Parks and Recreation Commission — Agenda Packet
Town of Hilton Head Island · Beaufort County · Parks and Recreation Commission · meeting of May 22, 2025 · Agenda packets
Open the original document More from Town of Hilton Head Island
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Town of Hilton Head Island
Parks and Recreation Commission Meeting
Thursday, May 22, 2025, 3:00 PM
1 Town Center Court, Hilton Head Island, SC
Benjamin M. Racusin Council Chambers
1. Call to Order
2. Pledge to the Flag
3. Adoption of the Agenda
4. Approval of the Minutes
a. Regular Meeting Minutes of November 14, 2024
5. Presentations
a. Island Parks and Rec Association Update - Frank Soule, Parks and Rec
Executive Director
b. Fiscal Year 25 Facilities Landscaping Efforts Update - Derrick Coaxum,
Facilities Director
6. Unfinished Business
7. New Business
a. Capital Improvement Plan - Overview of Parks and Pathways Updates to
Discuss the Status of Current Projects Related to Community Parks and
Pathways, Progress, and Any Adjustments to Project Scope or Funding - Jeff
Netzinger, Engineering & Projects Director, and Richard Loudin, Public
Projects Program Manager
8. Public Comment - Non Agenda Items
9. Commission Business
10. Chairman's Report
11. Staff Report
Page 1 of 37
12. Adjournment
FOIA Compliance: Public notification of this meeting has been published, posted, and
distributed in compliance with the South Carolina Freedom of Information Act and the
requirements of the Town of Hilton Head Island.
In accordance with the requirements of Title II of the Americans with Disabilities Act of
1990 ("ADA"), the Town of Hilton Head Island will not discriminate against qualified
individuals with disabilities on the basis of disability in its services, programs, or
activities. Auditory accommodations are available. Any person requiring further
accommodation should contact the Town of Hilton Head Island ADA Coordinator as
soon as possible but no later than 48 hours before the scheduled event.
Municipal Association of South Carolina (MASC) Civility Pledge:
“I pledge to build a stronger and more prosperous community by advocating for civil
engagement, respecting others and their viewpoints, and finding solutions for the
betterment of my city or town.”
Page 2 of 37
Town of Hilton Head Island Parks and Recreation Commission
Meeting Minutes
11/14/2024 Page | 1
Town of Hilton Head Island
PARKS AND RECREATION COMMISSION
MEETING
Thursday, November 14, 2024, 3:30 PM
Minutes
1. Call to Order
This meeting was called to order at 3:30 p.m.
2. Pledge to the Flag
3. Adoption of the Agenda
Chair Zurilla called for a motion to approve the agenda. The agenda was approved
unanimously.
4. Approval of the Minutes
a. Regular Meeting Minutes of September 12, 2024
Chair Zurilla called for approval of the September 12th meeting minutes. The meeting
minutes were approved unanimously.
5. Presentations
a. Island Parks and Rec Association Update - Frank Soule, Parks and Rec Executive
Director
Chair Zurilla introduced Frank Soule from Island Parks and Recreation, who provided
updates on various programs. Senior programs had grown, aided by a successful direct
mail campaign. A new bus service to the center was popular, and day trips filled up
quickly. The public pool has remained busy, especially from 8 to 11 AM, hosting high
school teams and offering swim lessons for second-graders. A dome was set to be
installed the following week for year-round use. Staffing has been a challenge.
Youth soccer was concluding that weekend, while adult soccer was about to begin. The
after-school program serves over 100 kids, and adaptive recreation and fitness classes
have continued to expand. Festivals remained well attended, and cleanliness was
frequently praised.
Vice Chair Parsons inquired about disc golf; Soule noted they lacked permanent access
to the track but had temporary holes in place, with 500 participants in six weeks. Old golf
courses were ideal for permanent setups. Ms. Kristian asked about nature clubs, which
were not yet offered but were in development. Mr. Manesiotis asked about field
conditions, and Soule reported they were in good shape, with team rotations and new
Page 3 of 37
Town of Hilton Head Island Parks and Recreation Commission
Meeting Minutes
11/14/2024 Page | 2
developments aiding maintenance.
6. Unfinished Business
7. New Business
a. Staff Support Update - Jeff Netzinger, Engineering and Projects Director
Jeff Netzinger introduces himself as the new Engineering and Projects Director and
Board Coordinator for the Parks and Recreation Commission.
