to the site as well as any FEMA applications or approvals that may be required.
45
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
6. Preliminary water and sewer plan and study. This plan shall be prepared by a registered
professional engineer. It is necessary that the engineer consult with the appropriate utility service
providers regarding the design of all utilities through the subdivision.
7. Preliminary landscape and open space plan. The landscape plan must address the treatment of all
exterior spaces. Landscape plans are to be designed to meet the requirements of this Code and
show approximate locations of trees, shrubs, groundcovers, turf, buffering, fences, walls and other
site amenities that will be included in the plan.
8. Traffic study. A TIA with requirements consistent with Section 7.3.2. This study must be prepared
by a professional traffic engineer and identify the projected impacts to the local and regional traffic
system. The direct roadway impacts and proposed share in the cost of regional improvements and
intersections must be identified for the project.
9. Archaeological Impact Assessment. An applicant may be required to provide the City, pursuant to
Section 8.4, with CHS records listing historically or archaeologically significant findings on the
property being subdivided at the applicant’s expense.
10. General ecological resource survey. Prepared by a qualified biologist, geologist, ecologist, or
similar qualified professional, a survey identifying the potential/absence/habitat of a threatened or
endangered species and wetlands or other ecologically sensitive area. Said survey shall make
practical recommendations regarding treatment or mitigation of the findings.
11. Conceptual Design. Applicant should provide conceptual design and massing examples (i.e. typical
building elevations, but not required for each individual lot), consistent with the requirements of
this Code.
C. Planning Commission Hearing. The Planning Commission shall hold a public hearing to approve, approve
with conditions, or deny the Preliminary Plat.
1. Notice to neighboring property owners. The City shall send advance notice of the Planning
Commission hearing by regular mail to neighboring property owners within 500 feet of the
property per this Code.
2. Approval. The Planning Commission shall review and act on the Preliminary Plat. The Planning
Commission shall approve, approve with conditions, or deny the Preliminary Plat based on the
review criteria below.
D. Review criteria. In addition to all provisions of this Code, the Planning Commission shall use the
following criteria to evaluate the Preliminary Plat:
1. The Preliminary Plat represents a functional system of land use and is consistent with the
rationale and criteria set forth in this Code.
2. The land use mix within the project conforms to the City’s Development Code and complies with
the Comprehensive Plan and Civic Master Plan.
3. The utility and transportation design are adequate, given existing and planned capacities of those
systems.
4. Lot layout, including structure, location, and design of each lot.
46
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
E. Phasing. The Preliminary Plat shall designate the boundaries of phases for which separate Final Plats will
be presented for approval. Each phase, either alone or in conjunction with previously approved and
recorded phases, must meet all of the requirements of this Code.
F. Early grading. After approval of a Preliminary Plat, Applicant may proceed with preliminary grading of
the project area if a construction plan set for grading and drainage is approved and a memorandum
authorizing grading work is issued by the City Engineer or Codes Administrator. Early grading and storage
of construction related equipment is at the risk of the Applicant and no Final Plat approval by the
Planning Commission is expressed or implied by any authorization of early grading.
G. Timeframe related to approval of Preliminary Plat. A Preliminary Plat approval is in full force and effect
for a period of two years from the date of approval. Approval will automatically expire at the end of two
years unless an applicant formally requests an 18 month extension from the Planning Commission prior
to termination or submits a completed Final Plat application for all or a portion of the property.
7.5.5 FINAL PLAT
A. P urpose. The purpose of the Final Plat is to complete the subdivision of land consistent with the
technical standards of the City.
B. A pplication process.
1. Application submittal. The Final Plat application shall substantially conform to the Preliminary Plat
as approved at the public hearing and shall meet all conditions of approval. The applicant shall
submit the completed Final Plat application package to the City. The Final Plat application shall be
formatted and packaged per the application submittal checklist provided by the City and include:
a. Development application form.
b. Application fee.
c. Title commitment. An updated title commitment, dated no more than 120 days from the date
of Final Plat application submittal.
2. Standards. The Final Plat drawing shall comply with the following standards:
a. All requirements of Section 7.5.4.
b. The plat shall be prepared by or under the direct supervision of a registered land surveyor,
shall be signed and stamped by said surveyor, and shall meet applicable State of South
Carolina requirements.
c. Existing and proposed easements (including rights-of-way) in and adjacent to property (labeled
and dimensioned).
d. Existing and proposed street names for all streets on and adjacent to the property.
e. Final Traffic Impact Analysis (if applicable) as per the requirements found in this Code.
f. If applicable, prior to commencement of construction, a State Highway utility permit from
SCDOT.
g. If applicable, prior to commencement of construction, a State Highway access permit from
SCDOT.
47
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
h. If applicable, prior to commencement of construction, a construction dewatering permit from
DHEC
i. If applicable, prior to commencement of construction, a 404 Permit from the Army Corps of
Engineers.
j. Prior to commencement of construction, acceptable collateral in the amount and form
stipulated in Section 7.1.5.
3. Original plats. The applicant shall submit to the City five original, signed copies of the Final Plat,
ready to record, and final executed copies of all agreements.
4. Complete engineering plans and specifications. As a condition of Final Plat approval the applicant
shall prepare and submit the following:
a. Construction plans and profiles. The plans and profiles shall be prepared by a registered
professional engineer licensed in the State of South Carolina. Plans shall be 24 inches high by
36 inches wide and provide the following information:
b. The horizontal to vertical scales shall be chosen to best depict the aspects of the design.
c. Minimum horizontal scale: One inch equals 100 feet.
d. Minimum vertical scale: One inch equals ten feet.
e. The typical road geometric and structural cross-section is to be shown on each plan sheet.
f. The plan must show right-of-way lines and widths, road names, lot lines, tangent lengths and
bearings, curve radii, delta angles, curve lengths, chord lengths and bearings, stationing at all
beginning of curves and end of curves, intersections, structures, angles, curb lines, cross pans,
traffic control devices (islands, striping, signs, etc.), drive cuts, curb returns and radii, and all
other features to enable construction in accordance with approved standards and standard
engineering practice. Stationing may be centerline if approved by the City Engineer or Codes
Administrator. Construction plans shall include water lines and appurtenances, sewer lines and
appurtenances, and storm water lines and appurtenances and any other wet utilities .
g. The profiles shall include existing and proposed grade at curb and gutter or centerline of street
elevation at point of intersection of vertical curves, intersections, grade breaks, point of curb
return (PCR), point of reverse curve (PRC), and other critical points, structures, and all other
features.
h. Signature blocks for all utility providers unless otherwise provided in agreement form.
i. Structure details. Sufficient data shall be given regarding construction of major structures and
road appurtenances such as bridges, culverts, gutters, drives, walks, cross pans, etc; detail shall
include orientation line and grade, cross-sections, dimensions, reinforcement schedules,
materials, quality specification, etc., or as the City Engineer may approve.
j. Final Water Report. A final water report including hydraulic analysis and pipe sizing
calculations. Note, this report can be verified by BJWSA and does not need to be submitted to
the City.
k. Final Sanitary Sewer Report. A sanitary sewer report including hydraulic analysis and pipe
sizing calculations. Note, this report can be verified by BJWSA and does not need to be
submitted to the City.
l. Sewage collection and water supply distribution plans, profiles and specifications. The plans,
profiles and specifications shall be prepared by a registered professional engineer and shall be
accompanied by written approvals from BJWSA.
48
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
m. Final drainage plans and reports. Based upon the approved preliminary drainage plan, a final
report is to be submitted in accordance with SOLOCO Drainage and Design Criteria, as
amended or as the City Engineer may approve. The plan and report must provide:
n. Erosion control plans, when required.
o. Sizing of all pipes, inlets, conveyance ways, and other appurtenances.
p. Final grading plan. The final grading plan shall be 24 inches high by 36 inches wide and
illustrate existing and proposed contours and lot and block grading details.
q. Soils report. The soils report shall detail pavement design and construction requirements a nd
s
hall be submitted after overlot grading is complete.
r. Final landscape and open space plan. The landscape plan must address the treatment of all
exterior spaces. Landscape plans are to be designed to meet the requirements of this Code a
nd
s
how trees, shrubs, groundcovers, turf, buffering, fences, walls and other site amenities that
will be included in the plan. All plant materials must be adapted to the physical limitations of
the local climate and specific conditions of the landscape plan. All plant materials must meet
specifications of the American Association of Nurseryman for number one grade. All street
trees must be selected from the City of Beaufort recommended tree list.
s. Landscape Plan drawn to scale (not greater than one inch equals 50 feet) on 24 by 36 -inc
h
s
heets which includes:
i. Project name.
ii. Scale, north arrow and date of preparation.
iii. Existing and proposed streets and street names.
iv. Lot lines, easements and public rights-of-way as shown on the subdivision plat, including
gross and net area of all parcels.
v. Location of proposed building footprints and parking areas.
vi. Location of storage, loading, and service areas.
vii. Existing and proposed two-foot contours (based on USGS datum).
viii. Natural features, wetlands, wildlife corridors, floodplains, streams, ditches , and other
waterways.
ix. The location of existing and proposed utilities. Utility lines can be 'ghosted' in on the
landscape plan to vary the line types for cleaner drawings.
x. All existing trees within the proposed site and adjacent to the site must be accuratel
y
i
dentified on the plan. Existing trees must be labeled as to their size, species and if the y
a
re intended to remain, be removed or transplanted. All replacement mitigation trees
will need to be shown separately on the plan. Tree protection standards for existing
trees to remain shall be included on the plan.
xi. The extent and location of proposed trees, shrubs and perennials and quantities of eac
h
s
pecies. Plant materials are to be drawn at two-thirds of their mature size.
xii. Landscape schedule including the represented plant symbol, Latin name, commo n
na
me, planting size and number of individual plants. All plant materials are to meet the
minimum size requirements as provided in this Code.
49
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
xiii. Proposed treatment of all ground surfaces must be clearly indicated, including turf,
paving, mulch, native grass, seeded grass, etc. Grass areas are to be specified as seed or
sod, and a seed mix/rate specified.
xiv. Sight distance triangles must be shown at street intersections pursuant to this Code.
xv. Project specific landscape notes and details to ensure the proper planting,
establishment and survival of plant materials. Additional notes detailing the warranty
for plant materials and continued maintenance shall be included.
xvi. Open space and pedestrian circulation system.
xvii. Proposed grading of the project site, including drainage swales, detention basins,
retaining walls and any off-site infrastructure improvements.
xviii. Notes for conservation and retention of topsoil and landscape soil preparation.
xix. Restoration, revegetation or enhancement of disturbed natural areas or open space
feature.
xx. Park structures, signage, play equipment, and other landscape or park amenities and
appurtenances.
xxi. A PDF file and an AutoCad drawing file of the Final Plat in an electronic format specified
by the City Engineer.
xxii. Design standards as required in Site Plan section 7.5.7.B.4.
5. Post approval actions. Prior to issuance of a building or grading permit, the applicant shall submit
the following documentation to the City:
a. List of contractors. List of all contractors that will be performing the improvements.
b. Proof of insurance/business license. Proof of workman's comprehensive insurance and liability
insurance for each contractor and business license.
c. Open space deed restriction. Areas designated as open space shall be protected by a deed
restriction or other appropriate method to ensure that they cannot be subdivided or
developed in the future and will remain as open space until the use is modified by the City.
d. Construction traffic control plan. Applicant will develop a plan for City Engineer, Codes
Administrator or appointee, review that addresses construction traffic, construction water,
temporary road closures, street repairs, dust, noise and other construction- related concerns.
e. Other certificates, affidavits, enforcements or deductions as required by the City .
C. Approval. The Administrator shall review and act on the Final Plat. The Administrator may choose to
approve, approve with conditions, or deny the Final Plat based on the criteria below.
1. Final Plat review criteria. In addition to all provisions of this Code, the Administrator evaluates the
applicant's Final Plat application based on whether the Final Plat is in substantial conformance with
the approved Preliminary Plat. For the purposes of this Code, "substantial conformance" includes
design adjustments made to meet any conditions of Preliminary Plat approval, and is determined
as follows:
:
50
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
a. Does not change any land use;
b. Does not contain changes which would render the final plat in nonconformance with
requirements of this Code;
c. Does not contain significant changes in street alignment and/or access points, or other public
elements such as drainage improvements, utility lines or facilities ; and
d. Does not increase density.
D. Timeframe related to approval of Final Plat. A Final Plat is in full force and effect for a period of two
years from the date of recordation unless a longer timeframe is specifically allowed by the City in an
approved Development Agreement or unless public improvements are completed and accepted on all or
a portion of the development. Applicants may formally request one 18 month extension from the
Administrator prior to termination of Final Plat approval. Prior to the expiration of the original two year
timeframe or the extension timeframe, an applicant may formally request an additional extension if
substantial progress has been made on installation of public improvements.
7.5.6 MINOR SUBDIVISION PLAT
A. P urpose.
1. The purpose of the Minor Subdivision Plat is a subdivision or amendment to a subdivision which
has been previously platted, which includes no additional public right-of-way dedication, and
includes one or more of the following:
a. The boundaries of five or fewer lots are created from one parent tract or lot, cumulatively and
not more than 3 acres(e.g., any portion of a tract that is subdivided counts toward the five
total, and does not itself become a new parent tract to subdivide an additional five lots from);
b. Any lot line adjustment, consolidation of multiple lots into one ; and
c. A consolidation of multiple lots into one when a new street or street change is not involved.
B. A pplication submittal. The applicant shall submit the complete Minor Subdivision plat application
package to the City. The application shall be formatted and packaged per the application submittal
checklist provided by the City and include:
1. Development application form.
2. Application fee.
3. Title commitment. A current title commitment, dated no more than 30 days from the date of minor
subdivision plat application submittal
C. Plat standards. The plat drawing shall comply with the following standards:
1. The plat shall be prepared by or under the direct supervision of a registered land surveyor and
meet applicable State of South Carolina requirements.
2. Except for parcels separated by public rights-of-way, public tracts, or railroads, parcels not
contiguous shall not be included in one plat, nor shall more than one plat be made on the same
sheet. Contiguous parcels owned by different parties may be included on one plat, provided that all
owners join in the dedication and acknowledgment.
51
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
3. Lengths shall be shown to the nearest hundredth of a foot and bearings shall be shown in degrees,
minutes and seconds.
4. Bearings, distances and curve data of all perimeter boundary lines shall be indicated outside the
boundary line, not inside, with the lot dimensions.
5. All signatures shall be made in black drawing ink.
6. Title of project.
7. North arrow, scale (not greater than one inch equals 100 feet) and date of preparation.
8. Vicinity map.
9. Legal description.
10. Basis for establishing bearing.
11. Names and addresses of owners, applicant, designers, engineers, and surveyors.
12. Total acreage of subdivision.
13. Bearings, distances, chords, radii, central angles, and tangent lines for the perimeter and all lots,
blocks, rights-of-way, and easements.
14. Lot and block numbers, numbered in consecutive order, and square footage or acreage to two
decimal places of each lot or tract.
15. Parcels excepted from inclusion noted as "not included in this subdivision" and the boundary
completely indicated by bearings and distances.
16. Existing rights-of-way in and adjacent to subject property (labeled and dimensioned).
17. Existing and proposed street names for all streets on and adjacent to the property.
18. Existing easements and their type in and adjacent to subject property (labeled and dimensioned).
19. Location and description of monuments;
20. Floodplain boundary with a note regarding source of information (if a floodplain does not exist
on the property, please state this on the plat).
21. Blocks for signatures of owner, surveyor, utility providers, and City approval, as applicable.
D. Recordation of Minor Subdivision Plat. Five signed copies of the Minor Subdivision plat shall be
delivered to the City. The applicant will be responsible for recording the minor subdivision plat with
Beaufort County.
7.5.7 SITE PLAN
A. Purpose. The Site Plan is a prerequisite to a building permit for all multi-family (excluding duplexes),
commercial, and industrial developments. The site plan shows how the lot will be developed so that the
City can ensure that the site design will be in compliance with the Development Code, Comprehensive
Plan, and Civic Master Plan.
B. Application. A Site Plan Application shall include the following:
1. Land use application form.
52
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
2. Application fee and fee agreement.
3. Site Plan plat — The Site Plan shall be a minimum of 18 inches by 24 inches and shall provide the
following information:
a. Title of project.
b. North arrow, scale (no greater than one inch equals 50 feet) and date of preparation.
c. Vicinity map.
d. Address of project.
e. Legal description of property.
f. Name, address, and phone number of property owner.
g. Name, address, and phone number of person or firm responsible for plan.
h. Lot size (square footage).
i. Bearings and distances of all lot lines.
j. Existing and proposed easements and rights-of-way.
k. Existing and proposed paved areas and sidewalks on the site and in the adjacent rights -of-way, all
dimensioned, showing how pedestrians will have access to the site and buildings.
l. Gathering areas for people.
m. Existing and proposed curb cuts on the site and in the adjacent rights -of-way (on both sides of
perimeter streets), all dimensioned.
n. Existing and proposed two-foot contours.
o. Existing waterways on or adjacent to the site.
p. Finished floor elevations for all structures.
q. Footprint (including roof overhangs and eaves, decks, balconies, and outside stairs and landings)
of all proposed structures and their use with their dimensions and locations noted with respect
to the property lines.
r. Existing structures and their use.
s. Square footage of the proposed building(s) and the footprint of the proposed building(s).
t. Proposed structure height.
u. For multi-family residential, the number of residential units and bedrooms per unit.
v. Location of proposed signs and lighting.
w. Sp
ecifications for the signs and lights, including type, height and general conformance to the
Code. For commercial and industrial uses, a photometric plan prepared by a qualified electrical
or lighting engineer shall be submitted that depicts all lighting fixtures and the light spread (i
n
f
ootcandles) of these fixtures across the site to all property boundaries.
x. Proposed traffic controls and striping for parking areas (all lanes, driveways, and parking spaces
must be dimensioned).
y. Trash disposal areas and enclosures including specifications for enclosures.
z. Location and size of existing and proposed water and sewer service connections and tap sizes.
53
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
aa. Location and size of water and sewer lines to which the service connections will be or are made.
bb. Location and size of water meter(s).
cc. Location and size of backflow-prevention devices.
dd. Indication of how and where perimeter drain will drain (if one exists).
ee. Location of existing electrical lines and poles on or adjacent to the site.
ff. Location of proposed electrical service connection and meter location.
gg. Location of electric transformer.
hh. Location of all fire hydrants. If none exist on site, note distance and direction of the closest
hydrant adjacent to the site within 500 feet.
ii. Location of detention/retention areas and storm sewer infrastructure with the required drainage
easements.
jj. The distance from the proposed building(s) or structure(s) to adjacent lot lines, easements, and
adjacent structures.
kk. A land use chart (table).
ll. Certificate blocks for signatures of owner, surveyor, utility providers, and City approval, as
applicable.
4. Design standards — Demonstrate in written or graphic form how the proposed structure(s) is
consistent with the design requirements of this Code. Provide elevations of proposed
structures/graphic visual aids. Provide complete building elevations, drawn to scale, with
illustrations of all colors and identifying major materials and cut sheets to be used in the
structure(s). In addition, Staff may require building floor plans, sectional drawings, perspective
drawings, models, and/or computer visualizations when the impacts of a proposal warrant such
information.
5. Certified drainage report — A certified drainage report, including an erosion control study and
plan, as applicable, must be reviewed and approved by the appropriate sanitation district (if
applicable) prior to submittal of the report to the City as part of the site plan application.
6. Final landscape and open space plan — Provide an existing and proposed landscape plan with tree
protection zones and a tree survey, and open space plan consistent with Chapters 5 and 7 of this
Code.
