SPECIAL MEETING
of
CITY COUNCIL
6:00 p.m., Tuesday, January 6, 2015
A Special Meeting of City Council was held at 6:00 p.m., Tuesday, January 6, 2015 in Council
Chambers of City Hall, 1207 Palm Boulevard, Is le of Palms, South Carolina. Attending the
meeting were Councilmembers Bergwerf, Bettelli, Buckhannon, Carroll, Ferencz, Harrington
and Ward, Mayor Cronin, City Administrator Tucker, Attorney Halversen, Assistant Administrator
Dziuban and Clerk Copeland; a quorum was present to conduct business. Councilmember
Loftus’ absence was excused.
1. Mayor Cronin called the meeting to order and acknowledged that the press and public
have been duly notified of the meeting in accordance with the Freedom of Information Act.
2. Appointment of Members to City Boards, Commissions and Committees
The Mayor noted that the recommended appointments to Boards and Commissions and the
standing committees of Council were included in meeting packets.
MOTION: Mayor Cronin moved to confirm appointments to Boards and
Committees and standing committees of Council as submitted; Councilmember
Carroll seconded. The motion PASSED on a vote of 7 to 0; Councilmember
Ferencz recused herself from the vote.
3. Appointment of City Judges, City Attorney and Assistant City Attorney
MOTION: Mayor Cronin moved to appoint Stirling Halversen for City Attorney
and Clay McCullough as Assistant City Attorney; Councilmember Harrington
seconded and the motion PASSED UNANIMOUSLY.
4. Appointment of Councilmember Bettelli to the CARTA Board
MOTION: Mayor Cronin moved to appoint Councilmember Bettelli to the
CARTA board; Councilmember Bergwerf seconded and the motion PASSED
UNANIMOUSLY.
5. Second Reading of Ordinance 2014-12
MOTION: Mayor Cronin moved to waive the reading and to approve
Second Reading of Ordinance 2014-12: AN ORDINANCE AUTHORIZING
THE ISSUANCE AND SALE OF A GENERAL OBLIGATION REFUNDING
BOND, SERIES 2015, OR SUCH OTHER APPROPRIATE SERIES
DESIGNATION, OF THE CITY OF ISLE OF PALMS, SOUTH CAROLINA, IN
THE PRINCIPAL AMOUNT OF NOT EXCEEDING $1,500,000; FIXING THE
FORM AND DETAILS OF THE BOND; AUTHORIZING THE CITY
ADMINISTRATOR OR LAWFULLY AUTHORIZED DESIGNEE TO
DETERMINE CERTAIN MATTERS RELATING TO THE BOND; PROVIDING
FOR THE PAYMENT OF THE BOND AND THE DISPOSITION OF THE
PROCEEDS THEREOF; AND OTHER MATTERS RELATING THERETO.
Special City Council
January 6, 2015
Page 2 of 4
Councilmember Bettelli reminded Council that, with this re-financed bond, the City will
save approximately seventy-two thousand dollars ($72,000) in interest over the six-year
(6 yr.) life of the bond.
Councilmember Ward asked whether staff had computed the present value of the
savings, i.e. how much it is in real money. The Administrator responded that the
computation of the present value had not been done.
Mayor Cronin added that the real dollars also relate to what the City is obligated to pay
that is currently at four percent (4%); in his mind these are real savings.
VOTE: The motion PASSED on a vote of 7 to 1 with Councilmember Ward
casting the nay vote.
6. Discussion of Shoal Management Project
Steven Traynum of Coastal Science and Engineering (CSE) was present to provide
Council with an update on the project. Mr. Traynum reported that, since the December
Special Meeting, the contractor has moved onto the shoal, and work has proceeded
since December 14
th. Sand is exclusively being harvested from the shoal and no sand is
being harvested from the beach between 53 rd and 56 th Avenues; Mr. Traynum stated
that he does not anticipate any way that the contractor would go back to that area.
Administrator Tucker added that additional sand will not be harvested between 53
rd and
56th Avenues for this renourishment project, but future projects are undetermined.
Mr. Traynum reported that as of Sunday evening, the contractor has moved
approximately one hundred fifty-six thousand (156,000) cubic yards of sand of the two
hundred fifty thousand cubic yards (250,000 cu. yds.) permitted for this initiative.