8. Public Comment - Non Agenda Items
Frank Babel announced his retirement and highlighted the arts magazine brochure. He raised
concerns about the challenge of attracting people to the parks and suggested the Commission
consider birding as a potential draw. He emphasized the need to find ways to increase
community engagement with the parks.
Vice Chair Parsons proposed creating a specialized bike and park map, similar to the existing
historic map, detailing park facilities and available activities. Mr. Babel suggested incorporating
it into social media or the website. Mr. Manesiotis recommended including the history of the
parks.
9. Commission Business
a. Confirm 2025 Meeting Schedule
Chair Zurilla explained that meetings would now be held at 3:00 PM on a bimonthly
schedule with a summer break. The proposal was put to a vote and it passed
unanimously.
b. Commissioner Nominees for ongoing CIP Project Meetings - Richard Loudin, Public
Projects Program Manager
Chair Zurilla introduced Richard Loudin, Public Projects Program Manager, and asked for
volunteers for each project. Mr. Quigg expressed concern about Commissioners serving
as the main liaisons, but Mr. Loudin confirmed that town staff would handle that role.
Mr. Loudin introduced the Pathway Program projects, outlining each one to give the
Commission an overview. Commissioners volunteered for various projects and agreed to
evaluate the process, with the option to revisit it if needed.
10. Chairman's Report
Chair Zurilla acknowledged the staff's efforts in clearing trees along the pathway to improve
the visibility of the park. Vice Chair Parsons suggested adding a bike rack to the location.
11. Staff Report
12. Adjournment
Page 4 of 37
Town of Hilton Head Island Parks and Recreation Commission
Meeting Minutes
11/14/2024 Page | 3
The meeting was adjourned at 4:48 p.m.
The recording of this Meeting can be found on the Town’s website
at www.hiltonheadislandsc.gov
Page 5 of 37
Capital Improvement Program
Parks Program Update
May 22, 2025
Parks and Recreation Commission Meeting
Town of Hilton Head Island
Richard Loudin
Public Projects Program Manager
Page 6 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – PRESENTATION OVERVIEW
Presentation Overview
1. FY 2026 Budget Overview
2. Park Project Updates
a. Barker Field Renovations
b. Chaplin Community Park Renovations
c. Coligny Circle Pocket Park
d. Crossings Park Renovations
e. Fords Shell Ring Improvements
f. Jarvis Creek Park Renovations
g. Mid-Island Tract
h. Patterson Family Park
i. Shelter Cove Community Park
j. Taylor Family Park
k. Chaplin Linear Park with Treehouse
l. Old Schoolhouse Park Improvements
m. Marshland Road Racquet Facility
n. Greens Shell Park Improvements
Park Locations
Page 7 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – FY2026 BUDGET OVERVIEW
Project PM Status FY 25 Budget FY26 Budget FY27
Priority
FY28
Priority
FY29
Priority
FY30
Priority
Barker Field Renovations, Phase 1 SB Construction 1,500,000 Carry
Forward
Barker Field Renovations, Phase 2 & Mitchelville SB Identified X X
Chaplin Community Park Renovations, Phase 1 SB Design 1,907,797 X X X
Chaplin Community Park Renovations, Phase 2 SB Design X X X
Coligny Circle Pocket Park SH Design 500,000 900,000
Crossings Park Renovations, Phase 1 NE Design 5,000,000 1,000,000 X X
Crossings Park Renovations, Phase 2 NE Design 750,000 X X
Crossings Park Renovations, Phase 3 NE Design 250,000 X X X X
Fords Shell Ring Improvements SB Permitting 50,102
Jarvis Creek Park Improvements SB Construction 100,000 X
Mid-Island Tract Park, Phase 1 SH Design 2,500,000 750,000 X X X X
Patterson Family Park SH Design 2,740,583 3,090,583 X
Taylor Family Park SH Design 2,911,416 3,261,416 X
Shelter Cove Community Park Expansion,
Phase 2 SB Design 500,000 X X
Chaplin Linear Park with Treehouse ZM Design 350,000 X X X
Old Schoolhouse Park Improvements NE Design 350,000 750,000 X
Marshland Road Racquet Facility SB Identified X
Greens Shell Park Improvements SH Complete 250,000
Page 8 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – BARKER FIELD RENOVATIONS, PHASE 1
Barker Field Extension Site Improvements Plan (April 2025)
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Renovation of the existing soccer field including improving field drainage,
installation of a new irrigation system, new lighting, bleachers, a new storage
facility, and new fencing.