7. Traffic Impact Analysis — Provide TIA as per requirements of Section 7.3.2.
C. TRC and Staff Review. Staff and TRC shall review the application and prepare comments. Staff and TRC will
review the site plan map to ensure it is consistent with the site plan review criteria. Following the review,
Staff will prepare a written report outlining any changes that the applicant must make before the site plan
can be recommended for public hearing with the Planning Commission . This report will be forwarded to
the applicant and the applicant shall make all necessary changes to the site plan and resubmit a revised
copy to the City..
54
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
D. Planning Commission Hearing.
1. Notice to neighboring property owners. The City shall send advance notice of the Planning
Commission meeting by regular mail to neighboring property owners within 500 feet of the
property per this Code.
2. The Planning Commission shall hold a public hearing on the proposal. The applicant and other
property owners likely to be materially affected by the application shall be given an opportunity to
be heard.
3. At the conclusion of the public hearing, the Planning Commission may approve, deny, or approve
with conditions the application for a Major Development. No Major Development shall be
approved unless the following findings of fact are made:
a. The plan is consistent with the City of Beaufort Comprehensive Plan and Civic Master Plan.
b. The plan complies with all applicable requirements of this Code.
c. There exists adequate infrastructure (transportation and utilities) to support the plan as
proposed.
d. The plan conforms to the character of the neighborhood, considering the location, type and
height of buildings or structures and the type and extent of landscaping on the site.
E. Post approval actions.
1. Building Permit. A building permit shall be issued only if a site plan has been approved. However,
with the approval of the City, an applicant may submit a building permit application concurrent
with the site plan application. Building permits shall not be issued for any development that is not
in conformance with the approved site plan.
2. Phasing and expiration of approval. The site plan shall be effective for a period of three years from
the date of approval, unless stated otherwise in the written site plan approval. Building permits
shall not be issued based on site plans that have an approval date more than three years old. For
multi-phased plans, building permits shall not be issued based on an approval date more than three
years from the date of Phase I approval.
F. Appeals. See Sections 7.6 and 9.17
G. Permit Validity. Upon the approval of a Major Development Design application, the applicant shall have 2
years to obtain a Project Permit. Failure to secure a permit for the permitted work within this time shall
render the compliance void. Any change to the approved plans that has not been authorized by the
Administrator shall invalidate the design approval, and any subsequent building permits.
H. Permit Extension. The Administrator may grant a one year extension of this time period upon submittal by
the applicant of sufficient justification for the extension. Extensions shall be submitted at least 1 month
prior to the expiration date.
I. Amendments to approved Site Plans.
1. Minor variations in the location of structures, improvements, or open space areas caused by
engineering or other unforeseen difficulties may be reviewed and approved by the City Staff. Such
changes shall not exceed ten percent of any measurable standard or modify the use, character, or
density of an approved site plan. All plans so modified shall be revised to show the authorized
changes and shall become a part of the permanent records of the City.
55
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
2. Changes to approved site plans that exceed the ten percent threshold, or other major
modifications (such as changes in building size or footprint, relocation of access points, changes to
required parking, etc.), shall be considered as a new site plan application. Such amendments shall
require Planning Commission review and approval to become effective. A complete site plan
application shall be prepared and submitted in compliance with the requirements set forth in this
Section.
7.6: APPEALS
See Chapter 9.17 for overall specifications regarding appeals.
56
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
Exhibit B (Chapter 9)
57
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9: DEVELOPMENT REVIEW PROCEDURES
9.1: PURPOSE AND GENERAL PROVISIONS
9.1.1 PURPOSE
In order to establish an orderly process to develop land within the jurisdiction of the City of Beaufort, the purpose
of this article is to provide a clear and comprehensible development process that is fair and equitable to all interests,
including the applicants, affected neighbors, city staff and related agencies, and the City Council.
9.1.2 APPLICABILITY
The provisions of this article shall be applicable to all development activity under the jurisdiction of the City of
Beaufort.
9.1.3 CONFORMITY WITH CODE
The Administrator shall not issue a permit or license for any use, building, or purpose that conflicts with any
provision of this Code.
9.1.4 PERMIT/DEVELOPMENT DESIGN REVIEW/HISTORIC REVIEW APPLICATION TYPE TABLE
See following pages.
58
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
APPLICATION TYPE SECTION PROCESS
TYPE
REVIEWING
AGENCY
PUBLIC
NOTIFICATION
(9.1.5)
APPROVING
AGENCY APPROVAL
PERIOD
APPROVAL
EXTENSION
ADMINISTRATIVE PERMITS
Zoning Permit 9.4 Ministerial Admin No Admin 6 months 6 months,
1 time
Building Permit 9.5 Ministerial Admin No Admin 6 months Resubmit
Certificate of Occupancy 9.7 Ministerial Admin No Admin n/a n/a
DEVELOPMENT DESIGN REVIEW
Development Design
Review, Minor Site Plan
9.8.1 Ministerial Admin No Admin 24 months 12 months,
1 time
Development Design
Review, Major Site Plan
9.8.2 Discretionary Admin, TRC Yes PC 24 months 12 months,
1 time
SUBDIVISION REVIEW
Sketch Plan 7.5.3 Discretionary Admin, TRC Yes PC 12 months 12 months,
Preliminary Plat 7.5.4 Discretionary Admin, TRC Yes PC 24 months 12 months,
1 time
Final Plat 7.5.5 Ministerial Admin, TRC No Admin 24 months 12 months,
1 time
HISTORIC PRESERVATION
Beaufort Historic District
- Certificate of
Appropriateness, Minor
9.9 Ministerial Admin Demolition
Only: Yes
Admin 24 months 12 months,
up to 3
times
Beaufort Historic District
- Certificate of
Appropriateness, Major
9.9 Discretionary Admin Demolition &
Design
Exception
only: Yes
HRB 24 months;
no
expiration
12 months,
up to 3
times
59
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
for
demolitions
ADJUSTMENTS
Administrative
Adjustment
9.12 Ministerial Admin No Admin 24 months 12 months,
up to 3
times
Special Exception 9.12 Discretionary Admin Yes ZBOA 24 months 12 months,
up to 3
times
Variance 9.13 Discretionary Admin Yes ZBOA 24 months 12 months,
up to 3
times
Admin-Administrator / PC-Planning Commission / CC-City Council / ZBOA-Zoning Board of Appeals / HRB-Historic District Review Board / TRC-
Technical Review Committee / Court - Circuit Court
Note: Any appeals that are assigned to Court are eligible for pre-litigation mediation pursuant to S.C. Code § 6-29-1155
(Ord. No. O-14-23, 9-26-2023)
60
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.1.5 PUBLIC NOTIFICATION
All public meetings shall be posted and advertised with the media as required by state law. The following
procedures have been established for development applications/petitions that require additional notification of
the public prior to consideration and/or approval.
A. BASIC NOTICE, MINIMUM STANDARDS FOR NOTICE OF ALL MEETINGS AND HEARINGS :
Written public notice of dates, times and places of all City of Beaufort development review public
meetings and hearings shall be provided in accordance with S.C. Code § 30-4-80, any other applicable
provision of State Law, and this Code. This includes, at minimum, posting of a copy of the notice,
including the agenda, in the building where the meeting shall be held, posting of the notice, the
agenda, and the meeting materials packet on the website maintained by the City of Beaufort, and
notifications to persons, organizations and news media requesting such notice as contemplated by S.C.
Code § 30-4-80 (E). While State Law requires a minimum of 24 hours written notice in the absence of a
special notice requirement, City Staff shall provide, at a minimum, seven (7) calendar days of notice.
B. PUBLICATION OF NOTICE OF A HEARING IN A NEWSPAPER:
When required by State Law, a distinctive advertisement (public hearing notice) shall be placed by the
Administrator in a local newspaper of general circulation within the City . This notice shall be published
in accordance with the time limits required by State Law or, if none, not less than 15 calendar days
prior to the meeting. The content of said published notice shall include all content required by State
Law, including without limitation the following:
1. The general location of land that is the subject of the application;
2. The tax map, parcel number, and street address if available;
3. The substance of the application, including the magnitude of proposed development and the
current zone;
4. The time, date, and location of the public hearing;
5. A phone number to contact the City; and
6. A statement that interested parties may appear at the public hearing.
C. NOTICE OF APPLICATION SIGN:
A notice of application sign shall be posted by the Administrator on the subject property in a location
clearly visible from each street adjacent to the property as required by State Law, including without
limitation for all hearings on applications for zoning or rezoning, variances, special exceptions, site
plans, and preliminary plats, as well as demolition and design exceptions. The notice shall be posted no
less than 15 calendar days prior to the hearing at which the application will be reviewed. The sign shall
include the following information:
1. Type of application;
2. The date, time, and place of the public hearing; and
3. A phone number to contact the city.
D. MAILED/EMAILED NOTICE:
Mailed/emailed notice shall be provided as required by State Law, including without limitation mailed
notice to adjoining property owners when required by State Law. Additionally, the City shall provide
mailed/emailed notices upon request as per S.C. Code § 30-4-80 (E) and the Policy and Procedures
61
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
contained on the website operated by the City. For demolition of structures listed on the most recent
“Above-Ground Historic Sites Survey” that are located outside the Historic District, written notice to
members of the Historic District Review Board (HRB), Historic Beaufort Foundation (HBF), and
neighbors within 500 feet of the property will be required at least 15 days before any permit is issued.
9.1.6 DECISION BASED ON PUBLIC HEARING
This section intentionally left blank.
9.1.7 WRITTEN NOTICE OF DECISIONS REQUIRED
Within 10 calendar days after a final decision is made by any reviewing body under the requirements of this Code,
a copy of the written decision shall be sent to the applicant or appellant. A copy of the decision shall be filed in the
office of the Administrator, where it shall be available for public inspection during regular offi ce hours.
9.1.8 TIME LIMITS FOR RESUBMISSION OF APPLICATIONS
In the event that any application required under this Code is denied or disapproved, an application for
substantially the same request shall not be refiled for one year from the advertised public hearing date. Where no
public hearing is required, time shall run from the date of mailing of the notice of denial.
9.1.9 VESTED RIGHTS AND EXPIRATION OF APPROVALS
A. General: Approval of any application pursuant to this Code shall authorize only the particular use, plan,
or other specific activity for which the application was issued, and not any other approval requiring
separate application.
B. Vested Rights for Final Development Plans/Plats: For specific provisions see chart in chapter 9.1.4 and
applicable provisions in chapter 7.
C. Time Limitations For Other Types Of Approval:
1. All permits and approvals not referenced in this section shall expire as shown in Section 9.1.4
(Permit/Development Design Review/Historic Review Application Type Table) without further
action, unless the holder of the permit or approval either submits a complete application for the
appropriate subsequent permit, approval, or extension, or if no subsequent permit, approval, or
extension is required, completes the work described in the permit or approval within the
timeframes established.
2. Upon written request, an extension of an approval may be granted by the decision- making body
for good cause for a period not to exceed that shown in Section 9.1. 4 (Permit/Development
Design Review/Historic Review Process Type Table). No written request for an extension shall be
considered unless submitted to the Administrator no later than one month prior to expiration.
Failure to submit an application for an extension within the time limits established by this section
shall result in the approval's expiration.
62
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.2: APPLICATION PROCEDURES
9.2.1 PRE-APPLICATION CONFERENCE
A. Mandatory Pre-application Conference: A pre-application conference with the Administrator shall be
required prior to filing an application for the following approvals:
1. Subdivision review involving the creation of new streets.
2. New construction, except for detached single-family homes not part of a new subdivision.
3. Text and Map amendment (Rezoning).
4. Site plan.
5. Text amendment.
The Administrator shall have the authority to waive any mandatory pre -application conference where
such conference is deemed unnecessary by the Administrator.
B. Optional Pre-application Conference: Prior to the submission of any application required by this Code,
a potential applicant may request an optional pre-application conference to discuss procedures,
standards, or regulations required by this Code. Upon receipt of such request, the Administra tor shall
afford an opportunity for such a pre-application conference at the earliest reasonable time.
9.2.2 APPLICATION FORMS AND FEES
The following regulations shall apply to all applications.
A. Forms: Applications required under this Code shall be submitted on forms and in such numbers as
required by the City.
B. Fees:
1. Filing fees shall be established from time to time by resolution of the City Council to defray the
actual cost of processing the application.
2. All required fees shall be made payable to "The City of Beaufort."
3. An applicant who has paid an appropriate fee pursuant to the submission of an application, but
who chooses to withdraw such application prior to any review or action taken, may request in
writing a refund of 75% of the total amount paid.
9.2.3 APPLICATION DEADLINE
This section intentionally left blank.
9.2.4 COMPLETE APPLICATION REQUIRED
A. The Administrator shall have 14 business days to review the application and shall determine whether
the application is complete and ready to proceed.
B. If the application is not complete, the Administrator shall inform the applicant in writing within the 14-
day period, specifying the ways in which the application is incomplete, and the applicant shall have 60
63
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
days during which to provide the requested materials and complete the application. Any application for
which additional materials have not been provided during this 60-day period shall be considered null
and void. This application period may be extended by the Administrator upon mutual agreement to
provide the required materials at some date certain in the future.
9.2.5 CONCURRENT PROCESSING
Any applicant may submit an application for any sequential approvals (such as a zoning map amendment and site
plan approval) required under this Code and request that such sequential approvals be processed concurrently;
however, such concurrent processing shall proceed at the applicant's own risk and shall have no implication in
regard to the approval of any of the various approvals requested.
64
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.3: APPLICATION REQUIREMENTS
The following general standards for various applications are intended to require only that data/information that is necessary to render an informed decision by
the reviewing agency. A narrative explaining the scope of the project will be required for all a pplications. The "Application Submittal Requirements" list, on file
with the Administrator, is intended to provide further guidance to applicants as to the necessary level of detail for each application component listed below.
APPLICATION TYPE CODE
SECTION
PRE-
APPLICATION
CONFERENCE
(7.5.4.B)
SKETCH PLAN
(7.5.3)
SITE PLAN –
INCL. BUILDING
ELEVATIONS
(7.5.7)
FINAL PLAT
(7.5.5)
TRAFFIC
IMPACT
ANALYSIS
(7.3.2)
ARCHEOLOG.
IMPACT
ASSESSMENT (8.4)
ADMINISTRATIVE PERMITS
Zoning Permit 9.4
See Administrator
Building Permit 9.5
Certificate of
Compliance 9.6
Certificate of Occupancy 9.7
DEVELOPMENT DESIGN REVIEWS
Minor Site Plan 9.8.1 See Code Sec. 7.5: Subdivision and Site Plan Standards Major Site Plan 9.8.2
SUBDIVISION REVIEWS
Subdivision, Major
(Sketch Plan)
9.9 See Code Sec. 7.5: Subdivision and Site Plan Standards Subdivision, Major
(Preliminary Plat)
Final Subdivision Plat
HISTORIC PRESERVATION
Beaufort Historic
District - Certificate of
Appropriateness (CoA),
Minor
9.10 □ □ □ N/A N/A N/A
CoA, Major 9.10 ■ ■ ■ N/A □ □
65
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
PERMIT TYPE CODE
SECTION
PRE-
APPLICATION
CONFERENCE
(7.5.4.B.4)
SKETCH PLAN
(7.5.3)
SITE PLAN –
INCL. BUILDING
ELEVATIONS
(7.5.7)
FINAL PLAT
(7.5.5)
TRAFFIC
IMPACT
ANALYSIS
(7.3.2)
ARCHEOLOG.
IMPACT
ASSESSMENT
(8.4)
ADJUSTMENTS
Administrative Adjustment 9.12 See Administrator
ZBOA Special Exception 9.13 ■ ■ ■ N/A □ N/A
ZBOA Variance 9.14 ■ ■ ■ N/A □ N/A
AMENDMENTS
Text & Map Amendments 9.16 ■ ■ ■ N/A N/A N/A
■ = Required Compliance □ = On an “as needed” basis as determined by the Administrator
66
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.4: ZONING PERMIT
9.4.1 APPLICABILITY
Only Required Permit: A zoning permit certifying compliance with this Code shall be the only type of approval
required for the following activities:
A. Home Occupations as regulated by Section 3.3.2 (Home Occupations — Major and Minor).
B. Temporary uses that do not materially affect the area's natural environment, parking requirements,
transportation patterns, public health, or economic values. (See Section 3.12 Temporary Uses)
C. Conditional uses not requiring a building permit.
D. Special events.
E. Changes of use, and any uses permitted with additional standards per Article 3 (Land Use Provisions).
F. Removal of trees as regulated in Section 5.4 (Tree Removal).
67
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.4.2 PROCESS AND APPROVAL
A. Process Type: Ministerial.
B. Pre-Application Procedure: None.
C. Required Application Information: See Administrator.
D. Public Notification: None.
E. Determination of Compliance: Once an application is deemed complete by the Administrator, the
Administrator shall review the application and approve or deny it based on compliance with the
standards contained in this Code.
F. Permit Validity: Upon the approval of the zoning permit, the applicant shall have 6 months to take
action on the approval. If no action is taken, the permit becomes null and void, and the applicant shall
resubmit. Exception: Tree Removal Permits have no expiration.
G. Permit Extension: The Administrator may grant a single extension of up to 6 months upon submittal by
the applicant of sufficient justification for the extension. Permits issued for temporary uses may be
renewed only if it is determined that said use is clearly of a temporary nature, will cause no traffic
congestion, and would not create a nuisance to surrounding uses.
9.5: BUILDING PERMIT
9.5.1 APPLICABILITY
A Building Permit shall be required for any building, structure, or attachment to a structure to be erected, moved,
added to, or structurally altered. This includes, but is not limited to:
A. Site Work: Any modifications to a parcel of land, not to include construction of a structure.
B. New Construction and Expansion:
68
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
1. Primary Building(s): New construction of all types of structures.
2. Accessory Structures or Uses: Accessory uses incidental to single-family residential structures
(e.g., detached garage, swimming pool, tool shed) as regulated by Section 3.11 (Accessory Uses
and Structures).
3. Building Expansions: Heated and unheated (e.g., porches, decks, sunrooms) building expansions.
4. Site Elements: Any site elements not attached to the building (e.g., porches, patios).
C. Signs: Erection of new signs or modification to existing signs, including Master Sign Plans.
D. Awnings: Includes new awnings and awning re-covers.
E. Fences and Enclosures: Erection of, demolition of, or any changes to fences and other types of
enclosures.
F. Demolition: Removal of existing buildings, structures, or site work.
9.5.2 PROCESS AND APPROVAL
A. Process Type: Ministerial.
B. Pre-Application Procedure: For large-scale projects, a pre-construction meeting may be required. For
all other projects, no meeting is required, but applicants are encouraged to call or visit the
Administrator prior to requesting a Building Permit to determine what information is required for the
application.
C. Required Application Information: See Administrator. The application shall include all drawings and
specifications required by building codes adopted by S.C. Code § 6-9-50.
69
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
D. Determination of Conformity: The review, approval, and distribution of drawings and specifications
required shall be coordinated by the Administrator in accordance with the building codes adopted by
S.C. Code § 6-9-50. Upon issuance of a permit, the Administrator shall endorse, by writing or stamp, all
sets of drawings showing approval. Such drawings shall be kept at the work site and made available for
inspection by the Administrator upon request. Approved Project Permits shall be conspicuously posted
by the applicant on the property for which they were obtained until the applicant has obtained a
Certificate of Occupancy, pursuant to Section 9.7.
E. Public Notification: None required.
F. Changes to Approved Plans: If a project has undergone design review and received Design Approval or
Beaufort Historic District - Certificate of Appropriateness, as applicable, no changes between the
design review set and the building permit set shall be permitted unless they are presented in writing
and approved by the Administrator at the time a Project Permit is sought. If the Administrator is not
made aware of any changes, the plans submitted for design review will take precedence.
G. Changes to Approved Permits:
1. After a Project Permit has been issued, no changes or deviations from the terms of the permit or
the application and accompanying plans shall be made without the specific written approval of
such changes or deviations by the Administrator. Any exterior changes may requir e review and
approval by the appropriate decision-making body.