On the subject of payment, Mr. Traynum noted that the City had the option of a unit rate
of four dollars and a quarter ($4.25) per cubic yard plus a surcharge of fifty cents ($.50)
per cubic yard for the first twenty-five thousand (125,000) cubic yards or a daily rate.
The daily rate is based on paying Baker per day worked, and the contractor would work
as long as possible around low tide. At this point in the project, paying a daily rate is
working to the City’s advantage; since moving onto the shoal, the cost per cubic yard is
approximately four dollars ten cents ($4.10) per cubic yard. When checking the
schedule and the tides, there are only two (2) days in January that they will not be able
to work. Mr. Traynum stated that he believes that the project can be completed without
paying any standby days; therefore, he was confident that the project will be completed
within budget. At this time, there are thirty-four (34) more working days in the budget
that will take the project into February.
Councilmember Carroll asked whether an extr a high or extra low tide was advantageous
to the project. Mr. Traynum responded that, with an extra low tide, the trucks can get
further onto the shoal, but the extra high tide levels out the work. As long as the weather
is good, the tide range does not matter as much to the performance of the fill.
Special City Council
January 6, 2015
Page 3 of 4
Mr. Traynum said that the average beach elevation is six feet (6 ft.), but the plan is to leave the
beach higher than normal until the end of the project to keep as much sand on the high beach
as possible.
Councilmember Carroll asked how far toward the inlet will sand be placed. Mr. Traynum
answered that he does not plan to go any further then they are presently; the closer the sand is
placed to the inlet, the faster it is going to be lost to the inlet.
Commenting that the bulk of sand permitted to be moved has already been done,
Councilmember Buckhannon asked whether the City was going to meet its objective or need a
bit more sand to do that.
Mr. Traynum stated that he would like to move as much sand as possible off the shoal onto the
beach, giving the City control over where the sand goes initially. Based on accessible sand, he
believes that the contractor will move very close to the permitted volume of sand; if the City
decides that more sand is needed, the permit will have to be modified. He indicated that he
does not know how the shoal will react to the project:
• W ill it form new shoals as it moves on shore, or
• Will most of the sand move onshore under water?
He remarked that he hopes that sufficient sand will be moved to the beach to solve enough of
the erosion problem to last for a year or two (2).
Mr. Traynum suggested that the City start the planning process for another permit for an off-
shore project; if the time comes when there is not enough accessible sand on the beach, an off-
shore project is the only alternative for beach renourishment. The permitting process will take
one to two (1-2) years; permits are good for five (5) years and can be renewed for another five
(5) years by proving that the beach is being regularly monitored.
Mayor Cronin stated that the appearance is that twice as much sand has been moved in front of
Ocean Club as was placed there in 2012 with nearly a hundred thousand (100,000) cubic yards
remaining in the permit. He observed that, with high tides, the waves had not created an
escarpment in front of Beachwood East. Mr. Traynum expressed confidence that the beach at
Beachwood East will be much more stable, but the plan is to add more sand.
Councilmember Ferencz asked whether there was any kind of repetitive cycle that would allow
the City to predict when major projects will be needed. Mr. Traynum replied that CSE does not
have the data or studies to predict when major projects will be needed, but he does know that a
shoal attaches about every six (6) years on average. CSE is of the opinion that the island may
go into a period of stability on the north end of the island if the spit at Dewees Inlet attaches.
6. Accomplishments of 2014
The Mayor encouraged everyone to review the 2014 Accomplishments and to compare
it to the report of accomplishments from prior years to see how the City has evolved.
The Mayor specifically noted that the adminis trative staff dedication and work to ensure
the completion of these and other accomplishments, large and small.
Special City Council
January 6, 2015
Page 4 of 4
7. Executive Session to receive legal advice for a potential claim related to the
Shoal Management Project.
MOTION: Mayor Cronin moved to go in to Executive Session at 6:29 p.m.
for the reason stated above; Coun cilmember Bettelli seconded and the
motion PASSED UNANIMOUSLY.
Council returned to regular session at 6:47 p.m.; the Mayor announced that Council had
not taken any action or taken a vote while in Executive Session.
8. Adjournment
MOTION: Councilmember Buckhannon moved to adjourn the meeting at
6:48 p.m.; Councilmember Bettelli seconded and the motion PASSED
UNANIMOUSLY.
Respectfully submitted;
Marie Copeland
City Clerk
Source: City of Isle of Palms website. First collected Nov 3, 2026.