Beach Fee and Hospitality Tax
Page 9 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CHAPLIN COMMUNITY PARK RENOVATIONS, PHASE 1
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Expansion of parking facility to add approximately 154 parking spaces to
existing northern and southern parking lots.
Page 10 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CHAPLIN COMMUNITY PARK RENOVATIONS, PHASE 2
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Connect northern parking lot to Castnet Drive and add approximately 82 parking
spaces; renovation of soccer fields, tennis courts, and dog park; construction of
new pavilion, multi-use facility with restroom, pickleball courts, and playground.
Page 11 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – COLIGNY CIRCLE POCKET PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Improvements include plaza amenity space, landscaping, and a multi-use
path.
Capital
Page 12 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CROSSINGS PARK RENOVATIONS, PHASE 1
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Construct new pickleball complex to include 18 courts, clubhouse with pro-
shop and restrooms, parking lot, landscaping and pathway connection to
Bristol Sports Area.
Hospitality Tax
Page 13 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CROSSINGS PARK RENOVATIONS, PHASE 2
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Renovation to Bristol Sports Arena with new cover and fencing over arena,
new skate park, and pump track.
Hospitality Tax
Page 14 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CROSSINGS PARK RENOVATIONS, PHASE 3
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.21.24
Project Funding
Project Scope
Construction of 2 new baseball fields, restroom, parking lot and Champions
Plaza; renovation of 3 existing baseball fields, concessions, training facility,
parking lot.
TBD
Page 15 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – FORD SHELL RING IMPROVEMENTS
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
CDBG project; Design and permitting for improvements to supplement
Beaufort's County's construction project
TIF Rev
Page 16 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – JARVIS CREEK PARK IMPROVEMENTS
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Replacement of playground equipment.
TBD
Page 17 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – MID-ISLAND TRACT PARK, PHASE 1
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 11.22
Project Funding
Project Scope
Improvements to stormwater and lagoon systems, pathways, parking lot off
Union Cemetery Road, and restrooms (site stabilization).
Hospitality Tax
Page 18 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – PATTERSON FAMILY PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 12.23
Project Funding
Project Scope
Construction of new Neighborhood Park on Marshland Road providing a
pavilion, lawn area, viewing platform overlooking Broad Creek, pedestrian
connectivity, parking, and other associated site amenities.
Hospitality Tax and Grants
Page 19 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – TAYLOR FAMILY PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 11.23
Project Funding
Project Scope
Construction of new Neighborhood Park on Wild Horse Road providing a
pavilion, lawn area, recreational play amenities, pedestrian connectivity,
parking, and other associated site amenities.
Hospitality Tax and Grant
Page 20 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – SHELTER COVE COMMUNITY PARK EXPANSION,
PHASE 2
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.23
Project Funding
Project Scope
Installation of Best Buddies playground followed by future construction of a
Broad Creek boardwalk and viewing platform and landscaping.
TBD
Page 21 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – CHAPLIN LINEAR PARK WITH TREEHOUSE
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Linear Park including trail head up-fit, pedestrian bridge at Broad Creek inlet,
tree house, and marsh-side trail connection to Singleton Beach Road.
TBD
Page 22 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – OLD SCHOOLHOUSE PARK IMPROVEMENTS
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Landscape & site improvements including ADA parking and sidewalks,
pickleball court replacement, restroom, shade, signage, seating, landscaping,
etc.
TIF Revenue
Page 23 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – MARSHLAND ROAD RACQUET FACILITY
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Renovation of the existing soccer field including improving field drainage,
installation of a new irrigation system, new lighting, bleachers, a new storage
facility, and new fencing.
TBD
Page 24 of 37
Town of Hilton Head Island
PARKS PROGRAM UPDATE – GREENS SHELL PARK IMPROVEMENTS
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Replacement of property line fencing, curb, playground equipment, and
observation decks
State ATAX and TIF Rev
Page 25 of 37
Capital Improvement Program
Beach Program Update
May 22, 2025
Parks and Recreation Commission Meeting
Town of Hilton Head Island
Richard Loudin
Public Projects Program Manager
Page 26 of 37
Town of Hilton Head Island
BEACH PROGRAM UPDATE – FY2026 BUDGET OVERVIEW
Project PM Status FY 25 Budget FY26 Budget FY27
Budget
FY28
Priority
FY29
Priority
FY30
Priority
Islanders Beach Park Improvements NE Design 3,750,000 X
Page 27 of 37
Town of Hilton Head Island
BEACH PROGRAM UPDATE – ISLANDERS BEACH PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.23
Project Funding
Project Scope
Parking area expansion and renovation, building improvements, stormwater
infrastructure improvements, playground equipment replacement,
construction of new pathways, landscaping and signage improvements, and
boardwalk repairs.