2. An amendment to a Project Permit that requires payment of an additional fee, either because of
an increase in the size of the buildings, a change in the scope of work, or an increase in the
estimated cost of the proposed work, shall not be approved until the applicant has paid the
additional fees, and the amendment has been properly reviewed by the appropriate decision-
making body.
H. Notification and Approval Before Construction Begins:
1. Before any work begins pursuant to the Project Permit, the applicant shall furnish the
Administrator with the name of the general contractors, or the owner acting as the general
contractor, who will be performing the work;
2. The applicant or the applicant's authorized agent shall provide adequate advance notice to the
Administrator at such time as the work is ready for inspection under the Building Code. Upon
receiving such notification, the Administrator shall inspect the work.
I. Licensed Specialty Contractor(s) May Be Required: Where any local ordinances or any provision of the
South Carolina Law require that work be done by a licensed specialty contractor of any kind, no Project
Permit for such work shall be issued unless it is to be performed by such licensed specialty contractor.
It shall further be the contractor's responsibility to conform to all local ordinances and state building
codes for all installations or repairs of a building or utility system.
J. Permit Validity: Any Project Permit shall become null and void unless the work approved by the permit
is commenced within 180 days after the date of issuance. No work shall be considered to have
commenced for the purposes of this paragraph until an inspection has been made and recorded. If
after commencement the work is discontinued for a period of 180 days, the permit shall immediately
expire. No work authorized by any permit that has expired shall thereafter be performed until a new
permit has been secured.
K. Permit Extension: None - shall resubmit.
70
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.6: [SECTION LEFT INTENTIONALLY BLANK]
9.7: CERTIFICATE OF OCCUPANCY
9.7.1 APPLICABILITY
A Certificate of Occupancy shall be required for occupancy and use of a building that is erected or enlarged.
9.7.2 PROCESS AND APPROVAL
A. Process Type: Ministerial.
B. Pre-Application Procedure: n/a.
C. Required Application Information: See Administrator.
D. Public Notification: None.
E. Issuance of Certificate of Occupancy: A final Certificate of Occupancy shall not be issued by the
Administrator until a design and landscape compliance review has been completed.
F. Temporary Certificate of Occupancy: Pending the issuance of a permanent Certificate of Occupancy, a
temporary certificate may be issued. The certificate shall be issued by the Administrator in conformity
with the provisions of this Code and the building code. The temporary certificate may include such
safeguards and conditions as will protect the safety of the occupants and the public. Where
improvements required by this Code or the specific approval of the development are incomplete, a
guarantee acceptable to the City — equal to 125% of the costs of such improvements — may be
required to ensure the installation of the improvements.
G. Permit Validity: n/a.
H. Permit Extension: n/a.
71
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.8: DEVELOPMENT DESIGN REVIEW
9.8.1 DEVELOPMENT DESIGN REVIEW (MINOR SITE PLAN)
A. Applicability:
1. All buildings, except single-family residential structures, in developments that contain 5 or fewer
residential units.
2. Demolition of structures of any size where no new building is proposed.
3. Improvements to existing non-residential or multi-family structures that do not exceed 75% of
the fair market value of the existing improvements.
B. Exceptions:
1. Detached single-family homes on individual lots outside of the Historic District are not subject to
Development Design Review. However, they may be subject to the Building Design Standards laid
out in Article 4, depending on the zoning district and Planning Commission (PC) conditions and
approvals, if applicable, on Preliminary and Site Plans.
2. Projects in the Beaufort Historic District are not subject to Development Design Review and shall
instead be evaluated by the HRB for compliance with the Historic District Guidelines. (See Section
9.10.2 - Beaufort Historic District - Certificate of Appropriateness, Minor and Major)
3. Projects in the LI Zone are not subject to Development Design Review. However , they are subject
to the Building Design Standards described in 4.2.2.B.3.
C. Process Type: Ministerial — The Administrator may submit any application subject to staff approval to
the Planning Commission for approval.
D. Pre-Application Procedure: No meeting is required, but applicants are encouraged to call or visit the
Administrator to determine what information is required for the application.
E. Required Application Information: see Section 9.3 (Table) for specific Application Requirements —
these may be waived by the Administrator as the Administrator deems appropriate.
F. Public Notification: None.
G. Determination of Compliance: Once an application is deemed complete by the Administrator, the
Administrator shall review the application and approve, deny, or approve the plan with conditions
based on compliance with the standards contained in this Code. All decisions shall be in wri ting.
Following an approval or approval with conditions, the applicant shall be directed to prepare detailed
Subdivision/Development Plats and/or Plans (see Section 7.5 for specific Subdivision and Site Plan
Standards) for final approval by the Administrator.
72
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
H. Permit Validity: Upon the approval of the Minor Development Design application, the applicant shall
have 1 year to obtain a Building Permit. Failure to secure Building Permits for the permitted work
within this time shall render the approval void. Any change to the approved plans that has not been
authorized by the Administrator shall invalidate the Minor Development Design Plan and any
subsequent Building Permits (see Section 9.5).
I. Permit Extension: The Administrator may grant up to one 1-year extension of this time period upon
submittal by the applicant of sufficient justification for the extension. Extensions shall be submitted at
least 1 month prior to the expiration date.
9.8.2 DEVELOPMENT DESIGN REVIEW (MAJOR SITE PLAN)
A. Applicability:
1. Civic and Educational Facilities: Any new development classified as a Civic Facility or Educational
Facility (see Sections 3.4.1 A. and 3.4.1 C., respectively).
2. Vehicle-Related Uses: Any new development that includes fuel-dispensing facilities, drive-thru
facilities, or structured parking.
3. Nonresidential Development: Any commercial or industrial development.
4. Residential Development: Single-family, attached, over 5 units or multi-family developments
containing more than 5units.
5. Exceptions:
a. Lots in the Beaufort Historic District are not subject to Development Design Review, and
shall instead be evaluated by the HRB for compliance with the Historic District Guidelines
73
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
(see Section 9.10 Beaufort Historic District - Certificate of Appropriateness, Minor and
Major).
b. Projects in Redevelopment District Overlay Districts, are not subject to review by the
Planning Commission and shall instead be evaluated by the Administrator (see Section
2.7.3). The Administrator shall post all projects for review in said districts for a 15- day
public review and comment period for each major submittal. Minor revisions to the plans
(not related to use, density, building frontage, or building height) shall not constitute a
major submittal. A copy of all public comments shall be disseminated to the applicant and
Administrator for each public comment period. The Administrator shall respond in writing
to all public comments after each major submittal, and the applicant will be required to
attend a TRC committee meeting before the project is issued final approval.
c. Design Exception: Design Exceptions may be used to modify any dimensional standards or
design requirements, found in Articles 2 and 4, for development projects that have unique
characteristics that justify a deviation from the underlying standards. Such deviations are
intended to provide flexibility from the underlying standards to permit compatible
development patterns which are indicative of the surrounding area and/or use an
innovative approach or technique. The process is intended to provide the mini mum relief
necessary to create a more innovative and context-sensitive development consistent with
the City's adopted plans. This tool is not intended to circumvent the map amendment
(rezoning) procedure where that tool would provide a similar modification of standards.
i. Applicability: Planning Commission shall have the authority to authorize a design
exception from any applicable standard(s) set forth in Article 2 (Maps and
Districts) — except for Section 2.6, Height and Section 2.7.4, Air Installation
Compatibility Use Zone (AICUZ) overlay district standards — and Article 4 (Building
Design and Infill Standards).
ii. Review Criteria: Planning Commission may approve an application for a Design
Exception where it reasonably determines that there will be no significant
negative impact upon residents of surrounding property, or upon the general
public. The board shall consider the following criteria in its review:
• Compatibility: The proposed exception is appropriate for its location. It is
compatible with the character of surrounding properties and the
development permitted by the zoning of the surrounding properties, and
will not reduce property values of surrounding properties.
• No Adverse Impact: The design of the proposed exception minimizes
adverse effects including visual impacts of the proposed use on surrounding
properties; furthermore, the proposed exception does not create a nuisance
for surrounding properties.
• Consistency with Adopted Plans: The proposed development is in general
conformity with the City's Comprehensive Plan, Civic Master Plan and other
plans officially adopted by the City.
74
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
B. Application Type, Requirements and Approval: See Table under Section 9.1.4 for standards and
requirements.
75
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.9: SUBDIVISION REVIEW
9.9.1 PROVISIONS FOR ALL SUBDIVISIONS
A. Applicability and Requirements: See Article 7 of this code
B. Unlawful to Record Plat without City Approval: It shall be unlawful to offer and cause to be recorded
any plan, plat, or replat of land within the city limits of Beaufort with the Beaufort County Register of
Deeds office unless the same bears the endorsement and approval of the city.
C. Permit Validity: A subdivision approval shall expire as set out in Section 9.1.9 (Vested Rights and
Expiration of Approvals) of this Code unless a Certificate of Compliance is obtained, or it is recorded at
the Beaufort County Register of Deeds office.
9.10: BEAUFORT HISTORIC DISTRICT - CERTIFICATE OF APPROPRIATENESS
9.10.1 APPLICABILITY
A. A Beaufort Historic District - Certificate of Appropriateness shall be required for any construction
activity on any property within the Beaufort Historic District (including the Beaufort Conservation
Neighborhood and the Beaufort Preservation Neighborhood) , including:
1. New structures.
2. Modification to, or expansion of, existing structures, including those that apply for the Bailey Bill
Special Tax Assessment for Rehabilitated Historic Properties.
3. Relocation of any existing structure.
B. Demolition or partial demolition of any structure.
9.10.2 PROCESS AND APPROVAL
A. Process Type: Ministerial. The review process required to approve a Beaufort Historic District -
Certification of Appropriateness is based on the following project types:
1. Minor: Administrative review shall apply to applications for a Beaufort Historic District -
Certification of Appropriateness for the following items. The Administrator may submit any
applications that are subject to staff approval to the Historic District Review Board (HRB) for
approval.
a. Changes to a building or property, to include fences, paint color, roof materials, canopies
and awnings, site changes, and window replacements on noncontributing structures.
b. New construction and building modifications to include construction of non- habitable
accessory buildings in the Beaufort Preservation Neighborhood (BPN).
76
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
c. Modifications to non-contributing structures in the Beaufort Conservation Neighborhood
(BCN).
d. Demolitions of non-contributing structures in the BCN.
e. Demolition or partial demolition of a structure that is listed in the "1997 Beaufort County
Historic Sites Survey," or the most recent historic sites survey, and lies outside the Beaufort
Historic District.
f. Demolition of noncontributing accessory structures (e.g., sheds, carports, etc.).
Such approval shall follow the procedures for Development Design Review -Minor Site Plan
(Section 9.8.1).
77
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
2. Major: Discretionary review by the HRB shall apply to all other applications for Beaufort Historic
District - Certificates of Appropriateness.
3. Design Exception: Design Exceptions may be used to modify any dimensional standards or design
requirements, found in Articles 2 and 4, for development projects that have unique
characteristics that justify a deviation from the underlying standards. Such deviations are
intended to provide flexibility from the underlying standards to permit compatible development
patterns which are indicative of the surrounding area and/or use an innovative approach or
technique. The process is intended to provide the minimum relief necessary to create a more
innovative and context-sensitive development consistent with the City's adopted plans. This tool
is not intended to circumvent the map amendment (rezoning) procedure where that tool would
provide a similar modification of standards.
a. Applicability: The HRB shall have the authority to authorize a design exception from any
applicable standard(s) set forth in Article 2 (Maps and Districts) — except for Section 2.6,
Height and Section 2.7.4, Air Installation Compatibility Use Zone (AICUZ) overlay district
standards — and Article 4 (Building Design and Infill Standards).
78
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
b. Review Criteria: The HRB may approve an application for a Design Exception where it
reasonably determines that there will be no significant negative impact upon residents of
surrounding property, or upon the general public. The board shall consider the following
criteria in its review:
i. Compatibility: The proposed exception is appropriate for its location. It is
compatible with the character of surrounding properties and the development
permitted by the zoning of the surrounding properties, and will not reduce
property values of surrounding properties.
ii. No Adverse Impact: The design of the proposed exception minimizes adverse
effects including visual impacts of the proposed use on surrounding properties;
furthermore, the proposed exception does not create a nuisance for
surrounding properties.
iii. Consistency with Adopted Plans: The proposed development is in general
conformity with the City's Comprehensive Plan, Civic Master Plan and other
plans officially adopted by the City.
B. Guidance Standards, Maintenance of Consistent Policies: In order to provide guidance and insight into
desirable goals and objectives for the Beaufort Historic District, the documents described in this section
are hereby adopted for use by the HRB in the exercise of its authority granted under Section 10.7 of
this Code.
1. The "Beaufort Preservation Manual," August 1979, and the "Beaufort Preservation Manual,
Supplement," August 1990, shall be utilized by the HRB for review of projects located within the
Beaufort Preservation Neighborhood.
2. The "Northwest Quadrant Design Principles," May 1999 shall be utilized by the HRB for the
review of projects located within the Beaufort Conservation Neighborhood.
3. The Secretary of Interior's "Standards for Rehabilitation" shall be utilized for review of all projects
that modify a contributing structure.
4. The Building Design Standards, in Article 4 of this Code, shall be utilized for review of all new
construction.
5. The Historic District Infill Design Guidelines, in Section 4.7 of this Code, shall be utilized for review
of all new construction.
6. Any special area policies adopted by the HRB.
C. Approval of Beaufort Historic District - Certificate of Appropriateness: In reviewing an application, the
HRB shall conduct a public meeting and consider, among other things, the historic, architectural and
aesthetic features of such structure, the nature and character of the surrounding area, the use of such
structure and its importance to the city, the character and appropriateness of design, scale of
buildings, arrangement, texture, materials and color of the structure in question, and the relation of
such elements to similar features of structures in the immediate surroundings. The HRB shall not
consider the interior arrangement or interior design unless the interior arrangement or design affect
the exterior appearance, nor shall it make requirements except for the purpose of preventing
developments that are not in harmony with the prevailing character of the Beaufort Historic District, or
that are obviously incongruous with this character.
79
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
D. Demolitions:
1. In all applications involving the demolition of a contributing primary structure or contributing
accessory structure, provisions shall be made for a public hearing as set forth in Section 9.1.5.
Demolition of non-contributing structures are approved by the Administrator.
2. In any case involving the demolition or partial demolition of a structure, before granting approval
or requiring a postponement, the HRB may call on the Administrator to provide them with a
report on the state of repair and structural stability of the structure under consideration.
3. Upon receiving an application for demolition or partial demolition of a structure that is listed in
the "1997 Beaufort County Historic Sites Survey" and lies within the limits of the city but outside
the Beaufort Historic District, the Administrator, within 30 days of receiving the application, shall
either approve it, or find that the preservation and protection of historic places and the public
interest will be best served by postponing the demolition for a designated period — this shall not
exceed 60 days from the receipt of the application, and notify the applicant of such
postponement. The application will be announced to the public in accordance with the
notification standards set forth in Section 9.1.3. Within the period of postponement of
demolition or alteration of any building, the Administrator shall take steps to ascertain what may
be done to preserve the building, including consultation with private civic groups, interested
private citizens and other public boards or agencies, including investigation of the potential use
of the power of eminent domain when the preservation of a given building is clearly in the
interest of the general welfare of the community and of certain historic and architectural
significance.
E. Denial of Beaufort Historic District - Certificate of Appropriateness: The HRB may refuse any
application that, in the opinion of the HRB, does not comply with the standards and guidelines listed in
Section 9.10.2.B. and thus would be detrimental to the interests of the city. In case of disapproval, the
HRB shall state the reasons therefore in a written statement to the applicant, and may give verbal
advice to the applicant and make recommendations in regard to appr opriateness of design,
arrangement, texture, material, color, etc. of the property involved.
Among other grounds for considering a design inappropriate and requiring disapproval and
resubmission are the following defects:
1. Arresting and spectacular effects.
2. Violent contrasts of materials or colors and intense or lurid colors.
3. A multiplicity or incongruity of details resulting in a restless and disturbing appearance.
4. The absence of unity and coherence in composition, that is not in consonance with the dignity
and character of the present structure, in the case of repair.
5. Construction of, remodeling, or enlargement of an existing building in a manner not consistent
with the prevailing character of the neighborhood.
F. Issuance of Beaufort Historic District - Certificate of Appropriateness (CoA): When a CoA and Building
Permit have been issued, the Administrator shall, from time to time, inspect the alteration or
construction approved by such certificate and may report such inspection to the HRB listing all work
inspected and reporting any work that is not in accordance with such certificate, or that violates any
ordinances of the city.
G. Resubmittal: After disapproval of an application, the applicant may make modifications to the plans
and resubmit. The applicant may not resubmit the same proposal, without modifying it based on HRB
comments, for 12 months from the date of the original submission. Reco nsideration of an application
80
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
for demolition that has been denied by the HRB may not be heard until 12 months from the date of the
original public hearing, unless a major change has occurred in the property condition that is
attributable to natural causes.
H. Appeal—Minor: Appeals of the decisions of the Administrator shall be heard by the HRB. The
application for appeal shall be made within 30 days of the decision.
I. Appeal—Major: Any party aggrieved by the decisions of the HRB may appeal to the circuit court withi n
30 d
ays of the decision.
9.11: HISTORIC DESIGNATION
9.11.1 STANDARDS FOR LOCAL HISTORIC DISTRICT DESIGNATION
A. A structure, group of structures, site or district may be designated for historic preservation if it
demonstrates at least one of the following:
1. Historic, Cultural Importance:
a. It has significant character, interest, or value as part of the development, or heritage of th
e
c
ommunity.
b. It is the site of a historic event with a significant effect upon society.
c. It exemplifies the cultural, political, economic, social, or historic heritage of the community.
2. Architectural or Engineering Importance:
a. It portrays the environment in an era of history characterized by a distinctive architectural
style.
b. It embodies those distinguishing characteristics of an architectural type or engineerin g
s
pecimen.
c. It is the work of a designer whose individual work has significantly influenced the
development of Beaufort.
d. It contains elements of design, detail, materials, or craftsmanship that represent significant
innovation.
3. Geographical Importance:
a. By being part of or related to a square, park, or other distinctive area, it should be
developed or preserved according to a plan based on a historic, cultural, or architectural
motif.
b. Owing to its unique location or singular physical characteristic, it represents an established
and familiar feature of the neighborhood, community or city.
4. Archeological Importance:
a. It has yielded, or may be likely to yield, information important in prehistory or history.
B. An area may be designated as a Beaufort Conservation Neighborhood (BCN) if it meets one or more of
the above criteria, and meets the following two additional criteria:
81
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
1. There are a sizable number of properties in the subject area that are not considered to contribute
to the architectural or historical significance of the area; and
2. The cultural values or financial resources of a significant number of property owners in the
subject area, as reasonably considered by Beaufort City Council, are such that the flexible
standards of the BCN are appropriate.
C. Individual structures, sites, and properties located within a BCN may be designated as notable
properties to be subject to Beaufort Historic District standards, guidelines and procedures rather than
BCN standards, guidelines, and procedures, at such time as standards, guidelines, and procedures may
be established for the BCN that are different from those in effect for the remainder of the Historic
District. Beaufort City Council may designate structures, sites, and properties as notable properties
where it reasonably determines that those structures, sites, or properties embody a particularly high
degree of significance in accordance with the criteria listed in this section.
9.11.2 LOCAL HISTORIC DISTRICT DESIGNATION PROCESS
Based upon the criteria set forth in this section, the HRB shall review such proposed designations, and then it shall
make a recommendation regarding the designation to City Council for final approval.
82
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.11.3 HISTORIC SIGN DESIGNATION
A. Historic Signs: A historic sign is a sign that, by its construction materials, unusual age, prominent
location, unique design, or craftsmanship from another period, makes a contribution to the cultural,
historic, or aesthetic quality of the city's streetscape.
