MINUTES
PUBLIC WORKS COMMITTEE MEETING AUGUST 7, 2023, 6PM
CITY HALL - COUNCIL CHAMBERS 5 E. BUTLER ROAD
4th Commitee Mee�ng
Commitee Members present: Jason Kraeling (Chair), Carol King, Michael Reynolds
Others present: PW Director Mathew Fleahman and City Administrator Seth Duncan
1. Call to Order- Chairman Kraeling
2. Public Comment- None
3. Reading and Approval of Minutes
a. Public Works Commitee Mee�ng: July 3, 2023
Mo�on: Councilwoman King made a mo�on to approve the minutes with Councilman
Reynolds seconding.
Vote: The vote was unanimous (3-0).
4. Reports or Communica�ons from City Officers
a. PW Director Mathew Fleahman
The vehicles and equipment have been listed on GovDeals. Some have been re-listed, so
the numbers will be presented to the commitee next month.
5. Unfinished Business- There is no unfinished business.
6. New Business
a. Stormwater Intergovernmental Agreement- This is a request to authorize the
intergovernmental agreement between the City and Greenville County. We have been
opera�ng under the 2010 agreement. The new agreement includes more descrip�ve
detail. There are no other changes and no financial impact.
Mo�on: Councilwoman King made a mo�on to send this agreement to Council with
Councilman Reynolds seconding.
Vote: The vote was unanimous (3-0).
b. Jenkins Streetscaping Funding Appropria�on- Staff requests Council appropriate an
addi�onal $1,531,573 from the Capital Fund Fund Balance for the streetscape project on
Jenkins Street and Jenkins Court in accordance with GLDTC Project Agreement 586.
CoTransCo has completed right-of-way acquisi�on, final engineering, and has bid out the
Jenkins St./Jenkins Court Streetscape project. Bids did come in within expecta�ons, but were
higher than previously projected. According to GLDTC Project Agreement 586, the City is
responsible for a match of $1,359,675, all cost overruns, right-of-way acquisi�on costs, and
railroad related expenses.
Staff proposes u�lizing Unassigned Capital Fund Fund Balance in the amount of $1,531,573
to complete the streetscaping por�on of this project.
Mo�on: Councilman Reynolds made a mo�on to send this agreement to Council with
Councilwoman King seconding.
Vote: The vote was unanimous (3-0).
c. Sewer Rehabilita�on Program- Amendment 5 with CHA- The City of Mauldin (City) and
Frazier Engineering (Engineer) entered into an Agreement dated March 15, 2015 for
Engineering-Construc�on Management Services related to the City's Sewer Rehabilita�on
Program. Amending the contract will allow for the Engineer to provide general engineering
services related to the City's overall rehabilita�on program and providing design and
construc�on management services for the City's sewer rehabilita�on construc�on projects.
The amendment will authorize the Engineer to implement the rehabilita�on work in
accordance with the grant from the South Carolina Infrastructure Investment Program. Staff
is reques�ng that Council approve the amendment – see atached amendment.
The cost associated with this amendment is 420,000 dollars. The budgeted municipal match
for the grant was 600,000 dollars and these engineering fees will be paid from the match.
The remaining 180,000 dollars from the budget match will apply to construc�on costs.
Mo�on: Councilwoman King made a mo�on to send this amendment to Council with
Councilman Reynolds seconding.
Vote: The vote was unanimous (3-0).
7. Public Comment
a. Brian Paton- 123 Kingsley Drive. Mr. Paton spoke at a previous Council mee�ng
regarding collapsed pipes behind Papa’s and Beer. A mee�ng was arranged with Mr.
Fleahman, the Mayor and Mr. Duncan. It was agreed that this is a problem, but there is a
ques�on as to whose responsibility it is. SCDOT has stated there has been no change to
the pipes in 32 years that should have contributed to the system failure and advised the
problem is the property owner’s responsibility. Mr. Paton said the property is being
destroyed.
Slides were shown of the ponds in Knollwood and slides of flooding yards. The pond
being discussed is now full of dirt and silt.
b. Lisa Schneider- 116 Muirwood Drive. Mrs. Schneider had a PowerPoint she presented
with videos and pictures of flooding. She has been told the problems are coming from
natural erosion. She is asking for help from the City.
c. David Untener- 104 Muirwood. He drove by Dollar Tree and the reten�on pond had
about a foot of water. He said the pond should have had water in it from the torren�al
rain that fell this evening. He doesn’t think the pond has been planned properly. Calls to
the County do not work.
d. Bill Schneider- 116 Muirwood Drive. He called DHEC to set up a mee�ng on his property.
DHEC did not show up to meet with him, but did come out and look at the creek. The
DHEC staff member told him the flooding is due to natural erosion. Mr. Schneider said if
you take all of the mud out of the pond and put it back in the creeks, the creeks would be
full of mud. The pond has been there for 45 years, but this problem only started a few
years ago. Where is all the mud from 45 years?
8. Commitee Concerns- Chairman Kraeling asked if this property was part of the stormwater
evalua�on that was just done. Mr. Fleahman said no, there is a property at Edgewood
Drive that was included. Chairman Kraeling said the City is working on stormwater, but it is
very expensive. Some good results have been received from the curbing that public works
is installing.
9. Adjournment- Chairman Kraeling adjourned the mee�ng at 7:24 p.m.
Respec�ully Submited,
Cindy Miller
Municipal Clerk