TBD
Page 28 of 37
Capital Improvement Program
Facility & Equipment Program Update
May 22, 2025
Parks and Recreation Commission Meeting
Town of Hilton Head Island
Richard Loudin
Public Projects Program Manager
Page 29 of 37
Town of Hilton Head Island
FACILITY & EQUIPMENT PROGRAM UPDATE – FY2026 BUDGET OVERVIEW
Project PM Status FY 25 Budget FY26 Budget FY27
Budget
FY28
Priority
FY29
Priority
FY30
Priority
Mitchelville Freedom Park Improvements SB Permitting 1,054,702 250,000 X
Page 30 of 37
Town of Hilton Head Island
Facility & EQUIPMENT PROGRAM UPDATE – MITCHELVILLE FREEDOM PARK
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: 5.23
Project Funding
Project Scope
Construction of drive and parking improvements to add dedicated parking and
install site electricity to support events.
State ATAX
Page 31 of 37
Capital Improvement Program
Pathway Program Update
May 22, 2025
Parks and Recreation Commission Meeting
Town of Hilton Head Island
Jeff Netzinger
Engineering & Projects Director
Page 32 of 37
Town of Hilton Head Island
PATHWAY PROGRAM UPDATE – FY2026 BUDGET OVERVIEW
Project PM Status FY 25 Budget FY26 Budget FY2Y
Priority
FY28
Priority
FY29
Priority
FY30
Priority
Jonesville Road Pathway
(Western Terminus to Spanish Wells Rd) SB Design 4,500,000 500,000 X X
Dunnagans Alley Pathway
(Wexford Drive to Arrow Road) SB Identified 100,000 250,000 X
William Hilton Parkway Eastbound Pathway
(Village at Wexford to Arrow Road) SB Design 100,000 300,000 X X
South Forest Beach Drive HAWK Signal
( at Marriott’s Grand Ocean Resort) SB Identified X X
Lagoon Road Pathway
(Avocet Road to North Forest Beach Drive) SH Identified X X
Palmetto Parkway Pathway
(Mathews Drive to William Hilton Parkway) NE Identified X X
Spanish Wells Road Pedestrian Bridge NE Identified X
Fish Haul Road
(Baygall Road to Alice Perry Drive) NE Identified X X X
William Hilton Parkway Eastbound Pathway
(Mathews Dr / Folly Field Rd to Shelter Cove Ln) SB Identified 100,000 X
Cross Island Parkway
(Coastal Discovery Museum to Spanish Wells
Rd)
SB Identified X
Muddy Creek Pathway Connection
(Muddy Creek Road to Cross Island Parkway) SH Identified X X
Page 33 of 37
Town of Hilton Head Island
PATHWAY PROGRAM UPDATE – JONESVILLE ROAD PATHWAY
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Construction of new (1.2 mile) pedestrian facility along Jonesville Road
beginning at the western terminus and connecting to the existing multiuse
pathway along Spanish Wells Road.
Sunday Liquor Permit Fee
Page 34 of 37
Town of Hilton Head Island
PATHWAY PROGRAM UPDATE – DUNNAGANS ALLEY PATHWAY
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓ ✓ ✓ ✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Construction of new pedestrian pathway that will provide separation from
traffic by adding green space and trees along Dunnagans Alley from Wexford
Drive to Arrow Road.
Sunday Liquor Permit Fee
Page 35 of 37
Town of Hilton Head Island
PATHWAY PROGRAM UPDATE – WHP EB PATHWAY (WEXFORD DR TO ARROW RD)
Project
Identified
Concept /
Master Plan Survey Design Permitting Bid Phase Under
Construction
Project
Complete
✓
Project Schedule
Project Status
Master Plan Approval Date: N/A
Project Funding
Project Scope
Construction of new pathway from Village at Wexford to Arrow Road.
SC DOT TAP Grant Project.
State ATAX
Page 36 of 37
Capital Improvement Program
Program Updates
May 22, 2025
Parks and Recreation Commission Meeting
Town of Hilton Head Island
Questions ?
Page 37 of 37