1. Signs are designated as historic signs by City Council upon a favorable recommendation of the
HRB. The council shall hold a public hearing before designating a sign a historic sign. Before
designating a sign as a historic sign, the council shall make a finding that all of the following
conditions are met:
a. The sign is at least 25 years old and has been at its present location for at least 25 years.
b. The sign is an appurtenant graphic to the property, i.e., an on- premises sign that relates to
the use of the property, as opposed to an off-premises billboard.
c. The sign is structurally safe or is capable of being made so without substantially altering its
historical significance.
d. The sign is of exemplary technology, craftsmanship, or design of the period in which it was
constructed, it uses historic sign materials (wood, metal, or paint directly applied to
buildings) and means of illumination (neon or incandescent fixtures), and it is not
significantly altered from its historic period. If the sign has been altered, it shall be
restorable and shall be restored to its historic function and appearance.
e. The sign is of extraordinary significance to the city.
2. Historic signs are exempt from the requirements of Section 11.6 (Nonconforming Signs).
9.12: ADMINISTRATIVE ADJUSTMENT
9.12.1 PURPOSE AND APPLICABILITY
A. Purpose: Administrative Adjustments are specified deviations from otherwise applicable development
standards where development is proposed that would be:
1. Compatible with surrounding land uses;
2. Harmonious with the public interest; and
3. Consistent with the purposes of this Code.
B. Adjustment of Numerical Standard: The Administrator shall have the authority to authorize
modification of up to 10% from any numerical standard set forth in Article 2 (Map & Districts) and
Article 4 (Building Design and Infill Standards) of this Code. Any request greater than 10% shall be
treated as a variance handled by the Zoning Board of Appeals (ZBOA), and subject to the requirements
of Section 9.14.
1. Specific to Landscaping and Tree Conservation: The following applies to landscaping and tree
conservation requirements in Article 5 (Landscaping, Parking & Lighting) with regard to the
criteria in Section 9.12.2 E.:
83
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
a. In unusual cases, where there are few existing trees on a site and the planned development
is small in size relative to the size of the parcel, then the Administrator may adjust the tree
planting requirements (Section 5.3) downward in order not to requi re excessive planting
out of proportion to the scale of the development.
b. In the case of multi-phase developments on one parcel, the tree planting requirements
(Section 5.3) may be adjusted according to the size of each phase of the development.
c. Any particular planting requirement shall be proportionately reduced where existing plant
materials are of sufficient sizes and forms to satisfy the requirement.
C. Adjustment of Building Design Standards: Where an existing condition (e.g. utility easement,
restrictive covenant, tree or natural feature) prohibits strict compliance with the building design
standards in Article 4, the Administrator may waive or adjust the standard as appropriate to assure
compliance to the extent practical. This adjustment shall be as small as possible in order to
accommodate the existing conditions.
D. Permission of Flag Lot: Where conditions set forth in Section 2.5.5 C. are met, the Administrator may
permit a flag lot. When a flag lot is proposed in conjunction with a Major Subdivision, it shall be
incorporated into the process laid out in Section 9.9.
9.12.2 PROCESS AND APPROVAL
A. Process Type: Ministerial
B. Public Notification: None.
C. Required Application Information: An application for an Administrative Adjustment shall include a
brief description of the requirement to be varied and any other material necessary to ensure the
criteria in this section are met.
84
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
D. Administrator Review: The Administrator shall review the application and approve, approve with
conditions, or deny the application, based upon the criteria in Section 9.12.2 E. A written decision
including affirmative findings on the criteria set forth below shall be transmitt ed to the applicant.
E. Administrative Adjustment Criteria: To approve an application for an Administrative Adjustment, the
Administrator shall make an affirmative finding that the following criteria are met:
1. Granting the Administrative Adjustment will ensure the same general level of land use
compatibility as the otherwise applicable standards.
2. Granting the Administrative Adjustment will not materially and adversely affect adjacent land
uses and the physical character of uses in the immediate vicinity of the proposed development
because of inadequate buffering, screening, setbacks, and other land use considerations.
3. Granting the Administrative Adjustment will not adversely affect property values in any material
way.
4. Granting the Administrative Adjustment will be generally consistent with the purposes and intent
of this Code.
F. Expiration and Lapse of Approval: Property owners shall have 6 months from the date of approval of
an Administrative Adjustment to secure a Building Permit to carry out the proposed improvements. If a
complete Building Permit application has not been filed within 6 months of the date of approval, the
approval shall be void.
85
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.13: ZBOA SPECIAL EXCEPTION
9.13.1 APPLICABILITY
ZBOA Special Exceptions may be made for situations in which proposed land uses are generally compatible with
the land uses permitted by-right in a district (per Section 3.2 Table of Permitted Uses) but require individual review
of their location, design, and configuration to evaluate the potential for adverse impacts on adjacent property and
uses. The ZBOA Special Exception process ensures the appropriateness of the use at a particular location within a
given District.
9.13.2 PROCESS AND APPROVAL
A. Process Type: Discretionary.
B. Required Application Information: All applicable forms as determined by the Administrator, along with
such accompanying material as is required to ensure compliance with the criteria listed in Section
9.12.2 E.
C. Public Notification: see Section 9.1.5 for specific Public Notification requirements
D. Staff Review and Report: The Administrator shall prepare a staff report that reviews the proposed
development in light of the Comprehensive Plan, Civic Master Plan, the review criteria listed below,
and the requirements of this Code. A copy of the report shall be provided to the Zoning Board of
Appeals (ZBOA) and the applicant before the scheduled hearing.
86
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
E. ZBOA Hearing:
1. The ZBOA shall hold a public hearing on the Special Exception application.
2. After review of the application and the public hearing, the ZBOA shall make a written finding and
approve, approve with modifications or conditions, or disapprove the request.
3. If approval, or approval with modifications or conditions, is granted, the decision shall be
communicated in writing within 15 days to the applicant, and the applicant shall then be
authorized to submit a development permit application consistent with this Code.
F. ZBOA Special Exception Review Criteria: The ZBOA may approve an application for a Special Exception
where it reasonably determines that there will be no significant negative impact upon residents of
surrounding property/-ies or upon the general public. The ZBOA shall consider the following criteria in
its review:
1. The proposed use/-s is/are compatible with existing land uses in the surrounding area.
2. The harmony of the proposed site plan, circulation plan, and schematic architectural designs with
the character of the surrounding area.
3. The likely impact on public infrastructure — such as roads, parking facilities, and water and sewer
systems —and on public services — such as police and fire protection and solid waste collection
— and the ability of existing infrastructure and services to adequately service the proposed use
without negatively impacting existing uses in the area and in the City (a traffic impact analysis
shall be required per Section 7.3.2).
4. The general conformity of the proposed use and designs with the city's Civic Master Plan,
Comprehensive Plan, and any other plans officially adopted by the City.
5. The likely impact on public health and safety.
6. The potential creation of noise, lights, fumes, dust, smoke, vibration, fire hazard, or other
injurious or obnoxious impacts.
G. Conditions: The ZBOA may impose such conditions and restrictions upon the application as may be
necessary to minimize or mitigate any potential adverse impacts of the proposed use.
87
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.14: ZBOA VARIANCE
9.14.1 APPLICABILITY
Variances to all ordinance standards may be requested with the following exceptions:
A. No variances to the Table of Permitted Uses (Section 3.2) shall be permitted.
B. No variances to sign regulations (Article 6) shall be permitted.
C. No variances to parking provisions for Carriage Houses (4.5.3.B.9) shall be permitted.
D. Design Exceptions shall be approved by the appropriate design review body.
9.14.2 PROCESS AND APPROVAL
A. Process Type: Discretionary.
B. Application Requirements: All applicable forms as determined by the Administrator, along with such
accompanying material as is required to ensure compliance with the criteria listed in Section 9.14.2 F.
C. Staff Review and Report: The Administrator shall prepare a staff report that shall be provided to the
applicant or appellant and the ZBOA before the scheduled hearing.
88
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
D. Public Notice: see Section 9.1.5 for specific Public Notification requirements.
E. ZBOA Hearing:
1. After review of the variance application and the public hearing, the ZBOA shall approve, approve
with conditions, or deny the application.
2. If approval or approval with conditions is granted, the decision shall be communicated in writing
to the applicant within 15 days, and the applicant shall be authorized to submit a development
permit application.
F. Criteria for Approval of Variances:
1. Required Findings: A variance may be granted by the ZBOA if it concludes that the strict
enforcement of any design and performance standard set forth in this Code would result in
unnecessary hardship to the applicant, and that by granting the variance, the spirit of this Co de
will be observed, public welfare and safety will not be diminished, and substantial justice will be
done. A variance may be granted in an individual case of unnecessary hardship only when the
ZBOA makes, and explains in writing, all of the following findings:
a. There are extraordinary and exceptional conditions pertaining to the particular piece of
property. For example, the variance is justified because of topographic or other special
conditions unique to the property and development involved, in contradistinction to the
mere inconvenience or financial disadvantage.
b. These conditions do not generally apply to other property in the vicinity.
c. The conditions are not the result of the applicant's own actions.
d. Granting of the variance would not substantially conflict with the Comprehensive Plan, the
Civic Master Plan and the purposes and intent of this Code.
e. Because of these conditions, the application of this Code to the particular piece of property
would effectively prohibit or unreasonably restrict the utilization of the property.
f. The authorization of a variance will not be of substantial detriment to adjacent property or
the public good, and the character of the zone will not be harmed by the granting of the
variance.
2. Limitations: The ZBOA may not grant a variance if it would do any of the following:
a. Allow the establishment of a use not otherwise permitted in the applicable district.
b. Increase the density of a use above which is permitted in the applicable district.
c. Physically extend a nonconforming use of land.
d. Change the zone boundaries shown on the Official Zoning Map.
3. Profitability Not to Be Considered: Profitability shall not be considered grounds for a variance.
4. Conditions: In granting a variance, the ZBOA may attach to it conditions regarding the location,
character, or other features of the proposed building, structure, or use as the ZBOA considers
advisable to protect established property values in the surrounding area, or to promote public
health, safety, or general welfare.
89
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
9.15: ADMINISTRATIVE APPEALS
9.15.1 APPLICABILITY
Any person aggrieved by a decision, interpretation or determination of the Administrator may appeal to the ZBOA.
As per South Carolina Code of Laws Section 6-29-800, the Zoning Board of Appeals (ZBOA) has the power to hear
and decide appeals where it is alleged there is error in an order, requirement, decision, or determination made by
an administrative official in the enforcement of the zoning ordinance, i.e. The Beaufort Development Code.
9.15.2 PROCESS AND APPROVAL
A. Process Type: n/a.
B. Pre-Application Procedure: n/a.
C. Required Application Information: Within 30 days of a decision or order of the Administrator, an
application for appeal shall be filed with the Administrator and the ZBOA specifying the grounds of the
appeal.
D. Public Notification: see Section 9.1.5 for specific Public Notification requirements.
E. Effect of Appeal: An appeal stays all legal proceedings in furtherance of the action in question, unless
the Administrator certifies to the ZBOA that a stay would, in his/her opinion, cause imminent peril to
life and property. In such case, proceedings shall not be stayed except by a restraining order that the
ZBOA or by a court of record may grant.
F. ZBOA Hearing: The ZBOA shall schedule the matter for a hearing at its next regularly -scheduled
meeting, and give at least 15 days public notice of such hearing in a newspaper of general circulation in
the city, as well as due notice to the parties of interest. At the h earing, any party may appear in person,
by agent, or by attorney. Following the hearing, the ZBOA shall take one of the following actions,
consistent with the provisions of this Code:
90
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
1. Affirm the action of the Administrator;
2. Modify the action of the Administrator, and to that end, the ZBOA shall have all the powers of
the officer, board, or commission from which the appeal is taken, and may issue a permit or
direct that a permit be issued; or
3. Reverse the action of the Administrator, and to that end, the ZBOA shall have all the powers o
f
t
he officer, board or commission from which the appeal is taken, and may issue a permit or direct
that a permit be issued.
G. Findings of Fact: The ZBOA, in its execution of the duties specified in this section, may subpoena
witnesses, and in case of contempt, may certify such fact to the circuit court that has jurisdiction.
H. Decision: All final decisions and orders of the ZBOA shall be in writing and shall be permanently filed i n
t
he office of the board as a public record. All findings of fact and conclusions of law shall be separately
stated in final decisions or orders of the ZBOA, which shall be delivered to parties of interest within 15
d
ays by certified mail.
I. Contempt Penalty: In case of contempt by a party, witness, or other person before the ZBOA, the ZBOA
may certify this fact to the circuit court of the county in which the contempt occurs, and the judge of
the court, in open court or in chambers, after hearing, may impose a penalty as authorized by law.
9.16: TEXT & MAP AMENDMENTS
9.16.1 APPLICABILITY
When the public necessity, convenience, general welfare, or good zoning practice justify such action, and after the
required review and report by the Planning Commission, the City Council may undertake the necessary steps to
amend this Code, and its accompanying map.
(Ord. No. O-14-23 , 9-26-2023)
9.16.2 INITIATION OF AMENDMENTS
A proposed amendment to this Code may be initiated by any member of the City Council, the PC, the
Administrator, or by any city resident or business owner filing an application with the Administrator.
(Ord. No. O-14-23 , 9-26-2023)
9.16.3 APPROVAL PROCESS
Requests to amend this Code shall be processed in accordance with the following requirements:
A. Application Procedure: Application forms for code amendment requests shall be obtained from the
Administrator. Completed forms, together with an application fee as required by Section 9.2.2, plus
any additional information the applicant deems pertinent, shall be filed with the Administrator .
1. A
pplications for zoning map amendments (rezoning) shall also include:
91
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
a. Boundary map of the subject property that is prepared and sealed by a registered land
surveyor.
b. Where applicable, a copy of correspondence illustrating that the applicant has solicited
written comments from the appropriate property owners' association regarding the
requested amendment. Such correspondence shall encourage the association to direct any
comments in writing to the Administrator and the applicant within 15 calendar days of
receipt of the notification.
c. Written consent from the owner of the property that is being considered for an
amendment. This is required if the applicant is not the city.
92
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
B. Staff Review and Report:
1. The Administrator shall prepare a staff report that reviews the proposed amendment in light of
the Comprehensive Plan and the general requirements of this Code. A copy shall be provided to
the PC and the applicant before the scheduled public meeting.
2. For amendments where the most intense permitted use in the proposed district would generat
e
m
ore than 50 external trips during the peak hour, a TIA (Section 7.3.2) may be required; all road
i
mprovements needed to maintain the current level of service shall be identified (based on that
analysis), and assurances shall be provided so that all road improvements will be in place so the
impacts of the development are accommodated, and the current level of service is maintained.
3. At the discretion of the Planning Commission, the submittal may include the requirements of a
Sketch Plan submittal as per Section 7.5.3, or a conceptual Site Plan (to include buildin
g
e
levations and any applicable Sketch Plan requirements as per Section 7.5.3) to be submitted
wi
th the map amendment request so that the impacts of development on the community ar e
pr
operly considered.
C. P
lanning Commission Hearing:
1. Public Notification: see Section 9.1.5 for specific Public Notification requirements.
2. H
earing by PC: All papers and other data submitted by the applicant on behalf of the amendment
request shall be transmitted to the PC. The PC, at regular meetings, shall review and prepare a
recommendation for transmittal to the City Council. At such meeting(s), any party may appear i
n
pe
rson, by agent, or by attorney. Following action by the PC, all papers and data pertinent to the
application shall be transmitted to the City Council for final action. The PC shall study the
proposed amendment, taking into account the following factors:
a. Consistency (or lack thereof) with the Comprehensive Plan and Civic Master Plan;
b. Compatibility with the present zoning, with conforming uses of nearby property, and wit
h
t
he character of the neighborhood;
c. Suitability of the property that would be affected by the amendment;
d. Compatibility with the natural features of — and any archaeological or cultural resources
on — the property;
e. Marketability of the property that would be affected by the amendment; a nd
f. Av
ailability of roads, sewer, water, and stormwater facilities generally suitable and
adequate for the affected property.
3. At the close of the public meeting, the PC shall recommend approval, modified approval, or
denial of the amendment.
4. Upon receipt of a recommendation from the PC, the staff shall have 30 days within which to
submit its report of the PC's deliberations and recommendation City Council. If the PC or its staff
fail to submit a report within the 30-day period, it shall be deemed to have recommended
approval of the proposed amendment.
5. If, after three PC meetings, no recommendation has been made (e.g., each meeting has resulted
in the request being tabled), the item will proceed to City Council. Staff will prepare a report o
f
t
he PC deliberations within 30 days of the third PC meeting.
93
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
D. City Council Action:
1. Public Notification: see Section 9.1.5 for specific Public Notification requirements.
2. Timing: City Council shall consider the proposed map or text amendment at the earliest
reasonable date and shall consider the report of the PC in making a decision.
3. Decision: City Council may schedule an additional public hearing to approve, approve with
modifications, or deny the proposed amendment.
4. Notification of Result: The applicant shall be notified in writing within 15 days of City Council's
action.
(Ord. No. O-14-23 , 9-26-2023)
9.16.4 UPDATE OF ZONING MAP
Following City Council's final action, any necessary changes shall be made to this Code, or to the Official Zoning
Map within 7 days. A written record of the type and date of such change shall be maintained by the Administrator.
After 7 days of the official action, the action by City Council shall be considered official even if the Administrator
fails to make the written change to the appropriate document.
9.17: APPEALS
9.17.1 APPLICABILITY
Any person or entity desiring to appeal any decision, order, requirement or determination of any official, board or
other authority set forth in this Code, thereby taking advantage of certain enumerated appeal rights granted by
the South Carolina legislature, are encouraged to carefully review the appeal provisions of the South Carolina Local
Government Comprehensive Planning Enabling Act of 1994, as amended, codified at South Carolina Code of Laws,
Title 6, Chapter 29, and to seek appropriate legal advice.
9.17.2 SPECIFIC AUTHORITIES
The following statutes apply to the different types of appeals. They should be consulted if filing an appeal.
A. Appeal from decision of the City Council on a Zoning Map amendment or other regulatory enactment
under this Code. See S.C. Code § 6-29-760.
1. Time Period: within 60 days of the final decision.
2. To Whom: Circuit Court.
B. Appeal from decision of the Planning Commission on a Subdivision Preliminary Plat and a Major
Development Site Plan. See S.C. Code §§ 6-29-1150 and 6-29-900, respectively.
1. Time Period: within 30 days after the affected party receives actual notice of the final decision.
2. To Whom: Circuit Court.
94
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
C. Appeal from decision of the Historic District Review Board. See S.C. Code § 6-29-900.
1. Time Period: within 30 days after the affected party receives actual notice of the final decision.
2. To Whom: Circuit Court.
D. Appeal from decision of the Zoning Board of Appeals. See S.C. Code § 6-29-820, et seq.
1. Time Period: within 30 days after the affected party receives actual notice of the final decision.
2. To Whom: Circuit Court.
E. Appeal of an alleged error in any order, requirement, determination or decision of administrative
official on a Subdivision Sketch Plan, Preliminary or Final Plat, Minor Plat, or Site Plan and involving
non-historic structures and neighborhoods under their legal purview. See S.C. Code §§ 6-29-880, 6-29-
890, and 6-29-1150, respectively.
1. Time Period: 30 days from date of the specific action appealed.
2. To Whom: Planning Commission.
F. Appeal of an alleged error in any order, requirement, determination or decision of administrative
official involving historic structures and neighborhoods under their legal purview . See S.C. §§ 6-29-880
and 6-29-890, respectively.
1. Time Period: 30 days from date of the specific action appealed.
2. To Whom: Historic District Review Board.
G. Appeal of an alleged error in any order, requirement, determination or decision of administrative
official in the enforcement of the zoning ordinance, not subject to statutory authority of the Planning
Commission or Historic District Review Board, as above. See S.C. Code § 6-29-800.
1. Time Period: 30 days from date of the specific action appealed.
2. To Whom: Zoning Board of Appeals.
H. Appeal of the issuance or failure to issue a Zoning Permit. See S.C. Code § 6-29-800 (A) and (C).
1. Time Period: 30 days from date of the specific action appealed.
2. To Whom: Zoning Board of Appeals.
I. Appeal of the issuance or failure to issue a Building Permit and/or a Certificate of Occupancy . See S.C.
Code § 6-29-880, 6-29-890, and 6-29-1150.
1. Time Period: 30 days from date of the specific action appealed.
2. To Whom: Planning Commission or Historic District Review Board, as applicable.
95
ATTACHMENT 2.B. - ORDINANCE & EXHIBTS
SCOTT MARSHALL
City Manager
CITY OF BEAUFORT
Community Development Department
1911 BOUNDARY STREET
BEAUFORT, SC 29902
(843) 525-7011
FAX (843) 986-5606
CURT FREESE
Community Development
Director
Date: May 22, 2025
From: Curt Freese, Community Development Director
To: City Council
Subject: Summary of Major Changes to Chapter 7
Below is a summary of the major changes to Chapter 7: Land Development/Streets. The summary focuses on
significant updates, additions, or modifications organized by subsection. Chapter 7 is a major chapter, ensuring
development, open space, and infrastructure meets high quality predictable and comprehensive standards the
City envisions for its future.
7.1: Improvement Requirements
• 7.1.1 Purpose:
• Added Goals: New purposes (F, G, H, I) emphasize complementing the city’s historic
development pattern, promoting compact, sustainable neighborhoods, fostering livable
communities with reduced vehicle dependency, and ensuring streets facilitate safe, efficient
walking, biking, and driving. These align with Beaufort’s Comprehensive Plan and historic
character.
• 7.1.2 Applicability:
• Clarified Exceptions: Exemptions for Minor Development Design Review, Minor Subdivisions, or
Historic District projects. Previously, the language was less specific.
• Final Plat Approval: Strengthened requirement that Final Subdivision Plat approval is contingent
on installing required improvements or providing guarantees (per 7.1.5), with clearer language
on city satisfaction.
• 7.1.3 Table of Required Improvements:
96
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
SCOTT MARSHALL
City Manager
CITY OF BEAUFORT
Community Development Department
1911 BOUNDARY STREET
BEAUFORT, SC 29902
(843) 525-7011
FAX (843) 986-5606
CURT FREESE
Community Development
Director
• Expanded Scope: Added requirements for Community Green Space and Open Space across
zoning districts, with varying mandates (required, discretionary, or exempt) based on district
type (e.g., T1, T3-S, T5-UC). Previously, this was not explicitly included in the table.
• Flexibility for Infill/Redevelopment: For Infill and Redevelopment Areas (per 8.3.2),
improvements are required only to the extent feasible, considering existing conditions like roads
and utilities. This adds flexibility for constrained sites.
• 7.1.6 Easement and Utility Standards:
• Easement Design: New requirement for easements to permit multiple utility installations, with a
minimum 10-foot width for public utility easements in subdivisions, improving efficiency.
• Underground Utilities: Strengthened mandate for underground utility lines (telephone, electric,
cable) with exceptions only for existing above-ground lines or high-voltage (115 kV+)
transmission lines, subject to city approval. Screening/fencing for surface equipment is now
required.
7.2: Street Network and Design Standards
• 7.2.1 Street Infrastructure Plans:
• Street Frontage Requirements: For Major Subdivisions, Major Development Design Reviews, or
Certificates of Appropriateness affecting a whole block face, property owners must install
prescribed streetscape improvements (e.g., sidewalks, trees) before Final Plat approval or
Certificates of Occupancy. Exceptions allowed if existing elements meet the intent of the street
section.
• Right-of-Way Dedication: Cleaned up this section. Property owners may be required to reserve
or dedicate right-of-way for streets on Official Maps, with compensation available for
97
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
SCOTT MARSHALL
City Manager
CITY OF BEAUFORT
Community Development Department
1911 BOUNDARY STREET
BEAUFORT, SC 29902
(843) 525-7011
FAX (843) 986-5606
CURT FREESE
Community Development
Director
installation costs (e.g., via Traffic Impact Fee reductions). Non-Official Map streets encourage
voluntary dedication with city-borne costs.
• Exceptions for Constraints: Administrator can adjust street section requirements for sites
constrained by wetlands, specimen trees, or existing structures, allowing alternative designs
that meet the same intent in smaller dimensions.
• 7.2.2 Street Network Requirements:
• Block Sizes: Specified maximum block perimeters by zoning district (e.g., 2,640 feet in T3-S,
1,320 feet in T4/T5/RMX), with preferred averages to promote walkability. Exceptions allowed
for natural features like wetlands or cultural resources.
• Street Stubs: Mandated connections to existing stubs and new stubs to adjacent properties,
with exemptions for steep slopes (18%+), marshes, or incompatible uses. Stub streets must
extend to property lines, with signage and plat disclosures indicating future connections.
• Cul-de-Sacs: Prohibited except in T3 and LI zones, with stricter standards (e.g., 300-foot
maximum length, pedestrian access easements, preference for closes or loop roads over
traditional cul-de-sacs).
• Gated Streets: prohibited, subject to Planning Commission discretion.
• 7.2.3 Lot Access Standards:
• Rear Access Emphasis: In T3-N, T4, and T5 zones, new access points must use rear alleys/roads,
except in the Historic District or where topography prevents connections (subject to Planning
Commission or Codes Administrator approval).
• Driveway Limits: Clarified maximum driveways per frontage (1 for <150 feet, 2 for ≥150 feet),
with additional driveways requiring demonstrated necessity and restricted to “right-in, right-
out” on arterial roads.
98
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
SCOTT MARSHALL
City Manager
CITY OF BEAUFORT
Community Development Department
1911 BOUNDARY STREET
BEAUFORT, SC 29902
(843) 525-7011
FAX (843) 986-5606
CURT FREESE
Community Development
Director
• Spacing Requirements: Updated minimum separation distances for curb cuts on Major
Thoroughfares, tied to posted speed limits (e.g., 100 feet for <35 mph, 500 feet for 55+ mph),
with specific 500-foot minimum on Robert Smalls Parkway west of Parris Island Gateway.
• Out-Parcels: Limited to internal access within shopping/office/industrial centers unless
approved in a master plan, with abandoned driveways required to be closed and restored.
• 7.2.4 Street Design Standards:
• Traffic Control: Developers may be responsible for partial or full traffic signal installation if
warranted by MUTCD standards, with roundabouts prioritized as alternatives.
• Sidewalk Waivers: Planning Commission can waive sidewalk requirements for alternative
pedestrian paths or severe topographic/vegetative constraints, ensuring flexibility without
compromising connectivity.
• Utility Placement: Utilities in areas with protected resources must be placed under streets to
minimize environmental impact, enhancing preservation efforts.
7.3: Street Engineering Standards
• 7.3.2 Traffic Impact Analysis (TIA):
• Expanded Applicability: TIA required for developments generating >50 peak-hour trips, including
phased projects or use changes exceeding this threshold. Exceptions for certain areas (e.g.,
Boundary Street Master Plan) exclude Educational Facilities with >100 students.
• Expanded Study area: Added half mile requirement and must utilize all TIA’s for current and
proposed developments in conducting TIA.
99
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
SCOTT MARSHALL
City Manager
CITY OF BEAUFORT
Community Development Department
1911 BOUNDARY STREET
BEAUFORT, SC 29902
(843) 525-7011
FAX (843) 986-5606
CURT FREESE
Community Development
Director
• Access Analysis: New requirement for an access analysis per SCDOT’s ARMS Manual, identifying
necessary improvements (e.g., deceleration lanes, curb cut locations) to be incorporated into
plans.
• Mitigation Plan: Mandatory if Traffic Service Level Goals (Level of Service D) are not met, with
developers responsible for mitigating impacts at affected intersections, including signal design
and progression analysis.
• Signal Spacing: Detailed standards for signalized intersections, including progression analysis to
maintain traffic flow (e.g., progressed band speed within 5-10 mph of posted speed), with
options like frontage roads or shared private roads to reduce signals.
• Review Process: TIA completeness and accuracy reviewed by TRC, with approval required before
Project Permit application, streamlining coordination with SCDOT and county entities.
7.4: Community Green Space and Community Open Space
• 7.4.1 Purpose and Intent:
• Definitions Added: Defined Community Green Space (e.g., parks, trails for recreation/aesthetics)
and Community Open Space (undeveloped land like forests, farms), clarifying their distinct roles.
• 7.4.2 Requirements:
• Flexible Standards: For properties <3 acres, green/open space requirements are at the
discretion of the Codes Administrator or Planning Commission, providing flexibility for small
sites.
• Added standards to transect districts wherein the more acreage, more open space is required
even in T-5 UC. Requirement based on size/acreage of site.
100
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
SCOTT MARSHALL
City Manager
CITY OF BEAUFORT
Community Development Department
1911 BOUNDARY STREET
BEAUFORT, SC 29902
(843) 525-7011
FAX (843) 986-5606
CURT FREESE
Community Development
Director
• Incentive for Types: Using ≥75% of the eight specified space types (e.g., Regional Park, Plaza)
allows a 20% increase in dwelling units, encouraging diverse, high-quality spaces.
7.4.5 Ownership and Maintenance:
• Enforcement: Failure to maintain spaces is a Code violation, with city authority to correct
deficiencies at the owner’s expense per the Code of Ordinances (Section 6-2003 or equivalent),
strengthening accountability.
7.5: Subdivision and Site Plan Standards
Added all new requirements for Subdivision and Site Plan standards, that did not exist. Standards add
process, approval, technical requirements, etc. to create predictable standards for Developers, Staff and
Approval Bodies.
• 7.5.1 General Provisions:
• Review Discretion: City discretion over scheduling reviews, with authority to vacate decisions or
void applications if changes are made post-submittal, enhancing procedural control.
• Submittal Checklists: Planning Department provides individualized checklists for subdivision
applications, clarifying requirements and referral agencies.
• 7.5.2 Subdivision Types:
• Minor Subdivision: Clarified as involving ≤6 lots from one parent tract (≤3 acres), lot line
adjustments, or consolidations without new streets. Cumulative lot counting prevents repeated
subdivisions.
• Major Subdivision: Updated to include subdivisions with ≥6 lots (previously ≥5), public/private
road dedications, or unplatted properties, aligning with increased complexity.
• 7.5.3 Sketch Plan:
101
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
SCOTT MARSHALL
City Manager
CITY OF BEAUFORT
Community Development Department
1911 BOUNDARY STREET
BEAUFORT, SC 29902
(843) 525-7011
FAX (843) 986-5606
CURT FREESE
Community Development
Director
• Comprehensive Requirements: Added detailed elements (e.g., road plan, open space plan,
pedestrian network, zoning/design, utility plan) with specific submittal items (e.g., title
commitment, traffic study, utility capacity letter), ensuring thorough conceptual planning.
• Review Criteria: Planning Commission evaluates consistency with Zoning Map, Comprehensive
Plan, Civic Master Plan, and functional system adequacy, formalizing alignment with city goals.
• Timeframe: Approval valid for 24 months, with minor amendments (≤10% changes) approved
administratively, balancing flexibility and oversight.
• 7.5.4 Preliminary Plat:
• Pre-Application Conference: Mandatory to discuss Code requirements, process, and Sketch Plan
conditions, improving applicant preparedness.
• Detailed Submittals: Added requirements for tree survey, archaeological impact assessment,
ecological resource survey, and conceptual design/massing, addressing environmental and
cultural impacts.
• Early Grading: Allowed post-approval with approved construction plans, but at applicant’s risk,
clarifying liability.
• Review Criteria: Expanded to include lot layout and structure design, ensuring comprehensive
evaluation.
• 7.5.5 Final Plat:
• Substantial Conformance: Defined as no changes to land use, density, or major public elements,
with design adjustments allowed to meet conditions, providing clear standards.
• Permits Required: Added requirements for SCDOT utility/access permits, DHEC dewatering
permits, and Army Corps 404 permits before construction, ensuring regulatory compliance.
102
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
SCOTT MARSHALL
City Manager
CITY OF BEAUFORT
Community Development Department
1911 BOUNDARY STREET
BEAUFORT, SC 29902
(843) 525-7011
FAX (843) 986-5606
CURT FREESE
Community Development
Director
• Timeframe: Approval valid for 2 years, with one 18-month extension and potential additional
extensions for substantial progress, offering flexibility for complex projects.
• 7.5.6 Minor Subdivision Plat:
• Streamlined Process: Clarified submittal requirements (e.g., 30-day title commitment) and plat
standards (e.g., bearings, distances, monument descriptions), with applicant responsible for
recording with Beaufort County.
• 7.5.7 Site Plan:
• Comprehensive Submittals: Added detailed requirements for site plan plat (e.g., photometric
plan for commercial/industrial, certified drainage report, final landscape plan), enhancing design
review.
• Review Process: Staff/TRC review ensures consistency with Code, with a public hearing and
findings of fact required for Planning Commission approval, aligning with Comprehensive and
Civic Master Plans.
• Phasing and Expiration: Site plan approval valid for 3 years, with multi-phased plans tied to
Phase I approval, ensuring timely implementation.
• Amendments: Minor variations (≤10% changes) approved by staff; major changes require new
application and Planning Commission review, clarifying modification procedures.
Key Themes of Changes
• Historic and Sustainable Development: New purposes (7.1.1) and street design standards (7.2)
emphasize Beaufort’s historic patterns, compact neighborhoods, and multi-modal connectivity.
103
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
SCOTT MARSHALL
City Manager
CITY OF BEAUFORT
Community Development Department
1911 BOUNDARY STREET
BEAUFORT, SC 29902
(843) 525-7011
FAX (843) 986-5606
CURT FREESE
Community Development
Director
• Environmental and Cultural Protection: Requirements for tree surveys, ecological assessments, and
archaeological studies (7.5), plus utility placement under streets in sensitive areas (7.2.4), prioritize
natural and cultural resource preservation.
• Community Green/Open Space: Enhanced standards (7.4) promote accessible, diverse spaces
supporting community health and cohesion. Increased and added open space and park requirements for
the denser transect district such as T5-UC to ensure green areas are part of new development.
• Added Procedures: Detailed submittal requirements, review criteria, and timeframes (7.5), plus
exemptions for constrained sites (7.2.1), balance rigor with practicality.
• Added Standards for Development: Added all new requirements for Subdivision and Site Plan
standards, that did not exist. Standards add process, approval, technical requirements, etc. to create
predictable standards for Developers, Staff and Approval Bodies.
• Traffic and Infrastructure Management: Strengthened TIA requirements (7.3.2) and street network
standards (7.2.2) ensure safe, efficient circulation, with compensation for right-of-way dedications
(7.2.1).
104
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Beaufort, South Carolina, The Beaufort Development Code
7: LAND DEVELOPMENT
Beaufort, South Carolina, The Beaufort Development Code Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 1 of 48
7: LAND DEVELOPMENT
7.1: IMPROVEMENT REQUIREMENTS
7.1.1 PURPOSE
The purpose of these land development requirements is to:
A. Encourage economically sound and environmentally sensitive development.
B. Assure the timely provision of required streets, utilities, and other facilities and services to new land
developments.
C. Assure the adequate provision of safe and convenient vehicular and pedestrian traffic access and
circulation in and through new land developments.
D. Assure the provision of needed open spaces and building sites in new land developments through the
dedication or reservation of land for recreational, educational, and other public purposes.
E. Assure, in general, the wise and timely development of new areas, in harmony with the Comprehensive
Plan of the city.
F. Encourage new subdivision developments that complement the City's historic development pattern.
G. Promote compact, well-defined, sustainable neighborhoods that enhance the City's character.
H. Create livable neighborhoods that foster a sense of community and reduce dependency on vehicles.
I. Encourage the proper arrangement of new streets in relation to existing or planned streets and
ensuring streets facilitate safe, efficient, and pleasant walking, biking and driving
7.1.2 APPLICABILITY
A. Unless noted otherwise in this section, all new development projects shall be required to have public
sewer and underground wiring, andwiring and shall comply with Section 7.2.3 (Lot Access Standards).
B. Installation or construction of the improvements specified in the Table of Required Improvements
(Section 7.1.3) is required for Aall development projects — with the exception of projects that qualify
as except those which (1) are subject to the Minor Development Design Review (Section 9.8.1) or
Minor Subdivision (Section 9.9.2), or are located in the Historic District, and (2) affect less than one
whole block face — are required to install or construct the improvements specified in the Table of
Required Improvements (Section 7.1.3).
C. The applicant, developer, and real property owner shall be responsible for the installation and
construction of required improvements according to the provisions of this Code, except as may
otherwise be specifically provided herein or by city policy or agreement.
D. Approval of aA Final Subdivision Plat (Section 9.9.4) shall not be approved unless be subject to the
applicant having installed the improvements designated in required by this article Chapter have been
105
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 2 of 48
installed or constructed, or having guaranteed (the applicant has made improvement guarantees
pursuant to (Section 7.1.5), to the satisfaction of the cCity, for the installation of said improvements.
7.1.3 TABLE OF REQUIRED IMPROVEMENTS
ZONING DISTRICT
REQUIRED
IMPROVEMENTS3
SECTION
REFERENCE
T1 T3-
S
T3-
N
T4-
HN
T4-
N
T5-
DC
T5-
UC
RMX IC LI MHP
Public Water and
Hydrants
7.1.3.B ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Public Sewer 7.1.3.B ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Paved Streets1 7.2.4 ■ ■ ■ ■ ■ ■ ■ ■
Streetscape2 Appendix C ■ ■ □ ■ ■ ■ ■ ■ ■ ■
Underground
Drainage
7.1.3.A ■ ■ ■ ■ ■ ■ ■ ■ ■
Curb and Gutter Appendix C □ □ □ ■ ■ ■ ■ ■ ■
Sidewalks 7.2.4.C □ □ □ ■ ■ ■ ■ ■ ■
Street Trees 7.2.5 ■ ■ ■ ■ ■ ■ ■
Street Lights n/a □ □ □ ■ ■ ■ ■ ■ ■ ■
Street Signs
(private streets)
n/a ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Underground
Wiring On-Site
7.1.3.C ■ ■ ■ ■ ■ ■ ■ ■ ■ ■ ■
Community
Green Space and
Open Space
Space
7.4 □ ■ ■ □ □
◼
◼ ◼ ■ □
■ required improvements by
district
□ may be required at the discretion of the administrator Planning
Commission based on existing conditions, surrounding context, and
street section Infrastructure Plans (Appendix C)
1 Rear lanes/alleys may be permitted to be paved with pervious material, such as gravel, depending
on the location.
2 Complete street requirements shall be coordinated with the Street Infrastructure Plans specific
street section found in the regulating plan in Appendix C.
3 For Infill and development of Redevelopment Areas or Districts, as defined in Section 8.3.2, these
items [referring to the table of required provisions' the installation or construction of these
improvements are required to the extent feasible based on existing conditions including roads,
utilities and adjacent buildings.
A. Street Improvements: Land designated for public streets shall be cleared and filled in accordance with
the latest edition of the "South Carolina Standard Specifications for Highway Construction", issued by
the South Carolina State Highway Department of Transportation, or as determined appropriate by the
aAdministrator. No land may be disturbed until a Project Permit has been issued (Section 9.5). See
Section 5.4 for Tree Removal Standards. See Section 7.2 for more standards on street location. See
Appendix C for Street Regulating Plan and Design Standards.
106
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 3 of 48
B. Water and Sewer Facilities: Water and sewer facilities shall be provided in accordance with the
standard procedures and policies of the water and sewer provider and the Department of Health and
Environmental Control Services (SCDESDHEC) and shall be approved by the water and sewer provider.
C. Utility lines: All utility lines within a development site shall be installed underground . The Planning
Commission may approve an exception only in cases , unless where there are existing above-ground
lines that serve the property.
7.1.4 SURVEY AND ENGINEERING
A. Installation of Permanent Reference Points: Permanent reference points shall be placed in accordance
with the following requirements:
1. General Standards: Boundary surveys shall be performed, in accordance with the state minimum
standards published by the State Board of Registration for Professional Engineers and Land
Surveyors, unless more stringent requirements are specified. A minimum of two points in an y
survey must be tied to the state plane coordinate system. The survey may be done on the
horizontal ground distance and tied back to the state plane coordinates.
2. Control Monuments: Vertical control monuments shall be placed in or near the centerline of
pavement of subdivision streets at a minimum of 1 per 4 acres. Where practical, control
monuments shall be placed at points of curvature and points of tangency of curves. The control
monument may be poured on the job or be a concrete marker of the type commonly used in the
area: at least 3 feet long and tapered with a 12-inch long, ¼-inch diameter brass or bronze rod
embedded in the top. Control monuments shall be placed in a cast iron water main valve type
box with a cover flush with the pavement.
3. Property Marker: A steel or wrought iron pipe, rebar, or the equivalent, not less than 0.5 inches
in diameter and at least 24 inches in length shall be set at all property corners and points of
curves, except those located by monuments. They shall be flush with the ground .
4. Accuracy: Land surveys within the city limits shall be Class A surveys, set at an accuracy of at least
1:10000.
7.1.5 IMPROVEMENT GUARANTEES
A. Types Allowed: Prior to approval of a Final Subdivision Plat (Section 9.9.4), the applicant shall provide a
performance guarantee to ensure the completion of required improvements within a period of time as
agreed upon by the Administrator and the applicant, and expressed in the guarantee. Such guarantee
may be in the form of a performance bond, a surety bond, a cash deposit, or a letter of credit. A
performance guarantee shall be posted in the amount of 125% of the total cost of improvements.
1. Performance/Surety Bonds and Letters of Credit: The performance or surety bond, or letter of
credit, shall be in a form acceptable to the Ccity. It shall include a pledge by the bank, insurance
company or other bonding/lending institution that the funds necessary to carry out the terms of
the agreement are guaranteed for payment, and will be released only upon receipt of written
instruction from the city.
2. Cash Deposits: If the surety is in the form of a cash deposit with the City of Beaufort,
proportional parts thereof shall be refundable in relation to progress payments less retainage,
subject to approval of the cCity and subject to a minimum deposit balance of 25% of the project
cost.
107
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 4 of 48
3. Maintenance Guarantees: If the applicant completes all required improvements and complies
with all conditions of the subdivision agreement as determined by the cCity, the remainder of
monies retained by a financial institution or by the cCity may be released to the applicant or his
successor in title. Prior to release, the applicant shall provide the Ccity, prior to the issuance of
any building permit, a performance bond, a surety bond, or a cash deposit equal to the amount
determined by the cCity that would necessary to ensure the repair of any damage to the existing
improvements during the course of any construction, but in no case will the amount of the
security be less than $1,000.00 for each individual building lot. Prior to the issuance of any
certificate of occupancy, the city shall determine whether or not any breakage or damage has
occurred. If no damage to any off-site improvements has occurred, then the city may release the
security to the applicant or his successor in title. If damages have occurred, they shall be
repaired, or the city may draw on the security before it is released.
7.1.6 Easement and utility standards
A. Multiple installations within easements. Easements shall be designed so as to provide efficient installation
of utilities. Public utility installations shall be located as to permit multiple installations within the easements. The
developer will establish final utility grades prior to utility installations. Public utility easement dedication shall be
required with any minor or major subdivision action. Public Utility Easements shall be a minimum of ten (10) wide.
B. Underground utilities. Telephone lines, electric lines, cable television lines and other like utility services shall be
placed underground. The applicant and/or developer shall be responsible for complying with the requirements of
this Section and shall make the necessary arrangements including any construction or installation charges with
each utility provider for the installation of such underground facilities. Transformers, switching boxes, meter
cabinets, pedestals, ducts and other facilities necessarily appurtenant to such underground utilities shall be placed
underground or on the surface but not on utility poles. Screening or fencing is required and subject to approval of
the City. Electric transmission and distribution feeder lines and neces sary appurtenances thereto may not be
placed above ground unless they are carrying greater than 115 kV. Upon approval of the City, such facilities shall
be placed within easements or rights-of-way provided for particular facilities.
7.2: STREET NETWORK AND DESIGN STANDARDS
7.2.1 STREET INFRASTRUCTURE PLANS
A. Purpose and Intent: The Street Infrastructure Plans (in Appendix C) provide diagrams of the cCity's
street network and establishes the ideal alignment, hierarchy and design characteristics - including
total right-of-way width, sidewalk and streetscape amenities, parking lanes, travel lanes and other
geometric and urban design details - for all existing streets, proposed streets that have been adopted
as part of an Official Map, and new potential streets in the City of Beaufort.
B. Official Street Network Plan: Pursuant to the authority of S.C. Code 1976 § 6-7-1210, et seq. (1976), as
amended, the City has previously adopted several Official Maps. An Official Street Network Plan is
incorporated into this Code in Appendix C.2 order to represent a composite of these previously-
adopted Official Maps.
1. Purpose: This plan represents a composite of all Official Maps, to date, in the City. The map
designates existing or proposed streets or ways within the City that are targeted for creation,
expansion or other improvements. The Official Street Network Plan shall in itially consist of a
108
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 5 of 48
series of four (4) separate maps, included in Appendix C, which shall be deemed a part of the
Beaufort this Code.
2. Modification: The Official Street Network Plan may be modified or supplemented per pursuant
to the procedure for Amendments and Rezonings (Section 9.16). The Planning Commission (PC)
will review the Official Street Network Plan on a regular basis at intervals of every 6 months, or
thereabouts. In addition, the maps will be automatically updated as additional Official Maps are
approved per pursuant to the appropriate process required by state law.
C. Street Frontage RequirementsSpecific Street Sections: The provisions regarding street sections noted
in Appendix C show specific street designs for the purposes of identifying future improvements by both
the cCity and fronting property owners. These sections depict the ideal arrangement and design of
street elements.
1. Applicability: For any project that is considered Major Subdivision (Section 9.8.3), Major
Development Design Review (Section 9.8.2)Site Plan, or requires a Certificate of Appropriateness,
Major (Section 9.10.2 A.2.) and affects one whole bBlock fFace, the fronting property owner shall
install all prescribed streetscape improvements as part of the development project. . The
installation of street frontage improvements is required prior to Final Plat approval for Major
Subdivisions, and Certificates of Occupancy for Site Plans.
a. Exception: If similar elements as prescribed in the street section exist — e.g., on-street
parking, sidewalk, tree plantings — the requirement to install the streetscape
element(s)shall be waived if those items meet the intent of the prescribed street section,
even if the existing items do not meet the exact requirements of that street section.
Example Scenarios: If a street section prescribes a 5-foot sidewalk, but a 4-foot sidewalk
already exists, the existing sidewalk will satisfy the sidewalk requirement. However, if the
street section requires a 5-foot planting strip between the curb and the sidewalk, and the 4 -
foot sidewalk is directly adjacent to the curb, this would not satisfy the intent of the street
section and would need to be reconstructed per the prescribed standards.
2. Scope of Improvements: Street frontage improvements shall be installed along the entire
frontage of the property, to the centerline of the street, or if a multi-lane street, the affected
lane, at the sole cost of the applicant as directed by the Codes Administrator. The Codes
Administrator may permit modification of street improvement standards where the required
street improvements are not in the opinion of the Codes Administrator, roughly proportionate to
the impact, type, scale and cost of the proposed development action.
A. Street frontage improvements may include the following: curb, gutter, sidewalk, storm
drainage, street lighting, traffic signal equipment, utility installation, extension, or relocation,
landscaping strip, street trees and landscaping, irrigation, street widening, pavement overlay or
reconstruction, and channelization.
B. In addition to required frontage improvements, the applicant shall provide ramps from the
new sidewalk or walkway to the existing shoulder, across streets and pavement and
channelization tapering back to the existing pavement and channelization as req uired to address
safety concerns.
2D. Dedication of Insufficient Right-of-Way Width:
1. Dedication of Right-of-Way. In the case of a street section adopted as part of an Official
Map, where the width of the existing right-of-way is insufficient to install the prescribed
109
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 6 of 48
street section, the fronting property owner may shall be required to reserve the
appropriate amount of right-of-way (as measured from the centerline of the existing
street). If the owner chooses to dedicate and install the complete right-of-way, the cost of
the improvements may be compensated - see Section 7.2.1 E. The future right-of-way shall
conform to all of the street network requirements of Section 7.2.2 . below. Where a new
right-of-way that is not shown in the Street Regulating Plan, is required as part of a new
development, it shall be designed with appropriate elements based on its proposed
location and zoning district. (See Appendix C).
2. Where a new right-of-way that is not shown in the street regulating plan, is required as
part of a new development, it shall be designed with appropriate elements based on its
proposed location and zoning district. (See Appendix C).
a. In the case of a street section adopted as part of an Official Map, where the width of the
existing right-of-way is insufficient to install the prescribed street section, the fronting
property owner may be required to reserve the appropriate amount of righ t-of-way (as
measured from the centerline of the existing street). If the owner chooses to dedicate and
install the complete right-of-way, the cost of the improvements may be compensated - see
Section 7.2.1 E.
a. b. In the case of a street section that is not part of an Official Map, where the width of the
existing right-of-way is insufficient to install the prescribed street section, the property
owner is encouraged to shall reserve the appropriate amount of right-of-way to complete
the desired street section. If the owner chooses to dedicates and installs the complete
right-of-way, the cost of the improvements may be compensated borne by the City - see
Section 7.2.1 EE).
b. Where an area is designated as future future right-of-way isand identified on an Official
Map, and thus represented on the Official Street Network Plan— these are indicated as
"New Adopted Streets" — new development shall reserve this area for the new street in
the future. If access is needed to the site in that location, the street shall be constructed in
the general location shown.
a. Alternative Paths: The administrator may approve a different street configuration if it the
proposed development plan provides a similar amount and quality of connectivity through
the site. This is determined by evaluating one or more of the following: number of
connections, connections of specific site elements, and required access to existing and
proposed structures. For modification of the Official Street Network Plan, See Section 7.2.1
B.2.
cc. Exceptions and Alternatives:
i. Where the available rights-of-way — due to existing structures and topographic
conditions, — do not functionally permit the full section to be constructed due
to existing structures or topographical conditions limited to wetlands, specimen
and landmark trees, , the Administrator may adjust the requiredments for the
street section.
ii. A different street section may be approved which accomplishes the same intent
in a smaller dimension.
D. Creation of New Right-of-Way:
110
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 7 of 48
1. Where a future right-of-way is identified on an Official Map, and thus represented on the Official
Street Network Plan— these are indicated as "New Adopted Streets" — new development shall
reserve this area for the new street in the future. If access is ne eded to the site in that location,
the street shall be constructed in the general location shown.
a. Alternative Paths: The administrator may approve a different street configuration if it the
proposed development plan provides a similar amount and quality of connectivity through the
site. This is determined by evaluating one or more of the following: number of connections ,
connections of specific site elements, and required access to existing and proposed structures.
For modification of the Official Street Network Plan, See Section 7.2.1 B.2.
b. Street Standards: The future right-of-way shall conform to all of the street network
requirements of Section 7.2.2 below.
2. Where a new right-of-way that is not shown in the street regulating plan, is required as
part of a new development, it shall be designed with appropriate elements based on its
proposed location and zoning district. (See Appendix C).
ED. Compensation: When a project is required to make off-site improvements within the existing right-of-
way, dedicate and/or improve a street with insufficient right-of-way, or install a new street (be it public
or private) per the requirements in Section 7.2.1 C,. above, compensation of the developer for the
costs associated with such improvements may be availablavailable at the City’s discretione. To the
extent that the City has the authority and the ability to do so, the Traffic Impact fee for the project shall
be reduced by the assessed value of the dedicated land and/or construction cost of the right -of-way
improvement. This may be done either as a direct reduction, rebate, or reimbursement of fees.
(Ord. No. O-14-23 , 9-26-2023)
7.2.2 STREET NETWORK REQUIREMENTS
A. Continuation of Adjoining Street System: The proposed street layout shall be coordinated with the
street system of the surrounding area to form an interconnected street pattern, formalized by a
platted public access easement. Adequate The adequacy of street connectivity shall be assessed by the
Technical Review Committee “TRC”, based on the ability of the proposed alignments to:
1. Permit multiple routes between origin and destination points;
2. Diffuse traffic; and
3. Shorten walking distances.
B. Block Sizes: Blocks shall be compact so that they are comfortably walkable and appropriate for their
context.
1. In T3-S zones, block sizes are flexible, but the perimeter shall not exceed 2,640 linear feet (½
mile). An average block perimeter of less than 2,000 feet is preferred.
2. In T3-N zones, block sizes are flexible, but the perimeter shall not exceed 1,700 linear feet (⅓
mile). An average block perimeter of less than 1,500 feet is preferred.
3. In T4, and T5 zones and RMX zones , blocks shall be no more than 400 feet on any side. An
average block length of 250—300 feet is preferred. The block perimeter shall not exceed 1,320
linear feet (¼-mile).
4. Exceptions may be made for natural elements such as wetlands, trees, topography, and cultural
resources, to be incorporated into the site design.
111
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 8 of 48
C. Street Stubs: New developments shall if practicable, connect to any existing street stubs from adjacent
properties and stub to all adjacent properties.
1. Exemptions: Street stubs shall not be required where the Planning Commission finds the
conditions listed below would prevent connections :
a. Topographical conditions (pre-development slopes of 18% or greater).
b. Environmental conditions (marshes, floodplains, specimen and landmark trees, etc.).
c. Property shape that would now allow for street stubs .
d. Property accessibility (existing platted subdivision with no stubs).
e. Incompatible adjacent land uses.
2. Location: Where multiple connection opportunities exist, street stub connections shall be
prioritized in the site design as follows:
a. Adjacent parcels 20 acres or greater in size.
b. Adjacent parcels that abut or are traversed by existing or proposed streets.
c. Where tThe Street Network Diagram recommends a street connection (indicated as a
proposed street).
3. Design:
a. Stub streets and streets intended for extension during future phases shall be constructed
to extend to the property line for constructability to adjoining property. or as close to the
line as practical.
b. It shall be the responsibility of the second development to construct the connection to an
existing stub street.
cb. Stub streets shall not exceed 150 feet in length without a paved turnaround (permanent or
temporary).
dc. Disclosure: The Final Subdivision Plant shall be recorded stating depicting that future
connection is possible required at any stub streets and streets intended for extension
during future phases. A clearly visible street sign mayshall be erected at the end of the stub
street stating that the street is planned to connect to a future street.
D. Cul-de-sacs and Dead-end Streets: Dead-end streets and cul-de-sacs are prohibited, except for in the
T-3 and LI zoning districts, where , unless specifically approved by the TRC. In T3 and LI zones only, cul-
de-sacs or other turn-arounds may be approved by the TRC Planning Commission. Compliance with the
following standards must be met in all circumstances:
112
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 9 of 48
1. Permanent dead-end streets shall be no longer than 300 feet and shall be provided with a turn, -
around such as a cul-de-sac or close.
2. Temporary dead-end streets shall be provided with a temporary turnaround area which shall be
designed considering traffic usage, maintenance, and removal.
3. Alternative design solutions, such as a close (first preference), or a loop road cul -de-sac (second
preference) are preferable to a typical cul-de-sac.
4. Cul-de-sacs shall have a minimum right-of-way radius of 50 feet and minimum paved radius of 40
feet. When ample radii space exists, cul-de-sacs shall contain a central planted median.
5. Whenever cul-de-sac roads are created, at least one pedestrian access easement shall be
provided, to the extent practicable, between each cul-de-sac head or road turnaround and the
sidewalk system of the closest adjacent road or pedestrian pathway. The access easement shall
be direct with a minimum width of 12 feet.
E. Gated Streets: New gated streets are not encouraged prohibited with the following exceptions.
However
1.Exceptions: they may be permitted, aAt the discretion of the Metropolitan Planning Commission, in
T3-S zoning districts where connection to the existing street grid is not practicable due to topography
or existing surrounding conditions.
2. They may be permitted by the applicable Design Review Authority At the discretion of the Planning
Commission when the access proposed to be gated is an alley or rear lane and is not the primary
building frontage.
F. Street Naming and Renaming: New street names and street renaming are subject to the requirements
of S.C. Code 6-29-1200. Proposed street names and number systems will shall be reviewed by and
subject to the approval of the aAdministrator and the Beaufort County Emergency Management
Department. No duplicate/similar names are allowed, as determined by these agencies.
G. Reserved Strips Prohibited: Reserved strips at the terminus of a new street shall be prohibited.
7.2.3 LOT ACCESS STANDARDS
A. Applicability: Any development that requires an one or more access points (rear alley/lane or
driveway) for purposes of ingress and/or egress shall be subject to the provisions of this section. All
new accesses access points must be approved by the appropriate permitting authority. Access points
may not be installed on undeveloped property less than 2 acres.
113
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 10 of 48
B. Maximum Number: For single-family and two- and three-family dwellings, only one driveway shall be
permitted per lot. In T3-S, circular driveways may be permitted on lots greater than 100 feet in width,
where no sidewalk exists. Driveways may only be installed when rear access is not possible or required.
For double frontage lots, one curb cut per street may be permitted. For all other building types, the
maximum number of driveways allowed for any property is outlined in the table below.
FRONTAGE
WIDTH
MAXIMUM PERMITTED DRIVEWAYS ACCESS POINTS (CURB CUTS)
PER STREET FRONTAGE
Less than up to
150 feet
1
150 feet or more 2 - Additional driveways access points (in excess of 2) shall be permitted
only after the applicant successfully demonstrates the necessity for such
additional access pointsdriveways, as determined by the appropriate
Ddesign rReview Bbody. Along arterial roads and thoroughfares, such
additional driveways access points shall be "right-in, right-out" driveways
only.
C. Location and Spacing:
1. Street Intersection: No curb cut or other access point shall be located closer than:
a. 20 feet from the intersecting point of the 2 street right-of-way property lines involved (or
such lines extended in case of a rounded corner);
b. 25 feet from the intersection of the 2 curb lines involved (or such lines extended in case of
a rounded corner), whichever is the least restrictive.
2. Spacing: All access points shall have a minimum separation from certain features as follows:
FEATURE MINIMUM SEPARATION1
Adjacent Property Line (does not apply to
shared or joint-use driveways)
0 ft
Another Curb Cut (driveway or street
intersection) on all roads except Major
Thoroughfares
25 ft
Another Curb Cut (driveway or street
intersection) on Major Thoroughfares —
defined as streets with the Street Section
designation of Major Thoroughfare, or the
Robert Smalls Parkway, Sea Island
Parkway/Lady's Island Drive, or Boundary
Street Specific Street Section — Another
Curb Cut (driveway or street intersection)
Depends on Pposted sSpeed Llimit as follows:
< 35 mph 100 ft
35 mph 200 ft
40 mph 250 ft
45 mph2 300 ft
50 mph2 400 ft
55+ mph2 500 ft
< 35 mph 100 ft
35 mph 200 ft
40 mph 250 ft
114
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 11 of 48
45 mph2 300 ft
50 mph2 400 ft
55+ mph2 500 ft
1 Minimum separation is measured from centerline
2 On Robert Smalls Parkway (Hwy 170) west of Parris Island Gateway, a minimum of 500 ft.
separation distance is required
3. Corner Lots: Access points on corner lots shall be from the side (or secondary) street, unless a
shared curb cut on the main thoroughfare is existing or proposed.
4. Access to Lots from Major Thoroughfares: Driveways serving individual residential lots shall not
have direct access onto streets identified as Major Thoroughfares — as identified on the second
row of the chart in Section 7.2.3 C.2. — unless no alternative means of access, such as alleys or
parallel access roads, exists, and it is unreasonable or impractical to require an alternative means
of access.
5. Shared Access: See Section 5.7.7 C.
6. Rear Access Required/No Front Access: For lots developed in the transect zones of T-3N, T-4, and
T-5 UC, lots, all new access points shall be from a rear alley and/or road, except for lots within
the historic district. Exemptions to allow front loaded access points where connection to the
existing street grid is not practicable due to topography or existing surrounding conditions shall
be at the discretion of the Planning Commission with approval of major subdivisions, and the
Codes Administrator for individual lots.
D. Size:
1. Alleys: Alley pavement width may be a maximum of 24 feet wide for two -way traffic and 16 feet
wide for one-way traffic. For more design standards, see Appendix C.
2. Driveways:
a. Driveways for single-family and 2- and 3-family uses may not exceed 12 feet wide, except in
T3-S district, where they may be a maximum of 20 feet wide.
b. Tandem Parking: Tandem parking is allowed in all zones for all residential uses if:
i. Both tandem parking spaces satisfy the parking requirement of one residential
unit; and
ii. Neither of the tandem parking spaces shall be for required accessible parking
spaces.
c. Driveways to other uses and parking areas shall not exceed 24 feet in width for 2 -way
drives or 12 feet in width for one-way drives, except those with turn lanes required by the
Ccity or SCDOT.
E. Access to Lots from Alleys/Rear Lanes:
1. Specific to T3-N, T4, and T5 districts: Alleys/rear lanes shall be provided along the rear property
lines of lots as follows:
a. In new subdivisions greater than 1 acre, alleys shall be provided for newly created lots that
meet any of the following criteria:
115
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 12 of 48
i. The lots are part of a bBlock fFace with an average lot width of 60 feet or less at
the building setback line (excluding lots on cul-de-sacs).
ii. The lots are arranged around a Common Open Space.
iii. The lots front a collector or arterial road, regardless of the average lot width.
iv. The lots are intended for multi-family dwellings and/or mixed-use buildings.
b. For In infill situations developments, the same standards apply as specified above in the
immediately preceding subsection, but only for developments that include 4 or more
contiguous lots, where one lot is a corner lot. In the Historic District, the standards apply
only to the Beaufort Conservation District; the requirement may be waived at the
discretion of the Historic Review Board.
F. Specific to Commercial Developments and Subdivisions:
1. Out-parcels: Out-parcels for shopping, office, or industrial centers shall be limited to internal
access to the center, unless otherwise approved as part of a master development plan. All
driveways shall be paved from the road to the property line.
2. Abandoned Driveways: Abandoned driveways (i.e., curb cuts that are no longer used for
vehicular access and are physically blocked by structures) shall be closed, and the area shall be
restored to the typical cross section of the right-of-way.
7.2.4 STREET DESIGN STANDARDS
A. Street Section Design: The elements and widths of all proposed streets shall be in conformity with the
appropriate street section designated in the Street Regulating Infrastructure Plans (Section 7.2.1 and
Appendix C).
B. Traffic Control and Signs: The type and location of traffic control devices used on City streets must be
approved by the Administrator or the Administrator’s designee and traffic control on private Streets
shall be included and approved as part of the major subdivision or site plan . Traffic signals should be
used where warranted, but alternate means of traffic control such as roundabouts should be
considered first. When it can be shown that a particular zoning action, master plan, or development
plan impacts the street system to a point that a traffic signal is warranted according to the latest
version of the United States Department of Transportation’s Manual on Uniform Traffic Control
Devices (MUTCD) and approved by the Administrator the Administrator’s designee, , the developer
shall be responsible for all or a portion of the signal installation. Traffic control and street name signs
shall be installed at all street intersections and other appropriate areas as determined by the applicant
and street owner.
C. Sidewalks/Multi-use Paths: Where required per the Street Section by the provisions of in Appendix C,
all sidewalks or multi-use paths must be constructed concurrently with the street, or, if the street is
already constructed, prior to acceptance of any improvements. Exceptions to , or partial waiver of, the
requirement to install a sidewalk may be granted by the Planning Commission if:
1. Alternative pedestrian paths/bikeways have been or will be provided outside of the normal right -
of-way.
2. There are unusual topographic, vegetative, or other natural conditions to the extent would
render that strict adherence to said the requirements would be unreasonable and not consistent
with the purposes and goals of this Code.
116
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 13 of 48
D. Utility Easements: Utility easements which require a width of 8 feet or larger more shall be located in
rear alleys or along the side adjacent to or rear lot lines. Special permission to install utility easements
in other locations may be requested by the utility companies and is subject to approval by the
appropriate dDesign Rreview Bbody.
E. Special Consideration to Protect Protected Resources and other Natural Features: Street layout and
design shall give additional consideration to preserving protected resources and enabling natural areas
to be protected or minimally disturbed. Where streets are built in areas that have protected resources
or natural features, all utilities shall be placed within the street right-of-way and under the street in
order to avoid additional destruction of the natural features.
7.2.5 STREET TREE PLANTING REQUIREMENTS
A. Planting Areas: Planting strips and tree wells shall be established in accordance with the width and
plantings designated in the appropriate Street Section of the Street Regulating Infrastructure Plans
(7.2.1 and Appendix C).
B. Location and Number: Street trees should shall be planted in the location and per the spacing specified
for the corresponding street classification in Appendix C. However, in specific caseswhere it is not
practical due, to due the location of utilities or other site constraints, , the Planning Commission may
allow street trees to may be planted on private property adjacent to the right-of-way.
C. Tree Species: Overstory The species of overstory and understory trees as prescribed in this section
reference Appendix A.2 (Recommended Trees and Shrubs) may be used for street tree planting.
D. Minimum Tree Size: At the time of planting, young trees should be 2.5 inch caliper, with the lower side
of the crown a minimum of 6 feet above grade to avoid hazards to pedestrians.
7.3: STREET ENGINEERING STANDARDS
7.3.1 STREET DESIGN, CERTIFICATION, AND CONSTRUCTION SPECIFICATIONS
A. Design Drawings and Certification: Professional engineers, registered in the sState of South Carolina,
shall prepare plans, profiles, cross sections, and specifications for all subdivision roads and streets. The
engineers shall certify that the roads/streets are built to comply with the approved plans and
specifications. Cross sections shall be developed every 100 feet at intersections and break points in
grade. Cross sections shall show the complete rights-of-way including travel lanes, shoulders, ditches,
curb and gutter, and sidewalks and utility locations, as applicable.
B. Construction Specifications for Paved Streets: Street construction specifications for paved streets shall
comply be in compliance with the South Carolina Department of Transportation Standards.
7.3.2 TRAFFIC IMPACT ANALYSIS
A. Applicability: A "tTraffic iImpact aAnalysis" (TIA) shall be required for any development that is shown to generate
more than 50 trips during the peak hour on the adjacent street (s)— in the most recent Institute of
Transportation Engineers (ITE) Trip Generation Manual or any alternative approved at the discretion of the
Planning Commission or the TRC, or by the engineering department. — to generate more than 50 trips during the
peak hour on the adjacent street(s).
1. A second phase, second subdivision, or addition that generates traffic beyond this threshold when taken as
a whole shall also require a TIA, even though that development may does not qualify on its own.
117
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 14 of 48
2. A use shall not be changed without conducting a new TIA if the new use would generate traffic beyond the
50 trips during peak hour threshold referenced above. The administratorPlanning Commission or TRC may
waive this requirement in unusual circumstances.
3. Exception: Development — except for Educational Facilities with greater than 100 students — on lots
included in the Boundary Street Master Plan, adopted on August 28, 2006, and lots in the area bounded by
Calhoun Street, Carteret Street, Bay Street, and Ribaut Road, and lots zoned Limited Industrial (LI), shall not
be subject to the requirements of this section. This exception does not apply to Educational Facilities with
greater than 100 students.
B. Traffic Access Management Analysis: As part of the TIA process, the proposed development shall have an "access
analysis" undertaken by the administrator to ensure that sufficient access to all proposed developments and
subdivisions is achieved.
1. The standards in the South Carolina Department of Transportation's "Access and Roadside Management
Standards Manual" (a.k.a. ARMS Manual) shall serve as a guide for this analysis, which shall include
identification of the following:
a. Access improvements, such as deceleration lanes, that the applicant must install at his or her the
Applicant’s own expense;, such as deceleration lanes;
b. The location of any curb cuts based on, but not limited to, sight distances, existing roadway
infrastructure, opposing driveways locations, and shared access;
c. Requirements for adequate driveway design, including, but not limited to, turning radius and stacking
distance.
2. The access requirements approved by the Planning Commission or the TRCadministrator shall be
incorporated on development or subdivision plans prior to their approval.
3. If an applicant is required to provide site-related traffic improvements, the cost of implementing such
improvements shall be borne by the applicant, and no such costs shall be eligible for a credit or offset from
any transportation impact fees unless specifically permitted by the Development Fee Procedures -as stated
in the Beaufort County Code of Ordinances, Chapter 82, Article VII or most recent version.
C. Traffic Impact Analysis Plan Preparation:
1. The TIA shall be conducted by an engineer registered in South Carolina who is experienced in the conduct of
traffic analysis.
2. Prior to beginning the TIA, the applicant shall supply the city CItywith the following:
a. A written narrative describing the proposed land use(s), size, and projected opening date of the
project and all subsequent phases.
b. A site location map showing surrounding development within a one-half mile radius of the property
under development consideration.
c. A proposed site plan or preliminary subdivision plat illustrating access to public or private roads and
connectivity to other contiguous developments.
3. Prior to beginning the TIA, the applicant shall receive, in writing, the parameters to be followed in the study,
including the directional split of driveway traffic, trip distribution, background traffic growth rate, previously
approved but not completed projects, and the intersections to be analyzed, along with any associated
turning movement counts that are available or discussed and approved by the TRC.
118
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 15 of 48
4. To review the TIA, the Planning Commission and TRC will utilizerequire current updated trip generation
information, available information on land use, travel patterns, and traffic conditions, and shall consult with
the SCDOT.
D. Plan Contents:
Background information Requirement
List of all nonexistent transportation improvements
assumed in the analysis
Required
Map of site location, description of the parcel, general
terrain features, and location within the
jurisdiction and region.
Required
Description of geographic scope/ limits of study area.
Within half mile/2640 feet of site and any roadway on
which 50 or more of the new peak hour vehicle
trips generated by the proposal are distributed.
At the discretion of the TRC or Planning Commission,
a larger study area may be required.
Plan at an engineering scale of the existing and
proposed site uses.
Required
Description and map or diagram of nearby uses,
including parcel zoning.
Required
Description and map or diagram of existing roadways. Required
Description and map or diagram of programmed
improvements to roadways, intersections, and
other transportation facilities within the study
area.
Required
Analysis of Existing Conditions
119
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 16 of 48
Collected daily and peak hour of the generator traffic
volumes, tabulated and presented on diagrams
with counts provided in an appendix.
Required
Analyses for intersections and roadways identified by
SCDOT. Delay and Level of Service (LOS) are
tabulated and LOS is presented on diagrams for
each lane group.
Required
When the type of development proposed would
indicate significant potential for walking, bike or
transit trips either on - or off - site, analyses of
pedestrian and bicycle facilities, and bus route
or routes and segment or segments, tabulated
and presented on diagrams, if facilities or routes
exist.
Within half mile/2640 feet of site and any roadway on
which 50 or more of the new peak hour vehicle
trips generated by the proposal are distributed –
At the discretion of the TRC or Planning Commission, a
larger study area may be required.
Incorporation of all Traffic Impact Analysis studies and
Trip Generation from approved developments
or vested unbuilt developments within mile
radius at time of proposal.
Required (submitted for any jurisdiction,
including the Town of Port Royal, and County of
Beaufort)
Speed Study If requested by City
Crash history near site If requested by City
Sight distance If requested by City
Analysis of Future Conditions without Development
Description of and justification for the method and
assumptions used to forecast future traffic
volumes.
Required
120
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 17 of 48
Analyses for intersections and roadways as identified
by SCDOT. Delay and Level of Service (LOS) are
tabulated and LOS is presented on diagrams for
each lane group.
Required
When the type of development proposed would
indicate significant potential for walking, bike or
transit trips either on - or off - site, analyses of
pedestrian and bicycle facilities, and bus route
or routes and segment or segments tabulated
and presented on diagrams, if facilities or routes
exist or are planned.
Within half mile/2640 feet of site and any roadway on
which 50 or more of the new peak hour vehicle
trips generated by the proposal are distributed.
At the discretion of the TRC or Planning Commission, a
larger study area may be required.
Trip Generation
Site trip generation, with tabulated data, broken out
by analysis year for multi- phase developments,
and including justification for deviations from
ITE rates, if appropriate.
Required
Description and justification of internal capture
reductions for mixed use developments and
pass-by trip reductions, if appropriate, including
table of calculations used.
Required
1. Phased Developments: All phases of a development are subject to review, and all traffic plans for
the entire development shall be integrated with the overall traffic analysis. A TIA for a specific
phase of development shall be applicable to the phase of development under imme diate review.
However, each phase of development shall expand and provide detailed analysis at the
development plan stage beyond the estimates provided for at the concept plan or master plan
stage.
2. Infrastructure Analysis: The adequacy of the roads that the development will be accessed from
shall be assessed in the TIA. Recommendations for improvements to these roads shall be made.
The relative share of the capacity created shall be broken down as follows: development share,
other developments' share, any existing overcapacity, and capacity available for future growth.
3. Required Elements of the TIA:
121
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 18 of 48
a. A site plan or subdivision plat identifying access pointses to and from existing or proposed
streets and intersections, along with all opposing intersections across adjacent streets.
b. Description of the proposed development, including the type and intensity of proposed
land use(s) including, but not limited to: the number of residential units by type, the
number of existing and proposed lots, the type of proposed nonresidential devel opment
and the amount of such development measured by gross floor area or other appropriate
unit of measurement, the general size and type of accessory development or facilities, and,
for nonresidential development, adequate information to identify the app ropriate land use
category for trip generation.
c. Projected vehicular trips to and from the completed development during a.m. and p.m.
peak hour — trip rates shall be taken from ITE Manual or alternatively, an applicant may
elect to perform, at his own expense, a "trip generation study" which may be submitted as
part of the traffic impact analysis TIA plan. Such The trip generation study shall be subject
to the review and verification of the TRC and engineer. For proposed uses not specifically
listed in the ITE Manual, and for which a trip generation study has not been performed, the
designated engineer(s) shall determine the most appropriate trip generation rate. The TRC
shall make the determination of the appropriate trip generation rate, from whatever the
source. The percentage of pass-by trips, if used in the plan, shall be included, as well as the
source of this information.
d. A written narrative setting forth the assumptions upon which any projection was made in
developing the traffic impact analysis TIA plan shall be included in the analysis. If the
assumptions are derived from the ITE Manual, the materials shall be referenced and
properly cited. If the assumptions are not from the ITE Manual, appropriate excerpts from
other reliable transportation planning resources shall be included in the study, and reasons
underlying the assumptions shall be stated in the narrative.
e. The TIA shall review access to the site. The adequacy of the entrance design shall be
evaluatedevaluated, and recommendations made on acceleration and deceleration lanes,
left-turn lanes, or signalizations shall be part of the TIA. Educational facilities shall include
pick-up and drop-off plans and analysis of the impact on the surrounding streets and
intersections.
f. The TIA shall review the number and types of curb cuts that are permitted. In particular,
the TIA shall assess the connection of the property to adjoining properties. Where the use,
scale of development, or size of adjoining properties is such that trip s would be anticipated
between the proposed use and the other properties, the TIA shall make recommendation
on interconnections. The TIA shall recommend interconnections to provide a smooth flow
of traffic between uses along arterials and collector roads to ensure that as much traffic as
possible uses secondary roads, rather than major roads, for short trips.
g. The TIA shall be based on intersection analysis procedures for signalized intersections as
identified in the most current edition of the tTransportation Rresearch Bboard's hHighway
cCapacity mManual, and/or the last update that analyszes and emulates these procedures
by means of computer software, if available. The results of any required analysis/computer
122
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 19 of 48
analysis shall, at a minimum, indicate compliance or variance from the Traffic Service Level
Goals (Section 7.3.32 M).
h. The intersections that must be analyzed in the study are identified as:
i. Any intersection that serves as a development's point of access. This will
include intersections of public and/or private roads with major arterials, and
driveways offering direct access.
ii. The first major intersection as identified by the city engineer on both side of
the development's point of access.
iii. Other intersections on major arterials if development generates more than 50
a.m. or p.m. peak hour trips to that intersection, or if the intersection's level of
service or demand is significantly impacted by site related traffic.
iv. Unsignalized intersections and access drives — these shall be considered if
development impacts are anticipated. The plan must include the results of an
analysis of the operating conditions of critical intersections and/or all
intersections identified in the concept plan. The analysis shall reflect the
projected condition of these intersections and movements, based on the
scheduled opening date of the development. Other phases of the development,
if they can be reasonably determined, shall be considered as well.
E. Mitigation Plan Required: If the initial analysis indicates that the city's adopted Traffic Service Level
Goals (Section 7.3.2 M.) will be not be met, a mitigation plan must be prepared, based on additional
analysis. The mitigation plan must show how the city's Traffic Service Level Goals are addressed as
mitigated. Applicants will be responsible for mitigating the traffic impacts at any intersection affected
by a proposed development.
1. If a traffic signal is recommended, the TIA shall provide information that:
a. Clearly indicates the need for a traffic signal.
b. Assesses the ability of other existing, planned, or proposed public roads to accommodate
the new traffic at a location other than the main highway in the vicinity of the proposed
development.
c. Describes in detail how a specific development will affect the study area transportation
system.
d. Provides documentation of appropriate South Carolina Manual of Uniform Traffic Control
Devices signal warrant satisfaction.
e. Gives design geometry of the private road that is consistent with that of public road
intersections, including curbs, appropriate lane widths, pavement markings, and vertical
alignment. Other roadway factors to be considered include, but are not limited to, speed,
type of highway, grades, sight distance, existing level of service, conflicting accesses, and
the effect of future traffic signal systems.
123
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 20 of 48
f. Provides an approach-throat length for the road to ensure the movement of vehicles
entering the site will not be impeded by conditions within the development, and ensure
that all signal-spacing requirements are adequately met.
2. The desirable spacing of signalized intersections on principal arterials is the SCDOT, county, or
Ccity standards. The TRC may recommend to SCDOT the installation of a traffic signal at locations
where, using SCDOT standards, spacing is inappropriate due to topography, existing or proposed
road layout, documented accident history, unique physical constra ints, existing or proposed land
use patterns, or requirements to achieve specific objectives for highway segment designations, as
shown in any locally adopted land use or transportation plan, approved Ccity or county
transportation plan, or approved transportation policy.
3. Signal spacing concerns may be ameliorated in the following ways:
a. A proposed private road that may otherwise be considered for the installation of a traffic
signal may be replaced by an on-site route or a frontage road that directs traffic to or from
a nearby public road.
b. A private road that is being considered for traffic signal installation may be required to
connect to the existing or planned local road system to allow uses of surrounding
properties.
c. An existing or proposed intersection may be relocated.
d. A shared private road may be required to serve the needs of the multiple properties.
4. A traffic signal progression analysis is required if the proposed location is closer than the SCDOT
standards, given the presence of existing signals or the possible existence of identified future
signals proposed as part of a highway signal system. A traffic signal progression analysis for all
new, revised, or planned traffic signal systems on state highways shall be performed using
methods, models, computer software, data sources, roadway segment length, and assumptions
approved by the TRC. The roadway segment, analyzed to the extent possible, shall include all
traffic signals in the existing or future traffic signal system. The progression analysis shall:
a. Demonstrate acceptable existing and future traffic signal systems operation that may
include the morning peak, evening peak, midday period, and other appropriate time period
during any day of the week, adjusted for peak season, for cycle lengths and tra vel speeds
approved by the TRC.
b. Provide for a progressed traffic band speed no more than 5 mph (8 km/h) below the
existing posted speed for both directions of travel during the off-peak periods, nor more
than 10 mph (16 km/h) below the existing posted speed during peak periods. Approv al by
the TRC is required where speeds deviate more than the above.
c. Demonstrate that sufficient vehicle storage is available at all locations within the traffic
signal system without encroaching on the functional boundaries of adjacent lanes and
signalized intersections. The functional boundary of an intersection shall be determined in
discussion with the TRC, based on existing or projected conditions.
d. Provide a common cycle length with adequate pedestrian crossing times at all signalized
intersections.
124
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 21 of 48
e. Provide a progression bandwidth as large as that required, or as presently exists, for
through traffic on the federal or state highway at the most critical intersection within the
roadway segment. The most critical intersection is the intersection carry ing the highest
through volume per lane.
5. The traffic signal progression analysis shall be supplemented by a traffic engineering report that
also considers highway capacity and safety of the roadway segment under consideration. Traffic
volumes, intersection geometry, and lane balance, considered at all locations, shall be
appropriate for the present and identified future conditions, which are usually considered to
include the year of completion, and 5 years into the future.
F. Summary: A clear and concise summary of recommended improvements that can serve as an
executive summary is required.
G. TIA Review: The TRC shall review all TIAs as part of the applicable Design Review phase — see Section
9.8 and 9.9 for appropriate process. Final TIAs shall be approved prior to the applicant submitting a
Project Permit application (Section 9.5).
H. Application: A TIA shall be submitted to the TRC. Coordination with other entities in the county
government or South Carolina Department of Transportation (SCDOT) shall be the responsibility of the
Ccity.
I. Completeness: The Planning Commission and/or TRCTRC shall determine whether a TIA is complete.
Thorough and complete TIAs are the responsibility of the applicant. Failure by the applicant to provide
a complete TIA may result in review delays for their its plat or plan.
J. Action on TIA: The TRC must first approve the TIA in regard to completeness and accuracy. Following
review of the required impact analysis plan, TRC shall recommend to the Planning Commission action
as follows:
1. Approval of the TIA as submitted;
2. Approval of the TIA with conditions or modifications as part of the development review and
approval process. An acceptable TIA with traffic mitigation measures may include the reduction
of the density or intensity of the proposed development, phasing of the proposed development
to coincide with state and/or county-programmed transportation improvements, applicant-
provided transportation improvements, fees in lieu of construction, or any other reasonable
measures to ensure that the adopted traffic service-level goals are met. If mitigation is required,
it shall be required as a condition of any approval from the city.
K. Timing of Implementation: If a traffic mitigation program is part of an approved TIA, the developer
may be required to place a performance bond on all traffic mitigation improvements required as a
result of his the project. This requirement may arise if the timing of the improvements needs to be
synchronized with other scheduled improvements anticipated for the area.
L. Responsibility for Costs of Improvements: The costs of implementation of an approved mitigation
program shall be the responsibility of the applicant. No certificates of zoning compliance or building
permits shall be issued unless provisions of the TIA are met.
M. Traffic Service Level Goals: The average stop time delay in seconds per vehicle for each intersection
determined to be critical to the TIA for the proposed development shall be compared to the cCity's
125
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 22 of 48
adopted traffic service level goal of "D" for the average delay for all vehicles at any signalized
intersection during the a.m. and p.m. peak hours.
7.4: COMMUNITY GREEN SPACE AND COMMUNITY OPEN SPACE
7.4.1 PURPOSE AND INTENT
A. Intent: Community Green Space and Community Open Space is are intended for the use and
enjoyment of a development's residents, employees, or users. These spaces serve to preserve natural
areas, ensure access to open areas and recreation, reduce the heat island effect, enhance stormwater
quality, and provide community health benefits. Community Green Space and Community Open Spaces
are not, by definition, required to be deeded to be granted via easement to any public entity or
municipality. See Section 7.4.5 for ownership information.
B. Purpose: The purpose of this section is to provide a set of Community Green Space and Community
Open Space types and their associated standards to use within all districts. Community Green Space
and Community Open Space types in this section are distinct from those areas that are environmentally
sensitive and must be otherwise protected as regulated through Article Chapter 8 (Environmental
Protection.)
C. Applicability: See Section 7.1.2.
D. Community Green Space Definition: an area of grass, trees, parks, trails or multi-use pathways, or other
vegetation set apart for recreational or aesthetic purposes in a development. It can be privately or publicly
owned.
E. Community Open Space Definition: Open space is land or water that is undeveloped and not used for
residential, commercial, industrial, or institutional purposes. It can be privately or publicly owned, and can include
areas like forests, farms, parks, and coastal lands.
7.4.2 COMMUNITY GREEN SPACE AND COMMUNITY OPEN SPACE REQUIREMENT
A. Minimum Requirements: Development in all districts shall preserve the minimum amounts of
Community Green Space and Open Space as identified below:
OPEN/CIVIC SPACE REQUIREMENT
SIZE T1 T3-S T3-N T4-HN T4-N T5-DC T5-UC RMX IC LI
Less 3-
than 10
no
50%mi
nimum
20% 15% Exempt 10% exempt 10% 10% 15%
126
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 23 of 48
acress
10
acres—
15
acres
50% 20% 15% exemp
t
10% exemp
t
exem
pt10%
exempt1
5%
exempt
20%
exempt
15
acres—
40
acres
50% 20% 15% n/a 105% exemp
t
exem
pt
15%
exempt
20%
exempt
20%
exempt
Greater
than
40
acres
50% 25% 20% n/a 520%% exemp
t
exem
pt20%
exempt
25%
exempt
25%
exempt
1 Each Manufactured Home Park shall have a minimum total area of 2,500 square feet set aside for common
recreational open space, or at least 100 square feet of space for each mobile home lot, whichever is greater.
2 Specific to TND Overlay Projects: The open space requirement may be calculated comprehensively or by specific
Transect zones. The requirements of 2.8.3.G.2.c E. must be met in addition to the requirements of this table.
3. For properties less than 3 acres, community green space and community open space shall be at the discretion of the approving authority
(i.e.) Codes Administrator or Planning Commission.
B. Areas to be Included in Community Green Space and Community Open Space Calculations: The
features and areas identified in Section 7.4.3 shall be credited towards the open space requirements
for the purposes of complying with this Chapter article.
C. Areas not to be Included in Community Green Space and Community Open Space Calculations: The
following areas shall not be counted toward open space requirements:
1. Private yards which are not subject to an open space or conservation easement.
2. Public road rights-of-way or private street easements, including sidewalks located within those
rights-of-way or easements.
3. Open parking areas and driveways for dwellings.
4. Land covered by structures not designated for active recreational uses.
5. Designated outdoor storage areas.
7.4.3 COMMUNITY GREEN SPACE AND COMMUNITY OPEN SPACE TYPES
The majority of Community Green Space and Community Open Space shall conform to one of the 8 types in the
table below. If 75% or more of the types listed below is utilized for required open space, a 20% increase in number
of dwelling units is permitted.
CIVIC/
OPEN
SPACE TYPE
DIAGRAM DESCRIPTION PERMITTED
DISTRICTS
SERVICE AREA/
SIZE
CHARACTER TYPICAL
FACILITIES
127
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 24 of 48
Regional
Park/Natural
Preserve
A natural
preserve that
is available
for
unstructured
recreation. It
may contain
small civic
buildings and
areas of
structured
activity, but is
primarily left
natural.
These areas
may include
forests as
well as
wetlands and
regional
retention
areas if they
are treated as
amenities
(e.g. Port
Royal's
Cypress
Wetlands).
T1 Regional
Min: 200
acres*
Max: None
*Natural
preserves with
no structured
activity have
no minimum
size.
Frontage:
Independent
Disposition:
Natural,
formal or
informal
Passive and
active
recreation,
drinking
fountains,
Community
facility <
7,500 gross
square feet,
paths and
trails
Sport
Complex
An open
space that
consolidates
heavily
programmed
athletic fields
and
associated
facilities.
T1, IC, RMX Regional
Min: 25 acres
Max: None
Frontage:
Independent
Disposition:
Formal or
informal
Passive and
active
recreation,
drinking
fountains,
community
facility <
7,500 gross
square feet,
paths and
trails
Community
Park
An open
space that is
available for
unstructured
recreation
and a limited
amount of
T3, T4, T5,
RMX, IC
Multiple
Neighborhoods
Min: 8 acres
Max: None
Frontage:
Independent
Disposition:
Informal
Passive and
active
recreation,
drinking
fountains,
community
facility <
128
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 25 of 48
structured
recreation. It
may contain a
limited
amount of
athletic fields.
5,000 gross
square feet,
paths and
trails
Greenway
A linear open
space that
may follow
natural
corridors, a
greenway
provides
unstructured
and limited
amounts of
structured
recreation.
T1, T3, T4,
T5, RMX, IC
Multiple
Neighborhoods
Min: 8 acres or
1 mile
Max: None
Frontage:
Independent
or building
Disposition:
Natural or
informal
Passive and
active
recreation,
drinking
fountains,
community
facility <
5,000 gross
square feet,
paths and
trails
Square/Green
An open
space that is
available for
civic
purposes,
unstructured,
and limited
amounts of
structured
recreation. It
can be
located along
waterfronts.
T3, T4, T5,
RMX, IC
Neighborhood
Min: 0.5 acres
Max: 5 acres
Frontage:
Building
Disposition:
Formal
Passive and
active
(unstructured
or
structured)
recreation,
accessory
structure,
drinking
fountains,
community
facility <
5,000 gross
square feet,
paths and
trails
Plaza
A formal
open space
available for
civic purposes
and
commercial
activities, a
plaza is
typically
hardscaped
and can be
T4, T5,
RMX, IC
Neighborhood
Min: 0.5 acres
Max: 2.5 acres
Frontage:
Building
Disposition:
Formal
Passive
recreation,
accessory
structure,
drinking
fountains,
paths and
trails
129
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 26 of 48
located along
waterfronts.
Pocket
Park/Pocket
Plaza
An open
space that is
available for
informal
activities in
close
proximity to
neighborhood
residences.
Pocket plazas
are usually
paved.
T3, T4, T5,
IC, RMX
Neighborhood
Min: 4,000
square feet
Max: 0.5 acre
Frontage:
Building
Disposition:
Formal or
informal
Passive
recreation,
accessory
structure,
drinking
fountains,
paths and
trails
Playground
An open
space
designed and
equipped for
the
recreation of
children. A
playground
may be
fenced and
may include
an open
shelter.
Playgrounds
may be
included
within other
civic spaces.
T3, T4, T5,
IC, RMX
Neighborhood
Min: None
Max: None
Frontage:
Independent
or building
Disposition:
Formal or
informal
Accessory
structure,
drinking
fountains,
paths and
trails
Notes:
1. The illustration and description of each civic space type is illustrative in nature and not regulatory.
2. The Permitted Districts may be modified per a plan if the project is utilizing the Traditional Neighborhood
Development Floating Overlay District (Section 2.8.3).
The following provisions apply to the 8 Community Green Space and Community Open Space Types listed in the
table:
A. Playgrounds and Community Gardens: These may be incorporated into any of the other Community
Green Space and Community Open Space types - except Natural Preserve - or may stand alone.
B. Waterfront: When Community Green Space and Community Open Space is required, per Section 7.4.2,
developments that contain waterfront access should include some type of common access to at least
25% of the waterfront. This counts towards the Community Green Space and Community Open Space
requirement. When open space is required, for every 10% of the waterfront that is allocated for public
130
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 27 of 48
access, a 5% increase in number of dwelling units shall be permitted, up to a maximum of a 20%
increase.
C. Illustrative Standards: The columns titled "Diagram," "Description," and "Typical Facilities" of the table
of Community Green Space and Community Open Space Types are illustrative only.
D. Regulatory Standards: The following elements shall be regulatory:
1. Service Area: Describes how the space relates to the city as a whole and the area that will be
served by the Community Green Space and Community Open Space.
2. Size: The permitted size for each Community Green Space and Community Open Space.
3. Frontage: The relationship along property lines of a Community Green Space and Community
Open Space to adjacent buildings or lots.
a. Building: Community Green Space and Community Open Spaces that are listed as having a
"building" frontage shall have the fronts of buildings, either attached to the park or across
a street, facing onto the space for a minimum of 75% of the perimeter.
b. Independent: Community Green Space and Community Open Spaces that are listed as
having an "independent" frontage shall have the fronts of buildings, either attached to the
park or across a street, facing onto the space to the maximum extent possible, but may
have the side or rear of a building or lot front onto the space. The side or rear of a building
or lot fronting onto the Community Green Space and Community Open Space shall be
designed with a secondary frontage and entrance along the space.
4. Disposition: The character of the design of the Community Green Space and Community Open
Space.
a. Natural: Civic spaces with natural character are designed in a natural manner with no
formal arrangement of elements.
b. Formal: Civic spaces with a formal character have a more rigid layout that follows
geometric forms and have trees and other elements arranged in formal patterns.
c. Informal: Civic spaces with an informal character have a mix of formal and natural
characteristics.
5. Food Production: Community Gardens and other Community Green Space and Community Open
Spaces may be used to grow food. See Section 8.54.3 for specifications and requirements.
7.4.4 DESIGN OF COMMUNITY GREEN SPACE AND COMMUNITY OPEN SPACES
A. Design Standards for Community Green Space and Community Open Space: Land used as Community
Green Space and Open Space shall meet the following design standards:
1. Location:
a. Where relevant and appropriate, the land shall be located so as to be readily accessible and
usable by residents and users of the development. To the maximum extent practicable, a
portion of the open space shall provide focal points for the development.
b. Common space set aside for children's play areas and other recreational activities shall be
clearly visible from the dwelling units on the site.
c. The land shall, to the maximum extent practicable, be located to adjoin, extend, and
enlarge any open areas, trails, parks, or other open space resources that exist or are
planned within or adjacent to the development.
131
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 28 of 48
2. Provision in Multi-Phase Developments: In multi-phase developments, open space Manuals may
be calculated either by phases, or by collectively looking at the development s as a whole.
B. Accessory Structure Standards: All accessory structures within parks and open spaces — including, but
not limited to, restrooms, open-air pavilions, gazebos, picnic shelters, and outdoor theaters — shall not
be subject to the physical requirements of the building form or siting standar ds in Article 2 Chapter 2
(Map and Districts). They shall be designed to be consistent with the character of the district in which
they are located. Such consistency may require accessory structures to maintain building setbacks,
frontage, massing, disposition, and character similar to adjacent development as determined by the
administrator.
7.4.5 OWNERSHIP AND MAINTENANCE OF COMMUNITY GREEN SPACE AND COMMUNITY
OPEN SPACE
A. Open space areas or other community facilities shall be preserved and maintained in accordance with
the approved:
1. Development Design, in accordance with Section 9.8;
2. Special Exception, in accordance with Section 9.13; or
3. Subdivision, in accordance with Section 9.9, whichever is appropriate.
B. Provision must be made by the property owner to ensure preservation and long term maintenance and
management of Community Green Space and Community Open Spaces through one of the following
mechanisms:
1. Conveyance of the land to a property owners' or homeowners' association that holds the land in
common ownership and will be responsible for managing and maintaining it for its intended
purposes.
2. Conveyance of the land to a third-party beneficiary, such as a nonprofit environmental or civic
organization, that is organized for, capable of, and willing to accept responsibility for managing
and maintaining the land for its intended purpose.
3. Dedication of the land to the city or other appropriate public agency that is organized for,
capable of, and willing to accept responsibility for managing and maintaining the land for its
intended purposes.
C. All methods utilizing private ownership shall require deed restrictions, covenants, or other legal
instruments that ensure continued use of the land and facilities for their intended uses, and provide for
the continued and effective management, operation, and maintenance of the land and facilities.
D. Failure to maintain Community Green Space and Community Open Space areas or other community
facilities shall be a violation of this Code subject to the remedies and penalties in Article 12 (Violations
and Enforcement).
E. If the owner of an Community Green Space and/or Community Open Space fails to maintain it in
reasonable condition, and in accordance with approved plans, and fails to correct deficiencies cited by
the city, the city shall have the authority to correct the deficiencies per the City's Code of Ordinances at
the owners expense., Section 6-2003 (or equivalent Health and Sanitation section of any updated Code
of Ordinances).
132
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 29 of 48
7.5: SUBDIVISION AND SITE PLAN STANDARDS
7.5.1 General provisions
The provisions of this Section shall apply to any and all subdivision of land, or site plan within
the municipal boundaries of the City, unless expressly and specifically exempted or provided
otherwise in this Code. No development shall be undertaken without prior approval or
authorization pursuant to the terms of this Code. All development shall comply with the
applicable terms, conditions, requirements, standards and procedures established in this
Section and the Code. The submittal of an application for approval pursuant to the provisions of
these Subdivision Regulations constitutes consent to, and agreement to comply with all of its
applicable provisions.
This Section establishes procedural and substantive rules for obtaining the necessary approval
to develop land and construct buildings and structures. Development applications will be
reviewed for compliance with the City’s Comprehensive Plan, Civic Master Plan, Beaufort
Preservation Manual, and this Code.
Scheduling of the review of development applications before Staff, TRC, the Planning
Commission or City Council is at the discretion of the City. Any change to a development
application by an Applicant after formal submittal of that application to the City constitutes a
decision by the Applicant that may result in the City deciding to vacate a decision reached
during or following a hearing and/or void the pending application. The City may then
reschedule or cancel the review of the development application at its discretion.
Prior to formal submittal of any subdivision application identified in this Section, the Planning
Department will typically provide to an applicant an individualized submittal checklist indicating
the documents and information needed, quantities of those documents to be submitted, and
the referral agencies that will be involved in the review process. The applicants are responsible
for being fully familiar with all applicable provisions of these Subdivision Regulations. Upon
determination by staff that a submittal constitutes a complete development application, the
City will forward the packets to each referral agency.
7.5.2 Subdivision types and process outlines
Methods of land subdivision. There are two ways to subdivide land based on the magnitude of
scale: Minor Subdivision and Major Subdivision.
A. Minor Subdivisions.
133
ATTACHMENT 2.C. - CHAPTER 7 SUMMARIES + REDLINE
Created: 2023-12-08 08:25:13 [EST]
(Supp. No. 1)
Page 30 of 48
Definition. A Minor Subdivision is a subdivision, or amendment to a subdivision,
which has been previously platted, which includes no additional public right-of-way
dedication, and includes one or more of the following:
1. The boundaries of six or fewer lots are created from one parent tract or lot,
cumulatively and more 3 acres;
2. Any lot line adjustment; and
3. A consolidation of multiple lots into one when a new street or street change is not
involedinvolved.
B. Major Subdivisions.
Definition. A Major Subdivision is a subdivision which includes one or more of the
following:
1. Dedication of public right-of-way, public infrastructure or other public tracts, or a
private road; or
2. The subdivision consists of fiveseven six or more lots or tracts; and,
3. The creation of lots on property which have never previously been platted.
Sketch SketchPCityCity’s CityCity PlanningComission
infrastructureare i. with full dicresion of the Planning Director,Civic MasterCityCity
7.5.3 Sketch Plan
A. Purpose. The Sketch Plan is a conceptual design of the development submitted
with a major subdivision application, that depicts what the applicant envisions for the overall
development, including zoning, transportation, pedestrian network, parks, tree canopy, open
space, and other amenities.
B. Requirements. A Sketch Plan is required for all major subdivisions. Major
proposed changes to any approved preliminary plat, will require a new Sketch Plan approval.
The Sketch Plan will consist of the following required elements:
1. Road plan: The applicant shall provide a preliminary traffic plan that addresses
the following elements:
i. The proposed street network and connectivity to the existing road network